INTERNATIONAL TELECOMMUNICATION UNION Council Working Group for the Elaboration of the Draft Strategic Plan and the Draft Financial Plan, 2008-2011 Document: WG-SP-FP-06/22 20 April 2006 English Comments from ITU Membership - Response REPLY TO THE COMMENTS MADE BY THE UNITED STATES OF AMERICA ON THE DRAFT ITU FINANCIAL PLAN, 2008-2011 (Document WG-SP-FP-06/21) AND BY FRANCE REGARDING DECISION 6 (MARRAKECH, 2002) Question 1.2 Process 1.2 c states that the draft financial plan shall include only the level of activities consistent with the level of activities for the previous period as well as new activities already authorized. It appears that the Plan as presented goes beyond this guideline. In addition, it is important for the Secretariat to identify those activities from the previous four years that will not be needed in the next quadrennial period or may be given lower priority. Answer The draft Financial Plan has been prepared on the basis of the conditions prevailing for the 20062007 approved budget, with the January 2006 values. It reflects the level of activities foreseen by the Sectors for the 2008-2011 timeframe. Question Part 2 Summary 2.1 Income The information provided throughout the document is based solely on the contributory unit of 329,000 CHF. In order to fully assess the financial plan, it is imperative that more complete figures also be provided at the three other levels of contributory unit requested at the January Working Group meeting, i.e. 318,000; 322,000 and 325,000. The United States believes that a budget based on the contributory unit of 318,000 is needed to serve as the baseline for budget discussions. Answer The four different scenarios are included in the draft financial plan, with an indication of the resources that are needed for the implementation of the full programme. Question 2.2 Expenditure The purpose of this paragraph is unclear as it proposes a contributory unit that is far in excess of any currently under consideration. The Secretariat was asked to prepare four budget scenarios, all using a balanced budget approach. To propose additional activities outside those scenarios 2 was not part of the charge to the secretariat from the Working Group. The United States is also concerned about the lack of any provision for prospective cost increases in the years 2006-2011 and believes that increases based at least on the Swiss CPI should be factored into the budget. Answer The provision for the prospective cost increase during the years 2008-2011 would amount to approximately CHF 35 million, based on the Geneva CPI of 2005 (+1.13 %). Based on a 1% annual increase, it would amount to CHF 31 million as mentioned under paragraph 4.4. Question 2.3 Firm Plan The figures in ‘Variance in %’ indicate increases of 7 and 9 % for various sectors and the general secretariat. Additional information on why these increases are included and what activities or positions are included is needed. Answer The variances first of all include the cost increase which represents 2.4% on average. Further, the table compares the 2008-2011 estimates with the 2004-2005 actuals and the 2006-2007 budget. The 2008-2011 estimates are based on the 2006-2007 approved budget. The savings realized in the 2004-2005 biennium are mostly non recurrent and consequently cannot be reincorporated into the 2008-2011 plan. These savings have been achieved in the spirit of Resolution 1250 and through the implementation of efficiency measures. The high staff turnover in 2004-2005 effectively resulted in recruitment delays which produced some significant reductions of expenditure. A favorable exchange rate also contributed to positive financial results. The planning of uncontrollable factors such as the exchange rate would put the budgets of the Union at risk, and a conservative approach must be taken to this effect. Question Part 4 Main Assumptions and Targets 4.3 Resource planning (see 7.1.8) Please provide additional explanation for the rise in the number of General Secretariat positions by nine. Answer The need for additional resources is specified in paragraph 7.1.8 – page 14 (see the corresponding answer below). Question 4.8 Reserve Account Additional clarification is sought on what the Secretariat is referring to or proposing when discussing reassessing the minimum level of the Reserve Account and how it is calculated. Answer It is rather difficult to predict the level of the Reserve Account during the next period of the financial plan. A prudent and conservative approach should be taken in that matter. To minimize the potential risks a revaluation of the minimum level could be considered. It would be appropriate to take all the ‘variable’ income as the basis. Cost recovery income and other income represent some 17% of the total planned income, at approximately CHF 57 million for a budgetary period. The coverage rate of the Reserve Account would have to be assessed on that basis, taking into account the trends and the experience of the past years. The level of the Reserve Account is to be set by Council. 