RECOVERY AND RECYCLING PROCESSES OF SCHEDULED WASTE IN MALAYSIA NORHASMI BINTI HASSAN A thesis submitted in fulfillment of the requirements for the award of the degree of Master of Engineering (Civil – Environmental Management) Faculty of Civil Engineering Universiti Teknologi Malaysia NOVEMBER 2009 iii Thank you very much for your courage and support, may Allah bless my beloved husband, Hisam bin Hussain childrens, Aqilah Husna Anwar Hazim Ammar Hakimi and sister Norshuzilah iv ACKNOWLEDGEMENT I would like to express my sincere gratitude and appreciation to my supervisor, Assoc. Prof. Dr. Johan bin Sohaili for his continue support, generous guidance, help, patience and encouragement in the duration of the thesis preparation until its completion. Last but not least, I would also want to thank to my friends and any party who has contributed into the completion of this thesis. Your contributions are really meaning to me. To all of you, thank you very much. v ABSTRACT For the past four decades treatment and disposal of scheduled wastes resulting in many environmental problems such as illegal dumping, illegal export and import of wastes. Nevertheless, with new technology development and increasing commitment, many types of scheduled wastes can be recovered or recycled. However, there are three main issues to consider when discussing scheduled waste management hierarchy, which are lack of awareness on the importance of scheduled waste recovery or recycling, regulatory constraints, and lack of knowledge on the state-of-the-art technology for the recovery or recycling processes. The aim and objectives of the study are to produce the recovery or recycling process flow for potential scheduled wastes that can be recovered or recycled, identify the waste acceptance criteria and material balance calculation. The study was conducted through an evaluation and comparison on the recovery or recycling processes done by the related industries in Malaysia and site visit to recycling factory. From the study, it was found out that out of total 77 types of scheduled wastes listed in the Environmental Quality (Scheduled Wastes) Regulations 2005 First Schedule, there are 41(53%) types are being recovered or recycled while the flow of recovery or recycling processes for 16 (21%) types of scheduled waste has been reviewed. In addition, the waste acceptance criteria have been identified from the minimum level of acceptance prior to recovery or recycling processes. The material balance calculation which indicates the percentage of treated or recovered waste materials, residual sludge material generated and wastewater discharged if the plant is operated at its maximum capacity is also been addressed in order to enable the factory or consultant have the certainty to invest in the required new technology, hence to ensure efficient scheduled wastes recovery activities. vi ABSTRAK Dalam tempoh empat dekad yang lalu, rawatan dan pelupusan sisa terjadual mengakibatkan banyak masaalah alam sekitar. Walaubagaimanapun, dengan kemajuan teknologi terkini dan komitmen yang tingg, berbagai jenis sisa terjadual boleh diperoleh semula atau dikitar semula. Namun, terdapat 3 isu utama yang perlu dipertimbang bila membincangkan tentang hiraki pengurusan sisa terjadual; iaitu kurangnya kesedaran tentang kepentingan peroleh atau kitar semula sisa terjadual, kekangan peraturan dan pengetahuan yang cetek tentang teknologi pembinaan untuk proses perolehan semula atau kitar semula. Tujuan dan objektif kajian adalah untuk menghasilkan proses aliran peroleh semula atau kitar semula sisa terjadual yang berpotensi untuk diperoleh atau dikitar semula, mengenalpasti kriteria kebolehterimaan sisa dan pengiraan keseimbangan bahan. Kajian dijalanakan melalui penilaian dan perbandingan terhadap proses peroleh dan kitar semula yang telah dilaksanakan oleh industri yang terlibat di Malaysia dan lawatan ke kilang kitar semula. Hasil dari kajian, didapati daripada jumlah 77 jenis sisa terjadual yang disenaraikan dalam Peraturan Alam Sekitar (Sisa Terjadual) 2005, Jadual Pertama, 41 (53%) jenis boleh di peroleh atau dikitar semula sementara aliran proses peroleh atau kitar semula 16 (21%) jenis sisa terjadual telah dikaji. Berikutan itu, kriteria kebolehterimaan sisa telah dikenalpasti dari tahap minimum untuk penerimaan sebelum proses peroleh atau kitar semula. Pengiraan keseimbangan bahan yang menentukan peratus perolehan semula bahan dari sisa terjadual, sisa terhasil dan penghasilan air sisa jika kilang beroperasi pada tahap kapasiti yang maksimum juga dikenalpasti bagi membolehkan pengusaha kilang atau perunding kitar semula sisa terjadual yakin untuk melabur dalam teknologi kitar semula sisa terjadual untuk memastikan kecekapan aktiviti kitar semula sisa terjadual. vii TABLE OF CONTENTS CHAPTER 1 TITLE PAGE DECLARATION ii DEDICATION iii ACKNOWLEDGEMENT iv ABSTRACT v ABSTRAK vi TABLE OF CONTENTS vii LIST OF TABLES xii LIST OF FIGURES xiv LIST OF ABBREVIATIONS xvi LIST OF APPENDICES xviii INTRODUCTION 1 1.1 Preface 1 1.2 Problem Statement 2 1.3 Aim and Objectives 4 1.4 Scope of Project 5 viii 1.5 2 3 4 Significant of the Study 5 LITERATURE REVIEW 6 2.1 Introduction 6 2.2 Hazardous Substance and Scheduled Waste 8 2.3 Types of Scheduled Waste Generated in Malaysia 10 2.4 Problems Associated with Scheduled Waste 14 2.5 Environmental Requirements on Scheduled Waste 15 2.6 The Basel Convention 19 2.7 Conclusion 21 RESEARCH METHODOLOGY 21 3.1 Informations Gathering 22 3.2 List of Data Collected 23 RECYCLING AND RECOVERY PROCESSES 27 4.1 Introduction 27 4.2 Dust, Slag, Dross Or Ash Recovery 27 4.2.1 27 General Elements of Dust, Slag, Dross Or Ash 4.2.2 Statement of Need 28 4.2.3 Waste Acceptance Criteria for Solder and 28 Aluminium Dross 4.2.4 Recovery Process Description 29 4.2.5 Material Balance 32 ix 4.3 Waste Catalyst Recovery 32 4.3.1 General Elements of Waste Catalyst 32 4.3.2 Statement of Need 33 4.3.3 Waste Catalyst Acceptance Criteria 33 4.3.4 Process Description for Gold Recovery 34 from Waste Catalyst 4.3.5 Process Description for Silver Recovery 35 from Waste Catalyst 4.3.6 Process Description for Palladium 37 Recovery from Waste Catalyst 4.3.7 4.4 Material Balance 40 Waste Oil Recovery 42 4.4.1 General Elements of Waste Oil 42 4.4.2 Statement of Need 43 4.4.3 Waste Acceptability Criteria for Waste Oil 43 Recovery 4.5 4.4.4 Waste Oil Recovery Process Description 44 4.4.5 Material Balance 52 4.4.6 Oil and Water Mixture Or Ballast Water 54 4.4.7 The Recovery Oil 56 Waste Coolant Recovery 56 4.5.1 General Elements of Coolant 57 4.5.2 Statement of Need 57 4.5.3 Waste Coolant Acceptability Criteria 58 4.5.4 Waste Coolant Recovery Process 59 Description 4.5.5 4.6 Material Balance for Coolant Recovery 61 Solvent Recovery 61 4.6.1 61 General Elements of Solvent x 4.7 4.6.2 Statement of Need 62 4.6.3 Waste Solvent Acceptability Criteria 62 4.6.4 Solvent Recovery Process Description 64 4.6.5 Material Balance 65 Used Industrial Container Recovery 67 4.7.1 General Elements of Industrial Container 67 4.7.2 Statement of Need 69 4.7.3 Waste Acceptability Criteria for Used 69 Industrial Container Recovery 4.7.4 Industrial Container Recovery Process 70 Description 4.7.5 4.8 Material Balance 73 Used Rags and Filters Recovery 73 4.8.1 General Elements of Rags and Filters 73 4.8.2 Statement of Need 74 4.8.3 Used Rags and Filters Waste Acceptability 74 Criteria 4.8.4 Used Rags and Filters Recovery Process 75 Description 4.8.5 4.9 5 Conclusion 78 78 CONCLUSION 79 5.1 Conclusion 79 5.2 Recommendations 80 REFERENCES Material Balance 81 xi Appendix A 85 xii LIST OF TABLES TABLE NO. TITTLE PAGE 2.1 Examples of typical scheduled wastes 10 2.2 Reported incidents of scheduled wastes illegal disposals in 15 Malaysia 3.1 41 Types of scheduled wastes listed in the Environmental 23 Quality (Scheduled Wastes) Regulations, 2005First Schedule are found being recovered or recycled 3.2 Recovery Percentage for 16 Types of Scheduled Wastes 25 4.1 Solder and aluminium dross waste acceptance criteria 29 4.2 Material balance for solder and aluminium dross recovery 32 4.3 Waste catalyst acceptance criteria 34 4.4 Material balance for waste catalyst recovery 40 4.5 Potential land-based and water-based sources of used oils 44 recovery 4.6 Waste oil acceptance criteria 45 4.7 Material balance for waste oil recovery 53 4.8 Material balance for oil and water mixture or ballast water 56 recovery xiii 4.9 Standard and specification of recovered waste oil 56 4.10 Waste coolant acceptance criteria for recovery 58 4.11 Material balance for coolant recovery 61 4.12 Boiling point, density and TLV of some common solvents 63 base on Material Safety Data Sheet 4.13 Waste solvent acceptance criteria 64 4.14 Material balance for waste solvent recovery 67 4.15 Industrial container acceptance criteria 69 4.16 Material balance for industrial containers recovery 73 4.17 Used rags and filters acceptance criteria 75 4.18 Material balance for rags or filters recycling 78 xiv LIST OF FIGURES FIGURE NO. TITTLE PAGE 2.1 Waste Management Hierarchy – “3 Rs” Concept 7 2.2 Scheduled waste generation Malaysia 1994 – 2005 12 2.3 Types of scheduled wastes can be recycled or 13 recovered 2.4 Examples of scheduled wastes illegal disposals will 16 pollute soil in the area 2.5 Overview of the scheduled waste management in 20 Malaysia 4.1 Ingot produced after smelting 30 4.2 Aluminium melting rotary furnace 30 4.3 Aluminium dross 30 4.4 Typical process flow diagram and material balance for 31 solder and aluminium dross recovery 4.5 Typical gold recovery process flow and material 36 balance by ion exchange 4.6 Typical gold recovery process flow and material 38 balance by acid treatment 4.7 Typical silver recovery process flow and material balance by acid treatment 39 4.8 xv Typical palladium recovery process flow and material 41 balance 4.9 Typical process flow and material balance across the oil 48 recovery distillation process 4.10 The typical flow and material balance of the 49 evaporation process 4.11 The typical flow and material balance of waste oil 51 pyrolysis recovery process 4.12 Schematic diagram of pyrolysis system 52 4.13 Gravity oil water separator 53 4.14 Stainless steel wire mesh bag filters 53 4.15 The typical flow of oil and water mixture centrifuge 55 system recovery process 4.16 Typical process flow and material balance across the 60 coolant recovery 4.17 The typical flow diagram of solvent separation and 66 evaporation recovery process 4.18 Types of industrial containers 68 4.19 The typical flow process of containers recycling 71 4.20 Cleaning Of Containers 72 4.21 A: typical industrial washing machine; B: industrial 76 dryer used for rags/filters cleaning 4.22 The typical flow process of contaminated rags or filters recycling 77 xvi LIST OF ABBREVIATIONS AuCl auric chloride Ag silver AgCl Silver chloride CCA Copper-chrome-arsenic CPI Corrugated Plate Interceptor DOE Department of Environment EIA Environmental Impact Assessment EPU Economic Planning Unit GDP Gross Domestic Product H+ hidrogen HCL hydrochloride acid HDPE High-density polyethylene HNO3 nitric acid IBC Intermediate bulk container IC Integrated Circuit N2 nitrogen NaCl Sodium chloride NaNO3 Sodium nitrate NH4 Ammonium N2H4 hydrazine xvii NH4Cl Ammonium chloride PCB Printed Circuit Board Pd2+ palladium R Resin SS Suspended Solids SW Scheduled Waste TDS Total Dissolved Solids WAC Waste Acceptance Criteria xvii LIST OF APPENDICES APPENDIX A TITTLE Environmental Quality (Scheduled Waste) Regulations 2005 PAGE 85 CHAPTER 1 INTRODUCTION 1.1 Preface According to the Environmental Quality (Scheduled Wastes) Regulations, 2005 scheduled waste means any waste falling within the categories of waste listed in the First Schedule. Due to its quantity, concentration, physical, chemical or infectious characteristics, scheduled waste may cause to an increase in mortality, or an increase in irreversible or incapacitating illness. Nevertheless, scheduled waste may pose a substantial present or potential hazard to human health or the environment when improperly treated, stored or disposed of, or otherwise mismanaged. Increasing volume of scheduled waste generated daily demands good management system as well as effective support of of infrastructure. High volume waste generated by Malaysian industries for the past three decades provides enough supply of wastes for recovery purposes (Azni et.al., 2004). With decreasing capacity of treating scheduled waste at Kualiti Alam Sdn Bhd, there is need to recover or recycle scheduled wastes for other uses. Scheduled wastes such as spent solvent, spent oil, slag and dross, as well as contaminated rag generated during manufacturing or packaging has been found having significant values. Hence, recovery and recycling of scheduled waste can offer a number of environmental in terms of reducing the volume of scheduled waste that needs to be finally disposed. In addition, recovery and recycling would help 2 industry to obtain alternative resources and give meaning to a concept of “waste to wealth” which is also able to reduce their manufacturing cost. As pollution is bad for business, innovative environmental management methods are designed to satisfy all regulatory requirements, to protect and enhance the value of physical assets as well as corporate reputations. 1.2 Problem Statement There are three main issues to consider when discussing scheduled waste management hierarchy of reduce, reuse, recycle, and recover. The three main issues are lack of awareness on the importance of scheduled waste recovery and recycling, regulatory constraints, and lack of knowledge on the state-of-the-art technology for the recovery and recycling processes. Manufacturing industry plays an important role for Malaysia’s economic growth for the past four decades. This sectors contribute to Malaysia’s Gross Domestic Product (GDP) grows 18.2% from 2004 to 2008 (EPU, 2008). The Malaysian Government is intended to focus its effort on developing the country’s agricultural industry as stated in The Ninth Malaysia Plan, however the manufacturing industry turn up as the leading sector for development process and economic growth. The existing management systems in Malaysia for industrial wastes give priority to end-of-pipe approach which promotes the use of treatment and disposal method, rather than recovery or recycling (Ahmad Fariz Mohamed et.al., 2008). Consequently, this approach has been found creating many environmental problems such as new land requirements for disposals and illegal dumping as the industrial activity generates huge amount of wastes. Scheduled waste management in Malaysia is well-established after more than 35 years of experience commencing from the enactment of Environmental Quality Act 1974. Nonetheless, problems associated with scheduled waste management such 3 as lack of sustainable awareness, enforcement, periodical monitoring as well as illegal dumping still exist that necessitate urgent intervention from relevant stakeholders. It should be stressed that the best scheduled waste management is by reducing the generation of the wastes, nevertheless, reuse or recycling and recovery of wastes by the local industries can promote local sustainability initiatives. As such, specific legislations on “green” production for industries such as implementation of cleaner technology should be enacted to facilitate this initiative. Regulation 6 in the Environmental Quality (Scheduled Wastes) Regulations 2005 and the amendment Regulations 2007 defines in a very general manner the recovery of material or product from scheduled waste. The 77 types of scheduled wastes listed in the First Schedule should be defined specifically by waste acceptance criteria prior recovery and recycling processes. A complete description of scheduled waste should identify source, type, categories and also the process involved in the generation of the scheduled waste. The chemical composition such as heavy metals, sulfur, benzene, etc should be defined as well. In addition, the criteria to be met before waste is accepted for recovery and recycling would enable the factory to have the certainty to invest in the required new technology. Environmental Impact Assessment Guidance Document states that the Waste Acceptance Criteria (WAC) contains the level of pollutants (impurities) in the scheduled wastes that can be accepted in the recovery process, as well as the level or percentage of precious metals that can be economically recovered. Basic processes used for recovery facilities are electrolysis, distillation, extraction, salvation, smelting, chemical stripping, etc. (DOE, 2007). Recovery and recycling of scheduled wastes, such as waste catalyst, spent or waste solvent, contaminated rag, paper and plastic, used drum, used HDPE container, etc. has become an important support industry. This is in line with the increasing volume of scheduled waste generated plus increasing demand for limited natural resource. Therefore, it provides alternative resources for the recycling industry and reduces dependency on natural resource such as oil for plastic and metal for drum. 4 However, the infrastructure for physical system such as transportation, handling facilities, and transfer station and treatment plant for industrial waste recovery is not fully established. These infrastructures are important to ensure that industrial waste recovery and recycling are done in sustainable manner and able to minimize impact to the environment and human health. Subsequently, there are also weaknesses in other sectors such as legislation, governance, technology, physical system, economic and human resource (Ahmad Fariz et.al., 2008). Malaysia is targeting to achieve 30% of total solid and scheduled waste recycling in 2020 besides 5% currently (Utusan Malaysia, 2009). Therefore, the current management approach needs to be changed towards a more sustainable management regime as there are now technology and demand to recover and recycle waste including scheduled waste for other uses. Through the Ministry of Natural Resources and the Environment and the Ministry of Housing and Local Government, scheduled waste recovery and recycling has been identified as an important activity. In addition, The Ministry of Energy, Green Technology and Water plus Key Performance Indicator as announced by Prime Minister recently could speed up the invention of scheduled waste recovery technology. Thus, the study would guide the investors on how the scheduled waste can be recovered and the quantity produced in Material Balance calculation for recovery and recycling processes. 1.3 Aim and Objectives The aim of the project is to produce the recovery and recycling process flow of selected scheduled wastes. The objectives of the study are: (i) To initiate the possibility of scheduled waste recovery and recycling processes based on the Environmental Quality Act requirements 5 (ii) To organized recovery and recycling processes of selected scheduled waste listed under Environmental Quality (Scheduled Waste) Regulations 2005 (iii) To formulate the Waste Acceptance Criteria (WAC) and Material Balance calculation for the recovery and recycling processes. 1.4 Scope of Project The scope of this study is the recovery and recycling processes practiced by factories in Malaysia who are involved in the scheduled waste recovery and recycling. Assessment on physical and chemical characteristics, WAC and material balance calculation will be based on current practice and findings by the related factories. 