CAPITAL PROJECTS LIST MARCH 2016 DESCRIPTION OF SCOPE WKU Baseball Field Replacement & Improve Site Drainage PROJECT MANAGER Casana Authorized Capital Budget SCM PHASE or % COMPLETE 0% NOTES Determination of responsibility in process: Letter of Intent to be sent. Time frame is 6/6/16 through 8/26/16 *Schedule: Ogden College Hall Construction & Renovation: Demo TCNW Completed 2/16/15 *Demolition of Thompson Complex North Wing *Construction of a new science building to take the place of TCNW (81,000 SF) to begin December 2015 Ogden College Hall Completion: 12/1/17 Chaney $ 48,000,000 1% TCCW Renovation Final Completion: 8/1/18 *Renovation of Thompson Complex Center Wing *Hardin Planetarium: 5/15/16-7/31/16 *Hardin Planetarium upgrades scheduled for Summer 2016 *Contractors have mobilized and broken ground Expand Chapel Columbarium Chaney $ 90,000 60% *Expand Chapel Columbarium to include 58 niches *Currently waiting on Stone CRD Microbrewery Chaney $ 410,728 90% *Space will be utilized by the Chemistry Department for instruction in fermentation classes *Planning to be brewing by April 1 The Stadium Park Plaza: Starbucks and WKU Gallery *Currently in design development Chaney $ 800,000 Phase B *Fast tracked project: Goal to be open by May 31 High Voltage Phase 9 *Change Zacharias & Meredith Halls to new 12,470 Volt System Johnson $ 200,000 Design Phase C *HRL is replacing transformers after commencement *WKU Section I: Complete Community Bikeway: The purpose of the project is to develop a network of bicycle and pedestrian facilities that connects area schools, parks and shopping areas to low- and mediumdensity residential neighborhoods and dormitories. *Section II: Design Complete Johnson $ 1,111,500 85% *Right-of-way, two parcels, is in the process of acquisition by KYDOT District 3. *Grant extended to March 21, 2017 Replace Chiller/Tower at CKCC Johnson $ 180,000 Steam Line Repairs 2016 Johnson $ 250,000 PHASE B *Design Phase B *Scope to be determined. Flyover report complete. Confucius Building: *Construct a 7,000 square foot facility on Normal Drive adjacent to the new Honors College and International Center. It will support the Confucius Institute with additional gallery, classroom, office and multiuse space. *Redesigned to a 1 story building Ogden $ 2,300,000 20% *Slab is poured and construction is progressing *Design on hold Chinese Friendship Garden Ogden/ Twardowski $ 247,960 Phase B *Most of the garden will be on HCIC site (between buildings) Gatton Academy/Florence Schneider Expansion: *The expansion of Florence Schneider Hall will expand the current Gatton Academy bed count from 120 to 200. *A new multipurpose meeting/conference room and additional administrative offices for The Gifted Studies program and Gatton Academy are planned. *Construction is Progressing Ogden $ 9,500,000 55% *A few weeks behind schedule *This project will add approximately 17,000 square feet and renovate 9,000 square feet of the existing building. Construct Honors College/International Center Chili's/Parking Office/Alumni Court Yard Ogden $ 22,000,000 98% Exterior site lighting being installed *Substantial completion is expected by Mid-April Ogden NA 60% Expected to serve food Mid-May Parking Structure #3 Pace $ 500,000 Phase B *Design was on hold from 01/27/2016 to 02/25/2016. Jones Jaggers HVAC Upgrades Pace $ 200,000 Phase C Design Phase C Helm Library HVAC Upgrades Pace $ 500,000 0% Equipment ordered Pace $ 370,000 0% *Construction to begin Summer 2016 *6 level parking structure in the rear of the Creason Lot Helm Library Exterior Restoration: *Repair & tuck point limestone veneer *Repair terra cotta panels *Clean the limestone and terra cotta panels *Sealant at capstone & windows Garrett Conference Center: *The second floor (17,000 square feet), will be renovated for Academic AffairsDivision of Extended Learning and Outreach (DELO) This will allow DELO to improve support to faculty members and students while providing the infrastructure and technology to advance distance education at WKU. *Phase 1 (Academic Affairs-DELO) is complete Peterson $ 3,200,000 Phase C *Construction documents are complete *Academic Affairs asked to put project on hold * An Elevator will also be added. *This project represents the first Phase of a complete facility renovation that is expected to cost $12-14M, based on studies & internal estimates Taylor Center Cheese Facility: *Mechanical project to facilitate operation of the cheese production facility at the Taylor Center Peterson $ 104,000 100% *Construction is complete. Equipment startup last week and will be able to process cheese within the next few weeks. Renovation projects in process: Current Renovation projects across campus Casana $ 1,395,098 Various *Currently 27 are funded and active @ $727,558.42 *61 are estimated @ $645,462.85 and awaiting customer approval to proceed *21 are estimated at $151,096.00 but are on hold *25 are currently being estimated $ 41,858,558