Public Consultation on an EU Initiative to Reduce the Cost of Rolling Out High Speed Communication Infrastructure in Europe Response from BT Group plc Background and Context BT recognises the importance for the European Commission, national and local government, to consider all options to facilitate high-speed broadband deployment. Reducing the costs of civil works forms one part of this picture but provision of access to physical infrastructure alone is not sufficient to stimulate investment and innovation. As Commissioner Kroes’ July policy statement (‘Enhancing the broadband investment environment’ – 12 July 2012) makes clear, technology neutrality and non-discrimination are key planks of an overall approach to high-speed broadband. The UK’s success in this area rests strongly on the concept of ‘open access’ i.e. wholesale access on a non-discriminatory basis. This ensures that consumers and businesses are always able to access a choice of downstream providers with competition driving lower prices and innovation and encouraging take-up. Our response to this consultation draws on contributions we have made to UK discussions on use of passive infrastructure. Executive Summary Any assessment of the option to open utility infrastructure should examine the opportunities and risks including any impact on the very large private sector investments currently underway or planned by telecoms operators, cable and others. In addition to established mechanisms for sharing of non telecommunications infrastructure (for example BT’s own pole-sharing arrangements with electricity companies), there may be a case for ensuring that it is possible to extend this approach to general utility infrastructure by legislation - but only if commercial arrangements do not deliver - in order to ensure it is available if required. Although this consultation is focused on access to other (non telecommunications) utility physical infrastructure, we believe that access to other telecommunications assets i.e. other than those of the SMP provider, in a similar manner to that offered by the incumbent telecoms operator is more likely to help the cost-effective deployment of broadband and broaden consumer choice. Governments and regulators therefore should take the opportunity afforded by Art. 12 of the EU Framework Directive to mandate infrastructure sharing on all communications providers and owners of telecommunications physical infrastructure to ensure equivalent access. It is essential to establish a well-structured, professional approach to infrastructure sharing in which responsibilities are clearly set out and understood by all parties involved. In addition, this response proposes other potential policy interventions which would improve rural access to broadband. There are also a number of areas relating to better collaboration between local planning and highways authorities and other organisations which could help to bring fibre broadband to communities across the UK. These are outlined below under ‘co-ordination of civil engineering / streetworks and transparency’. For ease of response we have grouped some of the questions and our answers together around the potential benefits of infrastructure sharing within the communications industry and across other utility sectors, barriers to accessing infrastructure, duct access, infrastructure mapping, streetworks permitting coordination of civil engineering and readiness of buildings for NGA. Finally, although our response indicates BT’s support for infrastructure sharing where this will be of benefit, we do believe that the economics of ‘passive’ access to physical infrastructure are such that over-reliance on this as a sole access remedy is very likely to lead to a foreclosure of competition based on vertically-integrated monopolies. We therefore believe that where companies provide a service using access to other utilities’ infrastructure, they should also have to wholesale resulting products in a way that allows other providers to offer service and therefore supports competition. Consultation Questions Potential benefits of infrastructure sharing 1.What are the benefits (including approximate savings) that could be achieved for NGA roll-out by a more intensive infrastructure sharing within the EU, including the infrastructure of utility companies? 2.What are the benefits that could be achieved by a more coherent regime of infrastructure sharing within the EU, including the infrastructure of utility companies? 4.What are the good practices in the EU and in third countries that could be identified and be promoted with respect to achieving a more intensive infrastructure sharing with a view to deploying high-speed communications networks? 