LAWYERS TO THE PROJECTS INDUSTRY www.klng.com Summer 2005 Projects Bulletin Building schools for the future will it work? Amongst the many criticisms levelled at PFI/PPP in the past there have been two issues which are very relevant to schools: first, that PFI is a procurement method which only works for the development of new facilities (and for most local authorities, the concern is maintaining the current school estate rather than constructing brand new ones) and second, that PFI projects are one-offs and neither the public sector side nor the successful consortium reaps the benefits of working together in the future. Building Schools for the Future ("BSF") is a programme which the Government has developed with a view to addressing these problems. Unlike conventional PFI projects, which traditionally cover one school or a group of schools in one local education authority ("LEA"), the intention of BSF is that a programme should be developed covering the complete secondary school estate across a wide geographical area. The geographical area can be one LEA, in the case of a big city such as Bristol, or a combination of smaller LEAs so as to produce a big enough mass. Following a competitive tender, the procuring authority appoints a strategic partner which is known as a Local Education Partnership or LEP. In legal terms, the LEP is set up as a limited company with three shareholders - typically the awarding authority as to 10%, Partnerships for Schools (see below) as to 10% and the balance of the shares will be held by a private sector partner. The private sector partner is usually a consortium involving a major contractor with interests in school building, a financial institution and possibly also operators or FM companies. Partnerships for Schools (“PfS”) is the national body which has been set up by DfES to roll out the BSF programme and, as part of that programme, to take investment stakes in LEPs around the country. The Strategic Partnering Agreement ("SPA") between the awarding authority and the LEP normally has a term of 10 years and as explained above it covers all works required in connection with the secondary schools in the relevant geographical area over that period. There may be some exclusions: for example, existing schools which are the subject of a previous PFI project may be "carved out" from the deal, but in theory it extends to all significant capital works (and this may go down as low as £10,000) to any school in the secondary school estate. Not all such capital projects will be suitable for a full blown PFI style procurement. Accordingly the Strategic Partnering Agreement provides that work may Welcome to the Summer Edition of the Projects Bulletin. This edition includes articles on various topics. Should you have any questions about them please find our contact details on page 8. Contents Building Schools for the Future will it work? 1 Update on procurement 3 Financing techniques 6 State Aid 8 Who to contact 8 Projects Bulletin alternatively be placed by the LEP with a contractor using an agreed form design and build contract, or there is an agreed form ICT contract for procuring services from ICT providers. There may be other standard form procurement documents agreed between the parties as part of the initial appointment process. The private sector partner to form the majority shareholder in the LEP is selected in the first place following a competitive procurement and that competition is based on a bid for a number of schools utilising a PFI structure. Although the private sector has to date embraced the BSF concept with some enthusiasm, there are a number of issues of principle which still give cause for concern. First of all, there is the somewhat uneasy relationship which may apply in relation to the organisation, control and management of the LEP which is simultaneously a customer of/supplier to the awarding authority and an investment vehicle in which the awarding authority has a stake. The majority private sector shareholder will carry the majority of the risk but does not have complete control over the LEP and the agreed form of documentation offers many opportunities for (not to put too fine a point on it) interference by PfS and/or the awarding authority. Moreover there are restrictions on the profits which the LEP may retain. Second, the BSF arrangements confer a degree of exclusivity at LEP level - the LEP will be given the first option to carry out projects within the secondary school estate during the life of the SPA. However there are some exclusions from this LEP exclusivity and in 2 SUMMER 2005 addition it may be difficult to create appropriate opportunities for subcontractors of the LEP. Supply chain companies that support the initial bid will be interested in securing the lion's share of the ongoing construction work throughout the life of the SPA but the market testing and benchmarking arrangements built in to the SPA and Shareholders Agreement are such that it may be difficult for the LEP to "guarantee" an appropriate share of the work to sub-contractors. The LEP's obligation to offer value for money to the awarding authority conflicts with its desire to push