Gist of Discussions held in a meeting on 28

advertisement
Gist of Discussions held in a meeting on
28th January 2015 for providing reliable telecommunication at
66 kV & 33 kV voltage level substations
To provide reliable communicating facilities at 66 kV & 33 kV voltage level substations in all
States/UTs, a meeting with the State/UT utilities was taken by Chairperson, CEA on
28/1/2015 in NRPC Conference hall, Katwaria Sarai, New Delhi -110016.
List of participants is enclosed at Annex-IA. The list of Nodal officer from Chhattisgarh,
Punjab, Bihar, DNH, Kerala, Nagaland and West Bengal, as collected in the meeting is
enclosed at Annex-IB.
Chairperson, CEA, welcomed the participants and initiated the discussion. He stated that
during recent devastation caused by cyclonic storm Hudhud in Visakhapatnam, and Odisha
state, failure of communication system affected restoration of essential services. Member
(GO&D), CEA had taken meeting on this subject on 11th & 12th Dec., 2014 and it was
decided that States/UTs would prepare DPR in regard to providing Optical Fiber
Communication (OFC) at 66 kV & 33 kV substations. The status/clarifications in preparation
of DPR is the agenda for the meeting. He clarified that MOP has decided that provision of
OFC upto 132 kV would be taken care of by PGCIL; and CEA would coordinate for provision
of OFC at 66kV & 33kV voltage level.
Member (GO&D), CEA stated that optical fiber connectivity at 33kV / 66kV substations would
enhance redundancy in day to day operation besides help in early restoration in times of
natural calamities. He stated that OFC should not be used for voice communication only but
transmission of data under SCADA should also be used. All new substations below 132 kV
should have optical fiber connectivity. For providing optical fiber to the existing substations,
States should explore all possibilities to tap fiber available at nearest source like GP (Gram
Panchayat), BSNL exchange in Block, overhead fiber, etc. Central Government Schemes “Integrated power Development Scheme” (IPDS) and “Deendayal Upadhyay Gram Jyoti
Yojna” (DDUGJY) provide an outlay of Rs. 120 Crores and Rs. 280 Crores respectively for
establishing missing link of optic fiber (up to substation from National Optical Fiber Network).
PFC & REC are the Nodal Agencies. He urged that the States/UTs can make use of these
two Central Govt. schemes for establishing optic fiber connectivity.
Chief Engineer (LD&T), CEA, stated that for use under contingency situations such as
cyclone, flood, earthquake etc., V-SAT communication should be provided at 33 kV and
higher voltage level substations. These could also be used for SCADA, as being
successfully implemented in Karnataka. Each State depending on requirement should
procure adequate number of V-SAT mobile vans also, so that emergency situations could be
handled effectively. He stated that there are about 27000 nos. 66 kV & 33 kV substations
which are mostly in interior parts of the States where BSNL network is available. Considering
this, a scheme is proposed (at Annex-II) for discussion.
PGCIL sought following details to facilitate preparation of DPR by them for communication
system from 132 kV and above voltage sub-stations level:
a) List of 132 kV and 220 kV sub-station existing in various States as on date.
b) Transmission lines connectivity of these 132 kV and 220 kV stations and their
distances.
c) Map showing all these stations for exploring redundancy in connectivity.
d) Earth wire details of transmission lines to assess suitability for OPGW (As per
Annexure-III)
PGCIL stated that above details are required urgently for preparation of DPR and requested
the concerned officials to furnish these details within a weeks’ time to PGCIL so that
Feasibility Report for 132 kV level and above is finalized expeditiously.
BSNL agreed that a list having details of state-wise BSNL Nodal Officers would be handed
over to CEA soon. Similarly, States/UTs would also furnish details of their nodal officers.
Each State utility would furnish details of 66 kV & 33 kV substations to BSNL Nodal officers
who in turn would establish feasibility of OFC provision from nearest fiber source and hand
over the same to the concerned state utility. BSNL feasibility report would contain all details
like length of fiber requirement, terminal equipment, cost, bandwidth, etc. and it would act as
input for the States to prepare DPR. PGCIL agreed to extend assistance (like sharing of old
DPR, etc.) to the States, if required, for preparation of DPR.
Karnataka stated that DPRs prepared by each DISCOM would be routed through STU
before handing over to REC & PFC with a copy to Chief Engineer (LD&T), CEA. It was
decided that rural and urban substations may be segregated in the DPR for fund assistance
in DDUGJY and IPDS schemes respectively. OPTCL has emailed its OPGW status and the
same is enclosed at Annex-IV.
Regarding reliability of BSNL network, BSNL informed that they would be the sole agency in
laying and maintenance of optical fiber. Keeping requirement of power sector, they would
make all efforts to provide higher level of services. However, utilities may keep backup
provision as well. Regarding tariff mechanism, BSNL stated that possibilities of customized
competitive tariff plan would be explored.
Some utilities like BSES in Delhi stated that they have their own rugged communication
network at 66 kV & 33 kV voltage levels. It was decided that such utilities which have their
own reliable communication network at 66 kV & 33 kV voltage level and therefore do not
wish to prepare DPR are required to send confirmation in this regard to Chief engineer,
LD&T, CEA.
Punjab stated that they have 850+ nos. 66 kV & 33 kV substations whose data would be
required to be shared with BSNL. He suggested their state may be allowed to create their
own network. Further, he suggested that one sample DPR may be prepared. It was clarified
that assistance from PGCIL may be taken for DPR preparation; regarding having own
network, it was stated that network owner is not important, what is important is availability of
reliable communication network and State is required to confirm the same.
Uttarakhand informed that there are 289 nos. of 33 kV & 66 kV substations in the State. 114
nos. are in Urban areas and 175 nos. are in Rural area. He informed that they had compiled
the information and sent to the concerned agencies. It was clarified that based on discussion
and decisions taken in the meeting, Uttarakhand is to take action and prepare DPR
accordingly for further submission.
After detailed deliberations, following actions along with timeline were decided:
Sr.
No.
1.
2.
3.
ACTION
TIMELINE
BSNL to furnish details of their state-wise Nodal 30/01/2015
Officers
States/UTs power utilities to furnish details of 02/02/2015
their Nodal Officers
States/UTs power utilities would furnish details 05/02/2015
of their 66 kV & 33 kV substations to respective
2
4.
5.
6.
BSNL Nodal Officer
BSNL would submit the Feasibility Report to the 10/02/2015
concerned state/UT power utility
States/UTs power utilities would submit DPR to 15/02/2015
Nodal Agencies (PFC & REC) with a copy to
Chief Engineer, LD&T, CEA
Progress / Status would be reviewed in meeting Following
15/02/2015
It was decided that CEA would upload all information in this regard on its website
[www.cea.nic.in] and all concerned should regularly track such information for required
actions.
The details of Nodal officers from CEA in this regard are as under:
1
Dr. Prabhat Mohan,
2
Chief Engineer, LD&T Division
CEA, 3rd floor, NRPC office
complex, Katwaria Sarai, New
Delhi-110016
Telefax:011-26565214; 26533754
Email:
prabhatmohan1957@rediffmail.com
Naresh Bhandari
Director, LD&T Division
CEA, 3rd floor, NRPC office complex,
Katwaria Sarai, New Delhi-110016
Tele-fax: 011- 26859952;
M-09899061449
Email:
nbnareshbhandari@gmail.com
The meeting ended with vote of thanks.
The sample DPR as furnished by Power Grid and nodal officers list as furnished by BSNL
are enclosed at Annex V & VI respectively.
3
ANNEX-IA
Meeting on 28/01/2015 at 1500Hrs in NRPC Conference Hall on Action
Plan for providing reliable telecommunication facilities at 66 kV & 33kV
Voltage level
LIST OF PARTICIPANTS
SL
NO.
