DETERMINATION OF FINANCIAL IMPACTS FROM FLOOD STUDIES MECKLENBURG COUNTY WATER AND LAND RESOURCES DIVISION FINAL REPORT April 2003 Prepared for: MECKLENBURG COUNTY ENGINEERING & BUILDING STANDARDS Charlotte, NC 28202 DETERMINATION OF FINANCIAL IMPACTS FROM FLOOD STUDIES MECKLENBURG COUNTY WATER AND LAND RESOURCES DIVISION FINAL REPORT April 2003 Prepared for: MECKLENBURG COUNTY ENGINEERING & BUILDING STANDARDS 700 North Tryon Street Charlotte, NC 28202 ABS Project No. 251045.01 Contents Page 1. Executive Summary.............................................................................................................................. 1-1 1.1 Project Background ....................................................................................................................... 1-1 1.2 Report Organization ...................................................................................................................... 1-3 1.3 Analysis Synopsis ......................................................................................................................... 1-4 2. Data Analysis ........................................................................................................................................ 2-1 2.1 Data Collection and Processing..................................................................................................... 2-1 2.1.1 Input Data .............................................................................................................................. 2-1 2.1.2 Data Processing Summary ..................................................................................................... 2-3 2.2 Building Damage Analysis............................................................................................................ 2-6 2.3 Building Valuation ........................................................................................................................ 2-7 2.4 Damage Curve Selection ............................................................................................................... 2-8 2.4.1 FIA Depth-Damage Curves.................................................................................................... 2-8 2.4.2 USACE Wilmington District Depth-Damage Curves ........................................................... 2-10 2.4.3 USACE Galveston District Curves....................................................................................... 2-11 2.5 Occupancy Mapping & Damage Assessment ............................................................................. 2-11 3. Flood Hazard Assessments .................................................................................................................. 3-1 3.1 McAlpine Creek Analysis ............................................................................................................. 3-7 3.1.1 Results Summary for the McAlpine Creek Basin.................................................................... 3-7 3.1.2 Data Analysis ......................................................................................................................... 3-9 3.1.2.1 Parcel and Building Data Review ................................................................................................ 3-9 3.1.2.2 Parcels Without a Surveyed Structure ........................................................................................ 3-11 3.1.2.3 Surveyed Structures Intersecting a Parcel .................................................................................. 3-13 3.1.2.4 Surveyed Structures Not Intersecting a Parcel ........................................................................... 3-14 3.1.3 3.2 Detailed Results ................................................................................................................... 3-14 Sugar Creek Analysis .................................................................................................................. 3-21 3.2.1 Results Summary for the Sugar Creek Basin (below Irwin Creek) ...................................... 3-21 3.2.2 Data Analysis ....................................................................................................................... 3-24 3.2.2.1 Sugar Creek Basin Characteristics and Study Data .................................................................... 3-24 3.2.2.2 Sugar Creek Watershed Depth Grid ........................................................................................... 3-25 3.2.2.3 Sugar Creek Parcel and Building Data Review .......................................................................... 3-30 iii 3.2.3 3.3 Detailed Results for the Sugar Creek Basin ......................................................................... 3-31 Long Creek Analysis ................................................................................................................... 3-38 3.3.1 Results Summary for the Long Creek Basin ......................................................................... 3-38 3.3.2 Data Analysis ....................................................................................................................... 3-41 3.3.2.1 3.3.3 3.4 Long Creek Basin Characteristics and Study Data ..................................................................... 3-41 Detailed Results for the Long Creek Basin .......................................................................... 3-48 Little Sugar and Briar Creek Analysis ........................................................................................ 3-55 3.4.1 Results Summary for the Little Sugar and Briar Creek Basin.............................................. 3-55 3.4.2 Data Analysis ....................................................................................................................... 3-58 3.4.2.1 3.4.3 3.5 Little Sugar & Briar Creeks Basin Characteristics and Study Data ............................................ 3-58 Detailed Results for the Little Sugar & Briar Creek Basins ................................................ 3-64 Four Mile Creek and Rocky Branch Analysis ............................................................................. 3-72 3.5.1 Results Summary for the Four Mile Creek and Rocky Branch Basins ................................. 3-72 3.5.2 Data Analysis ....................................................................................................................... 3-74 3.5.2.1 3.5.3 3.6 Four Mile Creek and the Rocky Branch Basin Characteristics and Study Data ......................... 3-74 Detailed Results Four Mile Creek and Rocky Branch Basins .............................................. 3-81 McDowell Creek Analysis .......................................................................................................... 3-88 3.6.1 Results Summary for the McDowell Creek Basin ................................................................ 3-88 3.6.2 Data Analysis ....................................................................................................................... 3-91 3.6.2.1 3.6.3 3.7 McDowell Creek Basin Characteristics and Study Data ............................................................ 3-91 Detailed Results for the McDowell Creek Basin .................................................................. 3-97 McMullen Creek Analysis ........................................................................................................ 3-104 3.7.1 Results Summary for the McMullen Creek Basin ............................................................... 3-104 3.7.2 Data Analysis ..................................................................................................................... 3-107 3.7.2.1 3.7.3 3.8 McMullen Creek Basin Characteristics and Study Data .......................................................... 3-107 Detailed Results for the McMullen Creek Basin ................................................................ 3-114 McKee Creek Analysis ............................................................................................................. 3-121 3.8.1 Results Summary for the McKee Creek Basin .................................................................... 3-121 3.8.2 Data Analysis ..................................................................................................................... 3-124 3.8.2.1 3.8.3 3.9 McKee Creek Basin Characteristics and Study Data ............................................................... 3-124 Detailed Results for the McKee Creek Basin ..................................................................... 3-130 Back Creek Analysis ................................................................................................................. 3-136 3.9.1 Results Summary for the Back Creek Basin ....................................................................... 3-136 3.9.2 Data Analysis ..................................................................................................................... 3-139 3.9.2.1 3.9.3 3.10 Back Creek and Back Tributary Basin Characteristics and Study Data ................................... 3-139 Detailed Results for the Back Creek Basin ........................................................................ 3-145 Six Mile Creek Analysis .................................................................................................... 3-151 3.10.1 Results Summary for the Six Mile Creek Basin .................................................................. 3-151 iv 3.10.2 Data Analysis ..................................................................................................................... 3-153 3.10.2.1 Six Mile Creek and Flat Branch Basin Characteristics and Study Data ........................................ 3-153 3.10.3 Detailed Results for the Six Mile Creek Basin ................................................................... 3-160 3.11 Clems Branch Analysis ...................................................................................................... 3-166 3.11.1 Results Summary for the Clems Branch Basin ................................................................... 3-166 3.11.2 Data Analysis ..................................................................................................................... 3-167 3.11.2.1 Clems Branch Basin Characteristics and Study Data.................................................................... 3-167 3.11.3 Detailed Results for the Clems Branch Basin .................................................................... 3-173 3.12 Reedy Creek Analysis ........................................................................................................ 3-175 3.12.1 Results Summary for the Reedy Creek Basin ..................................................................... 3-175 3.12.2 Data Analysis ..................................................................................................................... 3-177 3.12.2.1 Reedy Creek Basin Characteristics and Study Data...................................................................... 3-177 3.12.3 Detailed Results for the Reedy Creek Basin....................................................................... 3-184 3.13 Clarke Creek Analysis ....................................................................................................... 3-190 3.13.1 Results Summary for the Clarke Creek Basin .................................................................... 3-190 3.13.2 Data Analysis ..................................................................................................................... 3-192 3.13.2.1 Clarke Creek Basin Characteristics and Study Data ..................................................................... 3-192 3.13.3 Detailed Results for the Clarke Creek Basin ..................................................................... 3-199 3.14 Mallard Creek Analysis ..................................................................................................... 3-205 3.14.1 Results Summary for the Mallard Creek Basin .................................................................. 3-205 3.14.2 Data Analysis ..................................................................................................................... 3-208 3.14.2.1 Mallard Creek Basin Characteristics and Study Data ................................................................... 3-208 3.14.3 Detailed Results for the Mallard Creek Basin ................................................................... 3-214 3.15 Irwin Creek Analysis ......................................................................................................... 3-222 3.15.1 Results Summary for the Irwin Creek Basin ...................................................................... 3-222 3.15.2 Data Analysis ..................................................................................................................... 3-224 3.15.2.1 Irwin Creek Basin Characteristics and Study Data ....................................................................... 3-224 3.15.3 Detailed Results for the Irwin Creek Basin ........................................................................ 3-231 3.16 Rocky River Analysis ........................................................................................................ 3-239 3.16.1 Results Summary for the Rocky River Basin ...................................................................... 3-239 3.16.2 Data Analysis ..................................................................................................................... 3-241 3.16.2.1 Rocky River Basin Characteristics and Study Data ...................................................................... 3-241 3.16.3 Detailed Results for the Rocky River Basin ....................................................................... 3-249 3.17 Goose Creek Analysis ........................................................................................................ 3-256 3.17.1 Results Summary for the Goose Creek Basin ..................................................................... 3-256 3.17.2 Data Analysis ..................................................................................................................... 3-258 3.17.2.1 Goose Creek Basin Characteristics and Study Data...................................................................... 3-258 3.17.3 Detailed Results for the Goose Creek Basin ...................................................................... 3-266 v 3.18 Lower Clarke Creek Analysis ............................................................................................ 3-272 3.18.1 Results Summary for the Lower Clarke Creek Tributary Basin ......................................... 3-272 3.18.2 Data Analysis ..................................................................................................................... 3-274 3.18.2.1 Clarke Creek Tributary Basin Characteristics and Study Data ..................................................... 3-274 3.18.3 Detailed Results for the Lower Clarke Creek Tributary Basin .......................................... 3-281 3.19 Beaverdam Creek Analysis ................................................................................................ 3-286 3.19.1 Results Summary for the Beaverdam Basin ....................................................................... 3-286 3.20 Clear Creek Analysis ......................................................................................................... 3-287 3.20.1 Results Summary for the Clear Creek Basin ...................................................................... 3-287 3.21 Gar Creek Analysis ............................................................................................................ 3-288 3.21.1 Results Summary for the Gar Creek Basin......................................................................... 3-288 3.22 Paw Creek Analysis ........................................................................................................... 3-289 3.22.1 Results Summary for the Paw Creek Basin ........................................................................ 3-289 3.23 Steele Creek Analysis ........................................................................................................ 3-290 3.23.1 Results Summary for the Steele Creek Basin ..................................................................... 3-290 4. Recommendations for Data Enhancements ....................................................................................... 4-1 4.1 County Tax Assessor Data Enhancement...................................................................................... 4-1 4.2 Integration of Building Footprints and Parcel Data....................................................................... 4-2 4.3 Merging Survey Data and Assignment Data to Building Footprints ............................................. 4-2 4.4 Revisit Parcel Boundary Inconsistencies ...................................................................................... 4-3 4.5 Building Valuation ........................................................................................................................ 4-4 Appendices A. Reference Tables ................................................................................................................................. A-1 vi Tables 1-1. Total Estimated Flood Losses for Mecklenburg County ..................................................................... 1-8 1-2. Total Parcels and Total Vacant Parcels By Watershed ....................................................................... 1-9 1-3. Total Number of Flooded Structures by General Occupancy for all Watersheds Analyzed in This Project to Date ............................................................................................................................. 1-11 1-4. Total Buildings and “Ultimate Build out” ......................................................................................... 1-12 3-1. Estimated Structure Losses for Mecklenburg County ......................................................................... 3-2 3-2. Estimated Contents Losses for Mecklenburg County ......................................................................... 3-6 3.1-1. Number of Flooded Structures by General Occupancy: McAlpine Creek Watershed ..................... 3-7 3.1-2. Summary of Building and Content Damage by General Occupancy: McAlpine Creek Watershed.................................................................................................................................... 3-10 3.1-3. Foundation Type Distribution by Zone: McAlpine Creek Watershed ........................................... 3-13 3.1-4. Number of Flooded Buildings by HAZUS®MH Occupancy Type: McAlpine Creek Watershed .... 3-15 3.1-5. Structure Damage Percent by HAZUS®MH Occupancy Type: McAlpine Creek Watershed .......... 3-17 3.1-6. Structure Dollar Damage by HAZUS®MH Occupancy Type: McAlpine Creek Watershed ............ 3-18 3.1-7. Contents Damage Percent by HAZUS®MH Occupancy Type: McAlpine Creek Watershed .......... 3-19 3.1-8. Contents Dollar Damage by HAZUS®MH Occupancy Type: McAlpine Creek Watershed............. 3-20 3.2-1. Number of Flooded Structures by General Occupancy: Sugar Creek Watershed .......................... 