Lawyers to the real estate & construction industry insite Spring 2004 contents Withholding notices 1 Duty to warn 2 Choosing the right form of contract 3 Adjudication update 4 Letters of intent 6 Third Party Rights Act revisited 7 Affordable Housing 8 Who to contact 8 Get Your Withholding Notices Right! Welcome to the Spring edition. We consider the importance of issuing valid withholding notices and a professional's duty to warn of potential hazards. We consider what to bear in mind when deciding on procurement routes. We give an update on adjudication cases and consider the potential pitfalls of relying on letters of intent. The Contracts (Rights of Third Parties) Act 1999 has come before the courts and we report on the outcome. Finally, there is an update on initiatives within NGJ regarding affordable housing. www.ngj.co.uk The importance of issuing valid withholding notices cannot be overestimated if you have proper grounds for resisting payment of a sum claimed against you. The withholding notice provisions of the Housing Grants, Construction and Regeneration Act 1996 are aimed at protecting cashflow and section 111(1) provides that "a party to a construction contract may not withhold payment after the final date for payment of a sum due under the contract unless he has given an effective notice of intention to withhold payment…". There has been considerable, and often conflicting, case law on the meaning of section 111 and on the boundaries of situations in which it is possible to withhold payments without the need to issue a withholding notice first. The 'narrow' construction of section 111 has tended to be that if a sum is not "a sum due under the contract" in the first place (for example because the work was not performed at all) then section 111 does not apply. The 'wide' construction is that once a certificate has been issued, the sum is due and a failure to issue a section 111 notice within the prescribed time means the certified sum must be paid. This issue has recently been considered further by the Court of Appeal in Rupert Morgan Building Services v Jervis. The architect issued an interim certificate for sums due to the builder. The client disputed around half the amount, but failed to issue a withholding notice within the relevant in site time, and the builder claimed summary judgment of the disputed balance. When a warning is not a warning Adopting the 'narrow' construction of section 111, the client argued that he did not need to issue a withholding notice because the disputed sums related to work that had not been done, duplications of previous payments and snagging for works already done and paid for i.e. sums that were not ever "due" in the first place. The Court of Appeal has recently considered the extent of a professional's duty to warn in the case of Six Continents Ltd v Carford Catering Ltd. The builder naturally argued for the wide construction. In reminding the parties that the cashflow aspects of section 111 are "fundamental" and are not dealing with the final payment position between the parties, the Court agreed with the builder's position and held that if the client failed to issue a withholding notice on time, then he had to pay the sum certified. If he has overpaid he can get the matter put right on future certificates, or commence proceedings to recover the money. So it is extremely important to check certificates or applications for payments early enough to get your withholding notice in if need be. Those performing the role of contract administrator or a cost control function should also pay heed to the need to inform their clients as to the need to issue timely withholding notices. The Court considered that section 111 "provides a fair solution, preserving the builder's cash flow but not preventing the client who has not issued a withholding notice from raising the disputed items in adjudication or even legal proceedings". 2 Carford was engaged by Six Continents, the owners of a Harvester restaurant, as project managers for the design and installation of kitchen catering equipment. Carford were told to get hold of a certain type of rotisserie (which could be either table or wall mounted). Carford chose the wall mounted design and the rotisserie was subsequently installed on a timber stud wall faced with plywood then tiled. Problems with heat distribution arose after practical completion and Carford called in the suppliers, who made some minor modifications. They sent Carford a report on the same day recommending that a stainless steel sheet be fitted at the back of the unit to prevent a fire risk. Carford forwarded this report onto Six Continents and asked "can you please advise us what action, if any, you wish us/the builders to take?" Six Continents never replied to this message and, unfortunately, there was a fire. Six Continents brought a claim for damages against Carford. The trial judge decided that, although Carford was in breach, the letter which Carford sent to Six Continents broke the chain of causation. In other words, the losses fell at Six Continents' door because they did not heed the warning sent to them in the letter. Six Continents did not agree that a simple letter asking for advice could take away Carford's responsibility to act and they appealed. The Court of Appeal held that because Carford had a contract with Six Continents, they owed them a duty to install the kitchen equipment properly and to see there was no fire risk. When subsequently considering the issue of causation the judge should not