1.5 Significant of the Study Scheduled waste recovery or recycling contributed significantly to economic benefits and environmental protection. Currently, the amount of scheduled waste generated by the manufacturing industries in Malaysia shows increasing trends. Therefore, the study would help the Environmental Impact Assessment Consultant, investors and also private and government sectors to create an innovative technology in recovery or recycling processes for scheduled waste as listed in the Environmental Quality (Scheduled Wastes) Regulations 2005. CHAPTER 2 LITERATURE REVIEW 2.1 Introduction Protection of human health and the environment was to be accomplished by “cradle to grave” tracking of scheduled wastes through the use of a manifest. There are a number of concepts about waste management which vary in their usage between countries or regions. Some of the most general, widely-used concepts include "3 Rs" reduce, reuse and recycle, which classify waste management strategies according to the desirability in terms of waste minimization as showed in Figure 2.1. The waste hierarchy remains the cornerstone of most waste minimization strategies. The aim of the waste hierarchy is to gain the maximum practical benefits from products while generating minimal waste. Many authorities agree, the 3 R’s are the most immediate and effective way organizations and individuals can conserve resources, prevent pollution and save money. Waste prevention, or “source reduction,” means consuming and throwing away less or cutting down on waste and using products made to last rather than disposable. Reusing products when possible is even better than recycling, because the item does not need to be reprocessed before it can be used again. Recycling turns materials that would normally be turned to waste into valuable resources. In addition, “3 Rs” Concept is buying products that are less toxic for instance polystyrene container or contain less packaging, using reusable containers and other reusable 7 items, maintaining and repairing products, participating in recycling programs, and buying products made from recycled materials. Source Reduction Reuse Recycling and Composting Landfill with Energy Recovery Landfill Figure 2.1: Waste Management Hierarchy – “3 Rs” Concept Landfills have a significant impact on the environment. Burying waste in landfills also means valuable resources are lost, including those involved in producing some other valuable products. Malaysia will not be able to rely on landfills for ever as suitable space is limited. Recently, the private and government sectors in Malaysia are actively promoting the concept of 3 R’s. Some of the activities are encouraging the use of recycled bags in shopping complex, practicing “separation at source” for solid waste collection starting with Putrajaya residents, promoting the use of composed fertilizer in agriculture industries, etc. The launching of the National Green Technology Policy on 24 July 2009 marks an important milestone in Malaysia journey to the future, as Malaysia take cognizance of the need for better and more efficient use of technology which will also be less harmful to the environment. In conjunction with the policy, the government will embark on a focused effort to increase public awareness so that the development of green technology would be well received by all members of the 8 society. There will be promotion, education and information dissemination to create the buy-in of the public to support the 'green economy' and adopt 'green practices' as part of their lifestyle. Under this thrust, the Malaysian Government will lead by example by adopting Green Technology in government facilities (Mohd Najib Bin Haji Abdul Razak, 2009) 2.2 Hazardous Substance and Scheduled Waste Hazardous waste is a discarded substance that because of its quantity, concentration, physical, chemical or infectious characteristics may cause or contribute to a serious illness or pose a substantial or potential hazard to human health or the environment when improperly treated, stored, transported or disposed of (Naval School, 1997). In relation, hazardous substance is a material with a substantial potential to pose a danger to living organisms, materials, structures, or the environment. Such dangers include explosion, fire hazard, corrosion, toxicity to organisms, or other detrimental effects. There are a range of adverse environmental effects which can result from poorly managed waste disposal measures. These include such effects as contamination of ground water and other water bodies by leachate and creation of health hazards and offensive odors. As scheduled wastes are very toxic and dangerous to the environment as well as to human health, improper waste management will result in classification as a ‘non-compliances’ or an illegal dumping case. Provided that, scheduled waste is a hazardous substance that has been discarded or otherwise designated a waste material, or one that may become hazardous by interaction with other substances. Simply, a scheduled waste is something which has been left where it shouldn't be and may cause harm. Any activity, which involves any hazardous substance also, has the potential to have a significant adverse effect on the environment and on the health of the community. 9 Properties associated with scheduled waste are as following: (a) Toxicity Wastes that produce injury upon contact with or accumulate in man and other organisms which includes mutagens, teratogens, carcinogens, and bioaccumulation for instance cleaning products, chemical fertilizers, pesticides, etc. (b) Reactivity Wastes that tend to explode (dynamite), react spontaneously (calcium carbide), or react vigorously with air, water or other substances, or subject to heat or shock (magnesium) for instance waste from cyanide plating, bleach, and other oxidizers. (c) Corrosiveness Wastes that require special containers to prevent corrosion of standard materials, for instance acids and bases. (d) Flammability Wastes that pose a fire hazard for instance petroleum products, paper. (e) Radioactivity Substances that emit some form of radiation, for instance plutonium, monazite (sand mining). (f) Infectious Biological materials such as blood specimens, tissue, dressings etc. Usually, like radioactive materials, subject to special facilities and controls. 10 Having discussed some of those things which make wastes hazardous, it is the potential for toxicity, particularly to humans, which has caused the greatest public concern. Toxic effects can range from mild allergic reactions to death through three main exposure routes; inhalation entry via the respiratory tract; ingestion entry via the gastrointestinal tract; and dermal contact entry via the skin. The following list in Table 2.1 is not complete, but indicates various types of scheduled waste. Table 2.1: Examples of typical scheduled wastes (Environmental Protection Agency, 1996) Major Group Sub-Group Cyanides Cyanide containing wastes from treatment of metals, Complex cyanides, etc Sulphuric acid , Hydrochoric acid, Nitric acid, etc Coustic soda, potash, alkaline cleaners, Ammoniom hydroxide, Waste lime and cement, etc Metal carbonyls, Mercury, mercury compounds, Arsenic, arsenic compounds, etc Oxidising agents, Reducing agents, Explosives, Highly reactive chemicals Inorganic, organometallic pesticides, Halogen containing pesticides, Copper-chrome-arsenic (CCA) Aqueous based wastes, Solvent based wastes, Paint residues, etc Acids Alkalis Inorganic Chemicals Reactive Chemicals Pesticides Paints, lacquers, varnish, resins, inks, dyes, pigments and adhesives 2.3 Types of Scheduled Waste Generated in Malaysia In 1994, Malaysia generates 417,413 metric tons of scheduled waste and increased to 632,521 metric tons in 1996, later reduced to 548,916 metric tons in 2005 (DOE, 1995; 2003; 2006). The trend of scheduled wastes generation is shown in Figure 2.2. The trend of scheduled wastes generation shows that, the amount is adequate for recovery. In 2006, 122 scheduled waste recyclers were licensed by the 11 Department of Environment, Malaysia and approximately 45.75% of hazardous wastes have been recovered from total wastes generation from 2000 to 2005 (Ahmad Fariz et.al. 2008). Using estimated value of RM 4,000 per metric ton, the estimated value of industrial hazardous waste recovery within this period is RM 4.48 billion. In conjunction, according to the Department of Environment, in 2007, eight Written Approvals were issued for the import of 133,074 tonnes of wastes for use as raw materials in industrial processes. The imported wastes comprised of copper slag, waste gypsum arising from power plant, copper slag, spent acid, waste glass from cathode ray tube and calcium hydroxide sludges. A total of 7,108 tonnes of scheduled wastes were exported for recovery operations. The exported wastes were derived from 57 waste generators and comprised mainly of metal hydroxide sludges, electrical and electronic wastes, zinc dross and spent catalyst destined for metal recovery in foreign countries. A total of 68 Written Permissions were granted by the Director General Department of Environment in 2007 for the construction of treatment and disposal facility for scheduled wastes; 35 off-site partial recovery plants (e-waste), 18 off-site recovery plants (non e-waste), 11 off–site full recovery plants (e-waste) and 4 off-site storage facilities. Neverheless, a total of 609 licences were issued for both existing and new facilities for off-site recovery, off-site storage-transportation, scheduled wastes incinerators, land treatment, off-site treatment and secured landfills.This data shows that a significant amount of scheduled wastes have been recovered, with many types of these wastes being traded in local and international market. There are various types of scheduled waste specifically in Malaysia that could be recycled, reused or recovered. Rags and filters for example, are used to clean a variety of contaminated substances such as mixed solvent, organic-based oil, paint, dye and grease, ink in printing and electronic industries that produce PCB, IC and parts as well as other industry including adhesive industries and factories using paint and ink products are categorized as scheduled waste. Metric Tons (millions) 12 700 600 500 400 300 200 100 0 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 Year Figure 2.2: Scheduled waste generation Malaysia 1994 – 2005 (DOE, 1995; 2003; 2006). A spent material is any material that has been used and as a result of contamination can no longer serve the purpose for which it was produced without processing. Spent material may be recycled for reuse either at the facility or off-site of the generating facility. Spent solvent and spent coolant are some common type of scheduled waste generated by a variety of industries in Malaysia and have great value added after recycled or recovered. Spent or discarded paints from paint product could be recovered and reused for the production of lower quality paints where color control is not required. Nevertheless, used industrial containers including high-density polyethylene (HDPE) drums, intermediate bulk container (IBC), steel drums, tin, carboy and jerry can could be reused after the process of re-conditioned. A lower quality paints produced from spent or discarded paints would be used for re-conditioned industrial containers painting. The types of waste oil normally recovered are spent lubricating oil, hydraulic oil, cutting oil, oily residue from automotive workshop, service station, oil or grease 13 interceptor, etc. Besides, oil could also be recovered from oil and water mixture of ship industries. These types of wastes have potential adverse impact to the environment through indiscriminate handling, storage, usage and disposal activities. Aluminium, solder dross, brass dross and waste from electrical and electronic assemblies’ have a potential for recovery and recycling activities. Figure 2.3 shows types of scheduled wastes that could be recycled or recovered. Due to market need, the recovered dust, slag, dross, ash and waste catalysts containing metal collected from industries are known to be profitable business. According to the above scenario, the proper management of scheduled wastes through an appropriate method of waste identification from sources, transportation, recovery and disposal is absolutely important to prevent environmental pollution. Even though Malaysia through the department of Environment had introduced many programs and planning to improve scheduled waste management scenario but it is still unsatisfied. It is very true in the case of Malaysia which are generated a lot of scheduled waste since 1989 and later facing difficulties in handling waste effectively in the past and current year (Zulkifli et.al. 2008). A B C Figure 2.3: Types of scheduled wastes can be recycled or recovered (A: HDPE containers; B: industrial drums; C: spent paint) 14 Therefore, both planning and design of hazardous waste management systems require accurate prediction of hazardous waste generation and comprehensive identification of waste for recovery and recycling technology. 2.4 Problems Associated with Scheduled Waste The main problem in scheduled waste management is illegal dumping. The illegal disposal of scheduled wastes on the land and in waters creates problems for the environment, for people and their quality of life, as well as for fish and wildlife. Paints, used solvent, motor oil, and other hazardous materials have been carelessly tossed with other household wastes into state forests and state parks. Their contaminants leach into groundwater supplies and in some cases directly into exceptional value streams. The pollution is detrimental to fish, and wildlife suffers when encountering objects like broken glass which are not natural to their environment. Table 2.2 indicates reported incidents of scheduled wastes illegal disposals in Malaysia while and Figure 2.4 shows scheduled wastes illegal disposals. Secondly, scheduled wastes are often in diverse forms, particularly when there is presence of mixed scheduled waste such as solvent mixed with acid or alkaline. Such materials can present difficult handling problems, and pretreatment systems or specific technologies may need to be applied to such materials. In some cases, the development of an appropriate materials handling strategy and pretreatment system can be a more difficult and costly problem than the treatment itself (Department of Environment, Water, Heritage and the Arts, 1997) Thirdly, to fulfill the concept of cleaner production is another challenge that needs knowledge and creative state-of-the-art technology in managing scheduled waste. Cleaner production concept is a method of company-specific environmental protection initiative due to its daily operation. The purposes of cleaner production are to minimize the wastewater and emissions caused by industrial production and maximize product output at the same time (Johan Sohaili, 2009). 15 Table 2.2: Reported incidents of scheduled wastes illegal disposals in Malaysia (The Star, 2003; 2006) Year Location Amount Wastes 1989 1993 Pantai Remis, Perak Bukit Merah, Perak 1995 Pangkor Island, Perak 1995 Penang Island 2001 Ulu Tiram, Johor 1,500 tones of toxic wastes Radioactive wastes Asian Rare Earth Plant Forty-one drums of highly toxic potassium cyanide 28 drums of Trichiorofluoromethan 1,000 tones of metal ashes 2003 Ijok, Selangor 2005 Sungai Gatom, Johor 2005 Sungai Kandis, Klang, Selangor Sungai Klang, Selangor 2006 and Type of Company Unknown Mitsubishi Kasei. Unknown Unknown Foreign-based smelting company Unknown 500 drums of paint sludge and glue 6,000 tones of aluminium Hong Poh Metal dross 15,000 drums of sludge and oil Carbon World Industries 400 tones of aluminium dross Unknown In conjunction with slowing down of the rate of resources usable, and a gradual shift from linear to more circular processes, similar to those found in nature, the eventual goal of clean production is to achieve a 'closed loop' operation in which all excess materials are recycled back into the process. The benefits of cleaner production include decreased waste, the recovery of valuable by-products, improved environmental performance, increased resource productivity, increased efficiency, lower energy consumption, and an overall education in costs. 2.5 Environmental Requirements on Scheduled Waste As stated by the Department of Environment, Malaysia has developed a comprehensive set of legal provisions related to the management of toxic and hazardous wastes. The regulation was based on the cradle to grave principle. A facility which generates, stores, transports, treats or disposes scheduled waste is subject to the following regulations: 16 Figure 2.4: Examples of scheduled wastes illegal disposals will pollute soil in the area (i) Environmental Quality (Scheduled Wastes) Regulations 2005 (Amendment) 2007 (ii) Environmental Quality (Prescribed Conveyance) (Scheduled Wastes) Order 2005 (iii) Environmental Quality (Prescribed Premises) (Scheduled Wastes Treatment and Disposal Facilities) (Amendment) Order 2006 (iv) Environmental Quality (Prescribed Premises) (Scheduled Waste Treatment and Disposal Facilities) (Amendment) Regulations 2006 (v) Customs (Prohibition of Export) Order (Amendment) (No. 2) 1993 (vi) Customs (Prohibition of Import) Order (Amendment) (No. 2) 1993. In relation, some of the guidelines prepared by the Department of Environmental should be referred in correlation with related regulations: (i) Environmental Impact Assessment (EIA) Guidance Document For the Construction of Scheduled Waste Recovery Plant (Off-Site) (ii) Guidelines on the Installation of On-site Incinerator for the Disposal of Scheduled Wastes in Malaysia 17 (iii) Guidance Document for the Preparation of Environmental Impact Assessment (EIA) Report, Establishment of Industries Located within Gazetted and EIA Approved Industrial Sites (iv) Guidelines on Standard and Specification of Recovered Waste Oil in Malaysia (v) Guidelines for the Classification of Used Electrical and Electronic Equipment in Malaysia Specifically, the Environmental Quality (Scheduled Wastes) Regulations 2005 was enacted on 15 August 2005 (see Appendix A), to replace the Environmental Quality (Scheduled Wastes) Regulations 1989. There are 77 types of scheduled wastes listed in the First Schedule which are divided into 5 categories, as stated under these new regulations, namely: (i) SW 1 Metal and metal-bearing wastes (10 types of scheduled wastes SW 101-110 ) (ii) SW 2 Wastes containing principally inorganic constituents which may contain metals and organic materials (7 types of scheduled wastes - SW 201-207 ) (iii) SW 3 Wastes containing principally organic constituents which may contain metals and inorganic materials (27 types of scheduled wastes SW 301-327 ) (iv) SW 4 Wastes which may contain either inorganic or organic constituents (32 types of scheduled wastes - SW 401-432) (iv) SW 5 Other wastes (1 category – SW501) Under the stated regulations, a waste generator may store scheduled wastes generated by him for 180 days or less after its generation provided that the quantity of scheduled wastes accumulated on site shall not exceed 20 metric tones. However, waste generators may apply to the Director General of the Department of Environment in writing to store more than 20 metric tones of scheduled wastes. The containers that are used to store scheduled wastes shall be clearly labeled with the 18 date when the scheduled wastes are first generated and name, address and telephone number of the waste generator. The regulations also stated that land farming, incineration, disposal and offsite facilities for recovery, storage and treatment can only be carried out at prescribed premises licensed by the Department of Environment. However, with the signing of the concession agreement between the Government of Malaysia and Kualiti Alam Sdn. Bhd on 18 December 1995 (15 years concession period), all off-site treatment and disposal (incineration, wastewater treatment, storage and secure landfill) of scheduled wastes is not allowed. On-site incineration of scheduled wastes is not encouraged. If it is deemed necessary, the Environmental Quality (Scheduled Wastes) Regulations 2005 stated that application for the installation of such incinerator must strictly adhere to the Guidelines on the Installation of On-site Incinerator for the Disposal of Scheduled Wastes in Malaysia. The guidelines which is published by the Department of Environment, including carrying out a detailed environmental impact assessment and display of the EIA report for public comments. Other types of facilities such as off site recovery, recycling and treatment need approval or license to operate from the Department of Environment including transportation license and Environmental Impact Assessment approval. In conjunction, waste generators may apply for special management of scheduled wastes to have the scheduled wastes generated from their particular facility or process excluded from being treated, disposed of or recovered in premises or facilities other than at the prescribed premises or on-site treatment or recovery facilities, as stipulated under Regulation 7(1), Environmental Quality (Scheduled Wastes) Regulations 2005. Scheduled waste disposal is regulated by government through Section 34B of the Environmental Quality Act 1974, on which violating of the act shall be liable to a fine not exceeding RM 500,000 or to imprisonment for a period not more than 5 19 years or both together (EQA 1974). Figure 2.5 illustrates an overview of the scheduled waste management in Malaysia. 