NAME
DESIGNATION
PH. NO/MOBILE NUMBER & MAIL ID
CEA
1.
2.
Major Singh
P.K. Pahwa
Chairperson
Member (GO&D)
3.
Dr. Prabhat Mohan
Chief Engineer (LD&T)
4.
5.
6.
7.
Director (LD&T)
Dy. Director (LD&T),
AD (LD&T)
AD (LD&T)
GM (LD&C)
AGM (LD&C)
7042195068, sunil9@ powergridindia.com
9873549014, sharan@powergridindia.com
GM (Enterprises)
AM (EB-II)
Asst. GM ES-II
9868216586, anoopkumar.bsnl@gmail.com
9968265500, eb2bsnlhq@gmail.com
9868237711 eb2bsnlhq@gmail.com
13
14
15
Naresh Bhandari
Kamal K. Chauhan
R.K. Tiwari
S.R. Reddy
PGCIL
Sunil Agrawal
H.H. Sharan
BSNL
Anoop Kumar
Vipin Kumar
S. Janaki Raman
PFC
Arun Kumar
S.K. Srivastav
A.K. Shrivastava
011-26732201 chair@nic.in
011-26732601 agnipath1@yahoo.com,
pkpahwa2000@yahoo.com
26533754, 26565214
celdntcea@gmail.com,
prabhatmohan1957@gmail.com
9899061449, nbnareshbhandari@gmail.com
9811899762, ddtelecom2014@gmail.com
9013948608, rkt12004@yahoo.com
8447272084, adptcc@gmail.com
AGM
AGM
AGM
9650991240, arunk091@gmail.com
9650992712, sudhirksri1@gmail.com
9650992210,
arunkumarshrivastava@gmail.com
16
Jaipur Discom
G.R. Choudhary
Director(T)
09414004058
dr.technical_jvvnl@yahoo.com
17
WBSEDCL
D.K. Pal
8.
9
10
11
12
18
19
20
21
22
Power Department
Nagaland
Shikato Sema
B. Tiameren Ao
GETCO
M.K. Jani
Dadra, Nagar & Haveli
H.C. Surma
Goa
Jose E. de Nelo
09434507581, pal.wbsedcl@gmail.com
EE(T&G)
E.E (MIS)
09436003338, shikato_my@yahoo.co.in
09436260852, btiaao@yahoo.in
ETA to MD
09925208486,
demd.getco@gebmail.com,
demd.getco@gmail.com
Asstt. Engineer
09824154044 hcsurma@gmail.com
Ex. Engineer
08380015364 elizeuu@yahoo.co.in
24
HVPNL, Panchkula
Rakesh Garg
APSPDCL
Samasekhar
25
EPDCL
P. Gorki
26
APEPDCL/VSP
P. Anand Babu
Asst. Engineer
08331019101
anand_pediredla3456@rediffmail.com
27
TANTRANSCO
Ms. J. Rexline Terese
Superintending Engineer
09445396789, 09445396789
rexlineterese@gmail.com,
sedpcchn@tnebnet.org
CE/IT
Dy. CE/IT (APM)
09646108720, ce_it@pspcl.in
09646118735, se_it1@pspcl.in
DGM(T)
9999533667 sunder_dtl@rediffmail.com
XEN/P&D, Hisar
08685990920
cepdcdhbvn@gmail.com,
xenplanningdhbvn@gmail.com
23
31
PSPCL
Er. Damanjit Singh
Er. S.K. Manrow
SLDC, Delhi
Sunder Singh
DHBVN
Er. S.S. Rai
32
33
Jharkhand
Sahanshah Ali Khan
Sunil Kumar Sinha
34
Andaman Elect Dept.
Mahesh Lall
28
29
30
35
36
37
38
39.
40.
41.
42.
43.
44.
45.
CSEB
Ashok Kumar
KPTCL
R. Thyagaraj
Sumanth
HPSEB
Suneel Grover
N.P. Gupta
Delhi Transco Ltd
Dinesh Singh
BYPL
Anish Kalucha
Devender Sharma
UHBVN, Haryana
S.K. Dhull
RRVPNL
Rakesh Sharma
POSOCO
P.K. Agarwal
BSPHCL
09316369244 hvpnlppp@yahoo.com
Executive Engineer
Divisional Engineer, Telecom 09440814318,
& IT, Tirupati
somasekharaptransco@gmail.com
Divisional Engineer, Telecom 09440814370, gorkiputumbaka@yahoo.in
& IT
SE to RC Jharkhand Bhawan
011-26739013 Jhbhawan@gmail.com
Liaison Officer, Jharkhand 9999029231sunilsinha11@rediffmail.com
Urja Vikas Nigam Ltd.
Asst. Engineer,
Electt.
Andaman 09434262448 maheshnrse@gmail.com
Chief Engineer
09826308744 ashok.kumar@cseb.gov.in
Ex. Engineer
Director
09448365472 r.thyagaraj@gmail.com
0897100666 dt@kptcl.com
Chief Engineer (SO&P)
Addl. S.E.
09816096666, grovers_in@yahoo.com
09418376465 npgupta_sldc@yahoo.co.in
Manager (Tech) (Comm.)
9999533680, dineshsinghdtl@gmail.com
anish.kalucha@relianceada.com
devender.s.sharma@relianceada.com
XEN DD-III
07307301172 (Off.) 09254115233 (R)
xenddiii@gmail.com
XEN
09414061007, rakesh_jpr@hotmail.com
AGM
9910064320, pkagarwal@posoco.in
,
46.
47.
RE
ARE
9810172842, rendbsphcl@yahoo.in
9643245312, arendbsphcl@gmail.com
48.
Khagesh Chaudhary
Umang Anand
TPDDL(TATA)
Rajeev Agarwal
Manager(IT infra network)
49.
Vijay Kumar
Sr. Manager(EHV Projects)
9910934888, rajeev.agarwal@tatapowerddl.com
9871798582, vijay.kumar@tatapowerddl.com
50.
51.
52.
53.
54.
KSEB Ltd
Sreenivasan. G
BRPL
Satinder Singh Sondhi
UPCL
Satish Chand
V.S. Rana
PTCUL
S.P. Arya
Resident Engineer
9968213129, ksebdelhi@gmail.com
Addl. V.P
9312147009,
satinder.sondhi@relianceada.com
S.E
E.E.
09927001681, dgmre.upcl@yahoo.com
09412998578, vsrana@upcl.org
E.E
09412053135, sp-arya@ptcul.org
ANNEX-IB
Details of Nodal Officers
Sl.
No.
State
1
2
Chhatisgarh
Punjab, PSPCL
3
Bihar
4
5
Dadra Nagar
Haveli (UT)
Kerala
6
Nagaland
7
West Bengal
8
Uttarakhand
9
HVPNL (STU),
10
TANTRANSCO
Name of Nodal Officer
M. Vikas Sharma
Ex. Engineer
Er. Tejpal Bansal
Addl. SE/H(NSP)
Sri D.N. Tiwary
CE(O&M), NBPDCL
Sri C.L. Prakash,
CE(O&M), SBPDCL
Sri K.N. Singh
CE(Trans O&M), BSPTCL
Shri H.M. Patel
S.E.
Shri K. Sanal Kumar
Dy. Chief Enginner
KSEB Ltd.
Systerm Operations,
Kannaur
B. Tiameren Ao
Executive Engineer (MIS)
Department of Power
Dimapur, Nagaland
Dipak Kr. Pal
Superintending Engineer
(E)
IT&C Cell
Vidyut Bhawan
Kolkata 700091.
