Leveraging Steel Supply Chain Data for Structural Optimization PI: Staff:

advertisement
Vertically Integrated Steel Design
Leveraging Steel Supply Chain
Data for Structural Optimization
PI: Martin Fischer
Staff: Forest Flager
Glenn Katz
Marc Ramsey
Students: Henry Hamamji
Pratyush Havelia
1
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
Project Overview
Problem Addressed:
Conceptual
Design
CIFE TAC 2015
Design
Development
Detailed
Design / CD
/ CA
Copyright  2015
2
Vertically Integrated Steel Design
Project Overview
Proposed Solution:
Conceptual
Design
CIFE TAC 2015
Design
Development
Detailed
Design / CD
/ CA
Copyright  2015
3
Vertically Integrated Steel Design
MOTIVATING PROBLEM
Conventional Design Process
4
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
Architectural Rendering
DESIGNER
system / layout
Typical Framing Plan
sizing
FABRICATOR /
ERECTOR
detailing
detailing + estimate
MILL
material cost + availability
SCHEMATIC
DEVELOPMENT
DETAILED
CONST. ADMIN.
DESIGN PHASE
5
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
KEY
W14X233
W14X176
W14X132
W24X117
W18X86
Typical Framing Plan
DESIGNER
system / layout
Moment Frame Elevation
sizing
FABRICATOR /
ERECTOR
detailing
detailing + estimate
MILL
material cost + availability
SCHEMATIC
DEVELOPMENT
DETAILED
CONST. ADMIN.
DESIGN PHASE
6
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
Continuity
Plate
Doubler Plate
Exterior Beam – Column Connection
DESIGNER
system / layout
Typical Framing Plan
sizing
FABRICATOR /
ERECTOR
Interior Beam – Column Connection
detailing
detailing + estimate
MILL
material cost + availability
SCHEMATIC
DEVELOPMENT
DETAILED
CONST. ADMIN.
DESIGN PHASE
7
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
ArcelorMittal (W14X233)
Distance to site: 5725 miles
Gerdau (other sections)
Distance to site: 42 miles
Project Site
DESIGNER
system / layout
sizing
FABRICATOR /
ERECTOR
detailing
detailing + estimate
MILL
material cost + availability
SCHEMATIC
DEVELOPMENT
DETAILED
CONST. ADMIN.
DESIGN PHASE
8
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
Feedback Latency:
8-24 wks
DESIGNER
system / layout
sizing
FABRICATOR /
ERECTOR
detailing
detailing + estimate
MILL
material cost + availability
SCHEMATIC
DEVELOPMENT
DETAILED
CONST. ADMIN.
DESIGN PHASE
9
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
KEY
W14X233
W14X176
W14X132
W24X117
W18X86
Steel Weight
(met tns)
Total Cost
(M USD)
Schedule (wks)
Embodied
Carbon (t CO2e)
ORIGINAL DESIGN
W/ FABRICATOR INPUT
1412
1488 (+5%)
5.35
4.82 (-11%)
24
20 (-20%)
1298
1295 (-1%)
10
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
Problem Summary
• Engineers do not have access to accurate cost,
schedule and environmental impact data when
making key design decisions:
– Late in the design process
– Long latency
11
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
PROPOSED SOLUTION
Vertically Integrated Steel Design
12
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
System Architecture
BIM
DESIGNER
system / layout
Website
FABRICATOR /
ERECTOR
MILL
unit cost and schedule
sizing
analysis
API Service
detailing + estimate
optimization
material cost + avail.
13
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
Research Tasks
(1) Identify information requirements:
- member geometry, sizes
- connection fixity
BIM
DESIGNER
system / layout
Website
FABRICATOR /
ERECTOR
MILL
unit cost and schedule
sizing
analysis
API Service
detailing + estimate
optimization
material cost + avail.
14
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
Point(s) of Departure:
• SteelXML
Research Tasks:
(1) Identify information requirements
- unit cost
- unit schedule
BIM
DESIGNER
system / layout
Website
FABRICATOR /
ERECTOR
MILL
unit cost and schedule
sizing
analysis
API Service
detailing + estimate
optimization
material cost + avail.
15
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
Research Tasks:
(2) Develop method to automate
detailing and cost, schedule and
carbon estimate
BIM
DESIGNER
system / layout
Website
FABRICATOR /
ERECTOR
MILL
unit cost and schedule
sizing
analysis
API Service
detailing + estimate
optimization
material cost + avail.
16
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
Point(s) of Departure:
• 4D modeling
• Systems coordination / clash
detection
Research Tasks:
(3) Develop model-based
visualization methods
BIM
DESIGNER
system / layout
Website
FABRICATOR /
ERECTOR
MILL
unit cost and schedule
sizing
analysis
API Service
detailing + estimate
optimization
material cost + avail.
17
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
Cost (USD)
Cost vs. Carbon Trade-off
Point(s) of Departure:
• Minimal material optimization
Research Tasks:
(4) Develop multi-objective
optimization methods
Schedule (wks)
BIM
DESIGNER
system / layout
Website
FABRICATOR /
ERECTOR
MILL
unit cost and schedule
sizing
analysis
API Service
detailing + estimate
optimization
material cost + avail.
18
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
Research Validation
Model-based visualization methods
• Design charrettes with students and
professional engineers
Optimization methods
• Parallel and / or retrospective industry case
studies
METRICS
- solution quality
(e.g. cost, schedule, CO2e)
- design cycle duration
- total design cycles
19
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
Schedule
Jun
2015
(1) Identify information requirements
Aug
2015
(2) Prototype of automation methods
Nov
2015
(3) Prototype of model-based viz methods
Jan
2016
(4) Prototype of optimization methods
Mar
2016
(5) Charrette and case study validation complete
20
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
Research Team
Forest Flager
Marc
Ramsey
Martin
Fischer
Glenn Katz
Henry
Hamamji
Patrick
Tierney
Pratyush
Havelia
21
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
Value Proposition
Owners: higher quality, more reliable project delivery
Architects and Engineers: better performance data;
less rework
General Contractors: faster, more accurate sub
estimates
Fabricators + Erectors: demonstrate upstream
value; lower pursuit costs
Steel Industry: Differentiate from other materials
22
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
Industry Partners
Software
• Web front end development
• Secure API backend development
• Product integration
Structural Engineering
• Prior steel models and pricing data set
• Beta software user
Steel Fabrication
• Cost modeling data and algorithms
• Fabrication cost input
Steel Erection
• Steel erection cost input
• Beta software user
23
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
Why Now?
• Widespread BIM adoption
– BIM platforms in offices for visualization
– BIM documentation and exchange contractually
obligated
• Broadband saturation and decreasing cloud
infrastructure prices
• Emerging online markets for building
products (e.g., Amazon Supply, Alibaba)
24
CIFE TAC 2015
Copyright  2015
Vertically Integrated Steel Design
Broader Impact
REINFORCED CONCRETE
MECHANICAL ETC.
SYSTEMS PLUMBING SYSTEMS
CURTAIN
WALLS
If we can integrate the supply chain for
STRUCTURAL STEEL, why not…
25
CIFE TAC 2015
Copyright  2015
Download