In Site Autumn 2009 Author: Kevin Greene kevin.greene@klgates.com +44.(0)20.7360.8188 K&L Gates is a global law firm with lawyers in 33 offices located in North America, Europe, Asia and the Middle East, and represents numerous GLOBAL 500, FORTUNE 100, and FTSE 100 corporations, in addition to growth and middle market companies, entrepreneurs, capital market participants and public sector entities. For more information, visit www.klgates.com. Welcome to the Autumn 2009 edition of In Site, the first edition to be published electronically. We hope our regular readers will welcome the shift from hard-copy to electronic format. Summary judgment and the enforcement of adjudicator’s decisions form the focus of the Autumn edition of In Site. In this edition we report on the recent TCC consideration of whether a withholding notice was effective and resisting a summary judgment application on the basis that there was an arguable defence that an alleged employer was not a party to a construction contract. It is relatively unusual for the courts to decide not to enforce an adjudicator’s decision, but we also review another case, Vision Homes Ltd v Lancsville Construction Ltd where this was the outcome. We conclude with a brief review of the principles of interpretation of contracts set out in Chartbrook v Persimmon Homes and a consideration of whether an architect’s failure to inform clients of the resignation of a key individual amounted to fraudulent misrepresentation. When are withholding notices “effective”? Technical arguments designed to challenge an adjudicator’s jurisdiction have generally met with limited success in recent years as the courts seek to uphold the spirit of the Housing Grants, Construction and Regeneration Act (“the Act”), which is often encapsulated as “pay now, argue later”. The recent case of Windglass Windows Ltd v Capital Skyline Construction Ltd and another [2009] EWHC 2022 (TCC) illustrates this in relation to the content of withholding notices. It was held in this case that letters from an employer rejecting applications for payment did not amount to valid withholding notices under section 111 of the Act where they did not set out the grounds for withholding but simply said that the applications for payment had been submitted in the wrong format. Background Part II of the Scheme for Construction Contracts (England and Wales) Regulations 1998 (“the Scheme”) applied to the contract between Capital and Windglass. Windglass made two applications for interim payments. In response to each, Capital issued a notice refusing to process the payment on the basis of insufficient supporting information and the fact that the application for interim payment should, it said, be in a particular format. In the subsequent adjudication, the adjudicator concluded that there was no agreed format for the interim applications. Capital had failed to issue any effective withholding notices under the Scheme because the notices did not identify either the amount to be withheld or any valid grounds for withholding. A consequence of Capital’s failure to issue effective withholding notices was that they could not raise a cross-claim for defects or delay. Issues and the law When Windglass sought to enforce the adjudicator’s decision, Capital argued that the adjudicator exceeded his jurisdiction when he concluded that the withholding notices were ineffective because they did not set out any valid grounds for withholding. Capital argued that the Act does not require that the ground for withholding payment set out in the notice be valid for that notice to be an effective withholding notice. In Site Section 111 of the Act prevents a party from withholding payment unless "an effective notice of intention to withhold payment" has been given. To be effective, such a notice must specify the “amount proposed to be withheld and the ground for withholding payment" (or grounds, if applicable). Subsequent authorities have established that, to be effective, withholding notices must be in writing (Strathmore Building Services v Colin Greig [2001] 17 Const LJ 72) and must be issued a requisite time before the final date for payment (VHE v RBSTB [2000] BLR 187). The courts will take a practical view of the contents of a withholding notice and will not allow complaints as to form which might be described as artificial or contrived (Thomas Vale Construction v Brookside Syston Ltd [2006] EWHC 3637). Judgment The judge enforced the adjudicator’s decision for a number of reasons. On the issue of whether the notices constituted effective withholding notices within the meaning of section 111 of the Act, the judge concluded that, if the requirements of section 111 are not met, a notice is not effective and there is no "meaningful distinction between a ‘valid’ or an ‘effective’ notice". Capital had argued that it knew