work down to its agreed supply chain. Third, and this is principally a concern on the public sector side, many authorities are reluctant to grant exclusivity (even subject to exceptions) to one private sector partner over the whole of their school estate for a ten year period. This is significantly different in effect from entering into a PFI project for one or two schools, with the balance remaining under LEA control This concern alone has led to a number of LEAs dragging their feet when looking at BSF. Some authorities have also decided to pursue a nonprofit making approach as an alternative to the limited company LEP. However as a programme BSF appears here to stay and it is viewed by the Government as equivalent in scope and reach to LIFT in the health sector. Christopher Causer (ccauser@klng.com) is a member of the Expert Group advising the Minister for Schools on the development of the BSF programme. www.klng.com Update on procurement Public Procurement - update on developments in 2004/2005 New Public Procurement Directives - 2004 The new Directives on public procurement have been adopted by the EU Parliament on 30 April 2004. The first Directive relates to the procurement of public works, services and supply contracts by public authorities (the Public Sector Directive) whereas the second Directive focuses on the procurement of contracts by utilities in the sectors of water, electricity, gas transport and postal services (the Utilities Directive). The Directives replace the four existing Directives that were adopted between 1989 and 1993. The commercial landscape surrounding public procurement has evolved considerably since the 1990's. The nature and complexity of projects procured by public authorities and the level of technical sophistication available to bidders in delivering projects have increased as well. The new Directives ensure the liberalisation of the EU market and effectiveness of best value for money policies in public procurement by simplifying the existing procurement legislation, combining the rules for works, services and supplies public contracts in one text (instead of one per type of contract works, services or supply) and, finally, clarifying the existing rules by adopting recent developments in case law. The new Directives can be found on the European Parliament website: www.europarl.eu.int. The UK has 21 months to transpose the two Directives into national law. The UK Office of Government Commence ("OGC") has organised a consultation on the transposition of the EU Directives in English law and draft regulations were circulated for comments. The approach taken by OGC is to remain as close to the EU text as possible, because "any substantive departure would raise questions that the UK was trying to interpret the provisions to suit our own circumstances". Our recommendations and practical tips for tendering following the new Directives 2004 are: For public authorities and utilities: In the contract notice or the tender documentation, expressly reserve the right not to accept any bid Retain drafting control on contracts and ask bidders for mark-ups to facilitate comparative analysis of the bids Keep another bidder in reserve following announcement of the preferred bidder For private sector entities bidding for public contracts: Involve lenders early but monitor due diligence costs of lenders' advisers Seek clarification of the tender and bid documents as much as possible Agree allocation of risk between members of consortium For lenders: Due diligence on tender procedure Obtain warranties and sponsors' indemnity on legality of award of the contract Unresolved issues for contracting authorities and private sector tenderers 2004 These issues have not been wholly or partially addressed in the new Directives: Sub-contracting by private sector tenderers who have been awarded a PPP contract Abnormally low tenders Reimbursement of bid costs Protection of intellectual property and confidentiality. We will develop these issues and their implications for PPP and PFI contracts in our next edition of Projects Bulletin. Group or "in-house" awards 2005 The participation of the contracting authority in the capital of a legally distinct company in which a private undertaking participates as well means that the company is subject to the procurement rules. The ECJ held that an entity's private law status does not preclude it from being a contracting authority, in a judgment dated 11 January 2005 (City of Halle, 11 January 2005, Case C-26/03). It was clear under the "Teckal" rule that, in-house awards exempt public authorities from the application of procurement rules when contracts are awarded to their own administrative, SUMMER 2005 3 Projects Bulletin technical or other internal services (Teckal srl v City of Viano, 18 November 1998, Case C-107/98). Following the City of Halle decision of January 2005, the procurement rules apply when a contracting authority awards a contract to a legally distinct entity in which it has an interest, whether the involvement of the private sector in the same entity is minor or substantial. "Alcatel" and effective remedies - 2004/05 The Remedies Directive of 1989 