3-21 3.2-2. Summary of Building and Content Damage by General Occupancy: Sugar Creek Watershed ..... 3-23 3.2-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Sugar Creek Watershed ........... 3-32 3.2-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Sugar Creek Watershed .. 3-34 3.2-5. Structure Dollar Damage by HAZUS®MH Occupancy Type: Sugar Creek Watershed................... 3-35 3.2-6. Contents Damage Percent by HAZUS®MH Occupancy Type: Sugar Creek Watershed ................. 3-36 3.2-7. Contents Dollar Damage by HAZUS®MH Occupancy Type: Sugar Creek Watershed ................... 3-37 3.3-1. Number of Flooded Structures by General Occupancy: Long Creek Watershed ........................... 3-38 3.3-2. Summary of Building and Content Damage by General Occupancy: Long Creek Watershed ...... 3-40 3.3-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Long Creek Watershed ............ 3-49 3.3-4. Structure Damage Percent by HAZUS®MH Occupancy Type: Long Creek Watershed .................. 3-51 3.3-5. Structure Dollar Damage by HAZUS®MH Occupancy Type: Long Creek Watershed ................... 3-52 3.3-6. Contents Damage Percent by HAZUS®MH Occupancy Type: Long Creek Watershed .................. 3-53 3.3-7. Contents Dollar Damage by HAZUS®MH Occupancy Type: Long Creek Watershed .................... 3-54 3.4-1. Number of Flooded Structures by General Occupancy: Little Sugar and Briar Creek Watershed.................................................................................................................................... 3-55 3.4-2. Summary of Building and Content Damage by General Occupancy: Little Sugar and Briar Creek Watershed.................................................................................................................................... 3-57 3.4-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Little Sugar and Briar Creek Watershed.................................................................................................................................... 3-66 vii 3.4-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Little Sugar and Briar Creek Watershed.................................................................................................................................... 3-68 3.4-5. Structure Dollar Damage by HAZUS®MH Occupancy Type: Little Sugar and Briar Creek Watershed.................................................................................................................................... 3-69 3.4-6. Contents Damage Percent by HAZUS®MH Occupancy Type: Little Sugar and Briar Creek Watershed.................................................................................................................................... 3-70 3.4-7. Contents Dollar Damage by HAZUS®MH Occupancy Type: Little Sugar and Briar Creek Watershed.................................................................................................................................... 3-71 3.5-1. Number of Flooded Structures by General Occupancy: Four Mile Creek and Rocky Branch Watersheds .................................................................................................................................. 3-72 3.5-2. Summary of Building and Content Damage by General Occupancy Four Mile Creek and Rocky Branch Watersheds...................................................................................................................... 3-74 3.5-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Four Mile Creek and Rocky Branch Watersheds .................................................................................................................................. 3-83 3.5-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Four Mile Creek and Rocky Branch Watersheds...................................................................................................................... 3-85 3.5-5. Structure Dollar Damage by HAZUS®MH Occupancy Type: Four Mile Creek and Rocky Branch Watersheds .................................................................................................................................. 3-86 3.5-6. Contents Damage Percent by HAZUS®MH Occupancy Type: Four Mile Creek and Rocky Branch Watersheds .................................................................................................................................. 3-86 3.5-7. Contents Dollar Damage by HAZUS®MH Occupancy Type Four Mile Creek and Rocky Branch Watersheds .................................................................................................................................. 3-87 3.6-1. Number of Flooded Structures by General Occupancy: McDowell Creek Watershed ................. 3-88 3.6-2. Summary of Building and Content Damage by General Occupancy: McDowell Creek Watershed.................................................................................................................................... 3-90 3.6-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: McDowell Creek Watershed ... 3-98 3.6-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: McDowell Creek Watershed.................................................................................................................................. 3-100 3.6-5. Structure Dollar Damage by HAZUS®MH Occupancy Type McDowell Creek Watershed .......... 3-101 3.6-6. Contents Damage Percent by HAZUS®MH Occupancy Type McDowell Creek Watershed ......... 3-101 3.6-7. Contents Dollar Damage by HAZUS®MH Occupancy Type McDowell Creek Watershed .......... 3-103 3.7-1. Number of Flooded Structures by General Occupancy: McMullen Creek Watershed................ 3-104 3.7-2. Summary of Building and Content Damage by General Occupancy: McMullen Creek Watershed.................................................................................................................................. 3-106 3.7-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: McMullen Creek Watershed.................................................................................................................................. 3-115 viii 3.7-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: McMullen Creek Watershed.................................................................................................................................. 3-117 3.7-5. Structure Dollar Damage by HAZUS®MH Occupancy Type McMullen Creek Watershed .......... 3-118 3.7-6. Contents Damage Percent by HAZUS®MH Occupancy Type McMullen Creek Watershed ......... 3-119 3.7-7. Contents Dollar Damage by HAZUS®MH Occupancy Type McMullen Creek Watershed ........... 3-120 3.8-1. Number of Flooded Structures by General Occupancy: McKee Creek Watershed..................... 3-121 3.8-2. Summary of Building and Content Damage by General Occupancy: McKee Creek Watershed.................................................................................................................................. 3-123 3.8-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: McKee Creek Watershed ...... 3-131 3.8-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: McKee Creek Watershed.................................................................................................................................. 3-133 3.8-5. Structure Dollar Damage by HAZUS®MH Occupancy Type McKee Creek Watershed ............... 3-134 3.8-6. Contents Damage Percent by HAZUS®MH Occupancy Type McKee Creek Watershed .............. 3-134 3.8-7. Contents Dollar Damage by HAZUS®MH Occupancy Type McKee Creek Watershed ................ 3-135 3.9-1. Number of Flooded Structures by General Occupancy: Back Creek Watershed ........................ 3-136 3.9-2. Summary of Building and Content Damage by General Occupancy: Back Creek Watershed .... 3-138 3.9-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Back Creek Watershed ......... 3-146 3.9-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Back Creek Watershed . 3-148 3.9-5. Structure Dollar Damage by HAZUS®MH Occupancy Type Back Creek Watershed ................... 3-149 3.9-6. Contents Damage Percent by HAZUS®MH Occupancy Type Back Creek Watershed ................. 3-149 3.9-7. Contents Dollar Damage by HAZUS®MH Occupancy Type Back Creek Watershed ................... 3-150 3.10-1. Number of Flooded Structures by General Occupancy: Six Mile Creek Watershed................. 3-151 3.10-2. Summary of Building and Content Damage by General Occupancy: Six Mile Creek Watershed.................................................................................................................................. 3-153 3.10-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Six Mile Creek Watershed.................................................................................................................................. 3-161 3.10-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Six Mile Creek Watershed.................................................................................................................................. 3-163 3.10-5. Structure Dollar Damage by HAZUS®MH Occupancy Type Six Mile Creek Watershed ........... 3-164 3.10-6. Contents Damage Percent by HAZUS®MH Occupancy Type Six Mile Creek Watershed .......... 3-164 3.10-7. Contents Dollar Damage by HAZUS®MH Occupancy Type Six Mile Creek Watershed ............ 3-165 3.11-1. Number of Flooded Structures by General Occupancy: Clems Branch Watershed .................. 3-166 3.11-2. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Clems Branch Watershed .... 3-174 3.12-1. Number of Flooded Structures by General Occupancy: Reedy Creek Watershed .................... 3-175 3.12-2. Summary of Building and Content Damage by General Occupancy: Reedy Creek Watershed.................................................................................................................................. 3-177 3.12-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Reedy Creek Watershed ...... 3-185 ix 3.12-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Reedy Creek Watershed.................................................................................................................................. 3-187 3.12-5. Structure Dollar Damage by HAZUS®MH Occupancy Type Reedy Creek Watershed ............... 3-188 3.12-6. Contents Damage Percent by HAZUS®MH Occupancy Type Reedy Creek Watershed ............. 3-188 3.12-7. Contents Dollar Damage by HAZUS®MH Occupancy Type Reedy Creek Watershed ............... 3-189 3.13-1. Number of Flooded Structures by General Occupancy: Clarke Creek Watershed .................... 3-190 3.13-2. Summary of Building and Content Damage by General Occupancy: Clarke Creek Watershed.................................................................................................................................. 3-192 3.13-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Clarke Creek Watershed .... 3-200 3.13-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Clarke Creek Watershed.................................................................................................................................. 3-202 3.13-5. Structure Dollar Damage by HAZUS®MH Occupancy Type Clarke Creek Watershed .............. 3-203 3.13-6. Contents Damage Percent by HAZUS®MH Occupancy Type Clarke Creek Watershed ............. 3-203 3.13-7. Contents Dollar Damage by HAZUS®MH Occupancy Type Clarke Creek Watershed ............... 3-204 3.14-1. Number of Flooded Structures by General Occupancy: Mallard Creek Watershed .................. 3-205 3.14-2. Summary of Building and Content Damage by General Occupancy: Mallard Creek Watershed.................................................................................................................................. 3-207 3.14-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Mallard Creek Watershed ... 3-216 3.14-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Mallard Creek Watershed.................................................................................................................................. 3-218 3.14-5. Structure Dollar Damage by HAZUS®MH Occupancy Type Mallard Creek Watershed ............ 3-219 3.14-6. Contents Damage Percent by HAZUS®MH Occupancy Type Mallard Creek Watershed ........... 3-220 3.14-7. Contents Dollar Damage by HAZUS®MH Occupancy Type Mallard Creek Watershed ............. 3-221 3.15-1. Number of Flooded Structures by General Occupancy: Irwin Creek Watershed ...................... 3-222 3.15-2. Summary of Building and Content Damage by General Occupancy: Irwin Creek Watershed.................................................................................................................................. 3-224 3.15-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Irwin Creek Watershed ....... 3-233 3.15-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Irwin Creek Watershed.................................................................................................................................. 3-235 3.15-5. Structure Dollar Damage by HAZUS®MH Occupancy Type Irwin Creek Watershed ................ 3-236 3.15-6. Contents Damage Percent by HAZUS®MH Occupancy Type: Irwin Creek Watershed .............. 3-237 3.15-7. Contents Dollar Damage by HAZUS®MH Occupancy Type Irwin Creek Watershed ................. 3-238 3.16-1. Number of Flooded Structures by General Occupancy: Rocky River Basin............................. 3-239 3.16-2. Summary of Building and Content Damage by General Occupancy: Rocky River Basin ........ 3-241 3.16-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Rocky River Basin ............. 3-251 3.16-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Rocky River Basin ...... 3-253 3.16-5. Structure Dollar Damage by HAZUS®MH Occupancy Type Rocky River Basin ....................... 3-253 x 3.16-6. Contents Damage Percent by HAZUS®MH Occupancy Type Rocky River Basin ...................... 3-254 3.16-7. Contents Dollar Damage by HAZUS®MH Occupancy Type Rocky River Basin ........................ 3-255 3.17-1. Number of Flooded Structures by General Occupancy: Goose Creek Watershed .................... 3-256 3.17-2. Summary of Building and Content Damage by General Occupancy: Goose Creek Watershed.................................................................................................................................. 3-258 3.17-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Goose Creek Watershed ...... 3-267 3.17-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Goose Creek Watershed.................................................................................................................................. 3-269 3.17-5. Structure Dollar Damage by HAZUS®MH Occupancy Type Goose Creek Watershed ............... 3-269 3.17-6. Contents Damage Percent by HAZUS®MH Occupancy Type Goose Creek Watershed.............. 3-270 3.17-7. Contents Dollar Damage by HAZUS®MH Occupancy Type Goose Creek Watershed ............... 3-271 3.18-1. Number of Flooded Structures by General Occupancy: Lower Clarke Creek Watershed ........ 3-272 3.18-2. Summary of Building and Content Damage by General Occupancy: Lower Clarke Creek Watershed.................................................................................................................................. 3-274 3.18-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Lower Clarke Creek Watershed.................................................................................................................................. 3-282 3.18-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Lower Clarke Creek Watershed.................................................................................................................................. 3-283 3.18-5. Structure Dollar Damage by HAZUS®MH Occupancy Type Lower Clarke Creek Watershed ... 3-284 3.18-6. Contents Damage Percent by HAZUS®MH Occupancy Type Lower Clarke Creek Watershed .. 3-285 3.18-7. Contents Dollar Damage by HAZUS®MH Occupancy Type Lower Clarke Creek Watershed ... 3-285 A-1. Mapping of Mecklenburg Use Codes into HAZUS®MH Occupancy Codes....................................... A-1 A-2. Estimated Typical Floor Area and Cost per Square Foot by Mecklenburg Occupancy Code ........... A-4 A-3. HAZUS®MH Content Value as a Percentage of Structure Value........................................................ A-6 A-4. HAZUS®MH Foundation Distribution (default) and Adjusted Foundation Distribution Used in Mecklenburg County .................................................................................................................... A-7 Figures 1-1. Watersheds Analyzed For Mecklenburg County ................................................................................ 1-3 1-2. Total Estimated Losses for Mecklenburg County by Analysis Run.................................................... 1-5 1-3. Total Estimated Building and Content Losses for Mecklenburg County by Analysis Run ................ 1-6 2-1. Overview of Data Provided by Mecklenburg County (Image is from the Goose Creek Watershed) .. 2-4 2-2. FIA Credibility-Weighted Building Depth-Damage Curves as of 12/31/1998 ................................ 2-10 3-1. Total Estimated Losses by Watershed for Run 2 ................................................................................ 3-5 3.1-1. McAlpine Creek Watershed Aggregate Damage Estimation Results .............................................. 3-8 3.1-2. Floor Height Distribution Zones .................................................................................................... 3-12 xi 3.1-3. McAlpine Creek Watershed Aggregated Damage Estimation Results .......................................... 3-16 3.2-1. Sugar Creek Watershed Aggregate Damage Estimation Results ................................................... 3-22 3.2-2. Sugar Creek Basin Stream Network ............................................................................................... 3-24 3.2-3. Existing Conditions Flood Depth Grid ........................................................................................... 3-26 3.2-4. Distribution of Existing Condition Flood Depths........................................................................... 3-26 3.2-5. Future Conditions Flood Depth Grid.............................................................................................. 3-27 3.2-6. Distribution of Future Condition Flood Depths ............................................................................. 3-28 3.2-7. Increases in 100-year Flood Depths ............................................................................................... 3-29 3.2-8. Differences in 100-year Flood Depths ........................................................................................... 3-29 3.2-9. Sugar Creek Watershed Aggregate Damage Estimation Results ................................................... 3-33 3.3-1. Long Creek Watershed Aggregate Damage Estimation Results .................................................... 3-39 3.3-2. Long Creek Basin Stream Network................................................................................................ 3-41 3.3-3. Existing Conditions Flood Depth Grid ........................................................................................... 3-43 3.3-4. Distribution of Existing Condition Flood Depths........................................................................... 