i BEACH RESPONSE DUE TO THE PRESSURE EQUALIZATION MODULES (PEM) SYSTEM MOHD SHAHRIZAL BIN AB RAZAK A project report submitted in fulfillment of the requirements for the award of the degree of Master of Engineering (Civil-Hydraulics and Hydrology) Faculty of Civil Engineering Universiti Teknologi Malaysia JUNE 2009 iii Especially dedicated to my beloved family, fellow friends and to everyone who involves in my life, you will always be in my heart…………………….. iv ACKNOWLEDGEMENT I would like to convey my sincerest thanks to my supervisor Professor Hadibah Binti Ismail for her dedicated guidance, valuable assistance and endless encouragement throughout the accomplishment of this project. I am grateful to the staff of Department of Irrigation and Drainage Malaysia who had been very helpful in providing assistance throughout the work. Special thanks are also extended to Director of Department of Irrigation and Drainage, Malaysia for his permission to allow the accessibility of data for this project. My thanks are also extended to other lecturers for their advice whether directly or indirectly in improving my Master Project. Also not forgetting my friends especially Mr. Bahman Esfandiar Jahromi, Miss Hasmida Hamza, and Mr. Abdul Haslim Shukor Lim for their guidance in helping me to clarify any problems related to this study. I am indebted to my employer Universiti Putra Malaysia and Ministry of Higher Education for providing me the opportunity and the financial means to pursue this study. Last but not least, my deepest and eternal gratitude to all those who had helped directly or indirectly in my project. v ABSTRACT Coastal erosion is a significant problem with dramatic effects on the coastline. There is an urgent need to introduce new and cost-effective measures that can mitigate the impacts on the shoreline. This study has been initiated to investigate the response of the beach at Teluk Cempedak due to the beach nourishment and Pressure Equalization Modules (PEM) system. The objectives of this study are the determination of closure depth and effectiveness of the system in treating the erosion process. The depth of closure was examined using both data from a series of beach profile surveys and from empirical formulae. The widely accepted Fixed Depth Change (FDC) method was explored and the hc before and after the installation of PEM system was investigated. The research found that multiple closure points can occur along the profile lines. The closure depth after the installation of PEM system was found to be deeper and the closure point is further seaward at the southern part of the beach. The Hellemeier‟s equation over predict hc by 76 %, however it reveals that the equation is still robust in determining an upper limit of hc. The simplified equation was developed at Teluk Cempedak beach in predicting closure depth and can be equated to 0.98 times H0.137. From the survey data, it is found that after three years, the total sand volume and beach elevation are significantly higher in PEM areas. Generally, the result presented indicates the decreasing value of rate of erosion. Thus it revealed that PEM system is able to stimulate accretion of sand and yet slow down the erosion process. However, based on the sand volume distribution pattern, after three years, it is obviously seen that the accretion of sand occurring at the northern part while erosion process is taking place in the southern part of the beach. Based on the distribution pattern of bed elevation over the chainage, overall, the upper part of the beach is convex unlike earlier i.e before the installation of PEM system, where the beach was low and concave. This phenomena indicates that the system contribute to a significant accretion of sand and thus created a higher beach level at about 10 m to 55 m towards the sea. However, this trend only can be seen at a certain chainage. The PEM efficiency in terms of increment in bed elevation can only be observed at CH 400 till CH 800 while at CH 900 towards the south, the efficiency is decreasing. This shows that the accretion of sand is only occurring at the northern part and the beach is eroding at the southern part. Therefore, based on the available four years record of data, there is a certain part of the beach benefiting from the PEM system. However, some parts are still experiencing the erosion process. vi ABSTRAK Hakisan pantai merupakan masalah ketara yang memberi kesan kepada perairan pantai. Oleh itu, terdapat tindakan segera untuk memperkenalkan kaedah baru dan lebih menjimatkan yang mana dapat mengatasi masalah hakisan pantai ini. Kajian ini telah dijalankan untuk menyiasat tindak balas pantai terhadap penambakan pantai (beach nourishment) dan sistem Pressure Equalization Modules (PEM). Objektif utama kajian ini adalah penentuan kedalaman tertutup (closure depth) dan keberkesanan sistem dalam merawat hakisan pantai. Kedalaman tertutup telah dikenalpasti menggunakan kedua-dua data iaitu data ukur bersiri dan formula empirikal. Kaedah Perubahan Kedalaman Tetap telah digunakan dan kedalaman tertutup sebelum dan selepas pemasangan sistem PEM telah disiasat. Kajian menunjukkan bahawa beberapa kedalaman tertutup boleh berlaku di sepanjang garis ukur. Kedalaman tertutup selepas pemasangan sistem PEM didapati lebih dalam dan lokasi titik kedalaman tertutup jauh menghala ke tengah laut khususnya di bahagian selatan pantai. Persamaan Hellemeier didapati lebih tinggi dengan lebihan purata 76 % bagaimanapun mendedahkan bahawa persamaan ini masih kukuh bagi menentukan nilai had teratas untuk hc. Persamaan ringkas telah dicipta bagi pantai Teluk Cempedak dalam menentukan kedalaman tertutup dan boleh disamakan dengan 0.98 kali ketinggian ombak H0.137. Daripada data ukur juga, jumlah isipadu pasir and ketinggian pantai didapati lebih tinggi di kawasan pemasangan sistem PEM selepas tiga tahun pemantauan dijalankan. Umumnya, hasil keputusan menunjukkan bahawa kadar hakisan telah menurun. Ini menunjukkan bahawa sistem PEM berupaya mengumpul pasir sekaligus melambatkan proses hakisan. Walaubagaimanapun, berdasarkan kepada jumlah pengagihan isipadu pasir, jelas menunjukkan bahawa pengumpulan pasir hanya terjadi di bahagian utara pantai manakala proses hakisan masih berlaku di bahagian selatan pantai. Berdasarkan kepada bentuk pengagihan bagi ketinggian pantai pula, secara keseluruhannya, bahagian atas pantai lebih cembung berbanding sebelumnya yang mana ianya lebih cekung. Fenomena ini menunjukkan bahawa sistem PEM menyumbang kepada pengumpulan pasir seterusnya meningkatkan ketinggian pantai pada jarak 10 m hingga 55 m menghala ke arah laut. Bagaimanapun, keadaan ini hanya berlaku di kawasan-kawasan tertentu sahaja. Keberkesanan PEM dari segi peningkatan ketinggian pantai hanya berlaku di CH 400 hingga CH 800 sementara di CH 900 menghala ke selatan pantai pula menunjukkan penurunan peratus keberkesanan. vii Ini menunjukkan bahawa pengumpulan pasir terjadi di bahagian utara pantai manakala proses hakisan masih berlaku di bahagian selatan pantai. Oleh yang demikian, berdasarkan kepada data ukur bagi 4 tahun kerja pemantauan, terdapat sebahagian kawasan pantai yang mendatangkan manfaat daripada sistem PEM manakala sebahagiannya lagi masih mengalami proses hakisan. viii TABLE OF CONTENTS TITLE i CONFESSION ii DEDICATION iii ACKNOWLEDGEMENT iv ABSTRACT v ABSTRAK vi TABLE OF CONTENTS viii LIST OF TABLES xv LIST OF FIGURES xvi LIST OF ABBREVIATIONS xx LIST OF SYMBOLS xxii LIST OF APPENDIX xxiv CHAPTER TITLE PAGE I INTRODUCTION 1 1.1 Introduction 1 1.2 Statement of Problem 4 1.3 Objectives of Study 6 ix 1.4 Scope of Study 7 1.4.1 Study Area 7 1.4.2 Data Collection and Analysis 8 1.4.3 Determination of Closure Depth 9 Terminology Used in This Study 9 1.5.1 Beach Nourishment 9 1.5.2 Closure Depth 10 1.5.3 Equilibrium Profile 10 1.5.4 Pressure Equalization Modules System 11 Importance of Study 11 LITERATURE REVIEW 13 2.1 13 1.5 1.6 II Introduction PART A: BEACH NOURISHMENT/ DEPTH OF CLOSURE/ BEACH EQUILIBRIUM PROFILE 2.2 Beach Nourishment 14 2.2.1 Definition(s) of Beach Nourishment from Different Perspectives 15 2.2.2 Advantages and Disadvantages of Beach 2.3 2.4 Nourishment Activities 16 Identification of the Depth of Closure 18 2.3.1 Estimation of the Depth of Closure 23 2.3.2 Depth of Closure and Vertical Datum 24 Previous Case Study- Determination of Depth of Closure 24 x 2.5 2.4.1 Ocean City, Maryland 25 2.4.2 Pria de Fero, Algarve, South Portugal 25 2.4.3 Kelantan Coast, Malaysia 26 Equilibrium Beach Profile 27 PART B: PRESSURE EQUALIZATION MODULE (PEM) SYSTEM 2.6 2.7 III Pressure Equalization Module (PEM) System Application Concept 30 2.6.1 The Advantage of PEM System 32 Design Criteria of Pressure Equalization Module (PEM) System at Teluk Cempedak Beach, Kuantan 33 2.7.1 System Installation 35 RESEARCH METHODOLOGY 39 3.1 Introduction 39 3.2 Study Area 40 3.3 Data Set 43 3.3.1 Beach Profile Survey 43 3.3.2 Winds and Waves Data 44 3.3.3 Tidal Data 44 3.3.4 Bed Sediment Data 45 Measurement Techniques 47 3.4.1 Beach Profile Measurement 47 3.4.2 Historical Shoreline Changes 48 3.4 xi 3.5 3.4.3 Tidal Data Measurement 49 3.4.4 Aerial Photograph 49 Data Analysis 50 3.5.1 Determination of Depth of Closure from Beach Data Profile 50 3.5.2 Determination of Depth of Closure from Empirical Formula 3.6 IV 53 PEM Effectiveness Evaluation 53 DATA ANALYSIS AND RESULTS 56 4.1 Introduction 56 4.2 Description of Study Area 57 4.3 Data Set 58 4.3.1 Beach Profile Survey 59 4.3.2 Wave Data Analysis 62 4.3.3 Tidal Height Information 64 4.3.4 Sediment Properties 65 4.4 4.5 Determination of Depth of Closure from Beach Profile Survey 69 Depth of Closure for Pre-Project Condition (2003) 69 4.5.1 Closure Depth at CH 700 and CH 1400 69 4.5.2 Closure Depth at CH 100 70 4.5.3 Closure Depth at CH 200 71 4.5.4 Closure Depth at CH 300 72 4.5.5 Closure Depth at CH 400 73 4.5.6 Closure Depth at CH 500 74 xii 4.5.7 Closure Depth at CH 600 75 4.5.8 Closure Depth at CH 800 76 4.5.9 Closure Depth at CH 900 77 4.5.10 Closure Depth at CH 1000 78 4.5.11 Closure Depth at CH 1100 79 4.5.12 Closure Depth at CH 1200 80 4.5.13 Closure Depth at CH 1300 81 4.6 Summary of Depth of Closure for Pre-Project Condition 82 4.7 Depth of Closure for Post-Project Condition 83 4.8 2005 Beach Profile 83 4.8.1 Closure Depth at CH 100 84 4.8.2 Closure Depth at CH 200 85 4.8.3 Closure Depth at CH 300 86 4.8.4 Closure Depth at CH 400 87 4.8.5 Closure Depth at CH 500 88 4.8.6 Closure Depth at CH 600 89 4.8.7 Closure Depth at CH 700 90 4.8.8 Closure Depth at CH 800 91 4.8.9 Closure Depth at CH 900 92 4.8.10 Closure Depth at CH 1000 93 4.8.11 Closure Depth at CH 1100 94 4.8.12 Closure Depth at CH 1200 95 4.8.13 Closure Depth at CH 1300 96 4.8.14 Closure Depth at CH 1400 97 4.9 4.10 Summary of Depth of Closure for 2005 Post-Project Condition 98 2006 Beach Profile 99 xiii 4.11 4.12 4.13 4.10.1 Closure Depth at CH 100 99 4.10.2 Closure Depth at CH 200 100 4.10.3 Closure Depth at CH 300 101 4.10.4 Closure Depth at CH 400 102 4.10.5 Closure Depth at CH 500 until CH 800 103 4.10.6 Closure Depth at CH 900 105 4.10.7 Closure Depth at CH 1000 106 4.10.8 Closure Depth at CH 1100 and CH 1200 107 4.10.9 Closure Depth at CH 1300 109 4.10.10Closure Depth at CH 1400 110 Summary of Depth of Closure for 2006 Post-Project Condition 111 2007 Beach Profile 112 4.12.1 Closure Depth at CH 100 112 4.12.2 Closure Depth at CH 200 113 4.12.3 Closure Depth at CH 300 114 4.12.4 Closure Depth at CH 500 115 4.12.5 Closure Depth at CH 600 116 4.12.6 Closure Depth at CH 700 117 4.12.7 Closure Depth at CH 800 118 4.12.8 Closure Depth at CH 900 119 4.12.9 Closure Depth at CH 1000 120 4.12.10Closure Depth at CH 1100 121 4.12.11Closure Depth at CH 1200 122 4.12.12Closure Depth at CH 1300 123 4.12.13Closure Depth at CH 1400 124 Summary of Depth of Closure for xiv 2007 Post-Project Condition 4.14 Comparison of hc between Pre-Project Condition and Post-Project Condition 4.15 4.16 V 125 126 Estimation of Predictive Closure Depth by Hallemeier‟s Equation 128 PEM Effectiveness Evaluation 130 4.16.1 Total Sand Volume Changes 130 4.16.2 Beach Level Changes 136 4.16.3 Distribution Pattern of Beach Level Changes 137 4.16.4 PEM Efficiency 139 CONCLUSIONS AND RECOMMENDATIONS 143 5.1 Introduction 143 5.2 Recommendation 147 5.2.1 Criteria of Limit Line 147 5.2.2 Standard Deviation Depth Change (SDDC) Method 148 5.2.3 Profile Survey 148 5.2.4 Predictive Formula for Each Chainage 149 REFERENCES 150 APPENDICES 154 xv LIST OF TABLES NO. TITLE PAGE 1.1 List of Coastal Erosion Areas in Malaysia 5 4.1 Data Available for This Study 58 4.2(a) Centerline Coordinates of Selected Survey Data Set and Its Correspondence Depth (Before Installation of PEM System) 4.2(b) 61 Centerline Coordinates of Selected Survey Data Set and Its Correspondence Depth (After Installation of PEM System) 61 4.3 Tidal Level Along Study Shoreline (meter, LSD) 65 4.4 Summary of Design Size Ranges for Borrow Sand 67 4.5(a) Sand Size Analysis (upper beach face for pre-project condition) 68 4.5(b) Sand Size Analysis (lower beach face for pre-project condition) 68 4.6 Closure Depth for 2003 Pre-Project Profile 82 4.7 Closure Depth for 2005 Post-Project Profile 98 4.8 Closure Depth for 2006 Post-Project Profile 111 4.9 Closure Depth for 2007 Post-Project Profile 125 4.10 hc Simplified Equation Compared with Effective hc 2007 128 4.11 Total Sand Volume and Sand Gain or Loss at the Study Area 132 4.12 PEM Efficiency 140 xvi LIST OF FIGURES NO. TITLE PAGE 1.1 The Location of Study Area at Teluk Cempedak Beach, Kuantan 7 2.1 Schematic Diagram of the Depth of Beach Profile Closure 19 2.2 Definition Sketch of the Closure Depth 20 2.3 Pressure Equalization Module – schematization 30 2.4 PEM Function Dewatering the Beach 32 2.5 Design of Pressure Equalization Module Pipes 34 2.6 Preparation for PEM Installation on 9th July 2004 37 2.7 Preparation of borehole for PEM Installation on 9th July 2004 37 2.8 Placement of PEM Pipe 38 2.9 Exposed PEM Pipe at Chainage 800 38 3.1 Site Study Area 40 3.2 The Beach Slope is Steeper Due to Erosion Problem 41 3.3 The Beach is Narrower and Recreational Activities are Limited for Beach Visitor 41 3.4(a) Beach Condition Before the Installation of PEM System 42 3.4(b) Beach Condition After the Installation of PEM System 42 3.5 Location of Sediment Samples and Sand Source 46 3.6 The Algorithm of Closure Depth Determination 52 xvii 3.7 Research Methodology Chart 55 4.1 Profile Line at Study Area 60 4.2 Histogram of Design Wave Height 62 4.3 H0.137 Wave from SSMO Wave Data (1949-1983) 63 4.4 Relationship between Wave Height and Wave Period 64 4.5 Plan View for Distribution of Design Sand Size 67 4.6 Closure Depth (hc) at CH 100 for 2003 Pre- Project Profile 70 4.7 Closure Depth (hc) at CH 200 for 2003 Pre- Project Profile 71 4.8 Closure Depth (hc) at CH 300 for 2003 Pre- Project Profile 72 4.9 Closure Depth (hc) at CH 400 for 2003 Pre- Project Profile 73 4.10 Closure Depth (hc) at CH 500 for 2003 Pre- Project Profile 74 4.11 Closure Depth (hc) at CH 600 for 2003 Pre- Project Profile 75 4.12 Closure Depth (hc) at CH 800 for 2003 Pre- Project Profile 76 4.13 Closure Depth (hc) at CH 900 for 2003 Pre- Project Profile 77 4.14 Closure Depth (hc) at CH 1000 for 2003 Pre- Project Profile 78 4.15 Closure Depth (hc) at CH 1100 for 2003 Pre- Project Profile 79 4.16 Closure Depth (hc) at CH 1200 for 2003 Pre- Project Profile 80 4.17 Closure Depth (hc) at CH 1300 for 2003 Pre- Project Profile 81 4.18 Closure Depth (hc) at CH 100 for 2005 Post- Project Profile 82 4.19 Closure Depth (hc) at CH 200 for 2005 Post - Project Profile 83 4.20 Closure Depth (hc) at CH 300 for 2005 Post - Project Profile 86 4.21 Closure Depth (hc) at CH 400 for 2005 Post - Project Profile 87 4.22 Closure Depth (hc) at CH 500 for 2005 Post - Project Profile 88 4.23 Closure Depth (hc) at CH 600 for 2005 Post - Project Profile 89 4.24 Closure Depth (hc) at CH 700 for 2005 Post - Project Profile 90 4.25 Closure Depth (hc) at CH 800 for 2005 Post - Project Profile 91 4.26 Closure Depth (hc) at CH 900 for 2005 Post - Project Profile 92 xviii 4.27 Closure Depth (hc) at CH 1000 for 2005 Post - Project Profile 93 4.28 Closure Depth (hc) at CH 1100 for 2005 Post - Project Profile 94 4.29 Closure Depth (hc) at CH 1200 for 2005 Post - Project Profile 95 4.30 Closure Depth (hc) at CH 1300 for 2005 Post - Project Profile 96 4.31 Closure Depth (hc) at CH 1400 for 2005 Post - Project Profile 97 4.32 Closure Depth (hc) at CH 100 for 2006 Post - Project Profile 99 4.33 Closure Depth (hc) at CH 200 for 2006 Post - Project Profile 100 4.34 Closure Depth (hc) at CH 300 for 2006 Post - Project Profile 101 4.35 Closure Depth (hc) at CH 400 for 2006 Post - Project Profile 102 4.36 Closure Depth (hc) at CH 500 for 2006 Post - Project Profile 103 4.37 Closure Depth (hc) at CH 600 for 2006 Post - Project Profile 104 4.38 Closure Depth (hc) at CH 700 for 2006 Post - Project Profile 104 4.39 Closure Depth (hc) at CH 800 for 2006 Post - Project Profile 105 4.40 Closure Depth (hc) at CH 900 for 2006 Post - Project Profile 106 4.41 Closure Depth (hc) at CH 1000 for 2006 Post - Project Profile 107 4.42 Closure Depth (hc) at CH 1100 for 2006 Post - Project Profile 108 4.43 Closure Depth (hc) at CH 1200 for 2006 Post - Project Profile 108 4.44 Closure Depth (hc) at CH 1300 for 2006 Post - Project Profile 109 4.45 Closure Depth (hc) at CH 1400 for 2006 Post - Project Profile 110 4.46 Closure Depth (hc) at CH 100 for 2007 Post - Project Profile 112 4.47 Closure Depth (hc) at CH 200 for 2007 Post - Project Profile 113 4.48 Closure Depth (hc) at CH 300 for 2007 Post - Project Profile 114 4.49 Closure Depth (hc) at CH 500 for 2007 Post - Project Profile 115 4.50 Closure Depth (hc) at CH 600 for 2007 Post - Project Profile 116 4.51 Closure Depth (hc) at CH 700 for 2007 Post - Project Profile 117 4.52 Closure Depth (hc) at CH 800 for 2007 Post - Project Profile 118 4.53 Closure Depth (hc) at CH 900 for 2007 Post - Project Profile 119 xix 4.54 Closure Depth (hc) at CH 1000 for 2007 Post - Project Profile 120 4.55 Closure Depth (hc) at CH 1100 for 2007 Post - Project Profile 121 4.56 Closure Depth (hc) at CH 1200 for 2007 Post - Project Profile 122 4.57 Closure Depth (hc) at CH 1300 for 2007 Post - Project Profile 123 4.58 Closure Depth (hc) at CH 1400 for 2007 Post - Project Profile 124 4.59 Closure Depth at Teluk Cempedak beach, Kuantan 127 4.60 Closure Point at Teluk Cempedak beach, Kuantan 127 4.61 Total Sand Volume (m3) 131 4.62 Sand Gain and Loss for Year 2005 134 4.63 Sand Gain and Loss for Year 2006 134 4.64 Sand Gain and Loss for Year 2007 135 4.65 Sand Volume Distribution Pattern 135 4.66 Average Beach Level 70 m wide 136 4.67 Beach Level at CH 400 and CH 500 137 4.68 Beach Level at CH 600 and CH 700 138 4.69 Beach Level at CH 800 and CH 900 138 4.70 Beach Level at CH 1000 and CH 1100 138 4.71 Beach Level at CH 1200 and CH 1300 139 4.72 PEM Efficiency at CH 400 and CH 500 141 4.73 PEM Efficiency at CH 600 and CH 700 141 4.74 PEM Efficiency at CH 800 and CH 900 141 4.75 PEM Efficiency at CH 1000 and CH 1100 142 4.76 PEM Efficiency at CH 1200 and CH 1300 142 xx LIST OF ABBREVIATIONS CED Coastal Engineering Division CEM Coastal Engineering Manual CH Chainage cm centimeter DID Department of Irrigation and Drainage Malaysia EDM Electronic Distance Measuring FDC Fixed Depth Change hc Depth of Closure HAT Highest Astronomical Tide LAT Lowest Astronomical Tide LSD Land Survey Datum m meter mm millimeter MSL Mean Sea Level MHW Mean High Water MHHW Mean Higher High Water MLHW Mean Lower High Water MLW Mean Low Water MHLW Mean Higher Low Water xxi MLLW Mean Lower Low Water MMD Malaysian Meteorological Department MRCB Malaysia Resource Corporation Berhad NOS National Ocean Survey PEM Pressure Equalization Modules SDDC Standard Deviation Depth Change SSMO Synoptic Shipboard Meteorological Observation USGS U.S Geological Survey Quadrangles xxii LIST OF SYMBOLS A profile scale parameter with dimensions of length to the 1/3 power D16 size of material of which 16% is finer D50 size of material of which 50% is finer D84 size of material of which 84% is finer Dc/ h*/ hc closure depth g gravity h water depth at distance y from the shoreline hCi depth of closure, innershore; from profile survey hcm depth of closure, middleshore; from profile survey hco depth of closure, outershore; from profile survey He non breaking significant wave height that is exceeded 12 hour per t years or ( 100/730t)% of the time H0.137 significant wave height exceeded 12 hours in a year H/Hs annual mean significant wave height m fore shore slope of the beach profile t time Te wave period associated with He xxiii y equilibrium beach profile vb amplitude of the wave induced bottom velocity ρ mass densities of water ρs mass densities of sediment σH standard deviation xxiv LIST OF APPENDIX APPENDIX A TITLE PAGE Profile Surveys from the Coastline of Pantai Teluk Cempedak Kuantan 2003, 2005, 2006, and 2007 154 1 CHAPTER I INTRODUCTION 1.1 Introduction Land based activities and natural physical processes have resulted in significant modifications of the shorelines in many countries, with drastic effects on the coastal geomorphology as well as on the coastal infrastructures. There is an urgent need to introduce new and cost-effective measures that can mitigate the impacts on the shorelines. In many locations, coastal erosion is a significant problem with dramatic effects on the coastline. The impact on coast-near infrastructures and property can be massive. Until now the urgent need for coastal erosion protection, has forced society to 2 use costly solutions with bulky constructions and beach nourishment, where the dredging part of the process is very hostile to the marine environment. Coastal protection can generally be divided into hard engineering and soft engineering (Ghazali, 2005). Hard engineering structures such as revetments, seawalls, bulkheads and groynes are considered traditional erosion protection structures with distinct functions. These are typically constructed of quarry stones or concrete units. Seawalls and revetments are constructed parallel to the shoreline and form a barrier between waves and the coast. Whilst preventing any further loss of material landwards, waves reflected by the seawall causes scouring at the toe in front of the seawall and eventual lowering of the beach. Thus where recreational space is concerned, the use of seawalls and revetments are not beneficial in the long run as the end result is a deepening or steepening of the sea bed in front of the structure resulting in loss of beach space. The term „soft engineering‟ is normally used to describe methods that depart from hard protection structures that use quarry stones or concrete blocks as the main structural component. The use of sand either as a fill material placed directly on the eroding beach or encased within geotextiles are amongst the methods that qualify as soft engineering. In beach nourishment, loose sediments are imported and placed on the target beach to form a wider beach berm as a buffer for waves. The „new‟ beach will then continue to be shaped by the natural forces i.e. wind, wave and tidal currents, to an equilibrium shape. Beach nourishment is now common and is the preferred method of protecting or rehabilitating eroding recreational beaches (Ghazali, 2004). The construction process however involves dredging, transport and placement of sand in a marine environment which causes water quality problems, habitat displacement and stress to marine life. Beach nourishment is also considered semi-permanent and requires replenishment as time progresses. 3 Beach nourishment, also called artificial nourishment, replenishment, beach fill, and restoration, comprises the placement of large quantities of good quality sand within the near-shore system usually to address a continuing deficit of sand, manifested by shoreline recession (Dean, 2002). The term nourishment applies to both the initial placement of material and to later nourishments for the projects where multiple placements occur. The terms beach nourishment may be used to differentiate between material that is placed on the sub-aerial beach and its underwater extensions from profile nourishment or berm placement which involves the placement of material offshore with the anticipation that either the material will provide protection to the shore from erosion by reducing the effects of waves. SIC, Skagon Innovation Centre (Jakobsen, 2007) has invented an environmentally friendly coastal protection system. The SIC system is based on Pressure Equalization Modules (PEM). A long term and comprehensive test of the efficiency has been carried out on the west coast of Denmark. Furthermore, a three year scientific research programme was performed in year 2005. The obtained result shows that the system is far more efficient than conventional methods such as groins, breakwaters, and sand nourishment. Due to the well-known lee side erosion effect, groins and breakwaters create even greater erosion in adjacent coastal areas. Furthermore, Jakobsen reported that sand nourishment by dredging is in general terms a very expensive approach (about 130,000 USD/km/year in Denmark), but unfortunately, it is an inefficient solution since usually the sand will disappear during the first spring period. 4 1.2 Statement of Problem The evolution of the coast is produced by natural processes that occur on a broad time scale ranging from hours to millennia. Beach erosion is one such process that occurs when the losses of beach sediment exceed the gains. As this volume of sediment decreases, the beaches become narrower. When backed by fixed developments, beaches are unable to respond naturally to changes, resulting in a cessation of beach/dune interactions, instability of the fronting beach, and a reduction of sediment inputs into the sediment budget. In the absence of development, coastal erosion is not a hazard. The presence of large and expensive communities in the coastal zone creates the potential for major disasters resulting from erosion. Erosion is typically episodic, either with the shore recovering afterward or with the episodes being cumulative and leading to a progressive retreat of the shoreline and property losses. The erosional impact on properties depends on the width of the buffering beach and on the nature of the beach as defined by the morphodynamics model of Wright and Short (1983). Malaysia has about 4809 km of coastline. Of the 4809 km of coastline, about 1415 km is at present subject to erosion of various degree of severity (Annual Report DID, 2007). Along the coast, sediment is continuously being moved. When the rate of sediment entering and leaving the coast equals, the coast is said to be in dynamic equilibrium. Erosion occurs when, over a period of time, the volume of sediment transported out is greater than that transported into the coast. It follows that the reverse will result in accretion. The erosion process occurs continuously and as a result, the beach slowly retreats. This is normally indicated by the formation of beach scarp along the coast. Erosion may be amplified during monsoon period when high water levels, associated with the season, result in waves breaking directly against the scarp, causing loss of material. Though, some of this material might be returned to the shore by the 5 swells after the monsoon, the quantity returned is normally much less; hence the nett result is erosion. Control of coastal erosion has now become an important economic and social need. Table 1.0 shows the list of coastal erosion areas in Malaysia. From this table, it can be concluded that 73.40 % or 52.1 km of the total length of coastline in Pahang area has been eroded. To this end, the government is implementing a strategy to control the erosion problem. The government has spent about RM 15,400,000.00 to invest in a new system for control of coastal erosion called the Pressure Equalization Module (PEM). The system has been successfully installed at the Teluk Cempedak beach in Pahang and is the first coastal erosion project applying this method in Malaysia and Asia (Annual Report DID, 2004). Table 1.0: List of Coastal Erosion Areas in Malaysia Length of Coastline State (km) State Perlis Kedah Pulau Pinang Perak Selangor N.Sembilan Melaka Johor Pahang Terengganu Kelantan W.P Labuan Sarawak Sabah Total 20 148 152 230 213 58 73 492 271 244 71 59 1035 1743 4809 Length of Coastline Having Erosion Category 1 CRITICAL EROSION (km) Length Critically Eroded 4.4 31.4 42.4 28.3 63.5 3.9 15.6 28.9 12.4 20 5 2.5 17.3 12.8 288.4 6.0 % Category 2 Category 3 SIGNIFICANT ACCEPTABLE EROSION EROSION (km) (km) 3.7 2.2 19.7 18.8 22.3 7.7 15.1 50.3 5.2 10 9.5 3 22.3 3.5 193.3 4.0 % 6.4 6.9 1.1 93.1 66.1 12.9 6 155.6 37.6 122.4 37.6 25.1 9.6 279.2 932.8 19.4 % Total Length of Coastline Having Erosion (km) (%) 14.5 43.5 53.2 140.2 151.9 24.5 36.7 234.8 52.1 152.4 52.1 30.6 49.2 295.5 1,415 72.50 29.40 41.60 61.00 71.30 42.20 50.30 47.70 73.4 62.50 73.40 51.90 4.80 17.00 29.41 % Source: Annual Report, Department of Irrigation and Drainage, (DID) Malaysia (2007) 6 Based on the Detailed Design Report 2006, Teluk Cempedak beach has a history of erosion. The beach area has undergone slow and steady erosion that has resulted in the narrowing of the beach area, which has affected adversely on the recreational and tourist activity in this area. Although the beach is classified as stable under the National Coastal Engineering Study (NCES) of 1985, at present the average retreat rate is estimated to be 0.8 m/year. If protective measures are not taken, the beach eventually will be eroded, and the ocean waves approach the land will endanger the properties located along the beachfront and in the hinterland. At present, coastal structures of various designs had been built to protect the public recreational areas occupying the northern part of the beach and the hotels on the southern part. However more efforts are needed to protect and develop the beach to be among the best tourists‟ attractions in Malaysia. 