Vishal Singh Rana
Executive Engineer (IT)
I.T., UPCL, Gabar Singh
Bhawan, Dehradun,
Uttarakhand-248006
Er. Sunil Sethi,
Superintending
Engineer/D&C Haryana,
SLDC Complex, Sewah,
Panipat, Haryana
Er. P. Manohar, Chief
Engineer/P&C
Contact Details
09425510090
0946101251
07763818345
07763814021
07763817701
09924127039
hmpatel39@gmail.com
09446008255
socknr@ksebnet.com
eecm@ksebnet.com
9968213129 (Delhi)
09436260852
btiaao@yahoo.in
09434507581
pal.wbsedcl@gmail.co
m
0135-2767259; M09412998578
Email.:
vsrana@upcl.org
09315016201
09445397070
Email.:
cepc@tnebnet.org
ANNEX-II
PROPOSED LAYOUT PLAN FOR OPTICAL FIBER COMMUNICATION (OFC) FOR 66KV &33KV SUBSTATIONS
Note:
1) All GPs (Gram Panchayats) are proposed to be connected via BSNL network having bandwidth upto 100
Mbps.
2) Keeping 27000 nos. of 33 kV & 66 kV substations into consideration, 100 no. (approx.) of substations might
be kept under one ALDC (Area Load Despatch Centre). However, exact no. of 33 kV and 66 KV substations
to be kept under one ALDC would be decided by individual States based on their requirement.
3) On 132 KV and 66 KV power lines, OPGW (Optical Ground Wire) is feasible and accordingly fibre optic cable
layingcan be done.
4) In states where ALDC is provided, only a subset of data would flow from ALDCs to SLDC. In smaller states
like Manipur, data would flow directly from substations to SLDC.
Salient Features of OFC (Optic Fibre Communication) in power sector
1)
2)
3)
4)
5)
6)
Reliable voice communication.
Aids SCADA system.
Video Conferencing between load dispatch centres and substations.
Enables remote switching of circuit breakers and better protection.
Supports efficient Energy Management System (EMS).
Supports future SMART Grid applications, etc.
ANNEX-III
ANNEX-III
Attention:
This DPR has been furnished by Power Grid as a
sample DPR and the same should be used for internal purpose only
i.e. preparation of DPR for reliable Communication at 66 KV & 33 KV
Substations
FEASIBILITY CUM DETAILED PROJECT REPORT FOR
Establishment of Fibre Optic Communication System in Eastern Region
1.0
BACKGROUND
a) Electricity plays an important role in the overall economic development of the country. In
the last six decades, since independence, Indian Power Sector has achieved phenomenal
growth from a few scattered small generators supplying load to local process of elite
customers, to strong Regional Grids spanning throughout the length and breadth of the
country, and supplying to even remote corners of most of the States. The achievement of
increasing the installed power capacity from 1362 MW to over 1,73,626 (as on 31.03.2011)
MW along with development of EHV Transmission System of 765 /400/220 kV has made it
possible to provide electricity to cities, towns, industrial areas and the remote villages.
Considering the complexity & growth of Power System, need of effective management of
Power System were felt essential. Accordingly, Unified Load Dispatch & Communication
Projects (ULDC) was established on Regional basis for providing advance EMS/SCADA
and Communication System for Management of Regional Power Grids. These ULDC
Projects were commissioned progressively from July 2002 to February 2006 in Southern,
Northern, North-Eastern, Eastern & Western regions. Subsequent to commissioning of
ULDC Schemes in all the regions and formation of NEW Grid with the synchronization of
Northern, North-Eastern, Eastern & Western grids and increase of Inter-Regional Power
Exchange to around 22400 MW as of now, National Load Dispatch Centre (NLDC) at apex
level has been established to coordinate Inter-Regional and Inter-National Power
Exchanges and monitoring the Power situation at national level for ensuring security to
National Power Grid.
b) Under Eastern Region ULDC Project, Communication Network comprising of Microwave
(MW), Fiber Optic (FO), PLCC based communication Network was established to support
data and voice requirements of SCADA/EMS Projects.
The EMS/SCADA system and wideband communication system established under Eastern
Region ULDC Project is as below:
Sl. No.
ULDC Scheme
1
ER
Control
Centres
11
Fiber
MW Hops
Optics (in (in Kms)
Kms)
1453
40
It may be mentioned that in Eastern Region a scheme for replacement of existing Micro wave
communication links with Fiber optic based Communication system is under awarding stage
based on approval of ERPC and is likely to be completed by June 2013.
In the 17th ERPC meeting, it was deliberated that with fast growing expansion of Power System
and considering the technological requirement such as Special Protection Scheme, Phasor
Page 1 of 16
Measurement Unit etc., it would not be possible to meet the Communication requirement for
such applications through PLCC system. Further, in order to facilitate the voice and data
connectivity of POWERGRID stations with RLDCs in accordance with IEGC and also
considering technological requirement referred above, need of expansion of existing wideband
communication system is felt essential. This will facilitate connectivity of other users with data
collection points on CTUs system as envisaged in IEGC.
Accordingly, POWERGRID proposed a scheme of fibre optic based communication network
consisting of approximately 3643kms of OPGW cable at an initial estimated cost of Rs. 69
crores for providing voice and data connectivity of requisite central sector, SEBs substations
and IPPs generating stations. The scheme was approved in following two RPC meetings as
detailed below:
(i) The scheme was approved for 2588 kms of 24fibre OPGW cable along with
communication equipments with initial estimated cost of approximately 49croresin the
17th TCC/ ERPC meeting held on 16th & 17th March, 2011.
(ii)
The scheme was approved for 1055kms length of OPGW cable with an initial estimated
cost of approximately Rs. 20Crore in the 15th TCC/ERPC meeting held on 27th & 28th
Sept.2010.
It has also been approved that investment made on the same shall be recovered through tariff
to be determined by CERC. Further, in the meeting it was also agreed that POWERGRID shall
suitably keep the clause of quantity variation in case WBSETCL carry out some work of its own
before commencement of POWERGRID’s work. The copy of the minutes of the meeting is
enclosed at Annexure-I. During implementation, if any requirement of constituents received
shall be suitably taken care.
2.0
JUSTIFICATION
Subsequent to commissioning of ER-ULDC project, considerable number of EHV
Substations and Power Plants has been commissioned in Eastern Region but the
Wideband Network has not been expanded.
Power system communication requirements are reliability, availability and security of the
highest order. Past experience shows that fiber optics installed on Overhead Power lines is
the most reliable form of communication medium due to least amount of down time. Hence
an expansion of Fiber Optic based System is considered essential to meet the power
system communication requirements.
Though power system network has expanded very fast in the last few years and several
EHV substations are planned to be added in the network due to government emphasis for
accelerated development of the power sector and addition of generating capacity through
Ultra Mega Power Projects (UMPP), IPPs and Public Sector companies. The new
substations integrated to the SCADA system of ER-ULDC project are communicating to the
control centers on PLCC. The PLCC based communication system has limitations in regard
to data communication as the performance of this system deteriorates after two hops.
Further, due to frequency congestion only limited number of channels can be provided on
PLCC. Therefore, it is essential that in order to provide reliable and efficient communication
network to the fast growing power system network, existing FO Communication Network is
to be expanded to cater for additional Wideband Nodes in the Communication Network of
ER-ULDC project.
Power System in the country is expanding very fast and with increased number of
interconnections between Regions, many new technologies are being implemented. In
addition, Indian Grid is characterized by wide variation of Power flow due to variation in
Page 2 of 16
demand / generation during day / seasons. Further, consumer aspiration for quality and
reliable power supply is increasing. All the above, with increasing complexity of Grid
operation manifold, necessitates dynamic monitoring of Grid parameters / conditions on
real-time basis. The existing SCADA/EMS provides the data which are steady state in
nature and not suitable for dynamic monitoring and control for the Grid due to high degree
of latency of tele-metered data and also non-synchronized sampling of data. Emerging
technologies like Phasor Measurement Unit (PMU), Wide Area Measurement (WAM)
system provide dynamic monitoring of network on real time basis. Such monitoring through
the said measurements shall facilitate development of various control, regulation and
preventive features like Remedial Action Schemes (RAS), System Integrated Protection
Scheme (SIPS), Adaptive islanding, Self-healing Grid etc. These technologies have been
envisaged in the GoI report of Working Group on power for 11 th Plan as well as National
Electricity Plan – Transmission. Relevant extract of the report is enclosed at Annexure-II It
is expected that such emerging technologies would be deployed for development of Smart
Grid as soon as they are available in the market. These emerging technologies would
require communication system with least latency and high reliability. The OPGW based
Fiber Optic based communication system would be most suitable for such applications. The
proposed FO network would be used for such upcoming advanced technologies also.
