Low Moderate PRIORITY LEVEL High PlanCon C.I.P. ACHIEVEMENT METHOD Maintenance Other Safety & Accessibility Educational Program TYPE OF IMPROVEMENT Penncrest High School PART 1 February 5, 2007 Summary of Recommendations Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN PHYSICAL PLANT RECOMMENDATIONS A. SITE 1 Circulation No specific recommendations 2 Driveways and Parking Lots Monitor areas of recent site work where trenching has occurred; areas may settle over time Sidewalks and Curbs Repair damaged curbs and sidewalks near the receiving area 3 4 Site ADA Accessibility Renovate site infrastructure to conform to ADAAG and PA-UCC requirements. Renovations may include site regrading, drop curbs, ramps, railings and signage. 5 Play Areas Not Applicable 6 Landscaping No specific recommendations 7 Physical Education Areas Provide ADAAG compliant accessible routes to all of the various areas; repair worn areas in the field turf lawn areas Penncrest High School Page 1 of 14 X X X X X X X X X Low Moderate PRIORITY LEVEL High PlanCon C.I.P. ACHIEVEMENT METHOD Maintenance Other Safety & Accessibility Educational Program TYPE OF IMPROVEMENT Penncrest High School 8 February 5, 2007 Summary of Recommendations Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN Utilities No specific recommendations B. BUILDING EXTERIOR 1 2 Masonry Repair cracks and reseal joints Investigate incidences of trapped moisture and take corrective action, as needed EIFS Repair (refinish) rust stains 3 Curtain Wall Not Applicable 4 Windows No specific recommendations 5 Doors and Entryways Correct seals at certain doors to correct water infiltration issues 6 Repair damaged doors (few locations) Roofs Continue / complete roof replacement project(s) Penncrest High School X X X X X X Page 2 of 14 X X X X X X X X X X Low Moderate PRIORITY LEVEL High PlanCon C.I.P. ACHIEVEMENT METHOD Maintenance Other Safety & Accessibility Canopies, Soffits, Fascia Check and reseal flashing, copings, etc., that may be contributing to increased moisture in wall cavities Repair damaged soffits / canopies (few areas) Educational Program TYPE OF IMPROVEMENT Penncrest High School 7 February 5, 2007 Summary of Recommendations Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN C. BUILDING INTERIOR 1 Administrative Offices No specific recommendations 2 Athletic Facilities No specific recommendations 3 Art 4 Provide a separate room for kiln, where needed Renovate the outdated Art Rooms Auditorium Service or replace folding partitions Penncrest High School Improve accessibility to Auditorium and provide direct access to the Platform from house in conformance with ADAAG and PA-UCC Page 3 of 14 X X X X X X X X 7 Repair peeling paint and localized cracks Repair railings at raised platform Consider expansion of dining area or schedule changes to reduce crowded conditions Classrooms Consider renovating remainder of classrooms that were not upgraded as part of previous project in 2000. Replace casework, countertops, flooring, ceilings, visual display boards, etc., that are in fair or poor condition. Repaint walls and trim as needed. Computer/Keyboarding Lab Replace carpet Replace casework and countertops Repaint trim and walls Replace visual display and writing surfaces Remove window A/C units, provide a dedicated A/C system and restore windows Penncrest High School Page 4 of 14 X X X X X X X X X X X X X X Low Moderate High PlanCon C.I.P. PRIORITY LEVEL X X X ACHIEVEMENT METHOD Maintenance Other Educational Program Cafeteria and Kitchen Repair soft spots in floor 6 Deferred Maintenance TYPE OF IMPROVEMENT Penncrest High School 5 February 5, 2007 Summary of Recommendations Safety & Accessibility Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN X X X 10 X Low X Moderate High PRIORITY LEVEL PlanCon C.I.P. ACHIEVEMENT METHOD Maintenance Other Safety & Accessibility 9 Educational Program TYPE OF IMPROVEMENT Penncrest High School 8 February 5, 2007 Summary of Recommendations Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN Corridors Consider renovating the remainder of the corridor areas that were not upgraded as part of previous project in 2000. Replace flooring, ceilings, lockers, tackable surfaces, Tectum sound panels, etc., that are in fair or poor condition. Repaint walls and trim as needed. Replace carpeted wall surfaces (B Wing) Repair damaged bulkheads and other finished surfaces Faculty Dining Repair damage to GWB at window infill Family and Consumer Sciences (FCS) Clean and sanitize the FCS rooms; strip and reseal flooring Repair any minor damage that could harbor bacteria Reconfigure one or more workstation per ADAAG and PA-UCC 11 LGI Not Applicable 12 Library X X X X X X X X X Correct water leaks at sprinkler fittings and repair finishes (ceiling) Replace stained or damaged ceiling tiles Return Library classroom(s) to their intended use Consider improvements to sitelines or electronic surveillance