3 Question Part 5 Contributory Unit 5.2 Ratio between Member States and Sector Member’ Contributions The text indicates that, for purposes of preparing this Financial Plan, an increase from 1/5 to ¼ of the contributory unit has been applied to Sector Members and Associates. However, there is no justification provided for this unauthorized increase. This skews the budget figures based on unsubstantiated premises. The Financial Plan should be prepared using the current 1/5 ratio. If the Secretariat wishes to propose such a change, full justification in terms of expenditure and cost must be provided and approval requested. Answer The change of the ratio from 1/5 to ¼ would increase the level of income by CHF 21,7 million. The principle of 1/5 ratio of the unit was introduced in 1982, based on the structure of the ITU at that time. The question may be asked whether this ratio accurately reflects the proportion of the Sectors' expenses today. The full costs of Sector activities including the costs reallocated from the General Secretariat should be considered in establishing contributory units for Sector Members. Since the Union is now in a position to provide detailed assessment of costs with the use of the new cost allocation methodology (Decision 535), participation by Sector Members should be based on the full costs of the Sector outputs. The new financial management system currently in place provides for transparency in accounting for costs of outputs. On the other hand an across the board increase in the ratio of the Sector Members unit to the Member States unit may adversely affect the participation of some members, particularly those with limited interest in the activities of a Sector. To be fair and equitable, it would seem reasonable to assess the true costs of the services benefiting Sector Members and determine the financing of these services in terms of the level of the contributory unit. This could be calculated on the basis of certain pre-determined assumptions. Such an analysis may be provided if necessary. Question Part 7 Projected Expenditure 7.1.2 No provision has been made for additional staffing in the General Secretariat as a result of WSIS outcomes. This is appropriate, as most WSIS-related implementation should be undertaken in the Sectors and, with the conclusion of the Summit, resources devoted to that phase of WSIS can be reprogrammed to assist with implementation activities. Réponse A provision for additional staffing in the General Secretariat as a result of the WSIS outcomes is provided in Annex II – point 2 of the draft Financial Plan document, and would amount to CHF 2,8 million. Further resources would also be required in BDT for an amount of CHF 1,6 million. Question 7.1.4 Infrastructure Buildings Justification for upgrades and renovations for buildings need to be provided in light of limited budgetary resources. Answer Infrastructure Buildings resources are in line with the previous budgetary provisions (CHF 1,5 million per biennium). No increase is hence foreseen. A list of the planned projects for the 20082011 plan period is given in Annex B. 4 Question 7.1.8 Secretary General Office and Departments This section lists nine additional posts being added to the Secretariat. Six are related to security. The question arises if in-house employees and provision of such services is the appropriate mechanism or if this is a service that can be outsourced more efficiently. Two positions are envisioned for IM. Again, it is unclear if full consolidation of IM services has taken place within ITU to utilize the IM staff as fully and effectively as possible. What extrabudgetary resources were used in the past and why are they no longer available? One position is proposed to be reactivated in the finance section. ITU has already completed substantial work in moving toward results-based budgeting. Why is this being requested at this time? Answer The provision of six security positions, filled in by short term staff, is to comply with the identified requirements in this field. It is in line with the UN policy and in conformity with the practices of other organizations. Retired police officers are contracted as night guards only. The two posts in IS department are currently funded by the TIES contributions. The