1.3 Objectives of Study The main objective of this study is to investigate the response of the Teluk Cempedak beach due to installation of the Pressure Equalization Module (PEM) system. The specific objective of this study is to determine the depth of closure due to the installation of the Pressure Equalization Modules (PEM) system as well as to evaluate the PEM effectiveness based on total sand volume and beach level retained on the beach after a specific time period. A comparison of results before and after the installation of PEM system has been successfully investigated. 7 1.4 Scope of Study 1.4.1 Study Area The location of the study area is at Teluk Cempedak on the East Coast of Peninsular Malaysia near the town of Kuantan (see Figure 1.1). Teluk Cempedak is situated in a pocket bay adjacent to Hyatt- and Sheraton Hotel and has a total length of 1100 metres. The beach called Teluk Cempedak is one of the main tourist attractions in Pahang, where there are hotels and eateries occupying the northern portion of the beach, while Hyatt and Sheraton hotels are situated in the southern part. The beach is located between the headlands of Tanjung Pelindung Tengah and Tanjung Tembeling, with Sungai Cempedak draining into the northern end of the bay. This river drains Bukit Pelindung and discharges some sediment and moderately polluted water from developed areas within its catchment. The bay has been developed for public recreation as well as for local and international tourism activities. Location of Study Area:Teluk Cempedak Beach, Kuantan, Pahang Figure 1.1: The Location of Study Area at Teluk Cempedak Beach, Kuantan 8 1.4.2 Data Collection and Analysis Data collection is the most important part of this study. Data made available in this study comprise the following:- (i) Profile survey data. (ii) Bathymetric data. (iii) Wave data. (iv) Wind data. (v) Tidal data. (vi) Bed sediment data. A detailed description of this data is discussed in the following chapter. This data had been used to determine the depth of closure by using analytical procedure. Data analysis involves the following scope of work:- (a) Compiling, plotting and comparing series of survey data. (b) Analysis of wave data to obtain the significant wave height and wave period. (c) Analysis of sediment data for determination of mean particle size (D50). (d) Determination of closure depth using Hellemeier equation (1981). 9 1.4.3 Determination of Closure Depth Depth of closure is an important concept in coastal engineering that defines the seaward limit of significant net sediment transport along a wave-dominated sandy beach profile over a period of time and is used to establish shoreline and volume change relationships. The depth of closure can be observed along a specific segment of coast in a series of profiles taken over a period of years as the depth at which the profiles consistently come together within the accuracy of the survey procedures. (Robertson et al, 2008). Ferreira (2003) reported that the depth of closure is the depth that separates the active cross-shore profile from a deeper zone where the sediment transport is much weaker and where morphological changes are less perceptible. He suggested that this depth should be determined by morphological comparison, existing some formulations (e.g. Hallermeier, 1981, Birkemeier, 1985) that can be used for estimating a standard annual value for each coastal region when a morphological approach cannot be used. 1.5 Terminology Used in This Study 1.5.1 Beach Nourishment Beach nourishment involves the placement of large quantities of sand or gravel in the littoral zone to advance the shoreline seaward. Such nourishment can be used to create or to maintain a recreational beach or to build out the shore in order to improve 10 the capacity of the beach to protect coastal properties from wave attack (Komar,1998). Beach nourishment represents a soft solution and is the only form of shore protection that attempts to maintain a naturally appearing beach. 1.5.2 Closure Depth According to Nicholls et al (1998) in their Coastal Engineering Technical Note, they claimed the depth of closure for a given or characteristic time interval is the most landward depth seaward of which there is no significant change in bottom elevation and no significant net sediment transport between the near-shore and the offshore. 1.5.3 Equilibrium Profile Equilibrium beach profile is conceptually the result of the balance of destructive versus constructive forces (Dean, 2002). The beach profile is the variation of water depth with distance offshore from the shoreline. In nature, the equilibrium profile is considered to be a dynamic concept, for the incident wave field and water level change continuously in nature; therefore, the profile responds continuously. By averaging these profiles over a long period, a mean equilibrium can be defined. 11 1.5.4 Pressure Equalization Module System Pressure Equalization Module (PEM) system is a new innovative system originated from Denmark for beach erosion control. The system was successfully installed in many countries all over around the world including Australia, Ghana, Denmark as well as Malaysia. It is designed to stimulate accretion of sand on certain beaches and to slow down the erosion process in some other beaches. PEM system is radically different from other protection measures where hard structures like concrete walls, rock embankment and groynes are used. This system has low impact on the aesthetics of the beach area and thus represents a more environmental friendly coastal protection method. It is assumed that under PEM influence the groundwater table in the beach will be lower and the swash infiltration-exfiltration rate will decrease, that will cause decreasing of intensity of the beach erosion in the swash zone. 1.6 Importance of Study By the end of this study, the results presented will provide some base line information for local engineers in order to suggest a better plan for beach protection in other location by using a combination of PEM system and beach nourishment. Based on the findings of this study, the following expected results can be drawn:- (a) The depth of closure will be higher as well as the point of closure will be further seaward and the width of the beach will be wider due to the effect of the PEM system. 12 (b) From this study, engineers will be able to utilize an analytical model, specific to the local conditions, to predict depths of closure for areas where the beach has been installed with a PEM system. (c) The Pressure Equalization Modules system is expected to effectively create a new beach by enhancing infiltration and sediment deposition. (d) An effective PEM in combination with beach nourishment will be able to extend the lifetime of a nourished beach considerably. This technique of using a soft engineering approach could be applied to other beaches as well. 13 CHAPTER II LITERATURE REVIEW 2.1 Introduction This chapter comprises two parts, namely Part A and Part B. Part A consists of the literature review to provide the historical background regarding beach nourishment and the theory of determining the closure depth as well as equilibrium profile. Part B consists of the Pressure Equalization Modules (PEM) system that is being used for shore protection at the study area. Further explanation based on the PEM installation and how it works was discussed also in this part. Furthermore, some related case studies with regard to this PEM were also discussed. 14 PART A: BEACH NOURISHMENT/ DEPTH OF CLOSURE/ BEACH EQUILIBRIUM PROFILE 2.2 Beach Nourishment As mentioned previously in Chapter 1, beach nourishment is one of the common soft engineering techniques utilized for beach protection. Beach nourishment stands in contrast as the only engineered shore protection alternative that directly addresses the problem of a sand budget and deficit, because it is a process of adding sand from sources outside the eroding system. The result is a wider beach that improves natural protection while also providing additional recreational area. Beach nourishment is a viable engineering alternative (National Research Council, 1995) for shore protection and is the principal technique for beach restoration; its application is suitable for some, but not all, locations where erosion is occurring. Local, state, and federal regulatory agencies strongly encourage the use of nonstructural measures such as beach nourishment to prevent storm damage and control flooding, because beach nourishment closely resembles natural processes and is the least disruptive to the littoral transport processes. Structural measures include seawalls and revetments which often have adverse effects on adjacent and nearby beaches by increasing erosion through wave reflection and by eliminating important sediment sources. However, site-specific conditions (e.g., erosion rate, grain size distribution, wave climate) and proximity of coastal resources (e.g., salt marsh, eelgrass, shellfish, and rocky sub-tidal habitat) must be considered to minimize potential impacts to these sensitive resource areas as well as maximize protection of coastal development and infrastructure. 15 The most important factor for beach nourishment projects is the grain size distribution of the source material as compared to the native beach material, also referred to as sediment compatibility. For dredging projects, state policy requires that clean, compatible sediment be placed on adjacent beaches to keep the material in the littoral system (Haney et al., 2003). Note that location is important. If sediment is placed where it would not be stable due to its incompatibility, then unintended adverse impacts on seagrass, shellfish beds, mangroves, or the dredge channel could result. 2.2.1 Definition(s) of Beach Nourishment from Different Perspectives The placement of sand on a beach to restore (to build) is referred to as beach nourishment or beach fill and is the most non intrusive technique available to the coastal engineer. Typically, sand from offshore or onshore sources is placed on the eroding beach. Beach nourishment with its attendant widening of the beach, is used to accomplish several goals as follows; (i) to build additional recreational area; (ii) to offer storm protection (both by reducing the wave energy nearshore and creating a sacrificial beach to be eroded during a storm); and (iii) to provide, in some cases, environmental habitat for endangered species (Dean and Dalrymple, 2002). According to National Research Council (1995), beach nourishment is a technique used to restore an eroding or lost beach or to create a new sandy shoreline, involves the placement of sand fill with or without supporting structures along the shoreline to widen the beach. It is the only management tool which serves the dual purpose of protecting coastal lands and preserving beach resources. Beach nourishment requires large volumes of beach-quality sand. The initial nourishment project typically requires thousands of cubic meters of sand per kilometer of shoreline, and most beaches need periodic re-nourishment. 16 Other organization classified beach nourishment as the process of mechanically or hydraulically placing sand directly on an eroding shore to restore or form, and subsequently maintain, an adequate protective or desired recreational beach (USACE, 1984). Meanwhile, Oxford defines nourishment as “sustenance, food,” nourish is defined as “sustain with food, promote the development of (the soil, etc.)” (Oxford Univ. Press, 1998). The use of the term “beach nourishment” is considered by some to be a misnomer, given that nothing is actually being nourished. 2.2.2 Advantages and Disadvantages of Beach Nourishment Activities Beach nourishment is often proposed when beach erosion threatens to remove an existing beach, make it too narrow to be used, and/or when property behind an eroding beach is threatened. Because nourishment does not stop erosion, nourishment must be repeated to maintain the beach. This is called "beach re-nourishment". It is helpful to imagine that each nourishment project (i.e. an addition of a batch of sand) has a lifetime. The project's lifetime is simply the time it takes for all the nourishment sand to be eroded away. After that time, the beach would be back to its pre-nourishment width, and would need to be re-nourished with sand. Generally, whatever project related to beach protection will provide both positive and negative influences to the environmental condition. Below are listed the positive effects and negative effects due to beach nourishment adapted from Emery, K.O., (1961):- (a) Advantages:- 1. Nourishment restores and widens the recreational beach. 2. Structures behind the beach are protected as long as the added sand remains. 17 3. When erosion continues, beach nourishment does not leave hazards on the beach or in the surf zone. This is a big advantage when compared with "hard" beach stabilization structures like seawalls or groins. Seawalls may protect structures behind the beach, but they almost always cause the beach in front of the wall to become narrower. If erosion breaches the seawall, then debris from the wall will be left on the beach and in the surf. Since beach nourishment only puts sand on the beach, no debris is left when it erodes. (b) Disadvantages:- 1. Beach nourishment sand often (in fact, usually) erodes faster than the natural sand on the beach. A good rule of thumb is that nourished beaches erode two or three times faster than natural beaches. Erosion rates can differ widely, however. The biggest factor for the lifetime of a nourished beach is the number of storms that affect the beach. Storms are unpredictable, so nourished beach lifetimes are unpredictable too. The amount of sand added per yard of beach length and the sand placement design determine the new beach width. Wider nourished beaches last longer. 2. Beach nourishment is expensive, and must be repeated periodically. 3. The beach turns into a construction zone during nourishment. 4. The process of nourishment may damage, destroy or otherwise hurt marine and beach life by burying it, squishing it under bulldozers, changing the shape of the beach or making the water near the beach too muddy. In recent decades, a variety of plants, insects, turtles, shorebirds, 18 and other animals have become threatened or endangered as a result of human alteration of beach environments. Many of these organisms rely on storms and other natural beach processes (such as dune formation by wind) for the creation and/or maintenance of their habitats. Because of their dependence on natural beach processes, nourishment projects can affect the survival of certain species. For example, beach nourishment can modify a beach by making it too steep and/or too compacted for sea turtles to climb up and bury their eggs. Another example involves filterfeeding marine organisms, such as certain species of clams that are accustomed to relatively clear water. These organisms can be particularly hard hit by the extreme muddiness produced by nourishment, and they can die-off in large numbers. 5. The sand added to the beach is often different from the natural beach sand. It can be hard to find a perfect match. This means that the new material may have smaller or larger diameter sand grains than the natural beach. Such differences in "grain-size" affect the way waves interact with a beach. This will affect surf conditions and bars on the submerged part of the beach, and will also change the shape of the "dry beach", which is where people spread their towels and go for strolls. Fine-grained sand generally erodes faster than coarse-grained sand, so grain-size influences the replenished beach's "lifetime". 2.3 Identification of the Depth of Closure Depth of closure is an important concept in coastal engineering that defines the seaward limit of significant net sediment transport along a wave-dominated sandy beach profile over a period of time and is used to establish shoreline and volume change 19 relationships. The depth of closure can be observed along a specific segment of coast in a series of profiles taken over a period of years as the depth at which the profiles consistently come together within the accuracy of the survey procedures (Robertson et al, 2008). Estimates of depth of closure have also been developed by Hallermeier and Berkemeier based on wave climate. In some cases of following major storms, some researchers found that movement of sediment beyond the depth of closure. The depth of closure is the depth that separates the active cross-shore profile from a deeper zone where the sediment transport is much weaker and where morphological changes are less perceptible as illustrated in Figure 2.1. This depth should be determined by morphological comparison, existing some formulations (e.g. Hallermeier, 1981, Birkemeier, 1985) that can be used for estimating a standard annual value for each coastal region when a morphological approach cannot be used. Figure 2.1: Schematic Diagram of the Depth of Beach Profile Closure (Courtesy of www.brynmawr.edu/geology/dbarber/ retrieved on September 2008) 20 The depth of closure has been defined in various ways, including profile pinchoff depth, critical depth, depth of active profile, depth of active (sediment) movement, maximum depth of beach erosion, seaward limit of nearshore eroding wave processes, and seaward limit of constructive wave processes. These definitions have various applicabilities but are not considered sufficiently precise for beach-fill design. According to Nicolls et al (1998) in their Coastal Engineering Technical Note, they claimed the depth of closure as the following definition and illustrated as Figure 2.2 below:- “The depth of closure for a given or characteristic time interval is the most Iandward depth seaward of which there is no significant change in bottom elevation and no significant net sediment transport between the near-shore and the offshore.” Figure 2.2: Definition Sketch of the Closure Depth 21 The seaward limit of effective seasonal profile fluctuation is a useful engineering concept and has been introduced as the closure depth. Based on laboratory and field data, Hellemeier (1978, 1981) developed the first rational approach to the determination of the closure depth. He defines two depths, which is shallower depth and the deepest seaward. The shallower of the two appears to be of greatest engineering relevance and appropriate for beach nourishment design. Based on correlations with the Shields parameter, the shallower depth, h*, was recommended as:0.03 ρ v2b = (ρs- ρ)gh* (2.1) where; h* = closure depth; ρ and ρ s = mass densities of water and sediment; vb = amplitude of the wave induced bottom velocity; g = gravity. This result was developed into a more meaningful form for application using linear wave theory and transferred to field conditions by rationalizing that the seaward closure depth would be associated with wave conditions that are relatively rare. Hellemeier chose the effective significant wave height, He, as that which is exceeded only twelve hours per year or only 0.137 % of the time. The resulting approximate equation for the depth of closure was determined to be hc = 2.28He – 68.5 (He2/gTe2) (2.2) where; Te = wave period associated with He which can be approximated from the annual mean significant wave height H, and the standard deviation in wave height, σH as 22 He = H + 5.6 σH (2.3) Birkemeier (1985) evaluated Hellemeier‟s relationship using higher quality field measurements and recommended slightly different constants in the equation proposed by Hellemeier; hc = 1.75He – 57.9 (He2/gTe2) (2.4) and also found that the following simplified approximation provided nearly as good fit to the data; hc = 1.57He (2.5) As a conclusion, in the absence of profile data, equation 2.2 is recommended as the primary calculation method for estimating the depth of closure because it provides a more conservative estimate for design. Conservative prediction of the depth of closure by the Hallemeier equation is confirmed by Nichols, Birkemeier, and Hallemeier (1996), who showed that the formulation provides an upper bound to the scatter in measurements of depth of closure at Duck, North Carolina. Nevertheless, equation 2.5 also was used in this study to compare the result with equation 2.2 as well as to figure out the relationship among these equations. Therefore, boths equation 2.2 and 2.5 above were used in this study to determine the depth of closure as recommended by Hallemeier (1996). 23 2.3.1 Estimation of the Depth of Closure In application to beach fill design, the depth of closure is required to estimate the volume of sand needed to be placed on the beach profile. A typical design consists of a dune (to mitigate damage from storm inundation, waves, erosion) and a berm to protect the dune. The longevity of the berm is controlled by the historical shoreline-erosion rate and end loss and transition effects (typically longshore transport processes), as well as by adjustment of the filled profile to achieve equilibrium (a cross-shore transport processes)(Kraus, et al, 1993). The depth of closure enters in calculating the volume per unit length alongshore needed to be placed to provide a certain minimum berm width over a certain time period. The most accurate method of determining the depth of closure is from studying profile survey (Ghazali, 2007). Observed depth of closure can be empirically derived from the observation of a series of profile surveys taken over a period of time. Nicholls et.al (1996) claims that the depth of closure corresponds to a pinch out depth below which depth changes become small. In order to determine the closure depth based on the beach profile survey, there are two widely used methods in which describe the profile measurement i.e standard depth change method (SDDC) and fixed depth change method (FDC). The SDDC method is useful in the sense that it avoids bias from outliers (Hinton and Nicholls, 1998). FDC method explained by Nicholls et.al (1996) tells that the closure depth where the variation in depth between two profile surveys is equal or less than a pre-selected criterion usually associated with the accuracy of the profile survey. The closure depth is the absolute difference between the elevations of two consecutive surveys from the same profile line. Therefore, if a survey method has an accuracy of 0.25 m, any absolute change exceeding this limit value would be considered significant. In conventional hydrographic survey using eco sounders and where convective algorithms have been applied to account for heave and other boat movements, the accepted accuracy is typically 30 cm (Ghazali, 2007). 24 Hinton and Nicholls (1998) used an FDC criterion of 0.25 m and 0.5 m and found that since FDC captures the largest depth variation it generally gave the more landward values of closure. Ghazali (2007) found that FDC method is the accurate method in determining the closure depth for the beach fill design since it captures more significant changes and regularly produces deeper closure depth than the SDDC method. He also used an FDC criterion 0.3 m similar to the previous research that was conducted by Nicholls et.al (1998). 2.3.2 Depth of Closure and Vertical Datum The depth of closure is a water depth measured from some datum (for example, Admiralty Chart Datum (ACD)). ACD is a reference datum used by navigators and hydrographic surveyors (normally coincides with the lowest astronomical tide level. Predictive equations for the depth of closure (Hellemeier, 1978,1981; Birkemeier, 1985) employ the tidal datum mean low water (MLW) as a reference datum. Normally, beach profile data are in LSD, whereas MLW refers to ACD. Thus, a conversion must be made from ACD to LCD to obtain the tidal datum mean low water (MLW). 2.4 Previous Case Studies – Determination of Depth of Closure Previous studies based on determination of the closure depth were discussed in this chapter as the following. Two case studies from international experience and one case study from local experience were discussed briefly in order to give a better understanding and some basic information regarding the determination of depth of closure. The case studies are presented as below. 25 2.4.1 Ocean City, Maryland The beach fill design at Ocean City, Maryland, has been extensively examined in the literature because considerable monitoring data are available for this site (Staubble et al, 1992). During the particular stormy 3-1/2- year period from August 1988 to January 1992, data were compiled from near-shore wave gauge located at a depth of approximately 10m. The wave height exceeded for 12 hour during the period was 9.8 ft(3m) with and associated wave period of 10.2 second (occurring during January 1992 storm). This value was substituted into equation 2.2 above, and gives Dc = 20.4 ft (6.2m) from mean low water (MLW). The average of the significant wave heights measured at the gauge during the period was 2.1 ft(0.6m) and again these values were substituted into equation 2.2 and gives Dc = 18.7 ft(5.7m) from mean low water (MLW) level. Staubble et al, (1992) determined the depth of closure at Ocean City over the same period by examining profile survey data from 12 survey lines. Results of the analysis indicated a depth of closure ranging from 16 to 22 ft (4.9 to 6.7 m) from NGVD for individual profiles, with 20 ft (6.1 m) from NGVD being a representative value for all profiles. Thus, equation 2.2 accurately predicts the upper bound of the measured depth of closure for this data set. 2.4.2 Pria de Fero, Algarve, South Portugal The study to determine the depth of closure variability through time as a function of wave action has been done by Ferreira in year 1999. The location of study is at Pria de Fero, Algarve, South Portugal. For that purpose, bathymetric surveys were made along 6 profiles, in average every two months, between August 2001 and May 2003. The depth of closure was determined for all profiles between each two consecutive surveys by morphological comparison. Tides are semi-diurnal with a maximum range of about 3.5 m. Dominant wave directions are from west to south west and wave energy can be considered as moderate, with an average annual significant wave height (Hs=0.92 m). 26 Storm conditions (Hs > 3 m) do not exceed 2 % of the wave records, with recorded values of Hs above 5 m being scarce (about 0.2 %). The beach can be considered intermediated to reflective, with the beach face being composed by medium to coarse sand. The results showed that the observed depth of closure ranged from less than 2 m to up to 11 m depth below mean sea level (MSL). The depth of closure clearly demonstrates a variation through time in accordance with the wave energy distribution, with changes being minimal during low-energy periods and the maximum values being associated to high energy periods. For some periods, namely during summer, the closure depth is located at the level of the lower low tides, indicating a small wave impact at the sea floor. For the most of the year the depth of closure values are smaller than 6 m depth below MSL, with the higher values for the depth of closure being episodic. The threshold of significant wave height for inducing peaks of depth of closure was found to be of about Hs > 4 m. 2.4.3 Kelantan Coast, Malaysia Research conducted by Ghazali (2007) found that along the study shoreline at Pantai Sabak, more than one closure point can occur across the same profile over the seasonal and annual period. The study has examined the applicability of the Hallemeier equation in predicting depth of closure for the coastline at Pantai Sabak, Kelantan using nearshore waves which were transformed from offshore waves through numerical modeling. The predicted depth of closure was compared against measured depth of closure at 13 profiles that were surveyed in 1998, 1999, 2000, and 2004. The widely accepted Standard Deviation of Depth Change (SDDC) and Fixed Depth Change (FDC) methods to determine Dc were both explored and the Dc for monsoon, annual and 5 year events were investigated. He then, summarized that Hallemeier equation over predicts annual depth of closure (Dc) by 43 % and affirms previous findings that the predictive 27 equation determines an upper limit value of Dc. Within the limitations of survey data available, the annual depth of closure at Pantai Sabak can be equated to 1.5 times H0.137. 