have just asked 'what caused the fire?', but whether Six Continents' failure to heed the warning letter should relieve Carford from what was otherwise a breach of contract. They held that sending a warning letter to Six Continents was not enough to discharge Carford's duty. The Court of Appeal also decided that the letter was not really even a warning. It was merely a question. Carford were asking whether Six Continents would like them to take any action. This suggested that action was optional, not necessary. The Court of Appeal, in this case, has helped to clear up the law relating to the situation where one party to a contract tries to avoid liability on the grounds of causation. In effect the Court has made it very difficult for that party by ensuring that when deciding upon causation, courts and adjudicators alike will no longer just look at the facts but question more widely who should be responsible for the loss. The pros and cons of this method of approaching causation are many and varied but just alerting a party to a problem may not be sufficient if you actually ought to be doing something about it. Spring 2004 Deciding on the form of contract that is right for you There are a wide - and growing array of contract forms to choose from. In recent editions of "In Site" we have covered the introduction of the JCT Major Project Form, the new FIDIC 'rainbow' forms, and the Be Collaborative Contract which now all sit alongside the older, more familiar forms and the option of drafting bespoke documents. Which is the one for you? It is important to step back and decide on the best procurement route first. The decision to proceed rests with the client and different considerations will apply depending on whether they are a private or public sector entity and the extent of past experience with different procurement routes. Timing of the decision to proceed, and whether advisors and contractors are on board at that stage, will also be relevant factors, as will be the potentially competing objectives of time, cost and quality. The procurement method adopted will depend partly on the length of time available for design before needing to start on site. Obviously the longer that is available the more detailed the design can be before going out to tender. With that in mind, procurement options include competitive tendering on the basis of detailed bills and specifications and two stage tendering commencing with less detailed design information but moving to detailed design and fast-track procurement. Other options include negotiated or 'bespoke' contracts and open-book partnering. It is important to consider the type of contract structure which reflects the intended risk allocation and the intended rights and obligations of the parties. The choice of contract structure will typically be between the traditional structure, design and build, management contracting, construction management and partnering-style contracts. Another issue that should be addressed as early as possible is the appropriate type and level of insurance cover, and who is responsible for taking it out. The traditional structure allows the employer to retain responsibility and control over the design and specification and the contractor is responsible for carrying out the works. It can be slower than other procurement routes however as design often needs to be complete before invitations to tender are released. If something goes wrong it is often difficult to determine whether the defect is due to a design fault or workmanship and hence who is at fault. Examples of Standard Form contracts include the various forms of Private With/Without Quantities JCT Standard Form of Building Contract 1998 and the NEC Engineering and Construction Contract (Second Edition). Design and build contracting offers the employer the clear advantage of a single point of responsibility. It also allows the contractor to use its expertise in the design and therefore the 'buildability' of the project and may mean that construction work can 3 in site be started earlier than under the traditional structure, as design work can proceed in parallel. However, it is the contractor and not the employer that has a high degree of control over the project. Risks from the employer's point of view may include a higher price to compensate the contractor for that responsibility. From the contractor's perspective, a key commercial risk is that a fitness for purpose warranty is often implied even if it is not an express term. Design and build standard forms include JCT 98 With Contractor's Design, the ICE Design and Construct Conditions of Contract and the JCT Major Project Form. Management contracts, a form of prime cost contracting, allow for the management contractor to be engaged early on and to be treated as part of the design team, assisting in splitting the works into discrete works packages and is not usually directly involved in carrying out any of the construction work. Works contractors are directly responsible to the management contractor. The employer can be exposed to interrelated delay claims and increased costs, but this method of procurement can have the attraction of speed and flexibility. Under a construction management arrangement, the construction manager is paid a fee for management and co-ordination of the work, and the employer retains a large proportion of the risk. The trade contractors are directly contractually responsible to the employer. The main problem is again co-ordinating the different trade contractors and