Annual report 2007 BT Group plc Contents Chairman’s introduction 1 Review of the year 2 The Undertakings Governance Framework 4 The EAB BT’s approach to Undertakings delivery BT’s Undertakings delivery performance 8 Major Milestones Ongoing obligations Product KPI monitoring Monitoring of exemptions and variations Measuring behavioural change 15 The EAB’s Behavioural Dashboard Drivers Activities Outcomes Ongoing improvements Looking to 2007/08 19 About this report 21 PwC’s assurance opinion 23 Terms used in this report The Equality of Access Board (EAB) is a committee of the BT Group plc Board. BT Group plc is a public limited company registered in England and Wales. This is the EAB Annual Report for the period ended 31 March 2007. Unless otherwise stated all facts, statistics, events or developments are correct to the nearest practical date before 10 May 2007. The opinions expressed are those of the EAB, not necessarily those of BT Group plc. The EAB Annual Report is a requirement of the Undertakings given to Ofcom by BT pursuant to the Enterprise Act 2002. Introduction Chairman’s introduction The Equality of Access Board (EAB) was set up to monitor, report on, and advise BT regarding the implementation of the Undertakings – the new regulatory regime agreed by Ofcom and BT in September 2005. Twenty months on, BT has delivered a number of major products designed to enable equivalence for Communication Providers (CPs), and for BT’s own retail businesses. I thank my fellow EAB members for their diligence and insight. We have been ably supported by the Equality of Access Office (EAO) and the EAB Secretariat. The EAB has built on the foundations laid in its first few months of operation. Our validation process has become more thorough, particularly in the definition of success criteria. We have had to decide on potential breaches of the Undertakings, and ensure that BT took appropriate steps to remedy them subsequently. Now, the EAB will focus on BT’s delivery of the Wholesale Line Rental (WLR) products and ongoing compliance with the increasing number of milestones already delivered. We will also look at the impact of the Undertakings on behavioural change, as well as putting a focus on the Undertakings obligations regarding Next Generation Networks (NGNs). The pace and nature of progress in these areas will illustrate whether the Undertakings are becoming ‘business as usual’ for BT and the industry. This year, we have given particular focus to understanding and assessing the operation of Openreach, which lies at the heart of BT’s new relationship with CPs. The Openreach CEO met the EAB regularly to explain the annual operating plan, Openreach’s response to service challenges, the development of the Equivalence Management Platform (EMP) and plans for influencing employee behaviour. Carl Symon EAB Chairman 10 May 2007 Generally CPs are realistic about the challenges faced by BT as well as the progress being made We have listened to industry views about the impact of the new regulatory regime on their operations, and have found that generally CPs are realistic about the challenges faced by BT as well as the progress being made. The EAB has found interaction with industry to be helpful in focusing its discussions with BT. In the autumn, BT reviewed the EAB’s operations with Ofcom, as required by the Undertakings. The conclusion was that the three main parties interested in BT’s delivery of the Undertakings – industry, Ofcom and BT – feel that, on the whole, the EAB has been useful and effective. Equality of Access Board 1 Introduction Review of the year The EAB completed its first full year of monitoring BT’s compliance with the Undertakings, including implementation of major product milestones and a detailed assessment of employee behaviour. The views in this report are based on the EAO’s validation work, reviews conducted on behalf of the EAB and meetings with a variety of stakeholders including BT, CPs and Ofcom. Delivery of major milestones BT had to deliver several significant milestones during 2006/07. Many were met successfully: the EAB confirmed delivery of installed base migration complete (IBMC) for BT’s relevant retail broadband service in December 2006 and it validated delivery of Wholesale Extension Service/Backhaul Extension Service (WES/BES). This obligation was delivered in September 2006, although there remained some wider concerns among CPs regarding BT’s Ethernet portfolio. Other successful deliveries included improved access to engineering appointment books and the separation of Management Information Systems (MIS). BT went beyond the Undertakings requirement for analogue Wholesale Line Rental (WLR) service transfer requests by implementing this process for all customers rather than just new customers. Some milestones were missed altogether, or not delivered in their entirety. In January 2007, the EAB confirmed a non-trivial breach of IPStream IBMC, which was not achieved on 31 December 2006. BT asserts that mass migration of customer records was achieved by 20 March 2007. The EAB will assess full delivery in 2007/08. The EAB confirmed that BT did not achieve the good faith date of 31 December 2006 for supplying all BT New End Users using the Equivalence of Input (EoI) WLR analogue product. The EAB believes that this reflects the ambitious nature of the voluntary commitment. As a result, BT will pay the agreed allowances to CPs. BT’s delivery of its initial equivalence obligation on Local Loop Unbundling (LLU) was not complete. The EAB concluded that the 30 June 2006 deadline was largely met, except for a small number of orders which should have been processed equivalently. This constituted a trivial breach of the Undertaking. The EAB did not recommend any remedial action as BT had begun system development to process all orders using the new equivalence platform. BT also offered allowances to all eligible CPs. A summary of BT’s delivery of key milestones during 2006/07 is shown in the chart below. It demonstrates that the majority were delivered on time, although three were missed. The outcome of those still under review will be reported via the EAB’s website when validated. 2 Equality of Access Board BT’s Delivery of key Undertakings Milestone to 31 March 2007 3 3 24 Delivered on time Not delivered on time Still under review Source: EAO Monitoring ongoing obligations The EAB is focusing increasingly on monitoring BT’s compliance with ongoing obligations associated with the Undertakings. Compliance with these is assessed through the EAO’s Audit and Validation Plan, and through specific reviews in particular areas. The EAO has reviewed Partial Private Circuits transparency, Openreach Internal Trading arrangements and access controls for IPStream ordering. Improvements to reporting of Product KPIs BT has adopted the improvements to its external reporting of Product KPIs recommended by the EAB in last year’s report, including the publication of statistical significance measures and additional commentary. Introduction Not all SMP products covered by the Undertakings have passed EoI milestones. Of those that have, there are some differences in the levels of service provided to BT CPs compared with non-BT CPs. These are due to a range of factors including the mix of order types placed by different CPs and how CPs’ own processes identify and deal with items such as faults. Breaches of the Undertakings 2006/7 2 Increased focus on behaviour 4 New measures were developed in late 2006 to record changing behaviour in BT following the introduction of the Undertakings. These include the impact of the Code of Practice, customer satisfaction scores, system access data, product development measures, complaints and breaches. Initial analysis of these indicators shows a number of positive developments, and room for improvement in other areas. For example, the chart below shows a year-on-year improvement in the number of BT employees and team members completing their Code of Practice training – a measure of progress towards BT employees acting in the spirit of the Undertakings. Code of Practice Training completion rate 1 2 Information sharing Product milestones Equivalence of Input Control of Openreach assets Source: BT % Actual completions 100 The review of the EAB’s role by Ofcom and BT in October 2006 found that the EAB was operating satisfactorily, and that no modifications were required. An independent report from PricewaterhouseCoopers LLP (PwC), including its opinions on specific elements of this report, can be found on p23. 95 90 CP engagement 85 80 Managers Team Members March 2006 March 2007 Source: BT Governance developments There were a number of changes to the processes supporting the delivery of the Undertakings. The EAB proposed improvements to BT’s complaints handling process and these were adopted by December 2006. The EAB improved its validation processes and the transparency of its public reporting. Nine breaches were identified and reported during 2006/07. The chart opposite shows the different categories of reported breaches. The largest proportion involved information sharing, although the number of breaches reported in this area was still small. Two of the breaches were non-trivial, the rest were trivial. The EAB received its first complaint from a CP regarding Wholesale Line Rental (WLR3) contract conditions in August 2006. It did not uphold the allegations by IDT Direct Limited (trading as 'Toucan') that intellectual property rights (IPR) clauses in the new WLR3 contract would preclude EoI. The EAB invited five CPs to its meetings in 2006/07. These were Thus, Carphone Warehouse, Easynet, Tiscali and Cable & Wireless. They covered topics such as progress towards the delivery of BT’s 21st Century Network (21CN), the delivery of products within the Ethernet portfolio and their relationships with Openreach and BT Wholesale. The EAO also routinely met CPs and reported any significant findings to the EAB. CPs have told the EAB and the EAO that the introduction of newly-equivalent products by BT can require costly and timeconsuming systems changes by CPs in order to use those products. BT’s ability to deliver on time and in line with the expectations created by the Undertakings has proved to be an important factor in establishing and maintaining industry confidence. Focus for 2007/08 In 2007/08, the EAB will continue to focus on monitoring the delivery of key milestones, including the obligations on WLR. The EAB will focus also on BT’s ongoing compliance, with emphasis on Product KPIs and behavioural measures. The EAB’s monitoring of the delivery of Undertakings obligations for NGN began in 2006 and will gain prominence in 2007/08. The EAB will also assess the impact on Undertakings compliance of the recently announced changes in BT’s business structure. Equality of Access Board 3 Governance The Undertakings Governance Framework The EAB is a key element in BT’s governance arrangements for monitoring and reporting compliance with the Undertakings. This section describes the work of the EAB and EAO, with a focus on developments during the year. It also covers BT’s governance arrangements associated with the Undertakings. 1. 2. 3. The EAB The EAB was established on 1 November 2005 and there has been no change in membership during its first full year of operation. The members are: 1 Carl Symon, Chairman of the EAB Carl Symon was appointed a non-executive director of BT Group plc on 14 January 2002. He retired from IBM in May 2001 after a 32-year career, during which he held senior executive positions in the USA, Canada, Latin America, Asia and Europe, including Chairman and Chief Executive Officer of IBM UK. Carl is chairman of HMV Group and a non-executive director of Rolls-Royce and Rexam. 2 Sally Davis, BT senior manager Sally Davis was appointed as BT’s Chief Portfolio Officer in May 2005. She had previously held several senior executive roles within BT since joining the company in 1999. Before joining BT, Sally built start-up companies and held leading roles in several major communications companies, including Bell Atlantic in the US and Mercury Communications in the UK. She is a Fellow of University College, London. 3 Sir Bryan Carsberg, Independent Sir Bryan Carsberg was Professor of Accounting and Business Finance and Dean of the Faculty of Economic and Social Studies at Manchester University, before becoming professor of accounting at the London School of Economics from 1981 to 1984. He was Director General of Oftel (the former telecommunications regulator) 4 Equality of Access Board 4. 5. from 1984 to 1992, Director General of the Office of Fair Trading from 1992 to 1995 and Secretary General of the International Accounting Standards Committee from 1995 to 2001. Sir Bryan is currently Chairman of Council and Pro-Chancellor of Loughborough University. He holds a number of non-executive board appointments. He is a qualified Chartered Accountant. 