2.5 Equilibrium Beach Profile Since the beginning of the 20th century similarities observed in cross-shore profiles suggest the equilibrium concept in certain beach conditions. The beach profile is the variation of water depth with distance offshore from the shoreline. The equilibrium profile is conceptually the result of the balance of destructive versus constructive forces (Dean and Dalrymple, 2002). Though an equilibrium beach profile is unlikely outside of a laboratory, due to the continuous changes in the factors affecting the forces, the study of equilibrium beach profiles is important. It aids in the understanding of beach profiles in general and beach responses to changes in the dominant forces such as increases in sea level or storms. Studies of equilibrium beach profiles lead to better predictions, knowledge of beach profiles that are not currently in equilibrium and conditions that have caused the current profile of to obtain its state. Equilibrium beach profiles are also important to beach fill designs and coastal management, in predicting how beach nourishment designs will respond after they have been applied and in predicting the type of beach nourishment design that will fare best for conditions at the specified location. In nature, the equilibrium profile is considered to be a dynamic concept, for the incident wave field and water level change continuously in nature; therefore, the profile respond continuously. By averaging these profiles over a long period, a mean equilibrium can be defined. 28 There has been a long interest in equilibrium beach profiles. Bruun (1954) examined profiles from Denmark and Monterey Bay, CA and proposed the following; h(y) = Ay2/3 (2.6) where; h = water depth at distance y from the shoreline; and A= profile scale parameter with dimensions of length to the 1/3 power. The profile scale factor was later found to be dependent on sediment size. (Dean, 2002). This came from the assumption that turbulence in the surf zone was the dominant destructive force and the relationship between sediment size and the level of wave energy dissipation per unit water necessary for sediment transport (Dean, 1993). For this reason the Bruun model is commonly called the dissipation model. This relationship was later converted to an A vs. w relationship, where w is the fall velocity of the sediment (Dean, 1993). One downfall of the dissipation model is that it predicts an unrealistic vertical slope at the shoreline. To fix this anomaly a new model was developed by Larson, in 1988 that included gravity as a destructive force for a very small region near the shoreline (Komar 1998), this model will then be referred to as the gravity model. The resulting equation is y = h/m + h(3/2)/A(3/2) (2.7) where; y = Equilibrium beach profile; m = the fore shore slope of the beach profile, which is calculated using measured profile data; 29 h = water depth at distance y from the shoreline; and A= profile scale parameter with dimensions of length to the 1/3 power. In this turbulence model (represented by the 2nd term on the right side) remains the dominant destructive force except when the profile reaches shallow water. At that point the gravity term becomes the dominant destructive force. Current research in the field of equilibrium beach profiles has focused in areas of the parameters, A and m, and their sensitivities, the applicability of the equilibrium beach profile models both to beach nourishment design and to varying forcing conditions and beaches. For example Houston developed a simpler approach of designing beach – fill design that utilizes the dissipation equation. Dean had previously studied methods of using the equilibrium profile with sediment data to develop beach designs. In another study Larson et al, (1999) attempted to extend the applicability of equilibrium profiles to include profiles under breaking and non – breaking waves. 30 PART B: PRESSURE EQUALIZATION MODULE (PEM) SYSTEM 2.6 Pressure Equalization Module (PEM) System Application Concept A method of beach protection based on Pressure Equalization Modules (PEM) system has been developed by Mr Poul Jakobsen representing Skagen Innovation Centre (SIC) in Denmark. SIC claims that the system works by equalizing the ground water pressure present inside the beach. During his work he developed the following theory (in short):- The pressure equalization modules increase the drop of the water level in the coastal profile in the period from high tide to low tide. Thus, the beach will be more effectively drained of water (see Figure 2.3). When the water level is low on the coast during the period from low tide to high tide, the water circulation in the swash zone increases, which again increases the depositing of materials on the foreshore, thereby building up the beach from the sediments transported along the coast. (Skagen Innovation Centre, 2000). Figure 2.3: Pressure Equalization Modules – schematization (Courtesy of Eco Shore International, (2006)) 31 It has surprisingly been found by the inventor that positioning of pressure equalization modules in the beach results in sedimentation of material at the area where the modules are placed. A possible explanation as to why coastal accretion takes place is that the very fine sand which is fed to the profile partly by the sea and partly by the wind and which is packed with silt and other clay particles, reduces the hydraulic conductivity. Deeper layers in the coastal profile, which have exclusively been built by the waves of the sea, are primarily coarse in the form of gravel and pebbles which have a greater hydraulic conductivity. The difference in hydraulic conductivity will be seen clearly when digging into a coastal profile, it being possible to dig a hole in the profile, and the groundwater will then rise up into the profile once the water table is reached. The reason is the very different hydraulic conductivity and that the freshwater is under pressure from the hinterland. Thus, the coastal profile may be compared to a downwardly open tank where the tank is opened at the top with the pressure equalization modules which extend through the compact layers of the profile so that the water runs more easily and thereby more quickly out of the profile in the period from flood to ebb. This means that a pressure equalized profile is better emptied of freshwater and salt water in the fall period of the tide. When the tide then rises from ebb to flood, a greater fluctuation occurs in the foreshore, as the salt water in the swash zone is drained in the swash zone so that materials settle in the foreshore during this period of time (see Figure 2.4). Conversely, coastal erosion takes place if the freshwater is under pressure in the foreshore, as the salt water will then run back into the sea on top of the freshwater and thereby erode the foreshore. In reality, the pressure equalization modules start a process which spreads from the pressure equalization modules, as the silt and clay particles are flushed out of the foreshore when the fluctuation is increased because of the draining action of the modules. Further, a clear connection has been found between the amount of sediment transport on the coast and the rate of the coastal accretion. It has been found that the pressure equalization modules create a natural equilibrium profile with a system of about 1:20, so that the waves run up on the beach and leave material, as water in motion can carry large amounts of material which settle when the velocity of the water decreases. 32 Seepage Area High tide Low tide Sea Salt Water Tongue Figure 2.4: PEM Function Dewatering the Beach (Courtesy of Eco Shore International, (2006)) 2.6.1 The Advantages of PEM System SIC claims that, there are several advantages that can be drawn due to pressure equalization module system. (e) By using this Pressure Equalization Module System, the water table will drop and therefore enhance infiltration and sediment deposition. (f) The average beach level is raised in the PEM areas. (g) The accumulation of sand at the PEM areas is higher compare to the area without installation of PEM system. 33 (h) Coastal profiles with pressure equalization modules naturally become very wide, which results in a very good great sand drift on the foreshore. (i) The PEM system will create minimal disruption to the shoreline both in the physical and ecological sense. 2.7 Design Criteria of Pressure Equalization Modules System at Teluk Cempedak Beach, Kuantan The Pressure Equalization Module (PEM) system is a relatively new system currently being tested in Kuantan, Pahang. This is the first coastal erosion project applying this method in Malaysia and Asia which costs RM15, 400,000.00 (Annual Report DID, 2004). The PEM functions in the up rush zone of the beach where wave runs up the beach face and, upon reaching its limit, runs down and at the same time infiltrates into the bed. The infiltration of seawater into the bed is limited by the existing level of groundwater. Hence, if the groundwater can be lowered, more water from the run-up can percolate into the bed and less will run down the surface dragging sediments with the flow. The lowering of the local groundwater table can be achieved with the PEM system which relieves the pressure within the beach by physically „connecting‟ it with the atmosphere. In summary, the PEM increases vertical infiltration of up rush in the swash zone. Rows of perforated PVC pipes about 15 cm in diameter are installed normal to the shoreline in the area between the upper shore limit of the swash zone (area 34 influenced by wave run-up) and the mean low water line. The pipes behave as a vertical filter which equalizes groundwater pressure within the beach allowing increased circulation of seawater within the beach profile. The PEM pipe design is illustrated in Figure 2.5. Figure 2.5: Design of Pressure Equalization Module Pipes (Courtesy of Department of Irrigation and Drainage Malaysia (2006)) Each vertical PEM pipe is 2.0 m long with perforations measuring 400 to 900 microns (1 micron = 0.001 mm) and are placed vertically into the beach with the bottom end penetrating the phreatic line. The pipe wall thickness is 3 mm. Each section shall be 30 cm long and consist of horizontal arc slots cut into the pipe 1 mm apart, each arc slot with a length of 90o and width of not more than 0.2 mm. The distance between each section shall be 10 cm. First section shall start 75 cm below top of pipe as shown in Figure 2.5 above. The top of the pipe are closed with a plastic cap with filter, and 35 covered with sand so that they do not present obstacles to users of the beach. The cap made of PVC 2-3 mm thickness and of an easily observable colour (red or green). Any water pressure build-up within the beach will be transferred into the pipes. The PEM system is suited for littoral coastlines with a natural supply of sand from the coast. In cases where the natural sand supply has been depleted, beach nourishment is necessary. The presence of the PEM system causes the beach to retain more material on the foreshore area (between the low water line and the high water line) and form a more erosion-resistant beach. Its immediate affect will be in lowering the sediment transport capacity of wave down-rush. In the medium term, the shoreline undergoes a change whereby sediment mounds will form normal to the shore along the position of the PEM pipes. These then behave like groins and trap sediment movement in the alongshore direction (Jakobsen, 2002). With a more erosion-resistant beach, a beach nourishment replenishment interval is expected to increase. Another notable benefit is that the PEM system creates minimal disruption to the shoreline both in the physical and ecological sense. The construction phase of a PEM project, unless beach nourishment is required, uses very little machinery causing minimal disturbance to beach activities (Ghazali, 2005). 2.7.1 System Installation Due to lack of sediment transport along the coast of Teluk Cempedak, sand nourishment is required for the application of PEM system to rehabilitate the beach. In the case where PEM system will function to reduce the erosion rate of the sand nourishment, the sand nourishment would be designed to follow the estimated equilibrium profile for the design PEM. Installation of PEM system is generally done in two steps. The first set of pipes will be installed in a 100 m x 100 m matrix to drain the 36 beach and facilitate sand nourishment while the next will be the offset PEM system whereby involve the installation of another set of pipes after the sand nourishment process has been completed.:- (a) First Set - Installation of the Basic PEM system to drain the existing beach and prepare for sand nourishment. Vertical pipe 2 m long drainpipes are located in 100 m x 100 m matrix ( 11 columns and 5 rows) reaching from the surface of the beach to the groundwater table. Total number of drainpipes is 55 nos. The effect of the Basic installation is to initially increase the drainage capacity of the active zone, and secondly transport silt away from the beach thus accelerating further the drainage capacity. (b) Second Set - Installation of the Off-set PEM system after sand nourishment. Vertical pipe 2 m long drainpipes are located in 100 m x 100 m matrix, ( 11 columns and 5 rows) however, shifted 20 m in the along-shore direction. Total number of drainpipes is 55 nos. The experience from previous installation is that the cross-shore sand tongue develops in front of each of the rows of PEM modules. These sand tongues essentially have some effect as groynes arresting some of the sand transported with the long-shore currents thus building up sand between the rows. The total number of drainpipes needed is 110 nos. Figure 2.6, 2.7, 2.8 and 2.9 shows the preparation of PEM pipe installation at Teluk Cempedak beach during the construction stage in July 2004. 37 Figure 2.6: Preparation for PEM Installation on 9th July 2004 (Courtesy of Department of Irrigation and Drainage Malaysia (2004)) Figure 2.7: Preparation of borehole for PEM Installation on 9th July 2004 (Courtesy of Department of Irrigation and Drainage Malaysia (2004)) 38 Figure 2.8: Placement of PEM pipe (Courtesy of Department of Irrigation and Drainage Malaysia (2004)) Figure 2.9: Exposed PEM Pipe at Chainage 800 (Courtesy of Department of Irrigation and Drainage Malaysia (2004)) 39 CHAPTER III RESEARCH METHODOLOGY 3.1 Introduction A research methodology defines what the activity of research is, how to proceed, how to measure progress, and what constitutes success. This chapter is focused on how to determine the depth of closure by using analytical method before and after the installation of PEM system. The estimations of depth of closure are discussed in order to clarify the specific objective of this study. Data required for this study was also discussed in this chapter. After the implementation of methodology, data collection and analysis will be subsequently conducted to obtain the end results. 40 3.2 Study Area The location of this study is at Teluk Cempedak on the East Coast of Peninsular Malaysia near the town of Kuantan (see Figure 3.1). Teluk Cempedak is placed in a pocket bay at the east coast of Peninsular Malaysia. The beach is located in front of Hyatt- and Sheraton Hotel and has a total length of 1100 meters (1.1 km).The beach is a type of sandy beach and can be classified as a dissipative beach where all the arriving wave energy is dissipated on the near-shore. The waves also break by spilling. The beach slope is physically fairly uniform and gentle. As the beach is dissipative, the longshore currents and longshore transport occur throughout along a smoother crossshore profile. A dissipative beach profile is more conducive for infra gravity edge waves which have low frequency (T= 30 s - 120 s), where energy concentrated on upper beach profile to result in increased erosion and sediment transport. Figure 3.2, Figure 3.3 and Figure 3.4 (a) and (b) shows the physical condition at the Teluk Cempedak beach. Location of study area:Teluk Cempedak Beach, Kuantan Figure 3.1: Site Study Area 41 Figure 3.2: The Beach Slope is Steeper due to Erosion Problem (Courtesy of Department of Irrigation and Drainage Malaysia (2003)) Figure 3.3: The Beach is Narrower and Recreational Activities are Limited for Beach Visitor (Courtesy of Department of Irrigation and Drainage Malaysia (2003)) 42 Figure 3.4(a): Beach Condition before the Installation of PEM System (Courtesy of Department of Irrigation and Drainage Malaysia (2003)) Figure 3.4 (b): Beach Condition after the Installation of PEM System (Courtesy of Department of Irrigation and Drainage Malaysia (2007)) 43 3.3 Data Set Data collection is very important in this study. Data sets obtained for this study comprise the following:(a) beach profile survey data; (b) wind and wave data; (c) tidal data; and (d) bed sediment data. 3.3.1 Beach Profile Survey For the purpose of this research, beach profile survey data was obtained from Department of Irrigation and Drainage (DID) Malaysia which include pre and post installation of PEM system and this exercise would be critical to the accuracy of depth of closure estimates. Prior to analysis, cross-shore profiles that best represent the study shoreline has been determined. Four year survey data is used to analyze the depth of closure. Data obtained for year 2003 represent the pre installation of PEM while data for year 2005 until 2007 represent for the post installation of PEM system. The surveys consist of 14 chainage (CH) lines where CH 100 to CH 300 and CH1400 are not installed with PEM pipe while CH 400 to CH 1300 is installed with the PEM pipe. Beach nourishment was also applied between CH 400 to CH 1300. 44 3.3.2 Wind and Wave Data The data set also includes atmospheric wind data. Local wind data is available within the Malaysian Meteorological Department (MMD) where the nearest recording station to the study site is at Kuantan Airport. In the two monsoon periods the dominating wind directions are north / northeast in the North East monsoon and southwest/south/southeast in the South West monsoon. The highest wind speed was recorded on December with wind speed higher than 8 m/s. For wave analysis, wave data of 20 years or more is obtained from the information of Synoptic Shipboard Meteorological Observation Data (SSMO) of waves off the East Coast. For Kuantan area, SSMO data are available from 1949 to 1989, a period of 40 years. The main Marsden Square Number used to determine the significant wave height is 2633, 2634, 2635, 2643, 2644, and 2645. Statistical analyses of distribution of wave height and wave period were conducted in this study. Results obtained from numerical modeling conducted by MRCB, Malaysia shows that the shoreline at Teluk Cempedak is orientated 355o according to north, which exposes the most of the beach for waves coming from the main direction in the north east monsoon period (55o). 3.3.3 Tidal Data Tidal information is necessary to determine the local tidal regime. Predicted tidal heights are obtainable from the Royal Malaysian Navy Tide Tables and the Malaysia Survey and Mapping Department Tide Table. The nearest standard port to 45 the study is at Tanjung Gelang. The tidal level recorded within this area is ranged from 2.13 m to 3.05 m. (Malaysian Resource Corporation Berhad (MRCB), 2006) and the type of tide is diurnal. 3.3.4 Bed Sediment Data Sampling is needed to determine sediment characteristics, such as median grain size and grain-size distribution, which affect the beach profile shape and influence, fill volume requirements. The data for sediment is also required to determine the depth of closure. Significant changes in sediment type, size and colour at a particular nearshore location over time infers that the depth of closure is further seaward. Sediment sampling is of particular importance when fill and native material have different characteristics. Sediment samples were collected at selected locations within the project area to account for longshore and cross-shore variability in sediment characteristics. Figure 3.5 shows the location of collected sediment samples and location of the sand source. For this study site area, it is found that there is no sediment input from the sea into the pocket bay (MRCB, 2006). Therefore, due to lack of sediment transported on the alongshore at Teluk Cempedak beach, beach nourishment is required. For this purpose, borrow sand was mined from the seabed offshore where the sand source is located about 5 km from the shoreline and at water depth of approximately 14 m as shown in Figure 3.5. 46 Sungai Cempedak Sediment Samples Sand Source Figure 3.5: Location of Sediment Samples and Sand Source. 47 3.4 Measurement Techniques 3.4.1 Beach Profile Measurement Beach profiles vary with time, both seasonally as the wave climate changes and over the long term, in response to the pressures of erosion and accretion. Beach profiles measured at the same location over time can provide details about the behavior of the beach. By taking a series of profiles along a beach and then repeating the profile measurements at later times, the behavior of the entire beach can be examined in terms of shoreline recession and volumetric loss; moreover, an overall sand budget (sources and sinks of sand) can be determined. For inshore survey, the directions of the profiles are determined and are usually oriented perpendicular to the shoreline trend. These directions are then indicated through the use of pair of ranges pole or a surveyor with a theodolite to keep the surveyors on line. Using standard land surveying equipment, the surveyor determines the elevations of the dry beach along the profile line. This surveying is usually done during the low tide. The offshore portion of the profile is obtained using a survey vessel equipped with a fathometer and positioning system so that the position of the boat can be correlated with the depth measurements. The boat is kept on the profile line by the visual profile markers (the range poles), by radio, or more accurately by modern electronic distance measuring (EDM) equipment, or laser (Dean and Dalrymple, 2002). The offshore survey is usually taken out to a depth exceeding the depth of closure. This depth is chosen because it is the depth beyond which there is normally 48 no change in the profile with time. Always taking profile as far offshore as the depth of closure will make it likely that all the profiles taken along the same line will reach the same depth at the same distance offshore. 3.4.2 Historical Shoreline Changes Long term shoreline change rates can be determined from historical data at a given site. The types of data available are charts or maps and aerial photographs. The charts and photographs provide an historical record of shoreline position. Typically these historical positions, corrected to a common datum, are used to create an overlay of shorelines, and the shoreline changes with time are then determined. Usually, the oldest available data are historical navigation charts. Topographic maps, Admiralty Charts, National Ocean Survey (NOS) bathymetric surveys, and local, state, or university surveys made at different time can be utilized. These maps have limitations, however, because, for example, the U.S Geological Survey Quadrangles (USGS) maps are designed for upland use and the shorelines are usually obtained from aerial photographs (Dean & Darymple, 2002). The difficulty with these data is accuracy. The oldest maps suffer from positional inaccuracy as well as vertical elevation inaccuracy. However, these old maps provide an historical reference that may overshadow uncertainties about their accuracy. More recently, the chart accuracy is limited owing primarily to the different vertical datum that is used. For bathymetric maps, the mean low water and the mean sea level are used. The shoreline position is different for each one. Recent 49 chart sometimes represent a compilation of historical sounding and shoreline data rather than a complete new survey. This can lead to errors where the bathymetry has changed over time. 3.4.3 Tidal Data Measurement Hydrographic surveys are usually done with one boat, and thus considerable time is required for the survey to be completed. For tidal bodies of water, because the sounding depths are relative to the water levels at the time of sounding, a tide gauge system must be used to determine the water level associated with each profile. In all situations, tidal and non tidal, the water level with respect to a known datum is necessary to convert depths measured with the fathometer to the elevations used on the beach profiles (Dean and Dalrymple, 2002). 3.4.4 Aerial Photograph Aerial photographs are much more qualitative than profile or other surveys, yet can be useful in providing an overall indication of project performance especially the dry beach remaining, an important measure to the layperson. High quality aerial photographs taken at low tide can provide the basis for approximate measurements of dry beach width (Dean, 2002). 50 3.5 Data Analysis 3.5.1 Determination of Depth of Closure from Beach Data Profile A series of monitoring survey has been conducted by Jurukur Perunding Services Sdn. Bhd and therefore become the primary data set in this study. Graphical analyses of beach profiles were conducted to determine the profile characteristic, envelope of changes and trends of bar migration. Standard spreadsheet program such as Microsoft Excel was used to tabulate profile measurement data and to calculate variations in the depth leading to the determination of the seaward limit of significant change in elevation. Based on the data sets, investigation of depth of closure will be conducted before and after the installation of PEM system. Data sets are expected to reveal the effect of an erosional event on the depth of closure. Depths of closure from surveys are determined from the FDC method. When the FDC plot down crosses and remain below the limit line i.e 0.25 m, the first point after the down-cross is deemed as the depth of closure. The flowchart represents in Figure 3.6 below shows the algorithm to determine the closure depth from profile survey based of research conducted by Ghazali (2007). 51 START Plot bed elevation x-axis: distance shoreward y-axis: bed elevation Plot FDC line (A) x-axis: distance shoreward y-axis: bed elevation Plot FDC criteria line (B) Determine Fixed Depth Change (FDC) Determine opening and closing point At shoreline, 0 m LSD NO NO If A above B first point where A down-crosses B = closure point YES If A below B FDC line upcrosses B = opening point YES From a closure point and continuing seawards, the point when A next up-crosses B is recorded as reopening point. x 52 x Identify Morphological Zones Closure zone A down-crosses and remain below the B Reopening zones A up-crosses and down-crosses the B alternately along the profile. Multiple Closure Point hci = for the starting point of the first closure zone that occurs (expected at inner-shore) hcm = for the starting point of a subsequent closure point that occurs seawards of hci. (expected at middle-shore) hco= for the starting of the closure zone occurring in the outer-shore and seawards of hcm. Determine effective Dc for beach fill design A clear tailing-off of the A below the B. A tailing-off zone (closure zone) occurring between two zones of significant bed elevation change. END Figure 3.6: The Algorithm of Closure Depth Determination 53 3.5.2 Determination of Depth of Closure from Empirical Formula In order to make a comparison to the results obtained from the beach data profile survey, determination of the depth of closure using empirical formula is applicable for this study. Therefore, analytical method by using Hallemeier equation is proposed to fulfil the specific objective of this study. Equations 2.2 and 2.5 are recommended as the primary calculation method for estimating the depth of closure because they provide a more conservative estimate for design. A new equation for determination of closure depth was obtained in this study in combination with PEM system and beach nourishment. Thus, this predictive equation may be applied for any location along the east coast of Malaysia whereby the installation of PEM and beach nourishment is needed but to a similar wave climate and beach condition. 3.6 PEM Effectiveness Evaluation In order to meet the second objective of this study, PEM effectiveness evaluation was carried out. The evaluation procedure and methodology rests on a number of essential definitions. These definitions are described as follows:- (a) Total Sand Volume Total sand volume is determined by multiplying the beach level for each chainage with the beach width. The beach width in this study was set to 70 meter wide from the shoreline towards the sea. 54 (b) Average Beach Level The average beach level is calculated as the sum of the level of each transect over the beach length divided by the number of transect. The beach level was determined for each chainage line in order to obtain the variation in depth. The width of the beach is defined as the distance from the retaining wall to the mean high water level (MHWL). (c) PEM Efficiency PEM Efficiency was determined in terms of bed elevation. In order to implement this, the widely used equation to determine the efficiency has been applied as mentioned in section 4.16.4. 55 START Define objective and scope of study Literature Review/Previous Study Concept of beach nourishment, closure depth, beach equilibrium profile and PEM system approach. Data Collection 1. Profile data survey. 2. Wind and Wave data. 3. Tidal data. 4. Bed sediment data. Data will be obtained (before and after installation of PEM) from MRCB, licensed consultant company commisioned by DID, Malaysia. Compilation, Plotting, Comparing Data Series Data that obtained from the local authority is normally in a form of raw data. The compilation, plotting and comparing of data should be done in order to get the best set of data. NO Data Analysis 1. 2. 3. 