measures for better supervision Penncrest High School Page 5 of 14 X X X X X X X X X X X Repair, regrind and refinish terrazzo flooring Install missing base material Install missing thresholds Provide a secure vestibule connecting the Administrative Suite to the main entrance 14 15 Additional space is needed to support Music program Repair concrete floor slab cracks and damaged VCT Repair damaged fin-tube radiator Repair damage to stair in Choral Room Secure freestanding music storage casework Penncrest High School Page 6 of 14 X X X X X X X X X X X Low Moderate PRIORITY LEVEL High PlanCon C.I.P. Maintenance X Nurse's Office No specific recommendations ACHIEVEMENT METHOD Music Address sound transmission issues between Music Rooms Other Safety & Accessibility Main Lobby Repair all water damaged ceiling, soffit and bulkhead areas Educational Program TYPE OF IMPROVEMENT Penncrest High School 13 February 5, 2007 Summary of Recommendations Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN X X X X X X X X X X X X X X X X Stairways No specific recommendations 19 Tech Ed Labs / Shops Replace casework, countertops, flooring, ceilings, visual display boards, etc., that are in fair or poor condition. Repaint walls and trim as needed. Install missing thresholds at doors Provide additional space to support growing programs Correct noise (HVAC) problems at TV Studio Replace carpet at TV Studio Penncrest High School X X Page 7 of 14 X X X X X X X X Low Moderate X C.I.P. X Special Education See 'Classrooms' items Provide additional Special Education program spaces and support spaces 18 Maintenance High 17 PRIORITY LEVEL PlanCon Consider renovating remainder of the Science Rooms that were not upgraded as part of previous project in 2000. Replace casework, countertops, flooring, ceilings, visual display boards, etc., that are in fair or poor condition. Repaint walls and trim as needed. ACHIEVEMENT METHOD Other Safety & Accessibility Science Provide additional Science Labs as needed to support the educational program Consider reconfiguration of rooms reported to be cramped Educational Program TYPE OF IMPROVEMENT Penncrest High School 16 February 5, 2007 Summary of Recommendations Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN 20 Teacher Planning rooms Not Applicable 21 Toilet Rooms Conditions vary throughout the facility; renovate any toilet facilities where conditions are fair to poor. Any changes should conform to ADAAG and PA-UCC. 23 Environmentally Sensitive Materials Maintain ACBMs in a non-friable state; consider the removal of all VAT and any other ACBMs, PCBs, etc., from the building See individual descriptions for specific items to be addressed Accessibility (ADA) Issues - recommendations per ADAAG Although not an ADAAG or PA-UCC issue it is recommended to provide a building-wide master key system for all doors to improve security and accessibility Provide accessible drinking fountains Provide accessible workstations in the Art, FCS and Science Rooms Modify ramp in the Tech Ed area per ADAAG and PA-UCC Provide required clearances at doors / room entrances Provide ADAAG and PA-UCC compliant access to assembly and performance areas (Gymnasium, Auditorium and Platform) Provide exterior railings in conformance with ADAAG and PA-UCC Provide barrier-free lockers as required Penncrest High School Page 8 of 14 Low Moderate PRIORITY LEVEL High PlanCon C.I.P. ACHIEVEMENT METHOD Maintenance Other Educational Program Deferred Maintenance TYPE OF IMPROVEMENT Penncrest High School 22 February 5, 2007 Summary of Recommendations Safety & Accessibility Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN X X X X X X X X X X X X X X X X X X See individual descriptions for specific items to be addressed 24 Building Code Issues and Safety Concerns Follow recommendations in the CPTED-RED Report Install and identify fire extinguishers in a consistent manner throughout the facility Confirm / maintain fire-rated assemblies as required (It appears that some rated doors / glass may have been replaced with non-rated units) See individual descriptions for specific items to be addressed X X X X X X X X X X D. HVAC 1 2 Hot Water Heating System Boiler Number 1 has reached the end of it expected life. Confirm hot water system is balanced. Install 10,000 gallon fuel oil tank to decrease delivery requirement. Air Conditioning System (Chilled Water) Verify chilled water distribution system balance; replace chiller with a new machine with a variable frequency drive Penncrest High School Page 9 of 14 X X X X Low Moderate PRIORITY LEVEL High PlanCon C.I.P. ACHIEVEMENT METHOD Maintenance Other Safety & Accessibility Provide an Area of Rescue Assistance in the stair towers, where required Replace elevator with one that conforms to current ADAAG and PAUCC requirements Educational Program TYPE OF IMPROVEMENT Penncrest High School February 5, 2007 Summary of