4 Stephen Pettit, Independent Stephen Pettit is a non-executive director of National Grid plc, National Air Traffic Services and Halma plc. He is Chairman of ROK plc and a former executive director of Cable & Wireless plc. Before joining Cable & Wireless, Stephen was Chief Executive, Petrochemicals at British Petroleum. He was previously a non-executive director of KBC Advanced Technologies plc and Norwood Systems Limited. 5 Dr Peter Radley, Independent Dr Peter Radley is the Chair of the IEE Communications Sector Panel. He is a Fellow of the Royal Academy of Engineering and has been involved in the telecommunications industry since 1965. Between 1991 and 2002 he held positions in Alcatel with global responsibility for technology and marketing and as Chairman and CEO for Alcatel UK. He is a member of the Broadband Stakeholder Group. Since 2002, Peter has been an independent advisor to a number of organisations including the DTI and South East England Development Agency and he has also been chairman of technology start-up companies in the broadband, IP and mobile sectors. Governance Management reporting Ofcom EAB BT Group plc Board Compliance oversight Compliance reporting Public reporting BT CEO Operating Committee Openreach CEO Wholesale CEO Retail CEO Global Services CEO Group functions The EAB’s role within BT’s reporting structure How the EAB works The EAB is a committee of the BT Group plc Board although its structure, membership and obligations to Ofcom make it unique. It has oversight of the whole of BT to monitor compliance with the Undertakings. Its position in BT is outlined in the diagram above. The EAB has Terms of Reference setting out its role, monitoring and reporting remit, its powers, how its members are appointed and its organisation. See http://www.bt.com/eab for more information. The EAB is supported by the EAO and the EAB Secretariat on all matters within its remit. The EAO reports monthly to the EAB on the detailed status of BT’s delivery of the Undertakings. It carries out investigations into complaints made by CPs and into possible breaches of the Undertakings on the EAB’s behalf. During the last year, the EAO has developed aspects of its monitoring activities to ensure greater rigour. The EAB Secretariat organised eight EAB meetings and enabled the EAB to receive a wide range of input to its deliberations, including direct engagement with senior executives from several non-BT CPs, the new Ofcom CEO and the Chairman of NGNuk. EAB minutes have been provided to Ofcom as required and the EAB Chairman regularly reported the EAB’s views to the BT Group plc Board. The EAB Secretary conducted a board effectiveness review (a survey of individual EAB members) in autumn 2006. All individual EAB members were satisfied with the quality of information received from within BT, and with the Board’s access to senior executives. The EAO Director has reported to the EAB that he has had no concerns about the resourcing of his department by BT. The EAB has 11 dedicated support staff, nine in the EAO and two in the EAB Secretariat. The EAO post of Complaints Manager continues to be unfilled in light of the EAO only receiving one complaint during this year. The EAB judges that BT has continued to provide satisfactory resources for the fulfilment of its remit. Developments this year The EAB governance arrangements have been strengthened over this period. An ongoing monitoring plan, covering all Undertakings has been established and is operational. The breaches and complaints processes have been used in practice and increased engagement with non-BT CPs has enabled the EAB to gain a more rounded view of BT’s delivery of the Undertakings. Last year’s EAB report described the monitoring and reporting processes in detail, including the monthly cycle of data collection and analysis carried out by the EAO. For more information, see http://www.bt.com/eab. Improvements to EAB monitoring The EAB has strengthened its approach to validating the delivery of major Undertakings milestones and its monitoring of ongoing compliance. In particular, the milestone validation process involves more rigorous testing by the EAO of BT’s evidence that it has satisfied previously agreed success criteria for delivery of an Undertaking. There are also better defined specifications for ongoing compliance audits required by the EAO. Openreach and the EAB Openreach is the BT Line of Business (LoB) with principal responsibility for the delivery of products with a requirement for Equivalence of Input. It does this primarily via its Equivalence Management Platform (EMP) and through its control of the local access and backhaul networks. Each CP that has met with the EAB over the year has provided a perspective on how effectively Openreach is fulfilling its role. The EAB has also met regularly with the Openreach CEO, to review progress. The EAB monitors a number of requirements associated with Openreach’s operations and governance. This includes the location of the Openreach HQ management team in access-controlled accommodation separate from other parts of BT and the obligation to establish a separate annual operating plan. The EAB is generally satisfied that Openreach has complied with the Undertakings relating to its operations and governance, although some breaches have occurred. The EAB has also reviewed Openreach’s service provision, especially where this might have an impact on delivery of the Undertakings. Openreach has provided information on its service improvement plan – implemented in October 2006 to address outstanding repair work – and on the actions it took to restore service following extreme weather conditions in December 2006 and January 2007. Equality of Access Board 5 Governance The EAB’s validation process The EAB and BT have identified four broad categories of success criteria – product, process, people and systems – which are applied to all major deliverables. Each of these categories is populated and agreed in advance for each Undertakings deliverable. Examples of more detailed criteria under these headings include the existence of an operating model for equivalence, signed-off and in use by BT (product), inter-LoB trading agreements agreed and in use (process), evidence of training documentation and delivery (people) and operational readiness testing (systems). The EAB and EAO have learnt and applied lessons from each validation of a major product milestone. For example, the validation of the LLU RFS commitment highlighted the need for certainty over the precise interpretation of the full Undertakings requirement. The EAB’s opinion on BT’s delivery of this Undertaking is set out on p9. The EAO has also developed an Audit and Validation Plan (AVP). This is designed to ensure a rigorous approach is taken to the monitoring and reporting of all deliverables and ongoing compliance. This takes account of any exemptions from or variations to the Undertakings. The EAO established a ‘Quick Checks’ process in 2006 to ensure that all issues raised by CPs or internally would be assessed to determine if they required further investigation. The chart below shows that the EAO conducted a total of 70 Quick Checks in 2006/07. Of these, 50% were raised directly by external CPs. One Quick Check – of information available on the Openreach internal website – resulted in the EAO notifying the EAB formally of a trivial breach of the Undertakings. Almost a quarter have led to the EAB or the EAO recommending actions to BT, many of which involved BT explaining its policies or its approaches to delivering specific aspects of the Undertakings to CPs. Outcome of EAO Quick Checks 2006/07 4 5 4 13 Complaints and breaches During 2006/07, the EAB received one complaint from a CP, which was not upheld. The EAB’s first complaint In August 2006, the EAB received its first formal complaint from a CP. IDT Direct Ltd (trading as ‘Toucan’) alleged that IPR provisions in Openreach’s draft contract for the EoI version of Wholesale Line Rental (known as WLR3) would breach EoI requirements. Following an EAO investigation, the EAB concluded that the allegation was unfounded. The future terms and conditions under which Openreach will trade with BT and non-BT CPs are the same. In addition, the EAB confirmed that the definition of EoI does not require that the impact of such terms and conditions should be identical for all CPs. The complaint provided the first test of the EAO’s complaints handling arrangements. In this case, the EAB did not uphold the complaint, however its consideration led BT to look at the governance arrangements around these clauses, and to address any negative perceptions about the operation of such clauses in the future. The EAO communicated the EAB's findings to IDT. In light of the company's expressed dissatisfaction with the outcome, the EAO Director met with IDT to explain the evidence and arguments underpinning the EAB's decision. BT and the EAO have processes for assessing potential breaches of the Undertakings and for reporting them to the EAB. During 2006/07, the EAB confirmed nine breaches of the Undertakings. BT has reported seven breaches. The EAO has assessed five cases, including one CP complaint, and reported two breaches. Six possible breach cases raised during the year were still under consideration by BT and the EAO had no outstanding cases when this report was approved. The table below summarises the non trivial breaches identified during the year: Undertaking Details Identified by Remedy 3.1.1 in respect of IPstream IBMC BT had migrated less than a third of end users by the milestone date. BT BT reported that 99% of users were migrated by the end of March 2007. 44 Not yet validated by EAB. 5.12 Not applicable to the Undertakings Actions recommended to BT Referred to potential breach process EAO Review initiated Issues explained to CPs but no action recommended to BT Source: EAO Some Quick Checks have also resulted in the EAB’s requesting that the EAO conducts a more detailed review of the issues raised. This year the EAO has completed reviews of the management of the boundaries between Openreach and BT Wholesale, customer business management, Annex 2 processes and compliance with BT’s Code of Practice. See the Delivery and Behaviour sections for more information. 6 Equality of Access Board Due to a historical process, BT Global Services engineers had been performing single-line shifts BT BT has reported that it is putting remedies in place. Remedial action to be validated in due course by EAB. Governance In addition there were a number of trivial breaches identified during the year by BT and the EAO. Those identified by BT were: Use by BT Wholesale for price publication purposes of an administrative team and system located in BT Retail which involved inappropriate disclosure of BT Wholesale information; Inappropriate access on a limited number of occasions to Openreach and BT Wholesale information by one team dealing with customer complaints about broadband; Granting by Openreach of an LLU provisioning escalation request made by a BT Global Services employee outside of the process available to all CPs; Disclosure of Openreach commercial information to one CP, rather than to all CPs, in the course of the Openreach Statement of Requirements process; BT Wholesale planners outside of London were able to use a process that was not controlled by Openreach to allocate space on an MDF. Those identified by the EAO were: A small number of orders for New End Users were not processed equivalently after the RFS date for SMPF (see Delivery section for more information); An instance of inappropriate disclosure of information by Openreach on an intranet page accessible by BT people outside Openreach. The EAB has validated BT’s remedies for trivial breaches identified before January 2007 and will review the remainder early in 2007/08. Review of the EAB A year after the EAB was established, and as required by the Undertakings, BT conducted a review with Ofcom of the operation of the EAB which included an opportunity for industry input. The EAB was provided with a full copy of the resulting report in November 2006 and a summary of BT’s report was published by Ofcom in February 2007. The report demonstrated confidence from the EAB’s stakeholders, and included suggestions for greater EAB focus and engagement. No further formal reviews of the EAB are required by the Undertakings. BT’s approach to Undertakings delivery BT’s governance arrangements associated with the Undertakings have improved significantly in the past year. Areas of weakness identified in last year’s report, such as complaints handling, have been addressed. BT’s Undertakings delivery programme BT’s governance framework consists of the following three key components: The Group Undertakings Forum (GrUF) is a steering forum with responsibility for setting direction; The Group Programme Board’s role includes managing priorities, resolving issues and ensuring cross LoB consistency; The Group Programme Office supports the GrUF and the Group Programme Board