In essence need of wideband communication system can be summarized as follow:
(i) Expansion of Power Sector is taking place at a very fast pace leading to establishment of
IPPs, UMPPs, High Capacity Transmission System etc. This effectively means that the
no of substations and power plants requiring data & voice connectivity with the ERLDC
is increasing manifold.
(ii) The Utility of SCADA system has been realized by system operators and users are
asking for a very reliable system which is not possible without robust and reliable
communication system.
(iii) Due to expansion of Power System it is not possible to meet the communication
requirement with PLCC. POWERGRID transmission lines are being made LILO
frequently due to open access which disrupts the communication system based upon
PLCC as LILO increases no. of PLCC hops and more no. of PLCC hops deteriorates
the performance of PLCC communication.
(iv) The proposed communication network is to be used by all agencies connecting to grid
under control area of RLDCs. This ultimately results in more no of substations and
power plants using the communication network of power sector.
(v) With increasing complications in the power system, in order to ensure effective grid
operation in case of contingencies, the need of special protection schemes (SPS) is
being felt by the grid operators. These SPS requires the transfer of signals from one
node to many nodes simultaneously. Since these are contingency provisions there
effectiveness is of paramount importance. SPS can work effectively only when reliable
wide band network is available.
(vi) Wide Area Measurement System (WAMS) is the new emerging technology for grid
operators; PMU (Phasor Measurement Unit) is the basic building block for WAMS to be
installed at the Substations and Power Plants. The PMUs generate large volume of data
and if the data of all the feeders with higher sampling rate is to be accommodated, each
substation would require up to 2 Mbps bandwidth for PMU data alone. WAMS based
systems can be implemented with Fiber Optic based communication network only.
Page 3 of 16
(vii) Line Protection: For shorter lines current differential protection along with distance
protection is preferred as this ensures two line protections on two different principals
which is considered a better protection philosophy. The available current differential
protection relays exchange the current signals (the data such as magnitude of voltage
& current, displacement angle etc.) between the two ends of a line on dedicated fibers.
Further, the lines are being frequently LILO, many times resulting into smaller lines.
The availability of fibers would make it possible to implement current differential
protection on the lines.
(viii) Due to fast expansion of Power System it is getting increasingly difficult to provide
PLCC for protection and speech for new lines due to frequency congestion. FO based
communication network shall help in overcoming this problem.
(ix) Many of the central sector stations are being operated from remote and remote
operation of all the substations of POWERGRID is being planned. Presently PLCC
communication is being used for remote operation which is not very reliable, the
expansion of wide band network shall ensure effective remote operation of the existing
as well as new substations.
Accordingly, FO network has been finalized considering this aspect. The existing ER-ULDC
network, FO project in lieu of MW replacement and final FO network proposed for
implementation under Master Communication Plan is attached at Exhibit-1.0.
Previous experience shows that additional capacity available on FO network could be
utilized commercially by offering the same to the telecom service providers, the FO network
envisaged under this feasibility report would also provide the similar opportunities but the
extent of such usages would depend upon the market conditions prevailing at the time of
completion of the network. However, it may be mentioned here that as per ERPC approval,
the proposed facility shall be used by electricity sector only. If and when, in future,
POWERGRID wishes to utilise this facility for its commercial business through Telecom
Department, the matter would be suitably taken up with ERPC for approval of the same.
3.0
PROJECT OBJECTIVES
The objective of the project is to provide a reliable wideband communication system for
catering data & voice requirements as well as new Technological requirements such as
Special Protection Scheme, Wide Area measurement System, Advanced Protection
System, Substation Automation for the new/upcoming Sub-Stations / Generating Stations
and Control Centers in the Eastern Region.
3.1
Project Highlights
Project
Location of the Project
Beneficiary States
Project Cost
Monthly Fixed Charges
Commissioning Schedule
Fiber Optic Communication System
Eastern Region Under Expansion
Wideband Communication Network
Eastern Region –Phase1
Eastern Region
All the constituents of Eastern Region.
in
of
in
Rs 82.47Crore
Rs 1.83Crore
30 months from the date of Investment
Approval.
Page 4 of 16
3.2
Scope of work
The scope of work under the project to be implemented as a Central Sector Regional
Network can be categorized as follows:
(i)
Installation of OPGW fiber optic cable on the existing/new EHV transmission line of
POWERGRID covering approximately 3298 Kms of transmission network.
(ii)
47 nos. of terminal equipment for communication based upon Synchronous Digital
Hierarchy (SDH) technology to be installed in the substations and generating Stations
of Central Sector & Deptt. of Electricity of Sikkim. The project would also involve
installation of 66 nos. of multiplexers at the new/existing wide band nodes. To
monitor the network, NMS system is also envisaged.
The item wise break up of the scope of the work is as follows:
1. OPGW cable 3298Kms
2. SDH Equipment 47nos
3. Mux 66nos
5. DC Power Supply 47Nos
4.0
TARGET BENEFICIARIES
The FO communication system project is to be implemented to meet the communication
requirement as detailed above in view of the expansion of power system network. The
proposed communication network would be used primarily for supporting tools such as
EMS/SCADA, WAMS, SPS, System Protection Scheme, remote operation etc. required for
power system operation which is a critical infrastructure for grid operation. The beneficiaries
of the project would be all the constituents of Eastern Region.
5.0
PROJECT STRATEGY
Being a regional wideband communication project, POWERGRID had undertaken and
discussed the proposed communication network with constituents of Eastern Region at
SCADA O&M meeting, TCC & at ERPC level. The proposed communication network has
been approved at ERPC level. The approved network at ERPC level would meet the
present and future communication requirement of the region for grid operation. The
network shall be implemented as a Central Sector network and tariff on the investments for
the same shall be recovered from the constituents of the region as per CERC directives.
6.0
LEGAL FRAMEWORK
It is proposed to execute the above entire communication scheme as per provisions
contained in the Indian Electricity Act, 2003 and the rules made there-under and the
Electricity (Supply) Act, 1910 and 1948, in so far as these are applicable.. Approval of the
Govt. of India under section 68 of the Electricity Act, 2003 is not required as communicated
by MoP for similar projects.
Page 5 of 16
7.0
ENVIRONMENTAL AND SOCIAL ASPECTS
7.1
Forest involvement / Clearance
The project for implementation of FO communication network would involve installation of
OPGW on existing 765KV/400KV/220KV lines of POWERGRID and on few existing lines of
constituents. In addition, OPGW on new lines of POWERGRID shall also be installed and
requirement of forest clearance if any shall be taken care in concerned transmission line
project. Further the communication equipment would be installed in the existing as well as
new substations. Since the work is to be done on the existing transmission lines, on new
transmission lines in place of earth wire and new & existing substations, separate clearance
for involvement of forest for any work related to the proposed work is not foreseen.
7.2
Social Issues/R&R measures
Not foreseen, as the proposed scheme shall be established on the sub-stations and
transmission lines (Existing and new) and the requirements of Social Issues/R&R measures
shall be taken care in concerned transmission line projects. .