2.6 The Basel Convention In the late 1980s, a tightening of environmental regulations in industrialized countries led to a dramatic rise in the cost of hazardous waste disposal. Searching for cheaper ways to get rid of the wastes, “toxic traders” began shipping hazardous waste to developing countries and to Eastern Europe. When this activity was revealed, international outrage led to the drafting and adoption of the Basel Convention. The Basel Convention was the only global legal instrument dealing with the sound management of hazardous wastes, their disposal and transboundary movement. It had achieved remarkable success in establishing a ban on the transboundary movement of hazardous wastes from developed to developing countries. During its first Decade (1989-1999), the Convention was principally devoted to setting up a framework for controlling the “transboundary” movements of hazardous wastes from developed to developing countries. During its first Decade (1989-1999), the Convention was principally devoted to setting up a framework for controlling the “transboundary” movements of hazardous wastes, that is, the movement of hazardous wastes across international frontiers. It also developed the criteria for “environmentally sound management”. A Control System, based on prior written notification, was also put into place. Malaysia has signed up for Basel Convention on the 8th October 1993. The fourth meeting of the Conference of the Parties to the Basel Convention on the Control of Transboundary Movements of Hazardous Wastes and their Disposal was opened in Kuching on 23 February 1998. The President of the third meeting of the Conference of the Parties, Mr. Bakary Kante from Senegal officiated the meeting 20 (Report Of The Fourth Meeting Of The Conference Of The Parties To The Basel Convention, 1998) During Basel Convention 2002, it was reported that Malaysia and other signatory countries restricts the export of hazardous wastes and other wastes for final disposal and restricts the import of hazardous wastes and other wastes for recovery as well. The Malaysian Government through the funding agencies provided special capital allowance incentive to companies which generate wastes and intend to set up facilities to treat their own wastes covering all capital expenditure incurred. The Government also encourages industries to use locally produced wastes as raw materials (Malaysia Country Fact Sheet, 2006). Section 34b, Act 127 (500K/5 yrs/Both) Section 34b, Act 127 (500K/5 yrs/Both) Section 34b, Act 127 Generator Waste (500K/5 yrs/Both) EIA Order, 1987 Waste Transporter Prescribed Clean Air Regn., Sewage Conveyance, 2005. & Industrial Reg., Written Approval, Scheduled Waste Reg. Section 19, Act 127 Prescribed Premises EIA Order, Activity 18 Witten Approval, Section 19 2005, Dioxin & Furan Act 127 2004 License, Section 18 License, Section 18, Act 127 Figure 2.5: Overview of the scheduled waste management in Malaysia (Johan Sohaili, 2009) 21 As noted by Secretariat of the Basel Convention on March 2009, currently there are 172 Convention Parties and their fundamental aims are: (i) Control and reduction of the transboundary movement of hazardous and other wastes subject to the Convention 2.7 (ii) The prevention and minimization of their generation (iii) The environmentally sound management of such wastes (v) The active promotion of the transfer and use of cleaner technologies Conclusion Scheduled waste is a hazardous substance that needs proper management and appropriate method of disposal. Many authorities agree that 3 R’s are the most immediate and effective way of managing waste. However, problems related to scheduled waste management is not only illegal dumping, but also handling and pretreatment systems for diverse forms of scheduled waste as well as to incorporate the concept of cleaner production which means a gradual shift from linear to more circular processes. As scheduled waste has a great potential to be recycled or recovered, the Department of Environment Malaysia has developed a comprehensive set of legal provisions related to the management of toxic and hazardous wastes which based on the cradle to grave principle. The enthusiastic effort is to realizing the meaning of waste become raw material, waste become product and toxic waste become non-toxic. CHAPTER 3 RESEARCH METHODOLOGY 3.1 Informations Gathering The approach of the present research includes a literature review and making comparison and evaluation on the recovery and recycling processes done by the scheduled waste recyclers in Malaysia Informations were collected from the Department of Environment at Johor Bahru, Putrajaya and Ipoh. Informations gathered for the study are; (i) Type of scheduled waste that can be recovered or recycled (ii) The recovery and recycling processes technology of scheduled waste which is currently practiced (iii). The Waste Acceptance Criteria and Material Balance calculation for the recovery or recycling processes Site visit to few scheduled waste recovery factories was conducted in 2009. The purpose of the visit was to observe scheduled wastes recovery and recycling processes done in the premise. A common process for recovery and recycling selected scheduled waste has been developed for the study. The selected scheduled wastes are: (i) Dust, slag, dross or ash 23 3.2 (ii) Waste catalyst (iii) Waste oil (iv) Waste coolant (v) Waste solvent (vi) Used industrial containers (vii) Used rags and filters List of Data Collected Through reviewing the literature and personnel interview, it was found out that 41 types of scheduled wastes listed in the Environmental Quality (Scheduled Wastes) Regulations, 2005, First Schedule are found being recovered or recycled as listed in Table 3.1. Table 3.1: 41 Types of scheduled wastes listed in the Environmental Quality (Scheduled Wastes) Regulations, 2005First Schedule are found being recovered or recycled Code Type of waste SW102 SW104 Waste of lead acid batteries in whole or crushed form Dust, slag, dross or ash containing aluminium, arsenic, mercury, lead, cadmium, chromium, nickel, copper, vanadium, beryllium, antimony, tellurium, thallium or selenium excluding slag from iron and steel factory Slags from copper processing for further processing or refining containing arsenic, lead or cadmium Leaching residues from zinc processing in dust and sludges form Waste from electrical and electronic assemblies containing components such as accumulators, mercury-switches, glass from cathode-ray tubes and other activated glass or polychlorinated biphenyl-capacitors, or contaminated with cadmium, mercury, lead, nickel, chromium, copper, lithium, silver, manganese or polychlorinated biphenyl Waste catalysts Sludges containing one or several metals including chromium, copper, nickel, zinc, lead, cadmium, aluminium, tin, vanadium and beryllium Spent inorganic acids SW107 SW108 SW110 SW202 SW204 SW206 No. of Recyclers 4 18 1 5 4 6 4 5 24 Table 3.1: 41 Types of scheduled wastes listed in the Environmental Quality (Scheduled Wastes) Regulations, 2005First Schedule are found being recovered or recycled (continue) Code Type of waste SW 301 Spent organic acids with pH less or equal to 2 which are corrosive or hazardous Spent lubricating oil Spent hydraulic oil Spent mineral oil-water emulsion Oil tanker sludges Oil-water mixture such as ballast water Sludge from mineral oil storage tank Waste oil or oily sludge Oily residue from automotive workshop, service station, oil or grease interceptor Oil contaminated earth from refining of used lubricating oil Oil or sludge from oil refinery plant maintenance operation Tar or tarry residues from oil refinery or petrochemical plant Waste of non-halogenated organic solvents Waste of halogenated organic solvents Waste of halogenated or un-halogenated non-aqueous evaporation residues arising from organic solvents recovery process Uncured resin waste containing organic solvents or heavy metals including epoxy resin and phenolic resin Waste of thermal fluids (heat transfer) such as ethylene glycol Spent alkaline waste containing heavy metals Spent alkalis with pH more or equal to 11.5 which are corrosive or hazardous Disposed containers, bags or equipment contaminated with chemicals, pesticides, mineral oil or scheduled wastes Rags, plastics, papers or filters contaminated with scheduled wastes Spent activated carbon excluding carbon from the treatment of potable water and processes of the food industry and vitamin production Sludges containing cyanide Spent salt containing cyanide Spent aqueous alkaline solution containing cyanide Spent quenching oils containing cyanides Sludges of inks, paints, pigments, lacquer, dye or varnish Waste of inks, paints, pigments, lacquer, dye or varnish Discarded or off-specification inks, paints, pigments, lacquer, dye or varnish products containing organic solvent A mixture of scheduled wastes A mixture of scheduled and non-scheduled waste Spent processing solution, discarded photographic chemicals or discarded photographic wastes Chemicals that are discarded or off-specification SW 305 SW 306 SW 307 SW 308 SW 309 SW 310 SW 311 SW 312 SW 313 SW 314 SW 315 SW 322 SW 323 SW 324 SW325 SW 327 SW401 SW402 SW409 SW410 SW411 SW412 SW413 SW 414 SW415 SW 416 SW 417 SW 418 SW421 SW 422 SW 423 SW 429 No. of Recyclers 2 10 9 9 6 5 4 7 7 1 2 1 9 7 2 4 1 2 1 7 10 2 2 4 3 5 5 1 3 2 1 25 In an effort of reducing the volumes of scheduled wastes generated for disposal, it was found out that more than 80% of valuable resources from scheduled waste can be recovered accept 30% for SW202 Waste Catalyst as listed in Table 3.2. Table 3.2: Recovery Percentage for 16 Types of Scheduled Wastes Code Type of waste Recovery % SW104 Dust, slag, dross or ash containing aluminium, arsenic, mercury, lead, cadmium, chromium, nickel, copper, vanadium, beryllium, antimony, tellurium, thallium or selenium excluding slag from iron and steel factory Waste catalysts Spent lubricating oil Spent hydraulic oil Spent mineral oil-water emulsion Oil tanker sludges Oil-water mixture such as ballast water Sludge from mineral oil storage tank Waste oil or oily sludge Oily residue from automotive workshop, service station, oil or grease interceptor Oil or sludge from oil refinery plant maintenance operation Tar or tarry residues from oil refinery or petrochemical plant 99.90 SW202 SW 305 SW 306 SW 307 SW 308 SW 309 SW 310 SW 311 SW 312 SW 314 SW 315 SW 322 SW 323 SW409 SW410 Waste of non-halogenated organic solvents Waste of halogenated organic solvents Disposed containers, bags or equipment contaminated with chemicals, pesticides, mineral oil or scheduled wastes Rags, plastics, papers or filters contaminated with scheduled wastes 30.00 95 - 97 95 - 97 80.00 95 - 97 95 - 97 95 - 97 95 - 97 95 - 97 95 - 97 95 - 97 82.00 82.00 100.00 90.00 CHAPTER 4 RECYCLING AND RECOVERY PROCESSES 4.1 Introduction In the Environmental Quality (Scheduled Wastes) Regulations 2005, scheduled wastes are categorized based on type of waste rather than the source or origin of the wastes. Generally, scheduled waste is generated by industrial activities such as electronics manufacturer (Printing Circuit Board, Integrated Circuit and parts), paint industry, ink industry, printing companies, adhesive industries, mechanical workshop and factories using rags to wipe paint and ink products. Aware of the need to set up a proper scheduled waste treatment and disposal facility in the country, the Malaysian government has promoted the establishment of environmentally sound treatment, recovery and disposal facilities. In relation, such facilities are required to support the enforcement of legal provisions on scheduled waste (DOE, 2006). By having such facilities, industries in Malaysia are able to dispose scheduled waste in an orderly, regulated manner to avoid costly movements to other countries, and even more importantly, to avoid unnecessary risk to public health and the environment during its transport. Currently, there are two such facilities have been licensed for treatment and disposal of scheduled wastes, one in Negeri Sembilan and the other in Sarawak. As for the study, a common process for recovery and recycling of selected scheduled waste has been developed and the residual sludge will be disposed at the prescribed premise such as Kualiti Alam Sdn Bhd. 27 4.2 Dust, Slag, Dross or Ash Recovery Scheduled waste categorized under group SW 104 are dust, slag, dross or ash containing aluminium, arsenic, mercury, lead, cadmium, chromium, nickel, copper, vanadium, beryllium, antimony, tellurium, thallium or selenium. 4.2.1 General Elements of Dust, Slag, Dross or Ash Dust produced in metal industry can be recovered to extract metal and become raw material for new products production. Hence, the role of recovery in metal industry is a critical component both from its contribution to the environment and favourable economic impact on production. Durinck, et.al, (2008) stated that slags are an indispensable tool for the pyrometallurgical industry to extract and purify metals. Slag represents undesired impurities in the metals being smelted, which float to the top during the smelting process. While metals start to oxidize as they are smelted, slag forms a protective crust of oxides on the top of the metal and protects the liquid metal underneath. When the metal is smelted to satisfaction, the slag is skimmed from the top and disposed of in a slag heap to age. Aging slag is an important part of the process, as it needs to be exposed to the weather and allowed to break down slightly before it can be used. As a by product of metal smelting, hundreds of tons of slags are produced every year all over the world in the process of refining metals and making alloys. In appearance, slag looks like a loose collection of aggregate, with lumps of varying sizes. Slag actually has many uses such as in concrete, aggregate road materials, as ballast, and is sometimes used as a component of phosphate fertilizer; hence slags are rarely goes to waste. According to the Oxford Advanced Learner’s Dictionary, (1983), dross is a waste material rising to the surface of melted metals. It appears usually on the 28 melting of low melting point of metals or alloys such as tin, lead, zinc or aluminium, or by oxidation of the metals. Due to impurities such as metal oxides, dross is also refers to the lead oxides, copper, antimony, and other elements that float to the top of the molten lead. It can easily be skimmed off the surface before pouring the metal into a mold or casting flask into ingot. 4.2.2 Statement of Need Based on the study, solder dross and aluminium dross are the most metal and metal-bearing wastes being recycled and recovered in Malaysia. Due to the second source of supply for raw materials, scraps are also an important indicator for the sustainability of alloy and aluminium. As cited by Ahmad Fariz et.al., (2008) metal engineering includes solder and aluminium dross recycling and recovery is the third types of industrial scheduled wastes recovered by the recyclers.in Malaysia. Dross product is not entirely waste material; aluminum dross, for example, is used in secondary steelmaking for slag deoxidation, reducing processing costs by minimizing use of pure aluminum. Dross recycling is very attractive from both the energy and the economic standpoints. Solder dross alloy composition normally containing tin, silver and copper, or antimony or bismuth with the ratio either tin (96.3%) : silver (3.2%) : copper (0.5%), or tin (96.5%) : silver (3.5%), or tin (90%) : bismuth (5%) : silver (5%), or tin (95%) : antimony (5%) (DOE, 2008). 4.2.3 Waste Acceptance Criteria for Solder and Aluminium Dross The sources of wastes are mainly from the metal manufacturing industries. Raw material must meet the acceptance criteria prior recycling and recovery as categorized in Table 4.1. 29 Table 4.1: Solder and aluminium dross waste acceptance criteria (DOE, 2008). Wastes materials Solder dross Aluminium dross Waste Acceptance Criteria1 15% solder alloy in solder dross Dross containing at least 1% of aluminium metal from aluminium based industries 4.2.4 Recovery Process Description The incoming raw material collected must confirm to waste acceptance criteria before recovery processes. and will be sorted before being transferred into the furnace batch by batch for smelting process. During the smelting cycle, a temperature of 800°C is maintained in the furnace by controlling the amount of diesel fuel burnt in the furnace (DOE, 2008). During the smelting process, the dross is formed and need to be collected and stored for further smelting process, as these residue contain metal oxide which can be recovered. Molten dross will then undergo refining process where non-purified brass will be re-introduced into the smelting cycle repeatedly until the desired dross composition is achieved. Purified molten dross will then be casted into ingots and lastly being packaged for commercial use. The by-products of the recovery cycle will be slag, dust and fume (DOE, 2008). Slag containing high amount of impurities which are no longer usable will be collected and sent to Kualiti Alam for safe disposal. Dust and fume generated during the smelting process will then be collected by a series of cyclone dust filtered and only clean air will be permitted to be released into the atmosphere. The collected dust will also be sent to Kualiti Alam for safe disposal. The collected residue from the furnace that contained different types of waste may be classified as scheduled wastes under the Environmental Quality (Scheduled Wastes) Regulations, 2005, and require proper disposal. Figure 4.1, Figure 4.2 and 30 Figure 4.3 show ingots, furnace, and dross respectively while the process flow diagram for solder dross recovery is shown in Figure 4.4. Figure 4.1: Ingot produced after smelting Figure 4.2: Aluminium melting rotary furnace Figure 4.3: Aluminium dross 31 RAW MATERIAL No WASTE ACCEPTANCE CRITERIA Yes STORE Fuel SORTING Clean air SMELTING / FURNACE at 8000C DUST COLLECTION (100%) DROSS (0.098%) REFINING CASTING SLAG DUST (0.001 %) (0.001 %) Dispose at Kualiti Alam PACKAGING METAL INGOTS (99.9 %) Figure 4.4: Typical process flow diagram and material balance for solder and aluminium dross recovery 32 4.2.5 Material Balance Table 4.2 and Figure 4.4 represent the estimated value of material balance across the maximum solder and aluminium dross recovery production process. Depends on the plant capacity, from 100% of raw material collected, about 0.001% will be the slag containing high amount of impurities which are no longer usable, 0.001% residue and 0.098% dross containing metal oxide which can be recovered. Throughout the recovery process, it is estimated to recover about 99.9% of metal ingots if the plant is operated at its maximum capacity. Table 4.2: Material balance for solder and aluminium dross recovery Raw Material 100% 4.3 Metal Ingot 99.9 % Recovered Dross 0.098 % Slag 0.001 % Residue 0.001% Waste Catalyst Recovery Scheduled waste categorized under group SW 202 in the Environmental Quality (Scheduled Wastes) Regulations 2005 First Schedule is waste catalysts. 