Save Energy Now Industrial Assessment Report For OSU Memorial Union 26th and Jefferson Corvallis, OR 97331 INDUSTRIAL ASSESSMENT CENTER OREGON STATE UNIVERSITY INDUSTRIAL ASSESSMENT CENTER Sponsored by U.S. Department of Energy Managed by Center for Advanced Energy Systems Rutgers University Assessment Report No. 2001 December 17, 2008 Joseph F. Junker, Assistant IAC Director ________________________________ Peter Hanslits, Lead Analyst ________________________________ Assessment Participants Bryan Kilgore Elsie Deland Yuming Qui Justin Olson Dr. George Wheeler IAC Director Batcheller Hall 341 Corvallis, OR 97331-2405 (541) 737-2515 Motor Analyst Lighting Analyst and Safety Officer Chiller Analyst Energy Analyst Joseph F. Junker Assistant Director Batcheller Hall 344 Corvallis, OR 97331-2405 (541) 737-5034 PREFACE The work described in this report is a service of the Oregon State University Industrial Assessment Center (IAC). The project is funded by the U.S. Department of Energy’s Office of Energy Efficiency and Renewable Energy (EERE) Industrial Technologies Program and managed by Rutgers University Center for Advanced Energy Systems. The primary objective of the IAC is to identify and evaluate opportunities for energy conservation, waste minimization, and productivity improvements through visits to industrial sites. Data is gathered during a one-day site visit and assessment recommendations (ARs) are identified. Some ARs may require additional engineering design and capital investment. When engineering services are not available in-house, we recommend that a consulting engineering firm be engaged to provide design assistance as needed. In addition, since the site visits by IAC personnel are brief, they are necessarily limited in scope and a consulting engineering firm could be more thorough. We believe this report to be a reasonably accurate representation of energy use, waste generation, and opportunities in your building. However, because of the limited scope of our visit, the U.S. Department of Energy, Rutgers University, and the Oregon State University Industrial Assessment Center cannot guarantee the accuracy, completeness, or usefulness of the information contained in this report, nor assume any liability for damages resulting from the use of any information, equipment, method or process disclosed in this report. Pollution prevention recommendations are not intended to deal with the issue of compliance with applicable environmental regulations. Questions regarding compliance should be addressed to either a reputable consulting engineering firm experienced with environmental regulations or to the appropriate regulatory agency. Clients are encouraged to develop positive working relationships with regulators so that compliance issues can be addressed and resolved. The assumptions and equations used to arrive at energy, waste, and cost savings for the recommended ARs are given in the report. We believe the assumptions to be conservative. If you do not agree with our assumptions you may follow the calculation methodologies presented using revised assumptions to develop your own estimates of energy, waste, productivity, and cost savings. Please feel welcome to contact the IAC if you would like to discuss the content of this report or if you have another question about energy use or pollution prevention. The IAC staff that visited your building and prepared this report is listed on the preceding page. TABLE OF CONTENTS 1. Introduction....................................................................................................................... 1 2. Executive Summary .......................................................................................................... 2 3. Assessment Recommendations ......................................................................................... 5 4. AR No. 1. Pipe Insulation ........................................................................................ 5 Justin Olson AR No. 2. Chiller ..................................................................................................... 6 Yuming Qui AR No. 3. Winter HVAC ........................................................................................ 7 Peter Hanslits AR No. 4. Oven Exhaust Fan .................................................................................. 8 Bryan Kilgore AR No. 5. Skylights ................................................................................................. 9 Elsie Deland AR No. 6. Halogen Lights ..................................................................................... 10 Elsie Deland Calculation Methodology ............................................................................................... 11 AR No. 1. AR No. 2. AR No. 3. AR No. 4. AR No. 5. AR No. 6. Pipe Insulation ...................................................................................... 11 Chiller ................................................................................................... 14 Winter HVAC ...................................................................................... 21 Oven Exhaust Fan ................................................................................ 27 Skylights ............................................................................................... 30 Halogen Lights ..................................................................................... 35 APPENDIX A. Utilities ........................................................................................................................... 41 A.1. Energy Definitions .................................................................................................. 41 A.2. Energy Conversions ................................................................................................ 46 A.3. Energy Accounting ................................................................................................. 47 A.4. Energy Use .............................................................................................................. 55 B. Motors ............................................................................................................................. 59 B.1. Boiler Motor Definitions ......................................................................................... 59 B.2. Motor Inventory ...................................................................................................... 63 B.3. Motor Applications ................................................................................................. 64 B.4. Motor Use Summaries ............................................................................................ 65 B.5. Motor Economics .................................................................................................... 65 B.6. Motor Performance ................................................................................................. 66 B.7. Motor Power Factor ................................................................................................ 67 C. Lighting........................................................................................................................... 68 C.1. Lighting Worksheet Definitions.............................................................................. 68 C.2. Lighting Inventory .................................................................................................. 74 D. Refrigeration ................................................................................................................... 76 D.1. Refrigeration Worksheet Definitions ...................................................................... 76 1. INTRODUCTION This report describes how energy is used in your building, and includes our recommendations on cost effective steps you can take to reduce your energy and waste costs. The contents of this report are based on our recent visit to your building. The report is divided into 4 major sections and 4 appendices: 1. Introduction. The purpose, contents and organization of the report are described. 2. Executive Summary. Your energy use and waste generation costs, energy and waste savings, and our recommendations are summarized here with details in the following sections. 3. Assessment Recommendations. This section contains our Assessment Recommendations (AR), briefly highlights the current and proposed systems and summarizes the cost savings available upon implementation. Some of our recommendations will require a significant investment to implement, while others will cost little or nothing. We have grouped our recommendations by category and then ranked them by payback period. 4. Calculation Methodologies. This section includes detailed calculations for the Assessment Recommendations (AR). It includes any data that was collected during the audit, assumptions we use to estimate savings, our estimate of implementation cost, and the simple payback. We have grouped the calculations in the same order as the AR’s in Section 3. Appendix A: Utilities. Your utility bills and energy use by process are summarized and plotted in detail. Due to the changes in rate schedules and adjustments our calculations are an approximation and may not be exactly consistent with your bills. When available, we also include water and solid waste bills. Appendix B: Motors. Motors are typically a large energy user. This section contains your motor information including: nameplate information, area of the plant the motor is located in, and monthly energy use in each section of the plant. Appendix C: Lighting. The number and type of lighting fixtures are recorded for each area. This appendix also includes the Lighting Worksheet Definitions, which describe the symbols and terminology used in our lighting calculations. The lighting power and annual energy use for each plant area are summarized in the Lighting Inventory worksheet. Appendix D: Refrigeration. This appendix includes the Refrigeration Worksheet Definitions, which describes the accompanying Refrigeration Energy Savings worksheets. The worksheet uses bin weather data to model the refrigeration compressor’s operating conditions. 1 2. EXECUTIVE SUMMARY This section includes a summary of energy use and waste generation in your building, our recommendations, and total energy, waste, and cost savings of all recommendations if implemented. Recommendation Summary. The following is a brief explanation of each of the recommendations made in this report. If all 6 recommendations are implemented, the total cost savings will be $29,430 and will pay for costs in 0.3 years. AR No. 1: Pipe Insulation Insulate exposed hot steam and chilled water lines. This will reduce energy lost through these pipe surfaces by 92%. AR No. 2: Chiller Reduce the minimum R-22 discharge (head) pressure on both chiller units. This will reduce chiller operation costs by 25% through a reduction in compressor energy use. AR No. 3: Winter HVAC Turn off five major air handling units during winter night time hours. This will reduce total building steam use by 31% and reduce fan energy use by 33%. AR No. 4: Oven Exhaust Fan Turn off the Pangea oven exhaust fan at night and during the summer. This will reduce electrical costs for this fan by 43% and will reduce conditioned air exhaust when cooling or heating is needed. AR No. 5: Skylights Install photo sensor/timer units on T8 fixtures in skylights to reduce operating hours. Replace yellow glass with clear glass to allow more light into hallways. This will reduce lighting costs by 46% in this area. AR No. 6: Halogen Lights Replace Halogen fixtures in the ballroom with Compact Fluorescent fixtures. This will reduce energy usage in this area by 58%. 2 Our recommendations are summarized in the following table. Assessment Recommendation Summary Energy Cost Implementation AR# Description 1 Pipe Insulation 2 Chiller 3 Winter HVAC 4 Oven Exhaust Fan 5 Skylights* 6 Halogen Lights* Totals (MMBtu) Savings 44.0 $631 415.3 $5,700 1,301.3 $24,414 58.0 $789 20.6 $415 39.7 $483 1,878.9 $32,432 Cost $298 $6,000 $0 $100 $1,040 $2,533 $9,963 Payback (years) 0.5 1.5 Immediate 0.1 2.5 5.2 0.3 *Includes Incentives Total savings are the sum of the savings for each recommendation. Some of the recommendations may interact. Therefore, actual savings may be less than the total indicated above. In our calculations we indicate where we have assumed that other recommendations will be implemented in order to provide a realistic estimate of actual savings. Total savings, including interactions among recommendations, can be better estimated after you select a package of recommendations. Savings Summary. Total cost savings are summarized by energy cost savings. We then normalize savings as a percentage of annual building energy costs. For example, Energy Cost% is energy cost savings divided by the total energy cost from the Utility Summary. Savings Summary Source Qty. Units Cost Savings Energy Cost % $32,432 17.7% Energy 1,878.9 MMBtu Existing Energy Use Summary. We used your utility bills to determine annual energy use for all fuels. From these bills we summarized annual energy consumption at your plant in the following table. Energy costs and calculated savings are based on the incremental cost of each energy source. The incremental rate is the energy charge first affected by an energy use reduction and is taken from your utility rate schedules. For example, electrical use and savings include energy (kWh), demand (kW), reactive power charges (KVARh or power factor), and other fees such as basic charges, transformer rental, and taxes. However, if a recommendation does not affect your electrical demand, such as turning off equipment at night, then we use the cost of electrical energy alone. The fuel costs we used can be found in the Energy Accounting Summary in Appendix A. 3 Existing Energy Use Summary Source Electric Energy Natural Gas Steam Totals Qty. 1,972,560 10,890 4,067,500 Units kWh Therms lbs 4 MMBtu Energy % Cost Cost % 6,732 57.5% $91,527 50.0% 1,089 9.3% $12,244 6.7% 3,880 33.2% $79,316 43.3% 11,702 100.0% $183,087 100.0% 3. Assessment Recommendations AR No. 1 Pipe Insulation Recommendation Insulate exposed piping that is significantly hotter or colder than ambient temperature. This will reduce energy lost through pipe surfaces by 92%. Assessment Recommendation Summary Energy Savings (MMBtu) 44.0 Cost Savings $631 Implementation Cost $298 Payback (years) 0.5 Background About 33 feet of exposed pipe runs in the commons and bookstore maintenance rooms. Uninsulated pipes contribute to energy losses in heating and cooling systems. Proposal Insulate bare piping with suggested insulation to reduce further energy losses. Insulating these lines will save energy. Typical types of insulation used for pipes are listed below: • • • • Polystyrene High density fiberglass shaped for pipes or flat sections Blankets of fiberglass or mineral wool Spray-on foam (Primarily on cooling systems) We have recommended polystyrene with an aluminum jacket. This type of insulation results in a payback period of 0.6 years. Photo courtesy of The Boiler Burner For detailed calculation, see Pipe Insulation - Calculation Methodology later in this report. 