8.0
ON-GOING INITIATIVES
POWERGRID, the Central Transmission Utility, is entrusted with the responsibility of
establishment and operation of Regional and National Grids to facilitate transfer of power
within and across the regions with reliability, security and economy on sound commercial
principles. The operation of Regional & National Grids, presently being done by M/s
Power System Operation Corporation Limited (POSOCO), a 100% subsidiary of
POWERGRID. To facilitate smooth and efficient operation of Regional Grids,
POWERGRID has undertaken implementation of State-of-the-Art Unified Load Despatch
and Communication (ULDC) projects, for all the five (5) Regions of the country.
Subsequently National Load Dispatch Centre (NLDC) project has also been taken up. The
ULDC projects in Southern, Northern, North- Eastern, Eastern & Western Regions and
NLDC projects have been commissioned. OPGW based communication system has
been installed under these ULDC projects and same are under satisfactory operation.
POWERGRID has also implemented number of telecommunication projects involving
installation of OPGW cable for other utilities as part of Consultancy Project.
As a part of the WAMS project for Smart Grid implementation PMUs are to be installed in
Eastern Region. The OPGW network shall facilitate the implementation of WAMS project.
SPS have been planned by ERLDC for implementation. These SPS will require wideband.
POWERGRID has dedicated team of engineers for engineering and site work who have
requisite qualification and experience in the communication system. The engineering team
also has rich experience of handling domestic as well as international projects related to
communication system with the state of the art technology.
9.0
TECHNICAL FEATURES
9.1
Salient features
The major components of the fiber optic communication system to be established shall
include the following:-
Page 6 of 16
(a) OPGW Cable
(b) Approach Cable
(c) Fiber Optic Terminal Equipment
(d) Primary Multiplexers
(e) Network Management System(NMS)
(f) DC Power Supply along with Batteries
The salient technical particulars of these items shall be as under:
(a) Optical Ground Wire (OPGW) Cable and Approach Cable

Proposed OPGW cable shall contain 24 Fibers. For some portions of the route which
would be common for two directions 48 Fiber OPGW cable is also envisaged. Fibers
shall conform to ITU-T G.652D

The mechanical & electrical properties of OPGW shall be similar to the earth wire
being replaced and shall be adapted meeting the requirement of transmission line.
Installation of OPGW shall be carried out live line for existing lines and off-line for new
lines under construction if any.
Approach cable shall be armoured cable with fibers same as OPGW for providing
connectivity from joint box at the terminating station up to the communication room.


(b) Fiber Optic Terminal Equipment (FOTS) and Primary Multiplexers





FOTS shall be of SDH technology with at least STM-16 capacity.
FOTS shall be in hot standby configuration.
FOTS shall provide minimum repeater less distance of 250 kms.
FOTS shall be EMI/EMC compatible.
Primary Multiplexers shall cater connectivity of voice and data channels as per
requirement of users for transmission through SDH Equipment.
(c) Network Management System (NMS)


Network Management System (TMN) shall be provided for operational support to the
FOTS and associated Termination equipment subsystems.
TMN shall provide the capability to monitor, reconfigure, and control elements of the
telecommunications network from a centralized location and at each node of the
network where equipment is located.
TMN system shall assist Employer/Owner in the operations and maintenance of the
wideband communication resources of the including detection of degraded circuits, system
performance, the diagnosis of problems, the implementation of remedial actions and the
allocation or reallocation of telecommunications resources and addition/deletion of network
elements.
(d) DC Power Supplies & Batteries


DC Power Supply with battery back –up of 8 hours shall be provided.
VRLA type battery shall be provided.
Page 7 of 16
9.2
Support facilities
All the equipment shall be installed in the existing substations. The SDH equipment shall be
mostly located in the existing communication room, therefore additional support facilities
would not be required. However, at new wideband locations the air-conditioned space in the
existing control rooms of the substation is to be provided. At stations where equipments are
to be installed no additional infrastructure is envisaged except some minor civil work/airconditioning. The substations which are under construction the requirement of power supply
shall be coordinated with the Engg. Deptt.
In regard to 48 V DC power supply for communication equipment, same is envisaged at the
new wideband locations as per the requirement and is included in the scope of the project.
9.3
Design Criteria
High system availability, reliability and flexibility in maintenance of the system are the main
criteria for design of any communication network. Principally these are described as
follows:
(a) High Reliability: The system should be engineered to provide high reliability with
minimum loss of communication by selecting proven hardware and using proven
methods of communication.
(b) High Availability: The system should suffer only minimum degradation in the event of
circuits failing due to media shortcomings, and care should be taken to provide
alternative route of speech & data wherever it is economically feasible.
(c) Rapid Response: The system should offer quick response to changes in measured
values by keeping the update time within specified limits.
(d) Economy: The system should be engineered to provide the required performance in an
economical manner.
(e) Flexibility: The communication network should have enough flexibility to changed
requirements and future augmentation programs. The network should itself be capable
of being easily changed to embrace these new requirements.
(f) Maintainability: The network should use methods which make minimum demands for
maintenance. Also, adequate provision of spares should be allowed to ensure quick
remedial action of any fault at any station within the network.
The communication network under the proposed project shall have the following aspects in
order to meet the high reliability, availability and maintainability criteria:
(i) The proposed FO based communication network shall be primarily used for speech and
data communication to cater SCADA/EMS and associated systems, Special Protection
System, Wide Area Measurement Systems, Remote Operation etc. to efficiently operate
the large and interconnected Power System. Presently large no of RTUs installed at the
substations are communicating to the control center on PLCC at least for a portion of the
communication route. The performance of data communication over PLCC is not
satisfactory when the data transmission involves more than two hops, this problem is
further aggregated on aged lines of constituents due to high noise occurring out of poor
maintenance.
Page 8 of 16
(ii) The Fiber Optic cable to be laid shall have 24/48 fibers, which will ensure the continuity
of the link over a longer period as spare fibers can be used to replace the damaged
fibers at any point of the time during its design life time. The spare fibers can also be
used by telecom services which would generate additional revenue. However, this would
depend upon the prevailing market conditions at particular point of time.
(iii) The Fiber Optic (FO) terminal equipments to be installed under the project shall be
based upon SDH technology and will have at least STM-16 capacity. The interfaces
shall be selected meeting the present requirement and considering the forthcoming
developments in control center technology for grid management etc. The SDH
equipment shall be provided with redundancy to ensure path protection and against
failure of any interface card/power supply.
(iv) For longer lines (>250kms) if the output of FO terminal equipment does not meet the
link budget requirement, repeater may be required which shall be installed at the
substations.
(v) Primary multiplexers shall be provided at the new wide band locations. Each of these
primary mux shall have 2 Mbps capacity. Suitable interface cards shall be provided to
meet the present and future requirement for data transmission and interfacing with
digital and analog PLCC equipment as well as with data transmission equipment such
as RTU and sub-station automation system.
(vi) For ease of maintenance, configuration changes and centralized monitoring in the
equipment the Network Management System (NMS) shall be provided for Fiber Optic
Terminal Equipment as well as for primary multiplexers.
10.0 MANAGEMENT ARRANGEMENTS
10.1
Organizational set up
In POWERGRID the 'Organizational Concept' has been given due importance and the
basic structure of the organization has been made with a view to achieve the following
objectives:
i)
ii)
iii)
iv)
v)
To group related functions together to have clearly defined 'Roles' for the relevant
'functional heads'.
To have well defined 'Responsibility & Authority' centers in the structure.
To have well defined 'communication channels' and optimum 'span of control' in the
organization.
To have optimum manpower.
To have decentralization of activities as far as possible.