6.What measures could be envisaged to increase the business interest on the side of the utility companies to provide access to their infrastructure for broadband investment? We agree that there is potential to reduce the cost of rolling out NGA if existing civil infrastructure can be opened up in a suitable way, but we do not believe that it is a ‘silver bullet’ for lowering the costs of infrastructure deployment that will speed or extend the rollout of fibre broadband due to the range of other costs and issues that need to be addressed. There are already examples in the UK where commercial arrangements are in place which achieve infrastructure sharing. Therefore regulating / producing guidance to include other infrastructure may result in additional cost saving options, particularly in difficult to reach areas for fibre broadband. However we believe it is important to ensure that they do not: Undermine already committed and planned investment – e.g. through unfair terms or pricing, or removing the incentive the invest Stimulate Communications Providers to focus on substituting business/leased lines circuits Solely concentrate on areas already well served with current generation broadband or fibre infrastructure (e.g. metropolitan areas). It is therefore key for the EU to focus on the relevant policy objectives and those of the UK Government and how those can be supported by measures imposed. Potentially these could include coverage targets, homes passed, minimum contract periods etc for those utilising scarce assets in the long term. In looking at possible options, it is important that the full complexity and long term nature of investing in new networks is fully recognized and there are many examples of the operational and commercial challenges which can be cited from the UK’s recent past; for example the experience of the cable television industry over the past 15 years, Energis or the challenges faced currently by the South Yorkshire Digital Region project. The cost of infrastructure access is therefore clearly not the only issue facing service providers wishing to deploy fibre. There are many other aspects to deployment which are complex and costly to implement both in start-up and on an ongoing basis: customer facing and network management systems maintenance processes the development of open access wholesale products the costs and the processes associated with customer switching. To make investment in infrastructure commercially viable the infrastructure provider requires an efficient operational model that can utilise the infrastructure, often requiring scale economies to support its investment and that of its customers. There are a limited number of infrastructure networks suitable for infrastructure sharing and these options become even more limited as the requirement is pushed further into harder to reach areas. Factors that make use of the various networks identified in the discussion document problematic include: The availability of other utility infrastructure in remote or rural areas (often there are no sewer networks for example in remote areas) The proximity of the networks that do exist to both BT’s infrastructure and the customer premise. A large cost in Fibre To The Premise (FTTP) deployments is in the ‘last drop’ to the customer premise, and useable alternative infrastructure is often not available in this section of the network in rural areas Breaking out of the existing network at a suitable point for connection of the ‘final drop’. As a result of these types of issues we believe arrangements similar those we have with electricity distribution companies for the joint use of poles are likely to be the most useful in accessing alternative infrastructure to achieve our objectives. Although we have already agreed commercial agreements for this infrastructure for the deployment of copper cables, and are reviewing potential new agreements for fibre, it may be possible that legislating for access to this infrastructure could provide possibilities for fibre deployment that benefit or enable new commercial models or new ways of working to come to the market if commercial approaches fail. Possible additional interventions which may help to achieve further coverage are most likely to be based on opening up access to alternative telecoms network infrastructure such as Virgin Media’s duct (and potentially its poles); as we have already identified in the early stages of FTTP deployment that there are deployment areas where Virgin may have available duct and Openreach (BT’s local access division) has limited or no availability. Therefore in general, based on our experience we do not see great benefits of opening up utility infrastructure beyond the existing commercial arrangements that are already available, particularly in rural areas where alternative infrastructure is often unavailable, but would not wish to rule it out, nor to adversely affect the choice of other CPs in this matter. The specific issue of duct costs and access to alternative infrastructure for NGA deployment in the UK was investigated as part of the Broadband Stakeholder Group (BSG) report on Fibre costings for the UK undertaken by Analysis Mason .The report identified a potential 16% cost saving figure nationally for NGA deployment attributed to the use of alternative infrastructure of both Virgin and utility duct where available1. As such this is likely to be a maximum saving. However, the report also concludes that: “the percentage cost saving is greatest in urban areas and lowest in the rural areas” (Section 1.2.3). 