3-43 3.3-5. Future Conditions Flood Depth Grid.............................................................................................. 3-44 3.3-6. Distribution of Future Condition Flood Depths ............................................................................. 3-45 3.3-7. Increases in 100-year Flood Depths ............................................................................................... 3-46 3.3-8. Differences in 100-year Flood Depths ........................................................................................... 3-46 3.3-9. Long Creek Watershed Aggregate Damage Estimation Results .................................................... 3-50 3.4-1. Little Sugar & Briar Creeks Aggregate Damage Estimation Results ............................................. 3-56 3.4-2. Little Sugar Creek Basin Stream Network ..................................................................................... 3-58 3.4-3. Existing Conditions Flood Depth Grid ........................................................................................... 3-59 3.4-4. Distribution of Existing Condition Flood Depths........................................................................... 3-60 3.4-5. Future Conditions Flood Depth Grid.............................................................................................. 3-61 3.4-6. Distribution of Future Condition Flood Depths ............................................................................. 3-61 3.4-7. Increases in 100-year Flood Depths ............................................................................................... 3-62 3.4-8. Differences in 100-year Flood Depths ........................................................................................... 3-63 3.4-9. Little Sugar & Briar Creek Aggregate Damage Estimation Results .............................................. 3-67 3.5-1. Four Mile Creek and Rocky Branch Watersheds Aggregate Damage Estimation Results ............ 3-73 3.5-2. McAlpine Creek Basin Stream Network ........................................................................................ 3-75 3.5-3. Existing Conditions Flood Depth Grid: Four Mile Creek and Rocky Branch ................................ 3-76 3.5-4. Distribution of Existing Condition Flood Depths: Four Mile Creek and Rocky Branch ............... 3-77 3.5-5. Future Conditions Flood Depth Grid Four Mile Creek and Rocky Branch.................................... 3-78 3.5-6. Distribution of Future Condition Flood Depths Four Mile Creek and Rocky Branch ................... 3-78 3.5-7. Increases in 100-year Flood Depths ............................................................................................... 3-79 3.5-8. Differences in 100-year Flood Depths: Four Mile Creek and Rocky Branch ................................ 3-80 3.5-9. Four Mile Creek And Rocky Branch Aggregate Damage Estimation Results ............................... 3-84 xii 3.6-1. McDowell Creek Watershed Aggregate Damage Estimation Results............................................ 3-89 3.6-2. McDowell Creek Basin Stream Network ....................................................................................... 3-91 3.6-3. Existing Conditions Flood Depth Grid McDowell Creek Watershed ............................................ 3-92 3.6-4. Distribution of Existing Condition Flood Depths McDowell Creek Watershed ............................ 3-93 3.6-5. Future Conditions Flood Depth Grid McDowell Creek Watershed ............................................... 3-94 3.6-6. Distribution of Future Condition Flood Depths McDowell Creek Watershed ............................... 3-94 3.6-7. Increases in 100-year Flood Depths McDowell Creek Watershed ................................................. 3-95 3.6-8. Differences in 100-year Flood Depths McDowell Creek Watershed ............................................. 3-96 3.6-9. McDowell Creek Watershed Aggregate Damage Estimation Results............................................ 3-99 3.7-1. McMullen Creek Watershed Aggregate Damage Estimation Results .......................................... 3-105 3.7-2. McAlpine Creek Basin Stream Network McMullen Creek Watershed ........................................ 3-107 3.7-3. Existing Conditions Flood Depth Grid McMullen Creek Watershed........................................... 3-109 3.7-4. Distribution of Existing Condition Flood Depths McMullen Creek Watershed .......................... 3-109 3.7-5. Future Conditions Flood Depth Grid McMullen Creek Watershed ............................................. 3-110 3.7-6. Distribution of Future Condition Flood Depths McMullen Creek Watershed ............................. 3-111 3.7-7. Increases in 100-year Flood Depths McMullen Creek Watershed ............................................... 3-112 3.7-8. Differences in 100-year Flood Depths McMullen Creek Watershed ........................................... 3-112 3.7-9. McMullen Creek Watershed Aggregate Damage Estimation Results .......................................... 3-116 3.8-1. McKee Creek Watershed Aggregate Damage Estimation Results ............................................... 3-122 3.8-2. McKee Creek and Nearby Stream Systems.................................................................................. 3-124 3.8-3. Existing Conditions Flood Depth Grid ......................................................................................... 3-125 3.8-4. Distribution of Existing Condition Flood Depths......................................................................... 3-126 3.8-5. Future Conditions Flood Depth Grid............................................................................................ 3-127 3.8-6. Distribution of Future Condition Flood Depths ........................................................................... 3-127 3.8-7. Increases in 100-year Flood Depths ............................................................................................. 3-128 3.8-8. Differences in 100-year Flood Depths ......................................................................................... 3-129 3.8-9. McKee Creek Watershed Aggregate Damage Estimation Results ............................................... 3-132 3.9-1. Back Creek Watershed Aggregate Damage Estimation Results .................................................. 3-137 3.9-2. Back Creek and Back Creek Tributary ......................................................................................... 3-139 3.9-3. Existing Conditions Flood Depth Grid ......................................................................................... 3-140 3.9-4. Distribution of Existing Condition Flood Depths......................................................................... 3-141 3.9-5. Future Conditions Flood Depth Grid............................................................................................ 3-142 3.9-6. Distribution of Future Condition Flood Depths ........................................................................... 3-142 3.9-7. Increases in 100-year Flood Depths ............................................................................................. 3-143 3.9-8. Differences in 100-year Flood Depths ......................................................................................... 3-144 3.9-9. Back Creek Watershed Aggregate Damage Estimation Results .................................................. 3-147 3.10-1. Six Mile Creek Watershed Aggregate Damage Estimation Results ........................................... 3-152 xiii 3.10-2. Six Mile Creek and Flat Branch ................................................................................................. 3-154 3.10-3. Existing Conditions Flood Depth Grid ....................................................................................... 3-155 3.10-4. Distribution of Existing Condition Flood Depths....................................................................... 3-156 3.10-5. Future Conditions Flood Depth Grid.......................................................................................... 3-157 3.10-6. Distribution of Future Condition Flood Depths ......................................................................... 3-157 3.10-7. Increases in 100-year Flood Depths ........................................................................................... 3-158 3.10-8. Differences in 100-year Flood Depths ....................................................................................... 3-159 3.10-9. Six Mile Creek Watershed Aggregate Damage Estimation Results ........................................... 3-162 3.11-1. Clems Branch and Nearby Stream Systems ............................................................................... 3-167 3.11-2. Existing Conditions Flood Depth Grid ....................................................................................... 3-168 3.11-3. Distribution of Existing Condition Flood Depths....................................................................... 3-169 3.11-4. Future Conditions Flood Depth Grid.......................................................................................... 3-170 3.11-5. Distribution of Future Condition Flood Depths ......................................................................... 3-170 3.11-6. Increases in 100-year Flood Depths ........................................................................................... 3-171 3.11-7. Differences in 100-year Flood Depths ....................................................................................... 3-172 3.12-1. Reedy Creek Watershed Aggregate Damage Estimation Results .............................................. 3-176 3.12-2. Reedy Creek Basin Stream Network .......................................................................................... 3-178 3.12-3. Existing Conditions Flood Depth Grid ....................................................................................... 3-179 3.12-4. Distribution of Existing Condition Flood Depths....................................................................... 3-180 3.12-5. Future Conditions Flood Depth Grid.......................................................................................... 3-181 3.12-6. Distribution of Future Condition Flood Depths ......................................................................... 3-181 3.12-7. Increases in 100-year Flood Depths ........................................................................................... 3-182 3.12-8. Differences in 100-year Flood Depths ....................................................................................... 3-183 3.12-9. Reedy Creek Watershed Aggregate Damage Estimation Results .............................................. 3-186 3.13-1. Clarke Creek Watershed Aggregate Damage Estimation Results .............................................. 3-191 3.13-2. Clarke Creek Basin Stream Network ......................................................................................... 3-193 3.13-3. Existing Conditions Flood Depth Grid ....................................................................................... 3-194 3.13-4. Distribution of Existing Condition Flood Depths....................................................................... 3-195 3.13-5. Future Conditions Flood Depth Grid.......................................................................................... 3-196 3.13-6. Distribution of Future Condition Flood Depths ......................................................................... 3-196 3.13-7. Increases in 100-year Flood Depths ........................................................................................... 3-197 3.13-8. Differences in 100-year Flood Depths ....................................................................................... 3-198 3.13-9. Clarke Creek Watershed Aggregate Damage Estimation Results .............................................. 3-201 3.14-1. Mallard Creek Watershed Aggregate Damage Estimation Results ............................................ 3-206 3.14-2. Mallard Creek Basin Stream Network ....................................................................................... 3-208 3.14-3. Existing Conditions Flood Depth Grid ....................................................................................... 3-209 3.14-4. Distribution of Existing Condition Flood Depths....................................................................... 3-210 xiv 3.14-5. Future Conditions Flood Depth Grid.......................................................................................... 3-211 3.14-6. Distribution of Future Condition Flood Depths ......................................................................... 3-211 3.14-7. Increases in 100-year Flood Depths ........................................................................................... 3-212 3.14-8. Differences in 100-year Flood Depths ....................................................................................... 3-213 3.14-9. Mallard Creek Watershed Aggregate Damage Estimation Results ............................................ 3-217 3.15-1. Irwin Creek Watershed Aggregate Damage Estimation Results ................................................ 3-223 3.15-2. Irwin Creek Stream System........................................................................................................ 3-225 3.15-3. Existing Conditions Flood Depth Grid ....................................................................................... 3-226 3.15-4. Distribution of Existing Condition Flood Depths....................................................................... 3-227 3.15-5. Future Conditions Flood Depth Grid.......................................................................................... 3-228 3.15-6. Distribution of Future Condition Flood Depths ......................................................................... 3-228 3.15-7. Increases in 100-year Flood Depths ........................................................................................... 3-229 3.15-8. Differences in 100-year Flood Depths ....................................................................................... 3-230 3.15-9. Irwin Creek Watershed Aggregate Damage Estimation Results ................................................ 3-234 3.16-1. Rocky River Basin Aggregate Damage Estimation Results ....................................................... 3-240 3.16-2. Rocky River Stream System ...................................................................................................... 3-242 3.16-3. Existing Conditions Flood Depth Grid ....................................................................................... 3-243 3.16-4. Distribution of Existing Condition Flood Depths....................................................................... 3-244 3.16-5. Future Conditions Flood Depth Grid.......................................................................................... 3-245 3.16-6. Distribution of Future Condition Flood Depths ......................................................................... 3-246 3.16-7. Increases in 100-year Flood Depths ........................................................................................... 3-247 3.16-8. Differences in 100-year Flood Depths ....................................................................................... 3-248 3.16-9. Rocky River Basin Aggregate Damage Estimation Results ....................................................... 3-252 3.17-1. Goose Creek Watershed Aggregate Damage Estimation Results .............................................. 3-257 3.17-2. Goose Creek Basin Stream Network .......................................................................................... 3-259 3.17-3. Existing Conditions Flood Depth Grid ....................................................................................... 3-260 3.17-4. Distribution of Existing Condition Flood Depths....................................................................... 3-261 3.17-5. Future Conditions Flood Depth Grid.......................................................................................... 3-262 3.17-6. Distribution of Future Condition Flood Depths ......................................................................... 3-263 3.17-7. Increases in 100-year Flood Depths ........................................................................................... 3-264 3.17-8. Differences in 100-year Flood Depths ....................................................................................... 3-264 3.17-9. Goose Creek Watershed Aggregate Damage Estimation Results .............................................. 3-268 3.18-1. Clarke Creek Tributary Aggregate Damage Estimation Results ................................................ 3-273 3.18-2. Clarke Creek Tributary and Adjacent Basins ............................................................................. 3-275 3.18-3. Existing Conditions Flood Depth Grid ....................................................................................... 3-276 3.18-4. Distribution of Existing Condition Flood Depths....................................................................... 3-277 3.18-5. Future Conditions Flood Depth Grid.......................................................................................... 3-278 xv 3.18-6. Distribution of Future Condition Flood Depths ......................................................................... 3-278 3.18-7. Increases in 100-year Flood Depths ........................................................................................... 3-279 3.18-8. Differences in 100-year Flood Depths ....................................................................................... 3-280 3.18-9. Clarke Creek Tributary Aggregate Damage Estimation Results ................................................ 3-283 4-1. ArcView Image of Parcel Data and Survey Points.............................................................................. 4-4 xvi 1. Executive Summary 1.1 Project Background The National Institute of Building Sciences (NIBS) and the Federal Emergency Management Agency (FEMA) have contracted with ABSG Consulting (ABS), formerly EQE International, and Michael Baker Jr. Corporation (MBJ) to develop a nationally applicable flood loss estimation methodology that will be incorporated into the HazardsUS (HAZUS) software. The software development process requires a significant amount of time, and software release is scheduled for summer 2003. An oversight committee that includes a representative from Mecklenburg County guides the flood model development. It was through this effort that officials from Mecklenburg County envisioned the following study. Mecklenburg County was seeking a new approach to determine the impacts of changes to floodplain mapping, to drive mitigation planning initiatives and improve public In January 2000, the HAZUS®MH Flood Project Team information dissemination. presented a status report to the flood model oversight committee regarding the methodology for inventory development and flood loss estimation. At that time, it became evident that portions of the HAZUS®MH methodology could be utilized to address the County’s concerns regarding mapping revisions and public information dissemination. It was felt that providing estimates of potential flood losses would help policy makers and the general public better understand the effects of map revisions, thereby increasing support for future mitigation planning decisions. Mecklenburg requested that the HAZUS®MH flood model contractors submit a proposal to study a single watershed to evaluate the potential benefits of using loss estimates to evaluate the impacts of map revisions. 