4. Profile data survey analysis. Wave data analysis-Offshore wave height and wave period. Computation of closure depth using Hallemeier Equation. PEM effectiveness evaluation. YES Results and Discussions Conclusion and Recommendations END Figure 3.7: Research Methodology Chart 56 CHAPTER IV DATA ANALYSIS AND RESULTS 4.1 Introduction In this study, the data comprising of hydrographic survey, meteorological and oceanographic data, as well as sediment data were compiled in order to determine the depth of closure for each chainage. Four year records of hydrographic survey were used in this study which includes the beach profile surveys from year 2003 until year 2007. All surveys were conducted by licensed surveyors and hydrographers appointed by the Coastal Engineering Division, Department of Irrigation and Drainage Malaysia. These surveys were classified by two different periods, i.e before the installation of PEM 57 system (2003) and after the installation of PEM system (2005 to 2007). This chapter describes the details of the study area, results of the wave data analysis, tidal information, sediment properties, and determination of the depth of closure from profile surveys as well as determination of closure depth from empirical equation. 4.2 Description of Study Area The study area is located at Teluk Cempedak, Kuantan. Teluk Cempedak beach is located at the east of Kuantan town. It is a pocket beach between the granite headlands of Tanjung Pelindung Tengah and Tanjung Tembeling, with Cempedak River draining into the northern end of the bay. This river drains Bukit Pelindung and discharges some sediment and moderately polluted water from developed areas within its catchment. The bay has been fully developed for public recreation as well as for local and international tourism. The public recreational areas occupy the northern part of the beach and Sheraton and Hyatt Hotels on the southern part. The beach is about 1.1 km long, swash aligned and reflective. Beach morphology and undisturbed areas show two levels of beach cusp due to the difference in sea level and wave energy of the two monsoons. The sands are yellowish and course-grained, reflecting the nearby source of alongshore sands from the eroding headlands. The stretch of beach has a narrow and steep near-shore as a result of steady erosion over the years. The steep nearshore area is also prone to high wave activity that results in strong near-shore currents which may endanger swimmers. Although the National Coastal Erosion Study of 1985 classified this beach as stable, the recent Shoreline Management Plan of the coastline from Kuala Sg.Pahang to the State Boundary of Pahang/Terengganu (DID Malaysia, 2001) found that this coastline is eroding at an estimated rate of 0.8m/year. 58 4.3 Data Set The available data obtained in this study is as follows:- Table 4.1: Data Available for This Study Type of Data Sources Hydrographic Survey 9th Monitoring Survey Drawing of Projek Perintis Pemulihan Pantai Pelancongan dengan Menggunakan “Pressure Equalization Module System” di Teluk Cempedak, Kuantan , Pahang Darul Makmur. - Survey Report No. 647/2007. Waves Data Summary of SSMO data (1949 -1985). - Obtained from Head Quarters of Department of Irrigation and Drainage Malaysia, Kuala Lumpur. Tidal Information Tide Table 2003 published by the Royal Malaysia Navy for Tg. Gelang Station, Kuantan Sediment Properties Detailed Design Report of Projek Perintis Pemulihan Pantai Pelancongan dengan Menggunakan “Pressure Equalization Module System” di Teluk Cempedak, Kuantan , Pahang Darul Makmur. 59 4.3.1 Beach Profile Survey Hydrographic survey is very important in this study to capture the changes of the nearshore profile when erosion is expected to occur. Four years record of hydrographic survey was obtained in this study. The surveys were undertaken using the conventional survey technique i.e profile measurements were taken using a combination of land-based topographical survey and hydrographic survey techniques. Hydrographic surveys were measured in the convention of m CD but converted to m LSD for civil engineering and construction drawing purpose. The cross-shore plotting covering from the landward property boundary to about 30 m seawards below the L.A.T. The surveys were conducted for 18 chainage lines starting from chainage 100 m to chainage 1800 m. Nevertheless, only 14 monitoring surveys sections were used in this study which includes the area where the PEM system was installed as shown in Figure 4.1. The area of interest starts from chainage 100 in the north to chainage 1400 m in the south direction. The PEM pipe was successfully installed within CH 300 until CH 1300, while CH 100 to CH 300 and CH 1400 are the boundaries of the study area, representing the north and south boundary respectively. In order to determine the variation of depth towards the sea, the depth was captured for each 10 meter interval distance ending at 1250 m seaward. Table 4.2(a) and Table 4.2(b) shows the centerline coordinate points of the selected survey datasets and its corresponding depth at profile end before and after the installation of PEM system respectively. 60 Figure 4.1: Profile Line at Study Area 61 Table 4.2(a): Center line Coordinates of Selected Survey Data set and Its Corresponding Depth (Before Installation of PEM System) Center line Coordinates No. Chainage Northing Easting 1 CH100 11767.00 104137.00 2 CH200 11667.00 104137.00 3 CH300 11567.00 104137.00 4 CH400 11467.00 104137.00 5 CH500 11367.00 104137.00 6 CH600 11267.00 104137.00 7 CH700 11167.00 104137.00 8 CH800 11067.00 104137.00 9 CH900 10967.00 104137.00 10 CH1000 10867.00 104137.00 11 CH1100 10767.00 104137.00 12 CH1200 10667.00 104137.00 13 CH1300 10567.00 104137.00 14 CH1400 10467.00 104137.00 1. CH 100, CH200, CH300 & CH 1400 = NO PEM 2. CH 300 to CH 1300 = PEM and Beach Nourishment Depth at Profile End (m) 2003 -9.00 -9.15 -9.35 -9.40 -9.45 -9.65 -9.55 -9.75 -9.80 -9.75 -9.90 -10.10 -10.25 -10.40 Table 4.2(b): Center line Coordinates of Selected Survey Dataset and Its Corresponding Depth (After Installation of PEM System) Center line Coordinates No. Chainage Northing Easting 1 CH100 11767.00 104137.00 2 CH200 11667.00 104137.00 3 CH300 11567.00 104137.00 4 CH400 11467.00 104137.00 5 CH500 11367.00 104137.00 6 CH600 11267.00 104137.00 7 CH700 11167.00 104137.00 8 CH800 11067.00 104137.00 9 CH900 10967.00 104137.00 10 CH1000 10867.00 104137.00 11 CH1100 10767.00 104137.00 12 CH1200 10667.00 104137.00 13 CH1300 10567.00 104137.00 14 CH1400 10467.00 104137.00 1. CH 100, CH200, CH300 & CH 1400 = NO PEM 2. CH 300 to CH 1300 = PEM and Beach Nourishment Depth at Profile End (m) 2005 2006 2007 -9.65 -9.40 -9.40 -9.65 -9.70 -9.50 -9.75 -9.75 -9.60 -9.80 -9.75 -9.80 -10.00 -9.75 -9.85 -9.90 -9.75 -9.70 -10.00 -9.90 -9.50 -10.10 -10.05 -9.75 -10.25 -10.25 -9.80 -10.40 -10.05 -9.95 -10.45 -10.25 -10.05 -10.55 -10.30 -10.25 -10.60 -10.55 -10.45 -10.65 -10.50 -10.45 62 4.3.2 Wave Data Analysis For Kuantan coast, the only wave data of 20 years or more is obtained from the information of Synoptic Shipboard Meteorological Observation Data (SSMO) of waves off the East Coast. SSMO data are available from 1949 to 1989, a period of 40 years. The main Marsden Square Number used to determine the significant wave height is 2633, 2634, 2635, 2643, 2644, and 2645. The SSMO wave data were used to generate the annual wave and seasonal wave roses as well as for the frequency analysis of exceedance and obtained design waves such as Hs, H 0.137, and etc. In this study, wave data analysis was carried out to determine the effective significant wave height, He, as that which is exceeded only twelve hours per year or only 0.137 % of the time. The SSMO information on waves is obtained from the Coastal Engineering Division of the Malaysia Drainage and Irrigation Department. Figure 4.2 shows the histogram of wave height at the study area. The maximum wave height is recorded as 6 meter while the highest frequency of the wave height occurring is 1.0 m. The dominant wave heights are in the range of 1.0 m to 1.5 m. Histogram Wave Height 3000 2669 2500 Frequency, N 2000 1427 1500 1000 527 500 292 186 56 21 8 2 1 6 1 3 3.5 4 4.5 5 5.5 6 0 0.5 1 1.5 2 2.5 Wave Height,m Wave Height Figure 4.2: Histogram of Design Wave Height 63 The calculation of depth of closure using Hellemeier‟s equation required the significant wave height exceeded 12 hour in a year equivalent to an exceedance probability of 0.137 %. This wave height is determined from a plot of cumulative percentage against wave height as illustrated in Figure 4.3. It can be seen that, the H 0.137 wave was determined to be 3.53 m with a corresponding wave period of 7.85 sec. The corresponding wave period is determined based on the regression analysis as shown in Figure 4.4. Linear relationship between both parameters shows that greater wave height leads to higher wave period. Similarly, based on the analysis using LEO data (DID‟s LEO Station C01, Beserah Kuantan), the value of H 0.137 wave is found to be in the region of 3.5 m too. Wave Height (m) vs % of Exceedance 100.00 90.00 80.00 % of Exceedance 70.00 60.00 H 0.137 = 3.53 m 50.00 40.00 30.00 20.00 10.00 0.00 0.0 1.0 2.0 3.0 4.0 5.0 6.0 Wave Height, H (m) Wave Height Figure 4.3: H 0.137 Wave from SSMO Wave Data (1949-1983) 7.0 64 Relationship between Wave Height (m) and Wave Period (sec) 15 14 13 y = 0.242x + 6.994 12 11 Wave Period, sec 10 9 8 7 6 5 4 3 2 1 0 0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 5.5 6 6.5 7 Wave Height, m Figure 4.4: Relationship between Wave Height and Wave Period 4.3.3 Tidal Height Information Principal tidal levels information such as MHHW, MSL and MLLW are used in the design of the sand nourishment especially in conjunction with PEM system. Tidal information from the Tide Tables published by the Royal Malaysia Navy for Kuantan naval base in 2003 are used for determining the full range and magnitude of tidal variation in the study area. Tidal information is necessary to determine the vertical references of depth. Hallemeier (1981) suggested that the MLW level is important because it is the reference to depth of closure in the original definition. Table 4.3 shows the tide level along the study shoreline recorded in year 2003. The mean low water level 65 is determine based on the average of mean higher low water (MHLW) level and mean lower low water (MLLW) level. Therefore, based on tide level at Tg. Gelang station, the MLW level for the year 2003 is recorded as -0.66 m. Table 4.3: Tidal Level at Tanjung Gelang Station (m, LSD) Tidal Level Highest Astronomical Tide (HAT) Mean Higher High Water (MHHW) Mean Higher Low Water (MHLW) Mean Sea Level (MSL) Mean Lower Low Water (MLLW) Mean Lower High Water (MLHW) Lowest Astronomical Tide (LAT) 4.3.4 2003 2.18 1.65 -0.14 0.24 -1.17 0.61 -1.72 Sediment Properties Sampling is needed to determine sediment characteristics, such as median grain size and grain-size distribution, which affect the beach profile shape and influence, and fill volume requirements. The data for sediment is also required to determine the depth of closure. Significant changes in sediment type, size and colour at a particular nearshore location over time infers that the depth of closure is further seaward. Sediments and laboratory analysis of samples of the beach face above MSL and of the seabed below MSL are the most essential for the sand nourishment design. Both the locations of the public beach area and that in front of the hotel resorts are also required and measured. The sampling and analysis of the sediments are further divided into upper and lower limits of cross-shore profile as well as according to spring and neap tide situation. The beach nourishment region is within Chainage 400 m to Chainage 1300 m whereby the area had been installed with the PEM system. 66 As for this study, due to lack of sediments transport along the coast of Teluk Cempedak, sand nourishment is required for the application of PEM system to rehabilitate the beach. In this case, the PEM system will function to reduce the erosion rate of the sand nourishment. Accordingly, it is required that the sand nourishment be placed directly at the required location starting from the dune face and on the whole beach slope. Figure 4.5 shows the location of the design size sand that had been placed along the beach. Detail about the design sand size is described in Table 4.4. The median sand size (D50) ranged from 0.280 mm to 0.820 mm for lower beach and upper beach face respectively from CH 375 to CH 600 and CH 1100 to CH1350. Similarly, from CH 600 to CH 1100, the median sand size (D50) ranged from 0.330 mm to 1.000 mm for lower beach and upper beach face respectively. Table 4.5(a) and Table 4.5(b) show the results of the sand size analysis at the study area for pre-project condition. Based on the available sediment data in this study, it is found that the sand size for pre-project condition ranged from 1.483 mm to 0.969 mm for both locations i.e public beach and hotel beach above the MSL level in which describe the type of the sand is coarser. In contrast, the finer sand could be found at the locations which fall in the range of 0.948 mm to 0.842 mm below the MSL level. This trend typically explains that beach sediments are expected to be naturally sorted with the coarser sediments being deposited on the upper part of the beach while finer sediments get deposited further seawards. 67 Upper Beach Face Lower Beach Face D50 = 0.820 mm D50 = 0.280 mm D50 = 0.820 mm D50 = 0.280 mm D50 = 0.820 mm D50 = 0.280 mm D50 = 1.000 mm D50 = 0.330 mm D50 = 1.000 mm D50 = 0.330 mm D50 = 1.000 mm D50 = 0.330 mm D50 = 1.000 mm D50 = 0.330 mm D50 = 1.000 mm D50 = 0.330 mm D50 = 0.820 mm D50 = 0.280 mm D50 = 0.820 mm D50 = 0.280 mm D50 = 0.820 mm D50 = 0.280 mm CH 100 CH 200 CH 300 CH 400 CH 500 Hyaat Hotel CH 600 CH 700 CH 800 Faber/Sheraton Hotel CH 900 CH 1000 CH 1100 CH 1200 CH 1300 CH 1400 Figure 4.5: Plan View of Location for Design Size Sand Table 4.4: Summary of Design Size Ranges for Borrow Sand Parameter Size (mm) Parameter Size (mm) Parameter Size (mm) Parameter Size (mm) From CH 375 to CH600 and CH.1100 to CH1350 (Sand Sizes on the Upper Beach Face) D16 D50 0.282 0.820 From CH 375 to CH600 to CH.1100 to CH1350 (Sand Sizes on the Lower Beach Face) D16 D50 0.168 0.280 For the Middle Stretch From CH600 to CH.1100 (Sand Sizes on the Upper Beach Face) D16 D50 0.550 1.000 For the Middle Stretch From CH600 to CH.1100 (Sand Sizes on the Lower Beach Face) D16 D50 0.230 0.330 D84 1.600 D84 0.434 D84 1.300 D84 0.520 68 Table 4.5(a): Sand Size Analysis (upper beach face for pre-project condition) Location PB - aN PB - aS Mean Location HB - aN HB - aS Mean D16 0.220 0.250 0.235 D16 0.550 0.300 0.425 Above MSL – Coarser Sand (mm) D50 D84 BAND 0.330 0.820 0.600 0.850 1.400 1.150 0.590 1.110 0.875 D50 D84 BAND 1.000 1.300 0.750 0.600 1.100 0.800 0.800 1.200 0.775 SORTED INDEX 1.818 1.353 1.483 SORTED INDEX 0.750 1.333 0.969 Table 4.5(b): Sand Size Analysis (lower beach face for pre-project condition) Location PB - bN PB - bS Mean Location HB - bN HB - bS Mean Description:PB - Public beach; Band = D84-D16; a – above MSL; D16 0.095 0.100 0.098 D16 0.120 0.120 0.120 Below MSL – Finer Sand (mm) D50 D84 BAND 0.150 0.240 0.145 0.140 0.230 0.130 0.145 0.235 0.138 D50 D84 BAND 0.200 0.310 0.190 0.180 0.250 0.130 0.190 0.280 0.160 HB - Hotel Beach; Sorted Index = Band/D50; b - below MSL; N - Neap sample; SORTED INDEX 0.967 0.929 0.948 SORTED INDEX 0.950 0.722 0.842 S - Spring Sample 69 4.4 Determination of Depth of Closure from Beach Profile Survey The depth of closure was determined at 14 chainage lines (CH 100 to CH 1400) for both pre and post installation condition. For both conditions, FDC method was used to determine the closure depth by applying 0.25 m criteria line which corresponds to the accuracy of hydrographic surveys. The depth of closure for each chainage is expected to occur at the middle-shore. Figures of representative profiles are presented for better appreciation of the analysis. The discussion is presented beginning from the north direction to the south direction starting from CH 100 and ending at CH 1400. It is also useful to note that the movement of sediment is from north to south. 4.5 Depth of Closure for Pre-Project Condition (2003) The beach response to the PEM system can be observed from the temporal variation of its depth of closure. In order to compare the variations of depth, the closure depth before the installation of PEM need to be determined first. 4.5.1 Closure Depth at CH 700 and CH 1400 Based on analysis, it is found that FDC method does not produce a closure at these chainages whereby according to the FDC criterion line, all the FDC lines remain below the limit line i.e 25 cm. As for information, CH 700 was installed with PEM pipe. 70 4.5.2 Closure Depth at CH 100 CH 100 is located at the northern part of the beach where the granite headlands of Tanjung Pelindung Tengah is located. Based on the graph below, it is proven that the beach level is higher in which at the first 0 m distance, the beach level of about 50 m LSD was recorded and it is sharply decreased seaward. The first closure point was registered at 280 m from the baseline as -1.2 m and the reopening point begins at a distance 350 m until close at 360 m. Sand bar appears at 410 m to 520 m due to the migration of the sediment towards the sea. Nevertheless, the bed elevation remains stable and the closure zone was found to be at the middle-shore located at 630 m with the depth of -3.45 m LSD towards the sea. BEACH PROFILE FOR CHAINAGE 100 (CH 100) 50 5 4.75 4.5 4.25 40 4 3.75 3.5 30 3.25 hcm= -3.45 m @ 630 m 2.75 20 2.5 2.25 2 1.75 10 1.5 1.25 1 0 0.75 0.5 0.25 -10 0 60 160 260 360 460 560 660 760 860 960 1060 1160 1260 Distance, m Mar-03 Sep-03 MEAN MLW FDC Criteria Line Figure 4.6: Closure Depth (hc) at CH 100 for 2003 Pre-Project Profile FDC, m Depth, m 3 71 4.5.3 Closure Depth at CH 200 Similar to CH 100, CH 200 is placed at the northern part of the beach where the granite headlands of Tanjung Pelindung Tengah is located. Figure 4.7 shows that the beach level is still higher at 0 m with the value of about 50 m LSD and it sharply decreases towards the sea. The profile shows that the beach is stable along the chainage indicated that no significant bed elevation change occurred. The innershore closure depth was recorded as -2.45 m LSD and located at 310 m from the baseline. The next closure point was found to be at the middle-shore at a distance of 680 m with the depth of -4.75 m LSD and deemed as an effective closure depth for CH 200. BEACH PROFILE FOR CHAINAGE 200 (CH 200) 50 5 4.75 4.5 4.25 40 4 3.75 3.5 30 3.25 2.75 20 2.5 hci= -2.45 m @ 310m 2.25 hcm= -4.75 m @ 680m 2 1.75 10 1.5 1.25 1 0 0.75 0.5 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-03 Sep-03 MEAN MLW FDC Criteria Line Figure 4.7: Closure Depth (hc) at CH 200 for 2003 Pre-Project Profile FDC, m Depth, m 3 72 4.5.4 Closure Depth at CH 300 Figure 4.8 below shows that the beach level starts at higher level with the value of about 23 m LSD. The FDC method shows no change in shoreline position although there is a significant change in bed elevation about 120 m to 230 m after the shoreline. The beach is stable after this point towards the sea and thus, the effective closure depth was recorded as -3.35 m LSD at a distance of 370 m from the baseline. The closure zone starts at 370 m from the baseline and closes at a distance of 840 m from the baseline. BEACH PROFILE FOR CHAINAGE 300 (CH 300) 5 4.75 4.5 20 4.25 4 3.75 15 3.5 3.25 Depth, m 10 2.75 hci= -3.35 m @ 370m 2.5 2.25 5 2 1.75 1.5 0 1.25 1 0.75 -5 0.5 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-03 Sep-03 MEAN MLW FDC Criteria Line Figure 4.8: Closure Depth (hc) at CH 300 for for 2003 Pre-Project Profile FDC, m 3 73 4.5.5 Closure Depth at CH 400 Figure 4.9 below shows that the shoreline is moved shoreward about 40 m between March 2003 and September 2003.The FDC method registered a hci of -2.65 m LSD and hcm of -4.75 LSD at 170 m and 580 m from the baseline respectively. A sand bar appears at distance 120 to 180 m just after the shoreline indicates that the sediment has migrated seaward. Significant bed elevation changes also occur at the outer-shore bar at 1020 m from the baseline. Accordingly, the reopening zone was found to be near the offshore limit indicating that the active movement of sediment exists. The effective hc is -2.65 m LSD. BEACH PROFILE FOR CHAINAGE 400 (CH 400) 4 5 4.75 4.5 2 4.25 4 3.75 0 3.5 hci= -2.65 m @ 170m -2 3 2.75 hcm= -4.75 m @ 580m 2.5 2.25 -4 2 1.75 1.5 -6 1.25 1 0.75 -8 0.5 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-03 Sep-03 MEAN MLW FDC Criteria Line Figure 4.9: Closure Depth (hc) at CH 400 for for 2003 Pre-Project Profile FDC, m Depth, m 3.25 74 4.5.6 Closure Depth at CH 500 At CH 500, the FDC plot exceeds the 0.25 m criteria line above MLW and closes 530 m from the baseline. The first down-crossing FDC line is recorded to be at 530 m from the baseline. Therefore, the effective FDC hc for CH 500 is thus -4.65 m and 530 m from the baseline. The closure zone was to be found at 530 m to 950 m from the baseline. The significant bed elevation change only occurs at the outershore region indicating that the beach is unstable. BEACH PROFILE FOR CHAINAGE 500 (CH 500) 6 5 4.75 5 4.5 4 4.25 3 4 2 3.75 3.5 1 3.25 0 2.75 -2 2.5 hcm= -4.65 m @ 530m -3 2.25 2 -4 1.75 -5 1.5 -6 1.25 1 -7 0.75 -8 0.5 -9 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-03 Sep-03 MEAN MLW FDC Criteria Line Figure 4.10: Closure Depth (hc) at CH 500 for 2003 Pre-Project Profile FDC, m Depth, m 3 -1 75 4.5.7 Closure Depth at CH 600 A closure zone appears at a distance of 220 m to 700 m from the baseline. The inner-shore closure depth (hci) was recorded as -3.45 m LSD at 220 m as the inner-shore bar does not contribute to the shoreline changes. The middle-shore closure depth was found to be at 700 m with the depth of -6.25 m. The effective hc for CH 600 is -3.45 m LSD which lies 220 m from the shoreline. Nevertheless, in the outer-shore region, the bed elevation appears to produces some changes beginning from 920 m towards the sea indicating that the area is classified as reopening zone. BEACH PROFILE FOR CHAINAGE 600 (CH 600) 8 2 7 6 1.75 5 4 3 1.5 2 1 1.25 -1 hci= -3.45 m @ 220m -2 1 -3 hcm= -6.25 m @ 700m -4 0.75 -5 -6 -7 0.5 -8 -9 0.25 -10 -11 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-03 Sep-03 MEAN MLW FDC Criteria Line Figure 4.11: Closure Depth (hc) at CH 600 for 2003 Pre-Project Profile FDC, m Depth, m 0 76 4.5.8 Closure Depth at CH 800 Figure 4.12 below shows two closure points along the profile line for CH 800. The FDC method plot exceeds the 0.25 m criteria line above MLW and closes 130 m from the baseline. The effective FDC hc, for CH 800 is thus the first closure point -1.55 m LSD and 130 m from the baseline. Based on FDC method, the significant bed elevation change only occurs at distance 120 m which varies about 0.8 m depth from March 2003 to September 2003. After that point, the sea bed elevation remains stable whereby the variations are less than 0.25 m below the criteria line and thus recognized as closure zone. Closure depth, hco registered as -8.45 m and located 940 m from the baseline. BEACH PROFILE FOR CHAINAGE 800 (CH800) 8 2 6 1.75 hci= -1.55 m @ 130m 4 1.5 2 1.25 -2 hco= -8.45 m @ 940m 1 -4 0.75 -6 0.5 -8 0.25 -10 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-03 Sep-03 MEAN MLW FDC Criteria Line Figure 4.12: Closure Depth (hc) at CH 800 for 2003 Pre-Project Profile FDC, m Depth, m 0 77 4.5.9 Closure Depth at CH 900 Similar to CH 800, at least two closure points appear at distance of 170 m and 950 m with depth of -2.65 m and -8.55 m respectively. It is found that the inner-shore bar does not contribute to the shoreline changes. No significant bed elevation change occurs after the first closure point indicating that the beach is stable. BEACH PROFILE FOR CHAINAGE 900 (CH900) 8 2 6 1.75 hci= -2.65 m @ 170m 4 1.5 2 1.25 hco= -8.55 m @ 950m -2 1 -4 0.75 -6 0.5 -8 0.25 -10 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-03 Sep-03 MEAN MLW FDC Criteria Line Figure 4.13: Closure Depth (hc) at CH 900 for 2003 Pre-Project Profile FDC, m Depth, m 0 78 4.5.10 Closure Depth at CH 1000 A closure zone appears at a distance of 190 m to 690 m from the baseline. The inner-shore closure depth (hci) was recorded as -2.85 m LSD at 220 m as the inner-shore bar does not contribute to the shoreline changes. The effective hc for CH 1000 is -2.85 m LSD which lies 220 m from the baseline. The bed elevation change shows no significant variations after this point towards the sea. BEACH PROFILE FOR CHAINAGE 1000 (CH1000) 8 2 6 1.75 hci= -2.85 m @ 190m 4 1.5 2 1.25 -2 1 -4 0.75 -6 0.5 -8 0.25 -10 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-03 Sep-03 MEAN MLW FDC Criteria Line Figure 4.14: Closure Depth (hc) at CH 1000 for 2003 Pre-Project Profile FDC, m Depth, m 0 79 4.5.11 Closure Depth at CH 1100 Applying the FDC method, a closure zone is observed at CH 1100 from 580 m to 880 m and the first re-opening point appeared at the inner-shore bar 190 m from the baseline as shown in Figure 4.15. The inner-shore closure depth is recorded as -2.55 m at 190 m distance from the baseline. Next, the second closure depth is observed as -6.1 m LSD which lies 580 m from the baseline. Ah CH 1100, the effective hc is therefore -6.1 m at 580 m from the baseline. BEACH PROFILE FOR CHAINAGE 1100 (CH1100) 14 5 4.75 12 4.5 4.25 10 4 8 hci= -2.55 m @ 190m 3.75 3.5 6 3.25 3 2.75 2 2.5 0 2.25 2 -2 hcm= -6.1m @ 580m -4 1.75 1.5 1.25 -6 1 -8 0.75 0.5 -10 0.25 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-03 Sep-03 MEAN MLW FDC Criteria Line Figure 4.15: Closure Depth (hc) at CH 1100 for 2003 Pre-Project Profile FDC, m Depth, m 4 80 4.5.12 Closure Depth at CH 1200 The re-opening zone was observed at a distance of 860 m to 1140 m from the baseline where the FDC line up-crosses and down-crosses the 0.25 m criteria line alternately along the profile. This area is considered an area of significant sediment transport activity. However, the closure depth was not found within this area. The effective hc for CH 1200 is -4.6 m LSD which lies 340 m at the inner-shore limit from the baseline. The shoreline is change due to the inner-shore bar located at 190 m from the baseline. BEACH PROFILE FOR CHAINAGE 1200 (CH1200) 14 5 4.75 12 4.5 4.25 10 4 8 3.75 hci= -4.6 m @ 340m 6 3.5 3.25 3 2.75 2 2.5 0 2.25 2 -2 1.75 -4 1.5 1.25 -6 1 -8 0.75 0.5 -10 0.25 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-03 Sep-03 MEAN MLW FDC Criteria Line Figure 4.16: Closure Depth (hc) at CH 1200 for 2003 Pre-Project Profile FDC, m Depth, m 4 81 4.5.13 Closure Depth at CH 1300 The re-opening zone was observed at a distance of 360 m to 870 m from the baseline where the FDC line up-crosses and down-crosses the 0.25 m criteria line alternately along the profile. This area is considered an area of significant sediment transport activity. The effective hc for CH 1300 was found to be -2.35 m LSD which lies 210 m at the inner-shore limit from the baseline. BEACH PROFILE FOR CHAINAGE 1300 (CH1300) 32 5 30 4.75 28 4.5 26 4.25 24 4 22 3.75 20 3.5 18 3.25 hci= -2.35 m @ 210m Depth, m 14 3 2.75 12 10 2.5 8 2.25 6 2 4 1.75 2 1.5 0 1.25 -2 1 -4 0.75 -6 0.5 -8 0.25 -10 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-03 Sep-03 MEAN MLW FDC Criteria Line Figure 4.17: Closure Depth (hc) at CH 1300 for 2003 Pre-Project Profile FDC, m 16 82 4.6 Summary of Depth of Closure for Pre-Project Condition The analysis of depth of closure before installation of PEM system revealed that multiple closure across the profile produce at least three closure points as shown in Table 4.6. Applying the FDC method, whereby the criteria line was set at 0.25 m, the FDC line was recorded to be starting below the criteria line for all chainage. Therefore, it is easy to note that the line down-crosses the limit line deemed as closure point or reopening point. Out of 14 chainages, only two chainage were not registered i.e CH 700 and Ch 1400. Unfortunately, the FDC line remained below the criteria line along the profile line in which the closure depth does not existed. It is also found that the movement of sediment is active near the outer-shore zone at all chainages. Based on Table 4.6, the average hc is recorded as -2.58 m below MLW and at 319 m from the baseline. Table 4.6: Closure Depth for 2003 Pre-Project Profile FDC hc (Mac 2003 –September 2003) hci, hcm, Effective hc, Distance Chainage (m) (m) (m) Offshore, LSD LSD MLW (m) CH 100 na -3.45 -2.79 630 CH 200 -2.45 -4.75 -4.09 680 CH 300 -3.35 na -2.69 370 CH 400 -2.65 -4.75 -1.99 170 CH 500 na -4.65 -3.99 530 CH 600 -3.45 -6.25 -2.79 220 CH 700 na na na na CH 800 -1.55 -8.45 -0.89 130 CH 900 -2.65 -8.55 -1.99 170 CH 1000 -2.85 na -2.19 190 CH 1100 -2.55 -6.1 -1.89 190 CH 1200 -4.6 na -3.94 340 CH 1300 -2.35 na -1.69 210 CH 1400 na na na na Average -2.85 -5.87 -2.58 319 hci = innershore closure depth; hcm = middleshore closure depth; hco=outershore closure depth; na=not available 83 4.7 Depth of Closure for Post-Project Condition The closure depths after the installation of PEM system beginning from year 2005 to 2007 were determined and presented in the following section. Similar to analysis of closure depth before the installation of PEM system, the FDC method was used and the absolute bed change along the same profile over two consecutive surveys is plotted to describe the profile change along the profile line as well as to determine the effective depth of closure, hc. The closure depth after the installation of PEM system was compared with the analysis before the installation to reveal the response of beach due to this system. 