1 Analysys Mason (2008) The costs of deploying fibre-based next generation broadband infrastructure There is no specific figure for what saving may be available in rural areas, where there will typically be no cable duct, and in many cases no alternative infrastructure available in the vicinity (sewers etc.). Therefore our estimate is this could possibly halve the availability of alternative infrastructure and hence in many rural areas materially reduce any possible savings. It is also important to recognise that the Analysys Mason study considers both the reuse of existing utility infrastructure and the potential of new aerial infrastructure (fibre on new poles), and it is important not to confuse the savings potential of each scenario. This latter approach of deploying overhead fibre on new pole infrastructure has a number of practical difficulties but may be useful in ensuring that very hard to reach areas or areas where other duct assets are congested, can be addressed. So whilst there is potential for the use of other utilities infrastructure to reduce deployment costs in rural areas as identified by Analysys Mason and others, the scale of these cost reductions is not likely to be as high as the 16% figure. This is a national figure and investments in rural areas are less likely to be able to use these assets. These savings are also likely to be reduced significantly or potentially eliminated altogether, by the additional costs associated with integrating these assets into the existing operations, product set and systems etc of the investing CP as identified above. It is also worth bearing in mind that the Analysis Mason study only considered capital costs and therefore any ongoing charges to use these shared assets would also need to be taken into account. BT has already launched its Physical Infrastructure Access (PIA) products therefore opening up duct and pole networks for CPs who wish to deploy fibre. For utility operators, we presume it would be rational that they would be looking to improve ROCE through extending the use of their existing assets into other markets if it is viable. Potential new revenue streams from enabling access to their infrastructure would therefore need to ensure that the achievable rate of return on this activity and the additional costs involved in enabling infrastructure sharing products to be deployed and maintained were sufficient to justify the investment, compared to other potential uses for their capital. We would expect a utility infrastructure owner to be concerned that they would be able to protect any commercial returns they received from making their infrastructure available and ensure that these additional returns did not impact their existing regulated returns. Barriers 3.What are the main bottlenecks (practical, administrative, technical or legal) that operators wishing to deploy high-speed communications networks are confronted with when accessing existing infrastructures? We believe that anyone seeking to utilise infrastructure sharing and integrate it into their existing network will inevitably incur new costs as well as potentially lose operational control unless changes to systems and processes were introduced. The additional costs would need to be offset by any savings through infrastructure sharing. Recent studies, particularly by Analysys Mason for Ofcom2 into Openreach duct, have highlighted a range of such operational issues and success factors involved in utilising underground duct networks and overhead poles; and hence deployment based on the use of such infrastructure would need to address these. It is often these types of practical issues which are hidden from the CPs seeking access as they are dealt with on a day to day basis by the infrastructure provider who is responsible for installing, upgrading or expanding its own infrastructure network. These issues often then only become visible and pertinent for communications providers when they are begin to utilise infrastructure access in order to deploy their own fibre network. Typical operational issues encountered by Openreach and associated with gaining access to underground infrastructure include: access restrictions in traffic-sensitive areas special event restrictions placed by local authorities health and safety issues (sewage and residual gas) accuracy of infrastructure drawings chambers located in dense pedestrian areas high cable density in chambers (especially in aggregation points in the duct network) small chambers entirely filled with earth due to the rain washing the soil into the chambers - requiring physical excavation to even survey the asset. These issues affect a significant proportion of duct assets as shown by the recent Ofcom study. Typical operational issues associated with utilising overhead pole infrastructure include: trees obstructing poles access to the pole itself fragile roofs nearby overhead power lines lower parts of poles being subject to vandalism. These factors are further compounded by the issue of scale economies both locally and nationally. For example new entrants into the market with relatively small market shares in an area, or those who are serving less densely located entities such as businesses, are likely to find infrastructure sharing less economic as they will not have the number of customers in any location to support the necessary investment in equipment to make this a viable proposition. As a result it will be vital to ensure that other means of access to the infrastructure are maintained to enable continued market entry i.e. duct sharing may be necessary but it is not sufficient for continued competition. It is 2 Analysys Mason - Operational models for shared duct access (April 1st 2010) often the creation of fit for purpose active wholesale access products which are key enablers for competition. None of the above issues rule out the use of shared infrastructure as being useful, as indeed is highlighted by Openreach’s