MCC Project Charter Wait List • • • • • • • • • • • Executive Summary MCC Stakeholders Business Purpose Project Overview Project Requirements Project Management Project Costs/Budget Project Personnel/Resources Project Risks/Issues Project Organization Project Charter Approval 10/1/2010 MCC Project Charter 1 Wait List Executive Summary • Implement the Datatel course wait list process – – – – – • An equitable approach for students Standardized across the college divisions Automated for students, faculty, and staff Integrated with rest of Datatel processes Capture data for section demand planning Outside of project scope – Section demand planning & management process – Program wait list process 10/1/2010 MCC Project Charter 2 Wait List MCC Stakeholders • Project Sponsor(s) – • Cheryl Bassett, CTO Chair/Program/Project Manager – • Mark Leach, Director ITS Enterprise Services Customer/User Owners – Primary • • • – Secondary • • • 10/1/2010 MCC Students – helps them plan their schedule Student Services – helps them help students with scheduling Academic Affairs – helps them plan course section offerings Finance/Accounting – should improve section fill rates, revenue Financial Aid – could provide more flexibility for drop process ITS – may reduce system load MCC Project Charter 3 Wait List Business Purpose • Business Goal, Strategy, Objective – Improve enrollment management • • • For students – flexibility, fairness, and ease of use For college – process automation, section utilization Business Case, Need, Problem, Opportunity – Lack of standard/automated process • • • • No process/system exists, lists only maintained for demand Students have to constantly monitor for current openings Students may be subject to favoritism Faculty may be subject to pressure – • 10/1/2010 Not current issue due to elimination of overloads in Faculty CBA Section utilization is not optimized MCC Project Charter 4 Wait List Project Overview • Project Description, Objective – • Implement Datatel Wait List functionality Preliminary Scope, Assumptions, Constraints – Does not include program/admission wait lists • – Does not include section management • – Provides better info but may not meet other needs Need to integrate with Auto Drop processing • • – Financial – payment, financial aid, other TBD Academic – pre and co-requisites, other TBD Current culture is paper-based (not email) • – • For example, pre-nursing to nursing Student contact information is often not current Beyond set-up, limited resources needed to execute process Project Success Criteria, Metrics – – – 10/1/2010 Deployment / rolled-out to at least one course/division, … Yield / wait list entries, potential adds, actual adds, left on list, … Sections / percent seats filled, division section cancels & late adds, … MCC Project Charter 5 Wait List Project Requirements • Project Deliverables – Process documentation • • • – System configuration and operation procedures • • • – • Set-up, rule development, and related Communication management customization Additional reports/dashboards, current and historical Deployment strategy and roll-out plan • • – Include exception/error process and backup plans Leverage existing and/or develop new Job Aids System/process integration where needed Start with one course/program per division, heavily filled, manual process already Expand to rest of program/division, others, review in lab, then full roll-out Communication campaign and training People, Process, Technology – – 10/1/2010 Keep it simple & flexible Identify exceptions & get buy-in MCC Project Charter 6 Wait List Project Management • Project Management Approach – – • PDCA Cycle (7-Step CQI Process) PMBOK and Unified Process Summary Milestone Schedule – – – – – – – – • August 2010 – kick-off project September 2010 – complete project charter October 2010 – analyze process/requirements November 2010 – design/configure system February 2011 – complete testing & preparation April 2011 – implement for selected courses July 2011 – assess results, add more courses November 2011 – implement for all courses Communication and Reporting – – • • Via Project Sponsor to EC Via Troy Boquette to CPSC Change Management Acceptance 10/1/2010 MCC Project Charter 7 Wait List Project Costs/Budget • Purpose, Amount, Source – Software, no cost, included in Datatel ST – Consulting (may need), $500, Datatel Services – Training & Communication, existing budgets, all • • Wait List flyer for student orientation packets Update existing collateral, systems, and people – – – 10/1/2010 Student handbook, faculty resource guide, tabloid, DLES Queuing system (Q-Nomy), web site, e-mail, newsletter Leadership, faculty, division, department meetings MCC Project Charter 8 Wait List Project Personnel/Resources • Project Team – • Support – – • • • Datatel Using Registration document, section 5 Datatel Registration Learning Guide, chapter 8 Facilities Equipment Software Tools – – – – • See attached Datatel Student/Registration modules Datatel Communication Management Cognos Business Intelligence Special database clone for project (COLWAIT) including WebAdvisor Other 10/1/2010 MCC Project Charter 9 Wait List Project Risks/Issues • Scope – • When done? When we set default for course building to Yes, have wait lists Schedule – • EC and CPSC would like ASAP, not enough lead-time for Winter registration Budget – • Limited costs, assumed in budgets, but unforeseen expenses not in budget Other/Stakeholder – Students • – Waiting on special instructor, time conflict, multiple sections, many courses, financial aid, e-mail addresses and utilization Student Services • – Ability to deal with exceptions, student notification/communication & eligibility Academic • – ITS • 10/1/2010 Ability to leverage information for section planning & management Batch process scheduling (e.g., WLAV on top of FATR and Auto Drop, etc) MCC Project Charter 10 Wait List Project Organization • Roles & Responsibilities – Regular team meetings to review progress/plans – Sub-teams will work on system & report results – Unrepresented departments/divisions • Alana offered to help with Faculty, Troy with Divisions – Leverage existing meetings to communicate • Team Guidelines/Process – Bi-weekly working sessions – Thursday afternoons for 1.5 hours 10/1/2010 MCC Project Charter 11 Wait List Project Charter Approval • Executive Cabinet – Basic approval for direction on 9/28/2010 – Standard AQIP forms need to be completed • Project Sponsor – Approved 9/29/2010 • Chair/Program/Project Manager – Approved 9/29/2010 10/1/2010 MCC Project Charter 12