5 AR No. 2 Chiller Recommendation Reduce the approach temperature on both of the chiller cooling towers. This will reduce compressor energy use while maintaining your chilled water temperature. Assessment Recommendation Summary Energy Energy Cost Implementation Payback (MMBtu) (kWh)* Savings Cost (years) 415.3 121,800 $5,700 $6,000 1.1 *1 kWh = 3,410 Btu Background Chillers use a refrigerant loop to chill water and transfer the heat to ambient air. The chiller compressor pressurizes refrigerant, raising its temperature and pressure, then pumps refrigerant to the condenser where refrigerant condenses into a liquid, rejecting heat. The approach temperature difference between chiller refrigerant and water approaching the condenser is a good indicator of whether excess compression is required at the compressor. Your condenser’s minimum approach temperature is approximately 54 °F. We recommend an approach temperature of 20 °F. Proposal Reduce condenser approach temperature. This will reduce compressor energy use while maintaining chilled water temperature. It is likely that the chiller heat exchangers will have to be cleaned to lower approach temperature without effecting chiller capacity. As detailed in the Chiller - Calculation Methodology, there is a 1.1 year payback with $6,000 implementation cost. 6 AR No. 3 Winter HVAC Recommendation Turn off the five major air handling units during winter night time hours. The estimated reduction in total building steam use is 31% and the estimated reduction in electricity usage for these five fans is 33%. Assessment Recommendation Summary Energy Steam Energy Net Implementation (MMBtu) (lbs)** (kWh)* Savings Cost 1,301.3 1,273,843 25,251 $24,414 $0 *1 kWh = 3,410 Btu **1 lb Steam = 903 Btu Payback (years) Immediate Background Five major HVAC units currently run constantly throughout the year. During the summer, HVAC fans are needed at night to circulate cool outside air into the building for a night flush. However, during the winter, these fans exhaust steam heated air to the outside while bringing in chilled air that must be heated. While HVAC is needed during the day for circulation, nighttime usage can be eliminated. Turning off major HVAC units at night during the winter will significantly reduce building costs without negatively effecting air quality. Proposal Turn off five major air handling units at night during the winter. This action is expected to result in significant energy savings without negatively effecting building comfort. As detailed in the Winter HVAC - Calculation Methodology, there is an immediate payback with no implementation cost. Image courtesy of www.jmcmechanical.com 7 AR No. 4 Oven Exhaust Fan Recommendation Turn off the Pangea oven exhaust fan at night and during the summer. This will reduce fan electrical costs by 43% and loss of conditioned air when cooling or heating is needed. The heating and cooling savings are not taken into account in this recommendation. Assessment Recommendation Summary Energy Energy Cost Implementation Payback (MMBtu) (kWh)* Savings Cost (years) 58.0 17,010 $789 $100 0.1 *1 kWh = 3,410 Btu Background The kitchen oven exhaust fan runs constantly, even at night and during the summer when the ovens are not running. During these times the oven exhaust fan is unnecessarily exhausting conditioned air and consuming energy. Proposal Turn off Pangea oven exhaust fan during nights throughout the year and keep exhaust fan off during the summer when the ovens are not running. This should save approximately 43% of the energy consumed by exhaust fan. As detailed in the Oven Exhaust Fan - Calculation Methodology, cost savings will pay for implementation costs in 0.1 years. Image Courtesy of: www.greenheck.com 8 AR No. 5 Skylights Recommendation Install photo sensor/timer units on T8 fixtures in skylights to reduce operating hours. Replace yellow glass with clear glass to allow more light into hallways. This will reduce lighting costs by 46% in this area. Assessment Recommendation Summary Energy Energy Cost Implementation Payback** (MMBtu) (kWh)* Savings 20.6 6,574 $415 *1 kWh = 3,410 Btu **Cost after incentives Cost** $1,492 (years) 3.6 Background While visiting your building we observed 15 skylights with yellowed glass. Each skylight contained a T8 fixture that was lit during our visit. Proposal We recommend installing a photo sensor/timer unit for each skylight T8 fixture and replacing yellow glass panes in skylights with clear glass panes. Installing photo sensor/timer units will reduce the time each light is on and installing clear glass will allow more natural light into the second floor hallway so the T8 fixtures will be unnecessary on sunny days. As detailed in the Skylights - Calculation Methodology, there is a 3.6 year payback with $1,492 implementation cost after incentives. 9 AR No. 6 Halogen Lights Recommendation Replace halogen fixtures in the ballroom with compact fluorescent fixtures. This will reduce lighting energy usage in this area by 58%. Assessment Recommendation Summary Energy Energy Cost Implementation Payback** (MMBtu) (kWh)* Savings 39.7 12,650 $483 *1 kWh = 3,410 Btu **Savings after incentives Cost** $2,533 (years) 5.2 Background While visiting your facility we observed 45 halogen lights in the ballroom. According to maintenance and a report prepared by an outside source, the halogen lights are 450 watt mini candelabra lights. We observed them operating on a dimmer at 80% output. Proposal Replace candelabra base sockets with mogul base sockets that will accommodate 150 watt non-dimmable compact fluorescent bulbs. This will reduce energy consumption and heat produced by the fixtures. Dimmable compact fluorescent bulbs and fixtures are available and will save additional energy when dimmed. They also cost more, so implementation costs will increase. As detailed in the Halogen Lights - Calculation Methodology, there is a 5.2 year payback with $2,553 implementation cost. Photo courtesy of Amazon.com 10 4. Calculation Methodology AR No. 1 Pipe Insulation Calculation Methodology Recommendation Insulate exposed piping that is significantly hotter or colder than ambient temperature. This will reduce energy lost through pipe surfaces by 92%. Assessment Recommendation Summary Energy Savings Cost (MMBtu) Savings 44.0 $631 *1 kWh = 3,410 Btu Implementation Cost $298 Payback (years) 0.5 Data Collected Summary The bookstore maintenance room (BMR) and commons maintenance room (CMR) contain bare piping with energy loss. The following table summarizes data collected from those locations. Bare Pipe Data* Length Diameter Surface Temp. Ambient Temp. Area Description (in.) (in.) (˚F) (˚F) BMR Unidentified 84.0 3.8 185˚ 88˚ BMR Unidentified 34.3 3.8 210˚ 88˚ CMR Steam 28.5 17.0 200˚ 85˚ CMR Steam 58.0 4.5 200˚ 85˚ CMR Unidentified 49.0 2.3 150˚ 85˚ *Only bare pipes with significant temperature differential from ambient are included Savings Analysis Uninsulated pipes contribute to energy losses in heating and cooling systems. The system must make up for heat losses due to radiation and convection. Reducing the heat transfer coefficient by adding insulation will yield energy and cost savings. Note that the following calculations assume that the fluid or gas temperature in the pipe is constant. We used 3E+ software, a free insulation calculation tool prepared by the North American Insulation Manufacturer’s Association and made available by U.S. Department of Energy, to compare current and proposed energy losses and cost savings for several insulation thicknesses. 11 Cost savings are based on a steam energy cost of $0.0195/lb. The following table shows different thicknesses taking the Bookstore Maintenance Room piping at 185˚F as an example. Energy Savings Summary for Bookstore Maintenance Room Energy Insulation Surface Energy Cost Thickness Temperature Efficiency Cost Heat Loss Savings (inches) (°F) (%) ($/ft/yr) (Btu/ft/yr) ($/ft/yr) Bare 184.9 $27.86 1,860,000 0.5 132.4 80.7 $5.39 359,200 $22 1.0 120.6 87.1 $3.59 239,400 $24 1.5 114.1 90.4 $2.68 178,400 $25 2.0 109.7 92.5 $2.11 140,200 $26 2.5 106.6 93.8 $1.72 114,300 $26 Cost savings (CS) can be found as: CS = = = = Cost savings FT x EC 7 ft x $26/ft $182 FT = Feet of pipe to be insulated = 7 ft EC = Energy cost savings from 3E plus software using 2.0 inch thick insulation = $26/ft Where, Total savings for all bare piping is summarized in the table below. 3E+ calculated each scenario and the best result was chosen (as in example above). Area BMR BMR CMR CMR CMR Total Description Unidentified Unidentified Steam Steam Unidentified Total Cost Savings Summary New Energy Cost Insulation Surface Temp Efficiency Savings Thickness (˚F) (%) ($/ft) 2.0 109.7 92.4 $26 2.5 110.5 94.1 $35 2.0 110.1 84.2 $30 2.0 110.1 84.2 $30 2.5 98.3 82.4 $15 12 Pipe Length (ft.) 7.0 4.9 2.4 4.8 4.0 32.3 Energy Cost Savings $182 $172 $73 $145 $59 $631 Cost Analysis Implementation costs include material costs for the following insulation: • • • Insulation Layer 1: Polystyrene, Varied Outer Jacket Material: Aluminum, oxidized, in service Outer Surface Emittance 0.1 We used RSMeans Building Construction as an estimation tool of installation cost for the insulation. The insulation costs from RSMeans Building Construction ($2.87 /ft) seemed low from previous experience, so we added additional costs of $10/ft for installation to maintain a conservative estimate. Area BMR BMR CMR CMR CMR Total Total Cost Summary Pipe Length Description (ft.) Unidentified 7.0 Unidentified 4.9 Steam 2.4 Steam 4.8 Unidentified 4.0 Cost ($/ft) 12.9 12.9 12.9 12.9 12.9 Insulation Cost $91 $63 $31 $62 $51 $298 Cost savings will pay for implementation in 0.6 years. Incentive Summary Incentives don’t apply to energy efficiency projects with less than a one year payback. However, if this project is combined with another that creates a total project payback of greater than one year, then some energy incentives may apply. 13 AR No. 2 Chiller Calculation Methodology Recommendation Reduce the approach temperature on both of the chiller cooling towers. This will reduce compressor energy use while maintaining your chilled water temperature. Assessment Recommendation Summary Energy Energy Cost Implementation Payback (MMBtu) (kWh)* Savings Cost (years) 415.3 121,800 $5,700 $6,000 1.1 *1 kWh = 3,410 Btu Data Collected Summary From building personnel • Chillers don’t run in between October and February Assumptions • Chiller heat exchangers will require a thorough cleaning or additional capacity From nameplates and observation Chiller Nameplate and Observed Operating Conditions Summary East Chiller West Chiller Manufacturer Carrier Carrier Horsepower 35 40 Cooling Tower Type Wet Wet Minimum Approach Temperature 54 °F 54 °F Currently, the chiller system consists of three separate loops. 1. The chilled loop carries chilled water from the chiller evaporator to the end use, where the chilled water gains energy by absorbing heat. The chilled water then exhausts heat into the chiller evaporator. 2. The refrigerant loop carries low energy refrigerant to the chiller evaporator where the refrigerant absorbs energy from the chilled water. The high energy refrigerant travels through a compressor and exhausts energy at the chiller condenser. The refrigerant then travels through the expansion device back to the evaporator again. 14 3. The cooling loop carries low energy cooling water to the chiller condenser where it gains energy. The cooling water then travels to the cooling tower where it exhausts energy to the atmosphere. The following diagram is of the chiller system. Chiller System End Use Chilled Loop Chiller Evaporator Energy Flow Refrigerant Loop Chiller Compressor Chiller Condensor Cooling Loop Cooling Tower The heat exchangers referenced in this recommendation are in the chiller condenser. If the heat exchanger in the chiller condenser cannot be changed, changes in the cooling tower controls and maintenance might achieve similar results. 15 From regional weather data Ambient Temperature Data between September and February 1 Outside Wet Bulb Winter Hours at this Outside Wet Bulb Winter Hours at this Temperature Temperature Temperature Temperature (°F) (Hours) (°F) (Hours) 68 13 44 992 67 40 40 811 65 86 36 590 63 158 31 318 61 240 26 163 58 349 20 42 56 473 15 8 53 710 11 2 48 882 7 1 Savings Analysis A chiller spreadsheet developed by the Oregon State University Industrial Assessment Center is used to calculate chiller energy and cost savings. The spreadsheet uses weather data, current operating conditions and proposed operating conditions to find compressor energy savings. Annual cost savings are calculated by finding the cost savings associated with energy savings. CS = = = = Cost Savings EC x ES $0.0464 /kWh x 121,800 kWh $5,700 EC = = Incremental Energy Cost $0.0464 /kWh ES = = = = Energy Savings E+W 62,500 kWh + 59,300 kWh 121,800 kWh E = = East Chiller Energy Savings 62,500 kWh W = = West Chiller Energy Savings 59,300 kWh Where, Where, 1 Data is collected at and compiled by Salem Airport between the years of 1948 and 1985 16 Chiller Energy Savings are found using the spreadsheets at the end of the Chiller – Calculation Methodology. Spreadsheet terminology is described in Refrigeration Appendix D. Total annual cost savings are summarized in the following Savings Summary table: Savings Summary Source Quantity Units Energy (MMBtu) East Chiller Energy Use 62,500 kWh 213.1 West Chiller Energy Use 59,300 kWh 202.2 121,800 kWh Total 415.3 Cost Savings $2,900 $2,800 $5,700 Cost Analysis Based on the chiller loop temperatures and the refrigerant temperatures, the heat exchangers are not achieving a sufficiently low condenser approach temperature. Installing larger heat exchangers would greatly improve heat exchanger performance, but this is not cost effective. We assume a professional cleaning should improve chiller performance enough to accommodate a lower approach temperature. IC = = = = Implementation Cost HC x N $3,000 /Heat Exchanger x 2 Heat Exchangers $6,000 HC = = Cost to Professionally Clean the Heat Exchanger $3,000 /Heat Exchanger N = = Number of Heat Exchangers 2 Heat Exchangers Where, Total implementation costs are summarized in the following Implementation Summary table: Implementation Summary Source Quantity Units $/Unit Cost Heat Exchanger Cleaning Costs 2 Heat Exchangers $3,000 $6,000 Savings will pay for implementation in 1.1 years. 