1-1 In April 2000, ABS and MBJ undertook a project to estimate flood losses1 for a pilot watershed in Mecklenburg County – the McAlpine Creek watershed2. The purpose of the effort was to utilize the preliminary NIBS/FEMA HAZUS®MH Flood Loss Estimation Methodology to estimate potential flood damage based on Mecklenburg’s original and revised floodplain maps. Upon completion of the project, Mecklenburg County, ABS, and MBJ entered into discussions about performing similar analyses on the remaining watersheds within the county. ABS and MBJ developed a multi-task approach that resulted in this binder of analysis results for 17 watersheds. The original project was scoped with all 24 watersheds, but as the project progressed, it became apparent that some watersheds could be combined into a single report and some watersheds were deemed minor issues that could be addressed at a later time. Therefore, this binder, while providing 22 sections, contains reports for only 17 watersheds. Figure 1-1 below shows the analyzed watersheds included in this report. 1 Flood depth data for the pilot watershed were generated by MBJ, while inventory development and damage estimation were performed by ABS Consulting (formerly EQE International). 2 EQE International, “Determination of Impacts From Flood Study Modifications: McAlpine Creek Watershed (Final),” Prepared for Mecklenburg County Engineering and Building Standards, June 2000. 1-2 Figure 1-1. Watersheds Analyzed For Mecklenburg County 1.2 Report Organization The organization of the report binder is as follows: 1. Executive Summary – this section provides an overview of the project and a synopsis of results with a comparison of all the watersheds and a brief discussion on mitigation or floodplain regulation opportunities for the County. 2. Data Analysis – this section provides a detailed discussion related to the development of the data, the application of the HAZUS®MH methodology including the application of the default building parameters, modified to support local trends, the selection of building damage functions, and finally the analysis methods. 1-3 3. Flood Hazard Assessments – this section is further subdivided into sections containing the individual watershed results reported to the County during the course of the project. Each watershed has been assigned a section and the results are presented as independent reports allowing the County to remove the sections and utilize, reprint, or update without having to revise the entire report. 4. Suggestions for Geographic Information Systems (GIS) Data enhancement and future data collection – this section is provided to the County to assist their own internal planning and data development. The recommendations presented in this section are intended to advance the County’s ability to continue to lead the floodplain management community through the coordinated application of data developed by the various departments within the County. 1.3 Analysis Synopsis To determine the potential impacts of floodplain map modifications, three damage estimates have been developed for each watershed, as follows: 1. Estimated losses based on the current building inventory within the watershed (developed from surveyed data and parcel data) and the original 100-year floodplain boundary, based on the 1975 flood study (Run 1 – current inventory, original floodplain). 2. Estimated losses based on the current building inventory, expanded to include structures within the new floodplain that were previously outside the floodplain, and the newly revised floodplain boundary (Run 2 – current inventory, new floodplain). 3. Estimated losses to a projected future inventory that incorporates projected growth (“build out”), relative to the newly revised floodplain boundary (Run 3 – future inventory, new floodplain). The following tables provide a combined view of the results from the 17 reports prepared for the County and represents 19 of the County’s 24 watersheds. The remaining 5 watersheds are smaller watersheds that are not considered significant problem areas at this time. 1-4 Figure 1-2 shows the total estimated losses (structure and contents) for Mecklenburg County based on the watersheds analyzed to date. The figure shows how the new flood study methodology, including improved H&H models and digital terrain modes, and increased impervious soils from future development, indicates that a 100-year flood will result in greater estimated damages than those estimated using the older 1975 flood study. This is indicated by the increase in estimated damage from Run 1 to Run 2. Finally, Run 3 shows the increased estimated damage resulting from development within the floodplain that could occur without the increased floodplain regulations currently approved by the County. $700,000,000 $600,000,000 Estimated Loss ($) $500,000,000 $400,000,000 $300,000,000 $200,000,000 $100,000,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 1-2. Total Estimated Losses for Mecklenburg County by Analysis Run Assuming effective floodplain management, Figure 1-2 shows that the County has the potential to prevent over $300 million in structure and content losses throughout the county. The County has been very progressive in its mitigation planning and floodplain management and therefore has a very good opportunity to maximize the net reduction in losses. 1-5 To break these losses, Figure 1-3 shows the distribution of the structure and content losses for the county as a whole. It is interesting to note that the estimated content losses are greater than the estimated building damage. This is discussed in more detail later in this report, but in general that is an indication that losses to non-residential properties are contributing a significant amount to the total losses and typically the contents of non-residential properties is higher than the value of the building itself. $400,000,000 Structure Content $350,000,000 Estimated Loss (Dollars) $300,000,000 $250,000,000 $200,000,000 $150,000,000 $100,000,000 $50,000,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 1-3. Total Estimated Building and Content Losses for Mecklenburg County by Analysis Run Table 1-1 provides a quick look at the total estimated losses for all of the watersheds analyzed in this project. The total losses are a combination of structure (i.e., frame, drywall, insulation, etc.) and contents (i.e., furnishings, equipment, carpet, etc.) losses and represent the total impact of the flooding on the building. It is important to note that the occupancy type of the buildings can have a significant impact on the ratio of structure value to contents value. For example, in residential homes the contents values are typically estimated to be 50% of the value of the structure, whereas in commercial 1-6 buildings, the contents may be estimated to be as much as 150% of the value of the structure. Table 1-1 shows the total losses for all three runs as discussed above. The Table also demonstrates the increased damage between Run 2 and Run 3 where the 100-year flood elevations from the 2000 flood study were used with the current inventory (Run 2) and future or ultimate build-out (Run 3). The differences reflect new structures that may fall within areas of flooding. For that reason, the difference between the two runs (tabulated as “Future development Damage”) can be seen as potential damage that can be avoided with proper floodplain management. The differences are shown as both the net difference and the percent increase between Run 2 and Run 3. Finally a column is provided showing the increase in damage between Run 2 and Run 3 for each watershed as a function of the total increase in damage for all the watersheds in the County. The purpose of this column is to allow the County to rank each watershed as potential candidates for focused mitigation strategies. As seen in Table 1-1 three watersheds comprise 66% of the total potential increased damage throughout the County, and the top five watersheds account for 86% of the total potential increased damage. For clarity, these watersheds are shown in bold. 1-7 Table 1-1. Total Estimated Flood Losses for Mecklenburg County Watershed (Report Section) McAlpine1 (3.1) Sugar Creek (3.2) Long Creek (3.3) Little Sugar & Briar Creek (3-4) Four Mile Creek (3.5) McDowell Creek (3.6) McMullen Creek (3.7) McKee Creek (3.8) Back Creek (3.9) Six Mile Creek (3.10) Clems Branch (3.11) Reedy Creek (3.12) Clarke Creek (3.13) Mallard Creek (3.14) Irwin Creek (3.15) Rocky River (3.16) Goose Creek (3.17) Lower Clarke Creek (3.18) Total Total Estimated Losses (Structure and Content Losses) Run 1 Run 2 Run 3 $8,832,391 $6,665,418 $473,400 $150,033,099 $689,203 $566,154 $3,373,730 $11,904 $80,646 $718,663 $0 $285,267 $290,869 $3,893,488 $37,062,512 $3,485 $62,947 $0 $213,043,176 $14,078,086 $13,241,821 $860,879 $214,156,486 $1,318,264 $4,167,603 $5,729,832 $329,093 $105,480 $1,139,041 $0 $558,995 $358,509 $3,948,353 $57,320,865 $158,173 $199,602 $0 $317,671,082 $47,163,181 $67,593,742 $8,439,091 $326,867,763 $5,617,336 $16,894,746 $12,703,814 $2,872,244 $1,141,915 $4,899,923 $0 $3,153,789 $1,671,756 $38,442,556 $110,203,790 $2,270,997 $512,974 $202,407 $650,652,024 Future Development Damage (Run 2- Run 3) $33,085,095 $54,351,921 $7,578,212 $112,711,277 $4,299,072 $12,727,143 $6,973,982 $2,543,151 $1,036,435 $3,760,882 $0 $2,594,794 $1,313,247 $34,494,203 $52,882,925 $2,112,824 $313,372 $202,407 $332,980,942 Increase in Damage Between Run 2 & Run 3 (%) 235.0 410.5 880.3 52.6 326.1 305.4 121.7 772.8 982.6 330.2 0.0 464.2 366.3 873.6 92.3 1,335.8 157.0 --- Future Development Damage (% of Total) 9.9 16.3 2.3 33.8 1.3 3.8 2.1 0.8 0.3 1.1 0.0 0.8 0.4 10.4 15.9 0.6 0.1 0.1 1. The McAlpine watershed analysis was performed on a parcel basis as the building footprint coverage was not available when the analysis for this watershed was performed. 1-8 Table 1-2 provides insight into the mitigation or regulation possibilities for the County. Each watershed contains a number of developed and undeveloped or vacant parcels. For analysis purposes, the project team took the 100-year floodplain boundary from the 2000 flood studies and added a 100-foot buffer. This buffer was added to ensure that the project was conservative and that all parcels very close to and within the floodplain boundary were selected. While this is conservative in estimating the total number of parcels potentially impacted, it has no affect on the final estimated losses for the county. Table 1-2 lists the watersheds and the number of parcels within the floodplain boundary, and indicates how many of those parcels were vacant and subject to future development. The top five watersheds from Table 1-1 are also highlighted in this table with bold letters so the reader may quickly crosscheck the tables. Table 1-2. Total Parcels and Total Vacant Parcels By Watershed Watershed (Report Section) McAlpine1 (3.1) Sugar Creek (3.2) Long Creek (3.3) Little Sugar & Briar Creek (3.4) Four Mile Creek (3.5) McDowell Creek (3.6) McMullen Creek (3.7) McKee Creek (3.8) Back Creek (3.9) Six Mile Creek (3.10) Clems Branch (3.11) Reedy Creek (3.12) Clarke Creek (3.13) Mallard Creek (3.14) Irwin Creek (3.15) Rocky River (3.16) Goose Creek (3.17) Lower Clarke Creek (3.18) Total Parcels in Floodplain2 Vacant Parcels Percent Vacant 2,516 1,115 1,228 4,657 1,098 1,657 1,427 345 204 533 15 464 249 1,394 2,005 263 135 89 19,394 418 416 330 715 182 454 95 136 75 154 10 135 126 474 638 113 23 42 4,536 17 37 35 15 17 27 7 39 37 29 67 29 51 34 32 43 17 47 Rank by Vacant Parcels (%) 14 7 8 17 15 13 18 5 6 11 1 12 2 9 10 4 16 3 1. The McAlpine watershed analysis was performed on a parcel basis as the building footprint coverage was not available when the analysis for this watershed was performed. 2. Includes parcels that intersect the 100-foot buffer surrounding the floodplain. 1-9 When used together, Table 1-1 and Table 1-2 provide a clear picture for the County by identifying watersheds where the current inventory is the most vulnerable (those watersheds with large losses and large numbers of developed parcels) and identifying those areas where the potential for “at risk” development exists (those watersheds with large losses and a high percentage of vacant parcels). For example, Sugar Creek is a watershed with a substantial current exposure and still has a large potential for development with over a third of the parcels in the watershed being identified as vacant. Interestingly, in general the five watersheds with the largest damage differential between Run 2 and Run 3 (increased damage due to future development) rank in the lower 2/3rds among the watersheds in terms of vacant parcels as a percentage of built out parcels. Several possible inferences can be drawn from this apparent paradox. The first inference is that while the number of vacant parcels is limited, potential structures added to vacant parcels could be concentrated in the 100-year floodplain. In other words, it is possible that these vacant parcels are close to or within the 100-year floodplain and structures developed at or near the centroid of the parcel are subject to flooding. The second possibility is that the occupancies zoned for these parcels are either high value structures or high content value facilities thereby skewing the estimated damages when flooded. For example, the parcel may be zoned for large retail stores, which have a high content value to structure ratio. These possibilities will be discussed in further detail in Chapter 3 of this binder. Since the actual loss estimation for all studies, except the McAlpine Creek, used the building footprint data layer, it is also possible to provide a tabular view of the total number of buildings within the 100-year floodplain including the 100-foot buffer. Table 13 shows the number of structures within the 100-year floodplain (including the 100-foot buffer) in the current inventory and estimated to be within the floodplain at build-out. The table shows that overall, Mecklenburg County could see nearly 24% growth in the number of structures within the floodplain at build out. This percentage of growth, however, does not equate to growth in flooded structures. Table 1-3 shows that in some cases a modest increase in the number of buildings at build-out greatly increases the number of structures that will potentially flood. For example, build-out in the Back Creek watershed is estimated to increase the number of 1-10 structures by nearly 37% but this increase will translate into a 250% increase in the number of structures incurring flood damage. The reader is reminded that the methodology only assigns a single building to the centroid of every vacant parcel within the 100-year floodplain (plus the 100-foot buffer) and therefore this may not be a realistic estimation of the growth, but it is conservative. As previously mentioned, the HAZUS®MH specific occupancies (e.g. RES1) were mapped to the County Assessor occupancies for the parcels. The occupancy mapping can be seen in Table A-1 of Appendix A. Table 1-3 shows the total number of flooded structures for the County by general occupancy. Table 1-3 shows that the large majority of flooded structures are single or multi-family homes. This means that the implementation of standard mitigation strategies, such as a voluntary buy-out, has the potential to greatly reduce potential damages to existing homes. Non-residential structures create an interesting dilemma as most current mitigation programs are aimed at and most effective for residential structures. This analysis may help identify those areas where new approaches to non-residential mitigation efforts may need to be identified. Table 1-3. Total Number of Flooded Structures by General Occupancy for all Watersheds Analyzed in This Project to Date General Occupancy NonResidential Residential Total Description Commercial, Industrial, Religious, Education Single and Multi-Family Residential Run 1 334 Run 2 363 Run 3 699 1,438 1,965 3,158 1,772 2,328 3,857 1-11 Table 1-4. Total Buildings and “Ultimate Build out” Watershed (Report Section) McAlpine1 (3.1) Sugar Creek (3.2) Long Creek (3.3) Little Sugar & Briar Creek (3.4) Four Mile Creek (3.5) McDowell Creek (3.6) McMullen Creek (3.7) McKee Creek (3.8) Back Creek (3.9) Six Mile Creek (3.10) Clems Branch (3.11) Reedy Creek (3.12) Clarke Creek (3.13) Mallard Creek (3.14) Irwin Creek (3.15) Rocky River (3.16) Goose Creek (3.17) Lower Clarke Creek (3.18) Total Current Inventory Buildings in Floodplain N/A 1,240 1,248 5,314 902 988 1,694 223 308 412 9 397 291 1,578 1,917 259 176 48 17,004 Built-out Inventory Buildings in 2 floodplain N/A 1,617 1,578 5,961 1,084 1,442 1,789 359 383 566 19 532 413 2,052 2,555 372 198 90 21,010 Net Growth (%) N/A 30.4 26.4 12.2 21.3 46.0 5.6 61.0 24.4 37.4 111.1 34.0 41.9 30.0 33.3 43.6 12.5 87.5 23.6 No. of Flooded Buildings Run 1 N/A 91 27 972 7 25 115 2 4 23 0 13 1 27 222 1 6 0 1,536 Run 2 N/A 130 38 1,187 23 66 159 23 4 33 0 24 1 31 288 5 11 0 2,023 Percent Change in No. of Flooded Buildings (Run 1 to Run 2) N/A 42.9 40.7 22.1 228.6 164.0 38.3 1,050.0 0.0 43.5 0.0 84.6 0.0 14.8 29.7 400.0 83.3 0.0 31.7 Flooded Buildings Run 3 N/A 253 117 1,565 71 159 205 62 14 90 0 62 20 125 540 28 17 2 3,330 Percent Change in No. of Flooded Buildings (Run 2 to Run 3) N/A 94.6 207.9 31.9 208.7 140.9 28.9 169.6 250.0 172.7 0.0 158.3 1,900.0 303.2 87.5 460.0 54.5 200.0 64.6 1. The McAlpine watershed analysis was performed on a parcel basis as the building footprint coverage was not available when the analysis for this watershed was performed. 2. Includes buildings within parcels that intersect the 100-foot buffer surrounding the floodplain. Build-out assumes 1 building per vacant parcel. 1-12 2. Data Analysis The loss estimation analysis included the phases of data collection and processing, inventory development, flood hazard assessment, and damage evaluation. These processes are described in this section. 2.1 Data Collection and Processing As expected, this project utilized a large number of Geographic Information System (GIS) and database files containing building inventory information. As with every data intensive project, issues such as variations in the data and minor inconsistencies between tables require that a series of assumptions be put in place before the analysis proceeds. These issues and assumptions are discussed in detail below. Additionally, as the project progressed and the data sophistication increased, the scope of the data analysis also increased and the quality of the end results improved. As will be highlighted in Section 4 of this report, there is always an opportunity to improve the GIS data and subsequently the results of these hazard-based analyses. 2.1.1 Input Data Mecklenburg County provided a variety of flood hazard and building inventory data to ABS and MBJ. With the exception of the flood study data, these data were used throughout the entire project. These data served as the starting point for the loss estimation analysis, and included: 1. Digital terrain data: Mecklenburg County provided terrain data in an ESRI grid format with 20-foot postings developed by Watershed Concepts. Metadata indicated that the terrain data was developed in 1997. Examination by the county has validated the accuracy of the terrain data. 2. Adopted FEMA flood maps: Existing FEMA flood map surface elevations that are based on the 1975 flood study of the watersheds in Mecklenburg County. 