functions involved are operationally necessary. These should be included in the regular budget as the functions are ongoing regular work. One professional position in Finance Department is proposed to be reactivated in view of the increasing workload and the lack of resources. This post is not linked to the work of moving towards RBB. It is in line with the recommendation number 2 of the external auditor to reinforce the finance department and to take all necessary steps with a view to establishing an effective internal control system and to identify back-ups for key functions in the Finance Department (see document C06/8). Question 7.2 Radiocommunication Sector With no RRC being planned in this Financial Plan period, this results in a savings of 10 million CHF. However, the R budget rises. Additional justification for why the full amount of savings is being reallocated to other activities is needed. Answer Taking into account the program variance between the two Plans (no RRC in 2008-2011), the variance would amount to CHF 10,4 million, or an increase of 8%, which is in line with other Sectors. More detailed explanations are provided in Annex A below. Cost increase: 3% out of 8% Real growth and program variation: 5% out of 8% - Major CPM planned in 2010 - Increased number of RRB meetings - Additional security costs for WRC/RA - Increased interpretation level for RRB - Normal steps increases explain the cost increase of the Bureau Question 7.3 Telecommunication Standardization Sector Substantial increases in funding are envisioned, including for WTSA regional consultation sessions (121 to 353) and study group meetings (3,891 to 4,572). Additional concrete justification for such figures is needed. 5 Answer Concerning the WTSA regional consultation sessions, expenditure level has been set in line with the 2004 initial approved budget for WTSA regional sessions (346,000 CHF). This is a minimum level to comply with the newly adopted WTSA Resolution 43 (Florianópolis, 2004). Previous level of actual expenses corresponded to TSB Director’s initiative to launch regional discussions. Since 2004, the regional sessions have been institutionalized and need a budget to be organized. When comparing the addition of 2004-2005 and 2006-2007 appropriations for ITU-T Study Group meetings with the 2008-2011 request, we can see that there is actually a substantial decrease, the amount falls from 4,967,000 CHF to 4,572,000 CHF. The amount of 3,891,000 CHF corresponds to the addition of actual expenses for 2004-2005 and the budget for 2006-2007. Some savings were achieved in 2004-2005 that would not be possible in the future. ITU-T faces a multitude of new work areas like NGN, Home Networking, IPTV, RFID, Multilingualization, Grid and the fully networked vehicle. The level of 4,572,000 CHF allows ITU-T study groups to face additional workload that will occur and gives the Sector a minimum flexibility to adapt quickly to the changing environment. Question 7.4 Telecommunication Development Sector Substantial increases in funding are envisioned, particularly in RTDC (742 to 1104), TDAG (435 to 852) and study groups meetings (1577 to 2377). Additional concrete justification for these figures is needed. Answer Cost increase: 3% out of 7% Real growth: 4% out of 7% - 1 extra TDAG in 2008-20111, compared to 2004-2007 The draft financial plan represents a return to the normal cycle of an annual TDAG meeting, whereas the 2004-2007 was exceptional situation given the late date of the PP. - Extra study groups activities The increase represents a restoration of annual meetings whereas for budgetary reasons a budget for 2006 was not provided (which has been reinstated through Bureau savings followings results of TDAG and the WTDC). - For the RTDC, no resource increase was requested against the prior period. The discrepancy results from the fact that the expected expenditure were lower due to the generosity of host countries in absorbing certain expenditures. - Normal steps increases explain the cost increase of the Bureau Question Annex I Assessment Matrix between Objectives and Outputs The United States compliments the ITU on the useful matrix provided in Annex I. Analysis of this matrix allows for a more accurate picture of the use of the Union’s resources and provides some indication of the priorities of the sectors. Greater disaggregation of the information in the sector matrixes would be useful, for example by providing greater breakout of costs by study group, showing concentration of activity by individual study group. The model used in ITU-D for the Programs should be applied to other outputs in all sectors as well. We would note however that it remains difficult to discern the level of WSIS expenditure as some of such activities may be dispersed in several outputs. For example, the General Secretariat in the matrix has a line for WSIS at 460,000 CHF; that WSIS line in 7.1 is listed as 0. In addition, it appears that WSIS-related activities may be also undertaken under New Initiatives (from 0 to 202,000 in 7.1 and listed as 1,276,000 in Annex I) and projects (3,500,000 in 7.1 and 3,981,000 here). 