17 Note If the current chiller heat exchangers are undersized, it may not be possible to reduce approach temperature even with a thorough cleaning. In this case, larger heat exchanger will greatly increase implementation costs and payback period. During our first visit to your building, we observed anomalous chiller behavior including a cooling water loop approach temperature of over 80 °F. To preserve a conservative estimate in our calculations, we assume that the approach temperature is constant at 54 °F, the temperature we observed during our second visit to your building. 18 EAST REFRIGERATION ENERGY SAVINGS Report: Application: Buildings: Bin Data: 2001 Refrigeration Bookstore Maintenance Room Salem, OR Operating Conditions Minimum Condensing Temperature (Tm): Approach Temperature Difference (DT): Compressor Energy (EC): Condenser Fan Horsepower (Hp): Fan Power (FP): Average Fan Use Factor (UFe): Fan Energy (FE): Total Energy Usage: Total Energy Cost: Bin Calculation Dry Bulb We t Bin Bulb (Tdb) (Twb) 107 73 102 72 97 69 92 68 87 67 82 65 77 63 72 61 67 58 62 56 57 53 52 48 47 44 42 40 37 36 32 31 27 26 22 20 17 15 12 11 7 7 2 2 -3 -1 -8 -8 -13 -13 Totals Cooling Wate r Ente ring Conde nse r (Tcw) 88 87 84 83 82 80 78 76 73 71 68 63 59 55 51 46 41 38 38 38 38 38 38 38 38 Refrigerant: Energy Cost (E$): Annual Hours: Existing 70 54 156,870 3 1.6 100.0% 9,300 166,170 $7,710 Approach Te mp Hours (H) 0 0 2 13 40 86 158 240 349 473 710 882 922 811 590 318 163 42 8 2 1 0 0 0 0 5,810 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 Exist Cond Temp (Tce) 142 141 138 137 136 134 132 130 127 125 122 117 113 109 105 100 95 92 92 92 92 92 92 92 92 Prop Cond Temp (Tcp) 127 122 117 112 107 102 97 92 87 82 77 72 70 70 70 70 70 70 70 70 70 70 70 70 70 Energy and Cost Savings Compressor Energy Savings (CES): Fan Energy Increase (FEI): Total Energy Savings (ES): Total Cost Savings (CS): Implementation Cost (IC): Simple Payback: Deg-hr Savings (DHS) 0 0 42 325 1,160 2,752 5,530 9,120 13,960 20,339 31,950 39,690 39,646 31,629 20,650 9,540 4,075 924 176 44 22 0 0 0 0 232,000 Savings % (E%) 0.0% 0.0% 0.0% 0.1% 0.2% 0.5% 1.0% 1.6% 2.4% 3.5% 5.5% 6.8% 6.8% 5.4% 3.6% 1.6% 0.7% 0.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 39.9% R22 $0.04640 /kWh 5,810 Proposed 70 20 94,370 3 1.6 85.3% 7,900 102,270 $4,750 Compress Savings kWh (CES) 0 0 11 88 313 743 1,493 2,462 3,769 5,492 8,627 10,716 10,704 8,540 5,576 2,576 1,100 249 48 12 6 0 0 0 0 62,500 Savings 0 34 62,500 0.0 0.0 14.7% 1,400 63,900 $3,000 Fan Increase kWh (FEI) kWh kWh Total Savings kWh (ES) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 (8) (2) 0 0 0 0 0 0 62,500 0 62,500 $2,900 $3,000 1.0 19 Units °F °F kWh/yr hp kW 0 0 11 88 313 743 1,493 2,462 3,769 5,492 8,627 10,716 10,704 8,540 5,576 2,576 1,100 249 56 14 6 0 0 0 0 62,500 kWh/yr kWh/yr kWh/yr /yr years WEST REFRIGERATION ENERGY SAVINGS Report: Application: Buildings: Bin Data: 2001 Refrigeration Bowling Chiller Room Salem, OR Refrigerant: Energy Cost (E$): Annual Hours: Operating Conditions Minimum Condensing Temperature (Tm): Approach Temperature Difference (DT): Compressor Energy (EC): Condenser Fan Horsepower (Hp): Fan Power (FP): Average Fan Use Factor (UFe): Fan Energy (FE): Total Energy Usage: Total Energy Cost: Bin Calculation Dry Cooling Bulb Wet Water Bin Bulb Entering (Tdb) (Twb) Condenser (Tcw) 107 73 88 102 72 87 97 69 84 92 68 83 87 67 82 82 65 80 77 63 78 72 61 76 67 58 73 62 56 71 57 53 68 52 48 63 47 44 59 42 40 55 37 36 51 32 31 46 27 26 41 22 20 38 17 15 38 12 11 38 7 7 38 2 2 38 -3 -1 38 -8 -8 38 -13 -13 38 Totals Energy and Cost Savings Compressor Energy Savings (CES): Fan Energy Increase (FEI): Total Energy Savings (ES): Total Cost Savings (CS): Implementation Cost (IC): Simple Payback: R22 $0.04640 /kWh 5,810 Existing 70 54 173,370 3 1.6 100.0% 9,300 182,670 $8,480 Approach Temp Hours (H) 0 0 2 13 40 86 158 240 349 473 710 882 922 811 590 318 163 42 8 2 1 0 0 0 0 5,810 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 54 Exist Cond Temp (Tce) 142 141 138 137 136 134 132 130 127 125 122 117 113 109 105 100 95 92 92 92 92 92 92 92 92 Prop Cond Temp (Tcp) 108 107 104 103 102 100 98 96 93 91 88 83 79 75 71 70 70 70 70 70 70 70 70 70 70 Deg-hr Savings (DHS) 0 0 68 442 1,360 2,924 5,372 8,160 11,866 16,082 24,140 29,988 31,348 27,574 20,060 9,540 4,075 924 176 44 22 0 0 0 0 194,000 Savings % (E%) 0.0% 0.0% 0.0% 0.1% 0.2% 0.5% 0.9% 1.4% 2.0% 2.8% 4.2% 5.2% 5.4% 4.7% 3.5% 1.6% 0.7% 0.2% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% 33.4% Proposed 70 20 115,470 3 1.6 85.3% 7,900 123,370 $5,720 Compress Savings kWh (CES) 0 0 20 132 406 873 1,603 2,435 3,541 4,799 7,203 8,948 9,354 8,228 5,986 2,847 1,216 276 53 13 7 0 0 0 0 57,900 Savings Units 0 °F 34 °F 57,900 kWh/yr 0.0 hp 0.0 kW 14.7% 1,400 kWh 59,300 kWh $2,800 Fan Increase kWh (FEI) 0 0 0 0 0 0 0 0 0 0 0 0 (192) (371) (372) (241) (140) (39) (8) (2) 0 0 0 0 0 (1,400) 57,900 kWh/yr (1,400) kWh/yr 59,300 kWh/yr $2,800 /yr $3,000 1.1 years 20 Total Savings kWh (ES) 0 0 20 132 406 873 1,603 2,435 3,541 4,799 7,203 8,948 9,546 8,599 6,358 3,088 1,356 315 61 15 7 0 0 0 0 59,300 AR No. 3 Winter HVAC Calculation Methodology Recommendation Turn off the five major air handling units during winter night time hours. This will reduce total building steam use by 31% and fan energy use by 33%. Assessment Recommendation Summary Energy Steam Energy Net Implementation Payback (MMBtu) (lbs)** (kWh)* Savings Cost (years) 1,301.3 1,273,843 25,251 $24,414 $0 Immediate *1 kWh = 3,410 Btu **1 lb Steam = 903 Btu Data Collected Summary From building personnel • Building occupancy is minimal between midnight and 6 am • HVAC during the winter is to provide circulation, not for temperature control • The building switches between heating and cooling in October and April • The entire MU is wired at 230 Volts • Steam costs $0.0195/lb Steam for the 2008/2009 school year • Bowling Unit runs at 13.6 Amps (live) • Bookstore Supply Fan #7 runs at 10.1 Amps (live) • Bookstore Exhaust Fan #2 runs at 9.8 Amps (live) • Ballroom Unit runs at 21 Amps (live) • Lounge Unit runs at 21 Amps (live) From previous reports • Lounge unit draws heated supply air from the attic • Steam enthalpy is 903 Btu/lb Steam Assumptions • Building heating set-point is 60 °F • Bookstore Supply Unit #7, Bowling Unit and Ballroom Unit are running at rated airflow • Live amp readings accurately reflect conditions throughout winter 21 The following table summarizes current winter operating conditions. Current Winter Operating Conditions Summary Live Amps Volts kW CFM Winter Operating Hours Bookstore Supply Unit #7 10.1 230 2.3 20,000 4,380 Bookstore Exhaust Unit #2 9.8 230 2.2 18,000 4,380 Bowling Unit 13.6 230 3.1 7,500 4,380 Ballroom Unit 21.0 230 4.8 10,000 4,380 Lounge Unit 21.0 230 4.8 13,000 4,380 kWh 10,074 9,636 13,578 21,024 21,024 The following table summarizes average temperature conditions between 1 am to 8 am from October to April. Midnight to 8 am Winter Heat Load Summary 2 Building Setpoint Outside Temperature Temperature Difference Winter Hours at this Temperature (°F) (°F) (°F) (Hours) 60 57 3 43 60 52 8 149 60 47 13 269 60 42 18 336 60 37 23 288 60 32 28 212 60 27 33 95 60 22 38 37 60 17 43 15 60 12 48 5 60 7 53 0 Savings Analysis For the purpose of this analysis winter is assumed to be a 6 month period when the building requires heating. Current energy use is calculated using a building set-point of 60 °F. We propose reducing the winter operating hours of the air handling units by eight hours each night. This recommendation doesn’t change the maximum power value, so there are no demand savings. We calculate electrical savings first, then savings from space heating reductions. 2 Data is collected at and compiled by Salem Airport between the years of 1948 and 1985 22 Electrical savings are calculated as the difference between current and proposed electrical energy use. The Ballroom Unit is taken as an example: Electrical Savings for the Ballroom Unit EC = = = = Electricity Cost Savings ES x IE 7,047 kWh x $0.0464/kWh $327 ES = = = = Energy Savings CE – PE 21,024 kWh – 13,977 kWh 7,047 kWh IE = = Incremental Energy Cost $0.0464/kWh CE = = = = Current Winter Energy Usage CH x CP 4,380 hrs x 4.8 kW 21,024 kWh PE = = = = Proposed Winter Energy Usage PH x PP 2,912 hrs x 4.8 kW 13,977 kWh CH = = Current Winter Operating Hours 4,380 hrs CP = = Current Power 4.8 kW PH = = = Proposed Winter Operating Hours (24 hrs/day – 8 hrs/day) x 182 days/winter 2,912 hrs PP = = Proposed Power 4.8 kW Where, Where, Where, 23 The following table summarizes existing electrical conditions, proposed electrical conditions and electrical savings during winter. Winter Operating Conditions and Electrical Savings Summary Operating Hours kW kWh Existing Bookstore Supply Unit #7 4,380 2.3 10,074 Existing Bookstore Exhaust Unit #2 4,380 2.2 9,636 Existing Bowling Unit 4,380 3.1 13,578 Existing Ballroom Unit 4,380 4.8 21,024 Existing Lounge Unit 4,380 4.8 21,024 Proposed Bookstore Supply Unit #7 2,912 2.3 6,698 Proposed Bookstore Exhaust Unit #2 2,912 2.2 6,406 Proposed Bowling Unit 2,912 3.1 9,027 Proposed Ballroom Unit 2,912 4.8 13,977 Proposed Lounge Unit 2,912 4.8 13,977 Savings 1,468 0.0 25,251 Cost $467 $447 $630 $975 $975 $310 $298 $418 $648 $648 $1,172 Heating Savings for major Air Handling Units We propose to eliminate fan operating hours between midnight and 8 am. This will effectively eliminate steam heating in these units during these hours. Savings are determined by calculating the energy required to raise the temperature of outside air to the building set-point during these hours. Previous HVAC reports noted that the Lounge Unit draws heated air from the attic that is used during the winter without requiring additional heating. Also, the Bookstore Exhaust Unit #2 is not taken into account as no heating occurs within it. HC = = = = Heating Cost Savings SS x IS 1,345,787 lbs Steam x $0.0195/lb Steam $26,242 SS = = = = Steam Savings HS ÷ SE 1,215,246,240 Btu ÷ 903 Btu/lb Steam 1,345,787 lbs Steam IS = = Incremental Steam Cost $0.0195/lb Steam Where, 24 Where, HS = = = = Heating Savings CP x AT x SA x ℓ x 60 min/hr 0.24 Btu/lb-°F x 28,852 °F-hrs x 37,500 cfm x 0.078 lb/ft3 x 60 min/hr 1,215,246,240 Btu SE = = Steam Enthalpy 954 Btu/lb Steam CP = = Specific Heat of Air in btu/lbm-degF 0.24 Btu/lb-°F AT = = Annual Temperature Difference Hours = 28,852 °F-hrs SA = = = = System Airflow BU + BS + BA 10,000 cfm + 20,000 cfm + 7,500 cfm 37,500 cfm ℓ = = Air Density 0.078 lb/Ft3 Where, ∑(60° - T )× H Where, Variable Declaration and Winter Temperature Hours between Midnight and 8 am Temperature Outside Temperature Hours Spent at this Outside Temperature Variable (°F) Hours Variable (Hours) Ta 57 Ha 43 Tb 52 Hb 149 Tc 47 Hc 269 Td 42 Hd 336 Te 37 He 288 Tf 32 Hf 212 Tg 27 Hg 95 Th 22 Hh 37 Ti 17 Hi 15 Tj 12 Hj 5 BU = = Bowling Unit Airflow 10,000 cfm 25 BS = = Bookstore Supply Unit Airflow 20,000 cfm BA = = Ballroom Unit Airflow 7,500 cfm Total savings including electrical and heating are summarized in the following table. Electrical Energy Electrical Demand Heating Total Savings Summary Table Quantity Units Energy (MMBtu) 25,251 kWh 86.1 0 kW 1,273,843 lbs Steam 1,215.2 1,301.3 Cost $1,172 $0 $26,242 $27,414 Cost Analysis An additional cost associated with this recommendation is the labor cost of turning off the air handling units at night and turning them back on in the morning. From building personnel, there is maintenance staff onsite as early as 6 am and as late as midnight. Usually, we expect turning motors on and off to be within normal maintenance duties. However, as this is not an industrial facility, we assume that $3,000 annually will cover additional labor hours. Total Cost savings including annual costs are calculated below. Net Savings Summary Table Cost Savings Annual Labor Cost Net Savings $27,414 ($3,000) $24,414 There is no immediate implementation cost associated with this recommendation. Note A programmable logic controller or a direct digital controller can perform the task of turning the air handling units on and off at the appropriate hours automatically. This will eliminate the annual labor cost while increasing the implementation cost. This is not included in the cost analysis as we were unable to find a price for a suitable controller. 26 AR No. 4 Oven Exhaust Fan Calculation Methodology Recommendation Turn off the Pangea oven exhaust fan at night and during the summer. This will reduce fan electrical costs by 43% and loss of conditioned air when cooling or heating is needed. The heating and cooling savings are not taken into account in this recommendation. Assessment Recommendation Summary Energy Energy Cost Implementation Payback (MMBtu) (kWh)* Savings Cost (years) 58.0 17,010 $789 $100 0.1 *1 kWh =3,410 Btu Data Collected Summary The following data was collected during our visit • Marathon motor on main Pangea oven exhaust fan • 7.5 Horse power • 1760 RPM • 208 volts • Operates 24/7, even when ovens are not running • During the summer and at night, the ovens are not used Assumptions • Estimated motor efficiency: 86.5% (based on generic motor efficiency table) • Estimated load factor: 70% • Proposed operating hours: 4,980 hrs (based on turning fans off during the 3 summer months and 6 hours each night) 27 Savings Analysis Annual cost savings are calculated by finding the difference between the current and proposed conditions. We neglect any demand savings incurred to maintain conservative cost savings. ES = = = = Energy Savings EC x ES $0.0464/kWh x 17,010 kWh $789 EC = = Incremental Energy Cost $0.0464 /kWh ES = = = = Energy Savings CE – PE 39,420 kWh – 22,410 kWh 17,010 kWh CE = = = = Current Energy P x CH 4.5 kW x 8,760 hrs 39,420 kWh PE = = = = Proposed Energy P x PH 4.5 kW x 4,980 hrs 22,410 kWh P = = = = Power Usage (HP x C x LF) ÷ EF (7.5 hp x 0.746 kW/hp x 0.70) ÷ 0.865 4.5 kW CH = = Current Hours 8,760 hrs PH = = Proposed Hours 4,980 hrs HP = = Horse Power 7.5 hp Where, Where, Where, Where, 28 C = = Energy Conversion 0.746 kW/hp LF = = Load Factor 70% EF = = Motor Efficiency 86.5% Total annual cost savings are summarized in the following Savings Summary table: Source Energy Use Saving Summary Quantity Units Energy (MMBtu) 17,010 kWh 58.0 Cost Savings $789 Cost Analysis Turning off the exhaust fan requires only an attentive operator. The power switch is located behind a refrigerator, but is reachable. Moving the power switch to a location that is accessible is advised. The cost of moving one power switch will be about $100 for one hour of electrician work and material. Cost Summary Source Quantity Units $/Unit Electrician 1 hrs 50.0 Material Total Cost $50 $50 $100 Cost savings will pay for implementation costs in 0.1 years. Note An electronic controller will be more reliable than employee operated switch. However, we did not include this option in the cost analysis as the savings did not warrant a controller. 