2-1 3. Local flood map surface elevations (proposed): The Mecklenburg County watersheds were resurveyed and new floodplain maps were developed consisting of floodplain areas identified based on current, 2000, land use as well as future floodplain areas based on ultimate build-out areas in the watershed 4. County assessor data: The 2000 County Assessor data were provided to ABS at the start of this project. These data were used throughout the duration of all tasks. The assessor building data included such information as year of construction, effective floor area, occupancy type, and assessed valuation. The database consists of a total of 255,940 records for the entire county 5. Surveyed building information: Mecklenburg County has a comprehensive program for surveying structures within or near the floodplain boundary. Mecklenburg County provided four separate files containing survey data, where each file provides results from different survey methods and vintages. The surveyed building data includes structure information not contained in the assessor database, such as low floor elevation, or lowest adjacent grade elevation. The four files include: ï‚· Flood 3B: This file contains data developed for new construction through “old fashioned” transit surveys. This file was developed several years ago and was deemed the lowest quality by Mecklenburg County. ï‚· Flood 3C: This dataset is more current than the Flood 3B and therefore considered more accurate when duplicate sites were identified. This file contains data developed through “old fashioned” transit surveys. ï‚· GPSBFE: This is a newer dataset created between 1997 and 1998 and is therefore considered more accurate than either the Flood 3B and Flood 3C datasets when duplicates were identified. This file contains information developed through the use of GPS units. ï‚· Master Elevation Certificates: This dataset is the most recent survey data. Mecklenburg County identified this dataset as the most recent and accurate. Therefore, whenever duplicates with any of the other dataset exist, this dataset took precedence. 2-2 6. County Parcels: This GIS coverage contained polygon boundaries of all land parcels for the entire county. Only parcels that were within a 100-foot buffer surrounding the floodplain were used in the analyses for each watershed. 7. Building Footprints: This layer was used to refine the location of structures within the floodplain. The dataset is countywide and comprehensive. Note: This GIS coverage was not available when ABS performed the McAlpine Creek Watershed analysis and therefore the results in that watershed have slightly higher uncertainty. 8. Digital orthophotography: Mecklenburg provided digital orthoimagery that greatly assisted in the development of the inventory data and understanding potential issues within the GIS parcel coverage and associated attribute data. 2.1.2 Data Processing Summary While MBJ performed the data processing on the flood hazard data (see the discussion in each watersheds section), ABS performed processing on the countywide data for the building inventory. Generally, the inventory development process required attributing the building footprint polygons with the data necessary to perform the loss estimation analysis. This approach differs from the McAlpine effort in that the McAlpine study was performed at the parcel level, unless the parcel had a building that had been surveyed. In other words, during the McAlpine study the flood depth was attributed to the centroid of the parcel, because the parcel footprint data was not available and there was no way of knowing where the building was located within the parcel. In the remainder of studies, the flood depth has been applied to the centroid of the building footprint, or footprints if there were multiple buildings on the parcel. It is our belief that this results in the most accurate representation of the potential damages. Figure 2-1 shows a GIS map displaying a sample of the inventory data provided to ABS. This figure shows the parcels that intersect with the Goose Creek Floodplain, the building footprints, master-elevation-certificate, and “gpsbfe” data. With the exception of the McAlpine Creek study, this figure is good representation of the data utilized throughout the project. As the figure shows, the building footprint data represents a significant improvement over utilizing the centroid of the parcel for assessing the potential impact from inundation. For example, Figure 2.1 shows that a number of 2-3 parcels contain more than one structure and therefore we can appropriately apply the flood depths to individual footprints. Unfortunately, these parcels also turn out to require additional data manipulation because the assessor data typically had the data as a sum of all structures within the parcel. In general the value of the parcel was distributed over the structures in the parcel based on the floor area as discussed below. Figure 2-1. Overview of Data Provided by Mecklenburg County (Image is from the Goose Creek Watershed) Generally, the building inventory data processing procedure was as follows: 1. The building footprint polygons were intersected with the parcel polygons to assign a parcel number to all structures in the footprint file. All building footprints smaller than 500 square feet were omitted from this process because they were typically hidden in the assessor data, and more often than not these were small structures behind residential buildings, or “out-buildings”. Overall, it is assumed 2-4 that the damages to these structures would be dwarfed by damages to the larger buildings. 2. The master-elevation-certificate and “gpsbfe” survey data (both “point” GIS layers) were then assigned to building footprints. Typically the master-elevation certificate and “gpsbfe’ points intersected the building footprint polygons simplifying this task, but the addition of a small buffer around the data points ensured that the point layer and the footprint polygon had an intersection. 3. The county assessor data was then joined with the building footprint data, thereby providing information on floor area, year built, existence of a basement, valuation, number of floors, and occupancy. This join was accomplished using the parcel number assigned through the process in Step 1. 4. This joined dataset was reviewed to determine whether the parcel data reflected the building footprint or the entire parcel. In those cases where the parcel data appeared to reflect a sum of all structures on the parcel, the data was parsed to the various footprints based on the relative area (ratio) of the footprint polygons. This is discussed in greater detail in Section 2.3 below. 5. The HAZUS®MH occupancy classifications were assigned to the footprints based on the assessor occupancy classification. The assignments of the County Assessor occupancy classifications to the HAZUS®MH occupancy classes is provided in Table A-1 of Appendix A. 6. The HAZUS®MH building area (typical values) and valuation methodology were utilized to complete missing inventory data and to estimate future development on vacant parcels. In other words, using the parcel’s occupancy it was possible to assign a typical building area and valuation (see Table A-1 in Appendix A). 7. With the assignment of the HAZUS®MH occupancy classification and the typical building areas, it is possible to assign content value ratios, and building and content damage functions (see Table A-3 in Appendix A). 8. The HAZUS®MH foundation type and heights were assigned randomly to the footprints (see Table A-4 in Appendix A) unless a basement was specified in the Assessor’s dataset, in which case the first floor height was assigned the height 2-5 for the HAZUS®MH basement default. The foundation type and height distributions were based on the HAZUS®MH default distributions for North Carolina. These distributions were further modified to reflect distributions seen in the County Assessor and Survey data when performing the McAlpine Creek study. 9. Losses were estimated for each of the three runs. o Run 1: Original flood study and current inventory o Run 2: New flood study and current inventory o Run 3: New flood study and ‘built-out” inventory With the exception of the additional data and locational accuracy provided by the building footprint polygons, the process is the same as that used in the McAlpine analysis. In other words, the only difference between the McAlpine Creek analysis and the analysis performed for all other watersheds was the attribution of the flood depth at the centroid of the parcel rather than the centroid of the building footprint. 2.2 Building Damage Analysis To develop an estimate of the flood hazard losses, it is necessary to determine the flood depth of each structure within the inundated area. MBJ provided ABS with a flood depth grid representing the current (1975 flood study) and ultimate (new 2000 flood study) 100year flood scenarios. The flood grid included both positive (flooded) and negative (flood waters below grade) flood depths. The structures and vacant parcels were intersected with the depth grids to determine the depth of flooding at grade for each structure (building footprint) or proposed structure (centroid of the parcel). For those buildings where a survey point was available, the latitude and longitude of the survey point was used rather than the centroid of the building footprint. Upon assignment of the depth of flooding at grade for each building or vacant parcel, the project team adjusted the flood depth in order to account for the height of the first floor assigned to the building. For those building footprints with a survey point, the actual first 2-6 floor height from the survey was used. Those building footprints without floor height from survey data, had the HAZUS®MH floor height randomly assigned per Step 8 in the data process. This provided the project team with the flood depth within the structure. With this value and the known occupancy, the project team was able to apply the assigned depth-damage relationship for the structure and the building contents (these depth damage relationships are discussed in more detail in Section 2.4). From these depth-damage relationships, the estimated damage, in percent of value, was determined and subsequently the estimated loss, in dollars, was also determined. 2.3 Building Valuation Building valuations were provided as part of the County Tax Assessor files and were applied to structures on the parcels. For the McAlpine study, this was relatively straight forward as the analysis occurred at the parcel level and the valuation included all structures on that parcel. When the building footprint layer was added into the process, it became apparent that some data issues and limitations would need to be overcome. Examples of these issues include: ï‚· A parcel with multiple building footprints, but only one recorded floor area and value for the parcel. In this case, the project team assigned the valuation from the assessor file according to a ratio of the footprint area for an individual building to the total area of the footprints. ï‚· Parcels with multiple records for improvements (buildings) corresponding to multiple footprints shown in the footprint file, but the valuation and floor area in the Assessor file is constant for all of the improvements and appears to be the aggregated total for the improvements. As with the previous case, the project team took the total valuation and distributed it based on the relative areas of the footprints. ï‚· Parcels with multiple improvements recorded and only a single footprint in the footprint file. In this case, the project team assumed the footprint file to be the most accurate and assigned the total value of the parcel to the footprint. 2-7 ï‚· Parcels identified as vacant, but with footprints in the footprint file. The project team assigned a valuation based on the occupancy using the HAZUS®MH defaults. These values can be seen in Appendix A-2. ï‚· Contents values were determined as a percentage of the assigned structure value. The HAZUS®MH content value ratios for each occupancy were applied throughout the project. Some records in the County Assessor file contained an estimate of the building contents value. As this data was not consistent throughout the database, these values were not used. The HAZUS®MH default contents value expressed as a percentage of structure values can be seen in Table A-4 of Appendix A. 2.4 Damage Curve Selection Once the depth of water relative to the lowest floor was determined, occupancy-specific depth-damage functions were applied to determine the damage percentage for each structure. For single-family residential buildings, credibility-weighted depth-damage curves from the Federal Insurance Administration (FIA) were applied. For non- residential buildings, depth-damage curves from the U.S. Army Corps of Engineers (USACE) Wilmington and Galveston Districts were applied. 2.4.1 FIA Depth-Damage Curves The FIA has developed national depth-damage curves that are used in the actuarial rate setting process. The original FIA depth-damage functions, developed in 1970 and 1973, are referred to as “theoretical base tables”. Some of the information used to develop the initial curves came from post-flood surveys conducted by the Corps of Engineers. With time, a wealth of damage and loss data has been collected as part of the flood insurance claims process. Losses include both structure and contents losses, and are determined relative to actual cash value (depreciated replacement cost). The majority of claims are for residential structures. The FIA damage functions are updated annually based on this damage data, as part of the flood insurance rate review process. A statistical “credibility” analysis is used to 2-8 combine the “theoretical base tables” with the “rate review” results. When sufficient claims exist to provide statistical confidence in the results, the depth-damage relationship is based exclusively on the claims data. When claims data are insufficient, the claims data and base tables are combined using a weighting process. The result is two sets of curves: pure summaries of claims data, and credibility analyses combining available claims data into weighted curves. According to the NFIP Actuarial Information System “Credibility and Weighting” report (1998), credibility analyses and the resulting weighted curves are available for six structure categories: 1. One floor, no basement 2. Two or more floors, no basement 3. Two or more floors, with basement 4. Split-level, no basement 5. Split-level, with basement 6. Mobile home Figure 2-2 presents the six FIA credibility-weighted damage functions. It should be noted that several of the curves are not continuous. Because claims data are often sparse, damage values are not provided for all depths. For use in the HAZUS®MH software, missing damage values (e.g., damage at 6.0 feet for structures with 2 floors, no basement) was interpolated between known water depths to facilitate damage function application. 2-9 Figure 2-2. FIA Credibility-Weighted Building Depth-Damage Curves as of 12/31/1998 2.4.2 USACE Wilmington District Depth-Damage Curves The Wilmington District provided 13 residential structure and contents damage functions, and 49 non-residential structure functions that may be applied to contents using a contents-to-structure value ratio. The non-residential classes include: apartments, appliances, auto dealership, auto junk yard, auto parts, bait stand, bank, barber shop, beauty shop, boat stalls, book store, bowling alley, business, church, cleaners, clinic (medical), clothing, dentist office, department store, doctor’s office, drug/super, funeral home, furniture, garage, halls, hardware, hotel, jewelry, laundry, liquor, lumber, market/super, market/drive, motel, newspaper, office building, post office, private club, restaurant, rest home, school, service station, theater, theater (drive-in), TV station, tavern, variety store, wash-a-teria, and warehouse. 2-10 2.4.3 USACE Galveston District Curves The Galveston District has numerous damage functions, including residential, and more than 145 different non-residential flood damage functions. The non-residential damage functions include damage to the structure, as well as to inventory and equipment. The damage functions are based on flood damage records, as well as post-event surveys, including surveys following Hurricane Claudette in 1979. The damage curves are currently used by Galveston and other Districts, including Tulsa and Fort Worth, and are applicable to fresh-water flooding, under slow-rise, slow-recession conditions, with little velocity. The functions are based on damage to structures without basements, as structures along the Texas Coastal Plain are built without basements because of the high water table. 2.5 Occupancy Mapping & Damage Assessment Each depth-damage curve is associated with a specific building occupancy type. ABS has developed a damage curve library that includes the FIA, Wilmington, and Galveston depth-damage curves, for use in the HAZUS®MH loss estimation software. These curves are identified by the HAZUS®MH occupancy code. In order to apply the curves to the Mecklenburg data, it was necessary to associate each Mecklenburg occupancy code with a HAZUS®MH occupancy code, and select an appropriate depth damage curve for that occupancy. The results of this effort are shown in Table A-1 in Appendix A. There are a few notable items regarding the assignment of depth-damage curves and computation of flood damage: ï‚· FIA curves were applied for all single-family residential buildings. The style code from the Mecklenburg County database was used to determine the number of stories. The presence of a basement was assigned based on the building foundation distributions shown in Table A-3 in Appendix A. ï‚· For non-residential buildings, an effort was made to associate the building with a depth-damage curve from the USACE Wilmington District. If an appropriate match could not be made, a curve from the USACE Galveston District was applied. 2-11 ï‚· The USACE damage curves are based on specific building types, so matching a particular curve to the Mecklenburg County use codes of “Commercial” and “Industrial” was not possible. For buildings described as “Commercial”, damage curves for the categories of Retail Trade and Business/Professional/Technical Services were combined to develop a single depth-damage curve. It is assumed that these categories are representative of commercial buildings in Mecklenburg County. Likewise for “Industrial” buildings, curves for the categories of Light Industrial and Construction were combined. ï‚· For the calculation of contents damage, the contents curves collected from the FIA, Galveston District or Wilmington District curves were applied and the value of the contents within the structure was determined using the values seen in Table A-4 of Appendix A. 2-12 3. Flood Hazard Assessments The following tabs identify the individual damage assessment results for each watershed within Mecklenburg County. This report is designed to allow the County to update watersheds over time as the flood studies and inventory data are updated and enhanced. Since the methodology is consistent with HAZUS®MH and the HAZUS®MH Flood Information Tool (FIT), the County can perform these updates internally. Table 3-1 presents the overall structure losses estimated for each watershed. As can be seen in the table, nearly all the watersheds showed increasing estimated losses from Run 1 through to Run 3. It is important to note that since the inventory was held constant, the difference between Run 1 and Run 2 are the changes between the 1975 flood study flood depths and the 2000 flood study depths, where the BFE includes the increased runoff from future or ultimate build-out. Conversely, since the flood depths were held constant, the difference between Run 2 and Run 3 are revisions to the building inventory estimating the future or ultimate development on the vacant parcels within the floodplains. As discussed later, a vacant parcel was assumed to have a single building developed on the parcel and the size of the structure was based on the known zoning of the parcel and the HAZUS®MH “average” structure for that type of occupancy. 