has not been updated (yet) but the EU Commission has launched a consultation on the possible amendments to the Remedies Directive. The intention of the EU Commission is to enhance the effectiveness of procurement 4 SUMMER 2005 remedies by making them available against contracts entered into in breach of public procurement legislation. Contracts entered into in breach of public procurement rules are set aside until the infringement is rectified. Under the Remedies Directive decisions that are in breach of procurement rules must be set aside or annulled. To be successful a claimant has to prove that he had a good chance of success and would have won the contract if it were not for the breach of procurement rules. The now famous "Alcatel" ECJ case law (1998) provides that, while nonfinancial remedies such as contract annulment or setting aside of illegal decisions were available until the contract was concluded, the fact that the only available remedy afterwards being the allocation of damages did not comply with the EU Directive on remedies (Alcatel Austria and others, 28 October 1998, C-81/98). Claimants must be allowed to challenge a decision to award a contract before it is concluded. This is proven difficult in circumstances where award and conclusion of a contract take place simultaneously. Under English law, once the contract has been concluded, the only remedies for infringement of procurement rules is damages. English law does not provide for interim relief or relief at the trial either. The UK has failed to take account of the Alcatel case law so far. OGC is currently consulting on a mandatory standstill period of ten days allowing judicial review either between the decision to award a contract and the conclusion of the contact (first option), or following the conclusion of www.klng.com a contract (second option). The OGC published a consultation paper on possible amendments to English law in December 2001 the proposed amendments failed to impress the EU Commission who issued a reasoned opinion against the UK (31 March 2004). OGC went back to the drawing board and is now asking for views on new amendments to English law. In the recent English case Holleran a private sector entity was excluded from a tender procedure for which it had failed to apply for selection in the relevant time set out by the tender document (Holleran v Severn Trent Water, QBD, 4 November 2004). The judge held that Holleran were to bring proceedings "promptly", meaning within a few days of the alleged infringement, and not within the three month-period of judicial review. The judge refused to allow for an extension of the time allowed to bring proceedings. According to the EU Commission, the possibility to challenge a contract award would allow a more effective and fairer access to public procurement. The risk, however, is that unsuccessful tenderers with very little chance to win the award would use the available remedies to put an halt to the formation of public contracts by making vexatious claims. Will public authorities be prepared to compensate successful bidders from vexatious challenges? In the case Commission v Germany dated 3 March 2005 (Commission v Germany, C-414/03), the ECJ decided that the public authority when it is made aware that a contract had been concluded in breach of the procurement rules must take steps to terminate the contract. Here a German local authority had awarded and concluded a waste disposal contract with a private company without advertising the contract tender procedure. The public authority claimed that terminating the contract would result in the private entity claiming damages. The EU Commission sanctioned the lack of action in response to the infringement. Article 2(6) of the Remedies Directive requires to fully bring procurement infringements to an end by terminating contract already entered into. Green Paper on PPPs - 2005 Watch this space! The EU Commission had organised a consultation on the need for further legislation on the award of PPP contracts. The results are published SUMMER 2005 5 Projects Bulletin on www.europa.eu.net. We are awaiting for the EU Commission's response, expected this Autumn. Freedom of information and public procurement - 2005 On 1 January 2005, the Freedom of Information Act ("FOI") came into force in England and Wales. It is now compulsory for public authorities who receive requests from members of the public for copies of documents and contracts to authorise the communication of these documents. This includes tender documents such as reports on candidates applying to qualify for a public contract, analysis of tenders, award decisions and contract terms. In other words, members of the public may now have access to commercial information and details of deals and terms of contract entered into by public authorities, such as price and bonding arrangements, unless they agree with the contracting authority at the formation of the contract to treat these information as confidential and exempted from the FOI. Future issues will keep readers informed of the progress on these initiatives. If you have any queries on any aspect of Public Procurement, please contact Sophie Charveron (scharveron@klng.com) . 