29 AR No. 5 Skylights Calculation Methodology Recommendation Install photo sensor/timer units on T8 fixtures in skylights to reduce operating hours. Replace yellow glass with clear glass to allow more light into hallways. This will reduce lighting costs by 46% in this area. Assessment Recommendation Summary Energy Energy Cost Implementation Payback (MMBtu) 20.6 (kWh) 6,574 Savings $415 Cost $1,995 (years) 4.8 *1 kWh = 3,410 Btu Estimated Incentive Summary ETO BETC2 Net Net Payback Incentive Tax Credit Cost (years) $499 $456 $1,040 2.5 1 Energy Trust of Oregon Incentive 2 Oregon Department of Energy Business Energy Tax Credit 1 Data Collected Summary The following data was collected during our visit • 15 Skylights • Each skylight contains a T8 fluorescent fixture • Fixtures operate 4,969 hrs unnecessarily annually Assumptions • We assume each fixture runs constantly Savings Analysis Energy and maintenance cost savings for installing photo sensors are calculated using the Install Photo Sensor/Timer Units worksheet following this calculation. The lighting worksheet’s terminology is described in Appendix C. 30 Energy savings are estimated using power, current operating hours, and proposed operating hours per year. Energy cost savings are estimated with an incremental energy cost of $0.0464/kWh. CS = = = = Energy Cost Savings EC x ES $0.0464/kWh x 6,574 kWh $305 EC = = Incremental Energy Cost $0.0464/kWh ES = = = = Energy Savings CE – PE 12,264 kWh –5,690 kWh 6,574 kWh CE = = Current Energy Consumption 12,264 kWh PE = = Proposed Energy Consumption 5,690 kWh Where, Where, Reducing light operating hours will decrease maintenance costs, as estimated in the Install Photo Sensors table at the end of this calculation methodology. The maintenance material savings total $60 per year, while maintenance labor savings total $50 per year. Therefore, the total maintenance savings sum to $111 annually. Total annual cost savings are summarized in the following Savings Summary table: Saving Summary Energy Source Quantity Units (MMBtu) Cost Energy Use 6,574 kWh 22.4 $305 Maintenance Material $60 Maintenance Labor $50 Total 22.4 $415 31 Cost Analysis Implementation costs for photo sensors and clear glass panes include material and installation costs. Each skylight requires 1 photo sensor/timer unit and 24 glass panes. Labor costs were conservatively estimated at one hour per sensor installation with a typical electrician’s wage of $50 per hour and one hour per skylight for glass panes with a typical maintenance wage of $15 per hour. Cost Summary Item Units Cost/Unit Total Photo Sensors/Timers 15 $20 $300 Glass Panes 360 $2 $720 Electrician 15 $50 $750 Installation 15 $15 $225 Total $1,995 Incentive Summary Energy Trust cash incentives are available to help pay for implementation of energy saving measures if they save at least 10% of the energy used in a system. Incentives can be anticipated to equal the minimum of 25% of total project cost, $0.12 per kWh saved, or $1 per therm saved. CI Where, TES TC = = = = = ETO Cash Incentive Minimum of TES x $0.12 Minimum of 6,574 x $0.12 Minimum of $789 $499 = = Total Energy Savings 6,574 kWh = = Applicable Implementation Cost $1,995 or or or 0.25 x TC 0.25 x $1,995 $499 You may also be eligible for the Oregon Business Energy Tax Credit. If a project reduces system energy use by at least 10%, the incentive can be expected to equal 35% of project costs after applying other incentives. However the tax credit accrues over a 5 year period (10%, 10%, 5%, 5%, and 5%), or over one year for projects with implementation costs of less than $20,000. The Oregon Department of Energy also allows “pass through” of a onetime lump value, which is 25.5% of project costs over $20,000 and 30.5% of project costs under $20,000. As this is a reasonable estimate for the 35% tax credit’s net present value, we will use 30.5% as the value of the tax credit in our analysis and estimate of the “payback” period. 32 BTC = = = = Business Energy Tax Credit (TC – CI) x 0.305 ($1,995 – $499) x 0.305 $456 The following table summarizes implementation costs before and after incentives. Incentive Summary Description Pre-incentive Cost Energy Trust Incentives Business Energy Tax Credit Total after Incentives Cost $1,995 ($499) ($456) $1,040 Savings will pay for implementation costs in 2.5 years after incentives. 33 Install Photo Sensor/Timer Units Report Number: PLANT DATA Building: Area: Lamp Replacement Time: Ballast Replacement Time: Fixture Replacement Time: M emorial Union 2nd Floor Hallways 1/6 hours 1/2 hours 1 hours Existing $4.75 /kW-mo. $0.04640 /kWh $15.00 /hour $50.00 /hour Proposed Savings 4 Ft T8 Elec. 15 8,760 100% 3 1 $62.95 4 Ft T8 Elec. 15 4,064 100% 3 1 $62.95 0 4,696 0% 0 0 $0.00 F32-1 4 Ft T8 C.T. 45 20,000 $1.94 32 2,710 44% $38.24 $49.08 F32-1 4 Ft T8 C.T. 45 20,000 $1.94 32 2,710 20% $17.74 $22.77 0 0 $0.00 0 0 0 $20.50 $26.31 T32-5 4 Ft F32T8 15 75,000 $42.65 0% 93 12% $74.72 $43.80 T32-5 4 Ft F32T8 15 75,000 $42.65 0% 93 5% $34.67 $20.32 0 0 $0.00 0 0 0 $40.06 $23.48 FIXTURES FIXTURE CODE Description: Quantity: Operating Hours: Output Factor: Lamps per Fixture: Ballasts per Fixture: Fixture Cost: 2001 Incremental Demand Cost: Incremental Energy Cost: Recommended Foot-candles: M aintenance Labor Rate: Electrician Labor Rate: OFT8-2 Units OFT8-2 hours LAMPS LAM P CODE Description: Quantity: Life: Lamp Cost: Watts per Lamp: Lumens: Replacement Fraction: Annual Lamp Replacement Cost: Annual M aintenance Labor Cost: hours watts BALLASTS BALLAST CODE Description: Quantity: Life: Ballast Cost: Ballast Factor: Input Watts: Replacement Fraction: Annual Ballast Replacement Cost: Annual M aintenance Labor Cost: hours watts POWER AND ENERGY Power: Energy Use: 1.4 12,264 1.4 5,690 0.0 6,574 kW kWh LIGHT LEVEL CHECK Total Lumens: Foot-candles: Lighting Efficiency: 121,950 0 0.0 121,950 0 0.0 0 0 0 Lum./W ANNUAL OPERATING COST Demand Cost: Energy Cost: M aintenance M aterial Cost: M aintenance Labor Cost: Total Operating Cost: $80 $569 $113 $93 $855 34 $80 $264 $52 $43 $439 $0.00 $305.00 $60.55 $49.79 $415.34 AR No. 6 Halogen Lights Calculation Methodology Recommendation Replace Halogen fixtures in the ballroom with Compact Fluorescent fixtures. This will reduce energy usage in this area by 58%. Assessment Recommendation Summary Energy Energy Cost Implementation Payback (MMBtu) 39.7 (kWh)* 12,650 Savings $483 Cost $4,860 (years) 10.1 *1 kWh = 3,410 Btu Estimated Incentive Summary ETO BETC2 Net Net Payback Incentive Tax Credit Cost (years) $1,215 $1,112 $2,533 5.2 1 Energy Trust of Oregon Incentive 2 Oregon Department of Energy Business Energy Tax Credit 1 Data Collected Summary The following data was collected during our visit • 45 recessed cans • 1 Halogen T4 E11 fixture per recessed can Assumptions • The lights operate 1,340 hrs annually Savings Analysis Energy and maintenance cost savings for installing motion sensors and replacing metal halide lights are calculated using the “Replace Halogen Fixtures with Compact Fluorescents” spreadsheet that follows this calculation summary. Lighting spreadsheet terminology is described in Appendix C. 35 Energy savings are estimated using power, current fixture wattages, and proposed fixture wattages, and operating hours. Energy cost savings are estimated with an incremental energy cost of $0.0464/ kWh. ES = = = = Energy Cost Savings (CE – PE) x EC (21,762 kWh – 9,112 kWh) x $0.0464/ kWh $587 CE = = Current Energy Consumption 21,762 kWh PE = = Proposed Energy Consumption 9,112 kWh EC = = Energy Cost $0.0464/ kWh Where, Installing compact fluorescent fixtures will also lead to a decrease in fixture maintenance labor costs by extending the life of lamps. Annual labor savings are $56. However, the increased cost of lamps will increase material costs by $160 annually, totaling $104 of annual increased maintenance costs. Total annual cost savings are summarized in the following Savings Summary table: Savings Summary Source Energy Use Maintenance Material Maintenance Labor Total Energy Quantity Units MMBtu 12,650 kWh 39.7 39.7 Cost $ $587 ($160) $56 $483 Cost Analysis The cost of replacing the halogen fixtures with Compact Fluorescent fixtures is based on the cost of material and installation per fixture. There are a total of 45 fixtures that need replaced. We estimate that it will take an electrician one hour to install each fixture at a wage of $50 per hr. 36 The costs are summarized in the table below: Item 150 Watt Mogul CFL Mogul Base Socket Assembly Electrician Total Cost Summary Quantity Units 45 Lamps 45 Fixtures 45 Hours Cost/Unit $46 $12 $50 Total Cost $2,070 $540 $2,250 $4,860 Incentive Summary Energy Trust cash incentives are available to help pay for implementation of energy saving measures if they save at least 10% of the energy used in a system. In this case, the 10% savings is met. Incentives can be anticipated to equal the minimum of 25% of total project cost, $0.12 per kWh saved, or $1 per therm saved. CI Where, TES TC = = = = = ETO Cash Incentive Minimum of TES x $0.12 Minimum of 12,650 x $0.12 Minimum of $1,518 $1,215 = = Total Energy Savings 12,650 kWh = = Total Implementation Cost $4,860 or or or 0.25 x TC 0.25 x $4,860 $1,215 You may also be eligible for the Oregon Business Energy Tax Credit. If a project reduces system energy use by at least 10%, the incentive can be expected to equal 35% of project costs after applying other incentives. However, the tax credit accrues over a 5 year period (10%, 10%, 5%, 5%, and 5%), or over one year for projects with implementation costs of less than $20,000. The Oregon Department of Energy also allows “pass through” of a onetime lump value, which is 25.5% of project costs over $20,000 and 30.5% of project costs under $20,000. As this is a reasonable estimate of the net present value of the 35% tax credit, we will use 30.5% as the value of the tax credit in our analysis and estimate of the “payback” period. BTC = = = = Business Energy Tax Credit (TC – CI) x 0.305 ($4,860 – $1,215) x 0.305 $1,112 37 The following table summarizes implementation costs before and after incentives. Incentive Summary Description Pre-incentive Cost Energy Trust Incentives Business Energy Tax Credit Total after Incentives Cost $4,860 ($1,215) ($1,112) $2,533 Savings will pay for implementation costs in 5.2 years after incentives. 38 Replace Halogen Fixtures with Compact Fluorescents PLANT DATA Building: Area: Lamp Replacement Time: Ballast Replacement Time: Fixture Replacement Time: Memorial Union Ballroom 1/6 hours 1/2 hours 1 hours Report Number: Incremental Energy Cost: 2001 $0.04640 /kWh Maintenance Labor Rate: Electrician Labor Rate: $15.00 /hour $50.00 /hour FIXTURES Existing Proposed FIXTURE CODE Description: Quantity: Operating Hours: Output Factor: Lamps per Fixture: Fixture Cost: HF450 CF150 450 Watt Halogens 45 1,340 80% 1 $0.00 150 Watt CF 45 1,340 100% 1 $11.95 0 0 -20% 0 ($11.95) H450 450 Watt Halogens 45 2,000 $6.19 450 8,000 67% $186.63 $75.07 C150 150 Watt Compact Fluor 45 8,000 $46.06 150 8,000 17% $347.18 $18.77 0 (6,000) ($39.87) 300 0 1 ($160.55) $56.31 Savings Units hours LAMPS LAMP CODE Description: Quantity: Life: Lamp Cost: Watts per Lamp: Lumens: Replacement Fraction: Annual Lamp Replacement Cost: Annual Maintenance Labor Cost: hours watts POWER AND ENERGY Power: Energy Use: 20.3 21,762 6.8 9,112 13.5 12,650 $1,010 $187 $75 $1,272 $423 $347 $19 $789 $587.00 ($160.55) $56.31 $482.76 kW kWh ANNUAL OPERATING COST Energy Cost: Maintenance Material Cost: Maintenance Labor Cost: Total Operating Cost: IMPLEMENTATION COST Materials: Labor: Total Implementation Cost: $2,610 $2,250 $4,860 SIMPLE PAYBACK 10.1 39 years 40 APPENDIX A UTILITIES A.1 Energy Definitions An essential component of any energy management program is tracking energy. When utility bills are received, we record energy use and cost in a spreadsheet and get the appropriate graphs. A separate spreadsheet may be required for each type of energy used, such as oil, gas, or electricity. A combination might be merited when both gas and oils are used interchangeably in a boiler. In such a case we suggest using a common energy unit for a cost-benefit analysis that can represent most fuel options: the Btu. We have prepared a utility spreadsheet analysis based on the information provided by you or your utility companies. The worksheets are in section A.3, Energy, Waste, and Production Accounting. They show how energy is used and help identify potential energy savings. We use specific terminology and calculations in analyzing and discussing your energy, water, and waste expenses. Energy related terms and calculations are detailed below followed by those for waste and water. Electricity Definitions: Average Energy Cost. The total amount billed for 12 months of energy, divided by the total number of energy units. Each energy type (oil, gas, electricity, propane, etc.) has its own average energy cost. The average cost per energy unit includes the fees, taxes and unit cost. Average Energy Cost = (Total Billed $) ÷ (Total Energy Units) Average Load Factor. The ratio of annual electrical energy use divided by the average kilowatts (kW) and the hours in a year. Average Load Factor = (Total kWh) ÷ (Average kW x 8,760 hrs) Average Load Factor expresses how well