6 Answer Breakout of costs by study groups: planning has been established on an aggregated level. Actual costs are collected on detailed level. General Secretariat will be able to provide in the coming months the first actual figures at this level of details. Difference between tables: tables 7.1, 7.2, 7.3 and 7.4 provide primary costs only (costs than can be directly assigned to an output or to the Bureau), while the matrix in Annex 1 provides the full cost of outputs (including reallocated costs). Question Annex II Pending Items The majority of these items should remain unfunded or be incorporated into Sector budgets, with appropriate offsets being made to allow higher priority items to be undertaken first. Some items may be duplicative, such as the security projects and WSIS or unnecessary such as IT services. In all, this section asks for 24 new positions to be created, the majority of them in the General Secretariat. This would run counter to efforts made over several years to make the Union more effective and cost efficient and to streamline the staffing to an appropriate level. Answer All pending items can be identified separately. None is duplicative. Question Annex V Draft Decision 5 Paragraph 1.3 should include interpretation so as to read “that expenditure on interpretation, translation and text processing…” This is in line with the recommendation of the Working Group on Languages to provide total budgetary information regarding the provision of all language services to the Members. The United States does not support the inclusion of paragraphs 4 and 5 in their entirety. OP 4 is redundant and addresses items already taken into consideration by Council as part of budget deliberations and decisions. OP 5 addresses the authority of Council to override the decisions of the Plenipotentiary Conference in reference to the limits established to the contributory unit for the quadrennial period. The United States does not support inclusion of this additional provision and believes that Paragraph 7 adequately addresses any adjustments that must be made. Answer It is up to the membership to agree on the revision of Decision 5. The inclusion of interpretation in paragraph 1.3 is considered appropriate. Question (France) Draft financial plan for 2008-2011: comparison with Decision 6 (Marrakech, 2002) Answer The draft financial plan approved by the 2002 Marrakesh Plenipotentiary Conference in Decision 6 foresaw a financial envelop of KCHF 128,848 for the ITU-R, value 1st January 2002. So as to provide a proper comparison with the proposed estimates for the 2008-2011 timeframe, this amount is to be re-evaluated on the same basis, i.e., 1st January 2006. As indicated in the draft financial plan document, the cost increase between the 1st January 2005 and the 1st January 2006, i.e., for one year, amounts to KCHF 4,280 for the Radiocommunication Sector (Paragraphs 4.1 and 7.2). The comparison stands as follows: 7 ITU-R Financial envelop as per Decision 6 at January 2002 value Annual cost increase Estimated cost increase for four years (from January 2002 to January 2006) CHF(000) 128'848 4'280 17'120 ITU-R financial envelop as per Decision 6 at January 2006 Value 145'968 Proposed estimates for the ITU-R for the 2008-2011 timeframe 137'311 Difference -8'657 The proposed estimates for the R-Sector for the 2008-2011 timeframe are some CHF 8.7 million lower than the financial plan approved for the 2004-2007 timeframe in Decision 6 (Marrakesh, 2002). 8 ANNEX A Answer to USA comments on the draft financial plan, 2008-2011, relating to the Radiocommunication Sector 1 The difference of CHF 10 million should be adjusted to CHF 6.1 million for a fair an appropriate comparison at the same value or purchasing power of the Swiss Franc, as explained in the table below: Estimates 2008-2011 Less cost increase (between 1.1.2005 and 1.1.2006) Actual 2004-2005 + Budget 2006-2007 excluding RRC (136,990-10,077) Difference 2 CHF(000) 137'311 -4'280 126'913 6'118 This difference provides mainly from the two following factors: A) The use as a comparison basis of the 2004-2005 actual which include significant exceptional and non recurrent unspent appropriations; B) The program variation between the 2004-2007 and the 2008-2011 timeframes. A) 2004-2005 unspent appropriations CHF(000) 1 - The significant savings achieved for the Study Group meetings during the 2004-2005 timeframe were mainly on account of reduced level of interpretation. It is important to note, however, that the cost savings achieved in 2004-2005 are not necessarily recurrent and cannot be assumed to be replicable in the future, and in many instances (e.g. interpretation costs) also depend to a large extent on the cooperation of the membership. 