6 SUMMER 2005 Financing techniques Current financing techniques both in domestic PFI transactions and international project finance bear only conceptual resemblance to those which were a feature of the early projects carried out under the Private Finance Initiative in the UK in the mid 1990s. On an international level, many project finance structures, for example in the case of power projects, were largely formulaic. Project finance has become more sophisticated and more complex since then on both a domestic and international level. This trend is likely to continue for the foreseeable future and at a more rapid pace. There are several reasons for this. In addition to the related key factors of cost and risk allocation, while the deals on a national and international level have been much bigger than previously in capital value terms, there have been fewer deals. This in turn has led to increased competition among a large number of players for fewer deals. This has contributed to ingenuity and innovation in terms of structures which in turn have contributed to maximising margins, mitigating risks and squeezing costs. On the domestic PFI front, key financing innovations include the credit guarantee scheme ("CGS") and the prudential borrowing code ("PBC"), both initiatives of HM Treasury. The CGS is designed to reduce the cost of traditional PFI financing while maintaining the same risk-transfer matrix and advantages. Under this regime, bank loans are replaced by government gilts, which in turn are guaranteed by monolines and banks. HM Treasury monitors continually the credit worthiness of the latter and should there be a fall in the guarantors' rating, the idea is that that guarantor would find a replacement at its own cost. While the CGS has encountered resistance from all sectors of the market, the first deal to be financed in this manner has now closed and the CGS is likely to be used in other projects in the near future. These structures are in addition to the myriad of permutations and combinations in both conventional syndicated lending and in the bond project finance market, where innovation has come into its own in the "insurancewrapper" product market and particularly in the use of indices in determining bond yields. Under the PBC, local authorities can borrow directly from the Public Works Loan Board or from a private lender without specific permission from central government as long as the local authorities can prove that they have the capacity to make repayments. This does mean that the Local Authority can act as sponsor and owner in a project and only tender for an operator and turnkey construction contractor. The structure does mean also that there is no technical or legal due diligence from the lenders' advisers and therefore increases the onus on the local authority in this respect. It is also likely to have the effect of increasing costs at the refinancing stage. It is more likely that the PBC will be used only to partially fund projects (as it is unlikely that local authorities will be able to borrow sufficient funds to fully finance a project using this mechanism. This will lead to increased partnering at a finance level and also to co-fundings in these projects. www.klng.com On an international scale, the most significant amount of innovation and creativity has been in the transport sector and in the renewable energy sector. With the imperative for new sources of energy has come the need to look at other financial solutions to finance that procurement. Given the scarcity of these assets and their financial characteristics, demands are being put on financiers to come up with more cost efficient solutions than conventional financing methods can offer. Portfolio financings, mezzanine financings, leasing and tax based financings and private equity all feature in increasingly layered project financings. Export credit finance agencies also often have a role to play. In emerging markets, many projects are financed through local institutional and commercial bank investments where the local currency interest rate risk is an issue. In this context, it is likely that local interest rate risk will soon replace foreign currency devaluation risk on projects, (unlike in the case of projects with large international debt tranches where foreign currency devaluation is often a key risk). Multilaterals are looking to mitigate this risk with devices such as special reserve accounts that smooth out fluctuations over a long term project, thereby encouraging long term investments in markets which would otherwise be unattractive funding propositions for such a term. Developments in the secondary project finance market have revolved around private equity, securitisations and derivative products and often through structured transactions, such as collateralised debt obligations. financings will continue. On an international level, the additional costs imposed under the Basel Capital Accord on banks funding infrastructure projects and the "Equator Principles" to which an increasing number of banks are committing and on a national level, developments in partnering, proposed