by providing regular programme reporting and offering expert help and guidance to individual programme delivery teams. Each LoB also has its own Undertakings delivery programme office which reports into the Group Programme Office. The LoB team reports directly to the EAO in response to requests for monitoring information and clarification of issues raised through the EAO’s validations and Quick Checks process. Over the year, BT has demonstrated stronger cross business coordination of major deliverables. It established BT-wide implementation teams for MIS systems separation and IPStream consuming LLU. However, since three key milestones have been missed and some aspects of delivery have been incomplete, in the EAB’s view, there could have been better coordination between the LoBs for the delivery of key Undertakings (see Delivery section for more information). BT’s handling of complaints and breaches The EAB found initially that BT’s complaints handling arrangements in relation to the Undertakings were unclear to CPs, inconsistent across the business, and lacking in transparency. BT acted on the EAB’s suggested improvements with proposals for a consistent definition of complaints across BT, central logging of all complaints and reporting of these to the EAO, and referencing the role of the EAB and EAO in the process. By December 2006, the EAB agreed that BT had satisfactorily implemented all of the proposed improvements. The EAB is satisfied with BT’s management of internal complaints through the confidential helpline and it receives quarterly monitoring data on the volume, focus and outcome of complaints. Over the year, BT has reported to the EAB that it closed 28 CP complaints about BT’s delivery of the Undertakings and six internal employee complaints. At the time of last year’s report, BT had a process in place to consider potential breaches of the Undertakings, but none of the matters put through it were classified as breaches. A year on, several breaches have been identified and some matters are still under investigation (see p6). BT has kept the EAB informed of its findings on the potential breaches that have been investigated. The process has worked well and ongoing improvements have been made to the associated investigation and reporting processes. The EAB has monitored BT’s implementation of remedial actions following a breach, as well as ongoing compliance activities to prevent further breaches. Implementation of the Undertakings in Northern Ireland BT has an obligation to implement aspects of the Undertakings in Northern Ireland although its operations there are not affected by the structural provisions, and it continues to function as a single integrated unit. In April 2006, BT Northern Ireland and BT Ireland were brought under a single management structure. However, BT Ireland (North) has maintained a programme office to manage and report on its delivery of the Undertakings. Various developments have led to an improved approach to BT’s governance and oversight of the Undertakings in Northern Ireland. In April 2006 a Regulatory Compliance Committee was established to coordinate the delivery of the Undertakings on which the EAO – and more recently, non-BT CPs – have been granted observer status. BT has also participated in the Northern Ireland Telecoms Stakeholder Forum established by Ofcom and has provided effective quarterly reporting to the EAO on Undertakings delivery. Variations and Exemptions Between September 2005 and December 2006, Ofcom and BT agreed variations to the Undertakings. These variations included time extensions to agree whether or not EoI should apply to various products, the publication deadline for the EAB annual report and a variation to specify the requirements in respect of MIS separation. Details and the full text of these variations are published online by Ofcom at http://www.ofcom.org.uk/telecoms/btundertakings/ exemptionsandvariations/. Ofcom is responsible for agreeing exemptions and variations to the Undertakings, and the EAB monitors BT’s subsequent compliance with any additional obligations arising from the exemption process or the amended or varied Undertakings (for example, the obligation to withdraw ISDN Connect from new supply by 31 August 2006). Further information on the EAB’s monitoring of exemptions and variations can be found at http://www.bt.com/eab. Equality of Access Board 7 Delivery BT’s Undertakings delivery performance The Undertakings require BT to deliver a number of product-related obligations which are monitored by the EAB. This year saw a number of complex product and systems deliveries that challenged BT in terms of timing, scale and resource. Progress is charted in four main areas in this section. These are delivery of major milestones, ongoing obligations, Product KPIs and monitoring of variations and exemptions. Major milestones Local Loop Unbundling and IPstream portfolio The Local Loop Unbundling (LLU) and IPstream portfolio enables BT CPs and non-BT CPs to lease local loop infrastructure to offer telephony and broadband services to end users. To provide their own broadband service, some CPs purchase LLU from Openreach whilst others purchase IPStream from BT Wholesale. IPStream uses LLU as an input product, but includes more of BT’s network and functionality in the service. BT has a number of obligations with regards to the LLU and IPStream product portfolios in order to offer equivalent services to BT CPs and non-BT CPs. The building blocks of these products are shown in the diagrams below: LLU and IPStream MPF VOICE NETWORK CP DSLAM BES CP NETWORK MDF LLU(MPF) WWW BT LOCAL EXCHANGE SMPF voice switch MDF LLU(SMPF) BT TELEPHONY NETWORK CP DSLAM BES CP NETWORK WWW BT LOCAL EXCHANGE IPStream voice switch MDF IPStream using LLU(SMPF) BT TELEPHONY NETWORK BT DSLAM BT DSL NETWORK BT LOCAL EXCHANGE CP operated service 8 Equality of Access Board Openreach operated service BT Wholesale operated service Customer wiring WWW Delivery LLU EoI Ready for Service (RFS) (30 June 2006) The LLU obligations are second in size only to the WLR obligations (covered on p11). LLU includes both Shared Metallic Path Facility (SMPF) and Metallic Path Facility (MPF) products, and the Undertakings required BT to reach RFS for MPF and SMPF by 30 June 2006. The EAB validated BT’s delivery of LLU RFS in October 2006. BT had earlier indicated that it might miss the milestone by several weeks. Instead, the new Equivalence Management Platform (EMP) platform over which MPF and SMPF operate was in place and capable of taking orders from the RFS date although it was only required to handle low volumes. By the same date, the Undertakings also required BT Wholesale to be using LLU as an input to the IPStream product for new customers to BT. The delivery of both LLU RFS and IPStream using LLU as an input had been reported previously as two separate obligations. However, the EAB recognised after its October 2006 validation that both formed part of the LLU RFS obligation. The EAB found that in delivering IPstream using SMPF, BT Wholesale did not handle all IPStream orders on an EoI basis and was therefore in trivial breach of the LLU RFS obligation. It found that a certain class of IPStream orders from new customers to BT were not processed using the EMP. Although this issue continued for several months, the numbers involved were small. The EAB did not recommend any remedial action as BT had begun system development to process all IPStream orders using EMP. It completed the work in December 2006 and this was verified by the EAB in January 2007. BT also offered allowances of 25 pence per month per SMPF line to all eligible CPs. The EAB has recommended that BT continues to focus on improving the reliability and functionality of the EMP platform following the trivial breach. IBMC for IPStream using LLU as an input (31 December 2006) The LLU RFS milestone of 30 June 2006 required all new end user orders to be processed on an EoI basis. The corresponding IBMC required IPStream to use LLU (either MPF or SMPF) as an input for all existing end users by 31 December 2006. This involved transferring 8.9 million IPStream records from legacy systems onto new EoI systems and processes. The obligation to transfer IPStream records was the first obligation to require the processing of a high volume of orders using the EMP platform. BT stated that it did not achieve the Installed Base Migration Completion (IBMC) milestone of 31 December 2006 for IPStream consuming SMPF. By that date only 2.7 million customer records had been transferred to the EMP. BT formally notified the EAB of this breach in January 2007, and the EAB confirmed this breach as nontrivial. BT Wholesale said that it had refrained from more rapid transfers because it did not want to jeopardise customer service levels at a time when it was also encountering a high number of service issues. BT has informed the EAB that it achieved mass migration for SMPF on 20 March 2007 ahead of the revised target date of 31 March 2007. It also asserted that it had met the original IBMC milestone for MPF, which involved much smaller volumes of customers. The EAB will assess full delivery in 2007/08. IBMC for BT’s relevant retail broadband service (31 December 2006) This Undertaking required the installed base of BT’s retail broadband service to be migrated by 31 December 2006 so that all services used the EoI IPStream product. BT was also required to ensure that its retail agents were using EoI systems and processes for all broadband transactions. In January 2007, the EAB confirmed that BT had delivered IBMC for retail broadband by the required date and had also delivered some elements ahead of schedule. The Equivalence Management Platform (EMP) The EMP is the strategic system designed to handle the majority of transactions for EoI products. It links a number of specific EoI product systems. The first product to be made available on the platform was LLU in June 2006 and other EoI products are being added to it gradually. The next major EoI product delivery milestone over EMP is WLR RFS. The testing, implementation and deployment of the EMP has been a major cause for industry concern reported to the EAB with recurring problems leading to system downtime. Some CPs have told the EAB that this downtime has made them reluctant to migrate to the new platform. In response, BT has reported that Openreach is working with CPs to inform them of planned system outages ahead of schedule. The EMP will replace so-called ‘tactical’ BT systems – such as Line Share Automation (LiSA) – that pre-date the Undertakings. Openreach has told the EAB that it monitors the performance of the old and new systems and is working with CPs to manage issues related to the new platform. There is some recent evidence of improved stability, although WLR RFS remains a significant test for EMP. Equality of Access Board 9 Delivery Ethernet product portfolio Ethernet services BT EXCHANGE BT EXCHANGE WES WES-LA WEES CP Eqpt BES daisy chain CP Eqpt BES CP NETWORK/ POP Connects end user to CP Connects BT exchange to CP Connects end user to BT local exchange Connects BT exchange to BT exchange Connects end user to end user This product set includes the Wholesale Extension Services (WES) and Backhaul Extension Services (BES) products which are based on Ethernet technology. The Undertakings contain several obligations which require BT to launch EoI versions of various new and existing products. The volumes involved are smaller than those of IPStream consuming LLU or WLR but are of critical importance to many CPs. In January 2007, the EAB confirmed that BT had provided EoI versions of WES and BES by the RFS date of 30 September 2006. BT’s delivery of EoI for the WES and BES product sets was made using the existing tactical order and fault handling systems for extension services (e-Co X), and not via the strategic EMP system. The EAB shares Ofcom’s view that BT should aim to move the Ethernet product set to the EMP system as soon as possible. BT was also required to launch an EoI WES Backhaul (WES B) service by 30 September 2006. Following consultation with industry and Ofcom, Openreach decided that the launch of WES B could be achieved by adding an additional variant to the BES EoI product set (known as ‘BES daisy chain’). The WES B product launch was confirmed by the EAB. 10 Equality of Access Board Two further EoI Ethernet products are covered in the Undertakings but do not have specific delivery dates. The EAB confirmed that BT had launched the EoI Wholesale End-to-End Ethernet Service (WEES) on 30 September 2006 and the EoI WES Access product (WES-LA) in December 2006. In response to a concern raised by one CP, the EAB examined whether Openreach had acted appropriately in launching the WEES product in advance of WES-LA, particularly given that BT Global Services was a major user of the WEES product. The EAB found that the forecast demand for WEES was greater and more certain than for WES-LA, therefore it