the employer is potentially exposed to a 4 large number of inter-related delay claims. The JCT offers the MC98 Standard Form of Management Contract 1998 edition, and a Construction Management Agreement C/CM. The decision to adopt a partnering style contract will involve a consideration of some or all of the above issues, depending upon the identity of, and relationship between, the partners. It will also depend upon the degree of trust and existence of common goals which can be covered by partnering principles. A willingness to adopt partnering principles is key to the success of a partnering relationship, but the need to provide for mechanisms to deal with any breakdown in that relationship must also be considered. Common forms of partnering contracts available are the Be Collaborative and PPC2000 contracts. Adjudication update Professional negligence In the Scottish case of Gillies Ramsay Diamond v PJW Enterprises Limited (27 June 2002), GRD were appointed as contract administrator by PJW. The appointment did not contain an adjudication clause but despite this, when PJW terminated GRD's appointment, they served a notice of adjudication. The adjudicator awarded damages to PJW in respect of overpayments made to GRD arising from the lack of written instructions, sums in respect of bank overdraft costs and additional legal fees incurred as a result of an incorrect grant of an extension of time and a further sum in respect of losses and costs incurred on the early termination of GRD's contract. GRD sought judicial review of the adjudicator's decision, which resulted in a clear statement by the Court that an adjudicator is fully entitled to reach conclusions about the manner in which a professional person has carried out his or her duties in the course of the construction contract, including conclusions as to whether there might have been any professional negligence. Timely decisions The question of what happens when an adjudicator does not issue a decision within the required timescale was considered in Simons Construction Limited v Aardvark Developments Limited (29 October 2003). The adjudicator issued a draft decision on the date when the final decision was Spring 2004 due. The "final decision" was not issued until a week later. The Court held that the "draft" decision was not an effective decision because it was not signed or dated, it was marked "for the Parties' comments" (and each party had the opportunity to make comments on it) and the adjudicator did not say that the "draft" was for practical purposes final or final subject to textual corrections. The Court held however that the late final decision was a binding and effective decision. The failure to produce a decision within the required timescale did not deprive the adjudicator of jurisdiction. The contract was silent on the consequences of an adjudicator failing to reach a decision within the agreed period and under the Scheme, if an adjudicator fails to reach a decision within the relevant time period, any of the parties may serve a fresh referral notice. In this case no referral notice was served. Natural justice Natural justice issues were considered in the Scottish case of Costain Limited v Strathclyde Builders Limited (17 December 2003). During the course of an adjudication between the parties, the adjudicator discussed a point with his legal adviser and went on to decide in Costain's favour without disclosing the substance of the advice he had received or giving the parties an opportunity to comment. The Court identified two principles of natural justice to which adjudicators must adhere: an adjudicator should not have any bias or personal interest in the outcome, and both sides must be given a fair opportunity to present their cases. Looking at the issue of fairness in more detail, the Court set out certain propositions to ensure that parties to an adjudication receive a fair hearing. These propositions included: J each party must be given a fair opportunity to present its case. Subject to that, and any express provisions in the contract, the adjudicator has procedural discretion; J the strict time limits of adjudications must be borne in mind, which may mean that the time given to comment can be severely restricted; J each party must be given an opportunity to make comments at any relevant stage in the process and to respond to written contentions submitted by the other party insofar as they contain new material. Further, if an adjudicator is given the power: J to use his own knowledge and experience in applying propositions that have not been canvassed by the parties; J to require further information or test results to be provided; J to obtain technical or legal advice from a third party on a matter that has not been canvassed by the parties, then in each case the information should be shared with the parties with an opportunity given to them to comment. On the facts in Costain, the fact that the adjudicator had failed to allow the parties the opportunity to comment on the legal advice he had received was a breach of natural justice which had given rise to the opportunity for injustice to be done. Costain's application for summary judgment to enforce the adjudicator's decision was refused. London & Amsterdam Properties v Waterman Partnership (18 December 2003) also considered natural justice issues in the context of 'evidential ambush'. The adjudicator received late evidence from London & Amsterdam and found in their favour. Waterman had not been given a fair opportunity to comment. The Court