3-1 Table 3-1. Estimated Structure Losses for Mecklenburg County Estimated Structure Losses Watershed (Report Section) 1 McAlpine (3.1) Sugar Creek (3.2) Long Creek (3.3) Little Sugar & Briar Creek (3.4) Four Mile Creek (3.5) McDowell Creek (3.6) McMullen Creek (3.7) McKee Creek (3.8) Back Creek (3.9) Six Mile Creek (3.10) Clems Branch (3.11) Reedy Creek (3.12) Clarke Creek (3.13) Mallard Creek (3.14) Irwin Creek (3.15) Rocky River (3.16) Goose Creek (3.17) Lower Clarke Creek (3.18) Total Run 1 Run 2 Run 3 $5,635,741 $3,167,644 $316,227 $56,546,435 $442,926 $385,125 $2,141,966 $8,200 $51,615 $473,083 $0 $185,520 $173,044 $1,665,160 $11,169,985 $2,446 $45,644 $0 $82,410,761 $8,477,724 $6,117,840 $558,456 $82,124,414 $847,470 $2,607,031 $3,644,863 $217,095 $63,339 $728,967 $0 $351,145 $216,453 $1,693,843 $18,064,510 $112,446 $135,712 $0 $125,961,308 $25,216,387 $32,827,578 $5,228,264 $137,170,007 $3,225,844 $8,813,209 $7,491,171 $1,822,089 $563,791 $3,008,766 $0 $2,048,533 $1,120,419 $17,228,457 $46,986,475 $1,265,911 $348,193 $125,000 $294,490,094 Future Development Damage (Run 2- Run 3) $16,738,663 $26,709,738 $4,669,808 $55,045,593 $2,378,374 $6,206,178 $3,846,308 $1,604,994 $500,452 $2,279,799 $0 $1,697,388 $903,966 $15,534,614 $28,921,965 $1,153,465 $212,481 $125,000 $168,528,786 Increase in Damage Between Run 2 and Run 3 (%) 197.4 436.6 836.2 67.0 280.6 238.1 105.5 755.9 790.1 312.7 --483.4 417.6 917.1 160.1 1,025.8 156.2 --- 1. The McAlpine watershed analysis was performed on a parcel basis as the building footprint coverage was not available when the project started. 3-2 Future Development Damage (% of Total) 9.9 15.8 2.8 32.7 1.4 3.7 2.3 1.0 0.3 1.4 0.0 1.0 0.5 9.2 17.2 0.7 0.1 0.1 Table 3-1 is designed to allow the reader to view the losses from two perspectives. The first is on a watershed basis. The reader can see the estimated increase in damage between Run 2 and Run 3, representing the potential for increasing damage as the watershed develops but conditions (floodplain regulation) remains constant. The reader can also view the watershed as part of the overall increased potential for losses throughout the County. As Table 3-1 shows, there are three major groupings of the watersheds that have been analyzed. There are three watersheds (Sugar Creek, Little Sugar & Briar Creeks, and Irwin Creek) where increased floodplain regulation could greatly reduce the potential loss relative to the total losses for all of the county’s watersheds. The three watersheds represent nearly 66% of the total loss differential between Run 2 and Run 3. The next two watersheds (McAlpine Creek and Mallard Creek) represent another 19% of the total loss differential between Run 2 and Run 3. This means that nearly 85% of the total potential increased losses due to future development is within 5 watersheds with the remaining 15 percent of the losses scattered among the remaining 13 watersheds that were analyzed. Table 3-1 shows the overall impact of flooding on buildings or the overall structural damage that can be expected when a structure is inundated. Typically in flooding where there is little or no warning, the contents within the structure are also subjected to damage. As previously discussed, it is possible to estimate the total value of the contents within each structure based on the occupancy and value of the structure. Table A-4 in Appendix A shows the estimated value of contents relative to the value of the building as a percentage. Applying depth-damage relationships for contents it is possible to develop a similar table for the damage to building contents. Table 3-2 shows the results of this effort for each watershed. As expected, the same five watersheds represents over 87% of the total contents damage for every watershed in the County. As with the structure losses, this indicates opportunities to reduce or eliminate some of these damages through effective floodplain management. A review of the reports for the top five watersheds (McAlpine, Mallard, Irwin, Sugar and Little Sugar Briar) shows that while there is a significant residential contribution to the increased damage, a large part of the increase is due to commercial and industrial 3-3 development. This may complicate the County’s efforts to manage the development to prevent future damage as commercial and industrial structures are harder to mitigate against flooding during the time of development. For example, a property owner can build a home on piles above the BFE to prevent damage to the structure and also limit the impact of the development on structures downstream. With commercial structures, especially large retail or manufacturing facilities, it is significantly more difficult to build the structure in a fashion that has no adverse impact in the floodway or to structures downstream (due to the large asphalt requirements for parking). Reviewing the GIS data, it is evident that there are some vacant parcels that are completely subjected to flooding with the new flood study depth grid and significant effort will need to be put forward to guide development such that losses are minimized without adversely impacting other structures within the watershed. Conversely, there are clearly some parcels where there are areas on the parcel that can be developed without subjecting any structures to flooding. As the natural tendency is to develop available land, it is recommended that the County overlay the food depth grids onto the parcel boundary layer and identify such areas. Obviously, Mecklenburg County is well positioned and has a clear policy regarding the prevention of flood losses and future development that is supported by the results of this study. One of the direct benefits of this analysis is that the County can map the losses by watershed and identify those with the greatest estimated damage. This would indicate areas where mitigation and floodplain regulatory measures may have the greatest impact. For Example, Figure 3-1 graphically shows the total estimated losses (structure and content) for each watershed based on analysis Run 2. 3-4 Figure 3-1. Total Estimated Losses by Watershed for Run 2 3-5 Table 3-2. Estimated Contents Losses for Mecklenburg County Estimated Content Losses Watershed (Report Section) 1 McAlpine (3.1) Sugar Creek (3.2) Long Creek (3.3) Little Sugar & Briar Creek (3.4) Four Mile Creek (3.5) McDowell Creek (3.6) McMullen Creek (3.7) McKee Creek (3.8) Back Creek (3.9) Six Mile Creek (3.10) Clems Branch (3.11) Reedy Creek (3.12) Clarke Creek (3.13) Mallard Creek (3.14) Irwin Creek (3.15) Rocky River (3.16) Goose Creek (3.17) Lower Clarke Creek (3.18) Total Run 1 Run 2 Run 3 $3,196,650 $3,497,774 $157,173 $93,486,664 $246,277 $181,029 $1,231,764 $3,704 $29,031 $245,580 0 $99,747 $117,825 $2,228,328 $25,892,527 $1,039 $17,303 $0 $130,632,415 $5,600,362 $7,123,981 $302,423 $132,032,072 $470,794 $1,560,572 $2,084,969 $111,998 $42,141 $410,074 0 $207,850 $142,056 $2,254,510 $39,256,355 $45,727 $63,890 $0 $191,709,774 $21,946,794 $34,766,164 $3,210,827 $189,697,756 $2,391,492 $8,081,537 $5,212,643 $1,050,155 $578,124 $1,891,157 0 $1,105,256 $551,337 $21,214,099 $63,217,315 $1,005,086 $164,781 $77,407 $356,161,930 Future Development Damage (Run 2- Run 3) $16,346,432 $27,642,183 $2,908,404 $57,665,684 $1,920,698 $6,520,965 $3,127,674 $938,157 $535,983 $1,481,083 0 $897,406 $409,281 $18,959,589 $23,960,960 $959,359 $100,891 $77,407 $164,452,156 Increase in Damage Between Run 2 and Run 3 (%) 291.9 388.0 961.7 43.7 408.0 417.9 150.0 837.7 1,271.9 361.2 0.0 431.8 288.1 841.0 61.0 2,098.0 157.9 --- 1. The McAlpine watershed analysis was performed on a parcel basis, as the building footprint coverage was not available when the project started. 3-6 Future Development Damage (% of Total) 9.9 16.8 1.8 35.1 1.2 4.0 1.9 0.6 0.3 0.9 0.0 0.5 0.2 11.5 14.6 0.6 0.1 0.0 DETERMINATION OF IMPACTS FROM FLOOD STUDY MODIFICATIONS McALPINE CREEK WATERSHED (Report Delivered June 2000) Prepared for: MECKLENBURG COUNTY ENGINEERING & BUILDING STANDARDS Charlotte, NC 28202 3.1 McAlpine Creek Analysis 3.1.1 Results Summary for the McAlpine Creek Basin Two building inventories and two floodplain scenarios maps were combined to develop damage estimates for the three scenarios listed above. Table 3.1-1 shows a summary of the number of flooded buildings by general occupancy classification. The simulation predicted 236, 330, and 527 damaged buildings from Runs 1, 2, and 3, respectively. Table 3.1-1. Number of Flooded Structures by General Occupancy: McAlpine Creek Watershed General Occupancy NonResidential Residential Total Description Commercial, Industrial, Religious, Education Single and Multi-Family Residential Run 1 7 Run 2 6 Run 3 35 229 328 492 236 330 527 The dollar damage resulting from the analysis is shown on Figure 3.1-1. The damage for each scenario shown in the figure is an aggregate across all building occupancy types. As shown, there is an increase in estimated damage between Run 1 (structure $5.6 million, contents $3.2 million) and Run 2 (structure $8.5 million, contents $5.6 million). This corresponds to an increase of $2.9 million (52%) for structures and $2.4 million (75%) for contents. The increase tracks the effect of changes in the floodplain extent and depth between the 1975 flood study and newly revised floodplain map. Based on the assumption that the revised floodplain map is more accurate than the 1975 flood study, the estimated damage results from Run 2 are representative of current conditions. A comparison of the aggregate damage from Run 2 and Run 3 signifies the difference in damage between current and future building development conditions. For the analysis in Run 3, damage estimates for parcels that are currently vacant were developed based on 3-7 their zoning. The result is a sharp increase in estimated structure damage from $8.5 million to $25.2 million and a corresponding increase in estimated contents damage from $5.6 million to approximately $22 million. This corresponds to an increase of $16.7 million (196%) for structures and $16.4 million (293%) for contents. Although the exact value of the estimated damage (Run 3) was not know to Mecklenburg County, this significant escalation of potential damages based on future development was predicted by county staff and has led to efforts requiring new development to be 1-foot above the one-hundred base flood elevation. Figure 3.1-1 supports this effort, as the 1-foot requirement would reduce the results of Run 3 to levels more closely resembling the results of the existing development results presented by Run 2. $30,000,000 $25,000,000 Structure Contents $20,000,000 $15,000,000 $10,000,000 $5,000,000 $0 Run 1 Run 2 Run 3 Building Inventory and Floodplain Scenario Figure 3.1-1. McAlpine Creek Watershed Aggregate Damage Estimation Results 3-8 Table 3.1-2 shows a summary of the building and content damage results by general occupancy classification. In general residential buildings represent the bulk of the damages for all three runs. However, increased development in non-residential buildings leads to a large difference in damages between Run 2 and Run 3. The contents damages by general occupancy generally reflect the building damages with the exception of Run 3 where the increase in industrial and retail development causes a large increase in nonresidential content damages. The results are discussed in greater detail later in this report. 3.1.2 Data Analysis Please note that the data analysis for McAlpine Creek is different from the remaining sections within this report since the building footprint data was not available when the McAlpine Creek analysis was performed. For that reason, a synopsis of the data analysis is included for the reader’s convenience. 3.1.2.1 Parcel and Building Data Review The data for the parcel polygons, the vacant parcel polygons, and the surveyed structures were matched and processed to produce a consistent database representative of the existing and future built environment. Data were extracted that assisted in developing critical information such as distributions of foundation type and floor area. If information was not available, the HAZUS methodology was applied, and in some areas modified to reflect local conditions based on other information available within the datasets. The first dataset reviewed contained descriptive information for all parcels within the McAlpine Creek floodplain. These data were provided in the form of a GIS data layer with an associated dBase file. Initial review of the 2,525 records indicated that duplicate records existed for 9 parcels. In these cases, examination showed that all data were duplicated with the exception of the perimeter and area of the polygon boundary. These parcels were examined in ArcView® and it became apparent that the duplicate records were actually slivers that may have been an easement or a correction to the parcel layer. As such, the duplicate records were eliminated using the dissolve functionality in GIS, reducing the number of parcel records to 2,516. 3-9 Mecklenburg also provided a dBase file containing the parcels designated as vacant within the floodplain. Review of the 440 records indicated that the vacant parcels were a subset in the file of parcels discussed above, and that 19 of the vacant parcels were in fact developed (the fields for effective area, year built, and building value were non-zero). These 19 records were removed from the vacant parcel database but left in the total parcel database. In addition, 3 of the vacant parcels were duplicates, and were therefore dissolved as described in the preceding paragraph. After these minor modifications were performed, the number of vacant parcels was reduced from 440 records to 418. Table 3.1-2. Summary of Building and Content Damage by General Occupancy: McAlpine Creek Watershed General Occupancy Description Run 1 Run 2 Run 3 Structural Damage Total Average NonResidential Commercial, Industrial, Religious, Education $374,663 Residential Single and Multi-Family Residential $5,261,080 $22,974 $53,523 Total $523,437 Average $52,344 $7,954,288 $24,857 Total $9,068,717 Average $259,106 $16,147,671 $32,820 Content Damage Total Average NonResidential Commercial, Industrial, Religious, Education $504,491 Residential Single and Multi-Family Residential $2,692,158 $12,699 $56,084 Total $701,084 Average $70,825 $4,899,188 $16,330 Total Average $11,881,830 $325,986 $10,064,964 $21,880 The 325 surveyed structures were intersected with the parcel polygons and 20 structures were determined to be unassociated with a parcel polygon. The 20 structures were overlaid upon the parcel polygons and digital orthoimagery to determine the cause. It was found that in some of these cases, the surveyed structure was located within a parcel polygon, but the building footprints were clipped from the parcel boundaries (i.e., a hole 3-10 existed within the parcel at the boundary of the building location). In other cases, the surveyed structure was located outside of the extent of the parcel polygons. For the 305 surveyed structures that did intersect a parcel polygon, a comparison of the surveyed floor area data with the assessor data indicates general agreement. However, the valuation data were at times significantly different. Another inconsistency included some cases in which the parcel layer did not contain any information regarding the structure. This occurrence could lead to an overestimation of the future growth condition because the parcel itself is described as vacant although there are structures on the parcel. 3.1.2.2 Parcels Without a Surveyed Structure The majority of attributes required for loss estimation were contained in the parcel polygon coverage. However, the parcel data did not contain any first floor elevation information. To estimate the height of the first floor above grade, the following methodology was used: The locations of the surveyed structures were reviewed in ArcView® GIS and three clusters were noted, designated as Zone 1, Zone 2, and Zone 3 (Figure 3.1-2). Within each zone, the distribution of foundation types was determined. For parcels outside of the zones, the surveyed data points were used to develop an average distribution of foundation types for the entire McAlpine Creek basin. The resulting distribution is shown in Table 3.1-1. The distribution was compared to the HAZUS®MH default inventory distribution (Table 6-9 in the Technical Document) and found to be reasonably consistent. For this project, no effort was made to ensure that pile foundations are near the creek or slab-on-grade further away as might normally be assumed. 3-11 Figure 3.1-2. Floor Height Distribution Zones 3-12 Table 3.1-3. Foundation Type Distribution by Zone: McAlpine Creek Watershed Foundation Type Slab on Grade Crawlspace Basement Pier Solid Wall Pile Assumed Floor Height (where survey data not available) 1 ft. above grade Zone 1 (%) 74 Zone 2 (%) 55 Zone 3 (%) 37 Avg. Distn Applied to Remaining Parcels (%) 52 3 ft. above grade 4 ft. above grade 5 ft. above grade 7 ft. above grade 7 ft. above grade 13 6 5 0 2 17 17 9 0 2 18 16 22 3 4 16 13 14 2 3 The vacant parcel data were used to estimate the future development of the McAlpine floodplain. However, the vacant parcels lacked a key data attribute: valuation. To overcome this deficiency, the following procedure was employed: 1. The parcel occupancy type was used to determine the future use of each vacant parcel. 2. The county assessor data were used to estimate the typical floor area for each occupancy type. The query was restricted to post-1980 construction in order to reflect the growth of structures observed in recent years. For example, the average floor area for a home in Mecklenburg County is 1,624 square feet. For the post-1980 structures, the average floor area is 2,290 square feet. It is believed that the recent development will be more representative of future construction practices. 3. In a similar fashion, the average valuation for each occupancy type per square foot was calculated using the average values of the assessor’s data of post-1980 structures. The results of this analysis are presented in Table A-1 in Appendix A. Using this table, an estimated valuation was computed for each vacant parcel, based on its occupancy type. 3.1.2.3 Surveyed Structures Intersecting a Parcel Where available, the surveyed structure data were used to identify the structures in the parcel. The surveyed data had accurate assessments of the floor elevation and lowest adjacent grade, which are used to estimate the floor height above grade (required to estimate water depth in the structure). The attributes taken from the surveyed structure coverage included floor area, occupancy type, number of stories, first floor elevation, and 3-13 lowest adjacent grade. The valuation was assigned based on the characteristics of the intersecting parcel polygon. 