Recommendations Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN X X Low Moderate PRIORITY LEVEL High PlanCon C.I.P. ACHIEVEMENT METHOD Maintenance Other Safety & Accessibility 4 Ventilation System (Air Distribution) Replace the existing heating only units with a different unit that will move more air and have a cooling coil. In addition, ductwork may need to be added to the system to distribute the air more effectively. If this is not possible, at minimum, additional fans and openings should be added at lower to upper levels to provide cross ventilation of the space. Educational Program TYPE OF IMPROVEMENT Penncrest High School 3 February 5, 2007 Summary of Recommendations Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN X Exhaust System Provide dedicated exhaust for the Ceramic Art area or a dedicated hood, depending on usage needs; refinish dust collection equipment located outside 5 Additional Systems No specific recommendations 6 Temperature Control System Where possible provide or un-seal operable windows for occupant comfort Survey building control valves and dampers to confirm operation and interoperability with thermostat control Verify calibration of thermostats Install thermostat where terminal heating equipment is not thermostatically controlled Penncrest High School Page 10 of 14 X X X X X X X X X February 5, 2007 Summary of Recommendations E. PLUMBING 1 2 Fuel Systems Provide master shut-off in each gas line serving classrooms and provide emergency shut-off switch on wall Domestic Water Service Investigate system and install pressure-reducing system, if necessary 3 Domestic Hot Water System No specific recommendations 4 Sanitary Waste System No specific recommendations 5 Plumbing Fixtures Provide tempered water to emergency fixtures as required by current regulations Provide emergency showers where required Replace lavatory systems with more durable fixture(s) Kitchen Systems 6 7 No specific recommendations Fire Protection System No specific recommendations Penncrest High School Page 11 of 14 X X X X X X X X X X Low Moderate PRIORITY LEVEL High PlanCon C.I.P. ACHIEVEMENT METHOD Maintenance Other Educational Program Deferred Maintenance TYPE OF IMPROVEMENT Penncrest High School Safety & Accessibility Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN X X F. ELECTRICAL 1 Electrical Service No specific recommendations 2 Branch Panels No specific recommendations 3 Receptacles Provide additional receptacles / circuits as needed to support program 4 Lighting Control classroom lighting and other spaces with occupancy sensors to shut off lighting when the space is unoccupied 5 Platform (Stage) Lighting No specific recommendations 6 Exit Signs / Emergency Lighting No specific recommendations 7 Exterior Lighting No specific recommendations Penncrest High School Page 12 of 14 X X X X Low Moderate PRIORITY LEVEL High PlanCon C.I.P. ACHIEVEMENT METHOD Maintenance Other Safety & Accessibility Stormwater Drainage Replace roof drains and include cleaning of piping system after reroofing Educational Program TYPE OF IMPROVEMENT Penncrest High School 8 February 5, 2007 Summary of Recommendations Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN Emergency Generator No specific recommendations 9 Telecommunications No specific recommendations 10 CATV No specific recommendations 11 Intercom / Clock System Install speakers in office spaces where required 12 Remote Sound System No specific recommendations 13 Fire Alarm System The fire alarm system should meet current codes; however, problems were reported; recommend fixing troubled conditions through the vendor 15 Security Install camera system with digital recording Extend security panel to alarm all exterior doors Consider access card system Computer Cabling No specific recommendations Penncrest High School Page 13 of 14 X X X X X X X X Low Moderate X X PRIORITY LEVEL High PlanCon C.I.P. ACHIEVEMENT METHOD Maintenance Other Safety & Accessibility 8 Educational Program TYPE OF IMPROVEMENT Penncrest High School 14 February 5, 2007 Summary of Recommendations Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN EDUCATIONAL PROGRAM RELATED RECOMMENDATIONS 1 Provide accommodations for potential future growth 2 Provide additional space for small and large group instruction 3 Provide additional storage for instructional materials and supplies 4 5 Improve security zones and separations within the building Provide space for expansion of "Little Lions" Program and/or future daycare 6 See individual descriptions for specific items to be addressed Penncrest High School Page 14 of 14 X X X X X X X X X X Low Moderate PRIORITY LEVEL High PlanCon C.I.P. ACHIEVEMENT METHOD Maintenance Other Safety & Accessibility Educational Program TYPE OF IMPROVEMENT Penncrest High School PART 2 February 5, 2007 Summary of Recommendations Deferred Maintenance Rose Tree Media School District FIVE YEAR CAPITAL IMPROVEMENT EDUCATIONAL MASTER ACTION PLAN