own existing commercial agreement to use electricity poles. These issues can be and are overcome where it makes economic sense to do so, however this has implications when assessing cost savings which might be available through infrastructure sharing, which would need to take those existing savings into account and thus not assume they are automatic. Experience shows that infrastructure sharing through commercial arrangements or based on industry co-operation is more likely to be delivered quickly than a legislated solution. However our experience from the telecoms industry also shows that other providers are generally unwilling to open up their infrastructure or will only open up wholesale services on bespoke commercial terms where it is advantageous for them to do so, rather than equivalent wholesale services in the way that BT is prepared to do. As a result legislation is probably required, at the very least as a back-stop and an incentive to parties to reach commercial agreement. If legislation is needed it is important that any such access obligations are properly implemented and policed and it would need to be clear which regulator was responsible for implementing and enforcing any such regulation. Given that access here is required in order to provide telecoms services, this would suggest a role for Ofcom. However, other issues covered in the consultation (such as the impact on utilities’ price control regimes) do relate to the existing utility regulators, so there may be a need to consider concurrent powers for regulators in this area. Duct access 5.What would be the main benefits and disadvantages for broadband investment if access to ducts were mandated across infrastructures? Duct access may make a difference at the margin in some localities but it is a complex matter. For example whilst studies such as those by Analysys Mason for the Broadband Stakeholders Group3 confirm that the costs of civils infrastructure are relatively high for new build fibre, the additional costs of integrating new/non standard infrastructure into an infrastructure suppliers’ systems and processes from a range of suppliers is also significant. Additionally the existing duct does not necessarily have space available for sharing; Ofcom estimates 22% of BT ducts are already full and not everywhere in the UK has ducts – some phone lines are laid through bare earth meaning that it would be necessary to provide new duct for any fibre provision irrespective of the fibre owner, further increasing the common costs that need to be shared between the accessible users. The financial case for 3 Analysys Mason (2008) The costs of deploying fibre-based next generation broadband infrastructure multiple fibre installation and the ability of duct sharing to mitigate them is therefore not generally clear-cut. BT has already offered access to its ducts in order to maximise the opportunity for cost savings to all and we expect that others in the sector should also offer similar rights of access. Since the transposition into UK law of the revised EU Directives, Ofcom now has greater powers to mandate infrastructure sharing from non-SMP providers and we believe regulators should use these powers where there are proven benefits. We also support the fact that this consultation is looking at the potential opportunities to extend this approach beyond the telecoms sector to general utilities although as we have explained previously they are not currently a significant factor in the planning of our NGA deployments. Infrastructure mapping 7.How do you assess the importance of systematic infrastructure mapping / of drawing up consistent inventories of infrastructure? Besides the potential economic advantages for electronic communications operators, do you see other advantages that such mapping could entail for citizens, public authorities or other (economic) operators? 9.What information should be included in such maps with a view to facilitating cooperation, infrastructure sharing and broadband rollout? Who should be in charge of such mapping exercises and at what level should it be organised? 10.What would be the approximate cost of introducing systematic mapping? 14.To what extent would inventories of infrastructure be suitable for high speed communication infrastructure rollout? What kinds of infrastructures would you consider most suitable for being included in such an inventory? Who should be in charge of such an initiative? Should the obligation to announce planned investments apply only to the public sector, or also to private investors? What time horizon would you consider relevant for the availability of information about individual planned projects, so that this could lead to setting up concrete co-deployment projects? What are in your view the main organizational requirements, including costs, necessary for the establishment and maintenance of such an inventory? The extent and scope of the BT duct and pole network has evolved over many decades and there never was an expectation that it should be built and the inventory recorded in a way that would satisfy a multi-user environment. Existing records have been built-up in many cases by local planners and with local knowledge. Over the years many of these have been gradually incorporated into IT systems designed for BT network and operational personnel to access. Needless to say such computerisation is not fully implemented and to