it had a substantial counterclaim but that it also "had good grounds to forestall a payment application that was not in a format previously agreed". It therefore withheld on the latter grounds and then defended the adjudication on the substantial grounds - the notice was effectively used as a "foot in the door". The judge rejected this argument, emphasising the obligation of the paying party to give good reasons there and then if it wishes to withhold. Otherwise, it has to pay now and argue later. The absence of an effective withholding notice is fatal to the bringing of the cross-claim and therefore means that the adjudicator’s decision must be enforced. Summary judgment applications Estor Limited v Multifit (UK) Limited (2009) EWHC 2108 (TCC) represents a relatively rare instance of the courts not enforcing an adjudicator’s decision at summary judgment stage. In this case the judge refused to enforce on the basis that the alleged employer had an arguable defence that it was not a party to the construction contract. This case is a reminder that an employer and sub-contractor should give full consideration to their relationship by formally entering into a contract when a contractor leaves the scene and the sub-contractor is to finish off the work. Background Mr Keith Warner was the owner of the Ginger Group of companies (of which Estor Limited was the holding company) who engaged Hub Design Ltd for the fit-out works on newly acquired shop premises. The contract identified the Ginger Group as the employer. Hub subcontracted some of the works to Multifit (UK) Ltd. Matters did not proceed smoothly, with Hub leaving the project and Multifit agreeing to finish the work. Mr Warner sent an email confirming that Multifit should carry out the work in accordance with an agreed revised quote, but failed to indicate which company was accepting the quotation. Multifit was paid for the work but it was unclear which group company had made the payments. The resin floor was expressly excluded from both the original and revised scope of Multifit’s work. This aspect of the work was carried out by another of Hub’s subcontractors, who were paid by Multifit (allegedly under Mr Warner's direction). A dispute arose over defects in the resin flooring and who was responsible for them. The adjudicator found that there was a contract between Estor and Multifit (evidenced by the emails of Multifit and Mr Warner and a credit reference application signed by Mr Warner) and that, although the resin floor was not originally part of Multifit’s works, it became part of them and Multifit was responsible to Estor for defects in it (although on the facts none were proved). Estor was ordered to pay Multifit's costs and the majority of the adjudicator's fee. Enforcement proceedings Estor did not pay and sought declarations that (1) there was no contract with Multifit and (2) the adjudicator’s decision was unenforceable. Multifit counterclaimed seeking summary judgment to enforce the adjudicator’s decision. To resist summary enforcement of the adjudicator’s award, Estor needed to satisfy the court that there was a realistic prospect of establishing that the contract was not between Estor and Multifit. Autumn 2009 2 In Site On the evidence, the judge held that there was a realistic prospect of Estor establishing that it was not the company which entered into the contract with Multifit due to the evidence from Mr Warner and the payments which were made by another group company (albeit funded by Estor). The evidence against Estor included the credit reference application which expressly cited Estor. The court could only decide the issue by hearing oral evidence at a full hearing. Estor was given leave to defend the summary judgment application. The judge said, however, that as the defence raised by Estor was “at the weaker end of the scale”, Estor was required to make a payment into court of £35,000 (being just over half the sum claimed by Multifit). This reflected the court’s relative scepticism about the strengths of Estor’s case. Vision Homes Ltd v Lancsville Construction Ltd Compliance with the procedure for nominating an adjudicator was at the heart of the successful challenge to the adjudicator’s jurisdiction in the recent case of Vision Homes Ltd v Lancsville Construction Ltd [2009] EWHC 2042 (TCC). Vision engaged Lancsville to construct the shell and external envelope of new flats. The external envelope element of the works was subsequently omitted and the contract sum reduced. The remaining works were rescheduled but delays occurred. Vision claimed liquidated damages from Lancsville, who disputed this. It argued that, as part of the agreement to omit work, Vision was not entitled to liquidated damages. Both parties launched adjudications against the other on the same day, with Lancsville seeking a declaration that