Implementation of the RJ88 Plan and Procedures for the Notification of Frequency Assignments to Stations of the Broadcasting Service (Article 5) Y D1 D2 DR @AF 1 Administration A sends to BR a T04 notice under Article 5 of RJ88 Agreement; the notice contains the characteristics listed in Annex 3 (see also CR/125) and the names of administrations (C, E, H) with which A successfully completed the coordination N 2 BR receives on date D1 complete notice 3 BR seeks clarification indicating the deadline for the reply = yes, N = No = date of receipt of complete notice = date procedure of Sec.2 of Art.4 begins = date of entry into MIFR = list of administrations with which the agreement must be reached N 4 BR receives within dead line on date D1 complete notice 5 BR returns notoce to A Y Y 6 BR publishes notification of adm. A in Part I of BRIFIC 7 BR publishes notification of adm. A in Part III of BRIFIC (Unfavorable Finding) and returns the notice to A Y 6 BR finds that power exceeds 10 kW (6 of Annex 2 of the Agreement) N 8 BR finds that notified assigned frequency corresponds to channel assigned frequency (1610, 1620, ..,1700) of an allotment area corresponding to notified geographical location N (2.2 of Section 2) 9 BR finds that notified channel is allotted to adjacent allotment area of adm. K Y (2.1 of Section 2) 10 BR finds that limits of Section 4 of Annex 2 are exceeded with respect to adm.: G, H Y Y (1.4 of Section 1) N N 12 BR finds that limits of standardized parameters are exceeded (1 kW power, simple 90 deg height antenna) 11 @AFO = (G) 13 BR finds that Enom is exceeded at the limit of each territory separating the two allotment areas (1.5 of Section 1) Y 15 @AFB = (G, K) N Y N (1.1 of Section 1) 14 BR publishes notification of adm. A in Part II of BRIFIC (Favorable Finding) and records it in MIFR with date DR = D1 N (1.2 of Section 1) 16 BR finds that limits of Section 3 of Annex 2 (co-channel) are exceeded with respect to adm.: C, D (2.1.1 of Section 2) Y 18 BR finds that limits of Section 2 of Annex 2 (adjacent channel) are exceeded with respect to adm.: E, F (2.1.2 of Section 2) N (1.3 of Section 1) 17 @AFC = (D, G, K) Y (Procedure of Section 2 of Article 4 follows) Adm. A sends on date D2 to adm. F (and a copy to BR) a request for agreement (7 of Art.4) Y BR informs accordingly adm.: A and M BR finds that agreement of other am. M is required (9 of Art.4) 19 @AF = (D, G, K, M) N Within D2 + 90 days adm. F gives its agreement or communicates the characteristics of its existing or planned assignments that may affect the proposed assignment or be affected by it (10 of Art.4) Y Adm. F agreed Y N N N Adm. A requests BR for assistance (12 of Art.4) stop Y BR requests adm. F to give its agreement or to communicate the characteristics of its assignment (13 of Art.4) Y Adm. F replies within 60 days (14 of Art.4) N Adm. F agreed Y N Adm. F is deemed to have given its agreement to adm. A for the use of this station, either with standardized parameters, or with non-standardized parameters, provided that the proposed station does not cause any more interference than a station operating on the frontier with standardized parameters (14 of Art.4) Wieslaw Broszczak, 18 SEP 2006, last updated 30 NOV 2006