the extent that it has taken place is has proved to be a complex and very costly task. Whilst developing the PIA product, BT (through its Openreach division) had extensive discussions with CPs to determine their information needs to plan and use the PIA product. We now feel we have come to a pragmatic solution which allows appropriate levels of data to be supplied on demand to interested CPs on a region by region basis. Such an approach utilises existing systems and available information formats, as and when a CP is interested in investing. This is sufficient to enable planning of physical surveys which are the de facto test of whether the infrastructure is available and suitable for fibre deployment. Certainly given the UK experience it appears a highly disproportionate solution at this stage to require redesign of existing inventory systems and investment in new systems and processes before there is known demand and in the knowledge of the complexity and expense of such upgrades. The security of data in any form of Infrastructure mapping must also be taken into account. With the sensitive nature of the information provided any system that may be created must only be available to authorised users. Any transaction on such a database must be capable of being identified after the event should it be required. It must also factor in that utilities use differing systems for their mapping requirements and the cost of using a universal system may uneconomic. An inventory would create an unnecessary burden with associated security and resilience risks. Collaborative working across sectors is already in place as evidenced by the UK’s National Joint Utilities Group and the Highways Authorities and Utilities Committee (HAUC UK). More specifically, the National Underground Asset Group has been established to create a centrally accessed database indicating the location of all utilities and highways authority assets. Our commercial fibre deployment plans are made public on a quarterly basis with supporting stakeholder engagement, including planning and highways authorities. Co-ordination of civil engineering / streetworks and transparency 11.In your view, which substantial benefits would exist in offering possibilities to systematically lay new ducts when undertaking (public) works? In your experience, to what extent would additional potential revenue outweigh the extra costs? 12.What good practices are you aware of concerning transparency and coordination of civil engineering works? Should this be mandatory in the case of publicly financed works? 13.Are you aware of any sources of information concerning planned civil engineering works? To what extent are they comprehensive (for instance covering different types of infrastructure) and easy-to-access? Please specify their scope. 15.What other best practice examples to improve coordination of civil engineering works are you aware of? BT is committed to working with other utilities wherever possible and will seek to do so to minimise disruption and deliver our fibre programme as quickly as possible: Openreach has been working very closely with the power companies as each street cabinet requires a power connection as part of our NGA deployment programme This requires close collaborative working, coordination and effective management of street works notices Owing to the reactive nature of some of our work (e.g. when we are working in response to customer orders) joint-working with other utilities is not always possible In most cases, our NGA rollout doesn’t necessitate lengthy street works because we are accessing existing ducts via our manholes There are many examples of where we have worked with other utilities on projects to minimise disruption. We are active members of the London Cross Rail Joint Utilities Board, and the London Utilities Partnership Forums for example. We also support the principles of the UK National Underground Assets Group on exchange of information We are signatories of the Mayor of London’s Code of Conduct for Streetworks 2012 which reflects a desire to work collaboratively across sectors and to raise the standard of road works undertaken across London and reduce their impact on the travelling public, in terms of traffic disruption and other impacts. Permitting of streetworks 16.How do you estimate the costs and period of time needed for a company to receive all the necessary permits needed to rollout a high speed electronic communications access network? 17.What measures could help increase transparency and streamline the process of granting such permits? What kind of permits should be covered by such measures? 18.What kind of coordination would, in your view, facilitate the most the permits granting process? How could such coordination be best organized? How far should such coordination go and what would be the benefits achieved of the suggested level of coordination? 