Vision was not entitled to levy liquidated damages, whilst Vision claimed liquidated damages. The Scheme applied to both adjudications. This case concerns the first of those adjudications. Lancsville sent its notice of intention to refer a dispute to adjudication to Vision early on the morning of 14 May 2009, seeking its agreement to one of three named adjudicators. Later that day Lancsville requested the RICS to make an appointment and shortly thereafter on the same day Lancsville sent Vision a slightly modified notice of intention, which now included a claim for Vision to pay the adjudicator’s fees and expenses ("the Second Notice"). Five days later, on 19 May, Mr Bingham accepted his nomination as adjudicator by the RICS and on the following day Lancsville served its referral notice in that adjudication (“the Bingham adjudication”). The adjudicator decided that Vision was not entitled to deduct liquidated damages as the agreement to omit the works also removed the extension of time and liquidated damages provisions. He also ordered Vision to pay his fees and expenses, which demonstrated that he was proceeding under the Second Notice. Vision wrote to Mr Alway, the adjudicator on the other dispute (the “Alway adjudication”), saying that the Bingham adjudication was not binding on him, whilst Lancsville wrote to him asking him to resign in the light of the decision in the Bingham adjudication. Mr Alway decided that the Bingham adjudication did not relate to substantially the same dispute as that in the Alway adjudication, but suggested that the parties should obtain guidance from the court on the validity of the decision in the Bingham adjudication before he issued his decision. Vision then started proceedings in the courts, in which it set out several grounds why Mr Bingham’s decision was invalid. The only successful ground (lack of clarity of the decision, unfairness and two adjudications on the same point all failing) was the timing of the notices of intention to refer and the request to the RICS to nominate an adjudicator. The Scheme provides (paragraph 2 (1)) that “following the giving of a notice of adjudication … the referring party shall request the nominating body … to select a person to act as adjudicator.” Vision argued that this sequence was not followed, as Mr Bingham had proceeded on the basis of the Second Notice which had followed the request to the RICS, rather than preceded it as required by the Scheme. The judge agreed with Vision and held that “not without some misgiving I accept that the adjudicator had no jurisdiction to act, as he did, under the second notice of 14 May because that notice was not followed but preceded by a request to the nominating body”. Autumn 2009 3 In Site The “misgiving” arose from the fact that the alteration to the notice adding a claim for fees was of limited importance compared with the dispute as a whole. However, because in other circumstances the amendment may be more significant, the judge found that the question of jurisdiction “cannot depend upon the degree of importance of the additional claim”. Interpretation of contracts Chartbrook Limited v Persimmon Homes Limited and others [2009] UKHL 38 illustrates the extent to which the courts will be prepared to go to interpret a contract to give effect to the parties’ intentions and clarifies the established rule – known as the exclusionary rule – that evidence of pre-contractual negotiations is not admissible for the purposes of interpreting a contract. Chartbrook and Persimmon disagreed over the interpretation of a pricing formula in a development contract. Chartbrook said the payment provision should be interpreted literally, whilst Persimmon argued that Chartbrook’s interpretation did not give it a rational, commercial meaning. Both the court of first instance and the Court of Appeal found in favour of Chartbrook. Persimmon appealed to the House of Lords on the basis that its construction of the provision was correct and, in the alternative, that their Lordships should take into account precontractual negotiations in interpreting the provision. It argued that the exclusionary rule was illogical and prevented a court from putting itself in the position of the parties and ascertaining their true intent. With regard to the parties’ main arguments, the House of Lords found in favour of Persimmon and concluded that something had gone wrong with the language of the contract. As such, Chartbrook’s interpretation of the clause was “arbitrary and irrational”. Since the payment provision clearly contained a mistake and it was clear to the House how to correct that mistake, the House was able to effect the correction. In order to do this the court will look at the background matrix of facts when interpreting the contract. In reaching this decision, the House considered a pre-contractual letter