At the first level in the organization, Corporate Centre will be planning, monitoring and
controlling the objectives and activities of the organization. At the second level, the
Regional HQs will be playing the role of controlling the activities in the regions and will
report to Corporate Centre. In POWERGRID, nine regions have been identified as NR-I,
NR-II, SR-I, SR-II, WR-I, WR-II, ER-I, ER-II & NER, and these regions are headed by
GM/ED. At the third level in the structure, the Substation Groups will be controlling the
activities of the respective Substation and associated lines under that Group and will report
to the Regional HQs. The Groups will consist of basic working units such as sub station
Construction/maintenance, line construction/maintenance. The Groups will have both
service and technical functions, to cater the basic functional requirements. In regard to
work related to ER-ULDC system, ER-1 and ER-2 regions are responsible for the
maintenance and expansion of communication network of the respective region.
Page 9 of 16
10.2
Project Management
The project of Fiber Optic based Wideband Communication system will be planned,
implemented, monitored and controlled through Integrated Project Management and
Control System (IPMCS). IPMCS uses PERT/CPM technique as the basic management
tool. For effective project planning and review, three tier level of planning and review have
been adopted.
Level-I:
Planning is done by the central planning cell, which is in the form of an overall project
schedule called the Master Network, for the project which forms the basis for all subsequent
planning and monitoring of the activities. This covers broadly all the packages of project
and indicates activities of engineering, contracts, manufacturing, erection and
commissioning. The Master Network is prepared using computerized techniques which
subsequently helps in comparing the actual progress of the project with the scheduled
progress. This gives indication of the likely critical areas and helps in preventing the same,
thereby resulting in smoother implementation. The Master Network also acts as a source
for the planning to be done at Level - II & Level - III.
Level-II:
Planning is done package-wise and is worked out and finalised with the respective
contractor/vendor during the pre-award stage. Level II networks are made within the
milestones identified in the project Master Network (L-I).
Level-III:
Plans deal with elaborate schedules and weekly/monthly rolling plans which are prepared
for activities of engineering, supply (as the case may be) & field activities. These form the
basis of monitoring by the various functions.
The system envisages monthly review of the level II programmes with contractors and at
field on a weekly basis.
A site monthly progress report is sent to the head office having four sections, i.e.
i)
ii)
iii)
iv)
Project completion trend
Salient achievements for the month
Programme for next month
Areas needing attention of top management
11.0 MODE OF FINANCE AND PROJECT BUDGET
11.1
Project Cost Estimate
The estimated cost of the project based on 1st Quarter 2011 price level is as follows:
(Rs. in crores)
Total cost
1.
2.
FO Communication System
Interest during Construction
77.48
4.99
TOTAL
82.47
Page 10 of 16
The abstract cost estimate for FO Communication System is given at Annexure -1.0. The
break-up of the cost estimate for the project are given at Annexures-2.0, 3.0, 4.0, 5.0, 6.0,
7.0, 8.0, 9.0 & 10.0 respectively.
11.2
Basis of Cost Estimate
The estimated cost of the project as on 1st Quarter 2011 Price level works out to Rs.82.47
crores including an IDC of Rs.4.99 crores.
The Project IRR, Equity IRR and Economic IRR have been calculated on project completed
cost of the project and the same is tabulated below:For Completed cost
Project IRR
12.04 %
Equity IRR
Economic IRR
19.01 %
12.04 %
Unit rates for Fiber Optic Cabling portion has been considered from latest LOA dated28.02.11 awarded for Replacement of Microwave links replacement by OPGW system in
Southern Region. However, for SDH (STM-16) Equipments, as in- house cost data was not
available, unit rates have been accordingly adopted from the lowest of 3 nos. received
quotations, invited recently for similar type of works in Western Region.
The above cost estimate is inclusive of Excise Duty @ 10.3 % and CST @ 2 % as funding
for supply of equipment is assumed to be done through domestic Sources. F& I @4 %
have also been considered in the said estimate.
11.3
Project Overheads
The following overheads have been charged on to the cost of the Fiber Optic
Communication System as a percentage of the equipment cost:i)
ii)
iii)
iv)
11.4
Maintenance during construction
Establishment charges
Losses on stock
Contingencies
10.75 %
3.0 %
Funding arrangement:
The project is proposed to be funded through internal resources and domestic funding. For
the total project, equity component (30%) is proposed to be met through POWERGRID’s
internal resources and loan component (70%) through domestic funding.
The rate of interest for the domestic funding loan component has been considered @ 10.5
% p.a. The interest during construction would however be based on the actual financial
structure of the project and applicable terms of interest on loan(s), etc.
11.5
Phased Fund Requirement
The anticipated year wise fund requirement for the project including interest during
construction is given below:(Rs in Crores)
-----------------------------------------------------------------------------------------------------YEAR
TOTAL
-----------------------------------------------------------------------------------------------------2011- 2012
15.92
2012- 2013
17.21
Page 11 of 16
2013- 2014
45.47
2014- 2015
3.87
------------------------------------------------------------------------------------------------------
Total
11.6
82.47
Mode of Financing
The project is proposed to be funded through internal resources and domestic funding. For
the total project, equity component (30%) is proposed to be met through POWERGRID’s
internal resources and loan component (70%) through domestic funding.
11.7
Interest During Construction
Based on the assumption that the project being financed from equity and loan in the ratio of
70:30 and the equity component being released simultaneously along with the loan
component, the interest during construction works out to Rs 4.99 Crore.
The rate of interest for Domestic Loan has been considered @10.5 p.a. The interest during
construction would however be based on the actual financial structure of the project and
applicable terms of interest on loan(s), etc.
11.8
Monthly Fixed Charges
Considering rate of interest on Domestic Loan @ 10.5 %, return on equity @ 15.5 %, O&M
charges @ 7.5 %, Debt: Equity ratio 70: 30, interest on working capital @ 13 % the
indicative monthly fixed charges works out as Rs.1.83 Crores (ANNEXURE – 9.0) for base
cost and Rs.2.05 Crores (ANNEXURE – 9.0a) for completed cost. These charges are
based on present philosophy for ULDC project tariff. As the tariff notification for 2009-14,
did not have provision for communication system, a petition has been filed with CERC for
the same. Actual tariff for the same shall be based on CERC notification.
11.9
Completion Cost
The completion cost of the project is expected to be Rs.96.47 crores including IDC. The
above cost has been worked out based on the average movement of WPI (80% weightage)
and CPI (20% weightage) for the preceeding 12 month period as per guide lines dated
06.08.1997.
12.0 TIME FRAME
The said project is scheduled to be commissioned within 30 months from the date of
Investment Approval. (Enclosed at Exhibit-2.0).
13.0 RISK ANALYSIS
Revenue Risk
The capital cost of the Wideband Communication System comprises of (i) an equity component and (ii) a loan component. This is recovered through the annual charges consisting of
return required for the equity, an interest for the loan component together the O & M
charges and interest on working capital from the beneficiaries as per CERC/GOI
Guidelines. These are recovered in monthly fixed charges from the beneficiaries. In addition
to annual charges, FERV and incentives, etc. as per notification would also be payable.
Page 12 of 16
Regulatory Risk
The provision that the tariff for existing assets commissioned as well as the additional tariff
payable due to additional capitalization from year to year, etc. shall be computed by
POWERGRID based on norms / methodology to be specified by the Central Electricity
Regulatory Commission (CERC) as amended from time to time.
Environmental Risk
Not foreseen.
Legal / Contractual Risks
Not foreseen.
Project Management Risks
Not foreseen.
14.0 PAST RECORD OF SUCCESSFUL PROJECT IMPLEMENTATION
POWERGRID has built around 20,733 Km of FO based communication network by
installing the FO cable on POWERGRID and state utilities’ transmission lines under ULDC
projects and under POWERGRID’s Business Telecom Network. This network is in
successful operation. The state portion of the network is also being maintained by
POWERGRID on their behalf. As on March 31, 2011, POWERGRID operates about 82354
ckt. kms. of transmission lines and 135 Sub-stations with a transformation capacity of over
93050 MVA. POWERGRID has maintained the transmission systems availability over 99%
consistently.. POWERGRID has team of dedicated experts in the field of engineering for
Load Dispatch and Communication facilities comprising of SCADA/EMS system and
Telecommunication Systems, substation and Transmission Line Engg equipped with stateof-the-art technology, software capabilities and computer aided facilities for Planning,
Design, Operation and Maintenance of Load Despatch & Communication facilities and
transmission system. It has a well established system of continuous feedback from the field
and upgrades the system accordingly.