3.1.2.4 Surveyed Structures Not Intersecting a Parcel For surveyed structures unassociated with a parcel polygon, the required building inventory attributes were culled from the surveyed structure coverage. Because the buildings did not match to a parcel record, the valuation data was unavailable. Hence, Table A-1 was used to compute a valuation based on the floor area of each structure. 3.1.3 Detailed Results To determine the potential impacts of floodplain map modifications, three damage estimates have been developed, as follows: 1. Run 1 – current inventory, original floodplain. Estimated losses based on the current building inventory within the McAlpine Creek watershed (developed from surveyed data and parcel data) and the original 100-year floodplain boundary, based on the 1975 flood study. 2. Run 2 – current inventory, new floodplain. Estimated losses based on the current building inventory, expanded to include structures within the new floodplain that were previously outside the floodplain, and the newly revised floodplain boundary. 3. Run 3 – future inventory, new floodplain. Estimated losses to a projected future inventory that incorporates projected growth (“build out”), relative to the newly revised floodplain boundary. Table 3.1-4 presents the number of buildings damaged by flooding (i.e., non-zero dollar damage) by occupancy under each of the three scenarios. As noted in Section 2, a HAZUS®MH occupancy class was associated with each occupancy type in the Mecklenburg assessor database. As shown in the figure, the number of damaged buildings increases between runs for the majority of building types. The increase in the number of flooded buildings between Run 1 and Run 2 is due to differences in the floodplain boundary between the 1975 flood study and the new map revision. The increase between Run 2 and Run 3 is attributable to the projected rise in floodplain development. 3-14 The values shown in Table 3.1-4 are presented to give the reader perspective on the relative number of flooded buildings, which is useful when viewing the subsequent tables. For example, there are relatively few flooded buildings in the commercial category. It is therefore difficult to assert that the damage computed for these buildings is representative of other commercial buildings commercial buildings constructed within the watershed. On the other hand, there are quite a few flooded single-family residential buildings, suggesting that these results are more representative of the category as a whole. Table 3.1-4. Number of Flooded Buildings by HAZUS®MH Occupancy Type: McAlpine Creek Watershed HAZUS®MH Occupancy Code Description COM1/COM4 Mix of Retail Trade & Business/ Professional/Technical Services COM3 Personal & Repair Services COM4 Business/Professional/ Technical Services COM8 Entertainment & Recreation EDU1 Schools/Libraries IND2/IND6 Mix of Light Industrial & Construction REL1 Church/Membership Organizations RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling, Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement RES2 Mobile Home RES3 Multi-Family Dwelling Total No. of flooded buildings Total No. of unflooded buildings Run 1 0 Run 2 0 Run 3 8 1 1 1 3 1 9 3 1 0 3 1 0 4 1 10 1 49 2 72 2 200 46 76 76 27 32 32 78 107 137 0 29 0 33 1 46 236 1,923 330 1,829 527 2,050 The dollar damage resulting from the analysis is shown on Figure 3.1-2. The damage for each scenario shown in the figure is an aggregate across all building occupancy types. As shown, the estimated dollar damage increases from Run 1 to Run 2 and from Run 2 to Run 3. Tables 3.1-5 through 3.1-8 and the associated discussion go into greater detail about the results of the loss estimation. However, it should be noted that the significant escalation of estimated damage based on future development suggests the need for the 3-15 mitigation measures such as requiring future development to be 1-foot above the future one-hundred year flood elevation (as currently proposed by county staff). $30,000,000 $25,000,000 Structure Contents $20,000,000 $15,000,000 $10,000,000 $5,000,000 $0 Run 1 Run 2 Run 3 Building Inventory and Floodplain Scenario Figure 3.1-3. McAlpine Creek Watershed Aggregated Damage Estimation Results Table 3.1-5 presents the overall average damage percentage calculated for building structures by occupancy, through the application of the various depth-damage curves. Although there are changes in the building inventory and floodplain depth and extent between the three scenarios, the differences between the resulting structure damage percentages are relatively small. In general, the structure damage ranges from 10 to 25 percent. The exceptions to this case tend to occur for building types with a small number of flooded structures. Between Runs 1 and 2, there are a few building occupancy types, for which the computed damage decreased. 3-16 This is because the changes in the floodplain between the 1975 flood study and the recent map revision were not consistent in all places. Although there was an overall increase in floodplain extent & depth, there were some areas in which the floodplain actually decreased. Table 3.1-5. Structure Damage Percent by HAZUS®MH Occupancy Type: McAlpine Creek Watershed HAZUS®MH Occupancy Code Description COM1/COM4 Mix of Retail Trade & Business/ Professional/Technical Services COM3 Personal & Repair Services COM4 Business/Professional/ Technical Services COM8 Entertainment & Recreation IND2/IND6 Mix of Light Industrial & Construction EDU1 Schools/Libraries REL1 Church/Membership Organizations RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling, Split Level, No Basement RES1E Single Family Dwelling, Split Level, w/Basement RES2 Mobile Home RES3 Multi-Family Dwelling Run 1 --- Run 2 --- Run 3 37.5 12.0 19.7 15.1 13.2 15.1 39.4 11.0 --- 29.2 --- 29.2 25.6 3.6 45.2 19.6 3.3 32.3 20.5 3.3 32.3 24.8 10.8 12.3 12.3 11.5 13.2 13.2 19.1 20.1 25.0 --15.2 --18.8 64.0 21.8 Table 3.1-6 shows the dollar damage to building structures that is computed when the damage percentages are multiplied by the structure/parcel valuation. In contrast to the small relative difference between scenarios shown in the previous table, there are significant differences in the dollar damage between the three scenarios. Between Run 1 and Run 2, there is an increase in total structure damage from $5.6 million to $8.5 million. This corresponds to an increase of $2.9 million, or 52%. As the building inventory used for these scenarios are identical, the difference in damage is attributable to differences in the floodplain between the 1975 flood study and the recent revision of the 100-yr floodplain map. Proceeding from Run 2 to Run 3, there is a significant increase in estimated damage from $8.5 million to $25.2 million caused by projected development in the floodplain. This corresponds to an increase of $16.7 million, or 196%. A notable 3-17 finding from the results of Run 3 is a spike in both the total and average damage to commercial and industrial properties. Table 3.1-6. Structure Dollar Damage by HAZUS®MH Occupancy Type: McAlpine Creek Watershed HAZUS®MH Occupancy Code COM1/COM4 COM3 COM4 COM8 EDU1 IND2/IND6 REL1 RES1A RES1B RES1D RES1E RES2 RES3 Run 1 Total --$1,783 $15,877 $28,036 $152,124 --$176,843 $1,039,298 $735,383 $327,155 $2,092,447 --$1,066,797 Total $5,635,741 Run 2 Avg. --$1,783 $15,877 $9,345 $152,124 --$176,843 $21,210 $15,987 $12,117 $26,826 --$36,786 Total --$2,242 $28,143 $104,209 $138,602 --$250,241 $1,548,293 $1,325,143 $466,153 $2,952,764 --$1,661,935 $8,477,724 Run 3 Avg. --$2,242 $9,381 $34,736 $138,602 --$125,120 $21,504 $17,436 $14,567 $27,596 --$50,362 Total $1,254,703 $2,242 $3,841,280 $215,397 $138,602 $3,366,252 $250,241 $6,624,889 $1,325,143 $466,153 $4,770,281 $24,467 $2,936,738 Avg. $156,838 $2,242 $426,809 $53,849 $138,602 $336,625 $125,120 $33,124 $17,436 $14,567 $34,820 $24,467 $63,842 $25,216,387 Table 3.1-7 presents the overall average damage percentage calculated for building contents. Similar to the structure damage percent results shown in Table 3-2, the difference in contents damage percentages between runs is relatively small. In general, the contents damage ranges from 15 to 40 percent. Again, the outliers primarily occur for building types with a small number of flooded structures. Between Runs 1 and 2, there are a few building occupancy types, for which the computed damage decreased. This is because the changes in the floodplain between the 1975 flood study and the recent map revision were not consistent in all places. Although there was an overall increase in floodplain extent & depth, there were some areas in which the floodplain actually decreased. 3-18 Table 3.1-7. Contents Damage Percent by HAZUS®MH Occupancy Type: McAlpine Creek Watershed HAZUS®MH Occupancy Code Description COM1/COM4 Mix of Retail Trade & Business/ Professional/Technical Services COM3 Personal & Repair Services COM4 Business/Professional/ Technical Services COM8 Entertainment & Recreation IND2/IND6 Mix of Light Industrial & Construction EDU1 Schools/Libraries REL1 Church/Membership Organizations RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling, Split Level, No Basement RES1E Single Family Dwelling, Split Level, w/Basement RES2 Mobile Home RES3 Multi-Family Dwelling Run 1 --- Run 2 --- Run 3 37.5 49.6 17.4 83.6 8.9 83.6 38.0 11.0 --- 29.2 --- 34.4 35.3 3.6 45.2 24.3 3.3 36.3 25.0 3.3 36.3 29.7 12.9 15.3 15.3 13.8 15.7 15.7 19.3 20.4 23.0 --9.3 --33.6 51.1 41.2 Table 3.1-8 shows the estimated dollar damage to building contents. Similar to the structure dollar damage shown in Table 3-3, there are significant differences in the dollar damage between scenarios. Between Run 1 and Run 2, there is an increase in total estimated contents damage from $3.2 million to $5.6 million. This corresponds to an increase of $2.4 million, or 75%. The increase in damage is due to changes in the floodplain depth and extent between the 1975 flood study and the recent revision of the 100-yr floodplain map. Between Run 2 to Run 3, there is a significant increase in estimated damage from $5.6 million to nearly $22 million attributable to projected growth. This corresponds to an increase of $16.4 million, or 293%. Again, there is a notable spike in both the total and average damage to commercial and industrial properties between Runs 2 and 3. The significant escalation of estimated structure and contents damage based on future development, suggests the need for mitigation measures within the McAlpine Creek floodplain. 3-19 Table 3.1-8. Contents Dollar Damage by HAZUS®MH Occupancy Type: McAlpine Creek Watershed HAZUS®MH Occupancy Code COM1/COM4 COM3 COM4 COM8 EDU1 IND2/IND6 REL1 RES1A RES1B RES1D RES1E RES2 RES3 Run 1 Total Run 2 Avg. Total --$3,687 $6,990 $37,007 $196,848 --$259,959 $652,284 $439,920 $195,209 $1,068,416 --$336,329 ----$3,687 $6,213 $6,990 $10,200 $12,336 $137,556 $196,848 $179,351 ----$259,959 $367,854 $13,312 $946,337 $9,563 $837,537 $7,230 $280,172 $13,698 $1,502,898 ----$11,598 $1,332,244 Total $3,196,650 $5,600,362 3-20 Run 3 Avg. --$6,213 $3,400 $45,852 $179,351 --$183,927 $13,144 $11,020 $8,755 $14,046 --$40,371 Total $2,525,717 $6,213 $6,065,462 $410,988 $179,351 $2,326,245 $367,854 $3,964,776 $837,537 $280,172 $2,187,394 $9,764 $2,785,321 $21,946,794 Avg. $315,715 $6,213 $673,940 $102,747 $179,351 $232,625 $183,927 $19,824 $11,020 $8,755 $15,966 $9,764 $60,550 DETERMINATION OF FINANCIAL IMPACTS FROM FLOOD STUDIES SUGAR CREEK WATERSHED (Report Delivered November 2001) Prepared for: MECKLENBURG COUNTY ENGINEERING & BUILDING STANDARDS Charlotte, NC 28202 3.2 3.2.1 Sugar Creek Analysis Results Summary for the Sugar Creek Basin (below Irwin Creek) Two building inventories and two floodplain scenarios maps were combined to develop damage estimates for the three scenarios listed above. Table 3.2-1 shows a summary of the number of flooded buildings by general occupancy classification. The simulation predicted 91, 130, and 253 damaged buildings from Runs 1, 2, and 3, respectively. Table 3.2-1. Number of Flooded Structures by General Occupancy: Sugar Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) NonResidential Commercial, Industrial, Religious, Education 21 25 82 Residential Single and MultiFamily Residential 70 105 171 91 130 253 Total The dollar damage resulting from the analysis is shown on Figure 3.2-1. The damage for each scenario shown in the figure is an aggregate across all building occupancy types. As shown, there is an increase in estimated damage between Run 1 (structure $3.2 million, contents $3.5 million) and Run 2 (structure $6.1 million, contents $7.1 million). This corresponds to an increase of $2.95 million (93%) for structures and $3.6 million (103%) for contents. The increase demonstrates the effect of changes in the floodplain extent and depth between the 1975 flood study and newly revised (2000) floodplain map. Based on the assumption that the revised floodplain map is more accurate than the 1975 flood study, the estimated damage results from Run 2 are representative of current conditions. A comparison of the aggregate damage from Run 2 and Run 3 highlights the difference in damage between current and future building development conditions. For the analysis in Run 3, damage estimates for parcels that are currently vacant were assumed to be 3-21 developed based on their zoning. The result is a sharp increase in estimated structure damage from $6.1 million to $32.8 million and a corresponding increase in estimated contents damage from $7.1 million to approximately $34.8 million. This corresponds to an increase of $26.7 million (438%) for structures and $27.6 million (388%) for contents. Prior to this analysis, this significant escalation of potential damages based on future development was predicted by county staff and has led to efforts requiring new development to be 1-foot above the one-hundred year base flood elevation, where the BFE includes the increased runoff from future or ultimate build-out. These results support that effort as the 1-foot requirement would reduce the results of Run 3 to levels more closely resembling the results of the existing development results presented by Run 2 (see Figure 3.2-1). $40,000,000.00 $35,000,000.00 Estimated Damage (Dollars) $30,000,000.00 $25,000,000.00 Structure Contents $20,000,000.00 $15,000,000.00 $10,000,000.00 $5,000,000.00 $Run 1 Run 2 Run 3 Building Inventory and Floodplain Scenario Figure 3.2-1. Sugar Creek Watershed Aggregate Damage Estimation Results 3-22 Table 3.2-2 shows a summary of the building and content damage results by general occupancy classification. In general, Table 3.2-2 shows that the damages are fairly evenly split between residential and non-residential structures in Runs 1 and 2. However, increased development of non-residential buildings results in that occupancy group suffering the greatest proportion of damages in Run 3. The contents damage by occupancy generally increases with increasing building damage, again with the increase in non-residential development in Run 3 causing a large increase in content damage to that general occupancy classification. The results are discussed in greater detail later in this report. Table 3.2-2. Summary of Building and Content Damage by General Occupancy: Sugar Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) Structural Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $1,515,237 $72,154 $2,733,629 $109,345 $26,146,868 $318,864 Residential Single and Multi-Family Residential $1,652,407 $23,606 $3,384,211 $32,231 $6,680,709 $39,068 Average Total Average Content Damage Total NonResidential Commercial, Industrial, Religious, Education Residential Single and Multi-Family Residential Average Total $2,661,309 $126,729 $5,040,033 $836.466 $11,950 3-23 $2,083,948 $201,601 $30,685,583 $374,214 $19,847 $4,080,581 $23,863 3.2.2 Data Analysis 3.2.2.1 Sugar Creek Basin Characteristics and Study Data Sugar Creek is formed by the confluence of Irwin and Taggart Creeks. Depth grids were created for Sugar Creek, Taggart Creek, and three tributaries contributing flow to Sugar Creek. The grids depict the depth of flooding that will be exceeded with a 1-percent chance in any given year (100-year flood) under both existing and future development conditions. The network of streams analyzed is shown in Figure 3.2-2. The Irwin Creek basin was studied separately and, therefore, was not included in the Sugar Creek Basin. Figure 3.2-2. Sugar Creek Basin Stream Network 3-24 The studied reaches include approximately 12 miles of Sugar Creek and approximately 16 miles of tributary reaches, including Taggart Creek The following sections outline the specific analysis performed on Sugar Creek. 