was reasonable to launch it first. In response to requests, Openreach brought forward the WES-LA launch date to within three months of WEES. The EAB will monitor progress with these two services during 2007/08. BT is also required to deliver IBMC for Wholesale Extension Services by 31 March 2007. This Undertaking required the installed base of BT’s relevant retail Ethernet-based local area network extension services to be migrated so that they all used the EoI WES service. The validation of this Undertaking is currently underway. Delivery WLR product portfolio The Wholesale Line Rental (WLR) portfolio includes Analogue, ISDN2 and ISDN30 products, although only the Analogue product has milestones within this reporting period. WLR Analogue is the product CPs use to offer telephony service and the Undertakings require BT to use the WLR Analogue service to provide its own retail telephony service. BT plans to meet this commitment by launching a new EoI product variant known as WLR3. WLR RFS “good faith gesture” (31 December 2006) In November 2006, BT confirmed that it would not meet the good faith gesture date of 31 December 2006 for WLR to be RFS. It was concerned that the limited functionality of the WLR product would lead to a deterioration in customer experience. BT began using the EoI WLR service for a small number of its customers on 1 January 2007 but did not expect to serve all new end users this way until the RFS date. The formal delivery date for WLR RFS is 30 June 2007 and the failure to meet the voluntary date of 31 December 2006 did not constitute a breach. However, it did trigger the payment of the associated allowances (25 pence per month per WLR line) by BT to all eligible CPs. Going forward, the EAB will monitor BT’s progress towards achieving the formal WLR RFS date. At the time of this report, the EAB believes there are significant risks associated with this milestone. WLR Analogue service transfer requests (1 January 2007) The Undertakings required that, from 1 January 2007, BT had to use the WLR service provider gateway to raise WLR Analogue service transfer requests. These transfer requests arise when BT takes over a customer from another CP, and where that customer is not already a BT customer for any other retail product. This Undertaking will be superseded once WLR RFS is achieved in June 2007. The EAB validated that this Undertaking was delivered and noted that BT had implemented this process for all WLR Analogue customers and not just new customers as required by the Undertakings. This means that about 10,000 transfer orders per week are now being placed on the standard industry Service Provider Gateway (SPG). Management Information System (MIS) separation (22 October 2006) In October 2006, after consultation with industry, Ofcom amended the Undertakings relating to MIS separation. An earlier variation of the Undertakings in September 2006 changed the initial delivery date from 22 September 2006 to 22 October 2006 to allow for consultation on the variation. The key changes resulting from the October variation were: A definition of levels of incremental separation: ‘Level 1 System Separation’: the application of access rights and controls to ensure that users have access only to data to which they are entitled; ‘Level 2 System Separation’: separation of systems data and separate iterations of the application software so that users stay within their access rights. Of the MIS systems shared between Openreach and the rest of BT, 36 were identified by BT to require Level 2 separation by 22 October 2006; For the remaining 13 MIS systems, BT had to implement Level 1 separation by 22 October 2006 (to be tested by independent external audit) and Level 2 separation by 30 June 2010. In the interim BT must provide Ofcom with a roadmap setting out how it will implement Level 2 separation. The EAO completed a validation review of the Level 2 separation of 36 systems and commissioned an independent assurance report from PricewaterhouseCoopers LLP (“PwC”) in respect of the implementation of Level 1 separation for the 13 systems. The scope of PwC’s work was agreed in advance with the EAO.* The EAB confirmed that BT had successfully delivered its amended MIS separation obligations to date. However the EAB notes that tight control of individual employees’ rights of access to the systems – a process which may involve reliance on third party contractors – will be critical to ensure effective separation remains in place. Other BT deliverables A number of key deliverables were delivered toward the end of the last annual reporting period, but validated by the EAB in 2006-07. These are described in the table below: Undertakings obligation Status Areas in BT exchanges as a service (22 March 2006) The EAB has validated that this service – known as ‘NetLocate’ – was launched in March 2006. All CPs were invited to participate in the creation of the terms and conditions of this service and a small number did so. Some CPs were concerned that although the terms and conditions were sufficient for them to start using NetLocate, longer term changes would be needed to enable high volume roll out. BT plans to review the situation with NetLocate customers in July 2007 and notify them of the outcome later in the year. List of exchanges to be vacated (22 March 2006) BT was required to provide Ofcom and CPs with a list of exchanges that it intends to vacate by 22 March 2006 in accordance with its property strategy. The EAB has validated that this information was provided as required. Contract management mechanism (22 March 2006) BT committed to setting up a mechanism to deal with issues surrounding terms and conditions relating to Significant Market Power (SMP) products, excluding certain types of contractual provision. This is known as the Contract Management Mechanism (CMM). The EAB confirmed delivery of this Undertaking in July 2006, although it noted concerns from CPs about whether BT was acting in the Spirit of the Undertakings. In January 2007, BT and a number of CPs commenced a review of the CMM. Although the CMM had not been used, the parties agreed that this was partly a reflection of earlier work to resolve potential CMM issues by other means before resorting to the CMM process. In addition, the number of contract negotiations during the year was not large, and therefore, potential to invoke the CMM process had been limited. Therefore the remainder of the review was limited to finalisation of the arbitration process documents associated with the CMM and to confirm details for the next review of the CMM. * PricewaterhouseCoopers LLP ("PwC") will permit the disclosure of its report, to communication providers regulated by Ofcom subject to prior receipt of a hold harmless letter (in a form specified by PwC) under which the communication provider agrees and acknowledges, inter alia, that PwC, its members, partners, employees and agents neither owe nor accept any duty or responsibility to such third party. Equality of Access Board 11 Delivery Ongoing obligations The EAB monitors two types of ongoing obligation. A significant number of Undertakings do not have a set completion date and are monitored on an ongoing basis. Others have set delivery dates but require ongoing compliance from BT. The EAO monitors BT’s compliance with these ongoing obligations by examining regular monitoring reports from BT and by performing follow up checks, reviews or audits. Partial Private Circuit transparency In its last annual report, the EAB reported that BT had delivered its obligations to provide transparency around partial private circuits (PPCs) and that it would monitor feedback from CPs. BT is required to provide sufficient transparency to enable CPs to understand any difference between the PPCs it sells to them compared to products it supplies to its downstream divisions. It must then use reasonable endeavours to resolve any issues that CPs raise as a result of these differences. During 2006, the EAB maintained a dialogue with CPs and BT over concerns related to transparency of PPC type network elements as used in BT Internet Protocol Virtual Private Network and Featurenet products. As a result of discussions over several months BT provided additional information, particularly on costings. By November 2006, the EAB found that these arrangements were working satisfactorily. Stand-alone Address Matching service The validation of this Undertaking in January 2006 was reported in last year’s report. Since then, the EAB has encouraged Openreach to provide a measure to demonstrate that the number of address matching failures has been reduced following the launch of the stand-alone address matching service. The measure shows that the proportion of successful matches is increasing. See chart below: The EAB monitored BT’s retail divisions to ensure that robust compliance monitoring and reporting mechanisms were in place to detect potentially non-compliant access to IPStream and Ethernet product set. Of the instances reported to the EAB between the IPStream RFS and IBMC dates, a number related to the processing of existing customers and therefore were compliant. The EAB will continue to monitor the number of incidents and will investigate further if necessary. Openreach Internal Trading arrangements The Undertakings require Openreach to have sufficient influence over the assets it requires to deliver service, even if those assets sit within BT Wholesale. One of the key ways of ensuring this is through internal trading agreements and Service Level Agreements (SLAs). These same agreements also help Openreach to manage and operate at arms length from the rest of BT. The EAB undertook a review of the arrangements that were put in place for the first year of trading. On the whole, the EAB found the agreements were satisfactory and seemed to be operating well. It suggested development of additional detail around certain trading activities. One specific issue raised by the review is still under discussion with BT. Wholesale Leased Line products The Undertakings require BT to consult with CPs on parts of the wholesale leased line portfolio to identify reasonable modifications or enhancements. In 2005/06, BT consulted with its CP customers to understand their requirements in relation to leased line products. The review concluded that there was no customer requirement for an additional set of leased line products managed by BT Wholesale. BT has stated that as a result, it will not develop this product set, although it will continue to monitor market requirements and assess commercial opportunities as they arise. Address matching service performance % Successful Matches 100 90 80 70 60 50 40 30 Improved access to engineering appointment books The EAB’s validation review in November 2006 noted a number of issues that require ongoing monitoring. These include the effectiveness, availability and timeliness of the new improved engineering appointment process, and the need for improved communications between Openreach and CPs when engineers arrive at a CP’s customer premises to fulfil an appointment. The EAB will conduct a further review of the operation of the engineering appointment books facility and processes during 2007. Product KPI monitoring 20 10 0 04/06 05/06 06/06 07/06 08/06 09/06 10/06 11/06 12/06 01/07 02/07 03/07 Source: BT Openreach has confirmed that the address matching facility provided by 31 December 2005 included a volume matching facility. As more products are provided on an EoI basis, reliance on stand-alone address matching will diminish. IPStream EOI ongoing controls BT has an ongoing obligation to manage information flows between Openreach and BT’s downstream businesses (BT Retail and BT Global Services). Many of BT’s downstream call centre agents can deal with multiple services and products. This could lead to situations where call centre agents use inappropriate information for the EoI element of the transaction by looking at non-EoI product systems. These possibilities are gradually being precluded by system changes and management controls. 