held that the adjudicator should have either allowed an extension of the timetable for Waterman to comment, or excluded the late evidence. This case is also important because the Court considered the extent to which it is appropriate for complex disputes (in that case one involving questions of professional negligence) to be dealt with by way of adjudication. This decision highlights a potential tension between the legislation, which confers the right to adjudication in respect of any dispute that arises under a construction contract, and the feasibility of dealing with complex, time consuming and document heavy claims such as final account disputes or negligence claims within the timeframe provided by adjudication. Judge Wilcox concluded his judgment in this case by suggesting "A review as to the working of the Act is perhaps now timely". The extent to which arguments that a dispute was 'too complex' becomes a possible enforcement challenge and/or calls are made for Parliament to narrow the range of disputes that have an automatic right to adjudication remains to be seen. 5 in site Judge follows adjudicator’s decision In the case of Westminster Building Company Limited v Andrew Beckingham (20 February 2004), Westminster tendered for the refurbishment of Mr Beckingham's townhouse. The contractual documents proposed by Mr Beckingham's team included the JCT Intermediate Form. Mr Beckingham refused to pay two interim certificates because, he contended, that an agreement between him and Westminster capped the total sum payable for the work. The adjudicator found in favour of Westminster. Mr Beckingham resisted enforcement proceedings on three grounds: 1. Mr Beckingham claimed the contract contained no adjudication clause. As the works were to a dwelling house and Mr Beckingham was a residential occupier, the Housing Grants, Regeneration and Construction Act 1996 did not apply. Therefore the question of whether there was an adjudication clause in the contract depended upon whether the terms of the JCT Intermediate Form had been accepted by the parties. Mr Beckingham sent a Letter of Intent to Westminster which envisaged formal contract documents being signed. Westminster later signed the standard form contract but Mr Beckingham never did. He raised no objection to the form or content of the contract and the work proceeded 6 and was completed in accordance with the standard form. The Judge held that Mr Beckingham had accepted the standard form (including an adjudication clause) by his conduct and waived any precondition that both parties should sign the document. Therefore the parties had accepted the adjudication provision, which would otherwise not have applied. J the terms had been decided by Mr Beckingham's team and he had competent/objective advice available to him. The clause did not contravene the requirements of good faith; J the clause did not, if considered at the time of making the contract, constitute a significant imbalance to Mr Beckingham's rights; and 2. Mr Beckingham claimed the Capping Agreement precluded the adjudicator from having jurisdiction to decide the dispute. J the clause did not significantly exclude or hinder Mr Beckingham's right to take legal action or other legal remedy. The adjudicator decided that the Capping Agreement constituted a variation to the original contract and was therefore within his jurisdiction. He concluded that the Capping Agreement was not effective because it was not supported by consideration as there was "no practical benefit to Westminster" and therefore the original agreement applied. As Mr Beckingham had not served Notices to Withhold (as required by the original agreement) the sums due under the disputed certificates were both due and payable. The Judge agreed with the adjudicator. Therefore, the adjudication clause was not unfair and was binding on Mr Beckingham. 3. Mr Beckingham claimed the adjudication clause was not binding as it was unfair under the Unfair Terms in Consumer Contracts Regulations 1999. The Judge considered case law and decided: J although the terms were not individually negotiated, they were couched in plain and intelligible language; This case highlights the importance of clarity of terms to narrow the scope for dispute. Letters of intent Judge Richard Seymour QC, in his judgment on preliminary issues in the case of Tesco v. Costain Construction Ltd (2 July 2003), delivered some useful guidance on the true effect of letters of intent. He held that a letter of intent, which had been sent by a Tesco representative to Costain in March 1989, represented the sole contract between Tesco and Costain for the construction of a supermarket. The parties did not agree a formal contract. Accordingly, the letter of intent contained the only terms governing the relationship between Tesco and Costain: namely that Costain would commence the construction of the supermarket in a Spring 2004 ”those who wish to ensure Third Party Rights Act that third parties are not A Contracts (Rights of Third Parties) Act 1999 case has finally come before the courts in Nisshin Shipping Co Ltd v Cleaves & Company Ltd and Others (7 November 2003). One reason this case has been a long time coming is no doubt the willingness of contract drafters to exclude its provisions. The decision in Nisshin may well reinforce some drafters' views that the Act is best excluded. granted rights should expressly exlude the Third Party Rights Act” good and workmanlike manner using reasonably satisfactory materials, and if it took any