4.3.1 General Elements of Waste Catalyst As defined in the Oxford Advanced Learner’s Dictionary (1983), catalyst is a substance that speeding up a chemical process. Hence, the production of many chemicals involves catalysis. The influence on the reaction rate depends on the frequency of contact of the reactants in the rate-determining step. In general, catalysts increase the reaction rate and lower the activation energy by providing an alternative reaction pathway to the reaction product. For this the catalysts react with one or more reactants to form intermediates that subsequently give the final product. 33 Mori and McElroy (1996) have written that numerous metals are utilized as catalysts. Major catalyst deactivation metals are nickel, vanadium, iron and arsenic, whereas catalyst used in synthetic fuels have been identified as cobalt, molybdenum, iron, nickel, chromium, and tungsten. 4.3.2 Statement of Need Typical type of waste recovered under waste catalyst in Malaysia include used rags contaminated with silver, expired silver epoxy conductor, silver sludge, palladium in spent solution or in resin and gold in spent cyanide solution or in deposited activated carbon and ceramic plated with precious metals.. The sources of wastes are mainly from electronic industries (DOE, 2008) Regardless of how catalysts are used, or whether they take the form of monolithic structures, pellets, beads, extradates or solution, most companies especially in the electronic and chemical process industries depend on precious metals refiners to recover the valuable metals from their spent catalysts (Robert, 2005) In economic point of view, waste catalyst recovery is not only profit making business, but reinventing the use of materials is pollution abatement technology, as electrical and electronics industries is the first types of industrial scheduled wastes recovered by the recyclers .in Malaysia (Ahmad Fariz et.al., 2008). Moreover, these catalysts contain environmentally critical and economically valuable metals such as gold, silver and palladium. 4.3.3 Waste Catalyst Acceptance Criteria Prior to recovery process, samples of the waste materials are analyzed in order to identify the percentage of precious metals and also other heavy metals that 34 are present in the wastes. This is important for the determination of the waste composition and quantity of chemicals to be added in the reaction process. The sources of wastes are mainly from the metal manufacturing and electrolysis industries. Raw material must meet the acceptance criteria prior recycling and recovery as categorized in Table 4.3. Table 4.3: Waste catalyst acceptance criteria (DOE, 2008) Wastes materials Waste catalyst Waste Acceptance Criteria 0.05% gold for waste containing gold, or 2.5% silver for waste containing silver, or 0.005% palladium for waste containing palladium 4.3.4 Process Description for Gold Recovery from Waste Catalyst There will be two processes involved in the gold recovery, namely direct ion exchange and acid treatment. The ion exchange process is designed to recover gold in spent solution while the latter is for recovery of gold entrapped in the deposited activated carbon (DOE, 2008). The direct ion exchange gold recovery is a simple process with the use of synthetic resins (equation 4.1). The waste catalyst containing gold will be directly pumped into the resin column to undergo ion exchange process. The gold will be "exchanged" and retained on the resin. The spent solution from the resin column will be directed to waste treatment plant for further treatment. Au+ + R- -> AuR (4.1) The regeneration of the resin by the use of hydrochloride acid is the next step to precipitate the gold from the resin and dissolved it into aqueous gold monochloride (equation 4.2) AuR + 2HCI -> AuCl + HR (4.2) 35 The aqueous gold is then reduced into the metal form by addition of hydrazine in the drum. Gold ingots are obtained after further refining in the furnace. (equation 4.3) The process flow diagram of ion-exchange gold recovery process is shown in Figure 4.5. 2AuCl + 2N2H4 -> 2Au + 2NH4Cl + N2 (4.3) Diluted nitric and hydrochloride acids will be added into the spent waste catalyst solution in the case of recovery gold using acid treatment method (equation 4.4). The mixing process uses a stirrer. Gold monochloride in aqueous form will be produced after solution is left to stand for a day. Au+ + Cl- -> AuCl (4.4) Before proceeding to the reduction process, the solution will be filtered using fine nylon or steel mesh (depending on the nature of waste) to remove all the nonmetallic impurities, for instances, unburned carbon. The filtration is carried out by transferring the solution into another drum fitted with mesh. After soaking for a few hours, hydrazine will be added to reduce the aqueous gold into metal form followed by the addition of polymer. The end product of gold ingot is obtained after refining in the furnace (equation 4.5). The process flow diagram of acid treatment gold recovery process from deposited carbon is shown in Figure 4.6. 2AuCl + 2N2H4 -> 2Au + 2NH4Cl + N2 (4.5) 4.3.5 Process Description for Silver Recovery from Waste Catalyst Silver recovery process is specifically designed for the waste materials that contain silver. There are two types of waste that are subjected to this recovery 36 RAW MATERIAL No WASTE ACCEPTANCE CRITERIA Yes Resin SPENT SOLUTION OF GOLD (100%) FILL INTO COLUMN HCl regenerant GOLD AQUEOUS WASHING WITH N2H4 GOLD IN SEMISOLID FORM Wastewater treatment plant (70%) REFINING CASTING PACKAGING METAL INGOTS (30 %) Figure 4.5: Typical gold recovery process flow and material balance by ion exchange 37 process, namely ashes from rags contaminated with silver and silver sludge (DOE, 2008). Waste material is transferred into the drum and diluted with nitric acid using a hand pump. The acid acts to dissolve the silver and to form silver nitrate. Nonmetallic impurities such as epoxy and ceramic are separated from the aqueous silver solution by manually transferring the mixture into another drum with pump and filter mesh. The impurities will be sprayed with water to wash out any residual silver from the impurities. The resulting non-metallic impurities are non-toxic materials and will be discarded as normal solid waste. The chemical reaction between silver and nitric acid is shown in equation (4.6). Ag+ + HN03 -> AgN03 + H+ (4.6) The silver nitrate solution will be added with sodium chloride aided with polymer to obtain aqueous silver chloride. Mixing is achieved using a stirrer. Assisted with agitation, the sediment layer containing silver chloride will be mixed with hydrazine and water to precipitate out the silver. Silver in semi-solid form will be transferred to the furnace for refining. The upper layer that contains spent acids will be pumped to the wastewater treatment plant for treatment. The process flow diagram of silver recovery from wastes is shown in Figure 4.7. The chemical reactions are as in equation (4.7) and (4.8). AgN03 + NaCI -> AgCl + NaNO3 (4.7) AgCl + N2H -> Ag + NH4Cl + N2 (4.8) 4.3.6 Process Description for Palladium Recovery from Waste Catalyst The palladium recovery process is an ion-exchange process to recover both palladium from waste spent solution and resins. The waste is pumped to the resin column to undergo ion exchange to retain palladium on the resin. The spent solution after resin treatment will be directed to the wastewater treatment plant. 38 RAW MATERIAL No WASTE ACCEPTANCE CRITERIA HNO3 H2O Yes SPENT SOLUTION OF GOLD (100%) GOLD NITRATE AQUEOUS SPRAY WATER FILTER Polymer NON METALLIC OF IMPURITIES OF GOLD NITRATE AQUEOUS GOLD IN SEMISOLID FORM REFINING Wastewater treatment plant (70%) CASTING PACKAGING METAL INGOTS (30 %) Figure 4.6: Typical gold recovery process flow and material balance by acid treatment 39 RAW MATERIAL No WASTE ACCEPTANCE CRITERIA HNO3 H2O Yes SILVER ASH / SLUDGE (100%) SILVER NITRATE AQUEOUS SPRAY WATER FILTER NACL Polymer NON METALLIC OF IMPURITIES OF SILVER NITRATE AQUEOUS SILVER CHLORIDE AQUEOUS Wastewater treatment plant (70%) SILVER IN SEMISOLID FORM REFINING CASTING PACKAGING METAL INGOTS (30 %) Figure 4.7: Typical silver recovery process flow and material balance by acid treatment 40 The regeneration of resin by the use of ammonium solution is the next step to release palladium from the resin and dissolved it into aqueous palladium. The reactions taking place are as in equation (4.9) and (4.10). Pd2+ + R2- -> PdR (4.9) PdR + 2NH4+ -> Pd2+ + (NH4)2R (4.10) The aqueous palladium is then reduced to its solid form by the addition of hydrazine in the drum as in equation (4.11). The palladium end product is cast into ingots in the furnace. The process flow diagram of the palladium recovery from wastes is shown in Figure 4.8. 2Pd2+ + 2N2H4 -> 2Pd + 2NH4+ + N2 (4.11) 4.3.7 Material Balance Table 4.4, Figure 4.6, Figure 4.7 and Figure 4.8 represent the estimated value of material balance across the maximum waste catalyst recovery production process. Depends on the plant capacity, from 100% of raw material collected, about 30% will be the metal ingots. Throughout the recovery process, it is estimated to produce about 70% will be the wastewater which need proper treatment if the plant is operated at its maximum capacity. Table 4.4: Material balance for waste catalyst recovery Raw Material Metal Ingot (gold, siver and palladium) Wastewater 100% 30 % 70% 41 RAW MATERIAL No WASTE ACCEPTANCE CRITERIA Yes NH+ regenerant PALLADIUM IN RESIN / SPENT SOLUTION (100%) FILL INTO COLUMN PALLADIUM SOLUTION N2H4 WASHING Wastewater treatment plant (70%) PALLADIUM IN SEMI-SOLID FORM REFINING CASTING PACKAGING METAL INGOTS (30 %) Figure 4.8: Typical palladium recovery process flow and material balance 42 4.4 Waste Oil Recovery There are nine types of scheduled waste containing oil listed in the Environmental Quality (Scheduled Wastes) Regulations 2005 First Schedule have a common recovery process 4.4.1 General Elements of Waste Oil Waste oils are petroleum or synthetic oils that have been previously used for lubricating, heating, corrosion protecting or other purposes and no longer meet the requirements of these applications due to the loss of original properties and presence of contaminants or impurities. Wherever possible, every effort should be made to encourage the resource recovery such as re-refining, re-conditioning and reprocessing of used oils, particularly since virgin petroleum oil is a non-renewable fossil fuel resource that is in high global demand. Almost all of the manufacturing activities use oil products such as lubricating oil, heat transfer oil, fuel, hydraulic oil, gear oils used in cars or bikes, etc. The used oil can pollute the environment if it is not disposed of properly despite it has high energy value and can be used as fuel for a lot of industries. Waste oil poured directly onto the ground or into storm drains, or tossed into trash cans even in a sealed container can contaminate and pollute the soil and all water bodies such as groundwater, rivers and streams. Oil and associated contaminants floating on the groundwater beneath the site are a continuing source of water bodies’ contamination either ground or surface water. Removing the oil will keep the floating contamination from moving off the site and will reduce the chances of water pollution that the public will be exposed. This action will accelerate the overall site cleanup by removing a known source of ongoing groundwater contamination; however, it does not constitute the complete and final cleanup plan for the site.There are some general facts about used oils as revealed by Vander Pol, (2006): 43 (i) one litre of used oils may contaminate up to 1 million litres of freshwater – enough to supply 50 people with drinking water for 1 year (ii) used oil concentrations of 50 - 100 ppm can disrupt sewage treatment processes (iii) one barrel (42 gallons) of crude oil is needed to manufacture 2½ quarts of lubricating oil, but only 1 gallon of recycled oil is needed to manufacture an equal amount of re-refined lubricating oil (iv) two gallons of recycled oil can generate enough electricity to run the average household for almost 24 hours There is a promising market for Refined Fuel Oil (RFO) both locally and internationally. In Malaysia, the demand for recycled oil is continuing to escalate as the oil production is expected to reduce 3.98% between 2008 and 2018 and oil consumption is set to increase by 16.45% as reported in The Malaysian Oil Report (2009). 4.4.2 Statement of Need The types of waste oil normally recovered are spent lubricating oil, hydraulic oil, cutting oil, oily residue from automotive workshop, service station, oil or grease interceptor, etc. There are some potential land-based and water-based sources of used oils generated for recovery as listed in Table 4.5. 4.4.3 Waste Acceptability Criteria for Waste Oil Recovery Used oil is hazardous as it can contain such contaminants as lead, magnesium, copper, zinc, chromium, arsenic and chlorinated compounds (US Department of Energy, 1987). The processes within the plant will only be able to 44 accept oily wastes that meet or fall within a certain acceptable range to ensure compatibility with the waste processing systems employed. In this regard, all waste samples must first be analyzed at an accredited laboratory prior to commencement of collection from waste generators. Waste collected must meet the acceptance criteria prior recovery as categorized in Table 4.6. Once the samples have been analyzed and found to meet the required criteria, the waste will be transported to the recovery facility for storage and further treatment. Table 4.5: Potential land-based and water-based sources of used oils recovery (VanderPol, 2006) Type of Sources Land-based Sources Type of Waste Oil Sources of Waste Oil Vehicles and Machinery: cars, trucks and motorcycles; heavy trucks and buses; small engine equipment i.e. lawn mowers vehicle repair and servicing stations; automotive dealerships airports and railways; hotel and tourism trade; fishery and farming operations; telecommunications; refrigeration and air conditioning repair shops electricity generating; plants and transformer; sub-stations, oil refineries and processors; construction and general trades; mining and metal operations ports and terminals floating barges; marinas, harbors, anchorages and boatyards oil tanker and cargo vessels; cruise ships commercial fishing vessels; recreational watercraft Commercial Operators: Industrial Operations: Water-based Sources Port Reception Facilities: Ships an Small Watercraft: 4.4.4 Waste Oil Recovery Process Description The classical and most feasible solution to the waste oil recovery is distillation, evaporation or pyrolysis (DOE, 2008). Most of the commonly waste oil has boiling points no higher than 200oC. Hence the oil can be separated from the 45 Table 4.6: Waste oil acceptance criteria (DOE, 2007, 2008) Waste Materials Waste Category Gasoline or diesel engine oil Industrial gear oil or car differential oil Power steering oil Manual or automatic transmission oil Circulating oil or turbine oil Refrigeration system oil Mineral oil, polyalphaolefin (PAO), or diester based compressor oil Heat transfer oil Electrical insulating oils (e.g. transformer dielectric oils) Hydraulic or trans-hydraulic system oil Marine engine oil Oily tank washings (slops) Oily solids (sludges) Oily ballast water (from oil tankers) oily bilge water mixed oily liquids Machine tool oil Two-stroke engine oil Drilling oil Pneumatic system oil Chain oil (industrial or power chain saw) Conveyor lubricating oil SW 305- Spent lubricating oil SW 306- Spent hydraulic oil SW 308- Oil tanker sludges SW 309 – Oil-water mixture such as ballast water SW 310- Sludge from mineral oil storage tank SW 311- Waste oil or oily sludge SW 312- Oily residue from automotive workshop, service station, oil or grease interceptor SW 314 – Oil or sludge from oil refinery or petrochemical plant SW 315 – Tar or tarry residues from oil refinery or petrochemical plant Waste Acceptance Criteria Physical properties : liquid Color: Light yellow to dark brown Specific gravity: 0.5 – 1.0 Viscosity: < 80 cst Moisture content: < 30% Heavy metal: < 100 ppm Total halogen: < 1000 ppm Boiling point: 100 – 200 0 C Flash point: 75 – 88 0C Recovered: 80% – 88% dissolved substances which normally have much higher boiling point by distillation. The process requires minimal manual operation and the process is done is batches. There is no chemical reaction involves but physical separation. The process is selected due to the operational stability and easiness of maintenance of the system. As oil is inflammable which pose fire hazard to the surrounding, close monitoring and proper safety procedures are necessary to ensure safety. The waste oil will normally undergo two stages of the process i.e. separation and recovery process. During separation process, the waste oil collected need to undergo physical separation process for large suspended solid removal before 46 transferred for the recovery process. Waste oil which contain water but immiscible with water will be pumped to a decanter where the water separated will be discarded as scheduled waste (DOE, 2008). Waste oil from waste generators will be stored temporarily in an overhead collection tank with minimum height of 3 meters (DOE, 2007). The oil will flow by gravity from the overhead tank to a primary screener or Desorber to separate oil and water or liquid without using electricity or filters. The CPI (Corrugated Plate Interceptor) in the Desorber is used to remove heavier oil, grease, settable solids and floating light oil. At this stage the feed is still contaminated with water, fine particles and dissolved solids. The solid matter shall be screened or separated out and collected in a waste container. Estimated 2% of solid wastes or impurities is collected from the primary screening process and shall be stored and handle as a schedule waste prior disposed of at Kualiti Alam Sdn Bhd. (DOE, 2008) The outflow from the desorber will be enter the oil water separator tank where water or moisture will be stripped and the water by virtue of density difference settles down at the bottom of tank while the oil is removed from the unit via the outlet located at the top of the equipment. Water accumulated at the bottom of the tank is periodically removed through the opening of the water drain at the bottom. Pneumatic pump will be used to transfer oils from one container to another. Since the pump is driven by high pressure air from air compressor, it is spark and explosive proof. All containers will be covered during transferring process to minimize fugitive vapor. The water will be directed to the oil interceptor before being disposed to nearby wastewater treatment plant. The captured oil will then be directed back to the collection tank for reprocessing. The sludge will be extracted out to be dried, thickened and disposed. The oil is then being directed through a couple of stainless steel wire mesh bag filters to eliminate unwanted suspended solids with the help of a pressure pump. The stainless steel wire cloth bag filters remove any type of suspended solids ranging from 2 to 50 micron and the filter media is washable for reuse. 