12 Equality of Access Board Since January 2006, BT has met the requirements of the Undertakings to publish Key Performance Indicator (KPI) information each quarter. It has addressed the improvements to its external reporting recommended by the EAB in last year’s report, including the publication of statistical significance z-test charts and additional commentary. BT has also sponsored an independent review of the modified z-test statistical indicator of equivalence and this has led to some changes to the approach. How to understand the KPI graphs The objective of the KPI graphs is to compare service provided to CPs within BT with that offered to non-BT CPs for particular products. If there are significantly differing service levels then the reasons behind this are further investigated to understand whether it is due to noncompliance with the Undertakings or another cause. There are two types of graphs. The preferred option is a graph that uses a statistical method known as a ‘z-test’. If the volumes are low, the z-test cannot be used reliably so the absolute volumes are compared instead. The z-test graph includes control limits, shown on the chart as two parallel lines and, if actual outcomes fall between Delivery During September 2006, the KPI results moved in favour of non-BT CPs and subsequently remained that way. Analysis showed that the fault clearance performance of the IPStream circuits consuming LLU was worse than the performance of those that did not. As BT was the main user of this type of circuit, this trend had a greater impact on BT’s overall fault clearance performance than on that of other CPs. Also, BT passes back to BT Wholesale a higher proportion of cleared faults that fail to be cleared within the target timescales which leads to extended clearance times and poorer fault clearance performance. DataStream Provision 8 Non-BT CPs better 6 Pooled z-test score the lines, there is no statistically significant difference between the service levels experienced by BT CPs and non-BT CPs. In the absolute volume graphs, the two lines representing the performance of BT CPs and non-BT CPs can be seen directly and the EAB can assess whether the difference between the two lines requires further investigation. For each product, the performance of provision (or fulfilment) and repair (or assurance) is monitored. The comparison shown on the KPI graphs is only valid when the product has passed its EoI milestone date. Once RFS has been achieved, all new end users must be fulfilled on an EoI basis and so the provision (ie new order) service levels may be examined. However, not all orders are required to be on an EoI basis at this point. Only once a product has passed both RFS and IBMC milestones can provision and repair be examined on an EoI basis. BT has transparency but not EoI obligations regarding Datastream and Partial Private Circuits (PPCs) to ensure CPs can identify and understand any differences in performance. The KPIs for Ethernet products are not shown given their long delivery lead times as it is too early to capture meaningful trends. The EAB monitors KPIs for these products and will further investigate any significant differences in performance levels. 4 2 0 -2 BT CPs better IPStream Provision and Repair -4 04/06 05/06 06/06 07/06 08/06 09/06 10/06 11/06 12/06 01/07 02/07 03/07 100 Provision 80 Pooled z-test score 60 Non-BT CPs better Source: BT BT CPs better In early 2006, BT and non-BT CPs experienced different provisioning levels. This was because of the high volume of orders to change the speed of broadband lines. This was resolved from January 2006, although in January and February 2007 non-BT CPs experienced better performance. As this difference was temporary, no further investigation has taken place although the EAB will continue to monitor this KPI. 40 20 0 -20 -40 04/06 05/06 06/06 07/06 08/06 09/06 10/06 11/06 12/06 01/07 02/07 03/07 DataStream Repair Provision 100 Repair IPStream Provision The results indicate that non-BT CPs have consistently received a better provision service. BT Wholesale has provided analysis to the EAB, showing that the differing mix of the eight underlying order types was responsible. BT Retail uses a high proportion of ‘Simultaneous Provide of Telephony and Broadband’ order type which is more complex and has a lower fulfilment performance. Over the last twelve months the proportion of this order type has continued to grow and was also the first order type to be processed through the EMP, increasing the performance differential with CPs further during that period. IPStream Repair Repair showed a performance favouring BT up to June 2006, although the chart shows that this position was later reversed and has consistently favoured non-BT CPs after August 2006. Prior to June 2006, in comparison to other CPs, BT Retail was submitting a high volume of very simple faults. These faults were being closed within ten minutes, resulting in an artificially improved fault clearance performance. BT introduced a plan to reduce the number of faults passed to BT Wholesale and the KPI difference in favour of BT was resolved after June 2006. 90 % Faults cleared on time Source: BT IPStream RFS date: 31 December 2005 Relevant BT Retail Broadband product IBMC: 31 December 2006 80 70 60 50 40 04/06 05/06 06/06 07/06 08/06 09/06 10/06 11/06 12/06 01/07 02/07 03/07 Non-BT CPs Non-BT CPs 12 mth Avg BT CPs BT CPs 12 mth Avg Source: BT (Note: Repair volumes for BT are less than two hundred per month therefore the z-test analysis has not been applied.) Looking at absolute performance levels, the experience of BT CPs has been broadly comparable with that of non-BT CPs. In November 2006, there was a one-off reduction in performance for BT CPs offset by a move in the other direction in January 2007. Given the small volumes, this does not appear to be of statistical significance although the EAB will continue to monitor this area. Equality of Access Board 13 Delivery Partial Private Circuits (PPCs) BT publishes KPIs for PPCs on its website on a quarterly basis, but the EAB is unable to use these charts to reliably analyse the performance experienced by BT CPs versus that experienced by non-BT CPs. This is because BT CPs and non-BT CPs consume two different private circuit products: non-BT CPs use PPCs to connect an end-customer to their network, while BT CPs use Private Circuits (PCs) to connect one end customer to another. BT has chosen to publish these graphs for the sake of transparency and completeness. Analysis of the KPIs comparing PPCs and PCs show that BT’s quarterly provision experience is very similar to that of external CPs. However, the repair KPIs show that non-BT CPs’ repair performance is consistently better than the performance experienced by BT CPs. These differences in repair performance appear to be a result of the known product differences between PPCs and PCs. LLU (SMPF and MPF) Openreach launched the EoI versions of SMPF and MPF by 30 June 2006 and provision KPI data has been available to the EAB since that date. However, there have been very small volumes of MPF orders so far and this means that valid statistical analysis can be undertaken only for SMPF Provision. BT has informed the EAB that it achieved mass migration for SMPF on 20 March 2007, and that it had also met the IBMC for MPF. Therefore, repair data is not yet available for these products. Conclusions regarding product KPIs The product KPIs are an increasingly important monitoring tool for the EAB. They provide a valuable overview of relative performance which has allowed the EAB to ask for further analysis from BT to identify and understand potential issues. One area that requires some further development is migrations between products or between CPs. The Undertakings require products that have achieved EoI RFS to have an EoI Migration process in place. They also require that the EAB “shall pay particular attention to proposed KPIs for migrations…”. There have been ongoing consultations between Ofcom, BT and industry during 2006 to agree the migration processes that should be used. Once the outcome of these discussions is known, BT will be able to provide the associated migration KPIs. The first migration KPIs are expected to be available by May 2007. In the meantime, the EAO has proposed interim measures for IPStream and Datastream migrations. These do not currently indicate any matters of major concern. Non-BT CPs have raised a number of questions regarding the product KPIs. Some requested more detail on their own performance in comparison to the aggregated data in the charts, or the breakdown of the product KPIs into their component parts. Others requested that BT provides more detailed commentary with its quarterly KPI publication. BT continues to upgrade its reporting of KPIs and has included the detailed commentary requested by CPs. Monitoring of variations and exemptions SMPF Provision using EMP Modified pooled z-test score 10 Non-BT CPs better 0 -10 -20 BT better -30 -40 11/06 12/06 01/07 02/07 03/07 SMPF Basic Provide Source: BT The SMPF basic provide graph shows that external CPs were experiencing better performance at first. Analysis showed that this variance could be due to the different order types used by BT and non-BT CPs. The ‘Simultaneous Provide’ order type, which is subject to poorer performance than a ‘standard’ new provide, was the main BT order type. However since January 2007, the graph shows that performance has improved in favour of BT CPs. Data analysis and process investigation by BT has established that the better performance experienced by BT CPs can be attributed to BT Wholesale’s use of the new ‘flexible jumpering’ service being offered by Openreach. Normally, jumpering takes place on the Customer Committed Date (CCD). However, if CPs opt for flexible jumpering, this work can be carried out in advance of the CCD thereby shortening the provisioning time. Openreach has stated that all CPs were informed of this new service, although to date no non-BT CP has opted for flexible jumpering. The EAB is reviewing this situation. 14 Equality of Access Board The EAB has oversight of the variations and exemptions to the Undertakings agreed by Ofcom and BT. During 2006/07, the EAB confirmed that BT was complying with a number of the variations and exemption agreements including Local Area Network Extension Services2 (LES2), Megastream Ethernet, Openreach ancillary services including ISDN Connect and provision of low-loss exchange lines. Other Openreach ancillary services including temporary service, lines at non-served premises and alternatively routed lines will be reviewed following the launch of WLR3. A number of obligations arising from the variations and exemption agreements are scheduled to be delivered by BT over the next few years, and the EAB will monitor BT’s compliance with these obligations. These include the WLR-supplier-of-last-resort process and the ISDN and Highway Conversion Process in 2007. Other obligations due during 2008-2011 include Featurenet, 21CN network uplift programme and Pay and Call. Full details of the EAB’s work in this area can be found at http://www.bt.com/eab. Behaviour Measuring behavioural change The EAB monitors behaviour associated with the Undertakings and proposes behavioural measures and performance targets. It also hears the views of communications providers (CPs) to assess the impact of behavioural change on customers. This section of the report describes recent improvements to the EAB’s behavioural monitoring process and evaluates behavioural trends in a number of areas of BT’s operations. The EAB and the EAO worked with BT’s Group Programme Office to develop a ‘behavioural dashboard’ to bring together indicators relevant to the Undertakings. The dashboard – which was approved by the EAB – provides more detailed coverage of BT employee and commercial behaviour than was previously available. Excerpts from the dashboard are included in this report. The Behavioural Dashboard consists of three categories: Drivers, Activities and Outcomes. Drivers Drivers are metrics on the progress of Undertakings-related initiatives to drive cultural and behavioural change in the company. Code of Practice Training 100 % Actual completions Introduction to the EAB’s Behavioural Dashboard 95 90 85 80 Managers The Code of Practice The Code of Practice (CoP) is produced by BT to explain the Undertakings to BT employees. It deals with the organisational changes resulting from the Undertakings, restrictions on the sharing of certain information and limitations on influencing Openreach’s and BT Wholesale’s commercial policy. The Code of Practice was sent to all BT employees in December 2005. At the same time BT introduced an associated training programme: ‘It Matters’. BT set self-imposed targets to achieve training completion rates of: UK managers – 95% by 30 June 2006 UK Team members – 90% by 31 December 2006 Team Members March 2006 March 2007 Source: BT The chart above shows the percentage of training completion for managers and team members. Completion rates have increased over the last year, and by March 2007, had exceeded BT’s initial targets. The EAB has recommended that BT adopts the same targets for high risk contractors as it has achieved for employee training, even though this is not a direct requirement of the Undertakings. BT divides its contractors into high and low risk for the purpose of training in the Undertakings; with roles such as software developers and call centre staff classed as high risk and others – such as catering and security staff – classed as low risk. The EAB reviewed the Code of Practice and concluded that the majority of the Code’s principles are being effectively applied. The EAB has taken steps to ensure that all of the principles are part of its monitoring and validation activity, and that a monitoring plan exists for each one. Equality of Access Board 15 Behaviour Activities Undertakings-related complaints to BT confidential helpline This section of the dashboard measures the behaviour of BT employees including the way they work and their interactions with customers. The measures – known as ‘activities’ – are grouped to reflect the behaviour of individual employees and patterns in commercial behaviour. 