4.8 2005 Beach Profile Figures 4.18 to Figure 4.31 show the beach profile surveys for all chainages beginning from CH 100 and ending at CH 1400. Most of the profile lines show that the change in bed elevation is varied between two consecutives survey indicating that the movement of sediment is highly active within the PEM area. It is useful to note that, the PEM system was installed in 2004 in combination with beach nourishment activity and the first survey was carried out in March 2005. Therefore, it is reliable if the bed profile is varied since the sand starts to move seaward and shoreward before it remains stable to achieve the equilibrium profile. 84 4.8.1 Closure Depth at CH 100 Figure 4.18 below shows the beach profile for CH 100. The closure point was observed at -1.55 m LSD located at 280 m from the baseline. The reopening point is recorded at 350 m until it closes at 410 m. The insignificant bed elevation changes was observed at the middleshore area and produce a closure point at 730 m from the base line with the depth of -4.9 m LSD. The outershore closure depth was found to be at -8.1 m LSD located 1010 m far away from the shoreline. However, hcm was qualified as effective closure depth. 18 17.5 17 16.5 16 15.5 15 14.5 14 13.5 13 12.5 12 11.5 11 10.5 10 9.5 9 8.5 8 7.5 7 6.5 6 5.5 5 4.5 4 3.5 3 2.5 2 1.5 1 0.5 0 hci= -1.55 m @ 280m hcm= -4.9 m @ 730m hco= -8.1 m @ 1010m 60 260 460 660 860 1060 Distance, m Mar-05 Oct-05 MEAN MLW FDC Criteria Line Figure 4.18: Closure Depth (hc) at CH 100 for 2005 Post-Project Profile 1260 FDC, m Depth, m BEACH PROFILE FOR CHAINAGE 100 (CH 100) 60 58 56 54 52 50 48 46 44 42 40 38 36 34 32 30 28 26 24 22 20 18 16 14 12 10 8 6 4 2 0 -2 -4 -6 -8 -10 85 4.8.2 Closure Depth at CH 200 The insignificant change in bed elevation at the innershore zone does not contribute to the shoreline changes. Multiple closure point was recorded along the profile line of CH 200 as shown in Figure 4.18. The first downcrossing FDC line was found at -2.35 m LSD and 270 m from the baseline. The middleshore closure point is registered at 710 m from the baseline with the depth of -5.05 m LSD thus deemed as an effective closure depth since the variation in bed elevation create a small change. Last but not least, the outershore closure was observed at -8.65 m and 1030 m from the baseline. BEACH PROFILE FOR CHAINAGE 200 (CH 200) 50 5 4.75 4.5 4.25 40 4 3.75 3.5 30 hci= -2.35 m @ 270m 3.25 hcm= -5.05 m @ 710m 2.75 20 2.5 2.25 hco= -8.65 m @ 1030m 2 1.75 10 1.5 1.25 1 0 0.75 0.5 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-05 Oct-05 MEAN MLW FDC Criteria Line Figure 4.19: Closure Depth (hc) at CH 200 for 2005 Post-Project Profile FDC, m Depth, m 3 86 4.8.3 Closure Depth at CH 300 Applying the FDC method, the first downcrossing FDC line was found to be at 2.25 m LSD located 180 m from the baseline. A reopening zone appears at the middleshore area at 680 m to 860 m from the baseline. This indicates that the active movement of the sediment is occurring. The middleshore closure point is registered at 3.95 m and 520 m from the baseline. However, hci was qualified as effective closure depth. BEACH PROFILE FOR CHAINAGE 300 (CH 300) 5 4.75 4.5 20 4.25 4 3.75 hci= -2.25 m @ 180m 15 3.5 3.25 Depth, m hcm= -3.95 m @ 520m 2.75 2.5 2.25 5 2 1.75 1.5 0 1.25 1 0.75 -5 0.5 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-05 Oct-05 MEAN MLW FDC Criteria Line Figure 4.20: Closure Depth (hc) at CH 300 for 2005 Post-Project Profile FDC, m 3 10 87 4.8.4 Closure Depth at CH 400 At CH 400, the significant bed elevation changes were found at the innershore area thus contributing to shoreline changes. This phenomena showed that the sediment is moving towards the sea. The first closure point only can be found 360 m away from baseline associated with depth of -3.65 m LSD. The effective closure depth was registered at the middleshore zone -5.2 m LSD located at 640 m from the baseline. The sea bed is stable after this point whereby the FDC line remains below the criteria line. BEACH PROFILE FOR CHAINAGE 400 (CH 400) 4 3 hci= -3.4 m @ 280m 2.75 2 2.5 2.25 0 2 1.75 1.5 -4 1.25 1 -6 0.75 0.5 -8 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-05 Oct-05 MEAN MLW FDC Criteria Line Figure 4.21: Closure Depth (hc) at CH 400 for 2005 Post-Project Profile FDC, m Depth, m hcm= -5.2 m @ 640m -2 88 4.8.5 Closure Depth at CH 500 Similar to CH 400, the significant changes in bed elevation occur at the innershore area thus provide a shoreline change about 20 m from March 2005 to October 2005. The innershore closure point was registered to be -3.15 m LSD and 220 m from the baseline however does not qualify as effective closure depth. The hcm was chosen to be effective closure depth as the FDC line remains below the FDC criteria line of 0.25 m. This indicates that no significant change in bottom elevation and no significant net sediment transport between the nearshore and offshore occurred. The point was found at 510 m from the baseline with depth of -4.85 m. BEACH PROFILE FOR CHAINAGE 500 (CH 500) 6 2.5 hci= -3.15 m @ 220m 4 2.25 2 2 1.75 0 hcm= -4.85 m @ 510 m -2 1.25 1 -4 0.75 -6 0.5 -8 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-05 Oct-05 MEAN MLW FDC Criteria Line Figure 4.22: Closure Depth (hc) at CH 500 for 2005 Post-Project Profile FDC, m Depth, m 1.5 89 4.8.6 Closure Depth at CH 600 A reopening zone appears at a distance of 220 m to 590 m from the baseline. The zone of about 370 m thus describe that the movement of sediment is highly active. This scenario affected the change of the shoreline which shows that the PEM system is functioning. The effective closure depth can be found away from the shoreline which is located 790 m from the baseline and placed at -7.00 m LSD. BEACH PROFILE FOR CHAINAGE 600 (CH 600) 8 3 2.75 6 hci= -7.00 m @ 790m 2.5 4 2.25 2 2 1.75 -2 1.5 1.25 -4 1 -6 0.75 -8 0.5 -10 0.25 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-05 Oct-05 MEAN MLW FDC Criteria Line Figure 4.23: Closure Depth (hc) at CH 600 for 2005 Post-Project Profile FDC, m Depth, m 0 90 4.8.7 Closure Depth at CH 700 By applying the FDC method, the FDC line is seen to be upcrossing and downcrossing alternately within the innershore area. This phenomena was found to be the same as at CH 400, CH500 and CH 600. It is useful to note that the PEM pipe was installed at these chainages. Again, the PEM shows a positive sign that the system is functioning to accumulate sand on the nearshore zone. The effective closure depth lies 730 m from the baseline and placed at -6.65 m LSD. BEACH PROFILE FOR CHAINAGE 700 (CH700) 8 3 2.75 hci= -6.65 m @ 730m 6 2.5 4 2.25 2 2 1.75 -2 1.5 1.25 -4 1 -6 0.75 -8 0.5 -10 0.25 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-05 Oct-05 MEAN MLW FDC Criteria Line Figure 4.24: Closure Depth (hc) at CH 700 for 2005 Post-Project Profile FDC, m Depth, m 0 91 4.8.8 Closure Depth at CH 800 The beach profile at CH 800 shows that the reopening zone starts at distance of 180 m and closes at a distance of 980 m from the baseline. This phenomena indicates that the active sediment transport is occurring within the distance. The beach is stable after this point and remains below the criteria line up to distance 1100 m. It is very difficult to determine the effective closure depth due to the irregular changes in bottom elevation. Therefore, no closure depth was found at CH 800. BEACH PROFILE FOR CHAINAGE 800 (CH800) 8 3 2.75 6 2.5 4 2.25 2 2 0 -2 1.5 1.25 -4 1 -6 0.75 -8 0.5 -10 0.25 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-05 Oct-05 MEAN MLW FDC Criteria Line Figure 4.25: Closure Depth (hc) at CH 800 for 2005 Post-Project Profile FDC, m Depth, m 1.75 92 4.8.9 Closure Depth at CH 900 The beach profile at CH 900 shows that the reopening zone appears at a distance of 220 m and closes at a distance of 750 m from the baseline. Similar to CH 800, this phenomena indicates that the active sediment transport occurrs within the distance. Refreshing that the closure depth is defined as the most landward depth where there is no significant change in bed elevation, thus closure depth at CH 900 could not be found due to irregular changes in bottom elevation within the reopening zone. However, this shows a positive sign that the PEM system is functioning along the profile line at this chainage. BEACH PROFILE FOR CHAINAGE 900 (CH900) 8 3 2.75 6 2.5 4 2.25 2 2 1.75 -2 1.5 1.25 -4 1 -6 0.75 -8 0.5 -10 0.25 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-05 Oct-05 MEAN MLW FDC Criteria Line Figure 4.26: Closure Depth (hc) at CH 900 for 2005 Post-Project Profile FDC, m Depth, m 0 93 4.8.10 Closure Depth at CH 1000 At CH 1000, a closure zone appears at 340 m and closes at distance of 660 m from the base line. At least, two innershore closure points was observed at CH 1000, however, the outermost closure point is deemed as a closure point i.e hci = -4.25 m LSD, located 340 m from the baseline. The middleshore closure point was found to be at -6.45 m located 660 m from the baseline. Therefore, the effective closure depth was qualified as the outermost innershore closure point. BEACH PROFILE FOR CHAINAGE 1000 (CH1000) 8 3 2.75 6 2.5 4 2.25 2 2 1.75 hci= -4.25 m @ 340m -2 1.5 hcm= -6.45 m @ 660m -4 1.25 1 -6 0.75 -8 0.5 -10 0.25 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-05 Oct-05 MEAN MLW FDC Criteria Line Figure 4.27: Closure Depth (hc) at CH 1000 for 2005 Post-Project Profile FDC, m Depth, m 0 94 4.8.11 Closure Depth at CH 1100 The reopening zone exists again however this time the zone appears at the middleshore area located 440 m from the baseline and lasted until approach the offshore zone. The innershore closure point in which represent the effective closure depth was found to be at 220 m from the baseline and placed -3.15 m LSD. BEACH PROFILE FOR CHAINAGE 1100 (CH1100) 14 3 12 2.75 10 2.5 8 2.25 hci or hc = -3.15 m @ 220m 6 2 4 1.5 0 1.25 -2 1 -4 0.75 -6 0.5 -8 0.25 -10 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-05 Oct-05 MEAN MLW FDC Criteria Line Figure 4.28: Closure Depth (hc) at CH 1100 for 2005 Post-Project Profile FDC, m Depth, m 1.75 2 95 4.8.12 Closure Depth at CH 1200 At CH 1200, a sand bar was found to be at distance of 490 m to 610 m from the baseline. The middleshore closure point (hcm) is registered on this sand bar which is located 580 m from the baseline and placed -5.55 m LSD. However this does not qualify as an effective closure depth. Nevertheless, two others closure point appear along the profile line i.e hci -2.90 m LSD and located 230 m from the baseline, and hco -8.65 m LSD located 860 m from the baseline. Using FDC method, hci is deserved to be as an effective closure depth. It is also found that the beach seemed to be eroded since the shoreline had shifted back to the land. This might happen due to several factors. BEACH PROFILE FOR CHAINAGE 1200 (CH1200) 14 10 9.5 12 9 8.5 10 8 8 7.5 hci= -2.90 m @ 230m 6 7 6.5 6 5.5 2 5 0 4.5 4 hci= -5.55 m @ 580m -2 3.5 hci= -8.65 m @ 860m -4 3 2.5 -6 2 -8 1.5 1 -10 0.5 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-05 Oct-05 MEAN MLW FDC Criteria Line Figure 4.29: Closure Depth (hc) at CH 1200 for 2005 Post-Project Profile FDC, m Depth, m 4 96 4.8.13 Closure Depth at CH 1300 The significant bed elevation change appears along the profile line at CH 1300. The most obvious change was observed at 860 m from the baseline towards the sea. The profiles envelope first closes at -4.8 m LSD, 350 m from the baseline. Another closure point is detected at -7.4 m LSD at 670 m from the baseline and represents as hcm. The effective closure depth was found to be at 670 m due to insignificant bed activity. Therefore the closure depth is recorded to be at -7.4 m LSD. BEACH PROFILE FOR CHAINAGE 1300 (CH1300) 32 10 30 9.5 28 9 26 8.5 24 8 22 7.5 20 hci= -4.8 m @ 350m 18 7 6.5 16 Depth, m hcm= -7.4 m @ 670m 12 5.5 10 5 8 4.5 6 4 4 3.5 2 3 0 2.5 -2 2 -4 1.5 -6 1 -8 0.5 -10 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-05 Oct-05 MEAN MLW FDC Criteria Line Figure 4.30: Closure Depth (hc) at CH 1300 for 2005 Post-Project Profile FDC, m 6 14 97 4.8.14 Closure Depth at CH 1400 Figure 4.31 below shows the beach profile for CH 1400. The graph illustrates that there is no shoreline change occurring at this chainage even though insignificant bed elevation appears 250 m after the shoreline. The hci closure is detected at -3.6 m LSD located 260 m from the baseline however does not recognize effective closure depth. The hcm is chosen as effective depth since the FDC line remains below the limit line. The closure point was found to be at -6.15 m LSD, 480 m from the baseline. BEACH PROFILE FOR CHAINAGE 1400 (CH1400) 50 5 48 4.75 46 44 4.5 42 4.25 40 38 4 36 3.75 34 32 3.5 30 3.25 28 hci= -3.6 m @ 260m 24 Depth, m 3 2.75 22 20 2.5 18 hcm= -6.15 m @ 480m 16 2.25 14 2 12 10 1.75 8 1.5 6 4 1.25 2 1 0 -2 0.75 -4 0.5 -6 -8 0.25 -10 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-05 Oct-05 MEAN MLW FDC Criteria Line Figure 4.31: Closure Depth (hc) at CH 1400 for 2005 Post-Project Profile FDC, m 26 98 4.9 Summary of Depth of Closure for 2005 Post-Project Condition A summary of depths of closure for 2005 profiles is presented in Table 4.7 below. From the analysis, the significant bed elevation change occurred at most of the chainages along the profile line. The average of the effective closure depth, hc was recorded as -4.32 m MLW and this value is deeper compared to the beach profile for 2003. This indicates that the depth increment occurs in bed elevation. The closure point was also detected further seaward which lies 670 m from the baseline. As a conclusion, the PEM system was proven to increase the deposition of materials on the foreshore, thereby building up the beach from the sediments transported along the coast. Table 4.7: Closure Depth for 2005 Post-Project Profile FDC hc (Mac 2005 –October 2005) Chainage hci, (m) LSD hcm, (m) LSD hco, (m) MLW Effective hc, (m) MLW CH 100 -1.55 -4.9 -8.1 CH 200 -2.35 -5.05 -8.65 CH 300 -2.25 -3.95 na CH 400 -3.4 -5.2 na CH 500 -3.15 -4.85 na CH 600 -7.00 na na CH 700 -6.65 na na CH 800 na na na CH 900 na na na CH 1000 -4.25 -6.45 na CH 1100 -3.15 na na CH 1200 -2.90 -5.55 -8.65 CH 1300 -4.8 -7.4 na CH 1400 -3.6 -6.15 na Average -3.75 -5.50 -8.47 hci = innershore closure depth; hcm = middleshore closure depth; na=not available Distance Offshore, (m) -4.24 730 -4.39 710 -1.59 180 -4.54 640 -4.19 510 -6.34 790 -5.99 730 na na na na -3.59 340 -2.49 220 -2.24 230 -6.74 670 -5.49 480 -4.32 519 hco=outershore closure depth; 99 4.10 2006 Beach Profile The 2006 beach profiles were analyzed and results are presented have indicates that the significant bed changes occurred along the profile lines similar to the 2005 profiles especially at the PEM areas. Figure 4.32 to Figure 4.45 shows the profile survey for CH 100 until CH 1400. 4.10.1 Closure Depth at CH 100 The significant change in bed elevation appears to start at the shoreline before it become stable at 530 m from the baseline. The effective closure depth (hc) can be found only 50 m just after the end point of significant change in bed elevation i.e 580 m from the baseline. This point was chosen in accordance to the FDC method whereby there is no significant change observed after this point and seaward. Therefore, the closure depth is qualified to be -3.35 m LSD. BEACH PROFILE FOR CHAINAGE 100 (CH 100) 60 7 6.75 6.5 6.25 50 6 5.75 hcm= -3.35 m @ 580m 5.5 5.25 40 5 4.75 4.5 4 3.75 3.5 3.25 20 FDC, m Depth, m 4.25 30 3 2.75 2.5 2.25 10 2 1.75 1.5 1.25 0 1 0.75 0.5 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-06 Oct-06 MEAN MLW FDC Criteria Line Figure 4.32: Closure Depth (hc) at CH 100 for 2006 Post-Project Profile 100 4.10.2 Closure Depth at CH 200 At CH 200, the significant bed elevation occurs along the survey line. The innershore area shows the obvious variations in bottom elevation located 150 m to 590 m from the baseline, however does not contribute to shoreline changes. The effective hc was detected to be at 720 m from the baseline and placed -5.05 m LSD. BEACH PROFILE FOR CHAINAGE 200 (CH 200) 50 7 6.75 6.5 6.25 6 40 5.75 5.5 5.25 5 4.75 30 4.5 hcm= -5.05 m @ 720m 3.75 20 3.5 3.25 3 2.75 2.5 10 2.25 2 1.75 1.5 1.25 0 1 0.75 0.5 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-06 Oct-06 MEAN MLW FDC Criteria Line Figure 4.33: Closure Depth (hc) at CH 200 for 2006 Post-Project Profile FDC, m Depth, m 4.25 4 101 4.10.3 Closure Depth at CH 300 The shoreline was established at CH 300 although the innershore area shows significant changes in bed elevation. The first downcrossing FDC criteria line was found to be at -2.65 m LSD and located 220 m from the baseline (see Figure 4.34). A reopening point is registered at 340 m of the baseline until closes at 670 m seaward. At this point, the hcm closure point was detected with depth of -4.95 m LSD and thus recognized as effective closure depth. BEACH PROFILE FOR CHAINAGE 300 (CH 300) 4 5 4.75 4.5 2 4.25 4 hci= -2.65 m @ 220m 3.75 0 3.5 3.25 hcm= -4.95 m @ 670m Depth, m -2 2.75 2.5 2.25 -4 2 1.75 1.5 -6 1.25 1 0.75 -8 0.5 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-06 Oct-06 MEAN MLW FDC Criteria Line Figure 4.34: Closure Depth (hc) at CH 300 for 2006 Post-Project Profile FDC, m 3 102 4.10.4 Closure Depth at CH 400 At CH 400, the innershore closure depth was recorded at -2.65 m LSD located 190 m from the baseline. Applying the FDC method, the reopening zone was found to be along the profile line starting from 190 m to 1210 m of the baseline. This phenomena indicates that the active movement of sediment is taking place due to the PEM system. The middleshore closure point is registered at 680 m from the baseline and placed -5.55 m LSD. BEACH PROFILE FOR CHAINAGE 400 (CH 400) 4 5 4.75 4.5 2 4.25 hci= -2.65 m @ 190m 4 3.75 0 3.5 3.25 hcm= -5.55 m @ 680m 2.75 2.5 2.25 -4 2 1.75 1.5 -6 1.25 1 0.75 -8 0.5 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-06 Oct-06 MEAN MLW FDC Criteria Line Figure 4.35: Closure Depth (hc) at CH 400 for 2006 Post-Project Profile FDC, m Depth, m -2 3 103 4.10.5 Closure Depth at CH 500 until CH 800 Figure 4.36 to Figure 4.39 shows the profile survey for CH 500 to CH 800 respectively. The profiles are group together due to similarity results obtained for all chainages. The significant bed elevation changes are obviously occurs along the profile line beginning from the shoreline until reaching the offshore zone. Accordingly, the reopening zone appears at all chainage along the profile survey indicates the active movement of sediment. By using FDC method, the FDC lines seem to be downcrossing and upcrossing the limit line alternately with a little gap. This makes the analysis difficult in order to determine the closure depth. Therefore, as a conclusion, there is no closure point detected for all chainage due to inconsistency variation in bottom elevation. However, the shoreline is seemed to be established for all chainages. BEACH PROFILE FOR CHAINAGE 500 (CH 500) 6 5 4.75 4.5 4 4.25 4 2 3.75 3.5 3.25 0 2.75 -2 2.5 2.25 FDC, m Depth, m 3 2 -4 1.75 1.5 -6 1.25 1 0.75 -8 0.5 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-06 Oct-06 MEAN MLW FDC Criteria Line Figure 4.36: Closure Depth (hc) at CH 500 for 2006 Post-Project Profile 104 BEACH PROFILE FOR CHAINAGE 600 (CH 600) 8 5 4.75 4.5 6 4.25 4 4 3.75 3.5 2 3.25 Depth, m 0 2.75 2.5 2.25 -2 FDC, m 3 2 1.75 -4 1.5 1.25 -6 1 0.75 -8 0.5 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-06 Oct-06 MEAN MLW FDC Criteria Line Figure 4.37: Closure Depth (hc) at CH 600 for 2006 Post-Project Profile BEACH PROFILE FOR CHAINAGE 700 (CH700) 8 5 4.75 4.5 6 4.25 4 4 3.75 3.5 2 3.25 0 2.75 2.5 2.25 -2 FDC, m Depth, m 3 2 1.75 -4 1.5 1.25 -6 1 0.75 -8 0.5 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-06 Oct-06 MEAN MLW FDC Criteria Line Figure 4.38: Closure Depth (hc) at CH 700 for 2006 Post-Project Profile 105 BEACH PROFILE FOR CHAINAGE 800 (CH800) 8 5 4.75 4.5 6 4.25 4 4 3.75 3.5 2 3.25 0 2.75 2.5 2.25 -2 FDC, m Depth, m 3 2 1.75 -4 1.5 1.25 -6 1 0.75 -8 0.5 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-06 Oct-06 MEAN MLW FDC Criteria Line Figure 4.39: Closure Depth (hc) at CH 800 for 2006 Post-Project Profile 4.10.6 Closure Depth at CH 900 A closure zone appears at CH 900 beginning from 220 m to 550 m from the baseline as shown in Figure 4.49. Based on FDC method, the innershore closure point (hci) was found to be at -3.3 m LSD located 220 m from the baseline and thus recognized as effective closure depth whereby it is separated by outer bar by closure zone. Yet, it is found that the significant bed elevation changes actively, occuring at the middleshore area towards the sea. 106 BEACH PROFILE FOR CHAINAGE 900 (CH900) 8 5 4.75 4.5 6 4.25 4 4 3.75 3.5 2 3.25 0 2.75 2.5 2.25 -2 FDC, m Depth, m hci= -3.3 m @ 220m 3 2 1.75 -4 1.5 1.25 -6 1 0.75 -8 0.5 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-06 Oct-06 MEAN MLW FDC Criteria Line Figure 4.40 Closure depth (hc) at CH 900 for 2006 Post-Project Profile 4.10.7 Closure Depth at CH 1000 The reopening zone was observed to be at 240 m to 800 m from the baseline. The first downcrossing limit line was found at 140 m from the baseline and placed -1.25 m LSD. The next closure point (hcm) was registered at -7.55 m LSD located 800 m from the baseline. This point thus qualifies as effective closure depth (hc) whereby an insignificant change in bed elevation occurred after this point. 107 BEACH PROFILE FOR CHAINAGE 1000 (CH1000) 8 5 4.75 4.5 6 4.25 4 4 3.75 3.5 hci= -1.25 m @ 140m 2 3.25 0 2.75 2.5 2.25 -2 hcm= -7.55 m @ 800m FDC, m Depth, m 3 2 1.75 -4 1.5 1.25 -6 1 0.75 -8 0.5 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-06 Oct-06 MEAN MLW FDC Criteria Line Figure 4.41: Closure depth (hc) at CH 1000 for 2006 Post-Project Profile 4.10.8 Closure Depth at CH 1100 and CH 1200 Figure 4.42 and Figure 4.43 shows similar results along the profile lines. A shoreline retreat of almost 10 m and 40 m has occurred at the baseline for CH 1100 and CH 1200 respectively. The significant changes in bottom elevation occur along the profile lines for both chainages. This indicates that the significant sediment transport activity had achieved as explained by FDC method. Therefore, similar to CH 500 to CH 800, the closure depth was not found at these chainages. 108 BEACH PROFILE FOR CHAINAGE 1100 (CH1100) 14 5 4.75 12 4.5 4.25 10 4 8 3.75 3.5 6 3.25 Depth, m 2.75 2 2.5 2.25 0 FDC, m 3 4 2 1.75 -2 1.5 -4 1.25 1 -6 0.75 0.5 -8 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-06 Oct-06 MEAN MLW FDC Criteria Line Figure 4.42: Closure depth (hc) at CH 1100 for 2006 Post-Project Profile BEACH PROFILE FOR CHAINAGE 1200 (CH1200) 14 6 12 5.5 5.75 5.25 10 5 4.75 8 4.5 4.25 6 4 3.75 4 3.25 2 3 0 2.75 FDC, m Depth, m 3.5 2.5 -2 2.25 2 -4 1.75 1.5 -6 1.25 1 -8 0.75 0.5 -10 0.25 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-06 Oct-06 MEAN MLW FDC Criteria Line Figure 4.43: Closure depth (hc) at CH 1200 for 2006 Post-Project Profile 109 4.10.9 Closure Depth at CH 1300 Multiple closure point was recorded at CH 1300. The first down-crossing FDC criteria line was found to be at 200 m and placed -1.65 m LSD. The middleshore closure point appears at -5.95 m LSD and located 460 m from the base line and the hco is registered to be at -8.05 m LSD located at 760 m from the baseline. A closure zone appears to be at distance 460 m to 760 m from the baseline thus recognized hcm as effective closure depth. BEACH PROFILE FOR CHAINAGE 1300 (CH1300) 32 5 30 4.75 28 4.5 26 4.25 24 4 22 3.75 20 3.5 18 3.25 16 Depth, m 2.75 12 hci= -1.65 m @ 200m 10 2.5 8 2.25 6 hcm= -5.95 m @ 460m 4 2 1.75 2 1.5 0 1.25 -2 hco= -8.05 m @ 760m -4 1 0.75 -6 0.5 -8 -10 0.25 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-06 Oct-06 MEAN MLW FDC Criteria Line Figure 4.44: Closure depth (hc) at CH 1300 for 2006 Post-Project Profile FDC, m 3 14 110 4.10.10 Closure Depth at CH 1400 The shoreline for both surveys is located at 190 m from the baseline. The innershore closure point was registered at -5.45 m LSD and 410 m from the baseline does not produce any shoreline change. A closure zone was observed at 410 m and closes again at 760 m from the baseline thus produce and effective closure depth at -7.55 m LSD located 760 m from the base line. The insignificant bed elevation was found at the middleshore area indicates that the inactive sediment transport activity. BEACH PROFILE FOR CHAINAGE 1400 (CH1400) 48 5 46 4.75 44 42 4.5 40 4.25 38 36 4 34 3.75 hci= -5.45 m @ 410m 32 30 hcm= -7.55 m @ 760m 28 26 3.25 3 22 2.75 20 18 2.5 16 2.25 14 12 2 10 1.75 8 6 1.5 4 1.25 2 0 1 -2 0.75 -4 -6 0.5 -8 0.25 -10 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-06 Oct-06 MEAN MLW FDC Criteria Line Figure 4.45: Closure depth (hc) at CH 1400 for 2006 Post-Project Profile FDC, m Depth, m 24 3.5 111 4.11 Summary of Depth of Closure for 2006 Post-Project Condition The summary of closure depth for profile surveys 2006 is presented in Table 4.8 below. Out of 14 chainages, six chainage sections failed to produce any closure point i.e CH 500, CH 600, CH 700, CH 800, CH 1100 and CH 1200. This happened due to significant changes of bed sediment which occur along the profile survey. However, this is a good sign to indicate that the area is effectively treated by PEM system. The shorelines at CH 1200 to CH 1400 tend to be eroded due to the PEM pipe. Logically, if the groyne were to be placed at CH 1200 where the sediment is moved from north to south, the erosion could happen at CH 1300. This phenomena is the same as this scenario whereby the PEM pipes were placed at CH 1200. Consequently, the erosion occurs at CH 1300. Another reason why CH1300 tends to be eroded is because it is located at the headland of Tg. Tembeling where the wave energy is concentrated. Table 4.8: Closure Depth for 2006 Post-Project Profile FDC hc (Mac 2006 –October 2006) Chainage hci, (m) LSD hcm, (m) LSD hco, (m) LSD Effective hc, (m) MLW CH 100 na -3.35 na CH 200 na -5.05 na CH 300 -2.65 -4.95 na CH 400 -2.65 -5.55 na CH 500 na na na CH 600 na na na CH 700 na na na CH 800 na na na CH 900 -3.3 na na CH 1000 -1.25 -7.55 na CH 1100 na na na CH 1200 na na na CH 1300 -1.65 -5.95 -8.05 CH 1400 -5.45 -7.55 na Average -2.83 -5.70 -8.05 hci = innershore closure depth; hcm = middleshore closure depth; na=not available Distance Offshore, (m) -2.69 580 -4.39 720 -4.29 670 -4.89 190 na na na na na na na na -2.64 220 -6.89 800 na na na na -5.29 460 -6.89 760 -4.74 550 hco=outershore closure depth; 112 4.12 2007 Beach Profiles Beach profile surveys for the third year after the installation of PEM system were presented in the following section. The profile lines for each chainage described that the closure depths appear along the profile line. The bed elevation changes show that the small regular variation observed at all chainage, indicating that the beach is stable as it approaches the offshore zone. Unfortunately, the depth of closure was not found at CH 400 whereby using FDC method, the FDC line shows that the lines are below the limit line. 4.12.1 Closure Depth at CH 100 At CH 100, the FDC method produces an effective depth of -5.15 m LSD located at 750 m from the baseline. The FDC lines remain below the criteria line of 0.25 m after this point indicates that the bed elevation change is insignificant. BEACH PROFILE FOR CHAINAGE 100 (CH 100) 50 5 4.75 4.5 4.25 40 4 hcm = -5.15 m @ 750m 3.75 3.5 30 3.25 Depth, m 2.75 20 2.5 2.25 FDC, m 3 2 1.75 10 1.5 1.25 1 0 0.75 0.5 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-07 Jul-07 MEAN MLW FDC Criteria Line Figure 4.46: Closure Depth (hc) at CH 100 for 2007 Post-Project Profile 113 4.12.2 Closure Depth at CH 200 The closure zone appears at distance 730 m to 1030 m from the baseline. The first down-crossing criteria line was observed at -5.25 m LSD and located 730 m at the middleshore area, thus recognized as an effective closure depth for CH 200. Bed elevation changes are insignificant at this chainage especially in the innershore area. BEACH PROFILE FOR CHAINAGE 200 (CH 200) 50 3 2.75 40 2.5 2.25 30 2 20 hcm = -5.25 m @ 730m 1.5 1.25 10 1 0.75 0 0.5 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-07 Jul-07 MEAN MLW FDC Criteria Line Figure 4.47: Closure Depth (hc) at CH 200 for 2007 Post-Project Profile FDC, m Depth, m 1.75 114 4.12.3 Closure Depth at CH 300 The shoreline for both surveys is located at 100 m from the baseline. The innershore closure point was registered at -2.53 m LSD and 190 m from the baseline does not produce any shoreline change. The reopening point observed at 190 m and closes again at 440 m from the baseline however does not produce any closure depth. The effective closure depth only was found to be at -3.85 m LSD which is located 480 m from the base line. BEACH PROFILE FOR CHAINAGE 300 (CH 300) 3 2.75 20 2.5 2.25 15 2 hci = -2.53 m @ 190 m 1.75 hc = -3.85 m @ 480 m 1.5 5 1.25 1 0 0.75 0.5 -5 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-07 Jul-07 MEAN MLW FDC Criteria Line Figure 4.48: Closure Depth (hc) at CH 300 for 2007 Post-Project Profile FDC,m Depth, m 10 115 4.12.4 Closure Depth at CH 500 CH 500 shows FDC graph spiking over the criteria line at the innershore area but further offshore the FDC plots do not up-cross the criteria line. There was some doubt whether closure within 100 m of the baseline is accurate since this is the region where