47 The waste oil recovery process could be carried out through distillation, evaporation or pyrolysis method for recovery process. The detail of the process are as the following: (a) Distillation As for distillation method, the clean oil is fed into the vacuum dehydration system to remove access water (below 50% of oil saturation point), dissolved gasses and cracked oil (DOE, 2008) Then the oil would be to channel the outflow from the dehydration system to the membrane separator where the oil will pass through an electric field to remove oxidation products where positively charged particles are drawn to the negative pole and vice versa. The schematic flow diagram is given in Figure 4.9. (b) Evaporation Another alternative for waste oil recovery is through evaporation. Evaporation involves the utilization of thermal oil heater to supply the desired heat during the vaporation process. (DOE, 2008). The ultimate of this method is to ensure that water contain in the waste oil will be remove through evaporation, while the solids is settle at the bottom of distiller, prior removed and stored in the drum for disposal at Kualiti Alam Sdn Bhd. The vacuum evaporator evaporates unwanted vapor in oil. To purify the oil, the metal jacket will be heated at 140oC below atmospheric pressure to eliminate water vapor in the oil with the application of venture vacuum pump. The heated vaporous will then be condensed into droplets when passing through a condenser. The condensed water will then be passed through the oil interceptor before being discharged. The purified oil will then be channeled and stored into the product tank for further use or sell. The typical flow of the evaporation process is shown in Figure 4.10. 48 WASTE OIL No WASTE ACCEPTANCE CRITERIA Yes COLLECTION TANK (100%) DESORBER OIL WATER SEPARATOR SS BAG FILTERS SLUDGE OUT (3%) DISTILLATION SYSTEM OIL INTERCEPTOR MEMBRANE SEPARATION Dispose at Kualiti Alam RECOVERD OIL ( 97%) Wastewater treatment plant Figure 4.9: Typical process flow and material balance across the oil recovery distillation process 49 WASTE OIL No WASTE ACCEPTANCE CRITERIA Yes THERMAL OIL HEATER (100%) CONDENSER SLUDGE OUT (5%) OIL INTERCEPTOR Wastewater treatment plant Dispose at Kualiti Alam RECOVERED OIL (95%) Figure 4.10: The typical flow and material balance of the evaporation process 50 (c) Pyrolysis Pyrolysis is another alternative method for waste oil recovery. The waste oil collected need to undergo physical separation process, before transferring to the pyrolysis process. Pyrolysis will involve heating process where the water content will be removed from waste oil by heating up the oil at 400 - 600oC in an oxygen-free atmosphere. At such high temperature, most organic substances are decomposed by thermal cracking into gaseous, liquid, and solid (DOE, 2008). Pyrolysis is the term used to describe the process of this conversion. The term destructive distillation is often used as an alternative term for pyrolysis. Waste oil containing recoverable oil will be injected into the pyrolysis reactor at atmospheric condition, which later will be heated up to 600°C. During the pyrolysis process, about 97% of oil, gas and water vapour will be recovered. All substances will be directed into a cyclone separator to completely separate liquids from solids. The volatile gases will pass through condensers which most of the organic contents will be condensed into liquid phase as light oils. The uncondensed gases will then be recycled as fuel to heat up the pyrolysis reactor. The final product of waste oil pyrolysis process contains high energy value, acts as replacement for fuel oils or diesel which can be used as burner fuels for boilers, generators and other energy requirement applications. The typical flow of waste oil pyrolysis recovery process is given in Figure 4.1, while Figure 4.12 is the schematic diagram of pyrolysis system. Any residual released gas which is estimated 2% will be trap by the wet scrubber. It is estimated that 1% of the end product of pyrolysis will be tar (sludge) and char (coke) a solid material with a density between 150kg/m3 and 300 kg/m3 derived after the pyrolysis process (DOE, 2008). Char is the remaining end product which could be used for the plant operation or sold as fuel. Sludge produced, need to be proper disposed at Kualiti Alam Sdn Bhd. 51 WASTE OIL No WASTE ACCEPTANCE CRITERIA Yes HEATER at 400 – 6000C (100%) Air scrubber (2%) PYROLYSIS REACTOR (98%) CONDENSER SLUDGE OUT (1%) Dispose at Kualiti Alam OIL INTERCEPTOR Wastewater treatment plant RECOVERED OIL (97%) Figure 4.11: The typical flow and material balance of waste oil pyrolysis recovery process 52 WET SCRUBBER Wastewater Treatment Plant Gas to purification (gas release to scrubber) PYROLISIS REACTOR WASTE OIL CONDENSING TOWER Heat Exchang HEATING UNIT Char (Coke) Heavy Oil Light Oil Pyrolysis gas to Heating Unit Figure 4.12: Schematic diagram of pyrolysis system 4.4.5 Material Balance Figure 4.9, Figure 4.10, Figure 4.11 and Table 4.7, represent the material balance across the maximum oil recovery production process. Depends on the plant capacity, from 100% of waste oil collected, it is estimated to recover total 97% of recovered oil in distillation process, 95% of recovered oil in evaporation process and 97% in pyrolysis recovery system. The residual sludge that need to be proper disposed is estimated to be 3% in distillation process, 5% in evaporation process and 1% in pyrolysis process. 53 Table 4.7: Material balance for waste oil recovery Recovery Method Incoming Waste Oil Recovered Oil Distillation Evaporation Pyrolysis 100% 97 95 97 Figure 4.13: Gravity oil water separator Figure 4.14: Stainless steel wire mesh bag filters Residual Sludge 3 5 1 54 4.4.6 Oil and Water Mixture or Ballast Water Large quantities of waste water and oils mixture are continuously generated by ship activities to provide stability and maneuverability during a voyage. The oil and water mixture generated from these sources predominately those recovered from ballast water. These oils are composed primarily of the fuel used by particular ship. Steel drums or skid tank will be used to store the oil and water mixture. They are tough for handling, transportation and storage. Incoming oil water mixture varies depend on the type of ship. In general, the oil and water mixture will undergo two stages of the recovery process i.e. separation and recovery as mentioned above. In spite of the salinity presence in ballast water, the recovery process should be done separately from other waste oil materials if the above processes (distillation, evaporation or pyrolysis) needs to be applied. One other alternative for oil and water recovery is through centrifuge system. The oil and water mixture collected need to undergo separation process by means of gravitation separation in the skid tank. By leaving the oil in the skid tank undisturbed for enough time (normally 2 days), they will eventually settle at the tank bottom and can be easily removed. Then the oil will undergo the centrifuge system (hydrocyclones) at high pressure producing a rotor jet speed of 4,000 to 8,000 rpm for further separation in order to get better impurities removal (DOE, 2008). Debris and dirt will be pushed against the side inner wall of the rotor bowl while the clean oil is fed into the product storage tank. When sufficient time is not available, the centrifuge separation process may be accelerated by heating the oil to some safe temperature (with a steam coil heater to 90oC). Most of solids and sludge generated from centrifuge system are collected in the sludge holding bin, prior disposed at Kualiti Alam Sdn Bhd. The centrifuge system for oil and water mixture recovery process as well as the material balance is shown in Figure 4.15 and Table 4.8. 55 OIL AND WATER MIXTURE No WASTE ACCEPTANCE CRITERIA Yes RAW MATERIAL (100%) SEPARATION (95%) WATER (5%) HEATER at 90oC (90%) Wastewater treatment plant SUSPENDED SOLID (10%) CENTRIFUGE SYSTEM (80%) Dispose at Kualiti Alam RECOVERED OIL (80%) Figure 4.15: The typical flow of oil and water mixture centrifuge system recovery process 56 Table 4.8: Material balance for oil and water mixture or ballast water recovery Raw Material Recovered Oil) Sludge 100% 80 % 10% 4.4.7 The Recovery Oil The final recovered oil will meet specifications as set up in Guidelines on Standard and Specification of Recovered Waste Oil in Malaysia by the Department of Malaysia as tabulated in Table 4.9 Table 4.9: Standard and specification of recovered waste oil (DOE, 2009) Parameters / Constituents Allowable Level Arsenic Cadmium Chromium Lead Total Halogen Flash point Benzene Appearance 5 ppm maximum 2 ppm maximum 10 ppm maximum 100 ppm maximum 1000 ppm maximum 37.7oC or higher 5% maximum The recovered waste oil must have a clear and bright appearance 10 mg / 1 kg oil (10 ppm) maximum 10 mg / 1 kg oil (10 ppm) maximum 100 mg / 1 kg oil (100 ppm) maximum 100 mg / 1 kg oil (100 ppm) maximum 100 mg / 1 kg oil (100 ppm) maximum 100 mg / 1 kg oil (100 ppm) maximum (23-cd) pyrene 100 mg / 1 kg oil (100 ppm) maximum Benzo (a) pyrene Dibenz (ah) anthracene Benz(a) anthracene Benzo (b) fluoranthene Benzo (k) fluoranthene Chrysene Indeno 4.5 Waste Coolant Recovery Scheduled waste categorized under group SW 307 spent mineral oil-water emulsion of Environmental Quality (Schedule Waste) Regulations, 2005. 57 4.5.1 General Elements of Coolant As cited by Kidd et.al (1995), coolant is a complex form of multilayered heterogenous waste. Heat generated from friction between the object and the blade in cutting operations can be reduced by applying coolant. The machine coolant is primarily aqueous and contain water soluble oil consisting of ethanol amine emulsifier derived from fatty acids, both synthetic and natural. This emulsion carries away metal turnings from a part being machined on a lathe or other machining tool. When the coolant becomes spent, it contains chlorosolvents carried over from other cutting as well as a fair amount of tramp oil from machine bearings. This results in a multiphasic aqueous waste that requires treatment of metal and organic contaminants. There are various sources of coolant which can be collected from industries and such as: (i) metal-working using highly productive machinery with high cutting speeds (ii) machinery operations that apply grinding, turning, machining and drilling (iii) polishing done by Precision Parts Manufacturers lubricating in wet and dry wire drawing surface treatment in rolling mills industry Clean coolants ensure highly-effective machining with fine tolerances, while dirty coolant wears spindles, pumps and tools. Coolants polluted by leaked oil, are broken down by bacteria, lose their original properties and start smelling. 4.5.2 Statement of Need There are four types of contaminants that need treatment in waste coolant (DOE, 2008). The first contaminant is tramp oil which consist of free-floating oil, unstable oil coolant emulsion and microscopic oil particles. The second contaminant is suspended solids which exist in the form of particles from machine operation can 58 be present in the coolant, inhibiting heat transfer efficiency of the coolant. Thirdly, bacteria from water multiplies in warm conditions of the machine tool coolant sump. Finally the level of dissolved solids present in all water resources will contaminate coolant as dissolved solids reaches its threshold. 4.5.3 Waste Coolant Acceptability Criteria Upon receiving, the waste will be analysed to reconfirm their characteristic based on the information furnished by the spent coolant waste generators. The waste spent coolant must meet the acceptance criteria prior recycling as categorized in Table 4.10. Table 4.10: Waste coolant acceptance criteria for recovery (DOE, 2008) Wastes materials Spent mineral oil-water (coolant) Waste Acceptance Criteria2 Physical properties: Liquid Color : Light yellow to dark brown Chemical Properties : Inorganic Oil contents 2500-5000 mg/L TDS : <650 ppm SS : <1000 ppm pH : 7.3 – 8.9 Water content (%) : 70-80% Oil content (%) : 20-30% Boiling point (oC) : 120 Flash point (oC) : 88 Specific gravity : <1.0 Flammability : Yes Bacterial count : 107 - 109 No./ ml Emulsion concentration : 25% lower than new coolant Free oil : 5000 ppm Recovered (%) : >80% 59 4.5.4 Waste Coolant Recovery Process Description The coolant recovery system is devided into tramp oil removal, suspended solids removal and bacterial disinfections (DOE, 2008). Waste coolant from waste generators will be stored temporarily at the collection tank. A series of wire mesh particle filters (100 mesh, 150 mesh and 200 mesh) will be used consecutively to screen out various size particles to prevent clogging from build up at only 1 filter. With this design the frequency of filter cleaning is reduced. At this stage the feed is still contaminated with oil, fine particles passing 200 mesh filter and dissolved solids. Next, the contaminated feed will be fed into the Desorber to remove freefloating oil and oil coolant unstable emulsion completely (DOE, 2007). Due to the density difference between settleability solids, coolant and oil under the gravity effect, solids and coolant will settle below the top later of oil. A valve will be installed at the bottom part of the Desorber to discharge the solids as well as coolant for further recovery processes. The oil mixed coolant will be directed to the oil interceptor before being directed back to the temporary collection tank for reprocessing. The sludge will be extracted out to be dried, thickened and disposed. The coolant is then being directed through a couple of stainless steel wire mesh bag filters to eliminate unwanted suspended solids ranging from 2 to 25 micron with the help of a pressure pump. The stainless steel wire cloth bag filters is washable for reuse. The sludge will be removed for thickening and disposal. After the removal of tramp oil and machine solids, coolant will be passed through the disinfecting unit where it will be exposed to high strength UV light. The wavelength of 253nm is lethal enough to destroy bacteria thus disinfects the coolant. Coolant being opaque is thinned down into a fine sheet of paper before subjecting to UV treatment. UV reflector bulbs are positioned inside the disinfection unit for maximum destruction rate and area usage. Figure 4.16 shows the process flow and material balance across the maximum coolant recovery. 60 WASTE COOLANT No WASTE ACCEPTANCE CRITERIA YES COLLECTION TANK (100%) WIRE MESH FILTERS DESORBER SLUDGE OUT (19%)%) OIL INTERCEPTOR SS BAG FILTER Dispose at Kualiti Alam BACTERIAL DISINFECTION UNIT OIL PARTICLES OUT (1%) RECOVERED COOLANT (80% ) Figure 4.16: Typical process flow and material balance across the coolant recovery 61 4.5.5 Material Balance for Coolant Recovery Table 4.11 and Figure 4.16 represents the material balance across the maximum coolant recovery production process. Depends on the plant capacity, from 100% of waste oil collected, it is estimated to recover about 80% of treated coolant and generate about 15% of residual sludge material and 1% is estimated to be oil particle if the plant is operated at its maximum capacity. Table 4.11: Material balance for coolant recovery Incoming Waste Coolant Treated Coolant Residual Sludge Oil Particle 100% 80.00 % 19 % 1% 4.6 Solvent Recovery Scheduled waste categorized under group SW 322 is waste of nonhalogenated organic solvents and SW323 is waste of halogenated organic solvents of Environmental Quality (Schedule Waste) Regulations, 2005. 4.6.1 General Elements of Solvent Solvents have many diverse uses from paints and coatings, personal care products and pharmaceuticals to pesticides, cleaners and inks. Thousands of producers and manufacturers, and millions of workers, rely on solvents every day to provide solutions to new manufacturing needs and to sustain excellence in functional performance. A solvent is a liquid that has the ability to dissolve, suspend, or extract other materials without causing a chemical change to the material or solvent. Solvents 62 make it possible to process, apply, clean, or separate materials. The American Solvents Council (2002) states that solvents operate on the principle of “like dissolves like”; therefore, for a solvent to work it needs to have similar chemical characteristics to the substance that it is trying to dissolve. 4.6.2 Statement of Need Halogenated solvent is a synthetic solvents containing mixture of elements such as fluorine, chlorine, bromine, iodine, and astatine. Nevertheless nonhalogenated solvent is a petroleum solvent (Lee, 2008) There are various types of solvent which can be collected from industries. Table 4.12 lists down the examples of solvents to be recovered..The used solvents can be recovered by distillation or evaporation to separate the more volatile materials from less volatile materials by a process of vaporisation and condensation. Considerably, the most numerous industrial applications of evaporation have been for purification in chemical manufacturing and in processes involving solvent recycling as well. The solvents recovered have purity greater than 95%, varied from times to times depends on the nature of the spent solvents (DOE, 2007). To purify spent solvents which contain single solvent is simple. Whereas to separate mixed solvents like thinner requires more tedious process like longer condensing columns and longer evaporation time. The solvents that used in plating process may contain oil and grease that needs to be removed as this contributes to inefficient in plating process. 4.6.3 Waste Solvent Acceptability Criteria The solvent waste may be supplied from electronics manufacturer (PCB, IC and parts), paint industry, solvent based paint manufacturers and paint packing 63 factories, ink industry from ink manufacturer and printing companies and other industry including adhesive industries and factories using paint and ink products. Upon receiving, the waste will be analysed to reconfirm their characteristic based on the information furnished by the spent solvent waste generators. The waste spent solvent must meet the acceptance criteria prior recycling as categorized in Table 4.13. Table 4.12: Boiling point, density and TLV of some common solvents base on Material Safety Data Sheet Solvent Ketone Acetone Methyl Ethyl Ketone Ester Ethyl Acetate Alcohol Isopropyl Alcohol Ethanol n-Propanol Aromatic Toluene Xylene Chlorinated Solvent Methylene Chloride Trichloroethylene 1, 1, 1 -Trichloroethane Perch loroethylene o Boiling Point C Specific Gravity Threshold Limit Value (ppm) 56.0 80.0 0.791 0.805 750 200 77.0 0.902 400 82.4 78.0 97.0 0.785 0.785 0.804 400 1000 200 110.6 137.5 0.865 0.871 100 100 40.0 86.7 75.0 121.0 1.325 1.463 1.437 1.623 100 50 350 50 64 Table 4.13: Waste solvent acceptance criteria (DOE, 2007) Wastes materials Waste Category SW322- Waste of non-halogenated organic solvents Waste Acceptance Criteria Physical properties: Liquid or Emulsion Color : All Colour Chemical Properties : Organic Water contents : ± 2% Sediment contents : ± 3% pH : 4 – 8 Boiling point (oC) : 182 Flash point (oC) : 174 - 212 Specific gravity : <1.0 Flammability : Yes Recovered : 70% Residue : 2 - 5% SW323 Waste of halogenated organic solvents Physical properties: Liquid or Emulsion Color : Brown to Clear Water contents : ± 1% Sediment contents : ± 2% Chemical Properties : Organic Boiling point (oC) : 114 - 117 Flash point (oC) : 96 - 155 Specific gravity : >1.0 Flammability : No Water Solubility : Insoluble pH : 4 – 8 Recovered : 95 - 98% Residue : 2 - 5% From decreasing process of PCB, IC, solvent based paint, printing and adhesive industry. 