Load Dispatch and Communication facilities involve the technologies which are fast
developing and have comparatively short life cycle. The control center requirements are
also changing due to regulatory changes such as implementation of ABT, Open access,
desirability to declare spare transmission capacity etc. Based on the development on
technology front and the feedback from the grid operators as well as in pursuit to
economize the cost and implementation period, its experts are vigorously pursuing the
developments on technical and operational fronts and systems are designed considering
these developments.
POWERGRID has developed a project monitoring system matching with the organization
structure, complexity / intricacies involved in the project implementation and Management
information system. The system calls for increasing details of planning in all the facets of
functions such as engineering, contracts, site and corresponding levels of monitoring and
control, for generating a management summary report to the top management. This
management summary report highlights the project completion trends, actions being
taken/to be taken for the attention of the top management on exceptional basis of critical
areas.
Further, the monitoring system envisages a regular total project review called project review
meeting (PRM). This review meeting is headed by Regional in-charge with representation
from all functions viz. Contracts, Engineering, Field, Personnel, Finance, Corporate
Monitoring Group, etc. The participants discuss project critical, project interface problems
and project completion trends, etc.
Page 13 of 16
From the discussions held during the PRM emanates a status report and also an exception
report put up to the Chief Executive and Directors which highlights extremely critical areas
needing immediate attention and assistance required. Once in three months the PRM is
held at Corporate Centre. These discussions help in identifying the critical areas and
seeking decisions for speedy project implementation.
15.0 SUCCESS CRITERIA
The proposed Fiber Optic based Wideband Communication System for Eastern Region has
been evolved by carrying out detailed studies of existing wideband communication network,
availability of transmission line connectivity and discussions with beneficiaries at ERPC
level. Regarding achieving its objective in the stipulated time frame, it is to mention that
POWERGRID has in-house expertise in all specialized areas of Fiber Optic based
Wideband Communication Systems and associated requirements.
In support of above, it may be stated that POWERGRID has been rated as “Excellent” since
1993-94 in achieving the MoU targets with Ministry of Power and is recipient of Prime
Minister’s MoU Award consecutively for many years for being amongst top ten PSUs.
POWERGRID has also been associated for establishment of many complex SCADA/EMS
and communication projects by using live line stringing technology for OPGW installation in
most of the projects, which are in operation. Such projects include:
 State of the art Unified Load Despatch and Communication Project in Northern Region
involving 2142 Kms of Fiber –Optic and 78 Hops of Micro wave communication network.
 State of the art Unified Load Despatch and Communication Project in Southern Region
involving 2324 Kms of Fiber –Optic and 35 Hops of Micro wave communication network.
 State of the art Unified Load Despatch and Communication Project in North Eastern
Region involving 903 Kms of Fiber –Optic and 12Hops of Micro wave communication
network.
 State of the art Unified Load Despatch and Communication Project in Eastern Region
involving 1453 Kms of Fiber –Optic and 40 Hops of Micro wave communication network.
 State of the art Unified Load Despatch and Communication Project in Western Region
involving 2561 Kms of Fiber –Optic communication network.
 POWERGRID Telecom Diversification Project involving more than 13,000 kms of fiberoptic based commercial network.
Consultancy Projects
 OPGW System project for Bhutan Telecom comprising of 125 kms of OPGW based
network.
 OPGW System project for THPA, Bhutan comprising of 53 kms of OPGW based
network in a difficult terrain
 OPGW System Package associated with Northern Transmission System in Afghanistan
by laying 202 kms of OPGW cable on 220 kV transmission systems in a difficult terrain.
 Dhanu-Versoa (Mumbai) OPGW link for BSES by laying 105 kms of OPGW.
 Uttrakhand Load Despatch & Communication Project consisting 228 kms of OPGW
network.- ongoing.
 NLDC Project for Bhutan Power Corporation, Bhutan - ongoing
 Feasibility Report for MSETCL for establishing 2300 kms reliable wideband backbone
communication system under Comprehensive Communication Plan.
 DEWA, Dubai 300 kms of OPGW based communication system.
 ASCON project of Ministry of Defense, for engineering verification of the Microwave
Towers and aviation systems in at 9 locations including difficult terrain in J&K and NER.
Page 14 of 16
 SCADA/DMS NDMC Project comprising of establishment of SCADA/DMS control centre
having 28 Substation RTUs and, 60 kms of underground fiber optic based
communication system.
16.0 SUSTAINABILITY
16.1
System Design Philosophy
The Fiber Optic based Wideband Communication System designed in the most optimum
manner such that availability of the system is of the highest order prevailing in the industry.
The system and equipment parameters are chosen according to the present trends in
technology, the fibers available is such that the attenuation & dispersion in them are bare
minimum. Wideband communication equipment are SDH based technology with STM-16
capacity.
16.2
System Operation Philosophy
The Network Management System (NMS) is envisaged for the entire wideband
communication which will facilitate – configuration management, fault management,
performance management
and
management from a Centralized location and also
through local craft terminal during maintenance.
16.3
System Maintenance Philosophy
The maintenance management system in vogue in POWERGRID aims at keeping the
system under stable conditions while ensuring minimum maintenance cost and safety of
equipment and personnel. The maintenance management schedule includes detailed work
specification covering all maintenance jobs, permit to work system, long term maintenance
planning, meetings for finalising maintenance schedule for next 24 hours and resolution of
interface problems between departments. These meetings are supplemented by meeting
of HODs on alternate days to accelerate the decision making process and to lay down the
priorities and guidelines for maintenance work during next 72 hours. Further FO
communication system being specialized area, support of specialized agencies is taken for
electronic equipment through maintenance contracts as per existing practice in
POWERGRID and telecom industry. The provision for such maintenance support would be
kept in the technical specification for a limited period (for seven years) for which the cost
may be allocated to O&M charges.
16.3.1 Spare parts Management System
The primary objective of spare part management system will be to ensure timely availability
of proper spare parts for efficient maintenance of the Fiber Optic based Wideband
Communication System without excessive build-up on non-moving and slow moving
inventory. The spare parts management system for this project will cover the following
areas:
a)
b)
c)
d)
e)
Proper codification of all spares and consumables
Spare parts indenting and procurement policy
Ordering of critical mandatory and recommended spares
Judicious fixation of inventory levels and ordering levels for spare parts based on our
experience in other projects.
Development of more than one source wherever practicable.
Page 15 of 16
16.3.2 Training of personnel
The expertise available within the organization is required to be augmented to cater maintenance of state-of-the art technology SDH equipment & OPGW cable to be installed under
the proposed project. Accordingly, training in the areas including OPGW, SDH & MUX
Equipment and NMS shall be arranged by POWERGRID at manufacturer’s place and site
which is considered essential under the project. If communication equipments installed at
the constituent’s premises, the training for constituent representative shall also be
considered under this project.
16.3.3 O & M Manuals
a)
b)
Adequate O & M manuals will be distributed to all concerned as per the approved
distribution policy of the company.
O & M manuals will be available to all concerned prior to commissioning of Fiber Optic
based Wideband Communication System to avoid problems in preparation of
commissioning documents as well as proper installation & commissioning of equipment.