a given electrical system uses power. A higher load factor yields lower average energy cost. An example of how load factor applies: A large air compressor has high electric demand for small periods of time and is not a large energy user. It will usually have low load factor and relatively high demand charges. A smaller air compressor that runs for longer periods of time at higher part load efficiency will have higher load factor and lower demand charges. Basic Charge. The fee a utility company can charge each month to cover their administrative, facility, or other fixed costs. Some companies have higher energy or power rates that compensate for no or low basic charge. Energy. The time-rate of work expressed in kWh for electric energy. The common unit is million Btu (MMBtu). For a more complete description, see Power. Energy = Work ÷ Time = (Force x Distance) ÷ Time 41 Incremental Demand Cost. It is the price charged by your utility company for the capacity to meet your power needs at any given time. Peak demand is the highest demand level required over a set period of time and is calculated by continuously monitoring demand levels. Demand is usually billed based on peak power, but charges such as facility charges and other fees billed per kW are also included in the incremental demand cost. If your utility company has stepped demand cost rates, the step with the greatest demand is considered in the incremental demand cost. If your utility company bills one set rate for all power needs, this value is used as the incremental demand cost. Incremental Energy Cost (Electricity). It is cost of a unit of energy, from current use. This cost is usually taken from your utility rate schedule. When all large meters are on the same rate schedule, the incremental energy cost is the cost from the highest energy tier, or tail block. To further clarify this method: if a company is charged $0.05/kWh up to 100,000 kWh, and $0.03/kWh over 100,000 kWh and they are consistently buying over 100,000 kWh each month, any energy savings will be calculated using the $0.03/kWh cost. If your facility has multiple meters on different rate schedules or tariffs, the incremental cost is calculated by adding electrical energy costs and dividing by the total electrical energy use. Incremental Energy Cost = (Total kWh $) ÷ (Total kWh) Minimum Charge. The least amount billed by a utility at the end of the billing period. Power (and Energy). The rate at which energy is used, expressed as the amount of energy use per unit time, and commonly measured in units of watts and horsepower. Power is the term used to describe the capacity the utility company must provide to serve its customers. Power is specified three ways: real, reactive and total power. The following triangle gives the relationship between the three. Total Power (kVA) Reactive Power (kVAR) Ө Real Power (kW) Real power is the time average of the instantaneous product of voltage and current (watts). Apparent power is the product of rms (root mean square) volts and rms amps (volt-amps). Demand. The highest electrical power required by the customer, generally averaged over 15 minute cycling intervals for each month. Demand is usually billed by kW unit. 42 Kilovolt Amperes (kVA). Kilovolt amperes are a measure of the power available before accounting for power factor. See the triangle on the previous page. Power is sometimes billed by kVA. Reactive Power. Reactive power is measured in units of kVAR. Reactive power produces magnetic fields in devices such as motors, transformers, and lighting ballasts that allow work to be done and electrical energy to be used. Kilo Volt Amperes Reactive (kVAR) could occur in an electrical circuit where voltage and current flow are not perfectly synchronized. Electric motors and other devices that use coils of wire to produce magnetic fields usually cause this misalignment of three-phase power. Out-of-phase current flow causes more electrical current to flow in the circuit than is required to supply real power. kVAR is a measure of this additional reactive power. High kVAR can reduce the capacity of lines and transformers to supply kilowatts of real power and therefore cause additional expenses for the electrical service provider. Electric rates may include charges for kVAR that exceed a normal level. These charges allow the supplying utility to recover some of the additional expenses caused by high KVAR conditions, and also encourages customers to correct this problem. Power Factor. The ratio of real power to total power. Power factor is the cosine of angle θ between total power and real power on the power triangle. PF = cos θ = kW ÷ kVA Disadvantages of Low Power Factor • Increases costs for suppliers because more current has to be transmitted requiring greater distribution capacity. This higher cost is directly billed to customers who are metered for reactive power. • Overloads generators, transformers and distribution lines within the plant, resulting in increased voltage drops and power losses. All of which represents waste, inefficiency and wear on electrical equipment. • Reduces available capacity of transformers, circuit breakers and cables, whose capacity depends on the total current. Available capacity falls linearly as the power factor decreases. Low Power Factor Charges Most utilities penalize customers whose power factor is below a set level, typically in the range of 95% - 97%, or kVAR greater than 40% of kW. Improving power factor may reduce both energy and power costs, however these are generally much less than savings from real power penalties enforced by electrical utilities. Energy savings are also difficult to quantify. Therefore in our recommendations, only power factor penalty avoidance savings are included. 43 Improving Power Factor The most practical and economical power factor improvement device is the capacitor. All inductive loads produce inductive reactive power current (lags voltage by a phase angle of 90°). Capacitors, on the other hand, produce capacitive reactive power, which is the opposite of inductive reactive power (current leads…). Current peak occurs before voltage by a phase angle of 90°. By careful selection of capacitance required, it is possible to totally cancel out the inductive reactive power, but in practice it is seldom feasible to correct beyond your utilities’ penalty level (~95% for kVA meters). Improving power factor results in: • Reduced utility penalty charges. • Improved plant efficiency. • Additional equipment on the same line. • Reduced overloading of cables, transformers, and switchgear. • Improved voltage regulation due to reduced line voltage drops and improved starting torque of motors. Power Factor Penalty Utility companies generally calculate monthly power factor two ways. One way is based on meters of reactive energy and real energy. Monthly PF = cos [tan-1 (kVARh ÷ kWh)] The second method is based on reactive power and real power. Monthly PF = cos [tan-1 (kVAR ÷ kW)] Power Factor is often abbreviated as “PF”. Also see the Power Factor definition below. Cost Calculations Annual operating expenses include both demand and energy costs. Demand cost (DC) is calculated as the highest peak demand (D) multiplied by your incremental demand charge and the number of operating months per year: DC = D x demand rate ($/kW·mo) x 12 mo/yr Energy cost (EC) is energy multiplied by your incremental electric rate: EC = E x energy rate ($/kWh) 44 Natural Gas Definitions: Rate Schedules. (Or tariffs) specify billing procedures and set forth costs for each service offered. The state public utility commission approves public utility tariffs. For example: an electric utility company will set a price or schedule of prices for power and energy and specify basic and PF charges. A natural gas utility will specify cost to supply or transport gas and include costs such as price per therm, basic charge, minimum charges and other costs. Current rate schedules can often be found online at the utility company’s website. If you think your facility belongs in a different rate schedule, your utility representative can help you best. Tariff. Another term for rate schedule. Therm. The unit generally used for natural gas (1 therm = 100,000 Btu), but sometimes it is measured in MMBtu. Commodity Rate. The component of the billing rate that represents the company’s annual weighted average commodity cost of natural gas. Transportation. The movement of customer-owned natural gas from the pipeline receipt point(s). Waste and Water Definitions: Average Disposal Cost. The average cost per pickup or ton of waste or other scrap material. This cost is calculated using all of the annual expenses to get a representative cost per unit of disposal. Average Disposal Cost / Ton = (Total Disposal $) ÷ (Total tons removed) Average Disposal Cost / Pickup = (Total Disposal $) ÷ (Total number of pickups) BOD Charge. Charge levied by the sewer/water treatment utility to cover extra costs for high strength wastewater. High strength wastewater requires more intensive treatment by the utility and extra processing due to very low oxygen levels. BOD, biochemical oxygen demand, is a measure of how much oxygen will be used to microbiologically degrade the organic matter in the wastewater stream. State agencies such as a Department of Environmental Quality set BOD and other regulations that wastewater treatment facilities must meet to discharge treated water into nearby waterways. Your treatment facility may have ideas that could help lower the strength of your wastewater. Box Rental Charge. The fee imposed by the waste or recycling utility to cover costs of their receiving containers. Disposal Cost. Incurred by the waste utility for disposing of your waste in a landfill or other facility. These charges increase when hazardous materials are present in the waste. Pickup Costs. The cost charged by the waste utility for each pickup of waste or recycling. This charge is usually applied when the utility is working on an “on call” basis. Pickup costs can also be a flat rate for a certain number of pickups per month. 45 A.2. Energy Conversions An essential component of any energy management program is a continuing account of energy use and its cost. This can be done best by keeping up-to-date graphs of energy consumption and costs on a monthly basis. When utility bills are received, we recommend that energy use be immediately plotted on a graph. A separate graph will be required for each type of energy used, such as oil, gas, or electricity. A combination will be necessary, for example, when both gas and oil are used interchangeably in a boiler. A single energy unit should be used to express the heating values of the various fuel sources so that a meaningful comparison of fuel types and fuel combinations can be made. The energy unit used in this report is the Btu, British Thermal Unit, or million Btu's (MMBtu). The Btu conversion factors and other common nomenclature are: Energy Unit Energy Equivalent 1 kWh 1 MWh 1 cubic foot of natural gas 1 gallon of No. 2 oil (diesel) 1 gallon of No. 6 oil 1 gallon of gasoline 1 gallon of propane 1 pound of dry wood 1 bone dry ton of wood (BDT) 1 unit of wood sawdust (2,244 dry pounds) 1 unit of wood shavings (1,395 dry pounds) 1 unit of locally supplied steam (1 pound) 1 ton of coal 1 MWh 1 therm 1 MMBtu 1 kilowatt 1 horsepower (electric) 1 horsepower (boiler) 1 ton of refrigeration 3,413 3,413,000 1,030 140,000 152,000 128,000 91,600 8,600 17,200,000 19,300,000 12,000,000 954 28,000,000 1,000 100,000 1,000,000 Btu Btu Btu Btu Btu Btu Btu Btu Btu Btu Btu Btu Btu kWh Btu Btu 3,413 2,546 33,478 12,000 Btu/hr Btu/hr Btu/hr Btu/hr 8.33 7.48 1,000 200 pounds gallons gallons ft3 Unit Equivalent 1 gallon of water 1 cubic foot of water 1 kgal 1 unit wood fuel The value of graphs can best be understood by examining those plotted for your company in the Energy Summary. Energy use and costs are presented in the following tables and graphs. From these figures, trends and irregularities in energy usage and costs can be detected and the relative merits of energy conservation can be assessed. 46 A.3. Energy, Waste, and Production Accounting Energy Use Combined Meters / Utilities Month Jul-07 Aug-07 Sep-07 Oct-07 Nov-07 Dec-07 Jan-08 Feb-08 Mar-08 Apr-08 May-08 Jun-08 Totals Avg/Mo Electricity kWh Total $ 154,680 $7,177 189,440 $8,790 163,320 $7,578 172,240 $7,992 173,280 $8,040 141,600 $6,570 147,240 $6,832 181,040 $8,400 153,600 $7,127 160,680 $7,456 170,480 $7,910 164,960 $7,654 1,972,560 $91,527 164,380 $7,627 Steam Gas Therms 455 528 301 1,276 1,351 821 569 1,239 1,145 954 1,287 964 10,890 907 $ $511 $594 $339 $1,434 $1,519 $923 $640 $1,393 $1,287 $1,072 $1,447 $1,083 $12,244 $1,020 lbs 22,100 7,500 16,400 201,500 367,100 751,500 992,700 873,000 334,500 343,600 82,000 75,600 4067500 338958 $ $431 $146 $320 $3,929 $7,158 $14,654 $19,358 $17,024 $6,523 $6,700 $1,599 $1,474 $79,316 $6,610 Totals MMBtu $ 594 $8,119 707 $9,530 603 $8,237 908 $13,355 1,077 $16,718 1,282 $22,148 1,506 $26,830 1,575 $26,816 958 $14,937 972 $15,228 789 $10,956 731 $10,212 11,702 $183,087 975 $15,257 Combined Utility Summary Electricity Incremental Energy Cost Average Energy Cost $0.04640 /kWh $0.04640 /kWh Incremental Steam Cost Steam Energy Cost Natural Gas Incremental gas Cost Average Gas Cost $0.01950 /kWh $0.01950 /kWh Steam 1.1243 /therm 1.1243 /therm $11.24 /MMBtu 47 Electricity Use Month Jul-07 Aug-07 Sep-07 Oct-07 Nov-07 Dec-07 Jan-08 Feb-08 Mar-08 Apr-08 May-08 Jun-08 Totals Avg/Mo kWh 154,680 189,440 163,320 172,240 173,280 141,600 147,240 181,040 153,600 160,680 170,480 164,960 1,972,560 164,380 kWh$ $7,177 $8,790 $7,578 $7,992 $8,040 $6,570 $6,832 $8,400 $7,127 $7,456 $7,910 $7,654 $91,527 $7,627 Total $ $7,177 $8,790 $7,578 $7,992 $8,040 $6,570 $6,832 $8,400 $7,127 $7,456 $7,910 $7,654 $91,527 $7,627 Electric Utility Summary Energy Cost Average Electricity Cos 48 $0.04640 /kWh $0.04640 /kWh Natural Gas Use Month Jul-07 Aug-07 Sep-07 Oct-07 Nov-07 Dec-07 Jan-08 Feb-08 Mar-08 Apr-08 May-08 Jun-08 Totals Avg./Mo Therms 455 528 301 1,276 1,351 821 569 1,239 1,145 954 1,287 964 10,890 907 Therm$ $511 $594 $339 $1,434 $1,519 $923 $640 $1,393 $1,287 $1,072 $1,447 $1,083 $12,244 $1,020 MMBtu 45 53 30 128 135 82 57 124 114 95 129 96 1,089 91 Natural Gas Utility Summary Natural Gas Cost Average Energy Cost $1.12430 /therm $1.12 /therm $11.24 /MMBtu 49 Total$ $511 $594 $339 $1,434 $1,519 $923 $640 $1,393 $1,287 $1,072 $1,447 $1,083 $12,244 $1,020 Steam Use Month lbs Jul-07 22,100 Aug-07 7,500 Sep-07 16,400 Oct-07 201,500 Nov-07 367,100 Dec-07 751,500 Jan-08 992,700 Feb-08 873,000 Mar-08 334,500 Apr-08 343,600 May-08 82,000 Jun-08 75,600 Totals 4,045,400 Avg./Mo 367,764 Steam $ $431 $146 $320 $3,929 $7,158 $14,654 $19,358 $17,024 $6,523 $6,700 $1,599 $1,474 $79,316 $6,610 MMBtu 21 7 16 192 350 717 947 833 319 328 78 72 3880 323 Total $ $431 $146 $320 $3,929 $7,158 $14,654 $19,358 $17,024 $6,523 $6,700 $1,599 $1,474 $79,316 $6,610 Steam Summary Steam Cost Average Steam Cost $0.0195 / lb $0.01961 / lb $20 /MMBtu 50 51 52 53 54 A.4. ENERGY USE SUMMARY & ENERGY ACCOUNTING END USE SUMMARY Average Electricity Cost Average Natural Gas Cost Average Steam Cost $0.04640 /kWh $1.12430 /therm $0.01950 /lb ELECTRICITY MMBtu ENERGY % 1,454 21.6% 616 9.1% 2,202 32.7% 116 1.7% 849 12.6% 523 7.8% 152 2.3% 544 8.1% 275 4.1% 6,732 100.0% COST COST% $19,769 21.6% $8,373 9.1% $29,943 32.7% $1,573 1.7% $11,544 12.6% $7,113 7.8% $2,073 2.3% $7,398 8.1% $3,742 4.1% $91,527 100.0% UNIT therm therm therm MMBtu ENERGY % 950 87.2% 139 12.8% 1,089 100.0% COST COST% $10,681 87.2% $1,563 12.8% $12,244 100.0% HVAC Dishwasher Miscellaneous TOTALS USE UNIT 2,929,681 lbs 100,000 lbs 1,037,819 lbs 4,067,500 lbs MMBtu ENERGY % 2,795 72.0% 95 2.5% 990 25.5% 3,880 100.0% COST COST% $57,129 72.0% $1,950 2.5% $20,237 25.5% $79,316 100.0% ELECTRICITY NATURAL GAS STEAM TOTALS FUEL SUMMARY USE UNIT MMBtu ENERGY % 1,972,560 kWh 6,732 57.5% 10,890 therm 1,089 9.3% 4,067,500 lbs 3,880 33.2% 11,702 100.0% COST COST% $91,527 50.0% $12,244 6.7% $79,316 43.3% $183,087 100.0% Lighting BkStore EquipRoom Bowling Chiller Room Bowling Compressor Room Bowling Air-handling Room Ballroom Maintenance Rooftop Miscellaneous Motors Miscellaneous TOTALS USE UNIT 426,052 kWh 180,456 kWh 645,321 kWh 33,903 kWh 248,784 kWh 153,300 kWh 44,676 kWh 159,432 kWh 80,636 kWh 1,972,560 kWh NATURAL GAS Ovens Miscellaneous TOTALS USE 9,500 1,390 10,890 STEAM 55 56 57 58 APPENDIX B MOTORS B.1. Motor Worksheet Definitions The motor worksheet uses information obtained during the on-site visit to calculate electric motor energy use, as well as energy and cost savings for efficiency improvements. Motor worksheet information is also used for a variety of AR's, including refrigeration, air compressors, and turning off equipment. In addition, the information contained in the worksheet aids in determining an accurate plant energy breakdown. The worksheet calculation methods and symbols are described as follows: B.2. Motor Inventory (Nameplate) The Motor Inventory contains the manufacturer, horsepower, volts, amps and revolutions per minute (rpm), that are read directly from each motor nameplate. Standard NEMA values are used to estimate full load efficiency and power factor. Identification Number (ID#). An identification number is assigned to each motor. Manufacturer. The manufacturer of the motor. Horsepower (Hp). Nameplate horsepower. Volts. Rated voltage for the motor. If the motor can be wired for more than one voltage, the voltage closest to the operating voltage is entered. Amps. The rated full-load amperage of the motor corresponding to the voltage listed above. RPM. Rated full-load RPM. Power Factor (PF). The motor power factor at full load. Power factor is primarily taken from General Electric publications GEP-500H (11/90) and GEP-1087J (1/92). See section B.9 Motor Performance Table for data and other sources. Efficiency (EFF). The present motor efficiency at full load. Motor efficiencies for standard and energy-efficient motors are also taken from General Electric publications GEP-500H (11/90) and GEP-1087J (1/92). See section B.9 Motor Performance Table. Type. The type of motor is described in the table at the bottom of the inventory page. The purpose is to identify standard 900, 1200, 1800, and 3600 rpm motors (Type = 1) that could be replaced with energy-efficient motors. 59 B.3. Motor Applications (Measured Operating Conditions) The Motor Applications page contains application-specific information. The same motor may be used in several applications. This information is used to calculate the annual energy consumption of each application. Application Number (#). A number is assigned to each application described in this section. Area. A brief description of the location of the motor application. Identification Number (ID#). The identification number of the motor used in the application. The worksheet looks up the nameplate information for each motor application in section B.2 Motor Inventory. Use. Each use, such as refrigeration, is given a separate code. This allows the energy use and operating cost for each end use to be summarized in section B.7 Motor Use Summary. Description. A brief description of the motor application. Quantity (Qty). The number of motors in each application of the same horsepower and type. Horsepower (Hp). The horsepower of the motor(s) used in this application is looked up in section B.2 Motor Inventory, based on the motor ID#. Total Horsepower (Hptot). The total horsepower used in the application is the product of the quantity of motors and the motor horsepower. Power Factor (PF). For motors with no power factor correction, the operating power factor of the motor is approximated by the following equation to account for part-load conditions: PF = Nameplate PF x {0.728 + [0.4932 / (FLA%)] - [0.2249 / (FLA%)2]} The power factor correction, enclosed in ({}) brackets, has a minimum allowable value of 0.3 and a maximum value of 1.0 when FLA% is 90% or greater in the worksheet, and is shown as a curve in section B.10. If the motor has been corrected for power factor (PFC = "C"), or the motor is a synchronous type, 0.95 power factor is used. Power Factor Correction (PFC). If a motor has power factor correction capacitors and the amperage has been measured ahead of the capacitors, a "C" is input. Drive (DRV). All motors with standard V-belt drives (b) are considered for replacement with High Torque Drive (HTD) belts and sheaves. HTD Replacements are summarized in Section B.5. Volts. Measured operating voltage. 60 Amps. Measured operating amperage. Use Factor (UF). Use Factor is the percentage of the annual operating hours the motor is actually running. Percent Full Load Amps (FLA%). The measured operating amperage divided by the motor nameplate full load amps. Efficiency (EFF). Present motor efficiency (η0) is looked up in section B.2 Motor Inventory, based on the motor ID#. Demand. The operating power (D) of the motor in kilowatts (kW). If the operating amperage is known, the following equation is used: D = Qty x Volts x Amps x PF x 1.73 / 1,000 If operating amperage is not known, the motor load factor (LF) is estimated depending on motor application at your plant. Motor load was either modeled after similar applications at your plant or derived from averaged application specific data of over 160 previous audits. The operating power is found from D = Qty x LF x (0.746 kW/Hp) x Hp / η0 Load Factor (LF). The operating input power divided by the motor nameplate full-load input power, which is found from LF = (D x η0) / [Hp x (0.746 kW/Hp)] Hours. The annual motor operating hours (H) are entered in section B.7 Motor Use Summary for each use. Energy. The annual energy consumption (E) of the motor in kilowatt-hours (kWh) is calculated by: E = D x H x UF B.4. Motor Use Summary The Motor Use Summary summarizes motor power and energy requirements by end use. B.5. Economics The Economics Table summarizes the electrical energy and demand costs, payback criterion, and motor lifetime. 61 Energy Cost. The electrical energy charge ($/kWh) is taken from your rate schedule. If the energy charge varies seasonally, the average cost is used. Demand Cost. The demand charge ($/kW-Month) is taken from your rate schedule. If the demand charge varies seasonally, the average cost is used. Payback Criterion. Standard motors that are candidates for replacement with energy-efficient motors are listed in section B.3 Motor Efficiency. Motors for which the payback is less than this criterion are included in the total at the bottom of the table and included in the Energy Efficient Motors AR. B.6. Motor Performance Table The Motor Performance Table contains general motor information used in the worksheet. For each motor horsepower, efficiency, motor cost, and power factor for both standard and efficient motors are listed. Information is primarily taken for totally enclosed fan cooled (TEFC) motors from General Electric publications GEP-500H (11/90) and GEP-1087J (1/92). Larger motors that are not available in TEFC configuration are Open Drip Proof (ODP), and are shown in italics. For motors not found in the General Electric publications, the values for efficiency, motor cost, and power factor were taken as averaged values of several motor manufacturers from Motor Master, a database available from Washington State Energy Office. These sections are indicated by shading. B.7. Power Factor Power factor is graphed as a function of operating amperage (FLA%). The curve approximates motor performance data taken from General Electric publication #GEP-500G (3/87). The graph is used to calculate power factor in section B.2 Motor Applications. 62 B.2. Motor Inventory (Nameplate)* # Description 1 Pump 2 Pump 3 Air Compressor 4 Exhaust Fan 5 Fan 6 Pump 7 Pump 8 Pump 9 Pump 10 Pump 11 Pump 12 Pump 13 Pump 14 Air Compressor 15 Fan 16 Air Compressor 17 Pump 18 Pump 19 Pump 20 HRU-1 Supply 21 HRU-2 Supply 22 F2 23 F7 24 Exhaust Fan 25 HRU-1 Exhaust 26 HRU-2 Return 27 Chiller Compressor 28 Refrigerated Panel 29 Panda Cooler 30 Freezer Panel 31 MU Walk In 32 Lounge Blower 33 Ballroom Blower 34 Panda Freezer 35 Fan 36 Fan 37 Chiller 38 Chiller 39 Bowling AHU Hp Volts Amps RPM 0.5 208 2.6 1800 0.5 208 2.6 1800 0.75 208 3.9 1800 0.75 208 3.9 1800 1 208 4.7 1800 1.5 208 5.7 1800 1.5 208 5.7 1800 1.5 208 5.7 1800 1.5 208 5.7 1800 1.5 208 5.7 1800 1.5 208 5.7 1800 1.5 208 5.7 1800 1.5 208 5.7 1800 3 208 10.9 1800 3 208 10.9 1800 5 208 16.6 1800 5 208 16.6 1800 5 208 16.6 1800 5 208 16.6 1800 5 208 16.6 1800 5 208 16.6 1800 7.5 208 27.0 1800 7.5 208 27.0 1800 7.5 208 27.0 1800 7.5 208 27.0 1800 7.5 208 27.0 1800 10 208 34.1 1800 10 208 34.1 1800 15 208 48.9 1800 15 208 48.9 1800 15 208 20.0 1800 15 208 52.0 1180 15 208 48.9 1800 20 208 65.0 1800 25 208 80.9 1800 25 208 80.9 1800 35 208 129.0 1800 40 208 129.0 1800 5 460 6.4 1800 + Type Code 1=Standard Efficiency 2=High Efficiency C=Composite DC=Direct Current RPM=Not 900, 1200, 1800, or 3600 RPM V=Standard V-belt *Note: Some Nameplate Data May Be Estimated PF% 63% 63% 60% 60% 70% 79% 79% 79% 79% 79% 79% 79% 79% 78% 78% 78% 78% 78% 78% 78% 78% 82% 82% 82% 82% 82% 74% 74% 82% 82% 82% 80% 82% 83% 86% 86% 86% 83% 78% TS=Two Speed F=Fractional Horsepower G=Gear Motor H=Hermetic ASD=Adjustable Speed Drive 63 EFF% 72% 72% 76% 76% 77% 84% 84% 84% 84% 84% 84% 84% 84% 83% 83% 88% 88% 88% 88% 88% 88% 86% 86% 86% 86% 86% 90% 90% 91% 91% 91% 88% 91% 91% 92% 92% 90% 93% 88% Frame Type+ 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 284T 1 1 1 1 1 1 1 1 HD=Heavy Duty O=Oversize (>500hp) SY=Synchronous U=Unknown SP=Single Phase B.3. Motor Applications (Measured Operating Conditions) # 1 2 6 7 16 22 23 27 8 9 17 18 19 28 29 30 31 34 37 38 3 10 11 12 13 14 15 35 36 5 32 33 4 24 20 21 39 25 26 Area BkStore EquipRoom BkStore EquipRoom BkStore EquipRoom BkStore EquipRoom BkStore EquipRoom BkStore EquipRoom BkStore EquipRoom Miscellaneous Bowling Chiller Room Bowling Chiller Room Bowling Chiller Room Bowling Chiller Room Bowling Chiller Room Bowling Chiller Room Bowling Chiller Room Bowling Chiller Room Bowling Chiller Room Bowling Chiller Room BkStore EquipRoom Bowling Chiller Room Bowling Compressor Room Bowling Compressor Room Bowling Compressor Room Bowling Compressor Room Bowling Compressor Room Bowling Compressor Room Bowling Compressor Room Bowling Air-handling Room Bowling Air-handling Room Elevator Fan Room Ballroom Maintenance Ballroom Maintenance Rooftop Rooftop Miscellaneous Miscellaneous Miscellaneous Miscellaneous Miscellaneous Use 1 1 1 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 3 3 3 3 3 3 3 4 4 5 6 6 7 7 8 8 8 8 8 Description Pump Pump Pump Pump AirCompressor F2 F7 Chiller Compressor Pump Pump Pump Pump Pump Referigerated Panel Panda Cooler Freezer Panel MU Walk In Panda Freezer Chiller Chiller Air Compressor Pump Pump Pump Pump Air Compressor Fan Fan Fan Fan Lounge Blower Ballroom Blower Exhaust Fan Exhaust Fan HRU-1 Supply HRU-2 Supply Bowling AHU HRU-1 Exhaust HRU-2 Return Qty Hp Hptot PF% DRV 0 0.5 0 63.0% D 0 0.5 0 63.0% D 0 1.5 0 79.0% D 0 1.5 0 79.0% D 0 5 0 78.0% F 1 7.5 7.5 82.0% F 1 7.5 7.5 82.0% F 1 10 10 74.0% D 0 1.5 0 79.0% D 0 1.5 0 79.0% D 0 5 0 78.0% D 1 5 5 78.0% D 1 5 5 78.0% D 1 10 10 74.0% D 1 15 15 82.0% D 1 15 15 82.0% D 1 15 15 82.0% D 1 20 20 83.0% D 1 35 35 86.0% D 1 40 40 83.0% D 0 0.75 0 60.0% F 0 1.5 0 79.0% D 0 1.5 0 79.0% D 0 1.5 0 79.0% D 0 1.5 0 79.0% D 0 3 0 78.0% F 0 3 0 78.0% F 1 25 25 86.0% F 1 25 25 86.0% F 0 1 0 70.0% F 1 15 15 80.0% F 1 15 15 82.0% F 0 0.75 0 60.0% F 1 7.5 7.5 82.0% F 1 5 5 78.0% 1 5 5 78.0% 1 5 5 78.0% 1 7.5 7.5 82.0% 1 7.5 7.5 82.0% 64 UF% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 80% 80% 80% 80% 80% 66% 66% 10% 60% 60% 40% 40% 40% 66% 100% 100% 0% 100% 100% 100% 100% 100% 100% 100% 100% 100% EFF% 72.0% 72.0% 84.0% 84.0% 87.5% 86.0% 86.0% 89.5% 84.0% 84.0% 87.5% 87.5% 87.5% 89.5% 91.0% 91.0% 91.0% 91.0% 90.0% 93.0% 76.0% 84.0% 84.0% 84.0% 84.0% 83.0% 83.0% 91.7% 91.7% 77.0% 88.0% 91.0% 76.0% 86.0% 87.5% 87.5% 87.5% 86.0% 86.0% Demand kW 0.4 0.4 0.9 0.9 3.0 4.6 4.6 5.8 0.9 0.9 3.0 3.0 3.0 5.8 8.6 8.6 8.6 11.5 20.3 22.5 0.5 0.9 0.9 0.9 0.9 1.9 1.9 14.2 14.2 0.7 8.9 8.6 0.5 4.6 3.0 3.0 3.0 4.6 4.6 Energy LF Hours kWh 70% 8,760 3,504 70% 8,760 3,504 70% 8,760 7,884 70% 8,760 7,884 70% 8,760 26,280 70% 8,760 40,296 70% 8,760 40,296 70% 8,760 50,808 70% 8,760 7,884 70% 8,760 7,884 70% 8,760 26,280 70% 8,760 26,280 70% 8,760 26,280 70% 7,008 40,646 70% 7,008 60,269 70% 7,008 60,269 70% 7,008 60,269 70% 7,008 80,592 70% 5,810 117,943 70% 5,810 130,725 70% 876 438 70% 5,256 4,730 70% 5,256 4,730 70% 3,504 3,154 70% 3,504 3,154 70% 3,504 6,658 70% 5,810 11,039 70% 8,760 124,392 70% 8,760 124,392 70% 0 0 70% 8,760 77,964 70% 8,760 75,336 70% 8,760 4,380 70% 8,760 40,296 70% 8,760 26,280 70% 8,760 26,280 70% 8,760 26,280 70% 8,760 40,296 70% 8,760 40,296 B.4. Motor Use Summary Use 1 2 3 4 5 6 7 