4.6.4 Solvent Recovery Process Description Waste solvent could be recovered through separation and evaporation (DOE, 2007). After conforming to the waste acceptance criteria, the waste solvent will be fed into the Desorber to remove solids, free oil and grease by separating the heavy solids and grease from solvents. The coalescers in the Desorber will trap any free water and act as pre-filter to other processes. The heavier solids will settle at the bottom of the Desorber and will be extracted out to be dried, thickened and disposed at Kualiti Alam Sdn. Bhd. 65 The solvent is then being directed through a couple of stainless steel wire mesh bag filters to eliminate unwanted suspended solids ranging from 1 to 25 micron with the help of a pressure pump. The stainless steel wire cloth bag filters is washable for reuse. The sludge will be removed for thickening and disposal. After separation process, which is the removal of solid contaminants and grease by the Desorber and bag filters, the solvent will be fed into vacuum evaporation chamber for moisture removal. The vaporizer is used to preheat the solvent to the required temperature when it starts boiling while the pressure in the chamber is kept below the atmospheric pressure. The vaporized solvent is then drawn towards the refrigerated cooled condenser where it is condensed to liquid form. The air gets sucked inside the vacuum pump is directed out into the atmosphere. The process is continued till the solvent is completely evaporated while the non-volatile residue or sludge will be scrapped out through a valve system from the vacuum vaporizer. The typical flow diagram of separation and evaporation recovery process is given in Figure 4.17. The evaporation process works in an entirely closed system. The capacity of cooling system is well enough to condense all the vapor hence the fume emitted into the air is negligible. 4.6.5 Material Balance Figure 4.17 and Table 4.14 represent the material balance across the maximum solvent separation and evaporation recovery production process. Depends on the plant capacity, from 100% of waste oil collected, about 0.02% will be the settable solid. Throughout the recovery process, it is estimated to recover about 83% of treated coolant and generate about 2.0% of residual sludge material and 15.0% is estimated to be oily wastewater if the plant is operated at its maximum capacity. 66 WASTE SOLVENT No WASTE ACCEPTANCE CRITERIA Yes COLLECTION TANK (100%) DESORBER (83%) SLUDGE OUT STORAGE TANK (2%) Dispose at Kualiti Alam SS BAG FILTER VACUUM EVAPORATION CHAMBER CONDENSER Wastewater treatment plant (15%) Air SCRUBBER (1%) RECOVERED SOLVENT (82%) Figure 4.17: The typical flow diagram of solvent separation and evaporation recovery process 67 Table 4.14: Material balance for waste solvent recovery Incoming Waste Solvent 100% 4.7 Treated Solvent Residual Sludge Wastewater 82% 2% 15 % Used Industrial Container Recovery Scheduled waste categorized under group SW 409 is disposed containers, bags or equipment contaminated with chemicals, pesticides, mineral oil or scheduled waste. 4.7.1 General Elements of Industrial Container Most industries recognize that HDPE is the best plastic container of choice to ensure purity of chemical contents. In addition, the IBC tank which is super-sturdy and protectively enclosed industrial strength as well as chemical resistance are being used for chemical storage. Figure 4.18 shows some industrial containers used in the industries. Steel containers and tin have been used for a long time as a means of storing or transporting a variety of materials including resins, paints and some viscous organic chemical. These containers are built to withstand the exigencies of transit. Moreover, steel drums are typically made of a heavy gauge metal and are relatively expensive Excellent for storing large batches of materials such as distilled water, solutions or select chemicals, the carboys represent the most popular shapes and sizes used within the lab industry. In modern laboratories, carboys are usually made of plastic, though traditionally were made of ferric glass or other shatter-resistant glasses immune to acid corrosion or halide staining common in older plastic fomulations. Carboys are also used to collect and store waste solvents. 68 Carboy A B C D E Figure 4.18: Types of industrial containers (A:Carboy; B:Tin; C:IBC Tank; D:Small Tin; E: Jumbo Bags) Jerry can containers are used to transport chemicals of corrosive nature namely acids and alkalis that are soluble in water. As it is to store water soluble substances, jerry can could be recovered by manually washed that is spraying with 69 high pressure water. In addition, jumbo bags made of woven poly propylene normally used to contain dust or granule in some industries can also be recovered. 4.7.2 Statement of Need Many types of containers are being used in industries for chemical storage such as high-density polyethylene (HDPE) drums, intermediate bulk container (IBC), steel drums, tin, carboy and jerry can (DOE, 2007). Containers tainted with contaminants such as used or spent chemicals are considered as scheduled waste. These containers should be recovered properly to ensure the materials will have no unreasonable adverse effect on the environment, people handling the containers or users of the end-use products manufactured. 4.7.3 Waste Acceptability Criteria for Used Industrial Container Recovery The sources of containers are mainly from the various manufacturing industries. The collected residue from the containers that contained different types of waste may be deemed as "scheduled wastes" under the Environmental Quality (Scheduled Wastes) Regulations, 2005, and require proper treatment. The containers collected must meet the acceptance criteria prior recycling as categorized in Table 4.15. Table 4.15: Industrial container acceptance criteria (DOE, 2007) Wastes Materials High-density polyethylene (HDPE) drums, steel drums, tin, carboy, Jerry can and jumbo bags. Waste Acceptance Criteria From waste disposal of acid, coolant, solvent, dye, ink, paint, oil Content of waste < 1% of drum content No deformities or leakage 70 4.7.4 Industrial Container Recovery Process Description The process flow starts from the collection of containers as classified under SW409 of the Environmental Quality (Scheduled Wastes) Regulations 2005. The incoming containers are first segregated and classified based on the type of containers and the liquid raw materials that were transported in them and the cleaning techniques needed to be employed. These containers are further classified as mainly containing solvents, acid and alkaline. Each container is inverted and drained off its contents. Due to the viscous nature of the above compounds, the duration of the draining time will vary and may range between 2 to 6 hours (DOE, 2007). The containers containing solvent soluble residue will be sent for solvent recovery. Then they will be loaded onto a solvent washing machine, where the inside of the containers are mechanically sprayed with recycled solvent to wash off heavy solids, grease, paint, ink, oil and solvent. The containers containing acid and alkaline will go through drip drying process. Then the containers will go through the first stage rinsing process using city water and cleaning agent. The second stage rinsing process is to remove excess washing agent from the containers and to ensure the containers are clean. Liquid residue will be treated in the wastewater treatment plant and the collected residual sludge will be sent for disposal at the Kualiti Khidmat Alam. As carboy and HDPE containers are used to transport chemicals of corrosive nature namely acids and alkaline solution. They were manually washed by spraying high pressure water (DOE, 2007). The wastewater after washing is channeled into the wastewater system. After washing the containers are transferred into the storage area as finished. The typical process flow diagram for containers recycling process is presented in Figure 4.19 and Figure 4.20 shows the cleaning of containers in the system. Containers are used to transport thousands of different cargo; therefore the interiors and exteriors of these containers are cleaned and dried using hot air circulation (DOE, 2007). Before releasing the recovered containers for storage, high- 71 pressure leak test will be conducted to check the containers for leakage as well as reconditioned the containers to prevent contamination of materials from one cargo to the next and to ensure integrity of the containers. CONTAMINATED CONTAINERS WASTE ACCEPTANCE CRITERIA No Yes Dispose to Kualiti Alam SEGREGATION (100%) Contaminated waste solvent Contaminated waste acid / alkaline SOLVENT RINSING PROCESS 1st. STAGE WATER RINSING PROCESS DRIP DRYING PROCESS SOLVENT RECOVERY PROCESS WATER RINSING PROCESS NEUTRALIZATION 2nd . STAGE WATER RINSING PROCESS WASTEWATER TREAMENT Sludge to Kualiti Alam DRYING PROCESS SCRUBBER AIR PRESSURE CHECK FOR LEAK TEST RECOVERED CONTAINER (100%) Figure 4.19: The typical flow process of containers recycling 72 Container cleaning system either with water or solvent Container washing technique efficient cleaning quality IBC tank cleaning Figure 4.20: Cleaning of containers (DOE, 2007). 73 4.7.5 Material Balance Table 4.16 represents the material balance across the maximum containers recovery production process depends on the plant capacity, from 100% of contaminated containers collected, all of the containers can be recovered consider they are in good condition for recovery. Relative to the total weight of contaminated containers collected, 2% is estimated to be discharge as residual sludge material. Table 4.16: Material balance for industrial containers recovery Total Contaminated Containers (by weight) Residual Sludge (by weight) Recovery Containers (by weight) 100% 2% 98% 4.8 Used Rags and Filters Recovery Scheduled waste categorized under group SW 410 in the Environmental Quality (Scheduled Wastes) Regulations 2005 First Schedule are rags, plastics, papers or filters contaminated with scheduled waste. 4.8.1 General Elements of Rags and Filters Rags (also called wipes, wipers, and shop towels); filters and absorbent materials (such as mats, socks, and loose material such as speedy-dry) are use to clean a variety of contaminated substances. Besides widely use to clean mixed solvent, organic-based oil, paint, dye and grease; rags or filters and are also use to clean ink in printing and electronic industries that produce PCB, IC and parts as well as other industry including adhesive industries and factories using paint and ink products. Specifically, filters are cotton construction used mainly for particulate and organic waste removal to protect sensitive machines. 74 The contaminated rags or filters become solid wastes when they are too dirty and not suitable for cleaning purpose anymore. Hence, they are subjected to a hazardous waste determination under Environmental Quality (Scheduled Wastes) Regulations, 2005 (DOE, 2007). The contaminated rags or filters must be carefully managed to prevent or reduce the risk to human health and the environment. Subsequently, the contaminated rags or filters are valuable and could be recovered for reuse. The recycled rags or filters could be sold back to some waste generators especially for cleaning purpose at a discount price. The recycled materials could also be sold to traders or manufacturers or industries including printing and electronic due to high quality of recycled material. 4.8.2 Statement of Need The most efficient way of separating contaminants from used rags or filters is by washing and rinsing either with solvent or water. Normally the recovered rags or filters recovered have purity greater than 95%, varied from times to times depends on the efficiency during washing and rinsing (DOE, 2007). To purify the used rags or filters contaminated with acid or alkaline is simple that is through washing and rinsing with water. Whereas to separate mixed solvents, organic-based oil, paint, dye and grease requires more tedious process like washing using solvent followed with detergent and water. 4.8.3 Used Rags and Filters Waste Acceptability Criteria The sources of wastes are mainly from the printing and electronic industries. Waste collected must meet the acceptance criteria prior recycling as categorized in Table 4.17. 75 Table 4.17: Used rags and filters acceptance criteria (DOE, 2007) Wastes materials Waste cotton rags filters and absorbent materials such as mats, socks, and loose material such as speedy-dry materials. Waste Acceptance Criteria1 From waste contaminated with acid, solvent, cotton of electronic, printing, plastic injection moulding, packaging and machinery of industry. Non toxic substances. Good conditions and can be recycled and reused 4.8.4 Used Rags and Filters Recovery Process Description The contaminated rags or filters collected from various industries must be stored and transported in non-leaking closed containers. To prevent from burning, fire-resistant containers should be used and are kept away from sources of ignition. In addition, containers must also be in good condition and sufficient to prevent the release of contaminants to the air. Each drum of waste will be labeled according to the Third Schedule of the Environmental Quality (Schedule Waste) Regulations, 2005 to identify their contents. After conforming to the waste acceptance criteria, the incoming drum containing contaminated rags or filters are first segregated and classified based on the quality of rags or filters. The type of contamination that was transported in them will determine the cleaning techniques employed. Incompatible wastes will be segregated, dried and disposed to Kualiti Alam Sdn. Bud. The recyclable rags or filters are further classified as mainly contaminated with solvents, light oil or water soluble chemicals, resins and water-based paints (DOE, 2007). Depends on the contaminants present, rags or filters will be soaked in solvent or soaking agent which is mainly contain 20% of surfactant and 80% of solvent (DOE, 2007). The soaking machine separator separates solids, grease, and paint ink dye. After soaking, the materials will be sent to a centrifugal dryer where the machine will spin at high speed to remove the wet rags or filters of the soaking chemical. The solvent used in soaking process can also be recovered. 76 The semi dry rags or filters will be placed in a fiber trolley before them being loaded into the industrial washing machine. A non-ionic surfactant degreasing detergent, which produces minimal foam, will be used to soak and wash the rags or filters. After rinsing and drying in the industrial washing machine, the cleaned rags or filters will be dried in a controlled temperature of 100 - 250 oC oven. (DOE, 2007). The wastewater from washing and drying processes will be sent to the wastewater treatment plant and the collected residual sludge will be sent for disposal at the Kualiti Khidmat Alam. Finally, the cleaned rags or filters will undergo sewing and converted to the recycled rags or filters. Figure 4.22 shows the flow process of contaminated rags and filters. A B Figure 4.21: A: typical industrial washing machine; B: industrial dryer used for rags/filters cleaning 77 CONTAMINATED RAGS OR FILTERS Yes No WASTE ACCEPTANCE CRITERIA OK SOAKING TANK (100% Waste Materials) NOT OK SOLVENT RECOVERY PROCESS OK CENTRIFUGAL DRYING WASHING RINSING AND DRYING Waste Solvent DRYING Sludge to Kualiti Alam (9%) OVEN DRY Wastewater CLEANED RAGS OR FILTERS (90%) Wastewater treatment plant (1%) Figure 4.22: The typical flow process of contaminated rags or filters recycling 78 4.8.5 Material Balance Table 4.18 and Figure 4.22 represent the material balance across the maximum contaminated rags or filters recycling production processes. Depends on the plant capacity, from 100% of contaminated rags or filters collected, about 90% could be recycled. Throughout the recovery process, it is estimated about 9.00% of residual sludge material will be disposed to Kualiti Alam Sdn. Bhd. and 1.00% of wastewater must be properly treated in the plant. Table 4.18: Material balance for rags or filters recycling Incoming Contaminated Rags and Filters Recycled Rags and Filters Residual Sludge Wastewater 100% 90 % 9% 1% 4.9 Conclusion From the study, innovative recovery process flow is designed to satisfy all regulatory requirements, to protect and enhance the value of physical assets as well as corporate reputations. Hence, the invention of recovery and recycling processes is an integral plan between technology, environment and economy, given the concept of waste as a valuable resource and waste to wealth. In an effort of reducing the volumes of scheduled wastes generated for disposal, more than 80% of valuable resources from scheduled waste can be recovered accept 30% for SW202 Waste Catalyst. CHAPTER 5 DISCUSSION OF RESULTS Referring to the number of recyclers obtained from the information gathered, it was found out that out of total 77 types of scheduled wastes listed in the Environmental Quality (Scheduled Wastes) Regulations, 2005, First Schedule, there are 41 (53%) types of scheduled wastes are being recovered or recycled as listed in Table 5.1. For the study, flow of recovery and recycling processes for 16 (21%) types of scheduled waste have been reviewed to produce process flow. Table 5.1: 41 Types of Scheduled Wastes Listed in the First Schedule Are Being Recovered or Recycled (the recovered or recycled process flow are produced for the bolded 16 types) No. Code 1 2 SW102 SW104 3 SW107 4 SW108 Type of waste SW1 - Metal and metal bearing wastes Waste of lead acid batteries in whole or crushed form Dust, slag, dross or ash containing aluminium, arsenic, mercury, lead, cadmium, chromium, nickel, copper, vanadium, beryllium, antimony, tellurium, thallium or selenium excluding slag from iron and steel factory Slags from copper processing for further processing or refining containing arsenic, lead or cadmium Leaching residues from zinc processing in dust and sludges form No. of Recyclers 4 18 1 5 80 4 Waste from electrical and electronic assemblies containing components such as accumulators, mercury-switches, glass from cathode-ray tubes and other activated glass or polychlorinated biphenylcapacitors, or contaminated with cadmium, mercury, lead, nickel, chromium, copper, lithium, silver, manganese or polychlorinated biphenyl SW2 - Wastes containing principally inorganic constituents which may contain metals and organic Materials 6 SW202 Waste catalysts 6 7 SW204 Sludges containing one or several metals including 4 chromium, copper, nickel, zinc, lead, cadmium, aluminium, tin, vanadium and beryllium 8 SW206 Spent inorganic acids 5 SW3 - Wastes containing principally organic constituents which may contain metals and inorganic Materials 9 SW 301 Spent organic acids with pH less or equal to 2 which 2 are corrosive or hazardous 10 SW 305 Spent lubricating oil 10 11 SW 306 Spent hydraulic oil 9 12 SW 307 Spent mineral oil-water emulsion 9 13 SW 308 Oil tanker sludges 6 14 SW 309 Oil-water mixture such as ballast water 5 15 SW 310 Sludge from mineral oil storage tank 4 16 SW 311 Waste oil or oily sludge 7 17 SW 312 Oily residue from automotive workshop, service 7 station, oil or grease interceptor 18 SW 313 Oil contaminated earth from refining of used 1 lubricating oil 19 SW 314 Oil or sludge from oil refinery plant maintenance 2 operation 20 SW 315 Tar or tarry residues from oil refinery or 1 petrochemical plant 21 SW 322 Waste of non-halogenated organic solvents 9 22 SW 323 Waste of halogenated organic solvents 7 2 23 SW 324 Waste of halogenated or un-halogenated nonaqueous evaporation residues arising from organic solvents recovery process 4 24 SW325 Uncured resin waste containing organic solvents or heavy metals including epoxy resin and phenolic resin 25 SW 327 Waste of thermal fluids (heat transfer) such as 1 ethylene glycol SW 4 - Waste which may contain either inorganic or organic constituents 26 SW401 Spent alkaline waste containing heavy metals 2 27 SW402 Spent alkalis with pH more or equal to 11.5 which 1 are corrosive or hazardous 28 SW409 Disposed containers, bags or equipment 7 5 SW110 81 29 SW410 30 SW411 31 32 33 34 35 SW412 SW413 SW 414 SW415 SW 416 36 SW 417 37 SW 418 38 39 40 SW421 SW 422 SW 423 41 SW 429 contaminated with chemicals, pesticides, mineral oil or scheduled wastes Rags, plastics, papers or filters contaminated with scheduled wastes Spent activated carbon excluding carbon from the treatment of potable water and processes of the food industry and vitamin production Sludges containing cyanide Spent salt containing cyanide Spent aqueous alkaline solution containing cyanide Spent quenching oils containing cyanides Sludges of inks, paints, pigments, lacquer, dye or varnish Waste of inks, paints, pigments, lacquer, dye or varnish Discarded or off-specification inks, paints, pigments, lacquer, dye or varnish products containing organic solvent A mixture of scheduled wastes A mixture of scheduled and non-scheduled waste Spent processing solution, discarded photographic chemicals or discarded photographic wastes Chemicals that are discarded or off-specification 10 2 2 4 3 5 5 1 3 2 1 From the study, innovative recovery process flow is designed to satisfy all regulatory requirements, to protect and enhance the value of physical assets as well as corporate reputations. Hence, the invention of recovery and recycling processes is an integral plan between technology, environment and economy, given the concept of waste as a valuable resource and waste to wealth. In an effort of reducing the volumes of scheduled wastes generated for disposal, more than 80% of valuable resources from scheduled waste can be recovered accept 30% for SW202 Waste Catalyst as listed in Table 5.2. 