accounting changes for transactions under the PFI and mandatory treasury requirements for financing competitions in all PFI transactions are all likely to result in a completely different financial landscape when it comes to project financing structures in the future. If you have any queries on any aspect of FinancingTechniques please contact Carolanne Cunningham (ccunningham@klng.com) Current developments suggest that developments and innovation in project SUMMER 2005 7 Projects Travellers’Bulletin Checks State Aid - Commission announces new action plan for next 5 years State Aid is a critical part of the European Union's competition policy. The EC Treaty prohibits any aid granted by Member States or through state resources in any form whatsoever which distorts competition by favouring certain firms or the production of certain goods in so far as it affects trade between Member States. A number of exceptions are allowed and the Commission can approve aid which is notified to it and which fulfils specified public interest criteria. Aid is frequently granted by Member States in the context of major projects and the funding of such projects should always be closely scrutinised for compliance with the State Aid rules. If an unlawful State Aid is identified, the Commission will usually order the relevant Member State to recover the money from the persons or persons to whom it was paid. The Commission has recently announced a comprehensive reform of the State Aid rules and procedures, to take place over the next five years. The Commission has recognised that with the enlargement of the European Union from 15 to 25 Member States, and the proliferation over the years of different rules and guidelines, the time has come for a new framework within which the State Aid rules can be applied and enforced. The key aims of the Commission's Action Plan are: . to ensure that aid should be more targeted so that it delivers economic efficiencies, more growth and jobs, social and regional cohesion within the European Union, improves public services, and encourages sustainable development and cultural diversity; to apply a more sophisticated economic approach so that financial aid which has less of an effect on competition and which is not generally available on the financial markets can be approved more swiftly; to improve procedures for enforcement, increase transparency of decision making, and to accelerate approval procedures (e.g. by decreasing the number of aids which require notification for exemption); to increase co-operation between Member States and the Commission Who to Contact especially as regards notification of proposed aids and the recovery of illegally granted aid. The Commission has published its plans for consultation and invites comments before 15 September 2005. The plan can be found at: http://europa.eu.int/comm/competition/s tate_aid/others/action_plan/ As regards the next steps, the Commission aims this year to reform the Regional Aid Guidelines. The Commission will also be consolidating the various Block Exemption Regulations, which allow Member States to grant aid without having to notify them to the Commission, by the end of 2006. Future issues will keep readers informed of the progress on these initiatives. If you have any queries on any aspect of State Aid please contact Neil Baylis (nbaylis@klng.com). Kirkpatrick & Lockhart For further information contact the following Nicholson Graham LLP Christopher Causer Trevor Nicholls Carolanne Cunningham 110 Cannon Street ccauser@klng.com tnicholls@klng.com ccunningham@klng.com London EC4N 6AR T: +44 (0)20 7360 8147 T: +44 (0)20 7360 8177 T: +44 (0)20 7360 8160 www.klng.com Stuart Borrie Kevin Greene David Race sborrie@klng.com kgreene@klng.com drace@klng.com T: +44 (0)20 7360 8155 T: +44 (0)20 7360 T: +44 (0)20 7360 8106 T: +44 (0)20 7648 9000 F: +44 (0)20 7648 9001 Kirkpatrick & Lockhart Nicholson Graham (K&LNG) has approximately 950 lawyers and represents entrepreneurs, growth and middle market companies, capital markets participants, and leading FORTUNE 100 and FTSE 100 global corporations nationally and internationally. K&LNG is a combination of two limited liability partnerships, each named Kirkpatrick & Lockhart Nicholson Graham LLP, one qualified in Delaware, U.S.A. and practicing from offices in Boston, Dallas, Harrisburg, Los Angeles, Miami, Newark, New York, Palo Alto, Pittsburgh, San Francisco and Washington and one incorporated in England practicing from the London office. This publication/newsletter is for informational purposes and does not contain or convey legal advice. The information herein should not be used or relied upon in regard to any particular facts or circumstances without first consulting a lawyer. Data Protection Act 1998 - We may contact you from time to time with information on Kirkpatrick & Lockhart Nicholson Graham LLP seminars and with our regular newsletters, which may be of interest to you. We will not provide your details to any third parties. Please e-mail cgregory@klng.com if you would prefer not to receive this information. 8 SUMMER 2005 © 2005 KIRKPATRICK & LOCKHART NICHOLSON GRAHAM LLP. ALL RIGHTS RESERVED.