DRI #226 - BUSCH GARDENS SUBSTANTIAL DEVIATION
CITY OF TAMPA
RY 2005-06
On September 22, 1981, the Tampa City Council granted a Development Order (Ordinance No. 7771-A)
to Busch Entertainment Corporation for an expansion to the existing entertainment park consisting of a
400-room hotel, an administrative center and additional attractions (DRI #72).
The Development Order has been amended numerous times, the latest occurring on December 20, 1994
(Ordinance No. 94-278). The amendments authorized: cumulative extensions of six years, 11 months and
15 days for the project buildout date and Development Order expiration date; and construction of
additional ride facilities. The Development Order expired on September 8, 1998.
On April 16, 1998, the City of Tampa adopted Ordinance No. 98-0081, a Substantial Deviation
Development Order (SDDO) approving modifications for the existing Busch Gardens/Adventure Island
project (DRI #226). This Ordinance was subsequently rescinded and replaced with Ordinance No. 98-147
which was approved by Tampa City Council on June 25, 1998. The Ordinance authorized: extensions
of the buildout date (to December 3, 2010) and the Development Order expiration date (to December 31,
2011); incorporation of 36.6 additional acres including the former Anheuser Busch Brewery; construction
of a total of 2,100 hotel rooms with ancillary development, including a 100-room hotel (or 25,500 sq. ft.
of retail space) on a 2.3-acre parcel located south of Busch Boulevard; increased visitor parking spaces
to a total of 9,200; altered parking entrances and allows construction of up to two tunnels under 40th
Street; development of 5,500 square feet of general commercial on the 0.4 acre parcel south of Busch
Boulevard; and continuous replacement or renovation of development within the existing project. The
anniversary date for the Annual Report is April 1st of each year.
The SDDO has been amended twice, the latest occurring on October 2, 2003 (Ordinance No. 2003-253).
The Amendments have cumulatively authorized a net reduction of 0.5-acres to the project.
PROJECT STATUS
Development this Reporting Year: completed construction of a new roller coaster and culinary building
in Stanleyville, a new employee break room, operations and visitor pet boarding facility, Kenya Pavilion
and a AI Water Slide.
Cumulative Development: development is generally limited to attraction construction and/or remodeling.
No hotel or commercial development (south of Busch Boulevard) has occurred.
Projected Development: no specific development activity has been identified for the next reporting year.
SUMMARY OF DEVELOPMENT ORDER CONDITIONS
1.
The developer provided the following 2005 park attendance figures in accordance with Condition
5.C.10.b.: 4,200,118 to Busch Gardens and 590,076 to Adventure Island. These attendance figures
constitute increases of 5.37 and 2.37 percent, respectively, in comparison with the 2004 attendance
figures provided for each of these parks last year.
2.
The developer has completed the widening of 40th Street between Busch Boulevard and Fowler
Avenue in accordance with Conditions 5.A.11. and 5.D.1.
3.
Condition 5.D.2. requires the developer to initiate an annual traffic monitoring program to be
conducted for three consecutive weekday afternoons during the third week of July, with the results
submitted within each respective annual report. Initiation of such monitoring shall
commence/continue when the July average daily park attendance exceeds 20,132 (through 2003)
and 25,294 from 2004-2010. The monitoring was conducted on July 19-21, 2005 and revealed
that the project is currently generating 1,348 p.m. peak hour trips (obtained via manual counts) and
1,319 p.m. peak hour trips (obtained via machine counts) of the overall 2,284 p.m. peak hour trips
approved for the project.
4.
The developer shall pay appropriate Transportation Impact fees for hotel development beyond 400
rooms and for development of the parcel south of Busch Boulevard. Theme areas, rides, shows,
exhibits, etc. are all otherwise exempted from these fees as identified in Condition 5.D.3.
5.
The developer has confirmed that the Busch Boulevard sidewalk construction between 30th and
40th Streets was completed in 2002, in accordance with Condition 5.D.5.
6.
The developer has provided the following 2004 estimates of potable water, wastewater treatment
and solid waste demand in accordance with Conditions 5.C.10.c. & 5.G.2.:
Potable Water - 17,447,900 gallons (10,291,600 for Busch Gardens and 7,156,300 for Adventure Island).
Wastewater - 13,253,100 gallons (10,291,600 for Busch Gardens and 2,961,500 for Adventure Island).
Solid Waste - 2,615 tons (Busch Gardens and Adventure Island combined).
DEVELOPER OF RECORD
Busch Gardens, c/o Mark D. Rose, 3605 Bougainvillea Avenue, Tampa, FL 33612 is the firm responsible
for adhering to the conditions of the Development Order.
DEVELOPMENT ORDER COMPLIANCE
The project appears to be proceeding in a manner consistent with the Development Order. The City of
Tampa is responsible for ensuring compliance with the terms and conditions of the Development Order.