82 Table 5.2: Recovery Percentage for 16 Types of Scheduled Wastes No. Code Type of waste Recovery % SW1 - Metal and metal bearing wastes 1 Dust, slag, dross or ash containing aluminium, arsenic, 99.90% mercury, lead, cadmium, chromium, nickel, copper, vanadium, beryllium, antimony, tellurium, thallium or selenium excluding slag from iron and steel factory SW2 - Wastes containing principally inorganic constituents which may contain metals and organic materials 2 SW202 Waste catalysts 30.00% SW3 - Wastes containing principally organic constituents which may contain metals and inorganic materials 3 SW 305 Spent lubricating oil 97.89% 4 SW 306 Spent hydraulic oil 5 SW 307 Spent mineral oil-water emulsion 80.00% 6 SW 308 Oil tanker sludges 7 SW 309 Oil-water mixture such as ballast water 8 SW 310 Sludge from mineral oil storage tank 9 SW 311 Waste oil or oily sludge 97.89 10 SW 312 Oily residue from automotive workshop, service station, oil or grease interceptor 11 SW 314 Oil or sludge from oil refinery plant maintenance operation 12 SW 315 Tar or tarry residues from oil refinery or petrochemical plant 13 14 SW104 SW 322 Waste of non-halogenated organic solvents 83.00 SW 323 Waste of halogenated organic solvents SW 4 - Waste which may contain either inorganic or organic constituents 15 SW409 16 SW410 Disposed containers, bags or equipment contaminated with chemicals, pesticides, mineral oil or scheduled wastes Rags, plastics, papers or filters contaminated with scheduled wastes 100.00 90.00 CHAPTER 5 CONCLUSION 5.1 Conclusion The study has met the aim and objectives that have been setup earlier. Based on the Environmental Quality (Scheduled Wastes) Regulations 2005 First Scheduled, 41 types of scheduled waste generated from 4 categories which are SW 1, SW 2, SW 3 and SW 4 are found have been recycled and recovered by recyclers in Malaysia. Through literature review, evaluation and comparison on the recovery and recycling processes done by the related manufacturers in Malaysia, the general recovery and recycling process flow for 16 out of 77 types of scheduled waste have been reviewed to produce typical process flow. By comparison, the Waste Acceptance Criteria have been identified from the minimum level of acceptance prior to recovery and recycling processes and the Material Balance calculation indicate the estimated percentage of treated or recovered waste materials, residual sludge material generated and wastewater discharged if the plant is operated at its maximum capacity. 80 5.2 Recommendations In line with the concept of 4R (reduction, reuse, recycling and recovery) and “from cradle to grave” waste management, a greener environmental solution, thereby enabling the recycling industries to achieve 30% of total solid and scheduled waste recycling in 2020 besides 5% currently (Utusan Malaysia, 2009). Hence, the following recommendations should be carried out to improve the study: (i) The general recovery and recycling process flow for another 61 types or the most waste generated from the First Schedule Environmental Quality (Scheduled Wastes) Regulations 2005 should be produced. (ii) The costs associated with the price discovery for the technology which give NPV (Net Present Value) could be another element that should be enhanced in the study in order to give value added to the recycling industry. 81 REFERENCES Ahmad Fariz Mohamed, Mohd Raihan Taha, Shaharudin Idrus, Abdul Samad Hadi and Abdul Hadi Harman Shah (2008). Title of Paper: Infrastructure for Sustainable Industrial Wastes Recovery in Malaysia A S Hornby , 1983. Oxford Advanced Learner’s Dictionary of Current English, Oxford University Press Azni Idris, Bulent Inanc and Mohd Nasir Hasan, (2004). Overview of Waste Disposal and Landfills/Dumps in Asian Countries. Journal of Material Cycles and Waste Management. Volume 6, No.2, pp 104-110 Department of Environment (2007) Environmental Impact Assessment Guidance Document for The Construction of Scheduled Waste Recovery Plant (Off-Site) Putrajaya Department of Environment Malaysia (DOE), (2007). Environmental Requirements: A Guide For Investors. Putrajaya. Department of Environment Malaysia (DOE), (1995). Malaysia Environmental Quality Report 1994. Kuala Lumpur Department of Environment Malaysia (DOE), (2003). Malaysia Environmental Quality Report 2002. Putrajaya. Department of Environment Malaysia (DOE), (2006). Malaysia Environmental Quality Report 2005. Putrajaya. Dirk Durinck, Fredrik Engström, Sander Arnout, Jeroen Heulens, Peter Tom Jones, Bo Björkman, Bart Blanpain, Patrick Wollants, (2008). Resources, Conservation and Recycling, Volume 52, Issue 10, Pages 1121-1131 82 Environment Australia (1997). Appropriate technologies for the treatment of scheduled wastes. Department of Environment, Water, Heritage and the Arts, Australia Environmental Impact Assessment (2007). Containers and Rags Recycling, Mukim Plentong, Daerah Johor Bahru, Johor. Department of Environment, Malaysia Environmental Impact Assessment (2007). Oil Recovery Plant Kawasan Perindustrian Pengkalan 2, Kinta, Perak. Department of Environment, Malaysia Environmental Impact Assessment (2008). Precious Metal and Solder Dross Recovery, Pasir Gudang Industrial Estate, Mukim Plentong, Johor Bahru, Johor Department of Environment, Malaysia Environmental Impact Assessment (2008). Precious Metal and Waste Oil and Coolant Recovery, Sri Gading Industrial Estate, Batu Pahat, Johor. Department of Environment, Malaysia Environmental Impact Assessment (2007). Rags Recycling and Paint Recovery, Mukim Plentong, Johor Bahru, Johor. Department of Environment, Malaysia Environmental Impact Assessment (2007). Recycling Containers and Solvent Recovery, Mukim Plentong, Johor Bahru, Johor. Department of Environment, Malaysia Environmental Protection Agency, New South Wales (1996). Environmental Guidelines: Solid Waste Assessment Environmental Quality Act 1974 [Act 127] P.U. (A) 44/96 Environmental Quality (Prescribed Activities) (Environmental Impact Assesment) (Amendment) Order 1996 Environmental Quality (Scheduled Waste) Regulations, 1989 PU(A) 139/1989 Environmental Quality (Scheduled Waste) Regulations, 2005 PU(A)294/2005 Environmental Quality (Scheduled Waste) (Amendment) Regulations 2007 PU(A)158/2007 Hazardous Substances Division, (2009). Guidelines on Standard and Specification of Recovered Waste Oil in Malaysia. Department of Environment, Putrajaya Jacobsen, Robert T (2005).Chemical Engineering Progress United States of America Johan Sohaili (2009), Legislative and Economic Aspects of Cleaner Production (Introduction to Cleaner Production). Universiti Technology, Johor Malaysia Country Fact Sheet (2006). Basel Convention 2002 83 Malaysia, (2008). Malaysian Economy In Figures 2008. Economic Planning Unit, Prime Ministers Michael VanderPol, (2006). Regional Strategy For The Environmentally Sound Management Of Used Oils In The Caribbean Island States: Environment Canada, National Office of Pollution Prevention M.K. Carol Lee (2008). Non-Halogenated Solvent Dry Cleaning M.K. United States of America Mohd Najib Bin Tun Haji Abdul Razak, (2009). Pelancaran Dasar Teknologi Hijau Negara dan Perasmian Bangunan Baru Pusat Tenaga Manusia. Bangi, Selangor Naval School, Civil Engineer Corps Officers, (1997). Trainee Guide For Hazardous Waste Generators Course. Port Hueneme, California Report Of The Fourth Meeting Of The Conference Of The Parties To The Basel Convention, (1998) Scott Kidd, John S. Bowers (1995). Treatment of Mixed Waste Coolant. Lawrence Livermore National Laboratory Hazardous Waste Management Division, California Secretariat Of The Basel Convention (March 2009). Report On The Review Of The Implementation Of The Current Strategic Plan. Shuji Mori and A. D. McElroy, (1996). Future Catalyst Metals Availability And Assessment Of Waste Catalyst Reclamation, Midwest Research Institute, Kansas City, Missouri, USA The Star, (2003). RM 12 Million Disposal Costs Shock Selangor Exco, 4th December 2003 TF Market Research, (2009). Malaysia Oil and Gas Report Q3 2009, Malaysia: Business Utusan Malaysia, (2009). “Malaysia mahu capai 30 peratus kadar kitar semula”, Waste Oil: Technology, Economics and Environment,(1987) Health and Safety Considerations, US Department of Energy Zulkifli Abdul Rashid, Azil Bahari Alias, Mohd Jindra Aris, Mohanad El-Harbawi, H. 84 N. M. Ekramul, S.A.S. Abdul Kadir and Ayub Md Som. (2008) A Mathematical Model to Predict the Composition and Generation of Scheduled Waste in Malaysia University of Technology MARA , 85 APPENDIX A ENVIRONMENTAL QUALITY ACT 1974 ENVIRONMENTAL QUALITY (SCHEDULED WASTES) REGULATIONS 2005 __________________________________ ARRANGEMENT OF REGULATIONS Regulation 1. Citation and commencement 2. Interpretation 3. Notification of the generation of scheduled wastes 4. Disposal of scheduled wastes 5. Treatment of scheduled wastes 6. Recovery of material or product from scheduled wastes 7. Application for special management of scheduled wastes 8. Responsibility of waste generator 9. Storage of scheduled wastes 10. Labelling of scheduled wastes 11. Waste generator shall keep an inventory of scheduled wastes 12. Information to be provided by waste generator, contractor and occupier of prescribed premises 13. Scheduled wastes transported outside waste generator's premises to be accompanied by information 14. Spill or accidental discharge 15. Training Programme 16. Compounding of offences 17. Revocation SCHEDULES 86 ENVIRONMENTAL QUALITY ACT 1974 ENVIRONMENTAL QUALITY (SCHEDULED WASTES) REGULATIONS 2005 IN exercise of the powers conferred by sections 21 and 51 of the Environmental Quality Act 1974 [Act 127], the Minister, after consultation with the Environmental Quality Council, makes the following regulations: Citation and commencement 1. (1) These regulations may be cited as the Environmental Quality (Scheduled Wastes) Regulations 2005. (2) These Regulations come into operation on 15 August 2005. Interpretation 2. (1) In these Regulations, unless the context otherwise requires – "scheduled wastes" means any waste falling within the categories of waste listed in the First Schedule; "incompatible scheduled wastes" means scheduled wastes specified in the Fourth Schedule which, when mixed, will produce hazardous situations through heat generation, fires, explosions or the release of toxic substances; "on-site treatment facility" means a facility, other than a scheduled wastes incinerator or a land treatment facility, located on a waste generator's site and that is used solely to deal with scheduled wastes produced on that site; "contractor" means any person licensed by the Director General of Environmental Quality under subsection 18(1A) of the Act; "waste generator" means any person who generates scheduled wastes; 87 "prescribed premises" means premises prescribed by the Environmental Quality (Prescribed Premises) (Scheduled Wastes Treatment and Disposal Facilities) Order 1989 [P.U. (A) 140/1989]. (2) Words and expressions which are not defined in these Regulations shall have the same meaning as assigned to them in the Act and in the Environmental Quality (Prescribed Premises) (Scheduled Waste Treatment and Disposal Facilities) Order 1989. Notification of the generation of scheduled wastes 3. (1) Every waste generator shall, within 30 days from the date of generation of scheduled wastes, notify the Director General of the new categories and quantities of scheduled wastes which are generated. (2) The notification given under subregulation (1) shall include the information provided in the Second Schedule. Disposal of scheduled wastes 4. (1) Scheduled wastes shall be disposed of at prescribed premises only. (2) Scheduled wastes shall, as far as is practicable, be rendered innocuous prior to disposal. Treatment of scheduled wastes 5. (1) Scheduled wastes shall be treated at prescribed premises or at on-site treatment facilities only. (2) Residuals from treatment of scheduled wastes shall be treated or disposed of at prescribed premises. Recovery of material or product from scheduled wastes 88 6. (1) Recovery of material or product from scheduled wastes shall be done at prescribed premises or at on-site recovery facilities. (2) Residuals from recovery of material or product from scheduled wastes shall be treated or disposed of at prescribed premises. Application for special management of scheduled wastes 7. (1) A waste generator may apply to the Director General in writing to have the scheduled wastes generated from their particular facility or process excluded from being treated, disposed of or recovered in premises or facilities other than at the prescribed premises or on-site treatment or recovery facilities. (2) An application under subregulation (1) shall be submitted to the Director General in accordance with the guidelines for special management of scheduled wastes as prescribed by the Director General and shall be accompanied by fee of three hundred ringgit and shall not be refunded. (3) If the Director General is satisfied with the application made under subregulation (1), the Director General may grant a written approval either with or without conditions. Responsibility of waste generator 8. (1) Every waste generator shall ensure that scheduled wastes generated by him are properly stored, treated on-site, recovered on-site for material or product from such scheduled wastes or delivered to and received at prescribed premises for treatment, disposal or recovery of material or product from scheduled wastes. (2) Every waste generator shall ensure that scheduled wastes that are subjected to movement or transfer be packaged, labelled and transported in accordance with the guidelines prescribed by the Director General. Storage of scheduled wastes 89 9. (1) Scheduled wastes shall be stored in containers which are compatible with the scheduled wastes to be stored, durable and which are able to prevent spillage or leakage of the scheduled wastes into the environment. (2) Incompatible scheduled wastes shall be stored in separate containers, and such containers shall be placed in separate secondary containment areas. (3) Containers containing scheduled wastes shall always be closed during storage except when it is necessary to add or remove the scheduled wastes. (4) Areas for the storage of the containers shall be designed, constructed and maintained adequately in accordance with the guidelines prescribed by the Director General to prevent spillage or leakage of scheduled wastes into the environment. (5) Any person may store scheduled wastes generated by him for 180 days or less after its generation provided that (a) the quantity of scheduled wastes accumulated on site shall not exceed 20 metric tones; and (b) the Director General may at any time, direct the waste generator to send any scheduled wastes for treatment, disposal or recovery of material or product from the scheduled wastes up to such quantity as he deems necessary. (6) A waste generator may apply to the Director General in writing to store more than 20 metric tonnes of scheduled wastes. (7) If the Director General is satisfied with the application made under subregulation (6), the Director General may grant a written approval either with or without conditions. Labelling of scheduled wastes 90 10. (1) The date when the scheduled wastes are first generated, name, address and telephone number of the waste generator shall be clearly labelled on the containers that are used to store the scheduled wastes. (2) Containers of scheduled wastes shall be clearly labelled in accordance with the types applicable to them as specified in the Third Schedule and marked with the scheduled waste code as specified in the First Schedule for identification and warning purposes. (3) No person is allowed to alter the markings and labels mentioned in subregulations (1) and (2). Waste generator shall keep an inventory of scheduled wastes 11. A waste generator shall keep accurate and up-to-date inventory in accordance with the Fifth Schedule of the categories and quantities of scheduled wastes being generated, treated and disposed of and of materials or product recovered from such scheduled wastes for a period up to three years from the date the scheduled wastes was generated. Information to be provided by waste generator, contractor and occupier of prescribed premises 12. (1) A waste generator, contractor and occupier of the prescribed premises shall provide information in accordance with the Sixth Schedule in the manner provided in this regulation or Director General shall determine other method as he thinks fit. (2) A waste generator shall complete Part I of the Sixth Schedule in six copies and hand over the six copies of the Schedule to the contractor when the scheduled wastes are delivered to him. (3) The contractor shall, upon receiving scheduled wastes from a waste generator, complete Part II of the Sixth Schedule in the six copies given to him by the waste generator and shall thereafter immediately hand over two copies of the 91 Schedule to the waste generator who in turn shall submit a copy to the Director General within 30 days from the date of transportation of the scheduled wastes. (4) The contractor shall, within 10 days from the date of receipt of the scheduled wastes, deliver the scheduled wastes to the occupier of any prescribed premises and hand over the remaining four copies of the Sixth Schedule to the occupier. (5) The occupier of any prescribed premises shall, upon receiving scheduled wastes from the contractor, complete Part III of all the remaining four copies of the Sixth Schedule handed over to him by the contractor and shall, upon completion, retain one copy and return a copy each to the contractor, the waste generator and the Director General, within 20 days from the date of receipt of the scheduled wastes. (6) If the waste generator fails to receive his copy of the Sixth Schedule from the occupier of the prescribed premises referred to in subregulation (5) within 30 days from the date of delivery of the scheduled wastes to the contractor referred to in subregulation (2), he shall notify the Director General immediately and shall investigate and inform the Director General of the result of his investigation. (7) The waste generator, contractor or occupier of the prescribed premises shall keep a copy each of the Sixth Schedule. The Sign copy of Sixth Schedule must be retained as a record for at least three years from the date the scheduled wastes are accepted by the prescribed premises. Scheduled wastes transported outside waste generator’s premises to be accompanied by information 13. (1) Every waste generator shall provide information in accordance with the Seventh Schedule in respect of each category of scheduled wastes to be delivered to the contractor and shall give the Schedule to the contractor upon delivery of the waste to him. (2) The waste generator shall inform the contractor of the purpose and use of the Seventh Schedule. 