design decisions the design would be reasonably fit for its purpose. In return, Tesco would pay Costain. The terms of the letter of intent did not make Costain responsible for the design, even though it had always been intended that Costain would be the design and build contractor. This proved crucial, because several years later a fire caused extensive damage to the supermarket, which would not have spread so quickly if the design had included appropriate fire stops. For employers, this case emphasises the importance of concluding construction documentation. Once a letter of intent has been signed, the works have commenced and the contractor has been paid, execution of a formal contract can sometimes risk falling by the wayside. Contractors and consultants will also benefit from concluding the construction documents, because they will know exactly where they stand, particularly in the context of express and/or implied terms regarding reasonable skill and care and fitness for purpose. Clarity of terms will not always prevent disputes, but at least narrows the scope for arguing what those terms in fact are. The case concerned the interpretation of sections 1 and 8 of the Act. Section 1 provides that a third party can enforce a term of a contract if the contract expressly provides that he may, or the term purports to confer a benefit on him (subject to the proviso in section 1(2) that unless, on a proper construction of the contract, it appears that the parties did not intend the term to be enforceable by the third party). Where a section 1 right is subject to a term providing for the submission of disputes to arbitration and that agreement is in writing, section 8 of the Act provides that the third party is entitled and, indeed obliged, to refer the dispute to arbitration. Cleaves acted as brokers and arranged a number of charters for Nisshin with each charterparty providing for payment of commission to the brokers. Nisshin said, however, that the brokers were not entitled to the commission as they were allegedly in breach of the agency relationship. Cleaves referred the matter to arbitration. This was despite the fact that it was not a party to any of the chaterparties which contained arbitration clauses. These clauses did not provide for the broker to refer a dispute to arbitration but were wide enough to cover a claim by charterers to enforce the promise to pay commission against the owners. The arbitrators decided that under sections 1 and 8 of the Act, they did have jurisdiction to determine claims for commission said to be due to Cleaves. Nisshin then applied to the courts for a declaration that the arbitrators had no jurisdiction. The judge agreed with the arbitrators however and held that Cleaves fell within section 1 of the Act and they were therefore entitled to enforce the commission clauses. It did not matter that the arbitration clauses did not make express provision for enforcement by Cleaves, and although there was no positive indication that the parties intended Cleaves to have enforceable rights, they could not rely on the section 1(2) proviso as they had not demonstrated that they did not intend there to be third party enforcement. The decision is this case serves as a reminder to those who wish to ensure that third parties are not granted any rights under a contract: expressly exclude the Act. For those in favour of the Act, this case indicates that the courts are likely to give as liberal an interpretation to the contract as possible so as to give effect to the Act, which would be good news to those relying upon third party rights in substitution of collateral warranties. 7 in site Affordable Housing Group The affordable housing sector is undergoing considerable change, and facing many new challenges. Nicholson Graham & Jones has formed an Affordable Housing Group to draw together its expertise in construction, real estate, projects, and finance, in this important sector. The work of the Group will be of interest to all those involved in the sector including: J Those involved in social housing PFI or in the diversification of Housing associations into non-housing PFI, social care or education; J Developers and contractors involved in regeneration or working with housing associations on mixed use or residential sites; J J Housing associations looking to merge or restructure, or to expand their development programmes; Nicholson Graham & Jones has skills in a wide range of areas from town and country planning to tax, charities to corporate, and commercial property to litigation, all working together to deliver commercial solutions to the ever more demanding needs of clients in this sector. Please contact Sebastian Charles, or your usual contact at Nicholson Graham & Jones for more information. ”... Affordable Housing Group to draw together expertise in construction, real estate, projects, and finance...” Lenders looking to develop innovative structures secured on affordable housing stock, or offering development finance. Who to contact For further information contact David Race, James Hudson, Kevin Greene, Christopher Causer or Linda Kent. Nicholson Graham & Jones 110 Cannon Street, London EC4N 6AR 020 7648 9000 david.race@ngj.co.uk james.hudson@ngj.co.uk kevin.greene@ngj.co.uk christopher.causer@ngj.co.uk linda.kent@ngj.co.uk Internationally a member of GlobaLex. The contents of these notes have been gathered from various sources. You should take advice before acting on any material covered in this newsletter. © Nicholson Graham & Jones 2004 8