Using IED Data To Implement Substation Automation Functions Gerrit Dogger

advertisement
Using IED Data To Implement
Substation Automation Functions
Reducing Costs by Reusing Available Data
Gerrit Dogger
Product and Application Specialist
Cybectec Inc.
Objectives
‹
‹
‹
‹
‹
2
Where are we and what is needed
The benefits of using IED data
Discussion of challenges and their solutions
Discussion of future developments
Real-world case study:
Emergency power management and load restoration
Substation Evolution
1/2
SCADA
Existing situation
IED
RTU
3
PROTECTION
METERING POWER
QUALITY
Substation Evolution
2/2
New situation:
‹
‹
IEDs for protection,
measurement and control
Substation gateway/data
concentrator for
communication
IED
PROTECTION
4
METERING POWER
QUALITY
Automation Requirements
Substation automation functions need –
‹
‹
‹
5
Access to all substation data
Control capability of substation switchgear
A device with programming capability
Introducing the Intelligent Gateway
A communications gateway provides data access
and control capabilities
An intelligent gateway also provides automation
capabilities
Replaced by
6
Direct Benefits of the Intelligent
Gateway
‹
‹
‹
‹
‹
7
No PLC or other additional devices needed
Fewer devices reduce administrative costs
No additional cabling – IEDs are already connected
Opportunity for optimized price/performance relay
configuration
‹ Reinforced by the additional intelligence
Simplified substation architecture – vendor independent
Indirect Benefits of the Intelligent
Gateway
These might be more important in the long run –
‹
‹
‹
8
Simpler diagrams because of reduced cabling
Less maintenance on diagrams
Fewer devices means
‹ Fewer spare parts
‹ Less training
Challenges and Their Solutions
Using intelligent gateways introduces new challenges –
‹
‹
‹
9
Response times
Exception handling
Supporting redundancy
Response Times – Issues
‹
‹
Data acquisition delays due to communication between
gateway and IED
Delay in command execution
Note: Immediate faults are handled by the IED.
10
Response Times – Solutions
Modern protocols reduce data acquisition delays –
‹
11
DNP3, IEC 60870-5-101, IEC 60870-5-104 use unsolicited
reporting
Response Times – Solutions
Processor/task priority reduce the command delay –
‹
12
High priority for
‹ Automation tasks
‹ Command handling
‹ IED command handling
Exception Handling – Issues
Special care needs to be taken for –
‹
‹
13
Invalid incoming data
Command execution error handling
Exception Handling – Solutions
Data invalidity can be handled by –
‹
‹
14
Checking individual data point quality
Checking the communication link status
Exception Handling – Solutions
For command execution –
‹
‹
15
Check the protocol command acknowledgement
Check the corresponding indications
Supporting Redundancy – Issues
Redundancy introduces additional challenges –
‹
‹
‹
16
Correct handling of failover situations
Synchronization of data between the programs
No or limited concurrent execution
Supporting Redundancy – Solutions
To ensure correct execution –
‹
‹
‹
17
Plan redundancy from the start
Use internal program indications
Use external indications – binary inputs
Supporting Redundancy – Solutions
‹
‹
18
Fast failover needs data synchronization
Gateway must address this issue
Supporting Redundancy – Solutions
‹
19
Both synchronized gateways might execute the program.
‹ Highly undesirable
‹ Should be solved in the design
Future Developments
Some trends we see developing:
20
‹
IEC 61850 – GOOSE messages can optimize interaction
‹
Communication availability
‹ Substations can share more data
‹ This enables region-wide automation
Real-World Case Study: Emergency
Power Management and Load Restoration
Incomer #1
Incomer #2
EDG #1
EDG #2
EDG #3
52R-2
52L-3
52L-2
52L-1
52R-1
52L-R
NO
F1
21
F2
F16
F17
REDUNDANT CONTROL
CENTERS
REDUNDANT GATEWAYS
EDG
MCP
INCOMER
UNDERVOLTAGE
PLCS
GENERATOR
BREAKER IEDS
22
FEEDER IEDS
Start state
Initialization and
C: Start of SMP
A: Initialize system
IDLE state
C: One or both incomers closed &
C: `Permissive to syn and close EDG`s CBs`
A: Reset `Permissive to syn and close EDG`s CBs
IDLE
C: Both incomers open &
C: NOT `Permissive to syn and close EDG`s CBs`
A: Open feeders
C: Both incomers open &
C: `Permissive to syn and close EDG`s CBs`
Wait for feeders to
open
C: One or both incomers closed
Blackout:
open feeders
C: (Both incomers open &
C: All feeders open &
C: Bus load less than 1 MW) OR
C: FeederOpenTimer timout (10 sec)
A: Set `Permissive to syn and close EDG`s CBs
Wait for power
from generators
C: One or both incomers closed
Feeders open:
Start generators
C: 1 or more EDG`s CB s closed
A: Calculate power
A: Determine next feeder
C: All feeders Done &
C: Retrycounter < 3
A: Retrycounter := Retrycounter + 1
Retry feeders that
didn’t close
C: One or both incomers closed
Closing feeders
C: Power is available
A: Calculate power
A: Close selected feeder
Determine Close
Fail
Wait for close
confirmation
C: Feeders to retry deteminated
A: Determine next feeder
C: One or both incomers closed
23
C: (Feeder is closed || timeout (5sec)) &
C: Not all feeder are closed
A: Determine next feeder
Power:
Close feeders
(priority based)
Emergency Power Management and Load
Restoration
Basic facts
‹
‹
‹
24
Put into service in November 2005
Normal conditions: restore power within 1 minute
‹ Mainly waiting for generators to come online
Failover condition: restore power within 1.5 minutes
Concluding Remarks
Benefits
‹
‹
‹
‹
‹
‹
25
No additional hardware
Uses existing data and wiring
Fewer spare parts
Lower administration costs –
‹ Minimal training needed
Everything is available to implement it now
Proven concept
Concluding Remarks
Development
‹
‹
26
Better interaction using IEC 61850 GOOSE messages
Upcoming opportunities for region-wide automation
Contact Information
Gerrit Dogger
Product and Application Specialist
Cybectec Inc.
Gerrit.Dogger@Cybectec.com
27
Questions?
28
Download