gaps in survey data often exist. Hence the hci for CH 500 is placed at -3.65 m LSD, located 340 m from the baseline. After this point, the FDC lines remain below the limit line. This indicates that the hci closure point as an effective closure depth. BEACH PROFILE FOR CHAINAGE 500 (CH 500) 6 2 hc = -3.65 m @ 340 m 1.75 2 1.5 0 1.25 -2 1 -4 0.75 -6 0.5 -8 0.25 -10 0 0 200 400 600 800 1000 1200 Distance, m Mar-07 Jul 2007 MEAN MLW FDC Criteria Line Figure 4.49: Closure Depth (hc) at CH 500 for 2007 Post-Project Profile FDC,m Depth, m 4 116 4.12.5 Closure Depth at CH 600 Figure below shows the beach profile survey at CH 600. From the analysis, it was observed that only one closure point appear at the innershore area along the profile line. The hci or effective closure depth hc is found to be at -1.45 m LSD, located 120 m from the baseline. However it does not contribute to shoreline changes. The bed elevation variations do not show any significant change as the sand approach the offshore limit. BEACH PROFILE FOR CHAINAGE 600 (CH 600) 8 2 6 1.75 4 1.5 2 hci or hc = -1.45 m @ 120 m 1.25 -2 1 -4 0.75 -6 0.5 -8 0.25 -10 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-07 Jul-07 MEAN MLW FDC Criteria Line Figure 4.50: Closure Depth (hc) at CH 600 for 2007 Post-Project Profile FDC, m Depth, m 0 117 4.12.6 Closure Depth at CH 700 A closure zone appears to be at 120 m and close at 700 m from the baseline. The significant bed elevation only occurs 170 m from the reopening point and ends at 870 m from the baseline. Nevertheless, the bed elevation remains insignificant after this point towards the sea. Therefore, the effective closure depth was registered to be at 120 m from the baseline and placed -1.35 m LSD. BEACH PROFILE FOR CHAINAGE 700 (CH700) 8 2 hci or hc = -1.35 m @ 120 m 6 1.75 4 1.5 2 1.25 -2 1 -4 0.75 -6 0.5 -8 0.25 -10 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-07 Jul-07 MEAN MLW FDC Criteria Line Figure 4.51: Closure Depth (hc) at CH 700 for 2007 Post-Project Profile FDC, m Depth, m 0 118 4.12.7 Closure Depth at CH 800 Multiple closure point was recorded at CH 800. The first down-crossing FDC criteria line was found to be at 310 m and placed -3.85 m LSD. The middleshore closure point appears at -5.15 m LSD and located 530 m from the base line and hco was registered to be at -6.85 m LSD, located at 760 m from the baseline. It is found that hco was chosen as an effective closure depth due to the consistency of variation in bed elevation compared to other both designated closure point. BEACH PROFILE FOR CHAINAGE 800 (CH800) 8 2 6 1.75 hci = -3.85 m @ 310 m 4 1.5 2 hcm = -5.15 m @ 530 m 1.25 -2 hco = -6.85 m @ 760 m 1 -4 0.75 -6 0.5 -8 0.25 -10 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-07 Jul-07 MEAN MLW FDC Criteria Line Figure 4.52: Closure Depth (hc) at CH 800 for 2007 Post-Project Profile FDC, m Depth, m 0 119 4.12.8 Closure Depth at CH 900 The FDC method shows that the FDC line remain below the criteria line until the first downcrossing of the limit line is observed at 1030 m from the baseline and placed 9.15 m LSD. There is no doubt to qualify this single closure point as an effective closure depth since there is no other point found along the profile lines. The bed elevation is insignificant and the shoreline position is unchanged. BEACH PROFILE FOR CHAINAGE 900 (CH900) 8 2 6 1.75 4 1.5 2 1.25 hci = -9.15 m @ 1030 m -2 1 -4 0.75 -6 0.5 -8 0.25 -10 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-07 Jul-07 MEAN MLW FDC Criteria Line Figure 4.53: Closure Depth (hc) at CH 900 for 2007 Post-Project Profile FDC, m Depth, m 0 120 4.12.9 Closure Depth at CH 1000 The result obtained at CH 1000 is contradicting with the result at CH 900 in terms of the location of the closure point. However, it is still recorded that only one closure point was found to be at this chainage. The effective closure point was registered at 200 m distance from the baseline just after 80 m from the shoreline point. The depth was found to be -2.75 m LSD, which did not contribute to shoreline changes. BEACH PROFILE FOR CHAINAGE 1000 (CH1000) 8 2 6 1.75 hci = -2.75 m @ 200 m 4 1.5 2 1.25 -2 1 -4 0.75 -6 0.5 -8 0.25 -10 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-07 Jul-07 MEAN MLW FDC Criteria Line Figure 4.54: Closure Depth (hc) at CH 1000 for 2007 Post-Project Profile FDC, m Depth, m 0 121 4.12.10 Closure Depth at CH 1100 Bed elevation changes were observed at the innershore area beginning from the shoreline until it is stable again after 260 m from the baseline. The significant bed elevation changes however do not contribute to shoreline changes. Thus, the effective hc was qualified to be at -2.75 m LSD and lies at 210 m from the base line. From the profile investigation, the seabed slope is smooth and gentle towards the sea. BEACH PROFILE FOR CHAINAGE 1100 (CH1100) 14 2 12 1.75 hci = -2.75 m @ 210 m 10 8 1.5 6 Depth, m 2 1 0 -2 0.75 -4 0.5 -6 -8 0.25 -10 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-07 Jul-07 MEAN MLW FDC Criteria Line Figure 4.55: Closure Depth (hc) at CH 1100 for 2007 Post-Project Profile FDC, m 1.25 4 122 4.12.11 Closure Depth at CH 1200 At CH 1200, the FDC method produces an effective depth of -6.65 m LSD, located at 590 m from the baseline. The FDC lines remain below the criteria line of 0.25 m after this point which indicates that the bed elevation change is insignificant towards the sea. BEACH PROFILE FOR CHAINAGE 1200 (CH1200) 14 2 12 1.75 10 hc = -6.65 m @ 590 m 8 1.5 6 Depth, m 2 1 0 -2 0.75 -4 0.5 -6 -8 0.25 -10 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-07 Jul-07 MEAN MLW FDC Criteria Line Figure 4.56: Closure Depth (hc) at CH 1200 for 2007 Post-Project Profile FDC, m 1.25 4 123 4.12.12 Closure Depth at CH 1300 A closure zone appears at a distance of 220 m to 980 m from the baseline. At this chainage, a sand bar occurred at the middleshore area around 480 m to 610 m from the baseline. From the survey, it was observed that the shoreline tend to erode about 10 m even though, there is no significant change at the innershore area. The effective hc was found to be at -2.05 m, located 220 m LSD from the baseline. BEACH PROFILE FOR CHAINAGE 1300 (CH1300) 14 2 12 hc = -2.05 m @ 220 m 10 1.75 8 1.5 6 Depth, m 2 1 0 -2 0.75 -4 0.5 -6 -8 0.25 -10 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-07 Jul-07 MEAN MLW FDC Criteria Line Figure 4.57: Closure Depth (hc) at CH 1300 for 2007 Post-Project Profile FDC, m 1.25 4 124 4.12.13 Closure Depth at CH 1400 The analysis proceeds from the shoreline at a distance 190 m from the baseline. The significant bed elevation appears just 60 m after the shoreline which indicates the active sediment transport up to 240 m from the baseline. The innershore closure depth was found to be at 260 m from the baseline and placed -2.85 m LSD. The sea bed remains stable since the FDC line is less than 0.25 m of limit line. BEACH PROFILE FOR CHAINAGE 1400 (CH1400) 48 2 46 44 42 1.75 40 38 36 34 1.5 32 30 hc = -2.85 m @ 240 m 28 26 1.25 22 20 18 1 16 14 12 0.75 10 8 6 4 0.5 2 0 -2 -4 0.25 -6 -8 -10 -12 0 0 200 400 600 800 1000 1200 Distance, m Mar-07 Jul-07 MEAN MLW FDC Criteria Line Figure 4.58: Closure Depth (hc) at CH 1400 for 2007 Post-Project Profile FDC, m Depth, m 24 125 4.13 Summary of Depth of Closure for 2007 Post-Project Condition The analysis of depth of closure for 2007 beach profiles after the installation of the PEM system revealed that multiple closure across the profile produces at least three closure points as shown in Table 4.9. Out of 14 chainages, only one chainage was not registered i.e CH 400. Unfortunately, the FDC line remained below the criteria line along the profile line in which the closure depth does not exist. According to Table 4.9, the average hc is recorded as -3.47 m below MLW and lies 445 m from the baseline. The closure depth is found to be deeper compared to closure depth before the installation of PEM system and the distance of the closure point is further seaward. This positive sign indicates that the PEM system is functioning to accrete more sand on the nearshore zone. Table 4.9: Closure Depth for 2007 Post-Project Profile FDC hc (Mac 2007 –July 2007) Chainage hci, (m) LSD hcm, (m) LSD hco, (m) LSD Effective hc, (m) MLW CH 100 na -5.15 na CH 200 na -5.25 na CH 300 -2.53 -3.85 na CH 400 na na na CH 500 -3.65 na na CH 600 -1.45 na na CH 700 -1.35 na na CH 800 -3.85 -5.15 -6.85 CH 900 -9.15 na na CH 1000 -2.75 na na CH 1100 -2.75 na na CH 1200 na -6.65 na CH 1300 -2.05 na na CH 1400 -2.85 na na Average -3.24 -5.55 -6.85 hci = innershore closure depth; hcm = middleshore closure depth; na=not available Distance Offshore, (m) -4.49 750 -4.59 730 -3.19 480 na na -2.99 340 -0.79 120 -0.69 120 -6.19 760 -8.49 1030 -2.09 200 -2.09 210 -5.99 590 -1.39 220 -2.19 240 -3.47 445 hco=outershore closure depth; 126 4.14 Comparison of hc between Pre-Project Condition and Post-Project Condition Figure 4.59 and Figure 4.60 shows the summary of closure depths and closure points at the study area. These plots had been obtained based on the effective hc referring to the Table 4.7, Table 4.8 and Table 4.9 as shown previously. It is useful to note that the point in which crosses the 0 m depth indicated that there is no closure depth found at the particular chainage. Generally, the closure depth for the pre-project condition was found to be shallower at an average depth of -2.58 m MLW with a distance of 319 m from the baseline. This result indicates that erosion is occurring. After one year installation of PEM system and beach nourishment, the closure depth tends to be deeper and the closure point is further seaward. This phenomena indicates that the sediment has started to moved seawards to find its equilibrium profile. After 2 years installation program, the significant changes in bed elevation which depend on waves, tides and other hydrodynamics actions was observed at most of the chainages showing that the active movement of sediment is occurring. Consequently, more closure points were not found due to this process. After three years (2007), it is found that the beach is more stable where the closure point was recorded to be at most of the chainage and no significant changes in bed elevation was observed. Overall, the closure depth tends to be deeper and the closure point is further seawards. However, it is still early to conclude that the PEM system is able to achieve its operation although the beach is looks like stable after three years of the installation program. Further investigation and monitoring work should be carried out to figure out whether the system is able to serve its function or not. 127 Depth of Closure at Teluk Cempedak beach, Kuantan 2 1 0 Depth , m (MLW) -1 -2 -3 -4 -5 -6 -7 -8 -9 0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500 Chainage, m 2003 2005 2006 2007 Figure 4.59: Closure Depth at Teluk Cempedak beach, Kuantan Closure Point at Teluk Cempedak beach, Kuantan 1200 Distance Seaward, m 1000 800 600 400 200 0 0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500 Chainage, m 2003 2005 2006 2007 Figure 4.60: Closure Point at Teluk Cempedak beach, Kuantan 128 Estimation of Predictive Closure Depth by Hellemeier’s Equation 4.15 In order to determine the offshore limit of an active zone where yearly onshore and offshore cycle of sediment movement occurs, Hallemeier (1978) proposed to use an extreme wave height, which exceeds 12 hours per year from the distribution for cumulative wave heights and corresponding wave period. H 0.137 wave was determined in this study as described in section 4.5. These wave parameters are used to fit into equation 2.2 and 2.5 in order to obtain the predictive closure depth. Here, equation 2.2 and 2.5 are re-written as follows:- hc = 2.28He – 68.5 (He2/gTe2) (2.2) hc = 1.57He (2.5) Where; Te = wave period associated with He which can be approximated from the annual mean significant wave height H, Table 4.10: hc from Simplified Equation Compared with Effective hc 2007 Hellemeier‟s Equation 1.57He 2.28He – 68.5 (He2/gTe2) Average Hs 0.137 (m) 3.53 3.53 - Te (sec) 7.85 - Predicted hc (m) 5.54 6.64 6.09 hc 2007 (m) 3.47 3.47 3.47 Table 4.10 above describes that the predictive equations over-predict the effective hc value. The effective hc for beach profile 2007 was chosen due to the % diff. 59.65 91.35 75.50 129 insignificant bed elevation changes along the profile survey. The average hc or hc-1yr based on the algorithm used above was found to be -3.47 m MLW. The simplest relationship can thus be formed between this and the UKMO offshore wave, H 0.137; hc / H 0.137 = 3.47/3.53 = 0.98 Therefore, equating the above to hc hc = 0.98 H 0.137 In conclusion, this relationship may be applied at any location along the east coast of Malaysia to predict the depth of closure for a beach restoration project where a combination of PEM system and beach nourishment is used but applicable only to sites with similar wave climate and beach condition. 130 4.16 PEM Effectiveness Evaluation The main objective to apply the Pressure Equalization Module System at Teluk Cempedak beach area is to bring the beach back to a state where it can serve its purpose as a high standard tourist and recreational beach with good sand quality. Therefore, in order to determine whether the combination of beach nourishment and PEM system is able to serve its function or not, an evaluation to this system has been carried out. Thus, there are two ways to evaluate the effectiveness of the PEM system i.e estimation for total sand volume and beach level. The 2004 survey data is used as a baseline to determine the efficiency of this system. A comparison of results for year 2005 till 2007 has been carried out with reference to the 2004 baseline survey. It is useful to note that, the PEM pipes were installed at CH 400 to CH 1300. 4.16.1 Total Sand Volume Changes Figure 4.61 shows the total sand volume at the study area. The average sand volume is relatively higher within chainage 400 m until chainage 1200 m. Generally, it is proven that the PEM system is apparently functioning to gain and retains more sand on the beach whereby the said chainage was installed with the PEM pipes. As for information, data for the year 2004 is a baseline for this study whereby new sand had been added on the beach for the beach nourishment purpose. From the bar chart also, for the year 2005, it is shown that the volume of sand has been dropped at most of the chainage except for CH 600 and CH 1000. This result indicates that the sand had moved seaward to create an equilibrium profile. At CH 1300, it is shown that the biggest drop of amount of sand after 1 year installation of PEM and beach nourishment indicates that the erosion still occurs. As for information, CH 1300 is located near the headland of 131 Bukit Tembeling. Therefore, this confirms the fact that erosion occurs at areas where wave energy is concentrated at headlands. However, after two years, the sand volume has shown a slight increment at most of the chainages except at CH 900.This shows that the beach starts gaining sand back. Furthermore, it can be seen that the total sand keeps increasing in the year 2007 at all chainages except for the chainage located at the southern part of the beach i.e CH 900 to CH 1300. This trend qualifies that the accretion of sand is occurring at the northern part of the beach while erosion process is experienced at the southern part of the beach. Total Sand Volume (m3) 250 200 Sand Volume, m 3/m 150 100 50 0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 -50 -100 -150 Chainage, m 2004 2005 2006 2007 Figure 4.61 : Total Sand Volume (m3) Based on Table 4.11, the total sand volume during the installation of PEM system (2004) and beach nourishment is about 1766 m3. Unfortunately, the values decreased to 1556 m3 after one year of installation of PEM system (2005) and subsequently decrease to 1540 m3 in year 2006. This indicates that the volume of sand is 132 lost along the beach. However, in year 2007, the total sand volume increases describing that the system starts functioning to bring back the sand to the beach and the beach is now stable. Generally, the total sand loss is recorded to be decreasing from -245 m3 in year 2005 to -102.38 m3 in year 2006 and subsequently decrease to - 81.38 m3 in year 2007, showing that the rate of erosion is decreasing. Consequently, the total sand gain is increasing from 35 m3 to 178.50 m3 after 3 years installation of PEM and beach nourishment (see Table 4.11). Overall, this result reveals that the PEM system is able to stimulate accretion of sand and slow down the erosion process. However, further investigation has been carried out to look into detail at which areas of the beach are benefiting from the PEM system. Table 4.11: Total Sand Volume and Sand Gain or Loss at the Study Area Chainage 2004 2005 Total Sand Volume (m3) 2005-2004 2006-2005 2006 Loss/Gain Loss/Gain -31.50 11.38 -37.63 -4.38 7.88 -38.50 10.50 -38.50 -13.13 -21.88 138.25 1.75 -24.50 170.63 19.25 6.13 223.13 -2.63 -25.38 155.75 9.63 -4.38 143.50 1.75 -20.13 166.25 -6.13 2.63 189.00 9.63 0.00 200.38 -4.38 -2.63 187.25 9.63 -110.25 56.00 24.50 15.75 -70.88 10.50 1540.00 -245.00 -102.38 + 35.00 + 86.63 100 80.50 49.00 200 50.75 46.38 300 -38.88 -25.38 400 158.38 136.50 500 175.38 151.38 600 219.63 225.75 700 171.50 146.13 800 146.13 141.75 900 192.50 172.38 1000 176.75 179.38 1100 204.75 204.75 1200 180.25 177.63 1300 141.75 31.50 1400 -97.13 -81.38 Total 1765.75 1555.75 Loss Gain Net -210 Loss/Gain CH 100, CH200, CH300 & CH 1400 = NO PEM; CH 400 to CH 1300 = PEM with Beach Nourishment -15.75 56.88 84.88 -17.50 146.13 182.88 230.13 161.00 145.25 153.13 171.50 199.50 161.00 32.38 -70.00 1637.13 - 2007-2006 Loss/Gain 45.50 77.00 21.00 7.88 12.25 7.00 5.25 1.75 -13.13 -17.50 -0.88 -26.25 -23.63 0.88 -81.38 + 178.50 - + 97.12 2007 133 Figure 4.62 till Figure 4.64 represent the sand gain and loss along the stretch of the beach with the PEM system. It is shown that the losses of sand in year 2005 is greater than year 2006 which gives volumes of about -209.1 m3 and -13.14 m3 respectively. This result reveals that the sand is less likely to wash back to the sea and the sediment is readily deposited on the beach. However, after 3 years (2007), the losses of the sand increase to -81.38 m3. This phenomena indicates that the sand has moved away due to several factors such as washed or blown offshore and drifting away alongshore. From the literature, sand often shifts alongshore with change in wave climate in a pocket bay. Visually, the result is a shift in the profile of the beach in both the horizontal and vertical. Although such changes are commonly associated with monsoon (erosion) and inter-monsoon (accretion), in reality, they occur any time of year in response to stormy or fair weather. Accordingly, the sand gain is relatively higher in 2006 which is about 76.14 m3 compared to year 2005 and 2007 in which equals to 8.75 m3 and 34.13 m3. In term of sand volume distribution pattern, in year 2005, there is loss of sand volume at most of the chainage (see Figure 4.62). This scenario may happen due to several factors: (i) losses of the sand are due to interruption of longshore transport on the up-drift side, (ii) reduction of sediment source, (iii) storm surges and (iv) effect of wave reflection and refraction. On the other hand, the distribution pattern of the sand in 2006 shows that the sand is losing and gaining alternately along the beach. However, it revealed that the net sand gains is relatively higher that net sand losses as shown in Figure 4.63. This phenomena indicates that the beach is unstable after 2 years of the installation program. After 3 years, where the beach is more stable, it is obviously seen that the accretion of sand occurring at the northern part while from CH 900 towards the south, the erosion process occurs instead (see Figure 4.64). This result reaffirmed that the bathymetry survey in April 2003 showed that the slope is steeper at the southern part of the beach. This indicates that this part is more reflective to the waves, thus leading to erosion. Therefore, the sand has drifted to the northern part of the beach where the 134 accretion of sand occurs. A summary of the change in sand volume distribution pattern is provided in Figure 4.65. Sand Gain/Loss after 1 Year Installation of PEM System 20 +8.75 m3 0 400 500 600 700 800 900 Sand Volume, m3 -20 1000 1100 1200 1300 -209.1 m3 -40 -60 -80 Net = -200.4 m3 -100 -120 Chainage, m 2005 Figure 4.62: Sand Gain and Loss for Year 2005 Sand Gain/Loss after 2 Year Installation of PEM System 30 25 Net = +63 m3 Sand Volume, m 3 20 15 +76.14 m3 10 5 0 400 500 600 700 800 900 1000 1100 1200 -5 -13.14 m3 -10 Chainage, m 2006 Figure 4.63: Sand Gain and Loss for Year 2006 1300 135 Sand Gain/Loss after 3 Year Installation of PEM System 15 10 +34.13 m3 Sand Volume, m3 5 0 400 500 600 -5 700 800 900 1000 1100 1200 1300 -81.38 m3 -10 -15 -20 Net = -47.25 m3 -25 -30 Chainage, m 2007 Figure 4.64: Sand Gain and Loss for Year 2007 Summary of Sand Volume Distribution Pattern 100 Sand Volume, m3 50 0 0 200 400 600 800 1000 1200 1400 -50 -100 -150 Chainage, m 2005 2006 2007 Figure 4.65: Sand Volume Distribution Pattern 1600 136 4.16.2 Beach Level Changes Figure 4.66 shows the average beach level 70 m wide for CH 100 till CH 1400. Results showed the same trend as for total sand volume changes, whereby nourished areas installed with PEM system have indicated higher beach level compared to areas with no PEM and beach nourishment. In term of temporal distribution, in year 2005, the beach level is decreasing at most of the chainages where the drastic drop in bed level could be seen at CH 1300 from 2 m to 0.45 m height. This is because CH 1300 is located near the headland of Bukit Tembeling where wave energy is concentrated at this area and it is a byproduct of wave refraction. However, in year 2006, the beach level tends to increase except for CH 900 and CH 1100. In the following year (2007), the distribution pattern shows that the beach level is slightly higher in the northern half of the beach while the southern part is still experiencing erosion where the beach level shows a slightly decreased value. Average Beach Level 70 m wide 4 3 Beach Level, m 2 1 0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 -1 -2 Chainage, m 2004 2005 2006 2007 Figure 4.66: Average Beach Level 70 m wide 137 4.16.3 Distribution Pattern of Beach Level Changes Figure 4.67 until Figure 4.71 shows the cross-section profile at CH 400 until CH 1300 where the PEM pipes were installed. It can be observed that the beach elevation is higher than the baseline level in 2004. The upper part of the beach is convex unlike earlier (2003), where the beach was low and concave. This trend indicates that the system contributes a significant accretion of sand and thus creates a higher beach level at about 10 m to 55 m towards the sea. However, this trend can only be seen at a certain chainage. As can be observed in Figure 4.66 to Figure 4.70 below, the increment in bed elevation from year 2005 to year 2007 can be observed at CH 400 until CH 800 while at CH 900 towards the south, the bed elevation is decreasing. This shows that the accretion of sand is only occurring at the northern half and the beach is eroding at the southern half. Beach Level at CH 400 Beach Level at CH 500 5.00 7.00 6.00 4.00 5.00 3.00 2003 2004 (Baseline) 2005 2006 1.00 2007 Beach Level (m) Beach Level (m) 4.00 2.00 2003 3.00 2004 (Baseline) 2005 2.00 2006 2007 1.00 0.00 0 10 20 30 40 50 60 70 80 0.00 0 -1.00 10 20 30 40 50 -1.00 -2.00 Distance Seaward (m) -2.00 Distance Seaward (m) Figure 4.67: Beach Level at CH 400 and CH 500 60 70 80 138 Beach Level at CH 600 Beach Level at CH 700 7.00 6.00 6.00 5.00 5.00 4.00 2003 3.00 2004 (Baseline) 2005 2.00 2006 2007 Beach Level (m) Beach Level (m) 4.00 3.00 2003 2004 (Baseline) 2.00 2005 2006 2007 1.00 1.00 0.00 0.00 0 10 20 30 40 50 60 70 0 80 10 20 30 40 50 60 70 80 -1.00 -1.00 -2.00 -2.00 Distance Seaward (m) Distance Seaward (m) Figure 4.68: Beach Level at CH 600 and CH 700 Beach Level at CH 900 5.00 4.00 4.00 3.00 3.00 2.00 2003 2004 (Baseline) 2005 2006 1.00 2007 Beach Level (m) Beach Level (m) Beach Level at CH 800 5.00 0.00 2.00 2003 2004 (Baseline) 2005 2006 1.00 2007 0.00 0 10 20 30 40 50 60 70 80 0 -1.00 10 20 30 40 50 60 70 80 -1.00 -2.00 -2.00 Distance Seaward (m) Distance Seaward (m) Figure 4.69: Beach Level at CH 800 and CH 900 Beach Level at CH 1100 6.00 5.00 5.00 4.00 4.00 3.00 2003 2004 (Baseline) 2.00 2005 2006 2007 1.00 0.00 3.00 2003 2004 (Baseline) 2.00 2005 2006 2007 1.00 0.00 0 10 20 30 40 50 -1.00 -2.00 Beach Level (m) Beach Level (m) Beach Level at CH 1000 6.00 60 70 80 0 10 20 30 40 50 -1.00 Distance Seaward (m) -2.00 Distance Seaward (m) Figure 4.70: Beach Level at CH 1000 and CH 1100 60 70 80 139 Beach Level at CH 1300 Beach Level at CH 1200 6.00 5.00 5.00 4.00 4.00 3.00 2003 2004 (Baseline) 2005 2006 1.00 2007 Beach Level (m) Beach Level (m) 3.00 2.00 2003 2.00 2004 (Baseline) 2005 1.00 2006 2007 0.00 0 0.00 0 10 20 30 40 50 60 70 80 -1.00 -2.00 10 20 30 40 50 60 70 80 -1.00 -2.00 -3.00 Distance Seaward (m) Distance Seaward (m) Figure 4.71: Beach Level at CH 1200 and CH 1300 4.16.4 PEM Efficiency For this study, the basic formula in determining the efficiency of the system is used. The formula is described as follows:- Beach Level at Year (n+1) – Beach Level at Year (n) Efficiency, (%) = Beach Level at Year (n) (4.1) The PEM efficiency was then observed at CH 400 till CH 1300 across the Teluk Cempedak beach in terms of beach elevation as illustrated in Figure 4.72 until Figure 4.76. Similar to the evaluation for total sand volume, the beach level for the year 2004 is the baseline for this study. It is found that the efficiency of the system can only be seen at the northern part of the beach i.e for CH 400 till CH 800 whereby the efficiency was 140 recorded to be increasing from year 2005 to year 2007 (see Table 4.12). In contrast, although the beach level is higher compared to the baseline, the efficiency of the system is decreasing from year 2005 to year 2007 and this happened at CH 900 till CH 1300. Only at CH 1000 and CH 1200, the efficiency was observed to increase from year 2005 to year 2006 but the value suddenly drops in year 2007. At CH1300, no efficiency was recorded. Similar to earlier finding in sand volume changes described in section 4.16.1, it can be reaffirmed that the accretion of sand only occurrs at the northern part of the beach while erosion is still occurring at the southern part. This shows that the northern part is benefiting from the PEM system while the other part is still experiencing erosion. Table 4.12: PEM Efficiency Chainage 400 500 600 700 800 900 1000 1100 1200 1300 2005 43.48 25.00 56.52 25.93 72.22 12.50 34.62 38.46 43.38 -233.33 Efficiency (%) 2006 60.87 50.00 60.87 25.93 77.78 9.37 50.00 34.62 52.17 -188.89 2007 73.91 66.67 60.87 25.93 83.33 3.12 42.31 15.38 17.39 -211.11 141 PEM Efficiency at CH 400 PEM Efficiency at CH 500 100.00 100.00 50.00 50.00 0.00 0 10 20 30 40 50 60 70 80 2005 -50.00 2006 2007 Efficiency, % Efficiency, % 0.00 0 20 40 50 60 70 80 2005 2006 2007 -100.00 -150.00 -150.00 -200.00 Distance Seaward (m) 30 -50.00 -100.00 -200.00 10 Distance Seaward (m) Figure 4.72: PEM Efficiency at CH 400 and CH 500 PEM Efficiency at CH 600 PEM Efficiency at CH 700 80.00 50.00 60.00 0.00 40.00 0 10 20 30 40 50 60 70 80 -50.00 0.00 -20.00 0 10 20 30 40 50 60 70 80 2005 2006 -40.00 2007 -60.00 Efficiency, % Efficiency, % 20.00 2005 -100.00 2006 2007 -150.00 -80.00 -100.00 -200.00 -120.00 -140.00 -250.00 Distance Seaward (m) Distance Seaward (m) Figure 4.73: PEM Efficiency at CH 600 and CH 700 PEM Efficiency at CH 800 PEM Efficiency at CH 900 150.00 50.00 100.00 0.00 50.00 0 0 10 20 30 40 50 60 70 80 -50.00 2005 -100.00 2006 2007 -150.00 10 20 30 40 50 -250.00 2007 -200.00 Distance Seaward (m) 80 2006 -300.00 -350.00 70 2005 -100.00 -150.00 -200.00 60 -50.00 Efficiency, % Efficiency, % 0.00 -250.00 Distance Seaward (m) Figure 4.74: PEM Efficiency at CH 800 and CH 900 142 PEM Efficiency at CH 1100 PEM Efficiency at CH 1000 50.00 100.00 50.00 0.00 0 0 10 20 30 40 50 60 70 80 -50.00 2005 2006 -100.00 2007 Efficiency, % Efficiency, % 0.00 10 20 30 40 50 60 70 80 -50.00 2005 2006 2007 -100.00 -150.00 -150.00 -200.00 -250.00 -200.00 Distance Seaward (m) Distance Seaward (m) Figure 4.75: PEM Efficiency at CH 1000 and CH 1100 PEM Efficiency at CH 1300 PEM Efficiency at CH 1200 150.00 100.00 100.00 50.00 50.00 0.00 10 20 30 40 50 60 70 80 -50.00 2005 2006 2007 -100.00 Efficiency, % Efficiency, % 0 0.00 0 10 20 30 40 50 -200.00 Distance Seaward (m) 80 2007 -150.00 -250.00 70 2006 -100.00 -150.00 -200.00 60 2005 -50.00 -250.00 Distance Seaward (m) Figure 4.76: PEM Efficiency at CH 1200 and CH 1300 143 CHAPTER V CONCLUSIONS AND RECOMMENDATIONS 5.1 Introduction The determination of the depth of closure and the efficiency of the Pressure Equalization Module (PEM) system has been investigated in this study. The results presented indicate that the Teluk Cempedak beach is now more stable and the beach area is wider due to the beach nourishment and the PEM system. In order to determine the required amount of quantity of sand to be filled for beach nourishment, the determination of closure depth is essential as a basic requirement in order to define the specific location to place the toe of the beach fill. 144 In this study, the depth of closure for the shoreline of Teluk Cempedak beach, Kuantan was determined by analyzing four sets