33% Individual behaviours Measurements of individual behaviour include: Peripheral vision Peripheral vision is where call centre agents within BT Retail and BT Global Services who deal with multiple products and systems could use inappropriate information in an EoI product transaction. BT uses behavioural controls to prevent downstream call centre agents accessing inappropriate information. To measure the effectiveness of these controls, BT produces a monthly monitoring report showing all identified incidents of inappropriate access to information. Each incident is followed up with re-training with the potential for disciplinary action. The number of incidents is both very low (considering the size of BT’s call centre workforce) and decreasing over time. By the fourth quarter of the year, BT Retail had recorded no cases of inappropriate access. BT Global Services had a compliance rate of over 99% although there were a minor number of incidents and the EAB has encouraged this LoB to learn lessons from BT Retail to achieve a similar outcome. As a result, BT Global Services has put in place a behavioural change programme to drive the continued reduction in incidents. The number of incidents shown in the graph reflects a very small proportion of the day-to-day transactions conducted by call centre agents. For more information, see Delivery section, p12. Information sharing Equivalence Source: BT Other Individual Behavioural Measures The EAB also keeps a number of other behaviourial measures under review, including call monitoring, mystery shopping results, monitoring of peripheral vision for Ethernet advisers and CPs’ perceptions of their account managers’ behaviour. There were no issues that had to be pursued as a result of these reviews. Commercial behaviours Measurements of commercial behaviours include: Statement of requirements SOR Status-cumulative data from Feb-06 to Mar-07 20 100 18 90 16 80 14 70 12 60 10 % Modified pooled z-test score Volume of non compliant incidents identified on CSS for broadband advisors 67% 50 8 40 6 30 4 20 2 10 0 0 04/06 05/06 06/06 07/06 08/06 09/06 10/06 11/06 12/06 01/07 02/07 03/07 BTGS BT Retail Pending Rejected Accepted Withdrawn BT CPs (84% of the volume) Non-BT CPs (16% of the volume) Source: BT Source: BT Confidential Employee Complaints The EAB monitors the pattern of Statement of Requirements (SORs) accepted or rejected by Openreach from non-BT CPs compared with those from BT CPs. The evidence shows that a higher percentage of non-BT CPs’ SOR requests were rejected by Openreach, although those CPs submitted far fewer SORs. This is an area of considerable industry interest and the EAB will undertake a thorough review of the process during 2007. BT introduced a confidential process for handling employee queries and complaints regarding Undertakings issues. None of the six calls which were received over the year as part of this process were found to have led to a breach of the Undertakings and most concerned information sharing rules as the graph opposite shows: 16 Equality of Access Board Behaviour Appointment books performance for EMP and SPG Customer perceptions Openreach has made the new appointment booking facility available on two systems – Service Provider Gateway (SPG) and Equivalence Management Platform (EMP). SPG data is not yet available, but the availability of the EMP system for this facility has been consistently above 99.5% over the past year. BT conducts a number of customer satisfaction surveys. These include separate surveys of CP customers by BT Wholesale and Openreach: BT Wholesale Undertakings-related customer perceptions BTW Customer Satisfaction Survey The EAB requested that the EAO conduct a detailed review of Customer Business Management, focusing on the account management choices offered to CPs and the arrangements for placing orders for EoI products. The review also considered CPs’ views of whether their chosen options had resulted in their being disadvantaged in terms of pricing, service and quality. The review found that there was inadequate communication about account management alternatives. BT has agreed to clarify its policies in this area. The EAO also highlighted a common concern that the qualitative improvements expected of the new account management relationships are not yet being delivered by Openreach. CPs indicated that more could be done to champion fair access to products and services and to respond to customer development plans. This issue had been recognised by Openreach which has since embarked on a major behavioural change programme encompassing initiatives that seek to improve customer relationships. Outcomes This category of the behavioural dashboard assesses the results of behavioural change associated with the Undertakings. Measures of outcomes include: Complaints received by BT Undertakings-related complaints from CPs to BT closed in 2006-07 90 80 % Score Customer Business Management review 70 60 50 Question A Question B March 2006 March 2007 QA = “How confident are you that BT Wholesale will deliver against its commitments from the TSR?” QB = “How, thinking more specifically about equivalence, do you believe BT Wholesale delivers products equivalently to all its customers?” Key QA confidence rating between 1 (not at all confident) and 10 (completely confident); all respondent scores are then modelled to give a score on a 1 to 100 scale index. QB = % of respondents that answered "yes" Source: BT BT Wholesale customer satisfaction results show a small improvement over the year in the belief that BT Wholesale delivers its products equivalently and a small decrease in confidence in BT Wholesale’s delivery of its TSR commitments. 3 8 Openreach Undertakings-related customer perceptions Openreach Customer Satisfaction Survey 70 60 % Score 17 50 40 Spirit Equivalence Information sharing Source: BT Most of the 28 closed CP complaints received by BT were directed to Openreach (53%) while the rest were for BT Wholesale (29%) and BT Retail (18%). All these complaints were investigated by BT which asserts none resulted in a breach. The majority of complaints relate directly to the letter of the Undertakings and the degree of equivalence achieved by BT in delivering products and services. Less than one-third related to the spirit of the Undertakings and the behaviour of BT’s employees. The EAB has been informed of other concerns about the Spirit of the Undertakings during its CP engagement programme, and these have been shared with BT. Due to their informal nature however, they are not captured in BT’s reporting data. 30 Question A Question B March 2007 QA = “How confident are you that Openreach will deliver against its commitments from the TSR?” QB = “... do you believe Openreach delivers products equivalently to all its customers?” Key QA confidence rating between 1 (not at all confident) and 10 (completely confident); all respondent scores are then modelled to give a score on a 1 to 100 scale index. QB = % of respondents that answered "yes" Source: BT Equality of Access Board 17 Behaviour The Openreach survey commenced during 2007, so no previous year’s results are available for comparison. Within the year, the numbers show an improvement in respect of Question B. Openreach and BT Wholesale customer satisfaction surveys are processed differently and therefore the reported outcomes are not directly comparable. Differences include the approach to sampling and the weighting of results by revenue. BT is working with the EAO to provide more closely comparable data in future so that, whilst still meeting BT’s needs, the data may also more readily assist the EAB to discharge its monitoring responsibilities. Openreach engineers’ behaviours The EAB has heard concerns from some CPs regarding the behaviour of Openreach engineers when dealing with end-customers. As a first step in assessing trends in this area, Openreach is in discussions with industry regarding implementing a survey on engineering behaviour in the first half of 2007/08. Openreach Product Customer Satisfaction Survey The EAB was keen to see how satisfied CPs were with the EoI products that CPs are now using. Although data by product is not available, at an aggregate level the information shows that the time to repair faults has the lowest level of satisfaction. BT employee surveys BT conducts a number of surveys to assess employee behaviour with regards to the Undertakings. These include: BT Regulatory Culture Survey BT’s Regulatory Compliance team commissioned a survey of approximately 3,000 BT employees which obtained data on Undertakings-related perceptions. The survey’s results reported recently to the EAB were generally positive although BT identified some areas requiring further action. BT CARE Survey results BT Employee Survey 80 70 % Scored Positively 60 50 40 30 20 10 0 Question A Question B March 2006 March 2007 QA = “I believe that BT treats all customers, whether internal or external, in a fair and equal manner?” QB = “The company helps me comply with our legal and regulatory obligations?” Source: BT The EAB reviews detailed results from BT’s internal employee survey. These results indicate that employees are confident that BT treats its customers equivalently and helps employees to meet their regulatory obligations. The results show a slight decrease year on year. 18 Equality of Access Board It Matters During 2006, both BT Wholesale and BT Global Services have conducted employee surveys to measure the effectiveness of the Code of Practice ‘It Matters’ training. The results suggest that BT employees are developing a good understanding of the impact of the Undertakings with supplementary support available as required. Those not certain of their role appear prepared to seek further clarification. Conclusion In summary, the outcome measures do not raise major concerns, although they do not reflect the degree of change that might have been hoped for. This may be because change can only be measured effectively over a long period, and the Undertakings are still a new way of working for many BT employees. Ongoing improvements The Behavioural Dashboard is a recently introduced set of measures and will be developed further over the coming year. In January 2007, the EAB noted two issues where improvement was needed: training delivery for high risk contractors and action to reduce incidents of ‘peripheral vision’ by BT Global Services’ customer service teams. It has asked BT to address these issues. Despite the progress that BT has made in encouraging behavioural change among employees, customer reaction remains mixed. In April 2006, Ofcom published a survey of BT’s wholesale customers which identified a perception among some CPs that Openreach’s management focused on “ticking the box” to comply with the letter of the Undertakings. It also pointed to the risk that formal compliance might take precedence over “getting things right”. In November 2006, the Communications Management Association (CMA) conducted a survey among members of their perceptions of Openreach and reported the findings to the EAO. Whilst the survey involves only a small sample of end-users, it provides additional data on end-users’ perceptions of Openreach delivery. For example, nearly two-thirds of respondents offering a view said that Openreach engineers delivered a good service on their behalf. However, less than a fifth said access to engineering appointments had improved. In addition, the great majority of respondents reported that Openreach engineers act in an impartial way “between BT and BT’s competitors”. The EAB recognises that cultural change in an organisation as large and complex as BT is inevitably a long process. In future, it expects to see evidence of trends that show that BT is continuing to make significant progress in encouraging appropriate behaviour. The EAB will continue to monitor this indicator of the delivery of the Undertakings. Outlook Looking to 2007/08 The remaining milestones are fewer in number, but larger in scale. Milestones already successfully delivered need to be sustained through compliant behaviours. Also, as BT’s 21st Century Network programme develops, the challenge is to ensure that this project is delivered in a manner that supports equivalence. This section looks at these three areas in more detail. Future Undertaking milestones Ongoing compliance measures The key milestones in the coming year are as follows: As more Undertakings pass their milestones, the EAB will focus on ongoing compliance. This is an important aspect in the delivery of the Undertakings as it establishes whether BT is acting compliantly on a consistent