19.How do you estimate the costs incurred by any measure suggested? Fibre roll-out, particularly FTTP, is heavily dependent on street works. The Traffic Management Act allows local authorities to move to a new way of managing utility companies’ work on the public highway: instead of notifying plans to carry out street works, a utility company books time on the highway through a permit, for which it pays a fee. Those authorities using a Permitting process may also adopt Lane Rental. Despite the fact that BT does not undertake costly street works unless they are essential, civil engineering is one of the largest elements of our cost base. Permit and Lane Rental schemes could significantly increase our roll-out costs through the complexities of the process as well as charges for permits / lane rental fees. It is our belief that authorities should require permits for works on major routes only; and exempt work to install new infrastructure such as fibre broadband. Some permit schemes (e.g. in the English county of Kent) do not charge for minor roads. This template should be applied to all Permit Schemes as a matter of urgency. This change would ensure a real acceleration of our NGA rollout. We are concerned with the UK Government’s current proposal (which is opposed by utilities and highway authorities’ national representative bodies) to remove the Secretary of State for Transport from the permit scheme approval process. This will lead to a proliferation of scheme variations (possibly 170 across England). This will make both planning and deployment extremely difficult and costly. Permit schemes give Highways Authorities much control over progress with our works. This may be justified on major routes but as stated above is currently being used on all road types in many schemes e.g. London. Clearly highway authorities are not best placed to make a broader judgement about the economic and social benefits of our NGA deployment to the local community. The need to manage this, and potentially many different local requirements and conditions which may proliferate on the back of the proposed changes, will make it more difficult for us to deliver prompt service to our customers, and could delay our rollout ambitions. In addition, a NGA cabinet can take up to 10 permits, “Major Works” designation adds costs, plus planning related charges such as pre-application fees are now commonplace and seen a revenue-raising mechanisms by some planning authorities. Lane Rental We have numerous concerns around the principle and operation of the Lane Rental scheme in London. Fees add greatly to the cost of our fibre deployment and various rules and interpretations add bureaucracy and delay. Currently, the UK Government has signified an intention to approve three pioneer lane rental schemes (Transport for London, Kent County Council and one rural authority). BT would strongly argue that no further schemes should be approved until the results of these schemes are analysed over an extended period of time. Readiness of buildings for NGA 20. What existing requirements under construction laws are you aware of regarding in-building equipment for electronic communication infrastructure? Please specify the Member State, region or municipality. 21.What is, in your view, the most suitable and cost effective way to ensure the existence of adequate and state-of-the-art in-building equipment, while also securing open access for electronic communications providers? 22. What would be the advantages and disadvantages of an obligation to equip buildings with open next generation access? How do you assess the additional costs incurred? Common standards will become more important with the likely increase of NGA initiatives, involving a ‘mixed economy’ of telecoms providers, community organisations and local authorities. These common, national standards can ensure that a patchwork of ‘technology islands’ does not develop and that a range of providers can develop scale solutions with confidence. Within the home, it is important that developers use common standards and approaches when installing cabling to ensure relevant devices (and hence new applications) can be developed and supported independently of networks, interference avoided etc. The building industry needs to be better informed about developments in home networking technologies for the benefits of higher bandwidths to be realised. This will enable customers to more easily, and cheaply, consume future high bandwidth-enabled services. Common standards for connectivity in the home environment will make it easier for developers to pre-provide superfast broadband and for consumers to use new high bandwidth services. The Commission and UK Government should support and encourage UK industry initiatives such as the Connected Home’ project, recently established by the industry body, Intellect, which aims to identify minimum connectivity standards for new and re-furbished homes. Additional cost-saving measures 23.Are you aware of any good practices or measures other than those discussed above undertaken in order to facilitate the deployment of high speed broadband access networks? What has been their impact so far? How would you estimate the cost-saving potential of such measures? Nothing further to add. Additional comments Unlike standard street cabinets, fibre broadband cabinets need a power supply. We rely on several different power companies to ensure these power supplies are installed. Often this works well, but in some areas the power companies are not installing the power supplies fast enough or are charging excessively for the work. We have asked the UK Government to encourage the energy regulator Ofgem to support national standards for providing power supplies, to require power companies to commit to superior standard supply terms, and to help us develop new ways of working with them, for example by ‘renting’ their engineers. BT Group plc 19 July 2012