8 Total Area Bk. Store Equipment Room Bowling Chiller Room Bowling Compressor Room Bowling Air-handling Room Elevator Fan Room Ballroom Maintenance Rooftop Miscellaneous Hours Qty Hp 8,760 8 34 8,760 12 168 8,760 7 13 8,760 2 50 8,760 1 1 8,760 2 30 8,760 2 8 8,760 5 30 39 334 kW 20.6 96.7 7.9 28.4 0.7 17.5 5.1 18.2 195 kWh kWh% 180,456 12.3% 645,321 44.0% 33,903 2.3% 248,784 17.0% 0 0.0% 153,300 10.5% 44,676 3.0% 159,432 10.9% 1,465,872 100.0% B.5. Economics Energy Cost: Motor Payback Criterion: High Torque Drive Payback Criterion: $0.0464 /kWh 10 years 10 years 65 B.6 Motor Performance Table 900 RPM Horsepower (HP) 1 1.5 2 3 5 7.5 10 15 20 25 30 40 50 60 75 100 125 150 200 250 300 350 400 450 500 Standard 69.4 73.0 76.4 79.3 82.0 82.8 85.4 85.8 88.0 87.8 87.5 89.5 88.5 91.0 90.2 91.7 92.4 92.4 94.1 94.5 94.5 93.6 93.6 93.6 Motor Efficiency Efficient 75.5 80.0 85.5 86.5 85.5 86.5 91.0 91.0 91.7 91.7 93.6 93.0 93.6 93.6 94.1 94.1 94.5 94.5 95.0 95.0 95.0 95.0 95.0 95.0 Increase 6.1 7.0 9.1 7.2 3.5 3.7 5.6 5.2 3.7 3.9 6.1 3.5 5.1 2.6 3.9 2.4 2.1 2.1 0.9 0.5 0.5 1.4 1.4 1.4 Standard $283 $343 $459 $597 $824 $1,049 $1,243 $1,633 $1,968 $2,331 $2,746 $3,401 $4,052 $4,699 $6,258 $7,907 $9,193 $10,371 13443.0 15370.0 17411.0 10493.0 11692.0 12622.0 1200 RPM Motor Cost Efficient $359 $434 $581 $755 $1,043 $1,327 $1,573 $2,067 $2,491 $2,950 $3,475 $4,305 $5,128 $5,947 $7,920 $10,007 $11,635 $13,126 15989.0 18213.0 20633.0 12922.0 14251.0 15593.0 Increase $76 $91 $122 $158 $219 $278 $330 $434 $523 $619 $729 $904 $1,076 $1,248 $1,662 $2,100 $2,442 $2,755 2546.0 2843.0 3222.0 2429.0 2559.0 2971.0 Power Factor Standard Efficient 59.5 62.0 62.0 61.7 54.0 61.7 62.5 66.4 60.0 67.3 62.0 69.3 78.0 77.2 78.0 75.5 77.5 78.6 78.0 78.3 80.0 76.5 80.0 75.5 76.5 84.0 80.5 83.5 80.0 85.0 78.5 84.0 78.0 82.5 77.5 82.5 86.5 87.0 86.5 84.0 87.0 84.0 81.0 80.5 81.5 84.0 81.0 84.5 Standard 75.5 75.5 80.0 85.5 84.0 86.8 87.5 88.5 90.2 88.5 89.5 89.5 91.0 91.0 91.0 92.4 92.4 93.0 94.1 94.3 95.0 95.0 95.0 94.5 94.5 Motor Efficiency Efficient 82.1 87.5 87.5 89.5 89.5 91.7 91.7 91.7 92.4 92.4 93.0 93.6 93.6 94.1 95.0 95.0 95.0 95.8 95.4 95.4 95.4 95.8 95.8 96.2 96.2 Increase 6.6 12.0 7.5 4.0 5.5 4.9 4.2 3.2 2.2 3.9 3.5 4.1 2.6 3.1 4.0 2.6 2.6 2.8 1.3 1.1 0.4 0.8 0.8 1.7 1.7 1800 RPM Horsepower (HP) 1 1.5 2 3 5 7.5 10 15 20 25 30 40 50 60 75 100 125 150 200 250 300 350 400 450 500 Standard 72.0 77.0 80.0 82.5 84.0 86.5 87.5 87.5 89.5 90.2 91.0 90.2 91.7 91.7 91.7 91.7 92.4 93.0 94.1 93.6 94.1 94.5 94.5 95.0 94.5 Motor Efficiency Efficient 84.3 85.4 85.2 89.5 90.2 91.7 91.7 92.4 93.0 93.6 93.6 94.1 94.1 95.0 95.4 95.4 95.4 95.8 95.8 96.2 95.8 95.8 95.8 95.8 95.8 *Sources: Unless otherwise noted, all data is from General publications GEP-500H (11/90), and GEP-1087J (1/92). Increase 12.3 8.4 5.2 7.0 6.2 5.2 4.2 4.9 3.5 3.4 2.6 3.9 2.4 3.3 3.7 3.7 3.0 2.8 1.7 2.6 1.7 1.3 1.3 0.8 1.3 Standard $191 $209 $219 $197 $229 $329 $409 $541 $683 $820 $996 $1,280 $1,658 $2,489 $3,182 $3,837 $4,950 $6,021 $7,285 $8,157 10084.0 11574.0 13528.0 17016.0 10019.0 Standard $241 $193 $213 $283 $407 $550 $701 $946 $1,150 $1,396 $1,704 $2,229 $2,603 $3,008 $3,615 $5,088 $6,191 $6,818 $9,524 12140.0 14380.0 16692.0 18960.0 11465.0 12626.0 Motor Cost Efficient $302 $253 $280 $373 $548 $740 $869 $1,153 $1,403 $1,703 $1,952 $2,770 $3,232 $3,826 $4,575 $6,405 $7,371 $8,606 $11,733 14386.0 17042.0 19780.0 22470.0 14119.0 15549.0 Increase $61 $60 $67 $90 $141 $190 $168 $207 $253 $307 $248 $541 $629 $818 $960 $1,317 $1,180 $1,788 $2,209 2246.0 2662.0 3088.0 3510.0 2654.0 2923.0 Power Factor Standard Efficient 60.5 65.9 77.5 72.0 74.5 74.0 74.5 75.5 78.5 76.0 88.0 72.0 84.5 71.5 82.5 76.5 85.5 76.0 83.5 81.0 82.5 83.5 83.5 85.5 87.0 85.5 81.0 85.5 79.0 86.0 82.5 89.0 84.5 88.5 87.9 86.0 87.8 86.5 85.0 89.0 88.5 89.5 89.0 89.0 89.5 87.5 87.5 87.0 87.0 88.0 Increase $17 $193 $129 $64 $79 $102 $114 $165 $122 $166 $267 $330 $298 $224 $660 $576 $679 $1,145 $1,837 $3,037 2185.0 4638.0 2331.0 3458.0 2535.0 Power Factor Standard Efficient 81.6 81.8 86.0 82.4 87.5 89.9 81.0 87.0 82.0 88.0 82.0 88.5 83.5 88.5 83.0 88.5 90.0 90.0 90.5 91.0 91.5 91.0 85.5 92.0 85.0 92.0 90.0 92.0 91.5 92.0 89.0 91.5 92.5 93.5 92.0 93.5 93.9 94.0 92.5 89.5 92.0 93.0 93.0 93.0 93.0 93.5 93.5 93.0 90.0 93.0 3600 RPM Motor Cost Efficient $237 $262 $274 $262 $299 $431 $520 $695 $845 $1,028 $1,216 $1,560 $1,921 $2,856 $3,680 $4,517 $6,354 $7,415 $8,913 $11,181 12257.0 14068.0 16113.0 19023.0 12339.0 Increase $46 $53 $55 $65 $70 $102 $111 $154 $162 $208 $220 $280 $263 $367 $498 $680 $1,404 $1,394 $1,628 $3,024 2173.0 2494.0 2585.0 2007.0 2320.0 Power Factor Standard Efficient 72.9 76.0 74.2 78.5 78.5 86.5 79.0 80.0 84.0 83.0 83.0 82.5 85.0 81.0 83.0 81.5 84.5 82.0 85.0 83.5 83.0 83.0 80.0 87.5 85.5 86.5 82.5 85.5 83.5 84.5 87.0 85.0 84.5 89.0 86.5 88.0 89.5 90.0 88.5 83.0 90.0 84.0 90.5 90.5 91.0 91.0 91.0 91.0 89.0 90.0 Standard 74.0 80.0 81.5 82.5 84.0 86.5 87.5 87.5 87.5 88.5 89.5 88.5 89.5 89.5 91.0 90.2 91.0 91.7 93.0 93.0 91.0 91.7 91.7 93.0 94.1 Motor Efficiency Efficient 77.4 84.0 85.2 88.5 89.5 91.7 91.7 91.7 92.4 92.4 92.4 93.6 93.0 94.1 94.5 94.1 94.5 94.5 95.0 95.4 95.4 95.4 95.4 95.4 95.4 Price From Motor Master, Washington State Energy Office. Efficiency From Motor Master, Washington State Energy Office. Averaged Data. 66 Increase 3.4 4.0 3.7 6.0 5.5 5.2 4.2 4.2 4.9 3.9 2.9 5.1 3.5 4.6 3.5 3.9 3.5 2.8 2.0 2.4 4.4 3.7 3.7 2.4 1.3 Standard 256.0 $149 $173 $203 $251 $329 $395 $533 $719 $883 $974 $1,278 $1,772 $2,594 $3,089 $4,167 $5,809 $6,958 $8,695 $10,246 13351.0 15335.0 17948.0 18692.0 10947.0 Motor Cost Efficient 273.0 342.0 302.0 $267 $330 $431 $509 $698 $841 $1,049 $1,241 $1,608 $2,070 $2,818 $3,749 $4,743 $6,488 $8,103 $10,532 $13,283 15536.0 19973.0 20279.0 22150.0 13482.0 Open Drip Proof (ODP) Totaly Enclosed Fan Cooled (TEFC) 67 APPENDIX C LIGHTING C.1 Lighting Worksheet Definitions The following lighting inventory and any lighting worksheets contained in the report use information obtained during the on-site visit to determine any potential energy savings related to lighting improvements. In all cases the value in the Savings column is the existing value less the proposed value. The terminology and calculations are described as follows: PLANT Building. A description of the building if the plant includes several buildings. Area: The lighting calculations may refer to a specific location within the building. Recommended Footcandles. The recommended footcandle levels come from the Illuminating Engineering Society (IES) Lighting Handbook. Average Demand Cost (D$). The demand cost ($/kW-month) is taken from the appropriate rate schedule of your utility. Winter and summer rates are averaged, if necessary. Average Energy Cost (E$). The energy cost ($/kWh) is taken from the appropriate rate schedule of your utility for the least expensive energy block. Winter and summer rates are averaged, if necessary. Labor Cost ($/H). The cost of labor is estimated for operating and installation cost calculations. FIXTURES Description (FID). Fixture type, size, manufacturer, or catalog number may be included here. Quantity (F#). The number of fixtures in the area recorded during the site visit. Operating Hours (H). The number of hours which the lighting fixtures operate each year. Use Factor (UF). The fraction of fixtures that are used multiplied by the fraction of operating hours (H) that the lights are on. Lamps/Fixture (L/F). The number of lamps in each fixture. Ballasts/Fixture (B/F). The number of ballasts in each discharge fixture. 68 Cost (FC). The cost of the existing and proposed fixtures can be compared when modifying or replacing fixtures. LAMPS Description (LID). Lamp type, size, manufacturer, or catalog number may be included here. Quantity (L#). The number of lamps can be calculated from the number of fixtures and the number of lamps per fixture: L# = F# x L/F Life (LL). Lamp life is defined as the number of operating hours after which half the original lamps will fail. The life recorded here is based on 3 operating hours per start. This provides a more conservative estimate of lamp life than using longer hours per start. Replacement Fraction (Lf). The fraction of lamps that normally can be expected to burn out during a year can be calculated from the operating hours, the use factor, and the lamp life: Lf = H x UF / LL Watts / Lamp (W/L). The rated lamp power does not include any ballast power, which is included in the Ballasts section. Lumens (LM). Lamp output is measured in lumens. Lumens are averaged over lamp life because lamp output decreases with time. Cost (C/L). The retail cost per lamp is entered here. BALLASTS This section applies only to discharge lamps with ballasts. This section will be blank for incandescent lamps. Description (BID). Additional information such as type, size, manufacturer, or catalog number may be included here. Quantity (B#). The number of ballasts can be calculated from the number of fixtures and the number of ballasts per fixture: B# = F# x B/F 69 Life (BL). Ballast life is determined from manufacturer's data. A life of 87,600 hours for a standard ballast and 131,400 hours for an efficient ballast is used in the calculations. Replacement Fraction (Bf). The fraction of ballasts normally expected to burn out during a year can be calculated from the operating hours, the use factor, and the ballast life: Bf = H x UF / BL Input Watts (IW). Ballast catalogs specify ballast input watts that include lamp power. The input wattage varies for different combinations of lamps and ballasts. Cost (BC). The retail ballast cost is entered here. POWER AND ENERGY Total Power (P). For incandescent lamps total power is the product of the number of lamps and the watts per lamp. P = L# x W/L (Incandescent Lamps) For discharge lamps total power is the product of the ballast input watts and the number of ballasts: P = B# x IW (Discharge Lamps) Energy Use (E). The annual energy use is the product of the total power, the use factor, and the annual operating hours: E = P x UF x H / (1,000 watts/kilowatt) LIGHT LEVEL CHECK Total Lumens (TLM). The existing and proposed lumen levels are summed for all lamps. TLM = L# x LM Footcandles (FC). Light is measured in units of footcandles. The existing footcandle level (FC0) is measured, while the proposed level (FC1) is determined from the ratio of the proposed total lumens (TLM1) to existing total lumens (TLM0) times the existing footcandle level. FC1 = FC0 x (TLM1 / TLM0) The proposed footcandle level can then be compared to both the existing and the recommended levels to determine if there will be adequate light for the work space. 70 Lumens / Watt (LM/W). The total lamp output in lumens divided by the total power is a measure of lighting efficiency. LM/W = TLM / P ANNUAL OPERATING COST Power Cost (PC). The annual demand cost is the total power times the average monthly demand cost from the worksheet times 12 months per year: PC = P x D$ x 12 months/year Energy Cost (EC). The annual energy cost is the energy use times the electricity cost from your utility rate schedule: EC = E x E$ Lamp O&M Cost (LOM). Operation and maintenance costs are the sum of lamp and labor costs for replacing the fraction of lamps (L# x Lf) that burn out each year. LOM = L# x Lf x [LC + (0.166 hours x $/H)] We assume that two people can replace a lamp and clean the fixture and lens in about five minutes (0.166 man-hours/lamp), replacing lamps as they burn out. Ballast O&M Cost (BOM). Operation and maintenance costs are the sum of ballast (BC) and labor costs ($/H) for replacing the fraction of ballasts (B# x Bf) that burn out each year. BOM = B# x Bf x [BC + (0.5 hours x $/H)] We assume that one person can replace a ballast in about thirty minutes (0.5 man-hours/ballast), replacing ballasts as they burn out. Total Operating Cost (OC). The sum of the annual power and energy costs and lamp and ballast O&M costs. OC = PC + EC + LOM + BOM 71 IMPLEMENTATION COST The implementation costs depend on whether refixturing, group relamping, or spot replacing of lamps and ballasts is recommended. Refixturing Materials: The cost is the cost per fixture (C/F) times the number of fixtures (F#) plus the lamp cost (LC) times the number of lamps (L#). M$ = F# x (C/F) + L# x C/L Labor: The labor cost includes the removal of the existing fixtures and the installation of the recommended fixtures. Group Relamping Materials: When replacing all lamps at one time (group relamping), the cost of materials can be found from M$ = L# x C/L Labor: We estimate the labor cost for group relamping to be one half the cost of replacing each lamp as it burns out. We assume that two people can replace two lamps and clean the fixture and lens in about 5 minutes (0.083 man-hours/lamp, H/L). Because relamping does not require a licensed electrician, the labor rate for relamping is often lower than the labor rate for fixture replacement. To calculate the total labor cost for group lamp replacement we calculate the labor cost of group replacing all of the lamps. L$GROUP = L# x H/L x $/H Spot Replacement of Lamps & Ballasts Materials: When replacing lamps only as they burn out (spot relamping), we use the cost difference (LC1 - LC0) between standard and energy-efficient lamps for all lamps. M$ = L# x (LC1 - LC0) When replacing ballasts only as they burn out (spot reballasting), we use the cost difference (BC1 - BC0) between standard and energy-efficient ballasts for all ballasts. M$ = B# x (BC1 - BC0) Labor: There is no additional labor cost. 72 Total Cost (IC). Total implementation cost is the sum of materials and labor cost IC = M$ + L$ SIMPLE PAYBACK. The simple payback (SP) is calculated on each lighting worksheet. SP = IC / OC 73 C.2 LIGHTING INVENTORY & ENERGY CONSUMPTION CODE Area Description 101 Java Stop HF20 101 Java Stop 102 Office 102A Presidents Office 102A Presidents Office 103 Office 103A Vestibule 104A Work Area 104A WorkArea 104B Office 104B Office 104C Office 105 Meeting Room 105 Meeting Room 105 Meeting Room 105Meeting Room 106 Meeting Room 106 Meeting Room 106 Meeting Room 106 Meeting Room 106A Custodial 106A Custodial 108 Catering 108 Catering 109A Banquet Room 109A Banquet Room 109B Banquet Room 109B Banquet Room 109C Banquet Room 109C Banquet Room 109D Banquet Room 109D Banquet Room 109E Banquet Room 109E Banquet Room 110 Meeting 110 Meeting 111 Office 111 Office 111A Office Manager 112 Office 112A Office 112B Office 112C Vault 112D Office 115 Student Lounge 115 Student Lounge 115 Student Lounge 115 Student Lounge 115A Music Room 115A Music Room 115A Music Room 115B Quiet Room 115B Quiet Room 115B Quiet Room 116 Womens Restroom 116 Womens Restroom 20 Shop Office 201 Storage 203 Meeting Room 203 Meeting Room 204 Office 207 Meeting Room 207 Meeting Room 208 Meeting Room 208 Meeting Room 20A Shop 210 Meeting Room CF13 OFT8‐1 OFT8‐1 IF60 CF9 OFT8‐1 IF60 OFT8‐1 OFT8‐1 IF60 OFT8‐1 CF9 CF9 CF9 CF13 CF13 IF60 CF9 IF60 IF60 OFT8‐1 OFT8‐1 OFT8‐4 CF9 OFT8‐1 OFT8‐1 CF9 OFT8‐1 CF9 CF9 OFT8‐1 CF9 OFT8‐1 HF20 OFT8‐1 OFT8‐1 IF60 OFT8‐1 OFT8‐1 OFT8‐1 OFT8‐1 OFT8‐1 OFT8‐1 IF60 CF9 IF60 IF60 IF60 IF60 IF60 OFT8‐1 IF60 IF60 WLT8‐1 WLT8‐1 OFT8‐1 OFT8‐1 OFT8‐1 IF60 OFT8‐1 OFT8‐1 IF60 HF20 OFT8‐1 OFT8‐1 OFT8‐1 20 Watt Halogens 13 Watt CF 4 Ft T8 Elec. 4 Ft T8 Elec. 60 Watt Incand. 