basis across all relevant transactions. The EAB’s ongoing compliance monitoring is focused on three main areas: Wholesale Analogue Line Rental RFS In November 2006, BT confirmed that it would not meet the voluntary milestone of 31 December 2006 for WLR to be RFS. It was concerned that the limited functionality of the WLR product would lead to a deterioration in customer experience. The EAB will monitor BT’s progress towards achieving the formal WLR RFS date of 30 June 2007. At the time of this report, the EAB believes there are some significant risks associated with this Undertaking. Wholesale ISDN2 and ISDN30 Line Rental RFS BT is also required to deliver RFS for Wholesale ISDN2 Line Rental (30 September 2007) and Wholesale ISDN30 Line Rental (31 December 2007). The EAB will monitor the delivery of these obligations, which it considers to be at risk. Operational Support Systems and Management Information Systems Monitoring the separation of Operational Support Systems (OSS) and Management Information Systems (MIS) will be a key focus for the EAB in 2007/08. The implementation of system separation will make it more straightforward for BT to demonstrate to the EAB that no inappropriate transactions are taking place. In March 2007, Ofcom published a consultation on a variation to the Undertakings on OSS separation. The variation involves the introduction of a series of binding milestones towards the full delivery of physical separation of OSS by 2010. This variation, if confirmed, will lead to further EAB monitoring activity in this area. Product KPIs Product KPIs monitor the degree to which equivalence of output is being delivered. They can be used to indicate whether products are being operated on an EoI basis. Work to date on IPStream has shown that the product KPIs are easily misintrepreted. They often require further analysis to understand whether top level service differences are brought about by non-compliance or other factors. The EAB expects that product KPIs will become more informative once further data is available on the LLU and Ethernet portfolios. The EAB will also focus on migration KPIs once the migration processes have been agreed with Ofcom and industry. Behavioural Measures As each product passes its EoI milestones, the EAB will ask BT to implement additional monitoring of the behaviour of call centre agents and engineers to ensure that the equivalence concept is not undermined. Now that Openreach is established and fully operational, the EAB will put more weight on behavioural measures, including measures relating to the handling of processes such as ‘Statement of Requirements’ to manage product development equivalently. Equality of Access Board 19 Outlook Ongoing Audits The EAB will revisit the ongoing processes and controls to ensure that compliance with those milestones already delivered continues. The EAB has planned a series of audits to take place during 2007/08 to revisit most of the key Undertakings to ensure that compliance is maintained. The EAB plans to focus increasingly on whether a level playing field for all CPs is delivered in practice. It will do this by looking at situations where more than one equivalent product or system exists and BT uses one and non-BT CPs another. This can result in different service levels even though each solution is equivalent. This may occur for operational reasons, for example the new EMP system and older legacy systems may be operated in parallel for some time to allow CPs to migrate between systems. Alternatively, offering only one variant of a product for all types of CP may not meet market needs. The EAB will continue to monitor the issue and will examine instances where there appears to be no roadmap for convergence of products used mainly by BT and products used by CPs. Next generation networks (NGN) The Undertakings set out broad principles regarding NGNs rather than obligations of the kind included for other product portfolios. During the year, the EAB has developed its understanding of BT’s 21CN programme and the compliance issues involved. It has met the Chairman of NGNuk and BT’s 21CN Programme Director, and has also heard the views of CPs regarding NGN roll out. The EAO has attended the Consult 21 Steering Group and some of its working groups as an observer. The EAB is satisfied that the Steering Group is functioning effectively. CPs have expressed concern to the EAB that it can be difficult to manage the large number of updates provided by the Steering Group. BT has taken steps to address this issue and the EAB will continue to monitor the situation. The EAB is developing success criteria for the Undertakings relating to NGN. It is satisfied with BT’s compliance with the obligation to participate in an NGN industry group and an operational adjudicator scheme. It is also satisfied with BT’s progress towards agreeing arrangements for making compensation payments, and the steps BT is taking to fulfil its obligations on broadband dialtone and NGN implementation, which the EAB will continue to monitor. 20 Equality of Access Board The obligations regarding network access provision, design and equivalence are more complex. They are intended to cover areas such as ensuring network access is not foreclosed by certain design decisions and ensuring that its pricing is based on efficient design costs. They also ensure that network access is made available on an EoI basis within adequate timescales to allow all CPs to compete effectively. The EAB will continue to develop its approach in these areas and this will become one of the key monitoring areas in 2007/08 and beyond. BT reorganisation On 24 April 2007, BT announced a reorganisation of its businesses with the creation of BT Design and BT Operate. In due course, the EAB will review the impact of these changes on BT’s approach to ensuring compliance with the Undertakings. About this Report About this Report The EAB is required to submit an annual report to Ofcom providing its views on a range of matters relating to BT’s compliance with the Undertakings. The EAB must also publish a summary report (the ‘EAB Annual Report’) on its activities which is subject to independent assurance. This is the second EAB Annual Report and, like the first Report, it includes a number of key opinions which are independently assured by PricewaterhouseCoopers LLP (“PwC”). PwC also undertakes assurance activity on key performance indicators (KPIs) and other data in this Report and assesses whether this Report is consistent with the EAB’s annual report to Ofcom. PwC’s independent report and opinions are set out later in this report. This section explains the reporting policies adopted by the EAB in forming its opinions. Opinion on the EAB’s governance On page 5, the EAB reports that its governance arrangements have been strengthened this year. In reaching this opinion the EAB considered the following matters: The EAB’s confidence in the completeness and accuracy of the EAO’s compliance reports to highlight issues that are critical to the delivery of the Undertakings and identify actual or potential breaches. The actions taken by the EAO and BT to address governance issues identified in last year’s Report, particularly the commissioning and documentation of internal validation reviews. The performance of the EAO’s breaches and complaints processes. The findings of the BT Internal Audit review of the EAO in autumn 2006 and of BT and Ofcom’s joint Review of the EAB following one year of its operation. The views of CPs expressed during direct engagement with the EAB. The relevant skills and experience of EAB members and their understanding of the EAB’s role and responsibilities within BT. The EAO’s access to information held by BT; and the adequacy of the process for compiling the annual reports and the ability of the EAB to have unfettered influence on the detailed content and conclusions of the reports. Opinion on the adequacy of resources in support of the EAB This report concludes that BT has continued to provide satisfactory resourcing to enable the EAB to fulfil its remit (page 5). In reaching this opinion the EAB has had regard to: The timeliness and quality of monitoring reports and reviews submitted by the EAO. The quality of support provided by the EAB Secretariat in respect of the EAB’s meetings and its reporting responsibilities. The results of a board review exercise conducted in autumn 2006 in which individual EAB members were asked for their opinion on support for the EAB. The views of the Director EAO and the EAB Secretary on the resources at their disposal. The results of the independent review of the EAB by BT Internal Audit and the joint review by BT and Ofcom in autumn 2006 referred to above. The implications of views of CPs expressed during direct engagement with the EAB. Opinion on BT’s governance associated with the Undertakings On page 7, the EAB reports that BT’s governance arrangements associated with the Undertakings have improved significantly in the past year. In reaching this opinion the EAB has had regard to the following processes to identify evidence that BT has a clear framework for directing implementation of the Undertakings: Effective mechanisms for ensuring complete and accurate monitoring of implementation. Effective measures in place to detect potential breaches and to report and remedy actual breaches. Adequate processes to handle complaints relating to the Undertakings. Effective programme of reporting to the BT Group plc Board and relevant Board committees. The EAB also takes account of the following information resulting from the implementation of these processes: The findings of the EAO’s monthly monitoring reports on BT’s compliance with the Undertakings, including steps being taken to deliver future commitments. The Director EAO’s monthly report to the EAB which, inter alia, tracks and comments on governance developments. Quarterly reports from the Openreach CEO, on the measures being taken to ensure and maintain compliance in his organisation. The views expressed by individual CPs in presentations to and direct dialogue with the EAB. Equality of Access Board 21 About this Report The EAO’s quarterly reports on complaints relating to the Undertakings, which include an assessment of developments in BT’s complaints handling arrangements. Experience of reporting to the EAB on breach investigations by BT and the EAO. The results of the EAO ‘Quick Checks’ process, where all issues raised by CPs or internally are assessed to determine if they require further investigation. Milestone Due Date EAB Opinion Areas in BT Exchange as a service 22 March 2006* Delivered on time List of Exchange vacations 22 March 2006* Delivered on time Contract Management mechanism 22 March 2006* Delivered on time LLU RFS, including IPStream using LLU 30 June 2006 Not achieved: trivial breach of SMPF RFS. RFS for WES, BES, WES Backhaul 30 September 2006 Delivered on time Level 2 of separation of Management Information Systems 22 October 2006 Delivered on time WLR Analogue RFS (good faith gesture) 31 December 2006 Not achieved though not a breach Undertaking is at risk i.e. there are key issues that could impact the delivery of the Undertaking to the agreed date but these are being managed within the programme. IBMC for IPStream using LLU 31 December 2006 Not achieved: non-trivial breach Undertaking date has been missed or is in jeopardy i.e. there are Key unresolved issues that will impact the delivery of the Undertaking to the agreed date. IBMC for BT’s relevant broadband service 31 December 2006 Delivered on time WLR Analogue service transfers 1 January 2007 Delivered on time Opinions on BT’s delivery of the Undertakings during 2006/07 In the section ‘BT’s Undertakings delivery performance’, the EAB reports its opinions on BT’s delivery of several key Undertakings during the year. The individual opinions (summarised in the table opposite) are determined through the EAB’s Undertakings validation process, which is underpinned by a monthly EAO report on the status of each relevant Undertaking. The report includes the following status indicators: Blue Green Amber Red Summary of the EAB’s opinions on BT’s delivery of key Undertakings milestones reported in pages 8 to 14. Undertaking completed, auditable evidence provided to the EAO (or Internal Audit and Regulatory Compliance (“IARC”) acting on its behalf) and validation successfully completed. Undertaking delivery on track, or Undertaking completion asserted by BT And EAO validation is underway or is awaiting auditable evidence of achievement. Only the EAO can move an Undertaking from Green to Blue status. This decision is based on a validation review to determine whether BT has completed the requirements of the Undertaking by the due date. The EAO leads this review having previously agreed success criteria with BT, and where appropriate having commissioned IARC to undertake review activity on its behalf. The EAB and BT have identified four broad categories of success criteria – process, systems, people and product – which are applied to all major deliverables. Each of these categories is populated and agreed in advance for each Undertakings deliverable. Examples of more detailed criteria under these headings include the existence of an operating model for equivalence signed-off and in use by BT (Product), inter-LOB trading agreements agreed and in use (Process), evidence of training documentation and delivery (People) and operational readiness testing (Systems). The EAO has developed an Audit and Validation Plan (AVP). This is designed to ensure a rigorous approach is taken to the monitoring and reporting of all deliverables and ongoing compliance. This takes account of any exemptions from or variations to the Undertakings. 