of profile surveys. The profile surveys were analyzed using the most widely used method recommended by Nicholls (1998) i.e Fixed Depth Change (FDC) method. Based on the accuracies of the hydrographic survey, the criteria line of 0.25 m was chosen. The algorithm based on this method was also used to define the multiple point of closure depth along the profile lines as well as to obtain the effective closure depth at the study area. The results presented indicate that the closure depth before the installation of PEM system is considerably lower. The significant bed elevation changes appear along the profile line especially in PEM areas after two year installation of PEM system reveals that the PEM system started to develop its function to accumulate more sand on the nearshore zone. However, the bottom elevation shows a positive response whereby after three year of the installation, the results qualify that the beach is more stable with the closure depth value to be deeper and the location of the depth is further seaward at the southern part of the beach. However, this proves otherwise for the northern part of the beach. This phenomena may happen due to the effect of wave reflection and refraction process from the headland which located at the southern part of the beach. Besides, the depth of closure was also calculated using the Hallemeier equation and both results were compared. The predictive equations over predict the closure depth up to 76 % when compared to measured hc. However, Helllemeier equation is still adaptable in predicting an upper limit of closure depth. The simplest relationship to determine the closure depth at the study area was developed and presented as: hc = 0.98 H0.137 This relationship is recommended to be applied at any location along the east coast of Malaysia to predict the depth of closure for a beach restoration project where a 145 combination of PEM system and beach nourishment is used but applicable only to sites with similar wave climate and beach condition. The final finding of this study is the evaluation of the effectiveness of the PEM system. Two methods were used to describe the effectiveness of this system in terms of total sand volume and beach level. Generally, the total sand volume is relatively higher within the PEM areas. It is shows that the PEM system is apparently functioning to gain and retains more sand on the beach whereby the said chainage was installed with the PEM pipes. Overall, the total sand loss is recorded to have decreased from -245 m3/m in year 2005 to -102.38 m3/m in 2006 and subsequently decreased to - 81.38 m3/m in year 2007 which shows that the rate of erosion is decreasing. Consequently, the total sand gain is increasing from 35 m3/m to 178.50 m3/m after 3 years installation of PEM system and beach nourishment. This result reveals that the PEM system is able to stimulate accretion of sand and yet slow down the erosion process. However, further investigation has been conducted to look at into detail at which areas of the beach are benefiting from the PEM system. In terms of sand volume distribution pattern, in year 2005, the sand volume is losing at most of the chainages. In contrast, the distribution pattern of the sand in year 2006 shows that the sand is losing and gaining alternately over the chainages. However, it revealed that the net sand gains are relatively higher than the net sand losses. This phenomena indicates that the beach is unstable after 2 years of the installation program. After 3 years, it is obviously seen that accretion of sand has been occurring at the northern part, while starting from CH 900 towards the south, erosion is taking place instead. Besides, results of beach level evaluation shows the same trend as for total sand volume, whereby nourished areas installed with PEM system indicated that the beach level is higher compared to areas with no PEM and beach nourishment. Generally, this positive sign indicated that the PEM system is building sand on the beach and consequently higher beach levels were achieved. However, in terms of spatial distribution, after three years installation of PEM system and beach nourishment, 146 accretion of sand could be found at the northern part of the beach while erosion still occurred at the southern part of the beach. This result qualifies that the PEM system is benefiting only at certain parts of the Teluk Cempedak beach. Based on the distribution pattern of bed elevation over the chainage, generally, the upper part of the beach is convex unlike earlier i.e before the installation of PEM system, where the beach was low and concave. This phenomena indicates that the system contributes to a significant accretion of sand and thus created a higher beach level at about 10 m to 55 m towards the sea.However, this trend can only be seen at a certain chainage. The increment in bed elevation from year 2005 to year 2007 can only be found at CH 400 till CH 800 while at CH 900 towards the south, the bed elevation is decreasing. This shows that the accretion of sand is only occurring at the north part and the beach is eroding at the southern part. The PEM efficiency was observed at CH 400 till CH 1300 across the Teluk Cempedak beach in term of beach elevation. It is found that the efficiency of the system can only be seen at the northern part of the beach i.e for CH 400 till CH 800 whereby the efficiency was recorded to be increasing from year 2005 to year 2007. In contrast, although the beach level is higher compared to the 2004 baseline, the efficiency of the system is found to be decreasing from year 2005 to year 2007 and this happened at CH 900 until CH 1300. Only at CH 1000 and CH 1200, the efficiency was found to be increased from year 2005 to year 2006 but the value suddenly dropped in year 2007 and the efficiency was not found at CH 1300 at all. Again, these results reaffirmed the result obtained for the sand volume evaluation, where accretion of the sand only occurred at the northern part of the beach while erosion still occurred at the southern part of the beach. This shows that the northern areas are benefiting from the PEM system while the other part is still experiencing the erosion process. 147 In conclusion, based on the available four years record of data, it was discovered that only certain parts of the beach are benefiting from the PEM system, whereas, some parts are still experiencing erosion. 5.2 Recommendations This study provided a better overall understanding of the feasibility of the PEM system for the rehabilitation of Teluk Cempedak beach. Despite the PEM system having successfully achieved its operation in certain parts of the beach, encouragement should be given to review a better understanding of this system. Thus, further improvements and recommendations are suggested to enhance this research such as:- 5.2.1 Criteria of Limit Line The analysis above has used only 25 cm closure criterion associated with hydrographic survey accuracy. Other criterion can be applied to figure out more reliable results and a comparison between two limit lines is recommended. 148 5.2.2 Standard Deviation Depth Change (SDDC) Method The analysis of profile survey in this study was only based on Fixed Depth Change Method (FDC). Another method to determine the closure depth from profile survey i.e Standard Deviation Depth Change (SDDC) method was introduced by Kraus et al (1998). This method involves plotting the SDDC against distance seaward of the profile origin for each measured profile. The hc is thus the point where the SDDC reduces to a constant, non-zero value. It is recommended that both FDC and SDDC be applied in this study in order to obtain the effective closure depth. Comparison between both methods can also be done. 5.2.3 Profile Survey Four years record of profile survey was used in this study. Basically, in order to monitor the efficiency of any system, at least five years record of profile survey after the installation of a system should be used. One year record of profile survey before the installation of a system and five years record of profile survey is adequate to investigate the effectiveness of a system as well as to look at the response of the beach. Therefore, it is highly recommended that the Department of Irrigation and Drainage, Malaysia to continue the monitoring survey work. It is also recommended that the profile lines should be extended up to 3000 m seaward. 149 5.2.4 Predictive Formula for Each Chainage The analysis of profile survey in this study only considered the measurement of closure depth for each year and compared with the predictive equation by Hellemeier. It is useful if the predictive equation can be analyzed for every chainage to compare with the measured closure depth. To implement this, analysis of wave data for every single chainage should be performed. This analysis would require a good set of wave data whereby the wave data collection should be carried out. 150 REFERENCES Atlantic States Marine Fisheries Commission Beach Nourishment (2002), A Review of the Biological and Physical Impacts. ASMFC Habitat Management Series , 7 November 2002; Atlantic States Marine Fisheries Commission: Washington D.C. Birkemeier, W.A (1985). Field data on seaward limit of profile change. Journal of Waterway, Port, Coastal and Ocean Engineering 11(3), 598-602 Brunn, P. (1954). Coast Erosion and the Development of Beach Profiles. US Army Corps of Engineers, Beach Erosion Board, Tech. Memo No. 44 Coastal Engineering Division, Department of Irrigation and Drainage, Malaysia (2004) Annual Report 2004. Coastal Engineering Division, Department of Irrigation and Drainage, Malaysia (2007) Annual Report 2007. Coastal Engineering Division, Department of Irrigation and Drainage, Malaysia (2007). Detailed Design Report of Projek Perintis Pemuliharaan Pantai Pelancongan menggunakan Pressure Equalization Module (PEM) di Teluk Cempedak, Kuantan, Pahang. Report prepared by MRCB Dean, R.G., Healy, T.R. and Dommerholt, A .P. (1993). A “blind – folded” test of equilibrium beach profile concepts with New Zealand data. Mar. Geol., 109:253 266 Dean, R.G., and Dalrymple, R.A. (2002). Coastal Processes with Engineering Applications. Cambridge University Press. Dean, R.G. (2002). Beach Nourishment Theory and Practice. Advanced Series on Ocean Engineering Volume 18; World Scientific Publishing Co. Pte. Ltd. Singapore Emery, K.O., (1961). A simple method of measuring beach profiles. Limnology and Oceanography, v. 6, p. 90-93. 151 Eco Shore International (2006). Pressure Equalizating Modules (PEM). FDEP Workshop February 23, 2006. Ferreira, O. (1998). Depth of Closure Variability through Time as a Function of Wave Action. FCMA/CIACOMAR/CIMA, Campus de Gambelas, Faro, Portugal. Ghazali, NHM. (2004). Beach Nourishment and its Impact on Holiday Beaches; paper presented at „Seminar on Coastal Resources and Tourism‟ at Bukit Merah, Perak organized by Universiti Utara Malaysia; 21-22 December 2004. Ghazali, NHM and Ong, HL. (2005). Erosion Protection of Mangrove Coastlines; paper presented at Workshop „Lessons Learned in Mangrove Rehabilitation‟ organized by Forestry Research Institute of Malaysia; Sungai Petani, Kedah, June 2005 Ghazali, NHM. (2005). New Innovation and Technologies in Coastal Rehabilitation. International Conference on Innovations and Technologies in Oceanography for Sustainable Development. Kuala Lumpur 26-28 November 2005. Hallermeier, R. (1978). Uses for a calculated limit depth to beach erosion. Proceeding 16th Coastal Engineering Conference, ASCE 1493-1512. Hallermeier, R. (1981). Seaward Limit of Significant Sand Transport by Waves and Annual Zonation for Seasonal Profiles. Coastal Engineering Technical Aid, 81-2, 23p. Hinton, C. and Nicholls, R.J. (1998). Spatial and temporal behavior of depth of closure along the Holland coast. In: Proc. 26th Coastal Engineering Conference, ASCE, pp. 2913-2925 Jakobsen, P. and Brogger, C. (2007). Coastal Protection Based On Pressure Equalization Modules (PEM). Journal of Coastal Research, (Proceedings of the 9th International Coastal Symposium), Gold Coast, Australia. Jakobsen, P. (2002). Pressure Equalization Modules for Environmentally Friendly Coastal Protection. A briefing note submitted to Dept. of Irrigation & Drainage Malaysia. 152 Komar, P.D. (1998). Beach Processes and Sedimentation . (2nd ed.) Prentice Hall, Upper Saddle River, NJ. Kraus, N. C., and Wise, R. A. (1993). Simulation of January 4, 1992, Storm Erosion at Ocean City, Maryland. Shore & Beach 61 (l), 34-411. Larson, M., Kraus, N.C. and Wise, R.A. (1999). Equilibrium Beach Profiles Under Breaking and Non- Breaking Waves. Coastal Engineering, 36:59 – 85. Malaysian Resource Corporation Berhad (2006). Evaluation Report ,Spring 2006 Teluk Cempedak, Malaysia : Beach Nourishment combined with PEM System; Progress Report. Nor Hisham Mohd Ghazali (2007). Determination of Depth of Closure Along the Kelantan Coast. Universiti Teknologi Malaysia; Master Thesis National Research Council (NRC) (1995). Beach Nourishment and Protection. National Academy Press. Washington, D.C. Nicholls C. Kraus, Dr. Magnus Larson and Randall A. Wise. (1998). Depth of Closure in Beach-fill Design; Coastal Engineering Technical Note. Nicholls, R.J., Birkemeier, W.A., and Hallermeier, R.J. (1996). Application of the depth of closure concept, 25th International Conference on Coastal Engineering, Book of Abstracts, Paper No. 147, 294-295. Oxford University Press (1998): DK Illustrated Oxford Dictionary. New York. Richard, S. and John, R.C. (1997). Coastal Stabilization. Advanced Series on Ocean Engineering (Volume 14); World Scientific Publishing Co. Pte. Ltd. Singapore Robertson, W., Finkl, C.W., and Campbell, T.J. (2008). Determination of Event Depth of Closure (EDOC) for the South Florida Atlantic Coast Using Airborne Laser Bathymetry.Coastal Planning & Engineering, Inc. 153 Skagen Innovation Centre (2000). Environmentally friendly coastal protection by Pressure Equalization Modules. SIC Skagen Innovation Center, Denmark Stauble, D. K., Garcia, A. W., Kraus, N. C., Grosskopf, W. G., and Bass, G. P. (1992). Beach Nourishment Project Response and Design Evaluation, Ocean City, Maryland; Report 1, 1988 1992,Technical Report CERC-93-13, U.S. Army Engineer Waterways Experiment Station, Vicksburg, MS. U.S. Army Corp of Engineers (1984). Shore Protection Manual Volume I., Washington, D.C.: U.S. Government Printing Office. Website: Coastal Engineering Division, Department of Irrigation and Drainage, Malaysia. Documents reviewed on 21 July 2008. Website: www.brynmawr.edu/geology/dbarber/ Documents reviewed on September 2008 154 APPENDIX A PROFILE SURVEYS FROM THE COASTLINE OF PANTAI TELUK CEMPEDAK KUANTAN 2003, 2005, 2006, AND 2007 CH 100 Distance 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350 360 370 (All levels in m LSD) Profile 2003 57 53.5 50 45.8 41.2 37.3 34.4 30.3 26.4 20.2 14.6 6.4 3 1 0.2 -0.5 -0.6 -0.7 -0.8 -1 -1.1 -1.2 -1.4 -1.3 -1.3 -1.2 -1.3 -1.3 -1.3 -1.4 -1.4 -1.4 Profile 2005 57 53.5 50 45.8 41.2 37.3 34.4 30.3 26.4 11.8 8.9 3.1 3.35 2.55 0.6 -0.2 -0.45 -0.75 -1.15 -1.3 -1.35 -1.5 -1.55 -1.6 -1.45 -1.5 -1.45 -1.55 -1.55 -1.5 -1.5 -1.5 Profile 2006 57 53.5 50 45.8 41.2 37.3 34.4 30.3 26.4 20.3 14.6 6.55 3.15 0.75 0.25 0.05 -0.2 -0.45 -0.65 -0.9 -1.05 -1.15 -1.3 -1.4 -1.55 -1.55 -1.7 -1.7 -1.7 -1.7 -1.7 -1.75 Profile 2007 57 53.5 50 45.8 41.2 37.3 34.4 30.3 26.4 20.3 14.6 6.4 2.2 1.1 0.4 0.05 -0.2 -0.55 -0.8 -1.05 -1.2 -1.25 -1.3 -1.3 -1.35 -1.3 -1.3 -1.3 -1.25 -1.25 -1.25 -1.25 155 380 390 400 410 420 430 440 450 460 470 480 490 500 510 520 530 540 550 560 570 580 590 600 610 620 630 640 650 660 670 680 690 700 710 720 730 740 750 760 770 -1.5 -1.5 -1.5 -1.6 -1.6 -1.7 -1.8 -1.8 -1.9 -2 -2.1 -2.2 -2.3 -2.4 -2.4 -2.6 -2.8 -3 -3.1 -3.3 -3.1 -3.1 -3.2 -3.3 -3.3 -3.3 -3.5 -3.5 -3.7 -3.8 -4 -4.2 -4.2 -4.5 -4.5 -4.7 -4.9 -5 -5.1 -5.2 -1.5 -1.5 -1.45 -1.5 -1.55 -1.65 -1.75 -1.9 -2 -2.05 -2.1 -2.1 -2.2 -2.45 -2.6 -2.75 -2.85 -3.25 -3.55 -3.6 -3.6 -3.5 -3.55 -3.6 -3.55 -3.6 -3.7 -3.85 -3.95 -4.15 -4.3 -4.4 -4.6 -4.75 -4.85 -4.9 -5.05 -5.2 -5.35 -5.5 -1.6 -1.55 -1.55 -1.5 -1.5 -1.4 -1.25 -1.2 -1.35 -1.45 -1.55 -1.5 -1.55 -1.8 -2.15 -2.45 -2.75 -3.05 -3.3 -3.3 -3.35 -3.4 -3.4 -3.4 -3.45 -3.7 -3.7 -3.8 -3.85 -3.95 -4.05 -4.25 -4.5 -4.55 -4.6 -4.65 -4.85 -4.9 -5.1 -5.25 -1.3 -1.25 -1.3 -1.3 -1.3 -1.35 -1.4 -1.5 -1.65 -1.8 -2 -2.1 -2.3 -2.5 -2.65 -2.8 -2.95 -3.15 -3.3 -3.3 -3.4 -3.4 -3.3 -3.4 -3.45 -3.55 -3.6 -3.75 -3.9 -4 -4.15 -4.25 -4.35 -4.5 -4.55 -4.7 -4.85 -5.15 -5.35 -5.45 156 780 790 800 810 820 830 840 850 860 870 880 890 900 910 920 930 940 950 960 970 980 990 1000 1010 1020 1030 1040 1050 1060 1070 1080 1090 1100 1110 1120 1130 1140 1150 1160 1170 -5.4 -5.6 -5.7 -6 -6 -6.1 -6.1 -6.2 -6.3 -6.4 -6.5 -6.6 -6.7 -6.8 -6.8 -7 -7.1 -7.1 -7.3 -7.4 -7.5 -7.6 -7.8 -7.8 -7.9 -8 -8.1 -8.2 -8.3 -8.4 -8.4 -8.6 -8.7 -8.8 -8.8 -9.1 -9 -9 -9 -5.6 -5.75 -5.8 -5.95 -6 -6.1 -6.3 -6.4 -6.5 -6.6 -6.7 -6.75 -6.9 -7.05 -7.15 -7.2 -7.35 -7.45 -7.55 -7.75 -7.85 -7.95 -8.05 -8.15 -8.25 -8.35 -8.5 -8.6 -8.7 -8.8 -8.9 -8.9 -8.8 -8.85 -9 -9.05 -9.15 -9.25 -9.25 -9.25 -5.3 -5.5 -5.55 -5.65 -5.8 -5.9 -5.95 -6.05 -6.3 -6.45 -6.6 -6.7 -6.75 -6.85 -7.05 -7.1 -7.15 -7.35 -7.4 -7.5 -7.6 -7.75 -7.95 -8 -8.2 -8.35 -8.5 -8.65 -8.7 -8.7 -8.7 -8.75 -8.85 -8.9 -9 -9.05 -9.05 -9.1 -9.1 -9.15 -5.5 -5.6 -5.75 -5.75 -5.95 -6.1 -6.25 -6.3 -6.4 -6.5 -6.55 -6.7 -6.85 -7 -7.15 -7.25 -7.35 -7.5 -7.6 -7.7 -7.7 -7.8 -8 -8.05 -8.2 -8.3 -8.35 -8.5 -8.6 -8.7 -8.75 -8.8 -8.85 -8.95 -8.95 -9.05 -9.15 -9.1 -9.15 -9.3 157 1180 1190 1200 1210 1220 1230 1240 1250 -9.25 -9.3 -9.35 -9.4 -9.4 -9.45 -9.55 -9.65 CH 200 Distance 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 -9.2 -9.2 -9.25 -9.25 -9.25 -9.25 -9.35 -9.4 -9.35 -9.35 -9.35 -9.4 (All levels in m LSD) Profile 2003 50.3 49.3 45.4 41.4 37.7 34.1 30.8 27.5 23.2 19.1 12.9 5.95 3.45 1.9 0.85 0.1 -0.35 -0.85 -1.05 -1.2 -1.3 -1.5 -1.6 -1.7 -1.9 -2 Profile 2005 50.3 49.3 45.4 41.4 37.7 34.1 30.8 27.5 23.3 19.2 12.9 4.65 1.6 0.8 0.2 -0.4 -0.9 -1.15 -1.4 -1.65 -1.85 -2 -2.05 -2.15 -2.2 -2.2 Profile 2006 50.3 49.3 45.4 41.4 37.7 34.1 30.8 27.5 23.3 19.2 12.9 6 3.5 1.8 0.2 -0.2 -0.45 -0.65 -0.85 -1 -1.2 -1.4 -1.7 -1.9 -2.05 -2.1 Profile 2007 50.3 49.3 45.4 41.4 37.7 34.1 30.8 27.5 23.3 19.2 12.9 6 3.5 1.8 0.2 -0.2 -0.5 -0.8 -1.05 -1.3 -1.6 -1.8 -1.95 -2.1 -2.1 -2.25 158 260 270 280 290 300 310 320 330 340 350 360 370 380 390 400 410 420 430 440 450 460 470 480 490 500 510 520 530 540 550 560 570 580 590 600 610 620 630 640 650 -2.05 -2.25 -2.25 -2.4 -2.35 -2.45 -2.5 -2.55 -2.6 -2.65 -2.6 -2.65 -2.65 -2.65 -2.7 -2.75 -2.85 -2.85 -2.9 -2.85 -3 -2.95 -3.1 -3.15 -3.15 -3.25 -3.4 -3.45 -3.45 -3.5 -3.6 -3.6 -3.7 -3.8 -3.8 -3.85 -3.95 -4.1 -4.15 -4.25 -2.25 -2.35 -2.4 -2.5 -2.45 -2.5 -2.5 -2.65 -2.7 -2.7 -2.85 -2.75 -2.8 -2.8 -2.8 -2.85 -2.85 -2.95 -2.95 -3 -2.95 -3 -3 -3.15 -3.35 -3.65 -3.95 -4.05 -4.1 -4 -3.9 -3.9 -3.9 -3.9 -4.05 -4.05 -4.1 -4.15 -4.3 -4.4 -2.15 -2.35 -2.15 -2.25 -2.25 -2.4 -2.45 -2.6 -2.55 -2.6 -2.6 -2.6 -2.7 -2.85 -2.95 -2.95 -3 -3.05 -3.05 -3 -3 -3.05 -3.2 -3.3 -3.4 -3.45 -3.5 -3.55 -3.6 -3.55 -3.7 -3.75 -3.75 -3.75 -3.85 -3.85 -4 -4 -4.1 -4.25 -2.35 -2.45 -2.35 -2.35 -2.5 -2.6 -2.65 -2.7 -2.65 -2.65 -2.7 -2.65 -2.7 -2.7 -2.75 -2.8 -2.8 -2.8 -2.85 -2.95 -3.05 -3.1 -3.15 -3.25 -3.35 -3.45 -3.45 -3.5 -3.6 -3.65 -3.75 -3.75 -3.75 -3.85 -3.95 -4 -4 -4.1 -4.15 -4.25 159 660 670 680 690 700 710 720 730 740 750 760 770 780 790 800 810 820 830 840 850 860 870 880 890 900 910 920 930 940 950 960 970 980 990 1000 1010 1020 1030 1040 1050 -4.4 -4.5 -4.75 -4.65 -4.85 -4.9 -5 -5.15 -5.25 -5.45 -5.5 -5.65 -5.75 -5.95 -6.05 -6.1 -6.2 -6.4 -6.5 -6.65 -6.65 -6.8 -6.85 -6.9 -7 -7.2 -7.25 -7.35 -7.45 -7.55 -7.7 -7.8 -7.9 -8.05 -8.1 -8.15 -8.3 -8.35 -8.45 -8.5 -4.45 -4.6 -4.75 -4.85 -4.9 -5.05 -5.2 -5.4 -5.5 -5.6 -5.7 -5.8 -5.95 -6.15 -6.2 -6.25 -6.35 -6.5 -6.6 -6.7 -6.8 -6.85 -7 -7.15 -7.15 -7.35 -7.4 -7.5 -7.65 -7.75 -7.9 -8 -8.1 -8.15 -8.3 -8.4 -8.5 -8.65 -8.7 -8.75 -4.35 -4.4 -4.55 -4.65 -4.8 -4.95 -5.05 -5.15 -5.25 -5.4 -5.5 -5.7 -5.8 -5.95 -6 -6.2 -6.25 -6.3 -6.45 -6.6 -6.7 -6.8 -6.9 -7 -7.15 -7.25 -7.3 -7.4 -7.45 -7.6 -7.7 -7.8 -8 -8.15 -8.25 -8.25 -8.35 -8.45 -8.5 -8.6 -4.35 -4.4 -4.5 -4.65 -4.75 -4.9 -5 -5.15 -5.25 -5.4 -5.5 -5.6 -5.7 -5.85 -5.95 -6.1 -6.2 -6.3 -6.4 -6.55 -6.65 -6.75 -6.85 -7 -7.05 -7.15 -7.25 -7.45 -7.45 -7.6 -7.75 -7.85 -7.95 -8.05 -8.2 -8.3 -8.35 -8.4 -8.55 -8.65 160 1060 1070 1080 1090 1100 1110 1120 1130 1140 1150 1160 1170 1180 1190 1200 1210 1220 1230 1240 1250 -8.6 -8.65 -8.7 -8.75 -8.8 -8.9 -8.9 -9 -9 -9.05 -9.15 CH 300 Distance 0 10 20 30 40 50 60 70 80 90 100 110 120 130 -8.8 -8.95 -9 -9.1 -9.05 -9.15 -9.2 -9.15 -9.25 -9.3 -9.35 -9.4 -9.35 -9.45 -9.5 -9.55 -9.55 -9.6 -9.7 -9.65 -8.75 -8.9 -8.9 -8.9 -8.85 -8.9 -9 -9.1 -9.05 -9.05 -9.1 -9.25 -9.35 -9.3 -9.4 -9.4 -9.5 -9.5 -9.55 -9.7 -8.7 -8.75 -8.85 -8.9 -9 -9.05 -9.05 -9.1 -9.1 -9.05 -9.1 -9.15 -9.25 -9.3 -9.35 -9.4 -9.45 -9.5 (All levels in m LSD) Profile 2003 23.3 22.9 18.3 12.8 8.95 5.2 3.45 1.95 1.1 0.2 -0.1 -0.35 -0.6 -1.65 Profile 2005 23.2 22.8 18.2 12.8 8.3 3.6 2.3 2.3 1.7 0.8 0.25 -0.7 -1.3 -1.4 Profile 2006 23.2 22.8 18.2 12.8 8.3 3.6 2.3 2.3 1.7 0.85 0.75 0.4 -0.4 -0.9 Profile 2007 23.2 22.8 18.2 12.8 8.3 3.6 2.3 2.3 1.7 0.05 -0.4 -0.75 -1.15 -1.25 161 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350 360 370 380 390 400 410 420 430 440 450 460 470 480 490 500 510 520 530 -1.75 -1.75 -1.7 -1.95 -2 -2.3 -2.4 -2.5 -2.75 -2.8 -2.85 -2.85 -2.95 -2.9 -2.9 -2.95 -3 -3 -3.15 -3.1 -3.1 -3.25 -3.35 -3.35 -3.55 -3.6 -3.65 -3.7 -3.75 -3.85 -3.85 -3.8 -3.8 -3.8 -3.75 -3.75 -3.9 -3.9 -4.1 -4 -1.4 -1.5 -1.75 -1.9 -2.25 -2.55 -2.6 -2.65 -2.6 -2.7 -2.7 -2.75 -2.75 -2.9 -2.85 -2.8 -2.85 -2.9 -3.15 -3.2 -3.25 -3.25 -3.25 -3.35 -3.45 -3.6 -3.7 -3.7 -3.75 -3.75 -3.85 -3.8 -3.8 -3.8 -3.85 -3.85 -3.9 -3.9 -3.95 -3.9 -1.2 -1.4 -1.65 -1.9 -2.05 -2.25 -2.45 -2.6 -2.65 -2.6 -2.65 -2.75 -2.8 -2.85 -2.9 -2.9 -3.05 -3.2 -3.25 -3.25 -3.15 -3.25 -3.35 -3.3 -3.35 -3.55 -3.65 -3.65 -3.6 -3.7 -3.8 -3.8 -3.8 -3.75 -3.85 -3.85 -3.8 -3.9 -3.95 -3.95 -1.35 -1.55 -1.8 -2.05 -2.2 -2.35 -2.4 -2.45 -2.6 -2.65 -2.7 -2.75 -2.8 -2.85 -2.85 -2.9 -2.95 -3 -3 -3 -3.1 -3.15 -3.3 -3.4 -3.45 -3.55 -3.7 -3.85 -3.9 -3.85 -3.8 -3.85 -3.85 -3.9 -3.85 -3.85 -3.9 -3.9 -3.95 -3.95 162 540 550 560 570 580 590 600 610 620 630 640 650 660 670 680 690 700 710 720 730 740 750 760 770 780 790 800 810 820 830 840 850 860 870 880 890 900 910 920 930 -4.1 -4.05 -4.15 -4.2 -4.25 -4.35 -4.4 -4.45 -4.5 -4.65 -4.75 -4.8 -4.85 -4.95 -5.05 -5.25 -5.35 -5.35 -5.5 -5.6 -5.65 -5.9 -5.9 -6.1 -6.15 -6.25 -6.4 -6.45 -6.55 -6.7 -6.7 -6.85 -6.85 -7.05 -7.15 -7.3 -7.35 -7.4 -7.5 -7.7 -4.05 -4.05 -4.15 -4.2 -4.25 -4.35 -4.45 -4.5 -4.55 -4.65 -4.75 -4.8 -4.95 -5 -5.1 -5.25 -5.35 -5.45 -5.55 -5.7 -5.85 -5.9 -6.05 -6.05 -6.2 -6.35 -6.45 -6.55 -6.65 -6.75 -6.85 -6.95 -7.05 -7.1 -7.2 -7.3 -7.4 -7.55 -7.6 -7.8 -4.05 -4.2 -4.2 -4.3 -4.35 -4.4 -4.35 -4.45 -4.5 -4.55 -4.6 -4.75 -4.9 -4.95 -5 -5.15 -5.35 -5.4 -5.5 -5.55 -5.75 -5.8 -5.9 -6.05 -6.25 -6.25 -6.35 -6.4 -6.5 -6.7 -6.75 -6.85 -6.95 -7.1 -7.1 -7.2 -7.35 -7.5 -7.55 -7.7 -4 -4.1 -4.1 -4.2 -4.25 -4.25 -4.35 -4.4 -4.5 -4.55 -4.6 -4.7 -4.8 -4.9 -5 -5.1 -5.2 -5.3 -5.4 -5.6 -5.7 -5.85 -6 -6.1 -6.15 -6.3 -6.4 -6.55 -6.55 -6.65 -6.85 -6.9 -7 -7.05 -7.15 -7.2 -7.3 -7.4 -7.55 -7.7 163 940 950 960 970 980 990 1000 1010 1020 1030 1040 1050 1060 1070 1080 1090 1100 1110 1120 1130 1140 1150 1160 1170 1180 1190 1200 1210 1220 1230 1240 1250 -7.75 -7.85 -7.95 -8.1 -8.1 -8.25 -8.35 -8.3 -8.35 -8.4 -8.55 -8.55 -8.6 -8.65 -8.7 -8.8 -8.9 -8.95 -9 -9.05 -9.15 -9.15 -9.2 -9.25 -9.35 CH 400 Distance 0 10 -7.9 -8 -8 -8.15 -8.3 -8.4 -8.45 -8.5 -8.6 -8.7 -8.8 -8.95 -9.05 -9.05 -9.05 -9.1 -9.1 -9.2 -9.2 -9.25 -9.3 -9.35 -9.45 -9.45 -9.45 -9.45 -9.55 -9.65 -9.65 -9.75 -9.75 -9.75 -7.85 -7.9 -7.95 -8.05 -8.15 -8.15 -8.4 -8.55 -8.6 -8.65 -8.75 -8.85 -8.9 -8.95 -8.95 -9 -9.05 -9.1 -9.15 -9.2 -9.2 -9.35 -9.4 -9.45 -9.45 -9.5 -9.45 -9.45 -9.55 -9.6 -9.65 -9.75 -7.75 -7.9 -8.05 -8.15 -8.15 -8.35 -8.4 -8.5 -8.6 -8.7 -8.8 -8.8 -8.8 -8.85 -8.95 -9 -9.1 -9.15 -9.2 -9.25 -9.3 -9.3 -9.3 -9.35 -9.4 -9.45 -9.45 -9.45 -9.55 -9.6 (All levels in m LSD) Profile 2003 3.8 2.6 Profile 2005 4.05 3.55 Profile 2006 4.1 3.5 Profile 2007 4.1 3.4 164 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350 360 370 380 390 400 410 1.5 0.95 0.7 0.6 0.15 -0.55 -1.05 -1.3 -1.45 -1.65 -1.95 -2.05 -2.05 -2.2 -2.45 -2.65 -2.8 -2.9 -2.9 -3 -2.95 -3.15 -3.15 -3.2 -3.15 -3.2 -3.35 -3.35 -3.45 -3.4 -3.45 -3.45 -3.5 -3.6 -3.6 -3.75 -3.75 -3.85 -3.95 -3.85 3.2 3.15 1.85 1.3 0.85 0.7 0.25 -0.4 -1.15 -1.45 -1.55 -1.75 -1.95 -2.1 -2.35 -2.55 -2.65 -2.8 -2.85 -2.9 -2.9 -3.05 -3.15 -3.15 -3.15 -3.25 -3.4 -3.3 -3.4 -3.45 -3.45 -3.5 -3.6 -3.65 -3.65 -3.6 -3.7 -3.7 -3.8 -3.9 3.15 2.9 1.8 1.15 1 0.9 0.3 -0.5 -1 -1.25 -1.4 -1.45 -1.85 -2.05 -2.35 -2.5 -2.65 -2.65 -2.8 -2.85 -2.9 -3.05 -3.1 -3.1 -3.1 -3.1 -3.1 -3.25 -3.25 -3.25 -3.35 -3.45 -3.55 -3.6 -3.6 -3.7 -3.75 -3.9 -3.8 -3.8 3.5 4 1.7 0.4 -0.1 -0.3 -0.6 -0.9 -1 -1.4 -1.5 -1.8 -2.2 -2.4 -2.5 -2.5 -2.6 -2.7 -2.7 -2.75 -2.85 -2.85 -2.9 -3 -3.05 -3.1 -3.15 -3.2 -3.3 -3.3 -3.3 -3.35 -3.45 -3.5 -3.5 -3.65 -3.7 -3.7 -3.7 -3.8 165 420 430 440 450 460 470 480 490 500 510 520 530 540 550 560 570 580 590 600 610 620 630 640 650 660 670 680 690 700 710 720 730 740 750 760 770 780 790 800 810 -3.95 -4.05 -4.15 -4.1 -4.1 -4.15 -4.15 -4.3 -4.25 -4.3 -4.4 -4.45 -4.45 -4.45 -4.55 -4.65 -4.75 -4.75 -4.85 -4.9 -5.05 -5.1 -5.2 -5.15 -5.3 -5.35 -5.4 -5.6 -5.65 -5.8 -5.9 -6 -6.1 -6.2 -6.25 -6.4 -6.5 -6.55 -6.7 -6.8 -3.9 -3.9 -4 -4 -4.1 -4.15 -4.2 -4.2 -4.3 -4.35 -4.35 -4.45 -4.55 -4.6 -4.6 -4.6 -4.75 -4.9 -4.85 -5.05 -5 -5.1 -5.2 -5.3 -5.4 -5.45 -5.5 -5.65 -5.75 -5.85 -5.9 -6.05 -6.15 -6.25 -6.35 -6.4 -6.45 -6.55 -6.6 -6.8 -3.85 -3.95 -3.95 -4 -3.95 -4.05 -4.2 -4.3 -4.25 -4.25 -4.35 -4.4 -4.5 -4.5 -4.65 -4.8 -4.8 -4.8 -4.8 -4.95 -5.05 -5.05 -5.05 -5.1 -5.25 -5.45 -5.55 -5.55 -5.7 -5.85 -6 -6.05 -6.05 -6.15 -6.3 -6.35 -6.45 -6.45 -6.6 -6.75 -3.8 -3.9 -3.9 -3.95 -4.05 -4.1 -4.05 -4.1 -4.2 -4.2 -4.25 -4.3 -4.4 -4.5 -4.6 -4.65 -4.65 -4.75 -4.85 -4.9 -4.95 -5 -5.05 -5.15 -5.25 -5.3 -5.4 -5.45 -5.55 -5.65 -5.75 -5.85 -6 -6.1 -6.15 -6.3 -6.45 -6.5 -6.6 -6.7 166 820 830 840 850 860 870 880 890 900 910 920 930 940 950 960 970 980 990 1000 1010 1020 1030 1040 1050 1060 1070 1080 1090 1100 1110 1120 1130 1140 1150 1160 1170 1180 1190 1200 1210 -6.9 -7 -7.1 -7.1 -7.3 -7.4 -7.4 -7.5 -7.6 -7.65 -7.85 -7.9 -8 -8 -8.15 -8.15 -8.35 -8.35 -8.45 -8.6 -8.65 -8.65 -8.7 -8.75 -8.75 -8.8 -8.8 -8.95 -9 -9 -9.05 -9.15 -9.15 -9.35 -9.35 -9.4 -6.9 -7 -7.1 -7.25 -7.3 -7.4 -7.45 -7.55 -7.65 -7.7 -7.85 -7.95 -8.05 -8.1 -8.25 -8.3 -8.4 -8.5 -8.55 -8.6 -8.7 -8.8 -8.9 -8.95 -8.95 -9 -9 -9.05 -9.15 -9.2 -9.25 -9.25 -9.35 -9.45 -9.45 -9.5 -9.5 -9.5 -9.6 -9.65 -6.85 -6.95 -7 -7.05 -7.3 -7.35 -7.45 -7.5 -7.65 -7.8 -7.85 -7.9 -7.95 -8.15 -8.2 -8.25 -8.4 -8.45 -8.55 -8.55 -8.65 -8.75 -8.85 -8.85 -8.95 -9.05 -9.1 -9.1 -9.15 -9.25 -9.3 -9.35 -9.35 -9.35 -9.4 -9.55 -9.55 -9.5 -9.55 -9.6 -6.75 -6.8 -6.9 -7 -7.1 -7.2 -7.3 -7.4 -7.5 -7.7 -7.8 -7.95 -8 -8.1 -8.15 -8.3 -8.35 -8.4 -8.45 -8.6 -8.7 -8.7 -8.75 -8.85 -8.9 -9 -9 -9.1 -9.15 -9.15 -9.15 -9.25 -9.25 -9.4 -9.5 -9.45 -9.55 -9.55 -9.6 -9.55 167 1220 1230 1240 1250 -9.65 -9.7 -9.75 -9.8 CH 500 Distance 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 -9.6 -9.65 -9.75 -9.75 -9.55 -9.7 -9.75 -9.8 (All levels in m LSD) Profile 2003 5.3 3.2 1.9 1.1 0.35 -0.35 -0.65 -0.95 -1.1 -1.4 -1.65 -1.65 -1.9 -2.2 -2.5 -2.6 -2.7 -2.75 -2.8 -3 -3 -3.15 -3.1 -3.2 -3.35 -3.25 -3.4 -3.4 -3.45 -3.55 Profile 2005 5.1 3.9 3.25 3 2.35 1.7 1.25 0.5 -0.35 -0.95 -1.05 -1.2 -1.4 -1.7 -1.85 -2.15 -2.55 -2.75 -2.8 -2.9 -3 -3.1 -3.15 -3.2 -3.25 -3.3 -3.3 -3.35 -3.45 -3.5 Profile 2006 5.1 4 3.45 3.55 2.5 1.45 0.9 0.7 0.15 -0.55 -1.15 -1.25 -1.45 -1.5 -1.85 -2.15 -2.4 -2.6 -2.65 -2.75 -2.9 -3 -3 -3 -3 -3.1 -3.25 -3.35 -3.45 -3.4 Profile 2007 5.1 4.15 3.8 3.95 2.8 1.2 -0.05 -0.5 -0.55 -0.8 -1.05 -1.3 -1.55 -1.8 -2 -2.2 -2.4 -2.6 -2.65 -2.75 -2.85 -2.9 -3.05 -3.1 -3.1 -3.15 -3.2 -3.3 -3.35 -3.35 168 300 310 320 330 340 350 360 370 380 390 400 410 420 430 440 450 460 470 480 490 500 510 520 530 540 550 560 570 580 590 600 610 620 630 640 650 660 670 680 690 -3.6 -3.6 -3.65 -3.7 -3.75 -3.85 -3.85 -3.85 -4 -4 -4 -4.1 -4.1 -4.15 -4.2 -4.15 -4.35 -4.3 -4.4 -4.4 -4.55 -4.55 -4.6 -4.65 -4.75 -4.8 -4.85 -4.95 -5 -5.05 -5.05 -5.15 -5.2 -5.45 -5.5 -5.55 -5.55 -5.7 -5.8 -6 -3.55 -3.6 -3.65 -3.7 -3.75 -3.8 -3.75 -3.75 -3.85 -3.9 -4 -4.05 -4.05 -4.15 -4.3 -4.35 -4.4 -4.45 -4.5 -4.65 -4.75 -4.85 -4.95 -4.95 -5.05 -5.2 -5.25 -5.25 -5.3 -5.35 -5.35 -5.45 -5.5 -5.55 -5.65 -5.7 -5.75 -5.75 -5.9 -6 -3.45 -3.45 -3.6 -3.65 -3.65 -3.7 -3.7 -3.7 -3.9 -3.85 -3.95 -3.95 -4.05 -4.2 -4.3 -4.25 -4.25 -4.4 -4.55 -4.45 -4.5 -4.5 -4.6 -4.75 -4.75 -4.85 -4.9 -5.1 -5.15 -5.1 -5.25 -5.3 -5.4 -5.4 -5.55 -5.55 -5.55 -5.55 -5.65 -5.85 -3.45 -3.5 -3.55 -3.6 -3.65 -3.7 -3.7 -3.75 -3.8 -3.9 -4 -4 -4 -4.1 -4.2 -4.3 -4.3 -4.3 -4.4 -4.4 -4.5 -4.55 -4.6 -4.6 -4.7 -4.8 -4.85 -4.95 -4.95 -5.1 -5.15 -5.2 -5.3 -5.35 -5.4 -5.5 -5.55 -5.65 -5.75 -5.8 169 700 710 720 730 740 750 760 770 780 790 800 810 820 830 840 850 860 870 880 890 900 910 920 930 940 950 960 970 980 990 1000 1010 1020 1030 1040 1050 1060 1070 1080 1090 -6.05 -6.1 -6.15 -6.25 -6.35 -6.45 -6.55 -6.6 -6.7 -6.85 -6.85 -6.95 -7.1 -7.1 -7.3 -7.35 -7.4 -7.6 -7.5 -7.65 -7.7 -7.85 -7.9 -8 -8.1 -8.25 -8.25 -8.35 -8.35 -8.45 -8.45 -8.6 -8.65 -8.7 -8.75 -8.8 -8.8 -8.8 -9 -9 -6.1 -6.15 -6.2 -6.3 -6.4 -6.5 -6.65 -6.65 -6.75 -6.85 -6.95 -7.1 -7.25 -7.25 -7.35 -7.45 -7.5 -7.65 -7.7 -7.8 -7.95 -8 -8 -8.15 -8.25 -8.3 -8.4 -8.4 -8.5 -8.5 -8.55 -8.75 -8.75 -8.85 -8.95 -8.95 -9.05 -9.05 -9.15 -9.2 -5.9 -5.95 -6.1 -6.2 -6.35 -6.3 -6.5 -6.6 -6.65 -6.75 -6.8 -6.95 -7 -7.15 -7.25 -7.4 -7.4 -7.45 -7.55 -7.65 -7.7 -7.8 -7.9 -8.05 -8.1 -8.25 -8.3 -8.35 -8.5 -8.5 -8.55 -8.6 -8.75 -8.8 -8.75 -8.8 -8.95 -9 -8.95 -9.1 -5.9 -6.05 -6.1 -6.15 -6.2 -6.3 -6.45 -6.55 -6.7 -6.8 -6.9 -6.95 -7.05 -7.15 -7.25 -7.3 -7.35 -7.5 -7.6 -7.7 -7.75 -7.9 -8 -8.1 -8.2 -8.2 -8.25 -8.3 -8.4 -8.5 -8.6 -8.65 -8.7 -8.8 -8.85 -8.95 -9 -9.05 -9.1 -9.15 170 1100 1110 1120 1130 1140 1150 1160 1170 1180 1190 1200 1210 1220 1230 1240 1250 -9.1 -9.15 -9.15 -9.2 -9.35 -9.4 -9.35 -9.4 -9.45 CH 600 Distance 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 -9.25 -9.3 -9.35 -9.4 -9.5 -9.55 -9.55 -9.6 -9.65 -9.7 -9.75 -9.75 -9.85 -9.8 -9.9 -10 -9.15 -9.25 -9.25 -9.25 -9.35 -9.4 -9.4 -9.45 -9.5 -9.55 -9.55 -9.6 -9.7 -9.75 -9.7 -9.75 -9.2 -9.25 -9.3 -9.3 -9.4 -9.45 -9.5 -9.5 -9.55 -9.6 -9.65 -9.65 -9.65 -9.75 -9.8 -9.85 (All levels in m LSD) Profile 2003 5.85 4 2.8 1.55 0.3 -0.6 -0.7 -0.9 -0.95 -1.3 -1.5 -1.6 -1.8 -2.25 -2.4 -2.55 -2.65 -2.8 Profile 2005 6 4.8 3.95 3.5 3.6 2.65 1.95 0.8 -0.4 -1.25 -1.2 -1.15 -1.35 -1.55 -1.75 -2 -2.3 -2.65 Profile 2006 6 4.8 4 3.65 3.6 2.3 1.45 0.85 0.15 -0.65 -1.2 -1.35 -1.4 -1.45 -1.6 -1.9 -2.25 -2.5 Profile 2007 6 5.2 4.25 3.95 3.85 2.25 0.9 -0.05 -0.5 -0.8 -1 -1.15 -1.45 -1.75 -2 -2.2 -2.4 -2.6 171 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350 360 370 380 390 400 410 420 430 440 450 460 470 480 490 500 510 520 530 540 550 560 570 -2.85 -3 -3.15 -3.4 -3.45 -3.3 -3.35 -3.45 -3.6 -3.55 -3.6 -3.65 -3.8 -3.8 -3.9 -3.95 -3.9 -3.9 -3.95 -4.05 -4 -4.15 -4.2 -4.2 -4.25 -4.25 -4.3 -4.35 -4.45 -4.45 -4.6 -4.65 -4.7 -4.75 -4.8 -4.85 -4.85 -5 -5.05 -5.1 -2.85 -2.95 -3.05 -3.2 -3.3 -3.35 -3.45 -3.55 -3.5 -3.6 -3.65 -3.7 -3.75 -3.75 -3.75 -3.75 -3.8 -3.85 -4 -4.1 -4.15 -4.2 -4.25 -4.25 -4.25 -4.35 -4.4 -4.5 -4.5 -4.55 -4.65 -4.7 -4.7 -4.75 -4.85 -4.95 -5.1 -5.1 -5.15 -5.25 -2.7 -2.8 -2.95 -2.95 -3.05 -3.2 -3.3 -3.35 -3.35 -3.4 -3.4 -3.4 -3.5 -3.65 -3.75 -3.8 -3.8 -3.8 -3.85 -3.95 -3.95 -3.9 -4 -4.05 -4.25 -4.35 -4.4 -4.4 -4.55 -4.7 -4.65 -4.65 -4.8 -4.95 -4.9 -4.85 -4.9 -5.05 -5.2 -5.15 -2.7 -2.85 -2.9 -3 -3.05 -3.05 -3.15 -3.2 -3.25 -3.3 -3.35 -3.45 -3.5 -3.55 -3.6 -3.7 -3.75 -3.75 -3.8 -3.85 -3.9 -4 -4.15 -4.15 -4.15 -4.2 -4.3 -4.35 -4.45 -4.5 -4.55 -4.65 -4.65 -4.75 -4.75 -4.85 -4.95 -5.05 -5.1 -5.15 172 580 590 600 610 620 630 640 650 660 670 680 690 700 710 720 730 740 750 760 770 780 790 800 810 820 830 840 850 860 870 880 890 900 910 920 930 940 950 960 970 -5.15 -5.25 -5.35 -5.45 -5.4 -5.55 -5.65 -5.75 -5.8 -5.95 -5.95 -6.1 -6.25 -6.3 -6.3 -6.4 -6.5 -6.55 -6.7 -6.8 -6.85 -6.95 -7 -7.1 -7.15 -7.25 -7.35 -7.45 -7.6 -7.7 -7.75 -7.75 -7.85 -7.95 -8.15 -8.2 -8.25 -8.35 -8.45 -8.5 -5.25 -5.35 -5.45 -5.6 -5.65 -5.7 -5.8 -5.85 -5.9 -6 -6.05 -6.1 -6.15 -6.25 -6.3 -6.45 -6.6 -6.75 -6.8 -6.85 -6.95 -7 -7.05 -7.1 -7.2 -7.35 -7.45 -7.6 -7.65 -7.7 -7.8 -7.9 -8.05 -8.1 -8.15 -8.25 -8.35 -8.4 -8.45 -8.55 -5.2 -5.3 -5.45 -5.4 -5.4 -5.5 -5.65 -5.65 -5.65 -5.8 -5.95 -6.05 -6.1 -6.2 -6.35 -6.45 -6.45 -6.55 -6.55 -6.65 -6.75 -6.8 -6.9 -7.1 -7.15 -7.15 -7.25 -7.4 -7.6 -7.65 -7.7 -7.75 -7.9 -8.05 -8.15 -8.15 -8.25 -8.3 -8.35 -8.45 -5.2 -5.2 -5.25 -5.4 -5.4 -5.45 -5.65 -5.75 -5.8 -5.9 -6 -6.1 -6.15 -6.2 -6.3 -6.4 -6.45 -6.55 -6.6 -6.7 -6.8 -6.9 -7 -7 -7.05 -7.15 -7.25 -7.35 -7.45 -7.6 -7.75 -7.9 -8 -8 -8.1 -8.15 -8.3 -8.35 -8.4 -8.5 173 980 990 1000 1010 1020 1030 1040 1050 1060 1070 1080 1090 1100 1110 1120 1130 1140 1150 1160 1170 1180 1190 1200 1210 1220 1230 1240 1250 -8.55 -8.55 -8.65 -8.65 -8.75 -8.8 -8.8 -8.9 -9 -9.15 -9.05 -9.15 -9.2 -9.15 -9.3 -9.3 -9.35 -9.4 -9.45 -9.55 -9.65 CH 700 Distance 0 10 20 30 40 50 -8.55 -8.55 -8.6 -8.65 -8.85 -8.9 -9 -9 -9.1 -9.1 -9.25 -9.25 -9.35 -9.45 -9.4 -9.45 -9.45 -9.5 -9.65 -9.6 -9.6 -9.7 -9.75 -9.8 -9.8 -9.85 -9.85 -9.9 -8.5 -8.5 -8.6 -8.7 -8.75 -8.8 -8.9 -8.9 -8.95 -9.05 -9.15 -9.15 -9.2 -9.25 -9.25 -9.25 -9.35 -9.45 -9.45 -9.4 -9.4 -9.6 -9.6 -9.5 -9.6 -9.7 -9.7 -9.75 -8.55 -8.6 -8.65 -8.75 -8.75 -8.85 -8.9 -8.95 -8.95 -9 -9.05 -9.1 -9.15 -9.25 -9.3 -9.35 -9.35 -9.4 -9.45 -9.45 -9.5 -9.6 -9.65 -9.7 -9.6 -9.65 -9.65 -9.7 (All levels in m LSD) Profile 2003 6.3 6.1 5.05 2.35 1.3 0.1 Profile 2005 6.1 4.4 4.1 3.8 3.6 3.25 Profile 2006 6.1 4.4 4.1 3.8 3.8 3.45 Profile 2007 6.1 4.4 4.1 3.8 4 3.5 174 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350 360 370 380 390 400 410 420 430 440 450 -0.8 -0.85 -0.95 -1.2 -1.3 -1.5 -1.8 -2.1 -2.3 -2.6 -2.75 -3.05 -3 -3.05 -3.2 -3.3 -3.4 -3.45 -3.5 -3.55 -3.65 -3.65 -3.7 -3.7 -3.75 -3.85 -3.9 -3.9 -3.95 -4 -4.1 -4.1 -4.2 -4.25 -4.3 -4.3 -4.3 -4.4 -4.45 -4.45 2.1 1.15 0 -1 -1.3 -1.3 -1.45 -1.6 -1.8 -2 -2.4 -2.85 -3.05 -3.2 -3.35 -3.45 -3.5 -3.45 -3.55 -3.5 -3.55 -3.6 -3.7 -3.75 -3.7 -3.8 -3.9 -3.95 -3.95 -4 -4 -4.05 -4.1 -4.1 -4.15 -4.25 -4.3 -4.25 -4.35 -4.5 2.3 1.35 0.5 -0.4 -1.1 -1.35 -1.4 -1.45 -1.5 -1.9 -2.15 -2.55 -2.85 -3 -3.1 -3.2 -3.25 -3.35 -3.5 -3.45 -3.45 -3.5 -3.65 -3.7 -3.7 -3.7 -3.7 -3.8 -3.85 -3.85 -3.9 -4 -4.15 -4.1 -4.15 -4.25 -4.25 -4.45 -4.5 -4.5 1.85 0.4 -0.4 -0.7 -0.85 -1.1 -1.35 -1.6 -1.9 -2.15 -2.45 -2.65 -2.8 -2.95 -3.05 -3.15 -3.25 -3.3 -3.35 -3.45 -3.45 -3.5 -3.55 -3.6 -3.65 -3.75 -3.8 -3.85 -3.9 -3.95 -4 -4 -4.1 -4.2 -4.2 -4.3 -4.35 -4.35 -4.4 -4.45 175 460 470 480 490 500 510 520 530 540 550 560 570 580 590 600 610 620 630 640 650 660 670 680 690 700 710 720 730 740 750 760 770 780 790 800 810 820 830 840 850 -4.6 -4.55 -4.65 -4.7 -4.75 -4.9 -4.95 -4.95 -4.95 -5.05 -5.05 -5.2 -5.2 -5.3 -5.4 -5.55 -5.55 -5.7 -5.7 -5.9 -6 -6.05 -6.1 -6.25 -6.4 -6.45 -6.55 -6.65 -6.65 -6.8 -6.9 -7 -7 -7.15 -7.25 -7.3 -7.3 -7.45 -7.5 -7.55 -4.55 -4.65 -4.8 -4.8 -4.85 -4.85 -4.9 -5 -5.15 -5.1 -5.2 -5.35 -5.4 -5.4 -5.5 -5.6 -5.7 -5.75 -5.85 -6 -6.05 -6.2 -6.3 -6.3 -6.35 -6.45 -6.55 -6.65 -6.6 -6.75 -6.85 -7.05 -7.1 -7.15 -7.25 -7.25 -7.4 -7.45 -7.55 -7.65 -4.6 -4.7 -4.85 -4.8 -4.8 -4.9 -5 -5.2 -5.2 -5.15 -5.2 -5.35 -5.4 -5.5 -5.6 -5.65 -5.85 -5.9 -5.8 -5.8 -5.9 -6.05 -6.15 -6.15 -6.15 -6.35 -6.45 -6.55 -6.65 -6.7 -6.85 -6.95 -7 -7.05 -7.1 -7.1 -7.3 -7.4 -7.55 -7.65 -4.55 -4.65 -4.7 -4.75 -4.85 -4.9 -4.95 -5 -5.05 -5.2 -5.2 -5.25 -5.35 -5.35 -5.45 -5.55 -5.6 -5.6 -5.7 -5.75 -5.85 -5.95 -6 -6.1 -6.25 -6.35 -6.4 -6.5 -6.65 -6.7 -6.8 -6.9 -7 -7.05 -7.25 -7.35 -7.4 -7.5 -7.55 -7.65 176 860 870 880 890 900 910 920 930 940 950 960 970 980 990 1000 1010 1020 1030 1040 1050 1060 1070 1080 1090 1100 1110 1120 1130 1140 1150 1160 1170 1180 1190 1200 1210 1220 1230 1240 -7.7 -7.75 -7.85 -7.9 -7.95 -8.15 -8.25 -8.3 -8.4 -8.45 -8.5 -8.65 -8.6 -8.65 -8.8 -8.8 -8.8 -8.95 -8.9 -9 -9 -9.15 -9.15 -9.2 -9.3 -9.4 -9.35 -9.35 -9.4 -9.5 -9.55 -9.5 -9.55 -7.8 -7.9 -7.95 -8.05 -8.1 -8.2 -8.25 -8.35 -8.4 -8.5 -8.5 -8.6 -8.65 -8.75 -8.8 -8.9 -8.95 -9.05 -9.05 -9.15 -9.2 -9.25 -9.35 -9.35 -9.35 -9.4 -9.45 -9.45 -9.5 -9.55 -9.6 -9.65 -9.7 -9.65 -9.75 -9.75 -9.75 -9.9 -9.9 -7.75 -7.75 -7.85 -8.05 -8 -8.05 -8.1 -8.25 -8.3 -8.35 -8.45 -8.6 -8.6 -8.6 -8.65 -8.75 -8.9 -8.9 -8.9 -8.9 -9.15 -9.25 -9.3 -9.25 -9.4 -9.3 -9.25 -9.3 -9.4 -9.5 -9.55 -9.55 -9.6 -9.65 -9.7 -9.65 -9.7 -9.8 -9.85 -7.8 -7.85 -8 -8.05 -8 -8.1 -8.15 -8.25 -8.35 -8.45 -8.45 -8.6 -8.65 -8.7 -8.7 -8.75 -8.85 -8.95 -9 -9 -9 -9.05 -9.1 -9.15 -9.2 -9.25 -9.35 -9.35 -9.4 -9.5 -9.45 -9.45 -9.5 -9.5 -9.5 -9.5 -9.5 177 1250 -10 CH 800 Distance 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 -9.9 (All levels in m LSD) Profile 2003 6.2 6 6 4.65 2.6 1.6 0.4 -0.6 -0.85 -1.05 -1.1 -1.4 -1.2 -1.55 -2.1 -2.45 -2.75 -2.9 -3.1 -3.2 -3.35 -3.4 -3.4 -3.4 -3.65 -3.65 -3.7 -3.75 -3.8 -3.8 -3.95 -4 -4 Profile 2005 6.3 6 6 4.4 3.55 3.45 3.05 2.15 1.1 -0.25 -1 -1.2 -1.2 -1.4 -1.55 -1.7 -2 -2.5 -2.8 -3.15 -3.3 -3.4 -3.4 -3.4 -3.5 -3.55 -3.65 -3.65 -3.75 -3.8 -3.8 -3.95 -4 Profile 2006 6.3 6 6 4.4 3.8 3.7 3.4 2.1 1.25 0.15 -0.65 -1.2 -1.35 -1.35 -1.45 -1.7 -2.25 -2.45 -2.8 -2.95 -3.1 -3.2 -3.3 -3.3 -3.4 -3.65 -3.7 -3.7 -3.65 -3.85 -3.95 -3.95 -3.9 Profile 2007 6.3 6 6 4.4 3.9 4 3.25 1.8 0.45 -0.5 -0.9 -1.05 -1.3 -1.55 -1.75 -2 -2.35 -2.6 -2.8 -3 -3.05 -3.2 -3.3 -3.35 -3.4 -3.5 -3.55 -3.7 -3.7 -3.8 -3.85 -3.85 -3.9 178 330 340 350 360 370 380 390 400 410 420 430 440 450 460 470 480 490 500 510 520 530 540 550 560 570 580 590 600 610 620 630 640 650 660 670 680 690 700 710 720 -4.05 -4.1 -4.1 -4.1 -4.2 -4.3 -4.3 -4.4 -4.4 -4.35 -4.45 -4.55 -4.6 -4.7 -4.75 -4.8 -4.75 -4.9 -4.9 -5.05 -5.05 -5.15 -5.2 -5.25 -5.4 -5.4 -5.55 -5.55 -5.75 -5.8 -5.8 -5.95 -5.95 -6.2 -6.3 -6.4 -6.4 -6.45 -6.55 -6.7 -4 -4 -4.05 -4.1 -4.15 -4.3 -4.3 -4.3 -4.4 -4.45 -4.45 -4.55 -4.7 -4.85 -4.95 -5 -5 -5.05 -5.05 -5.05 -5 -5.05 -5.15 -5.3 -5.35 -5.5 -5.6 -5.8 -5.85 -5.9 -5.95 -6.05 -6.05 -6.15 -6.3 -6.35 -6.45 -6.55 -6.55 -6.6 -3.9 -3.9 -3.9 -3.95 -4 -4.15 -4.15 -4.2 -4.35 -4.55 -4.55 -4.5 -4.6 -4.7 -4.75 -4.7 -4.7 -4.85 -5.1 -5.05 -5.15 -5.2 -5.35 -5.4 -5.45 -5.6 -5.6 -5.65 -5.7 -5.75 -5.9 -5.95 -6.1 -6.2 -6.3 -6.3 -6.4 -6.45 -6.45 -6.55 -3.95 -4.05 -4.1 -4.1 -4.2 -4.15 -4.25 -4.3 -4.4 -4.5 -4.5 -4.55 -4.6 -4.7 -4.75 -4.8 -4.9 -4.95 -5 -5.1 -5.15 -5.2 -5.35 -5.4 -5.5 -5.45 -5.55 -5.7 -5.8 -5.9 -5.9 -6 -6.05 -6.05 -6.15 -6.25 -6.35 -6.4 -6.4 -6.5 179 730 740 750 760 770 780 790 800 810 820 830 840 850 860 870 880 890 900 910 920 930 940 950 960 970 980 990 1000 1010 1020 1030 1040 1050 1060 1070 1080 1090 1100 1110 1120 -6.8 -6.9 -7 -7.05 -7.05 -7.15 -7.25 -7.35 -7.4 -7.5 -7.55 -7.65 -7.75 -7.8 -7.9 -7.95 -8.05 -8.15 -8.25 -8.3 -8.4 -8.45 -8.5 -8.55 -8.55 -8.65 -8.65 -8.75 -8.7 -8.9 -8.95 -8.95 -9.05 -9.15 -9.1 -9.2 -9.25 -9.35 -9.3 -9.45 -6.8 -6.9 -6.95 -7 -7.15 -7.25 -7.35 -7.35 -7.5 -7.5 -7.55 -7.7 -7.75 -7.9 -7.95 -8 -8.1 -8.25 -8.3 -8.3 -8.4 -8.45 -8.5 -8.6 -8.65 -8.75 -8.8 -8.85 -8.95 -9 -9.1 -9.2 -9.2 -9.2 -9.25 -9.3 -9.35 -9.4 -9.4 -9.45 -6.7 -6.75 -6.85 -7 -7.05 -7.1 -7.1 -7.15 -7.3 -7.45 -7.45 -7.5 -7.8 -7.9 -7.9 -7.85 -7.95 -8.15 -8.3 -8.25 -8.3 -8.4 -8.45 -8.55 -8.6 -8.6 -8.8 -8.85 -8.95 -9 -9.05 -9.15 -9.2 -9.2 -9.15 -9.2 -9.4 -9.35 -9.3 -9.35 -6.55 -6.65 -6.75 -6.85 -6.95 -7.1 -7.2 -7.25 -7.3 -7.4 -7.5 -7.6 -7.7 -7.75 -7.9 -8 -8.1 -8.15 -8.25 -8.3 -8.35 -8.45 -8.5 -8.55 -8.6 -8.7 -8.65 -8.75 -8.8 -8.9 -8.9 -9 -9 -9 -9.1 -9.2 -9.3 -9.3 -9.35 -9.3 180 1130 1140 1150 1160 1170 1180 1190 1200 1210 1220 1230 1240 1250 -9.4 -9.55 -9.6 -9.6 -9.55 -9.6 -9.7 -9.75 CH 900 Distance 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 -9.5 -9.55 -9.6 -9.7 -9.7 -9.7 -9.8 -9.75 -9.85 -9.9 -9.95 -10.05 -10.1 -9.45 -9.45 -9.4 -9.55 -9.7 -9.65 -9.6 -9.75 -9.7 -9.75 -9.85 -10.05 -10.05 -9.35 -9.45 -9.45 -9.55 -9.6 -9.6 -9.6 -9.7 -9.7 -9.7 -9.7 -9.7 -9.75 (All levels in m LSD) Profile 2003 6.2 6.2 6.2 5.75 4.25 3.1 1.95 0.65 -0.55 -1 -1.2 -1.3 -1.4 -1.55 -1.75 -2.05 -2.35 -2.65 -2.9 -3.05 -3.2 Profile 2005 6.1 6.2 6.2 4.7 4.6 3.8 3.55 3.6 2.8 1.75 0.5 -0.6 -1.05 -1.05 -1.2 -1.4 -1.7 -2.2 -2.55 -2.95 -3.25 Profile 2006 6.1 6.2 6.2 4.7 4.6 3.95 3.85 3.5 2.65 1.8 0.5 -0.7 -1.25 -1.3 -1.35 -1.4 -1.8 -2.15 -2.55 -2.9 -3.15 Profile 2007 6.1 6.2 6.2 4.7 4.4 4.25 4 3.45 2.2 0.85 -0.35 -0.8 -0.9 -1.15 -1.4 -1.6 -1.95 -2.25 -2.65 -2.95 -3.1 181 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350 360 370 380 390 400 410 420 430 440 450 460 470 480 490 500 510 520 530 540 550 560 570 580 590 600 -3.25 -3.35 -3.45 -3.55 -3.65 -3.65 -3.8 -3.8 -3.8 -3.85 -4 -4 -4.05 -4.1 -4.15 -4.2 -4.2 -4.25 -4.35 -4.45 -4.5 -4.55 -4.65 -4.6 -4.8 -4.75 -4.85 -4.9 -4.9 -4.95 -5.15 -5.05 -5.15 -5.15 -5.35 -5.35 -5.5 -5.55 -5.7 -5.7 -3.4 -3.5 -3.55 -3.65 -3.7 -3.75 -3.85 -3.8 -3.85 -4 -4.05 -4 -4.05 -4.2 -4.25 -4.25 -4.3 -4.35 -4.4 -4.45 -4.5 -4.5 -4.5 -4.55 -4.6 -4.65 -4.7 -4.8 -4.95 -5 -5.15 -5.2 -5.25 -5.3 -5.4 -5.5 -5.55 -5.65 -5.7 -5.8 -3.25 -3.3 -3.4 -3.4 -3.4 -3.6 -3.75 -3.85 -3.85 -3.85 -3.95 -4 -4.1 -4.05 -4.1 -4.15 -4.2 -4.25 -4.3 -4.35 -4.55 -4.55 -4.55 -4.55 -4.6 -4.7 -4.8 -4.85 -4.85 -4.9 -5.05 -5.1 -5.2 -5.25 -5.25 -5.4 -5.55 -5.7 -5.75 -5.7 -3.15 -3.25 -3.3 -3.4 -3.45 -3.5 -3.6 -3.65 -3.75 -3.8 -3.85 -3.95 -3.95 -4.05 -4.1 -4.2 -4.25 -4.3 -4.3 -4.35 -4.4 -4.45 -4.6 -4.65 -4.7 -4.8 -4.8 -4.8 -4.9 -5.05 -5.2 -5.2 -5.3 -5.4 -5.45 -5.5 -5.6 -5.7 -5.75 -5.9 182 610 620 630 640 650 660 670 680 690 700 710 720 730 740 750 760 770 780 790 800 810 820 830 840 850 860 870 880 890 900 910 920 930 940 950 960 970 980 990 1000 -5.85 -5.95 -6.05 -6.1 -6.15 -6.2 -6.3 -6.45 -6.6 -6.7 -6.75 -6.75 -6.9 -7.05 -7.1 -7.2 -7.25 -7.35 -7.45 -7.5 -7.55 -7.6 -7.7 -7.75 -7.8 -7.95 -8.05 -8.2 -8.2 -8.25 -8.3 -8.35 -8.5 -8.5 -8.55 -8.6 -8.7 -8.75 -8.85 -8.9 -5.8 -5.95 -6.15 -6.3 -6.4 -6.5 -6.55 -6.6 -6.7 -6.75 -6.75 -6.8 -6.9 -7.1 -7.15 -7.2 -7.3 -7.4 -7.5 -7.6 -7.7 -7.75 -7.85 -7.9 -8 -8.1 -8.1 -8.25 -8.3 -8.3 -8.4 -8.5 -8.55 -8.6 -8.7 -8.75 -8.8 -8.85 -8.9 -8.9 -5.9 -6 -5.9 -5.95 -6.15 -6.35 -6.5 -6.55 -6.65 -6.65 -6.75 -6.85 -6.9 -6.9 -6.95 -7.1 -7.2 -7.3 -7.25 -7.35 -7.5 -7.6 -7.7 -7.85 -7.9 -7.95 -8.1 -8.1 -8.15 -8.25 -8.3 -8.4 -8.4 -8.45 -8.65 -8.7 -8.65 -8.65 -8.95 -9.05 -5.9 -5.9 -6 -6.1 -6.15 -6.3 -6.3 -6.4 -6.5 -6.55 -6.65 -6.7 -6.8 -6.85 -6.95 -7 -7.1 -7.2 -7.25 -7.35 -7.4 -7.55 -7.65 -7.7 -7.85 -7.95 -8.05 -8.15 -8.2 -8.25 -8.3 -8.4 -8.45 -8.5 -8.6 -8.6 -8.65 -8.75 -8.8 -8.85 183 1010 1020 1030 1040 1050 1060 1070 1080 1090 1100 1110 1120 1130 1140 1150 1160 1170 1180 1190 1200 1210 1220 1230 1240 1250 -8.95 -8.95 -9 -9.15 -9.1 -9.2 -9.3 -9.3 -9.3 -9.4 -9.5 -9.5 -9.55 -9.6 -9.65 -9.75 -9.8 -9.8 CH 1000 Distance 0 10 20 30 40 50 60 70 80 -9.05 -9.1 -9.1 -9.25 -9.3 -9.35 -9.4 -9.4 -9.45 -9.45 -9.55 -9.6 -9.65 -9.75 -9.75 -9.75 -9.85 -9.9 -9.9 -10 -10.1 -10.05 -10.2 -10.25 -10.25 -9 -9.1 -9.05 -9.1 -9.1 -9.15 -9.25 -9.25 -9.3 -9.5 -9.55 -9.5 -9.45 -9.6 -9.55 -9.7 -9.75 -9.95 -10 -9.95 -10.05 -10.2 -10.25 -10.2 -10.25 -9 -9.1 -9.15 -9.2 -9.25 -9.25 -9.3 -9.35 -9.45 -9.45 -9.5 -9.5 -9.6 -9.6 -9.7 -9.7 -9.7 -9.75 -9.75 -9.8 -9.8 (All levels in m LSD) Profile 2003 8.8 7.9 7 6.1 5.8 4.5 3.15 2.85 1 Profile 2005 8.8 7.9 7 6.1 5.7 4.3 3.8 3.55 3.65 Profile 2006 8.8 7.9 7 6.1 5.7 4.3 3.8 3.7 3.8 Profile 2007 8.8 7.9 7 6.1 5.7 4.3 4 4 3.6 184 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350 360 370 380 390 400 410 420 430 440 450 460 470 480 -0.4 -0.85 -1.1 -1.3 -1.5 -1.6 -1.75 -2.05 -2.25 -2.5 -2.85 -3.1 -3.3 -3.35 -3.5 -3.55 -3.6 -3.8 -3.75 -3.8 -3.9 -4 -4.05 -4.1 -4.1 -4.2 -4.25 -4.35 -4.35 -4.4 -4.55 -4.55 -4.6 -4.65 -4.75 -4.8 -4.85 -4.85 -4.95 -5 3.2 1.95 0.6 -0.85 -0.9 -1.15 -1.3 -1.5 -1.75 -2.1 -2.6 -3.1 -3.3 -3.45 -3.65 -3.7 -3.75 -3.8 -3.85 -3.85 -4 -4.1 -4.1 -4.15 -4.2 -4.25 -4.3 -4.3 -4.35 -4.4 -4.45 -4.6 -4.65 -4.7 -4.8 -4.85 -4.85 -4.95 -4.95 -5.1 3.05 1.75 0.4 -0.7 -1.1 -1.25 -1.35 -1.45 -1.55 -1.95 -2.35 -2.7 -3 -3.25 -3.45 -3.55 -3.65 -3.65 -3.7 -3.85 -3.8 -3.8 -3.8 -4 -4.15 -4.15 -4.15 -4.15 -4.25 -4.4 -4.3 -4.4 -4.6 -4.6 -4.6 -4.7 -4.85 -4.95 -4.8 -4.75 2.8 1.7 0.35 -0.65 -0.85 -1 -1.35 -1.5 -1.8 -2.1 -2.5 -2.75 -3.05 -3.2 -3.35 -3.5 -3.6 -3.7 -3.7 -3.9 -3.95 -3.95 -4.05 -4.15 -4.15 -4.2 -4.2 -4.25 -4.4 -4.4 -4.4 -4.45 -4.5 -4.55 -4.6 -4.7 -4.8 -4.9 -5 -5.05 185 490 500 510 520 530 540 550 560 570 580 590 600 610 620 630 640 650 660 670 680 690 700 710 720 730 740 750 760 770 780 790 800 810 820 830 840 850 860 870 880 -5.05 -5.25 -5.25 -5.3 -5.4 -5.45 -5.55 -5.65 -5.65 -5.7 -5.85 -5.85 -6 -6.1 -6.2 -6.25 -6.4 -6.45 -6.5 -6.6 -6.75 -6.85 -6.85 -6.95 -7.1 -7.15 -7.3 -7.35 -7.4 -7.45 -7.55 -7.6 -7.7 -7.8 -7.9 -8 -8.05 -8.05 -8.15 -8.25 -5.15 -5.25 -5.25 -5.4 -5.45 -5.5 -5.6 -5.7 -5.9 -5.85 -5.9 -6.1 -6.2 -6.25 -6.3 -6.25 -6.4 -6.45 -6.5 -6.65 -6.75 -6.8 -6.9 -7.2 -7.2 -7.3 -7.45 -7.4 -7.5 -7.6 -7.7 -7.75 -7.85 -7.9 -7.95 -8 -8.1 -8.2 -8.2 -8.25 -5 -5.2 -5.2 -5.35 -5.3 -5.3 -5.4 -5.6 -5.7 -5.7 -5.8 -5.95 -6.1 -6.15 -6.2 -6.2 -6.35 -6.35 -6.35 -6.45 -6.6 -6.65 -6.75 -7.05 -7.05 -7.15 -7.25 -7.25 -7.35 -7.4 -7.5 -7.55 -7.7 -7.75 -7.8 -7.9 -7.95 -8 -8.05 -8.15 -5.05 -5.1 -5.2 -5.2 -5.3 -5.4 -5.55 -5.6 -5.7 -5.8 -5.85 -5.9 -6 -6.1 -6.2 -6.25 -6.4 -6.4 -6.5 -6.55 -6.65 -6.7 -6.8 -6.85 -6.9 -7 -7.15 -7.2 -7.35 -7.4 -7.5 -7.55 -7.65 -7.75 -7.85 -7.9 -8 -8.05 -8.1 -8.15 186 890 900 910 920 930 940 950 960 970 980 990 1000 1010 1020 1030 1040 1050 1060 1070 1080 1090 1100 1110 1120 1130 1140 1150 1160 1170 1180 1190 1200 1210 1220 1230 1240 1250 -8.25 -8.4 -8.5 -8.45 -8.6 -8.6 -8.75 -8.75 -8.85 -8.85 -8.95 -9.05 -9 -9.1 -9.2 -9.2 -9.25 -9.3 -9.35 -9.4 -9.4 -9.5 -9.5 -9.55 -9.65 -9.6 -9.65 -9.75 -9.75 -8.35 -8.4 -8.6 -8.65 -8.65 -8.75 -8.8 -8.85 -8.95 -9 -9.05 -9.15 -9.2 -9.3 -9.35 -9.4 -9.45 -9.5 -9.5 -9.6 -9.6 -9.7 -9.7 -9.75 -9.8 -9.9 -9.9 -10 -10.05 -10.05 -10.15 -10.15 -10.15 -10.2 -10.25 -10.35 -10.4 -8.25 -8.3 -8.4 -8.55 -8.7 -8.75 -8.7 -8.65 -8.7 -8.8 -8.95 -9.15 -9.2 -9.2 -9.25 -9.3 -9.3 -9.4 -9.45 -9.45 -9.5 -9.55 -9.55 -9.6 -9.65 -9.75 -9.8 -9.9 -9.85 -9.95 -10 -10.05 -10 -10.1 -10.05 -10 -10.05 -8.2 -8.25 -8.35 -8.45 -8.6 -8.7 -8.8 -8.8 -8.8 -8.9 -8.95 -9 -9.05 -9.1 -9.2 -9.2 -9.3 -9.3 -9.35 -9.4 -9.45 -9.55 -9.55 -9.6 -9.6 -9.75 -9.8 -9.9 -9.95 -9.95 -10.05 -10 -9.95 187 CH 1100 Distance 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350 360 (All levels in m LSD) Profile 2003 13.8 12.9 11.7 10.4 7.7 6 4.85 3.25 3.65 0.9 -0.1 -0.75 -1.15 -1.35 -1.4 -1.55 -1.7 -2.05 -2.25 -2.55 -2.85 -3.05 -3.25 -3.35 -3.5 -3.65 -3.75 -3.9 -3.95 -4 -4.05 -4.15 -4.15 -4.3 -4.3 -4.4 -4.4 Profile 2005 13.8 12.9 11.8 10.4 7.7 6.1 4.15 3.85 3.6 3.65 3.55 2.4 1.05 -0.3 -0.8 -1.05 -1.25 -1.5 -1.7 -2.05 -2.45 -2.9 -3.15 -3.3 -3.6 -3.7 -3.8 -3.85 -3.95 -4.05 -4.15 -4.25 -4.25 -4.3 -4.45 -4.45 -4.6 Profile 2006 13.8 12.9 11.8 10.4 7.7 6.1 3.8 4 3.7 3.75 3.45 2 0.4 -0.95 -1.5 -1.4 -1.35 -1.55 -1.75 -1.95 -2.4 -2.8 -3.05 -3.35 -3.5 -3.6 -3.85 -3.9 -3.9 -3.85 -3.9 -4.05 -4.15 -4.15 -4.2 -4.25 -4.3 Profile 2007 13.8 12.9 11.8 10.4 7.7 6.1 4.8 4.2 4.2 3.95 3.3 2.5 1.15 -0.4 -0.75 -1 -1.3 -1.6 -1.75 -2.1 -2.45 -2.75 -3.1 -3.3 -3.5 -3.6 -3.65 -3.75 -3.85 -3.95 -4 -4.1 -4.1 -4.15 -4.2 -4.3 -4.4 188 370 380 390 400 410 420 430 440 450 460 470 480 490 500 510 520 530 540 550 560 570 580 590 600 610 620 630 640 650 660 670 680 690 700 710 720 730 740 750 760 -4.45 -4.6 -4.65 -4.75 -4.75 -4.8 -4.95 -5 -5.05 -5.15 -5.15 -5.25 -5.3 -5.4 -5.5 -5.5 -5.6 -5.6 -5.75 -5.8 -5.95 -6.1 -6.1 -6.15 -6.2 -6.25 -6.45 -6.45 -6.65 -6.7 -6.8 -6.85 -6.95 -7.1 -7.05 -7.2 -7.3 -7.4 -7.45 -7.45 -4.7 -4.7 -4.8 -4.85 -4.9 -4.9 -4.95 -5 -5.1 -5.1 -5.15 -5.25 -5.35 -5.35 -5.45 -5.6 -5.7 -5.75 -5.9 -5.95 -6.05 -6.15 -6.15 -6.3 -6.5 -6.45 -6.45 -6.55 -6.7 -6.75 -6.8 -6.95 -7 -7.2 -7.25 -7.3 -7.4 -7.4 -7.5 -7.6 -4.45 -4.5 -4.55 -4.6 -4.7 -4.85 -5 -5.05 -5.05 -5.1 -5.15 -5.25 -5.3 -5.35 -5.4 -5.55 -5.6 -5.7 -5.85 -5.95 -6 -6.1 -6.15 -6.1 -6.2 -6.25 -6.3 -6.45 -6.55 -6.65 -6.8 -6.9 -7.05 -7.1 -7.1 -7.2 -7.25 -7.35 -7.5 -7.5 -4.4 -4.5 -4.6 -4.65 -4.75 -4.75 -4.85 -4.95 -5.05 -5.1 -5.15 -5.15 -5.25 -5.35 -5.45 -5.5 -5.65 -5.75 -5.85 -5.9 -5.9 -5.9 -6 -6.1 -6.2 -6.3 -6.4 -6.4 -6.5 -6.55 -6.65 -6.75 -6.9 -7 -7.1 -7.15 -7.2 -7.25 -7.35 -7.4 189 770 780 790 800 810 820 830 840 850 860 870 880 890 900 910 920 930 940 950 960 970 980 990 1000 1010 1020 1030 1040 1050 1060 1070 1080 1090 1100 1110 1120 1130 1140 1150 1160 -7.6 -7.7 -7.8 -7.8 -8 -8.05 -8.1 -8.15 -8.25 -8.4 -8.4 -8.45 -8.55 -8.6 -8.7 -8.8 -8.8 -8.85 -8.95 -9.05 -9 -9.05 -9.1 -9.1 -9.2 -9.25 -9.3 -9.4 -9.4 -9.5 -9.45 -9.55 -9.55 -9.65 -9.7 -9.75 -9.75 -9.85 -9.9 -9.85 -7.75 -7.8 -7.95 -8 -8 -8.1 -8.2 -8.25 -8.35 -8.5 -8.55 -8.6 -8.65 -8.75 -8.7 -8.8 -8.85 -8.9 -8.95 -9.2 -9.15 -9.2 -9.25 -9.3 -9.4 -9.4 -9.5 -9.5 -9.5 -9.55 -9.65 -9.7 -9.8 -9.8 -9.85 -9.95 -9.95 -10.05 -10.1 -10.1 -7.6 -7.7 -7.7 -7.8 -7.85 -8 -8.15 -8.3 -8.35 -8.4 -8.35 -8.45 -8.4 -8.45 -8.65 -8.65 -8.8 -8.9 -9 -9 -9 -9 -9.1 -9.15 -9.2 -9.3 -9.4 -9.5 -9.5 -9.55 -9.55 -9.65 -9.7 -9.75 -9.8 -9.9 -9.9 -9.95 -10 -9.95 -7.5 -7.6 -7.7 -7.75 -7.85 -8 -8.1 -8.15 -8.25 -8.35 -8.35 -8.4 -8.5 -8.6 -8.65 -8.7 -8.7 -8.75 -8.85 -8.95 -9 -9.1 -9.15 -9.2 -9.25 -9.3 -9.35 -9.4 -9.45 -9.45 -9.5 -9.6 -9.65 -9.65 -9.65 -9.7 -9.75 -9.75 -9.8 -9.9 190 1170 1180 1190 1200 1210 1220 1230 1240 1250 -9.9 CH 1200 Distance 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 -10.1 -10.15 -10.25 -10.2 -10.25 -10.3 -10.3 -10.35 -10.45 -9.95 -10 -10.1 -10.1 -10.15 -10.2 -10.2 -10.2 -10.25 -9.95 -9.95 -10 -10 -10.05 (All levels in m LSD) Profile 2003 12.8 10.7 9.9 9.9 7.2 6 6 4.3 3.4 2.15 1.4 0.2 -0.6 -1.15 -1.35 -1.35 -1.8 -1.9 -2.05 -2.25 -2.5 -2.75 -2.95 -3.2 -3.4 Profile 2005 12.8 10.7 9.9 9.9 7.2 6 6 4.2 3.45 3.35 3.25 3.35 2.4 1.45 0.75 0.05 -0.85 -1.1 -1.25 -1.45 -1.85 -2.15 -2.55 -2.9 -3.45 Profile 2006 12.8 10.7 9.9 9.9 7.2 6 6 3.9 3.8 3 2.1 1.6 1.15 0.7 -0.1 -0.9 -1.3 -1.3 -1.35 -1.5 -1.95 -2.25 -2.75 -3.1 -3.35 Profile 2007 12.8 10.7 9.9 9.9 7.2 6 6 3.9 3.6 3.9 3.9 3.5 2.8 1.9 0.45 -0.9 -1.1 -1.15 -1.45 -1.7 -1.95 -2.4 -2.7 -3.05 -3.25 191 250 260 270 280 290 300 310 320 330 340 350 360 370 380 390 400 410 420 430 440 450 460 470 480 490 500 510 520 530 540 550 560 570 580 590 600 610 620 630 640 -3.6 -3.7 -3.9 -4 -4.1 -4.15 -4.25 -4.3 -4.35 -4.6 -4.55 -4.6 -4.75 -4.75 -4.9 -4.95 -5.05 -5.1 -5.2 -5.3 -5.25 -5.5 -5.55 -5.6 -5.6 -5.7 -5.75 -5.75 -5.85 -5.95 -6 -6.05 -6.15 -6.3 -6.35 -6.4 -6.55 -6.55 -6.65 -6.8 -3.75 -3.9 -3.9 -3.95 -4.1 -4.2 -4.3 -4.4 -4.4 -4.45 -4.6 -4.7 -4.7 -4.65 -4.75 -4.9 -5.05 -5.15 -5.35 -5.4 -5.55 -5.65 -5.8 -5.95 -6 -5.9 -5.85 -5.7 -5.45 -5.35 -5.3 -5.35 -5.4 -5.55 -5.8 -6.15 -6.6 -6.8 -6.85 -6.95 -3.5 -3.6 -3.75 -3.85 -4.05 -4.15 -4.2 -4.35 -4.3 -4.25 -4.4 -4.45 -4.5 -4.55 -4.7 -4.9 -5.05 -5.1 -5.1 -5.2 -5.35 -5.5 -5.7 -5.9 -6 -5.95 -5.95 -5.85 -5.7 -5.7 -5.7 -5.8 -6 -6.15 -6.35 -6.55 -6.65 -6.7 -6.75 -6.75 -3.45 -3.6 -3.8 -3.9 -3.95 -4 -4.1 -4.15 -4.25 -4.3 -4.35 -4.5 -4.6 -4.65 -4.7 -4.9 -4.95 -5.05 -5.1 -5.2 -5.25 -5.35 -5.5 -5.65 -5.8 -6 -6.1 -6.25 -6.35 -6.35 -6.45 -6.55 -6.6 -6.6 -6.65 -6.7 -6.75 -6.7 -6.7 -6.75 192 650 660 670 680 690 700 710 720 730 740 750 760 770 780 790 800 810 820 830 840 850 860 870 880 890 900 910 920 930 940 950 960 970 980 990 1000 1010 1020 1030 1040 -6.9 -7 -7.15 -7.2 -7.3 -7.4 -7.45 -7.55 -7.55 -7.65 -7.7 -7.8 -7.9 -8 -8.05 -8.2 -8.2 -8.25 -8.3 -8.4 -8.45 -8.5 -8.65 -8.75 -8.8 -8.85 -8.85 -8.9 -8.95 -9.05 -9.05 -9.15 -9.15 -9.25 -9.35 -9.4 -9.45 -9.45 -9.45 -9.45 -7.05 -7.05 -7.05 -7.15 -7.3 -7.3 -7.35 -7.5 -7.55 -7.7 -7.8 -7.8 -7.95 -8 -8.15 -8.25 -8.25 -8.35 -8.4 -8.5 -8.55 -8.65 -8.7 -8.7 -8.8 -8.9 -8.95 -8.95 -9.1 -9.2 -9.2 -9.25 -9.3 -9.3 -9.4 -9.4 -9.45 -9.55 -9.55 -9.55 -6.85 -6.9 -7 -7.1 -7.15 -7.3 -7.35 -7.35 -7.4 -7.55 -7.65 -7.75 -7.8 -7.9 -7.95 -8 -8.15 -8.25 -8.3 -8.3 -8.45 -8.5 -8.55 -8.6 -8.7 -8.8 -8.9 -8.95 -9 -9.05 -9.1 -9.15 -9.2 -9.25 -9.3 -9.35 -9.4 -9.35 -9.45 -9.55 -6.85 -6.95 -7 -7.1 -7.2 -7.3 -7.3 -7.4 -7.5 -7.55 -7.65 -7.75 -7.85 -7.9 -7.95 -8.05 -8.1 -8.15 -8.25 -8.3 -8.4 -8.45 -8.55 -8.65 -8.65 -8.75 -8.85 -8.95 -8.95 -9 -9.1 -9.2 -9.2 -9.2 -9.3 -9.3 -9.3 -9.4 -9.5 -9.5 193 1050 1060 1070 1080 1090 1100 1110 1120 1130 1140 1150 1160 1170 1180 1190 1200 1210 1220 1230 1240 1250 -9.7 -9.6 -9.7 -9.65 -9.75 -9.9 -9.95 -9.9 -10 -9.95 -10 -10.1 -10.1 CH 1300 Distance 0 10 20 30 40 50 60 70 80 90 100 110 120 -9.65 -9.7 -9.8 -9.8 -9.85 -9.85 -10 -10.05 -10.05 -10.1 -10.1 -10.15 -10.15 -10.25 -10.3 -10.35 -10.3 -10.3 -10.45 -10.4 -10.55 -9.6 -9.6 -9.65 -9.7 -9.7 -9.8 -9.8 -9.85 -9.95 -9.95 -10.05 -10.05 -10.05 -10.05 -10.15 -10.2 -10.2 -10.2 -10.25 -10.35 -10.3 -9.6 -9.6 -9.7 -9.7 -9.7 -9.75 -9.85 -9.95 -9.95 -10 -10.05 -10.1 -10.15 -10.2 -10.25 -10.2 -10.25 (All levels in m LSD) Profile 2003 31.4 27.6 23.5 20.5 18.9 16.9 13.2 8 5.45 5.2 4.25 3.65 4.7 Profile 2005 31.4 27.6 23.5 20.5 18.9 16.8 12.3 7.8 6.3 5.3 3.5 3.9 5.7 Profile 2006 31.4 27.6 23.5 20.5 18.9 16.8 12.3 7.8 6.3 5.3 3.5 3.9 5.7 Profile 2007 31.4 27.6 23.5 20.5 18.9 16.8 12.3 7.8 6.2 6.3 5.3 3.5 3.9 194 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350 360 370 380 390 400 410 420 430 440 450 460 470 480 490 500 510 520 3.95 0.25 -1 -1.15 -1.35 -1.55 -1.9 -2.15 -2.35 -2.4 -2.7 -3 -3.3 -3.55 -3.75 -3.9 -4.2 -4.25 -4.4 -4.45 -4.6 -4.7 -4.8 -4.9 -5.05 -5.05 -5.25 -5.3 -5.35 -5.4 -5.45 -5.5 -5.45 -5.55 -5.65 -5.75 -5.85 -6 -6 -6.1 4.1 1.8 0.35 -0.75 -1.3 -1.4 -1.55 -1.75 -1.95 -2.15 -2.55 -3.1 -3.55 -3.7 -4 -4.15 -4.2 -4.25 -4.4 -4.5 -4.65 -4.75 -4.8 -4.85 -4.9 -4.95 -5 -5.15 -5.15 -5.25 -5.5 -5.65 -5.7 -5.65 -5.7 -5.75 -5.85 -6 -6.1 -6.2 4.2 1.8 0.65 -0.35 -1.2 -1.35 -1.45 -1.65 -1.8 -2.25 -2.65 -3.15 -3.45 -3.7 -3.85 -4.05 -4.1 -4.25 -4.3 -4.4 -4.55 -4.7 -4.85 -4.9 -4.9 -4.9 -5 -5.1 -5.2 -5.45 -5.65 -5.75 -5.85 -5.95 -6 -5.95 -5.9 -5.8 -5.75 -5.7 5.7 3.7 1.15 -0.2 -0.85 -1.1 -1.25 -1.55 -1.75 -2.05 -2.5 -2.9 -3.15 -3.4 -3.65 -3.85 -4.05 -4.2 -4.35 -4.45 -4.55 -4.7 -4.75 -4.9 -5 -5.15 -5.25 -5.4 -5.55 -5.65 -5.85 -6 -6.05 -6.15 -6.25 -6.25 -6.2 -6.1 -6 -5.9 195 530 540 550 560 570 580 590 600 610 620 630 640 650 660 670 680 690 700 710 720 730 740 750 760 770 780 790 800 810 820 830 840 850 860 870 880 890 900 910 920 -6.25 -6.25 -6.3 -6.5 -6.45 -6.65 -6.65 -6.75 -6.8 -6.8 -7 -7.05 -7.15 -7.25 -7.4 -7.4 -7.5 -7.6 -7.65 -7.8 -7.85 -7.9 -7.95 -8 -8.15 -8.25 -8.3 -8.45 -8.45 -8.45 -8.55 -8.65 -8.7 -8.8 -8.85 -8.85 -8.95 -9 -9.1 -9.1 -6.3 -6.4 -6.45 -6.55 -6.5 -6.45 -6.55 -6.7 -6.8 -6.9 -7 -7.2 -7.3 -7.35 -7.4 -7.55 -7.55 -7.65 -7.75 -7.85 -7.9 -8 -8.05 -8.15 -8.25 -8.3 -8.4 -8.45 -8.5 -8.6 -8.7 -8.8 -8.8 -8.95 -8.95 -9.05 -9 -9.1 -9.1 -9.2 -5.75 -5.9 -6.05 -6.2 -6.35 -6.55 -6.65 -6.7 -6.75 -6.95 -7.1 -7.1 -7.1 -7.1 -7.15 -7.3 -7.35 -7.4 -7.6 -7.75 -7.8 -7.8 -7.95 -8.05 -8.1 -8.25 -8.3 -8.35 -8.3 -8.3 -8.4 -8.5 -8.6 -8.65 -8.7 -8.75 -8.9 -8.95 -9.05 -9.15 -5.85 -5.85 -5.9 -5.9 -6 -6.2 -6.4 -6.6 -6.8 -6.95 -7.1 -7.1 -7.15 -7.25 -7.35 -7.4 -7.4 -7.5 -7.55 -7.7 -7.75 -7.9 -8 -8.05 -8.15 -8.2 -8.3 -8.3 -8.4 -8.45 -8.5 -8.5 -8.6 -8.6 -8.7 -8.8 -8.85 -8.95 -9.1 -9.2 196 930 940 950 960 970 980 990 1000 1010 1020 1030 1040 1050 1060 1070 1080 1090 1100 1110 1120 1130 1140 1150 1160 1170 1180 1190 1200 1210 1220 1230 1240 1250 -9.15 -9.2 -9.25 -9.3 -9.4 -9.4 -9.5 -9.55 -9.5 -9.65 -9.6 -9.65 -9.65 -9.75 -9.85 -9.95 -9.95 -10 -10 -10.15 -10.1 -10.15 -10.15 -10.2 -10.25 -10.25 CH 1400 Distance 0 -9.25 -9.3 -9.35 -9.45 -9.45 -9.5 -9.5 -9.55 -9.65 -9.7 -9.8 -9.9 -9.95 -9.95 -9.9 -9.95 -10 -10.05 -10.15 -10.2 -10.2 -10.15 -10.2 -10.25 -10.3 -10.35 -10.35 -10.4 -10.45 -10.5 -10.5 -10.6 -10.6 -9.2 -9.3 -9.25 -9.3 -9.35 -9.3 -9.45 -9.5 -9.45 -9.45 -9.55 -9.7 -9.75 -9.8 -9.75 -9.8 -9.85 -9.9 -9.9 -10 -10 -10.05 -10.15 -10.25 -10.25 -10.2 -10.2 -10.3 -10.3 -10.35 -10.4 -10.45 -10.55 -9.25 -9.2 -9.25 -9.3 -9.4 -9.45 -9.4 -9.5 -9.5 -9.6 -9.65 -9.7 -9.75 -9.75 -9.85 -9.9 -9.9 -9.9 -10 -10.05 -10.05 -10.1 -10.15 -10.2 -10.25 -10.3 -10.35 -10.4 -10.45 -10.45 (All levels in m LSD) Profile 2003 48 Profile 2005 48 Profile 2006 48 Profile 2007 48 197 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240 250 260 270 280 290 300 310 320 330 340 350 360 370 380 390 400 43.1 38.2 33.5 29 28.9 31.6 35 35.4 35.5 33.2 30 27.8 22.8 17 11 5.55 1.45 -0.3 -1.05 -1.4 -2.15 -2.5 -2.6 -2.75 -3.1 -3.3 -3.6 -3.85 -4.15 -4.3 -4.55 -4.7 -4.85 -4.95 -5.05 -5.2 -5.3 -5.3 -5.55 -5.7 43.1 38.2 33.5 29 28.9 31.6 35 35.4 35.5 33.2 30.2 27.8 23.5 17 11 3.5 2.7 2.1 -1.3 -1.5 -1.65 -1.85 -2.2 -2.65 -3.2 -3.6 -3.85 -4.1 -4.2 -4.25 -4.45 -4.7 -4.8 -4.85 -5.05 -5.2 -5.25 -5.25 -5.35 -5.4 43.1 38.2 33.5 29 28.9 31.6 35 35.4 35.5 33.2 30.2 27.8 23.5 17 11 3.5 2.7 2.1 -1.6 -1.9 -1.95 -2.15 -2.5 -3 -3.35 -3.65 -3.85 -4.05 -4.2 -4.2 -4.4 -4.6 -4.8 -4.95 -5 -5.15 -5.25 -5.35 -5.4 -5.45 43.1 38.2 33.5 29 28.9 31.6 35 35.4 35.5 33.2 30.2 27.8 23.5 17 11 3.5 2.7 2.1 -1.7 -0.75 -1.4 -1.8 -2.4 -2.85 -3.2 -3.45 -3.75 -4.05 -4.25 -4.45 -4.55 -4.65 -4.75 -4.9 -5.1 -5.25 -5.45 -5.6 -5.8 -5.9 198 410 420 430 440 450 460 470 480 490 500 510 520 530 540 550 560 570 580 590 600 610 620 630 640 650 660 670 680 690 700 710 720 730 740 750 760 770 780 790 800 -5.8 -5.85 -5.9 -5.95 -6 -6.1 -6.05 -6.2 -6.25 -6.3 -6.4 -6.45 -6.5 -6.55 -6.65 -6.85 -6.9 -6.95 -7.1 -7.15 -7.15 -7.3 -7.3 -7.45 -7.55 -7.6 -7.65 -7.8 -7.8 -7.9 -7.9 -8.05 -8.05 -8.2 -8.3 -8.4 -8.45 -8.45 -8.6 -8.6 -5.35 -5.5 -5.6 -5.7 -5.75 -5.8 -5.95 -6.15 -6.2 -6.35 -6.4 -6.45 -6.5 -6.8 -6.95 -7.05 -7.1 -7.15 -7.35 -7.4 -7.35 -7.4 -7.45 -7.45 -7.55 -7.6 -7.7 -7.8 -7.85 -7.95 -8.1 -8.15 -8.2 -8.25 -8.35 -8.4 -8.5 -8.6 -8.7 -8.7 -5.45 -5.45 -5.55 -5.75 -5.85 -6 -6.05 -6 -6.15 -6.2 -6.3 -6.45 -6.5 -6.55 -6.6 -6.65 -6.65 -6.65 -6.75 -6.9 -7 -7.05 -7.15 -7.3 -7.5 -7.55 -7.6 -7.65 -7.75 -7.95 -8.05 -8.1 -8.15 -8.2 -8.2 -8.3 -8.35 -8.4 -8.55 -8.6 -6 -6.05 -6.1 -6.15 -6.2 -6.15 -6.25 -6.25 -6.35 -6.35 -6.4 -6.6 -6.7 -6.8 -6.8 -6.9 -7 -7 -7.05 -7.05 -7.2 -7.3 -7.4 -7.5 -7.5 -7.55 -7.6 -7.65 -7.75 -7.85 -7.85 -8 -8.1 -8.1 -8.2 -8.3 -8.35 -8.5 -8.55 -8.65 199 810 820 830 840 850 860 870 880 890 900 910 920 930 940 950 960 970 980 990 1000 1010 1020 1030 1040 1050 1060 1070 1080 1090 1100 1110 1120 1130 1140 1150 1160 1170 1180 1190 1200 -8.7 -8.7 -8.8 -8.95 -9 -9.05 -9.1 -9.15 -9.2 -9.25 -9.25 -9.4 -9.4 -9.4 -9.55 -9.55 -9.5 -9.6 -9.65 -9.65 -9.8 -9.75 -9.75 -9.75 -9.9 -9.95 -10.05 -10.05 -10.05 -10.2 -10.1 -10.25 -10.3 -10.3 -10.4 -10.4 -10.4 -8.75 -8.85 -8.85 -8.95 -9.05 -9.05 -9.1 -9.2 -9.2 -9.25 -9.35 -9.35 -9.45 -9.5 -9.55 -9.65 -9.7 -9.65 -9.75 -9.8 -9.85 -9.9 -9.9 -9.9 -9.95 -10.05 -10.05 -10.15 -10.2 -10.25 -10.3 -10.3 -10.35 -10.35 -10.35 -10.45 -10.4 -10.45 -10.5 -10.5 -8.65 -8.7 -8.8 -8.8 -8.85 -8.9 -9 -9.05 -9.1 -9.15 -9.15 -9.2 -9.2 -9.35 -9.45 -9.55 -9.55 -9.5 -9.45 -9.55 -9.65 -9.7 -9.8 -9.75 -9.9 -9.9 -9.95 -10 -10 -10 -10.1 -10.15 -10.25 -10.35 -10.35 -10.35 -10.35 -10.3 -10.35 -10.4 -8.75 -8.75 -8.85 -8.85 -8.95 -9.05 -9.1 -9.15 -9.2 -9.3 -9.3 -9.35 -9.45 -9.45 -9.45 -9.5 -9.55 -9.6 -9.65 -9.75 -9.75 -9.8 -9.85 -9.8 -9.85 -9.9 -10 -10.05 -10.1 -10.15 -10.2 -10.25 -10.25 -10.3 -10.35 -10.3 -10.3 -10.3 -10.4 -10.4 200 1210 1220 1230 1240 1250 -10.55 -10.65 -10.65 -10.6 -10.65 -10.45 -10.45 -10.5 -10.5 -10.5 -10.4 -10.35 -10.45