9 Watt CF 4 Ft T8 Elec. 60 Watt Incand. 4 Ft T8 Elec. 4 Ft T8 Elec. 60 Watt Incand. 4 Ft T8 Elec. 9 Watt CF 9 Watt CF 9 Watt CF 13 Watt CF 13 Watt CF 60 Watt Incand. 9 Watt CF 60 Watt Incand. 60 Watt Incand. 4 Ft T8 Elec. 4 Ft T8 Elec. U‐Bent T8 Elec. 9 Watt CF 4 Ft T8 Elec. 4 Ft T8 Elec. 9 Watt CF 4 Ft T8 Elec. 9 Watt CF 9 Watt CF 4 Ft T8 Elec. 9 Watt CF 4 Ft T8 Elec. 20 Watt Halogens 4 Ft T8 Elec. 4 Ft T8 Elec. 60 Watt Incand. 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. 60 Watt Incand. 9 Watt CF 60 Watt Incand. 60 Watt Incand. 60 Watt Incand. 60 Watt Incand. 60 Watt Incand. 4 Ft T8 Elec. 60 Watt Incand. 60 Watt Incand. 4 Ft Elec. Wet/Dust 4 Ft Elec. Wet/Dust 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. 60 Watt Incand. 4 Ft T8 Elec. 4 Ft T8 Elec. 60 Watt Incand. 20 Watt Halogens 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. FC 10 10 74 Qty Fixtures 25 9 6 6 1 4 4 2 20 4 1 6 4 5 12 6 6 1 4 2 1 1 4 8 12 18 6 4 6 4 4 6 12 18 6 8 4 1 8 20 7 8 4 12 8 11 32 21 4 16 2 1 18 9 4 28 30 4 48 1 8 12 1 4 48 66 8 Lamps/ Fixture Ballasts/ Fixture 1 1 2 2 1 1 2 1 2 2 1 2 1 1 1 1 1 1 1 1 1 2 2 2 1 2 2 1 2 1 1 2 1 2 1 2 2 1 2 2 2 2 2 2 1 1 1 1 1 1 1 2 1 1 2 2 2 2 2 1 2 2 1 1 2 2 2 Watts/ Lamp 0 0 1 1 0 0 1 0 1 1 0 1 0 0 0 0 0 0 0 0 0 1 1 1 0 1 1 0 1 0 0 1 0 1 0 1 1 0 1 1 1 1 1 1 0 0 0 0 0 0 0 1 0 0 1 1 1 1 1 0 1 1 0 0 1 1 1 20 13 32 32 60 9 32 60 32 32 60 32 9 9 9 13 13 60 9 60 60 32 32 32 9 32 32 9 32 9 9 32 9 32 20 32 32 60 32 32 32 32 32 32 60 9 60 60 60 60 60 32 60 60 32 32 32 32 32 60 32 32 60 20 32 32 32 Input Watts 0 0 62 62 0 0 62 0 62 62 0 62 0 0 0 0 0 0 0 0 0 62 62 62 0 62 62 0 62 0 0 62 0 62 0 62 62 0 62 62 62 62 62 62 0 0 0 0 0 0 0 62 0 0 62 62 62 62 62 0 62 62 0 0 62 62 62 Output Factor 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% Hr/Yr 5,100 5,100 3,060 3,060 3,060 3,060 5,100 2,040 2,040 3,060 3,060 3,060 3,060 3,060 3,060 3,060 3,060 3,060 3,060 3,060 1,275 1,275 3,060 3,060 1,275 1,275 1,275 1,275 1,275 1,275 1,275 1,275 1,275 1,275 3,060 3,060 3,060 3,060 3,060 3,060 3,060 3,060 1,275 3,060 5,100 5,100 5,100 5,100 3,060 3,060 3,060 5,100 5,100 5,100 5,100 5,100 3,060 1,275 3,060 3,060 3,060 3,060 3,060 3,060 3,060 5,100 3,060 kW kWh 0.5 0.1 0.4 0.4 0.1 0 0.2 0.1 1.2 0.2 0.1 0.4 0 0 0.1 0.1 0.1 0.1 0 0.1 0.1 0.1 0.2 0.5 0.1 1.1 0.4 0 0.4 0 0 0.4 0.1 1.1 0.1 0.5 0.2 0.1 0.5 1.2 0.4 0.5 0.2 0.7 0.5 0.1 1.9 1.3 0.2 1 0.1 0.1 1.1 0.5 0.2 1.7 1.9 0.2 3 0.1 0.5 0.7 0.1 0.1 3 4.1 0.5 2,550 510 1,224 1,224 306 0 1,020 204 2,448 612 306 1,224 0 0 306 306 306 306 0 306 128 128 612 1,530 128 1,403 510 0 510 0 0 510 128 1,403 306 1,530 612 306 1,530 3,672 1,224 1,530 255 2,142 2,550 510 9,690 6,630 612 3,060 306 510 5,610 2,550 1,020 8,670 5,814 255 9,180 306 1,530 2,142 306 306 9,180 20,910 1,530 211 Meeting Room 211 Meeting Room 211 Meeting Room 212 Meeting Room 213 Meeting Room 214 Office 214 Office 215 Office 217 Office 218 Office 219 Womens Restroom 22 Womens Restroom 22 Womens Restroom 220A Custodial Closet 222 Council Room 222 Council Room 222 Council Room 226 Womens Restroom 226 Womens Restroom 23B Storage Closet 24 Storage, Ballroom Stage 24A Light Storage, Ballroom Stage 24B Storage Ballrom Stage 24C Storage, Custodial, Ballroom 24D, Storage, Custodial Ballroom 27C Storage 28 Storage 28A Storage 28B Storage Closet 28D Stoarge 29 West Ballroom 29A Piano Practice Room 29B Piano Practice Room 29C Piano Practice Room 30 Kitchen 31 Hall From Loading Dock 31B Custodial Supervisor Office 31C Freezer 31D Cooler 32 Storage 32 Storage 32A Mechanical Room 34 Storage 35 Lounge 35 Lounge 36 Locker 37 Storage 38 Closet H10 Hall, Jefferson Entry H109 Hall, Banquet Rooms H109 Hall, Banquet Rooms H11 Hall, Bookstore to Ballroom H11 Hall, Bookstore to Ballroom H112 Hall, MU Business Office H12 Hall, to Rec Center H14 West Ballroom Exit H201 Balcony V10, Vestibule, ATM, Jefferson Entry V116 Vestibule, Vending/Womens Restroom Bookstore Lower Bookstore Lower Bookstore Upper Bookstore Upper Bookstore To Mu Mesanine Hallway and Lounge Bites Mesanine Hallway Mesanine Lounge Commons Commons Commons Ballroom 2nd floor Hallway Totals for Lighting Inventory CF13 OFT8‐1 CF13 CF9 OFT8‐1 IF60 OFT8‐1 OFT8‐1 OFT8‐1 OFT8‐1 WLT8‐1 CF13 OFT8‐1 IF40 OFT8‐1 CF13 CF13 OFT8‐1 CF13 OFT8‐1 OFT8‐1 CF13 OFT8‐1 OFT8‐1 OFT8‐1 CF13 OFT8‐1 CF13 CF13 CF13 OFT8‐1 OFT8‐1 OFT8‐1 OFT8‐1 OFT8‐1 OFT8‐1 OFT8‐1 CF13 CF13 OFT8‐1 OFT8‐1 OFT8‐1 OFT8‐1 OFT8‐1 CF13 OFT8‐1 CF13 CF13 OFT8‐1 CF13 CF18 OFT8‐1 OFT8‐4 OFT8‐1 OFT8‐1 OFT8‐1 CF13 OFT8‐1 OFT8‐1 OFT8‐2 OFT8‐1 OFT8‐4 OFT8‐1 CF9 CF13‐2 OFT8‐1 CF9 CF9 CF13‐2 CF13‐3 CF13 HF450 OFT8‐1 13 Watt CF 4 Ft T8 Elec. 13 Watt CF 9 Watt CF 4 Ft T8 Elec. 60 Watt Incand. 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft Elec. Wet/Dust 13 Watt CF 4 Ft T8 Elec. 40 Watt Incand. 4 Ft T8 Elec. 13 Watt CF 13 Watt CF 4 Ft T8 Elec. 13 Watt CF 4 Ft T8 Elec. 4 Ft T8 Elec. 13 Watt CF 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. 13 Watt CF 4 Ft T8 Elec. 13 Watt CF 13 Watt CF 13 Watt CF 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. 13 Watt CF 13 Watt CF 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. 13 Watt CF 4 Ft T8 Elec. 13 Watt CF 13 Watt CF 4 Ft T8 Elec. 13 Watt CF 18 Watt CF 4 Ft T8 Elec. U‐Bent T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. 13 Watt CF 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. 4 Ft T8 Elec. U‐Bent T8 Elec. 4 Ft T8 Elec. 9 Watt CF 13 Watt CF 4 Ft T8 Elec. 9 Watt CF 9 Watt CF 13 Watt CF 13 Watt CF 13 Watt CF 450 Watt Halogens 4 Ft T8 Elec. 80 65 65 65 15 85 15 15 15 15 15 15 15 12 48 9 8 36 1 8 18 8 8 4 4 16 1 21 6 14 2 1 2 3 5 1 1 1 4 29 1 1 1 27 6 6 4 30 48 4 4 1 4 36 6 6 8 4 10 1 1 8 4 6 6 10 2 14 6 2 16 2 140 12 46 108 4 14 19 164 19 29 59 40 45 15 1 2 1 1 2 1 2 2 2 2 2 1 2 1 2 1 1 2 1 2 2 1 2 2 2 1 2 1 1 1 2 2 2 2 2 2 2 1 1 2 2 2 2 2 1 2 1 1 2 1 1 2 2 2 2 2 1 2 2 3 2 2 2 1 8 2 1 1 8 2 1 1 2 0 1 0 0 1 0 1 1 1 1 1 0 1 0 1 0 0 1 0 1 1 0 1 1 1 0 1 0 0 0 1 1 1 1 1 1 1 0 0 1 1 1 1 1 0 1 0 0 1 0 0 1 1 1 1 1 0 1 1 1 1 1 1 0 0 1 0 0 0 0 0 0 1 13 32 13 9 32 60 32 32 32 32 32 13 32 40 32 13 13 32 13 32 32 13 32 32 32 13 32 13 13 13 32 32 32 32 32 32 32 13 13 32 32 32 32 32 13 32 13 13 32 13 18 32 32 32 32 32 13 32 32 32 32 32 32 9 13 32 9 9 13 13 13 450 32 0 62 0 0 62 0 62 62 62 62 62 0 62 0 62 0 0 62 0 62 62 0 62 62 62 0 62 0 0 0 62 62 62 62 62 62 62 0 0 62 62 62 62 62 0 62 0 0 62 0 0 62 62 62 62 62 0 62 62 93 62 62 62 0 0 62 0 0 0 0 0 0 62 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 3,060 3,060 3,060 3,060 3,060 3,060 3,060 3,060 3,060 3,060 5,100 5,100 5,100 1,275 3,060 3,060 3,060 5,100 5,100 1,275 1,275 1,275 1,275 1,275 1,275 1,275 1,275 1,275 1,275 1,275 1,340 1,340 1,340 1,340 5,100 5,100 3,060 1,275 1,275 1,275 1,275 1,275 1,275 5,100 5,100 5,100 1,275 1,275 8,000 8,000 8,000 8,000 8,000 8,000 8,000 8,000 5,100 5,100 5,100 3,160 3,160 3,160 3,160 3,160 5,100 3,160 5,100 5,100 5,100 5,100 5,100 1,340 8,760 0.2 3 0.1 0.1 2.2 0.1 0.5 1.1 0.5 0.5 0.2 0.1 1 0 1.3 0.1 0.2 0.1 0 0.1 0.2 0.1 0.1 0.1 0.1 0.1 1.8 0 0 0 1.7 0.4 0.4 0.2 1.9 3 0.2 0.1 0 0.2 2.2 0.4 0.4 0.5 0.1 0.6 0 0 0.5 0.1 0.1 0.4 0.6 0.1 0.9 0.4 0 1 0.1 13 0.7 2.9 6.7 0 1.2 1.5 0.2 3 1.5 0.5 20.3 0.9 118.3 75 612 9,180 306 306 6,732 306 1,530 3,366 1,530 1,530 1,020 510 5,100 0 3,978 306 612 510 0 128 255 128 128 128 128 128 2,295 0 0 0 2,278 536 536 268 9,690 15,300 612 128 0 255 2,805 510 510 2,550 510 3,060 0 0 4,000 800 800 3,200 4,800 800 7,200 3,200 0 5,100 510 41,080 2,212 9,164 21,172 0 0 3,792 7,650 1,020 15,300 7,650 2,550 27,202 7,884 381,268 APPENDIX D REFRIGERATION D.1 REFRIGERATION WORKSHEET DEFINITIONS The refrigeration worksheet uses data gathered during the on-site visit and local weather data to estimate the energy savings due to reducing condensing pressure. The worksheet calculation methods and symbols are described as follows: EXISTING OPERATING CONDITIONS (e) Minimum Existing Condensing Temperature (Tme). The condenser fans cycle on and off to maintain a minimum condensing temperature. The minimum existing condensing temperature is the average of the fan cut-in and fan cut-out temperatures. When system load or low ambient temperatures permit, the condensing temperature drops. A pressure switch maintains the minimum condensing temperature and pressure by turning the condenser fans off, reducing the condensing capacity, and causing the condensing temperature to rise. The same pressure switch also turns the fans back on when the condensing temperature rises. During periods of high system load or high ambient temperatures, the condensing temperature may stay above the fan shut off point. Temperature Difference (DTe). With the condenser fans on, the condensing temperature floats at an average temperature difference above the ambient temperature. Compressor Energy (ECe). The annual energy consumption of the high-stage compressors, calculated in Appendix A.3: Motor Applications Table. Condenser Fan Horsepower (HPe). The total condenser fan horsepower of the system. Fan Power (FPe). The actual power used by the condenser fans, taking motor load and efficiency into consideration. Annual Operating Hours (OH). Annual operating hours of refrigeration system. PROPOSED OPERATING CONDITIONS (p) Minimum Proposed Condensing Temperature (Tmp). Same as the definition for the existing conditions, except that the fan cut-in and fan-cut out points have been reduced. The condensing capacity may have been increased if needed to reduce the condensing temperature. The minimum proposed condensing temperature is 50°F for reciprocating compressors and screw. 76 compressors without liquid injection cooling. The minimum pressure is 125 psig for screw compressors with liquid injection cooling, and 93 psig with liquid injection booster pumps. Temperature Difference (DTe). Same as the definition for the existing conditions, except that the temperature difference may be reduced if condenser capacity or fan use is increased. Compressor Energy (ECp). The annual energy consumption of the high-stage compressors with reduced condensing temperature. BIN CALCULATION Long term (30-year average) local weather data is commonly available in a "bin" format. A temperature bin is a five degree range of dry bulb temperatures. Bin weather data consists of the average number of hours per year that the temperature was within each 5-degree range. The middle temperature of each bin is defined as the dry bulb temperature for that bin. For example, the temperature bin between 45°F and 49°F is listed as the average dry bulb temperature of 47°F. Dry Bulb Temperature (Tdb). The dry bulb temperature for each bin is used for air-cooled condensers. Wet Bulb Temperature (Twb). The mean coincident wet bulb temperature for the corresponding bin is used for wet or evaporative condensers. Hours (H). The annual hours of occurrence for the bin temperature. Existing (Tce) and Proposed (Tcp) Condensing Temperature. We assume the existing condensing temperature floats above the ambient wet or dry bulb temperature while maintaining the existing minimum condensing temperature. Resetting fan pressure switches will allow the proposed condensing temperature to float above the wet or dry bulb temperature with a new proposed minimum condensing temperature. The actual condensing temperatures are therefore: Tce = Larger [Tme, T + DTe] Tcp = Larger [Tmp, T + DTp] where, T = Twb, Wet Bulb for wet or evaporative condensers or T = Tdb, Dry Bulb for air cooled condensers Degree-Hour Savings (DHS). The Degree-Hour Savings reflects the decrease in condensing temperature multiplied by the number of hours for each bin temperature in the worksheet. The Degree-Hour Savings is calculated when the proposed condensing temperature is less than the existing condensing temperature: DHS = (Tce - Tcp) x H 77 Energy Savings Percent (E%). Energy savings will occur due to reduced running time, increased capacity, and reduced compressor power. Savings of 1% in compressor energy per degree drop in condensing temperature are possible. The energy savings percent of the total annual compressor energy for each bin temperature can be found from: E% = DHS / HT Where, HT = Total annual bin hours: 8,760 hr annually Compressor Energy Savings (CES). The compressor energy savings for each bin temperature can be calculated by: CE = ECe x E% Fan Energy Increase (FEI). Reducing the minimum condensing temperature will increase the condenser fan energy consumption. We assume that the fans will operate at full load during periods when the condensing temperature is above the minimum condensing temperature. When the condensing temperature reaches its minimum setpoint, a decrease in the dry or wet bulb temperature results in fan cycling to maintain the minimum condensing temperature. The fan energy increase for each bin temperature can be found from: FE = FP x H x (OH / HT) x [ DTp / (Tcp-T) – DTe / (Tce-T)] ENERGY AND COST SAVINGS Total Energy Savings (ES). The compressor energy savings minus the fan energy increase. ES = CE - FE Total Cost Savings (CS). The total annual cost savings resulting from multiplying the total annual energy savings by the cost of electricity (E$): CS = ES x E$ Implementation Cost (IC). There is no implementation cost to reduce the pressure switch settings. If there are no pressure switches, these cost about $75 each to install. The cost of liquid pumps for screw compressors with liquid injection to ensure adequate compressor cooling or other systems will be approximately $3,000 each. Hy-Save pumps for freon systems cost approximately $1,200 each. The cost of increasing evaporative condenser capacity is estimated at $75/ton. Simple Payback (PB). The simple payback is calculated as: PB = IC / CS 78