Page 16 of 16
BSNL List of Nodal Officers
ANNEX-VI
S.N. Circle
Name Shri/Smt
Post
Phone
Fax
1
P K Sahana
DGM (EB)
03192-230028
03192-238700
9433000170 pksahana@gmail.com
Damodar Rao
GM (EB)
040-23202030
040-23204060
9440000403 gmeb_ap@bsnl.co.in
M Sambasiva Rao
DGM (EB) Hybd
040-23202233
040-23201103
9440000488 msambasivarao@bsnl.co.in
Assam
KVN Rao
Sr.GM (EB)
0361-2736430
0361-2462103
9435000006 gmbd_assam@bsnl.co.in
Assam
Inrajeet Dass
DGM
0361-2735625
0361-2734217
9435599275 agmeb_co@bsnl.co.in
Bihar
R P Singh
GM EB
0612-2227500
0612-220419
9431000026 gmbdnc_bihar@bsnl.co.in
Bihar
Manoj Bhakta
DGM EB
0612-2236700
0612-2221681
9431000300
Chhattisgarh Shyam Sunder Chandak
GM(Gold)
0771-2534300
/2536661
Chhattisgarh Kush Manhar
DGM(Gold)
Gujarat
Devesh Kumar
Sr. GM(Gold)
Gujarat
Girish N KATARIA
DGM (GOLD)
Haryana
Naresh Kumar Sharma
GM (EB)
Haryana
H.C. Ahuja
DGM
HP
Anita Johari
GM (EB)
HP
Rajender Kumar
J&K
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
A&N
Andhra
Pradesh
Andhra
Pradesh
0771-2228700/
2535553
07710771-2229800
2228700/253555
079-26481441 / 3079-26481857 /
2648-111226480909
079-26480608 079-26480609
Mobile
E-mail
manojkbhakta@gmail.com,man
ojbhakta@bsnl.co.in
9406401001 gmeb_cg@bsnl.co.in
9425201888 dgmeb.cg@gmail.com
9428815511 gmnwpcfa@gmail.com
9426677899 dgmeb.gj@gmail.com
0171-2603366 0171-2603311
01710171-2603285
2603350/260324
0177-2620440,
0177-2628881
2628880
9466100018 naresh_sharma@bsnl.co.in
DGM(EB)
0177-2622100
0177-2626999
A K Garg
GM (EB)
0191-2477011
0191-2475759
9418071222 dgmebithp@bsnl.co.in,dgmbdh
p@gmail.com
9419120005 garg_ak@yahoo.com
J&K
Girdhari Lal
DGM EB
0191-2470266
0191-2477160
9419120058
Jharkhand
Arun Kumar
GM (EB)
0651-2273700
0651-2273733
9471700088 arungmd@gmail.com
Jharkhand
S K Rana
DGM (EB)
0651-2205249
0651-2211500
9431140555 dgm.skr@gmail.com,sunil_ku
mar_rana@hotmail.com
Karnataka
Surinder Shinoy
GM (EB)
080-25558585
080-25308585
9448010689 sshenoy@bsnl.co.in
Karnataka
P S Subramanyam
DGM(EB&Silver)
080-25554855
080-25554877
9448010993 pssubramanyam@bsnl.co.in
Kerala
K.Venkataraman
GM (EB)
0471-2306600
0471-2305922
9400001800
Kerala
Biji Pratap
DGM (EB &CP)
0471-2309393
0471-2309292
9447127766 biji.bsnl26@gmail.com
Kolkatta TD Amit Kumar Bhattacharya GM (EB)
033-22135000
033-22424242
9433005055 srgmebctd@gmail.com
Kolkatta TD Rangarajan
DGM (EB)
033-22109000
033-22109001
94133000442 n.rangarajan.kam@gmail.com
Sandeep Sawarkar
GM(Gold)
0755-2666888
0755-2767073
Arun Kumar
DGM (Gold- S&M)
0755-2550214
0755-25502010
022-26604816 /
022-26603030
26601366
Madhya
Pradesh
Madhya
Pradesh
9416004402 dgm_eb_har@bsnl.co.in
9418054151
kkvenkataraman61@gmail.com
,gm_sm_cm_kerala@bsnl.co.in
9425007212 gmebmp@gmail.com
9425111174
Maharashtra S.K. Bose
GM(Gold)
Maharashtra Vijai Pal
DGM (EB) Gold
022-26615816
022-26601256
9422431332 vijai.pal@gmail.com
PUNE
Kali Sharan Ahirwar
GM (Pt & Gold Pune) 020-24426666
020-24422525
9422320100 gmebbsnlpune@gmail.com
PUNE
LB Rawate
DGM (Gold) Pune
020-24220538
9422001122 jaykumarthorat@gmail.com
NE - I
D Giri
020-PS
24226030,
Sr.GM (Mktg/IT&EB) 0364-2222100
0364-2228244
9420488316 skbose941@gmail.com
9436100016 gmmktgne1@gmail.com
17
18
19
20
21
22
23
24
25
26
NE - I
Om Prakash
DGM (Mktg)
0364-2502765
0364-2501909
9436962425 dgmeb_ne1@bsnl.co.in
NE - II
Feroz Anwar
GM
03862-237147
03862-237149
9452020123 gmhrne2@gmail.com
NE - II
Jai Kumar Thorat
DGM
03862-
03862-
9402050505 jaykumarthorat@gmail.com
Orissa
J Ganta
GM (EB)
0674-2545900
0674-2541220
9437494374
j.ganta@bsnl.co.in/j0.ganta@g
mail.com
Orissa
Ramesh Chandra Khuntia
DGM(Mktg. & EB)
0674-2541100
0674-2540066
9437300100
rckhuntia@bsnl.co.in,rameshkh
untia@gmail.com
Punjab
B D Garg
GM (EB)
0172-2612888
0172-2612800
9465700003 bdgarg@bsnl.co.in
Punjab
R S Sharma
DGM
0172-2647575
0172-2608173
9463999044 dgmebcopb@gmail.com
Rajasthan
Gunjan Saxena
Sr G M (BB/NOWCFA&EB)
0141-2363132
0141-2374888
9413399055 gmdraj.bsnl@gmail.com
Rajasthan
N K Meena
DGM(EB)
0141-2374887
0141-2374888
9414004110
Chennai TD Ram Ganesan
GM (Pt&Gold)
044-25612077
044-25612003
9444556878 ramganesan2k@gmail.com
Chennai TD Munuswamy
DGM (EB)
044-25611446
044-26471336
9444909890 muniswamybsnl@yahoo.co.in
Tamilnadu
Mahender Kumar
GM (EB)
044-28256000
044-28251718
9444000904 gmbd_tn@bsnl.co.in
Tamilnadu
V Gopalakrishanan
DGM(EB)
044-28217700
044-28211636
9486100440 dgmebtn@gmail.com
U.P. (East)
Rajesh Kumar
GM (EB)
0522-2624600
0522-2628400
9415111155 rajeshkumar1@bsnl.co.in
U.P. (East)
Binod Shahi
Addl GM (EB)
0522-2628454
0522-2628400
9454000065
U.P. (West)
P K Srivastava
GM (EB&Mktg)
0121-2664500
0121-2664300
9412000160 srgmmktgupw@gmail.com
U.P. (West)
A K Jain
DGM (EB)
0121-2600786
0121-2643620
9412739000 dgmeb_upw@yahoo.com
Uttranchal
Rajeev Johari
GM (EB)
0135-2713055
0135-2712272
9412000630 gmcfaukd@bsnl.co.in
Uttranchal
Rahul Rastogi
DGM (Mktg, BB &
EB)
0135-2652100
0135-
West Bengal Kundu A K
Sr. GM(Sales&Mktg)
033-22135747
033-22135746
9433000608 gmmktgeb@gmail.com
West Bengal Adhir Kr Biswas
DGM(Sales&Mktg)
033-22420411
033-22420413
9434774349 adhir1955@gmail.com
dgmeb_raj@bsnl.co.in/
nkmeena96@gmail.com
ebcellupe@gmail.com/binodsh
ahi2211@gmail.com
9412000255 dgmebukd@gmail.com
Download