92 (3) The contractor shall carry with him the Seventh Schedule for each category of scheduled wastes being transported and shall observe and comply with the instructions contained therein. (4) The contractor shall, in the selection of transportation routes, as far as possible avoid densely populated areas, water catchment areas and other environmentally sensitive areas. (5) The contractor shall ensure that all his employees that are involved in the handling, transportation and storage of scheduled wastes attend training programmes. (6) The contractor shall ensure that during the training programme each employee is well informed on the purpose and use of the Seventh Schedule. Spill or accidental discharge 14. (1) In the event of any spill or accidental discharge of any scheduled wastes, the contractor responsible for the waste shall immediately inform the Director General of the occurrence. (2) The contractor shall do everything that is practicable to contain, cleanse or abate the spill or accidental discharge and to recover substances involved in the spill or accidental discharge. (3) The waste generator shall provide technical expertise and supporting assistance in any clean-up operation referred to in subregulation (2). (4) The contractor shall undertake studies to determine the impact of the spillage or accidental discharge on the environment over a period of time to be determined by the Director General. Training Programme 15. Every waste generator shall ensure that all his employees involved in the 93 identification, handling, labeling, transportation, storage and spill response of scheduled wastes, attend training programme. Compounding of offences 16. (1) Every offence which consists of any omission or neglect to comply with, or any act done or attempted to be done contrary to these Regulations may be compounded under section 45 of the Act. (2) The compounding of offences referred to in subregulation (1) shall be in accordance with the procedure prescribed in the Environmental Quality (Compounding of Offences) Rules 1978 [P.U. (A) 281/1978]. Revocation 17. The Environmental Quality (Scheduled Wastes) Regulations 1989 [P.U. (A) 139/1989] is hereby repealed as from the commencement of these Regulations. FIRST SCHEDULE (Regulation 2) SW 1 Metal and metal-bearing wastes SW 101 Waste containing arsenic or its compound SW 102 Waste of lead acid batteries in whole or crushed form SW 103 lithium Waste of batteries containing cadmium and nickel or mercury or SW 104 Dust, slag, dross or ash containing arsenic, mercury, lead, cadmium, chromium, nickel, copper, vanadium, beryllium, antimony, tellurium, thallium or selenium excluding slag from iron and steel factory SW 105 Galvanic sludges SW 106 Residues from recovery of acid pickling liquor 94 SW 107 Slags from copper processing for further processing or refining containing arsenic, lead or cadmium SW 108 Leaching residues from zinc processing in dust and sludges form SW 109 Waste containing mercury or its compound SW 110 Waste from electrical and electronic assemblies containing components such as accumulators, mercury-switches, glass from cathode-ray tubes and other activated glass or polychlorinated biphenyl-capacitors, or contaminated with cadmium, mercury, lead, nickel, chromium, copper, lithium, silver, manganese or polychlorinated biphenyl SW 2 Wastes containing principally inorganic constituents which may contain metals and organic materials SW 201 Asbestos wastes in sludges, dust or fibre forms SW 202 Waste catalysts SW 203 Immobilized scheduled wastes including encapsulated, solidified or stabilized sludges SW 204 Sludges containing one or several metals including chromium, copper, nickel, zinc, lead, cadmium, aluminium, tin, vanadium and beryllium SW 205 Waste gypsum arising from chemical industry or power plant SW 206 Spent inorganic acids SW 207 Sludges containing fluoride SW 3 chemically fixed, Wastes containing principally organic constituents which may contain metals and inorganic materials SW 301 Spent organic acids with pH less or equal to 2 which are corrosive or hazardous SW 302 Flux waste containing mixture of organic acids, solvents or compounds of ammonium chloride SW 303 SW 304 Adhesive or glue waste containing organic solvents excluding solid polymeric materials Press cake from pretreatment of glycerol soap lye SW 305 Spent lubricating oil 95 SW 306 Spent hydraulic oil SW 307 Spent mineral oil-water emulsion SW 308 Oil tanker sludges SW 309 Oil-water mixture such as ballast water SW 310 Sludge from mineral oil storage tank SW 311 Waste oil or oily sludge SW 312 Oily residue from automotive workshop, service station, oil or grease interceptor SW 313 Oil contaminated earth from re-refining of used lubricating oil SW 314 Oil or sludge from oil refinery plant maintenance operation SW 315 Tar or tarry residues from oil refinery or petrochemical plant SW 316 Acid sludge SW 317 Spent organometallic compounds including tetraethyl lead, tetramethyl lead and organotin compounds SW 318 Waste, substances and articles containing or contaminated with polychlorinated biphenyls (PCB) or polychlorinated triphenyls (PCT) SW 319 Waste of phenols or phenol compounds including chlorophenol in the form of liquids or sludges SW 320 Waste containing formaldehyde SW 321 Rubber or latex wastes or sludge containing organic solvents or heavy metals SW 322 SW 323 Waste of non-halogenated organic solvents Waste of halogenated organic solvents SW 324 Waste of halogenated or unhalogenated non-aqueous distillation residues arising from organic solvents recovery process SW 325 Uncured resin waste containing organic solvents or heavy metals including epoxy resin and phenolic resin SW 326 Waste of organic phosphorus compound 96 SW 327 Waste of thermal fluids (heat transfer) such as ethylene glycol SW 4 Wastes which may contain either inorganic or organic constituents SW 401 Spent alkalis containing heavy metals SW 402 Spent alkalis with pH more or equal to 11.5 which are corrosive or hazardous SW 403 Discarded drugs containing psychotropic substances or containing substances that are toxic, harmful, carcinogenic, mutagenic or teratogenic SW 404 Pathogenic wastes, clinical wastes or quarantined materials SW 405 Waste arising from pharmaceutical product SW 406 Clinker, slag and ashes from scheduled wastes incinerator SW 407 Waste containing dioxins or furans SW 408 Contaminated soil, debris or matter resulting from cleaning-up of a spill of chemical, mineral oil or scheduled wastes SW 409 Disposed containers, bags or equipment contaminated with chemicals, pesticides, mineral oil or scheduled wastes SW 410 Rags, plastics, papers or filters contaminated with scheduled wastes SW 411 Spent activated carbon excluding carbon from the treatment of potable water and processes of the food industry and vitamin production SW 412 Sludges containing cyanide SW 413 Spent salt containing cyanide SW 414 Spent aqueous alkaline solution containing cyanide SW 415 Spent quenching oils containing cyanides SW 416 Sludges of inks, paints, pigments, lacquer, dye or varnish SW 417 Waste of inks, paints, pigments, lacquer, dye or varnish the preparation and production of 97 SW 418 Discarded or off-specification inks, paints, pigments, lacquer, dye or varnish products containing organic solvent SW 419 Spent di-isocyanates and residues of isocyanate compounds excluding solid polymeric material from foam manufacturing process SW 420 Leachate from scheduled waste landfill SW 421 A mixture of scheduled wastes SW 422 A mixture of scheduled and non-scheduled wastes SW 423 Spent processing solution, discarded photographic chemicals or discarded photographic wastes SW 424 Spent oxidizing agent SW 425 Wastes from the production, formulation, trade or use of pesticides, herbicides or biocides SW 426 Off-specification products from the production, formulation, trade or use of pesticides, herbicides or biocides SW 427 Mineral sludges including calcium hydroxide sludges, phosphating sludges, calcium sulphite sludges and carbonates sludges SW 428 Wastes from wood preserving operation using inorganic salts containing copper, chromium or arsenic of fluoride compounds or using compound containing chlorinated phenol or creosote SW 429 Chemicals that are discarded or off-specification SW 430 Obsolete laboratory chemicals SW 431 Waste from manufacturing or processing or use of explosives SW 432 Waste containing, consisting of or contaminated with, peroxides SW 5 Other wastes SW 501 Any residues from treatment or recovery of scheduled wastes SECOND SCHEDULE (Regulation 3) ENVIRONMENTAL QUALITY ACT 1974 ENVIRONMENTAL QUALITY (SCHEDULED WASTES) 98 REGULATIONS 2005 NOTIFICATION OF SCHEDULED WASTES (Two copies to be completed) For office use only File Reference No:………………………… Waste Generator Code: State Code: 1. IDENTIFICATION (i) Name and Address of Premise: ……………………………………………………….……………… …………….………………………………………………………… ………………………………………………….…..……………… ……………………………………………………………………… …………………………………………………………… Tel. No: …………………… Fax No: …………………. Telex No: …..………… (ii) Owner of Premise: ………………………………………………………………. Designation: .……………………………………………………………………… . 2. PRODUCTION DATA (i) List of raw materials/chemicals and quantities used per month* Raw Material/Chemicals 3. Quantity (Metric Tonnes) WASTE DATA Scheduled wastes generated per month** Waste Category Waste Source1 Name of Waste Waste Component2 Quantity (Tonnes/Month)3 99 Code Note: 1 Unit Operation in the process/plant Name the elements, compound or material 3 Guide to conversion (only data in metric tonnes/month is acceptable) * Use additional sheet if required ** Estimates 2 I certify that the information provided is true and correct to the best of my knowledge. …………………………… ………….. Signature of Reporting Officer *** Name: ………………………………….. Designation: …………………………… Date: ……………………………………. Note: *** Reporting officer refers to the person handling scheduled wastes. THIRD SCHEDULE (Regulation 10) 100 LABELLING REQUIREMENT FOR SCHEDULED WASTES EXPLOSIVE SUBSTANCES (WASTE) Symbol (exploding bomb): black; Background: light orange Label 1 INFLAMMABLE LIQUIDS (WASTE) Symbol (flame): black or white; Background: red Label 2 101 INFLAMMABLE SOLIDS (WASTE) Symbol (flame): black; Background: white with vertical red stripes Label 3 SOLID: SPONTANEOUSLY COMBUSTIBLE (WASTE) Substance liable to spontaneous combustion Symbol (flame): black; Background: upper half white, lower half red Label 4 SOLID: DANGEROUS WHEN WET (WASTE) Substances which, if in contact with water, emit inflammable gases Symbol (flame): black or white; Background: blue Label 5 102 OXIDIZING SUBSTANCES (WASTE) Symbol (flame over circle): black; Background: yellow Label 6 ORGANIC PEROXIDES (WASTE) Symbol (flame over circle): black; Background: yellow Label 7 103 TOXIC SUBSTANCES (WASTE) Poisonous (toxic) substances Symbol (skull over crossbones): black; Background: white Label 8 INFECTIOUS SUBSTANCES (WASTE) Symbol (three crescents superimposed on a circle): black; Background: white Label 9 CORROSIVE SUBSTANCES (WASTE) Symbol (liquids spilling from two glass vessels and attacking a hand and a metal): black; Background: upper half white, lower half black Label 10 104 MIXTURE OF MISCELLANEOUS DANGEROUS SUBSTANCES (WASTE) Symbol (nil); Background: white with upper half vertical black stripes Label 11 PARTICULARS OF LABELS 1. The label shall be a square set at an angle of 45 degrees. The dimension of the label shall not be less than 10 cm by 10 cm except where the size of the container or package warrants for a label of smaller size. 2. The colours used on the labels 1 to 11 shall be in accordance with British Standard BS 381 C, “Colours for specific purposes”. Colour French blue .. Canary yellow .. Signal red .. Light orange .. Reference No. .. .. .. .. .. .. .. .. 166 309 537 557 3. The labels shall be divided into halves, the upper half of the label shall be reserved for the pictorial symbol and the lower half for text printed in block capitals. 4. The text shall be printed in black on all labels except when the background of the label is black, red or blue, the text shall be in white. 5. The labels may be of the following types: (a) stick-on; (b) metal plates; or (c) stencilled or printed on the container or package. 105 6. All labels shall be able to withstand open weather exposure without a substantial reduction in effectiveness. 7. Label shall be placed on a background of contrasting colour. 8. In the case of waste capable of causing two or more hazards, all the hazards must be clearly identified and the waste shall be labelled accordingly. FOURTH SCHEDULE (Regulation 2) SCHEDULED WASTES OF POTENTIAL INCOMPATIBILITY The mixing of a waste in Group A with a waste in Group B may have the following potential consequences: Group 1-A Alkaline caustic liquids Alkaline cleaner Alkaline corrosive liquid Caustic wastewater Lime sludge and other corrosive corrosive acid alkalies Group 1-B Acid sludge Chemical cleaners Electrolyte, acid Etching acid, liquid or solvent Pickling liquor and other Spent acid Spent mixed acid Potential consequences: Heat generation, violent reaction. Group 2-A Asbestos Beryllium Unrinsed pesticide containers Pesticides Group 2-B Solvents Explosives Petroleum Oil and other flammable wastes Potential consequences: Release of toxic substances in case of fire or explosion. Group 3-A Aluminium Beryllium Calcium Lithium Group 3-B Any waste in Group 1-A or 1-B 106 Magnesium Potassium Sodium Zinc powder and other reactive metals and metal hydrides Potential consequences: Fire or explosion; generation of flammable hydrogen gas. Group 4-A Alcohols 1-A or 1-B Group 4-B Any concentrated waste in Group Calcium Lithium Metal hydrides Potassium Sodium Water reactive wastes Potential consequences: Fire, explosion or heat generation; generation of flammable toxic gases. Group 5-A Alcohols Group 5-B Concentrated Group 1-A or 1-B wastes Aldehydes Halogenated hydrocarbons Nitrated hydrocarbons and other reactive organic compounds and solvents Unsaturated hydrocarbons Group 3A wastes Potential consequences: Fire, explosion or violent reaction. Group 6-A Spent cyanide and sulphide solution Group 6-B Group 1-B wastes Potential consequences: Generation of toxic hydrogen cyanide or hydrogen sulphide gas. Group 7-A Group 7-B 107 Chlorates and other strong oxidizers Chlorites Chromic acid Hypochlorites Organic acids Group 2-B wastes Group 3-B wastes Group 5-A wastes and other Nitrates combustible wastes Nitric acid Perchlorates Permanganates Peroxides flammable and Potential consequences: Fire, explosion or violent reaction. FIFTH SCHEDULE (Regulation 11) ENVIRONMENTAL QUALITY ACT 1974 ENVIRONMENTAL QUALITY (SCHEDULED WASTES) REGULATIONS 2005 INVENTORY OF SCHEDULED WASTES AS AT: …………………..………………… * aDate * Waste Category Code * Name of Waste *Quantity Generated (Metric Tonnes) Methodb *Waste Handling Quantity in Metric Tonnes Placec 108 Note: * a b c Inventory of the current generation of scheduled wastes Date when the scheduled wastes are first generated Stored, processed, recovered for materials or product from such scheduled wastes, incinerated, exchanged or other methods (specify) Give name and address of the facility I hereby declare that all information given in this form is to the best of my knowledge and belief true and correct in all respect. Name of Reporting Officer: ……………………………………..……………………………….. Designation: …………………………..………………………………………………………….. Signature:………………………..………… Date:…………….………………………………… I.C. Number : ……………………………………………….. SIXTH SCHEDULE (Regulation 12) ENVIRONMENTAL QUALITY ACT 1974 ENVIRONMENTAL QUALITY (SCHEDULED WASTES) REGULATIONS 2005 CONSIGNMENT NOTE FOR SCHEDULED WASTES I WASTE GENERATOR For office use only Fail Reference No: …………………………… Waste Generator Code: State Code: 109 Name of Waste Generator: ………………………..…………………………...………………….. Address: …………………………………………………………………………...………… ……. Name of Responsible Person: .………………………………………………………..…………… Tel. No: …………………… Fax. No: ………………………. Telex No: ………………..…….. Name of Waste: …………………………………. Waste Category Code: Waste Component: ………………………………………………………………………………… Waste Origin: ……………………………………. Waste Origin Code: Type of Waste: Liquid Solid Sludge Waste Packaging: Pallet Container Canister 55 gallon Drum Other (Specify) ………………………………… Quantity: Metric Tonnes And If Possible m3 Cost of Treatment and Disposal RM……………../Metric Tonne Name and Address of Final Destination: ……………………………………………………………………………………… …………… Delivery Date: ………………………………… Person: Delivery Time:………………………………… ……………………………………… II CONTRACTOR Signature of Responsible 110 For office use only Contractor Code: State Code: Name of Contractor: …………………………...………………………………………………….. Address: …...………………………………………………………………………………… ……. Name of Responsible Person:……………………………………………………………………… Tel. No: ………………….………… Fax. No: …….………… Telex No: .……………………. Vehicle Registration No: ………………………………………………………………….……….. Name of Driver: …………………………………………………………………………………… Temporary Storage: No Yes, Address: …………….………………………………… Date Received: …………………………… Signature of Driver: ………………….…………… Time Received : ………………………….. III STORAGE/TREATMENT/ RECOVERY/DISPOSAL/ FACILITY OPERATOR For office use only Facility Code: State Code: 111 Name of Facility: ..………………………………….…..………………………………………… Address of Facility: …………………………………………..…………………………………… Name of Responsible Person: ……………………………….…………………………………… Tel. No: .………………………. Fax. No: …..……………… Telex No: ………………………. Type of Operation: Storage Landfill Regrouping Physical/Chemical Treatment …………………. Recovery Landfill Incinerator Others (specify) …….…………… Quantity of Waste and If Possible Received: m3 Metric Tonnes Date Received: …………………………………… Signature: ………………………………... Time Received:………………………………… SEVENTH SCHEDULE (Regulation 13) INFORMATION A. Properties 1. Category of waste - 2. according to the First Schedule Origin Secure 112 - state from which process, activity, occurrence, etc. the waste is generated. 3. Physical properties of waste Flashpoint o C - Boiling point o C - Consistency at room temperature (gas, liquid, sludge, solid) - Vapours lighter/heavier than air - Solubility in water - Waste lighter/heavier than water - 4. B. Risks - by inhalation - by oral intake - by dermal contact Handling of waste 1. Personal protection equipment - 2. gloves, goggles, face shield etc. Procedures/Precautions in handling, packaging, transporting and storage 3. Appropriate label - 4. C. labels for the containers Recommended method of disposal Precautions in case of spill or accidental discharge causing personal injury 1. 2. In case of inhalation of fumes or oral intake - Symptoms of intoxication - Appropriate first aid - Guidelines for the physician In case of dermal contact or contact with eyes - Symptoms of intoxication - Appropriate first aid - Guideline for the physician 113 D. Steps to be taken in case of spill or accidental discharge causing material damage arising from – 1. Spill on floor, soil, road etc. 2. Spill into water 3. Fire 4. Explosion Made 2005 [AS(S)91/110/919/014; PN(PU2)280/VII] DATO’ SRI HAJI ADENAN HAJI SATEM Minister of Natural Resources and the Environment