put forward by Persimmon which clarified the commercial purpose of the payment clause. Whilst maintaining the status quo regarding the exclusionary rule, their Lordships accepted that there are no conceptual limits as to what may be regarded as background evidence (BCCI v Ali (No 1)). So, prima facie, evidence of pre-contractual communications between the parties may be relevant (and therefore admissible) as part of the background which might cast light on what the parties meant by the language they used. The question is whether this represented a departure from the exclusionary rule. The answer is no: the House refused to go so far. Lord Hoffmann noted that there are two important safeguards which operate to prevent the exclusionary rule from causing injustice: (1) rectification if the agreement mistakenly does not reflect the common agreed intention of the parties and (2) estoppel by convention if the parties have agreed that certain words will have a particular meaning. In clearly restating the exclusionary rule, the case is a reminder that evidence of relevant precontractual negotiations is only likely to get before a judge if arguments of rectification or estoppel by convention can be raised. This case is a salutary lesson to those drafting contracts to avoid ambiguity. With particular regard to payment clauses, parties could provide worked examples of payment calculations, minimise the number of defined terms used or rely on a simple formula. However, where errors do occur, parties may be able to seek the assistance of the court who will assume the role of a “reasonable person”. Fraudulent misrepresentation Whilst it is common practice for an employer to engage an architectural practice as “architect” on a project, the understanding (often made an express term of the contract) is that specific individuals within that practice will devote some, if not all, of their time to the project. The issue which came up in Fitzroy Robinson Ltd v Mentmore Towers Ltd [2009] EWHC 1552 was whether a failure to inform clients of the resignation of one such key individual amounted to fraudulent misrepresentation. A director of Fitzroy Robinson Ltd (the architect) had been expected to carry out a key role on two projects for a client, Mentmore Towers Ltd. He resigned, however, before the professional appointments were signed. Fitzroy did not tell Mentmore of the resignation until 8 months later. Autumn 2009 4 In Site It was decided on the facts that this amounted to fraudulent misrepresentation. Although the case does not make new law, it does provide a number of important practical lessons, first and foremost of which is that professional consultants should promptly inform their clients of key personnel changes. Even if a failure to do so does not amount to misrepresentation, it may amount to breach of contract (for example if key personnel are stated in the contract) and may cause damage to the professional consultant's reputation. Anchorage Austin Beijing Berlin Boston Charlotte Chicago Dallas Dubai Fort Worth Frankfurt Harrisburg Hong Kong London Los Angeles Miami Newark New York Orange County Palo Alto Paris Pittsburgh Portland Raleigh Research Triangle Park San Diego San Francisco Seattle Shanghai Singapore Spokane/Coeur d’Alene Taipei Washington, D.C. K&L Gates is a global law firm with lawyers in 33 offices located in North America, Europe, Asia and the Middle East, and represents numerous GLOBAL 500, FORTUNE 100, and FTSE 100 corporations, in addition to growth and middle market companies, entrepreneurs, capital market participants and public sector entities. For more information, visit www.klgates.com. K&L Gates comprises multiple affiliated partnerships: a limited liability partnership with the full name K&L Gates LLP qualified in Delaware and maintaining offices throughout the U.S., in Berlin and Frankfurt, Germany, in Beijing (K&L Gates LLP Beijing Representative Office), in Dubai, U.A.E., in Shanghai (K&L Gates LLP Shanghai Representative Office), and in Singapore (K&L Gates LLP Singapore Representative Office); a limited liability partnership (also named K&L Gates LLP) incorporated in England and maintaining offices in London and Paris; a Taiwan general partnership (K&L Gates) maintaining an office in Taipei; and a Hong Kong general partnership (K&L Gates, Solicitors) maintaining an office in Hong Kong. K&L Gates maintains appropriate registrations in the jurisdictions in which its offices are located. A list of the partners in each entity is available for inspection at any K&L Gates office. This publication is for informational purposes and does not contain or convey legal advice. The information herein should not be used or relied upon in regard to any particular facts or circumstances without first consulting a lawyer. ©2009 K&L Gates LLP. All Rights Reserved. Autumn 2009 5