22 Equality of Access Board *Validated in 2006/7 Opinions on BT’s progress towards Undertakings due in 2007/08 The EAO’s monthly status report also informs the EAB’s plans for monitoring, and perspectives on, BT’s future compliance set out in the ‘Looking to 2007/08’ section of this Report. This section includes the EAB’s opinion that there remain ‘some significant risks’ associated with BT’s delivery of the Wholesale Analogue Line Rental RFS of 30 June 2007, and that the delivery of ISDN2 and ISDN30 later in 2007 is ‘at risk’. Product KPI monitoring The EAO monitors BT’s KPIs on products covered by the Undertakings on a monthly basis, and reports on them to the EAB. In conducting this review the EAO considers the accuracy of KPI data supplied by BT, the effectiveness of BT’s mechanisms for ensuring complete and accurate reporting of KPIs and BT’s future plans for KPI development. BT publishes these KPIs on a quarterly basis. The EAO’s monthly report highlights significant changes in individual indicators which might suggest potential non-equivalence. The EAO investigates these situations further with BT and reports findings to the EAB. Independent Assurance Report to the Equality of Access Board and Ofcom Respective responsibilities of the Equality of Access Board and PricewaterhouseCoopers LLP We have been engaged to express an independent opinion on selected aspects of the Equality of Access Board (“EAB”) Annual Report for the year ended 31 March 2007 (the “Report”). The preparation of the Report in accordance with the requirements of the Undertakings given to Ofcom by BT Group plc (“BT” or the “Group”) pursuant to the Enterprise Act 2002 effective 22 September 2005 (the “Undertakings”) is the sole responsibility of the EAB. There are no generally accepted standards for reporting on compliance with the Undertakings or in respect of related performance measures. The reporting policies adopted by the EAB in forming their opinions expressed within the Report are described in the section titled ‘About this Report’ on pages 21 to 22 (the “Reporting Policy”). Scope and approach Our engagement was designed to provide assurance on: whether, in our opinion, the EAB’s opinions in respect of: its governance arrangements; BT’s governance associated with the Undertakings; BT’s delivery of the Undertakings during 2006/07; and BT’s progress towards Undertakings due in 2007/08; are fairly stated in accordance with the Reporting Policy. These opinions are shown on pages 5 and 7 within the The Undertakings Governance Framework, and page 19 in Looking to 2007/08 and reproduced in bold italic text within the Reporting Policy and in respect of BT’s delivery of the Undertakings during 2006/07 shown in the table on page 22 of the Reporting Policy with further description given on pages 8 to 14 of the Report under “Major Milestones” (the “EAB’s Opinions”). In this regard, we planned our procedures to have a reasonable expectation of detecting material misstatements or omissions in the EAB’s Opinions. We obtained an understanding of the relevant controls and procedures applied by the EAB and the EAO to generate, aggregate and evaluate information in respect of the Group’s governance, delivery and ongoing compliance with the Undertakings, including the EAO monitoring and reporting, the audit and validation, the quick checks, the exemptions and variations and the breaches and complaints processes. We performed tests of these controls and procedures and reviewed the work undertaken by BT’s Internal Audit and Regulatory Compliance department (“BT IARC”) on behalf of the EAB including, to the extent considered necessary, review of detailed workpapers and re-performance of testing; whether, in our opinion, the Report is consistent with the EAB’s annual reporting to Ofcom which consists of the Report and certain additional annexes (the “Ofcom Report”). In this regard, we planned our procedures to have a reasonable expectation of identifying any material inconsistency in the Report compared with the content of the Ofcom Report. We performed a full comparison of the text of the Report to the more detailed Ofcom Report. Other than the consistency of the Report and the Ofcom Report we have not been engaged to provide assurance over the Ofcom Report. Accordingly we do not express any separate opinion on the Ofcom Report; whether, in our opinion, the Product Key Performance Indicators (the “KPIs”) for IPStream Provision and Repair, Datastream Provision, Datastream Repair, SMPF Provisioning using EMP shown on pages 13 and 14 are properly prepared in accordance with the Reporting Policy. In this regard, we planned our procedures to provide us with reasonable assurance they are properly prepared in accordance with the Reporting Policy from the underlying management information of the Group. We completed, in conjunction with BT IARC tests over data generation, consolidation and reporting; and whether, in our opinion, the numerical and graphical measures of Code of Practice Training completion, Volume of non-compliant incidents identified on CSS for broadband advisors, Undertakingsrelated complaints received to BT confidential hotline, Statement of Requirements status, analysis of closed CP complaints received by BT, BT Wholesale Customer Satisfaction Survey, Openreach Customer Satisfaction Survey and BT Employee Survey related to measuring behavioural change disclosed on pages 15, 16, 17 and 18 (the “Measures of Behaviour”) are properly compiled from the underlying management information of the Group. In this regard, we planned our procedures to provide us with reasonable assurance they are properly compiled from the underlying management information of the Group. We completed, in conjunction with BT Internal Audit, tests over data consolidation and reporting. In addition, we reviewed the minutes of EAB meetings, discussed with employees of the Equality of Access Office the processes to collate the Report and reviewed the remainder of the Report for consistency with our knowledge of the Group in order to report whether anything came to our attention to indicate that the remainder of the Report is inconsistent with the findings of our work. Our engagement includes the expression of an opinion on the fairness of the EAB’s opinions in respect of BT’s governance measures associated with the Undertakings, BT’s delivery of key Undertakings milestones during 2006/07 and BT’s ongoing compliance with the Undertakings in 2006/07. Our assurance procedures, which are described above, focus on understanding and evaluating the relevant controls and procedures applied by the EAB and the Equality of Access Office (“EAO”) to generate, aggregate and evaluate information in respect of the Group’s governance and compliance with the Undertakings. We have not been engaged to provide any separate independent assurance over the internal controls and other actions implemented by the Group to ensure compliance with the Undertakings. Accordingly we do not express an opinion in this regard. We planned and performed our evidence-gathering procedures to obtain a basis for our conclusions in accordance with the International Standard on Assurance Engagements 3000 (Revised) – “Assurance Engagements other than Audits or Reviews of Historical Information”. We have not performed an audit, and therefore do not express an audit opinion, in accordance with International Standards on Auditing (UK and Ireland). We believe that our work provides a reasonable basis for our conclusions. Considerations and limitations The Group’s governance measures to ensure compliance with the Undertakings represent a set of internal controls and other actions designed to provide reasonable assurance regarding compliance, in all material respects, with each of the Undertakings and to support reporting of compliance with those Undertakings. Further, the EAB’s governance measures to monitor, assess and report on the Group’s compliance with the Undertakings represent a set of internal controls and other actions designed to provide reasonable assurance Equality of Access Board 23 regarding the assessment of compliance, in all material respects, with each of the Undertakings. Because of the inherent limitations in any set of internal controls, for example the degree of judgement required in applying certain controls, internal controls may not prevent, detect or report non-compliance with the Undertakings. Also, projections of any evaluation of effectiveness to future periods are subject to the risk that controls may have become inadequate because of changes in conditions, or that the degree of compliance with the policies or procedures may deteriorate. This report, including the conclusion, has been prepared for and only for the EAB and Ofcom for the purpose of allowing the EAB to meet its requirements under the Undertakings and for no other purpose. We do not, in giving this opinion, accept or assume responsibility for any other purpose or to any other person to whom this report is shown or into whose hands it may come save where expressly agreed by our prior consent in writing. Conclusions In our opinion: the EAB’s Opinions, shown in bold italic text on pages 21 and 22 of ‘About this report’ and in respect of delivery of the Undertakings during 2006/07 shown in the table on page 22 of ‘About this report’ are fairly stated in accordance with the Reporting Policy; the EAB Annual Report for the year ended 31 March 2007 is consistent with the Ofcom Report; The KPIs on pages 13 to 14 are properly prepared in accordance with the Reporting Policy with the exception of the “SMPF Provisioning using EMP” KPI shown on p14 which is properly compiled from the underlying management information of the Group extracted from the Equivalence Management Platform (“EMP”). Whilst all aspects of the EMP are included in the BT IARC programme of testing from 1 April 2007 this was not complete by the date of this report. As such we have been unable to form an opinion on the processes and controls relevant to data generation and consolidation within the EMP; the Measures of Behaviour on pages 15 to 18 are properly compiled from the underlying management information of the Group; and Nothing has come to our attention to indicate that the remainder of the EAB Annual Report for the year ended 31 March 2007 is inconsistent with the findings of our work. PricewaterhouseCoopers LLP Chartered Accountants London 10 May 2007 24 Equality of Access Board Terms used in this report 21CN – BT’s 21st Century Network programme AVP – The EAO’s Audit and Validation Plan BES – Backhaul Extension Service BT CPs – BT’s downstream businesses BT Wholesale, BT Global Services and BT Retail CCD – Customer Committed Date Consult 21 – BT’s 21st Century Network consultative group CoP – Code of Practice CPs – Communications Providers DSLAM – Digital Subscriber Line Access Multiplexer EAB – Equality of Access Board EAO – Equality of Access Office e-Co X – BT’s existing order and fault handling system for LLU and extension services EMP – Equivalence Management Platform EoI – Equivalence of Input IBMC – Installed Base Migration Complete IP VPN – Internet Protocol Virtual Private Network IPR – Intellectual Property Rights ISDN – Integrated Services Digital Network LiSA – Line Share Automation LOB – BT Line of Business LLU – Local Loop Unbundling MDF – Main Distribution Frame MIS – Management Information Systems MPF – Metallic Path Facility NGN – Next Generation Network NGNuk – Independent NGN industry body Non-BT CPs – Communications Providers external to BT OSS – Operational Support Systems PPC – Partial Private Circuit SLA – Service Level Agreement SMP – Significant Market Power SMPF – Shared Metallic Path Facility SPG – Service Provider Gateway TSR – Ofcom’s strategic review of telecoms WES – Wholesale Extension Service WES B – Wholesale Extension Service Backhaul WES LA – Wholesale Extension Service Local Access Product WEES – Wholesale End-to-End Ethernet Service WLR – Wholesale Line Rental WLR3 – The new EoI WLR product Z-test – Statistical indicator of equivalence BT Group plc Registered Office: 81 Newgate Street, London EC1A 7AJ Registered in England and Wales No: 4190816 Produced by the Equality of Access Office