1'525 2 - The sales of publications for the Radiocommunication Sector were in the magnitude of CHF 16.5 million, i.e. some 70% of the overall ITU sales of publications. This result was achieved while generating some important savings in the production and dispatch costs for the ITU-R Publications. These factors have already been taken into consideration in the estimates used for the elaboration of the draft financial plan for 2008-2011. 1'185 3 - The unspent appropriations for the Bureau were mostly due to the unforeseen and exceptional recruitment delays that occurred during this timeframe. 2'720 4 - With regards to The RRB and the RAG, some savings were made possible with regards to a reduced interpretation level. Nonetheless, the comments in 1-) on the exceptional nature of these "savings" is also valid for this point Total 2004-2005 non recurrent unspent appropriations 440 5'870 These factors have been duly considered when preparing the financial estimates for the 2008-2011 timeframe but were recognized as non-recurrent factors. 9 B) 2008-2011 program variation 1 - Increased security costs for the WRC/RA 2 - Increased number of meetings of the RRB (15 meetings for 20082011 as against 13 in 2004-2007) 3 - Anticipated increased interpretation level for the RRB Total 2008-2011 program variation CHF(000) 300 350 200 850 The total of the two above factors amounts to CHF 6,720, i.e., some 0.6 million more than the difference indicated in paragraph 1 above. 3 Should the comparison of the 2008-2011 estimates be made with the 2006-2007 budget and with the same output program, the comparison would be as follows: CHF(000) 2006-2007 Budget excluding RRC (CHF 75’250’000 – 7’151’000) 68'099 Multiplied by 2 to consider a four-years period 136'198 Less the estimates of one WRC and one RA (only one venue during the 2008-2011 timeframe) Plus the program variation as indicated above Plus cost increase Estimates 2008-2011 Difference -2'723 850 4'280 137'311 -1'294 Using the 2006-2007 budget as a reliable comparison basis, the 2008-2011 estimates appear CHF 1.3 million lower than the current level of appropriation. It is also important to note that, as indicated in paragraph 4.3 of the draft financial plan and as it was already the case for the 20062007 budget, the anticipated staffing level for the 2008-2011 timeframe is 3 positions lower than the current planned one. ANNEX B List of projects planned for 2008-2011 to be funded from the Buildings Maintenance Fund (in thousands of CHF) Category E BD BD BCE E DE E B BE AE E E BE BCE E Description Buildings Replacement of condenser banks Rearrangement and renovation of Tower meeting room vestibule (Salle des pas-perdus) Rearrangement and renovation of reception (Tower) Facade renewal (Tower) Replacement of inverter unit (Tower) Renovation of men's facilities for delegates (2nd basement of Tower) Replacement of control unit for backup electrical power system (Tower) Modification of LV cabinets for backup and main power Replacement of lighting (Tower) Renovation of the kitchen of the cafeteria (15th floor of Tower) Restaurant (cafeteria on 15th floor of Tower): furniture and equipment Buildings Complete renovation of wastewater/rainwater runoff collectors (Tower) Renovation of domestic hot water system (Tower and Varembé) (excludes central cafeteria) Replacement of radiators (Varembé) Facade renewal (Varembé) Renewal of slab sealing system (Tower lawn) Biennium 2008-2009 Biennium 20102011 400 800 850 11'000 55 310 40 *) *) *) 217 40 60 *) 10'500 2'750 11 Restaurants (central cafeteria): furniture and equipment Total per biennium Allowance for sundries and contingencies (5%) Indexed at 5% per biennium (on 2006-2007 basis) Grand total per biennium GRAND TOTAL 2008-2011 *) Figures unavailable Explanation of categories: A – Urgent works related to safety and/or hygiene B – Works leading to savings and/or greater efficiency C – Works required for compliance with host country codes D – Works related to improving ITU's image E – Works related to replacement of facilities in disrepair 129 13'672 684 718 15'074 30'642 13'479 674 1'415 15'568