3.2.2.2 Sugar Creek Watershed Depth Grid Flood elevation grids were created interpolating between water surface elevations determined at numerous cross sections along the study reaches. In all, 419 cross sections were used: 166 on Sugar Creek and 253 on the tributaries, including 66 on Taggart Creek. The flood elevation grids were extended at the upstream end of each stream, at the confluence with each tributary, and at relatively large areas where floodwaters are not conveyed but, rather, pond at the elevation on the main stream. Where two stream flood elevation grids overlap the final flood elevation grid uses the greater of the two elevations. The flood elevations at the confluence of Irwin and Taggart Creeks were extended up into the Irwin Creek Basin. Depth grids were created by subtracting the ground elevation in the digital elevation model from the flood elevation at the corresponding cell in the elevation grid. Cells with flood depths less than zero (those outside of the floodplain, for example) were deleted from the flood elevation and flood depth grids. There are, apparently, gravel-mining operations in and near the floodplain along Sugar Creek. Flood depths in those areas were eliminated from the grids. The resulting existing conditions flood depth grid is shown in Figure 3.2-3. Approximately 1,758 acres are within the 100-year floodplain. Figure 3.2-4 shows the distribution of floodplain area inundated at 1-foot depth increments. Except in the mining areas, the maximum depth is approximately 23 feet. The average (mean) depth is 6.84 feet. Approximately 434 acres is inundated at a depth greater than 10 feet. 3-25 Figure 3.2-3. Existing Conditions Flood Depth Grid Sugar Creek Basin 180 160 140 120 100 80 60 40 20 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 Flood Depth (feet) Figure 3.2-4. Distribution of Existing Condition Flood Depths 3-26 The future conditions flood depth grid is shown in Figure 3.2-5. Approximately 1,992 acres are within the 100-year floodplain, an increase of 234 acres or a little more than 13 percent. The distribution of floodplain area inundated at various depths is shown in Figure 3.2-6. The maximum depth is 25.32 feet (more than 2 feet greater than existing conditions). The mean depth is 7.76 feet (about 0.9 foot greater than existing conditions). The area inundated by more than 10 feet is approximately 647 acres (213 acres more than the existing conditions). Figure 3.2-5. Future Conditions Flood Depth Grid 3-27 Sugar Creek Basin 180 Area Inundated (acres) 160 140 120 100 80 60 40 20 0 1 3 5 7 9 11 13 15 17 19 21 23 25 Flood Depth (feet) Figure 3.2-6. Distribution of Future Condition Flood Depths Subtracting the existing conditions flood depth grid from the future conditions flood depth grid yields a grid showing the increase in 100-year flood depths expected as a result of development within the basin. That grid is shown in Figure 3.2-7. The distribution of changes in 100-year flood depths is shown in Figure 3.2-8. Note that most (approximately 97.5 percent) of the differences are less than three feet. The 100year flood depth increases are expected to exceed 3 feet in approximately 50 acres within the Coffey Creek floodplain. Those increases occur in approximately 40 acres in the vicinity of the upstream of the York Street crossing and approximately 10 acres upstream of Piney Top Road. 3-28 Figure 3.2-7. Increases in 100-year Flood Depths Sugar Creek Basin 1400 Area Affected (acres) 1200 1000 800 600 400 200 0 1 2 3 4 5 Difference in Flood Depths (feet) Figure 3.2-8. Differences in 100-year Flood Depths 3-29 3.2.2.3 Sugar Creek Parcel and Building Data Review To determine the parcels and building footprints impacted by Sugar Creek, the floodplain boundaries from both the 1975 flood study and the 2000 flood study were combined and a buffer of 100-feet added. The buffer was added to ensure that not only those structures and parcels intersecting the parcels were selected, but those that are fairly close are also selected to provide Mecklenburg County with a more complete perspective on the development surrounding Sugar Creek. There are 1,115 parcels that intersect the floodplain boundary (including the 100-foot buffer) surrounding Sugar Creek. Some duplicate parcels were identified and reviewed. In all cases, these turned out to be slivers in the GIS data, most likely right-of-ways that have been either returned to the parcel, or offers of dedication that were never acted upon. In all cases, the slivers were merged back into the main parcel. Of the 1,115 parcels, 416 (37%) are identified as “vacant” of these parcels, 39 parcels had structures on them, typically large structures that covered more than one parcel, and an additional 6 parcels had information in the “effective area” field in the county assessor data indicating that a structure was on the parcel. The high percentage of vacant parcels (33% based on 377 parcels) provides Mecklenburg County opportunity to manage future development and reduce future damage. There are 1,234 building footprints greater than 500 square feet that intersect the floodplain boundary. Of these, 123 were surveyed as part of the master-elevation- certificate surveys and another 79 were surveyed as part of the “gpsbfe” survey data. Unfortunately of the 123 data points from the master-elevation-certificate surveys, 20 were missing data in either the first floor elevation or the lowest adjacent grade fields rendering the data unusable, all of the “gpsbfe” records contained the necessary data. An additional 34 parcels matched with survey data from the Flood 3C or Flood 3B survey data. Therefore, a total of 216 of the 1,234 could be assigned a first floor elevation and lowest adjacent grade from the survey data available. For the current inventory analysis, the 6 parcels without a building footprint that were identified as non-vacant based on the square footage in the assessors data will be carried as single structures at the centroid of the parcel for a total of 1,240 “buildings” in the floodplain (including the 100-foot buffer). 3-30 For the future conditions or “build-out”, a single structure was placed at the centroid of the 377 vacant parcels identified earlier. ®MH HAZUS This structure was established to have the default floor area and value based on the occupancy class assigned to the approved zoning of the parcel (see Tables A-1 and A-2 in Appendix A). Therefore the total “buildings” within the floodplain for the built-out inventory is assumed to be 1,617. 3.2.3 Detailed Results for the Sugar Creek Basin To determine the potential impacts of floodplain map modifications, three damage estimates have been developed, as follows: 1. Run 1 – current inventory, original floodplain. Estimated losses based on the current building inventory within the Sugar Creek watershed (developed from surveyed data and parcel data) and the original 100-year floodplain boundary, based on the 1975 flood study. 2. Run 2 – current inventory, new floodplain. Estimated losses based on the current building inventory, expanded to include structures within the new floodplain that were previously outside the floodplain, and the newly revised floodplain boundary. 3. Run 3 – future inventory, new floodplain. Estimated losses to a projected future inventory that incorporates projected growth (“build out”), relative to the new (2000) floodplain boundary. Table 3.2-3 presents the number of buildings damaged by flooding (i.e., non-zero dollar damage) by occupancy under each of the three scenarios. As noted in Section 2 a HAZUS®MH occupancy class was associated with each occupancy type in the Mecklenburg assessor database. As shown in the figure, the number of damaged buildings increases between runs for the majority of building types. The increase in the number of flooded buildings between Run 1 and Run 2 is due to differences in the floodplain boundary between the 1975 flood study and the 2000 flood study map revisions. The increase between Run 2 and Run 3 is attributable to the projected increase in floodplain development. The values shown in Table 3.2-3 are presented to give the reader perspective on the relative number of flooded buildings, which is useful when viewing the subsequent tables. 3-31 Table 3.2-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Sugar Creek Watershed HAZUS®MH Occupancy Description Code COM1/COM4 Mix of Retail Trade & Professional/Technical Services COM2 Wholesale Trade COM3 Personal & Repair Services COM4 Business/Professional/ Technical Services COM7 Medical Office/Medical Clinic COM8 Entertainment & Recreation GOV1 General Government IND2/IND6 Mix of Light Industrial & Construction RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling, Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement RES3 Multi-Family Dwelling RES4 Temporary Lodging/Hotel/Motel Current Inventory, Original Floodplain (Run 1) 1 Current Inventory, New Floodplain (Run 2) 1 Future Inventory, New Floodplain (Run 3) 14 4 3 5 4 6 4 9 10 15 0 1 1 0 0 1 1 2 1 2 1 39 42 69 127 14 15 15 4 4 4 6 5 10 4 1 12 1 15 1 91 130 253 1,149 1,110 1,364 Total No. of flooded buildings Total No. of unflooded buildings The aggregate dollar damage across all building occupancy types is shown in Figure 3.29. As shown, the estimated dollar damage increases from Run 1 to Run 2 and from Run 2 to Run 3. Tables 3.2-3 through 3.2-7 and the associated discussion go into greater detail about the results of the loss estimation. However, it should be noted that the significant escalation of estimated damage based on future development suggests the need for 3-32 mitigation measures, such as requiring future development to be 1-foot above the future one hundred year flood elevation (as currently proposed by county staff). $40,000,000.00 $35,000,000.00 Estimated Damage (Dollars) $30,000,000.00 $25,000,000.00 Structure Contents $20,000,000.00 $15,000,000.00 $10,000,000.00 $5,000,000.00 $Run 1 Run 2 Run 3 Building Inventory and Floodplain Scenario Figure 3.2-9. Sugar Creek Watershed Aggregate Damage Estimation Results Table 3.2-4 presents the overall average damage percentage calculated for building structures by occupancy, through the application of the various depth-damage curves. Table 3.2-4 clearly shows that changes in inventory development greatly affects the average percent damage in Run 3. Viewing the GIS data indicates that many of the currently vacant parcels assumed to be developed in the “build out” are either largely or completely within the future floodplain boundary. In Runs 1 and 2, most of the average structure damage levels are less than 20 percent. In Run 3, most of the occupancies have structure damage ranges between 20 and 45 percent. In many cases, the larger percent damage can be attributed to occupancies with a small number of damaged 3-33 structures, most notable being the occupancy class GOV1 where a single small structure drives the damage percentage. Table 3.2-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Sugar Creek Watershed HAZUS®MH Occupancy Code Description COM1/COM4 Mix of Retail Trade & Professional/Technical Services COM2 Wholesale Trade COM3 Personal & Repair Services COM4 Business/Professional/ Technical Services COM7 Medical Office/Medical Clinic COM8 Entertainment & Recreation GOV1 General Government IND2/IND6 Mix of Light Industrial & Construction RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling, Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement RES3 Multi-Family Dwelling RES4 Temporary Lodging/Hotel/Motel Current Inventory, Original Floodplain (Run 1) 4.4 Current Inventory, New Floodplain (Run 2) 4.4 Future Inventory, New Floodplain (Run 3) 40.8 7.5 10.4 20.8 12.7 33.8 12.7 30.3 45.7 52.0 --- 5.6 5.6 --- --- 42.5 1.0 16.2 1.6 26.7 1.6 32.9 17.8 19.9 25.3 12.6 15.6 15.6 14.7 21.1 21.1 43.5 46.5 40.2 13.5 34.1 18.7 43.0 20.7 43.0 Table 3.2-5 shows the dollar damage to building structures that is computed when the damage percentages are multiplied by the structure/parcel valuation. As with the previous table, there are significant differences in the dollar damage between the three scenarios. Between Run 1 and Run 2, there is an increase in total structure damage from $3.2 million to $6.1 million. This corresponds to an increase of $2.95 million, or 93%. As the building inventories used for these scenarios are identical, the difference in damage is attributable 3-34 to differences in the floodplain between the 1975 flood study and the 2000 revision of the 100-yr floodplain map. Proceeding from Run 2 to Run 3, there is a significant increase in estimated damage from $6.1 million to $32.8 million, suffered by projected development in the floodplain. This corresponds to an increase of $26.7 million, or 438%. A notable finding from the results of Run 3 is a spike in both the total and average damage to commercial and industrial properties and a significant increase in the single-family losses Table 3.2-5. Structure Dollar Damage by HAZUS®MH Occupancy Type: Sugar Creek Watershed HAZUS®MH Occupancy Code COM1/COM4 COM2 COM3 COM4 COM7 COM8 GOV1 IND2/IND6 RES1A RES1B RES1D RES1E RES3 RES4 Current Inventory, Original Floodplain (Run 1) Total Avg. $17,869 $17,869 $78,085 $19,521 $10,031 $3,344 $1,317,996 $146,444 --------$1,492 $1,492 $4,491 $2,246 $708,186 $16,862 $309,012 $22,072 $48,455 $12,114 $342,341 $57,057 $244,414 $61,103 $85,273 $85,273 Total $3,167,644 Current Inventory, New Floodplain (Run 2) Total Avg. $17,869 $17,869 $299,022 $59,804 $16,488 $4,122 $2,272,909 $227,291 $9,193 $9,193 ----$2,375 $2,375 $8,247 $4,124 $1,295,099 $18,770 $400,183 $26,679 $69,048 $17,262 $353,753 $70,751 $1,266,129 $105,511 $107,526 $107,526 $34,809 $6,117,840 Future Inventory, New floodplain (Run 3) Total Avg. $2,383,879 $170,277 $1,108,184 $184,697 $16,488 $4,122 $6,187,158 $412,477 $9,193 $9,193 $162,225 $162,225 $2,375 $2,375 $16,169,840 $414,611 $3,967,198 $31,238 $400,183 $26,679 $69,048 $17,262 $600,265 $60,027 $1,644,016 $109,601 $107,526 $107,526 $47,060 $32,827,578 $129,753 Table 3.2-6 presents the overall average damage percentage calculated for building contents by occupancy type. Similar to the structure damage percent results shown in Table 3.2-4, the difference in contents damage percentages between Run 1 and Run 2 is relatively small, while Run 3 exhibits a large increase over Run 2. In general, the contents damage ranges from 15 to 40 percent. Again, many of the outliers occur primarily for building types with a small number of flooded structures. 3-35 Table 3.2-6. Contents Damage Percent by HAZUS®MH Occupancy Type: Sugar Creek Watershed HAZUS®MH Occupancy Description Code COM1/COM4 Mix of Retail Trade & Professional/Technical Services COM2 Wholesale Trade COM3 Personal & Repair Services COM4 Business/Professional/ Technical Services COM7 Medical Office/Medical Clinic COM8 Entertainment & Recreation GOV1 General Government IND2/IND6 Mix of Light Industrial & Construction RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling, Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement RES3 Multi-Family Dwelling RES4 Temporary Lodging/Hotel/Motel Current Inventory, Original Floodplain (Run 1) 4.4 Current Inventory, New Floodplain (Run 2) 4.4 Future Inventory, New Floodplain (Run 3) 40.8 7.5 42.1 20.8 50.7 33.8 50.7 30.3 45.7 52.0 --- 5.6 5.6 --- --- 42.5 75.3 25.2 90.9 37.1 90.9 46.7 21.0 24.3 28.6 15.8 20.9 20.9 18.3 24.4 24.4 19.5 26.3 31.3 12.3 34.1 24.7 43.0 33.2 43.0 Table 3.2-7 provides the estimated dollar damage to building contents by occupancy type. Similar to the structure dollar damage shown in Table 3.2-5, there are significant differences in the dollar damage between scenarios. Between Run 1 and Run 2, there is an increase in total estimated contents damage from $3.5 million to $7.1 million. This corresponds to an increase of $3.6 million, or 103%. The increase in damage is due to changes in the floodplain depth and extent between the 1975 flood study and the recent 2000 revision of the 100-yr floodplain map. Between Run 2 to Run 3, there is a significant increase in estimated damage from $7.1 million to nearly $34.8 million attributable to projected growth. This corresponds to an increase of $27.6 million, or 388%. Again, 3-36 there is a notable spike in both the total and average damage to commercial and industrial properties between Runs 2 and 3. residential contents damage. Also notable is the increase in the single-family The significant escalation of estimated structure and contents damage based on future development, suggests the need for mitigation measures within the Sugar Creek floodplain. Table 3.2-7. Contents Dollar Damage by HAZUS®MH Occupancy Type: Sugar Creek Watershed HAZUS®MH Occupancy Code COM1/COM4 COM2 COM3 COM4 COM7 COM8 GOV1 IND2/IND6 RES1A RES1B RES1D RES1E RES3 RES4 Current Inventory, Current Inventory, New Current Floodplain Floodplain (Run 1) (Run 2) Total Avg. Total Avg. $35,970 $35,970 $35,970 $35,970 $270,954 $67,739 $1,037,608 $207,522 $21,613 $7,204 $33,626 $8,406 $2,092,977 $232,553 $3,609,380 $360,938 ----$22,982 $22,982 --------$56,200 $56,200 $67,841 $67,841 $3,498 $1,749 $5,532 $2,766 $414,294 $9,864 $782,318 $11,338 $197,261 $14,090 $271,847 $18,123 $$30,272 $7,568 $40,167 $10,042 $78,504 $13,084 $85,758 $17,152 $116,134 $29,033 $903,858 $75,321 $180,097 $180,097 $227,095 $227,095 Total $3,497,774 $38,437 $7,123,981 3-37 Future Inventory, New Floodplain (Run 3) Total Avg. $4,798,750 $342,768 $3,845,399 $640,900 $33,626 $8,406 $9,825,207 $655,014 $22,982 $22,982 $360,139 $360,139 $67,841 $67,841 $11,504,545 $294,988 $2,208,445 $17,389 $271,847 $18,123 $40,167 $10,042 $218,376 $21,838 $1,341,746 $89,450 $227,095 $227,095 $54,800 $34,766,164 $137,416 DETERMINATION OF FINANCIAL IMPACTS FROM FLOOD STUDIES LONG WATERSHED (Report Delivered November 2001) Prepared for: MECKLENBURG COUNTY ENGINEERING & BUILDING STANDARDS Charlotte, NC 28202 3.3 3.3.1 Long Creek Analysis Results Summary for the Long Creek Basin Two building inventories and two floodplain scenarios maps were combined to develop damage estimates for the three scenarios listed above. Table 3.3-1 shows a summary of the number of flooded buildings by general occupancy classification. The simulation predicted 27, 38, and 117 damaged buildings from Runs 1, 2, and 3, respectively. Table 3.3-1. Number of Flooded Structures by General Occupancy: Long Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) NonResidential Commercial, Industrial, Religious, Education 2 2 9 Residential Single and Multi-Family Residential 25 36 108 27 38 117 Total The dollar damage resulting from the analysis is shown on Figure 3.3-1. The damage for each scenario shown in the figure is an aggregate across all building occupancy types. As shown, there is an increase in estimated damage between Run 1 (structure $316 thousand, contents $157 thousand) and Run 2 (structure $558 thousand, contents $302 thousand). This corresponds to an increase of $242 thousand (77%) for structures and $145 thousand (92%) for contents. The increase tracks the effect of changes in the floodplain extent and depth between the 1975 flood study and newly 2000 revised floodplain map. Based on the assumption that the revised floodplain map is more accurate than the 1975 flood study, the estimated damage results from Run 2 are representative of current conditions. 3-38 A comparison of the aggregate damage from Run 2 and Run 3 signifies the difference in damage between current and future building development conditions. For the analysis in Run 3, damage estimates for parcels that are currently vacant were developed based on their zoning. The result is a sharp increase in estimated structure damage from $558 thousand to $5.2 million and a corresponding increase in estimated contents damage from $302 thousand to approximately $3.2 million. This corresponds to an increase of $4.7 million (836%) for structures and $2.9 million (962%) for contents. Prior to this analysis, this significant escalation of potential damages based on future development was predicted by county staff and has led to efforts requiring new development to be 1-foot above the one-hundred year base flood elevation, where the BFE includes the increased runoff from the future or ultimate build-out. These results support that effort as the 1-foot requirement would reduce the results of Run 3 to levels more closely resembling the results of the existing development results presented by Run 2 (see Figure 3.3-1). $6,000,000.00 $5,000,000.00 Estimated Damage (Dollars) $4,000,000.00 Structure Content $3,000,000.00 $2,000,000.00 $1,000,000.00 $Run 1 Run 2 Run 3 Building Inventory and Floodplain Scenario Figure 3.3-1. Long Creek Watershed Aggregate Damage Estimation Results 3-39 Table 3.3-2 shows a summary of the building and content damage results by general occupancy classification. In general, Table 3.3-2 shows that the damages are dominated by damage and losses to residential structures in Runs 1 and 2. However, increased development to both sectors cause the significant differences between Run 2 and Run 3. The contents damages by occupancy generally reflect the building damages, although the typically higher content to structure ratios involved with non-residential development in Run 3 causing a large increase in content damages to that general occupancy classification. The results are discussed in greater detail in Section 3 of this report. Table 3.3-2. Summary of Building and Content Damage by General Occupancy: Long Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) Structural Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $11,913 $5,957 $21,106 $10,553 $1,845,766 $205,085 Residential Single and Multi-Family Residential $304,314 $12,173 $537,350 $14,926 $3,382,499 $31,319 Content Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $15,529 $7,764 $25,915 $12,957 $1,332,420 $148,047 Residential Single and Multi-Family Residential $141,645 $5,666 $276,508 $7,681 $1,878,407 $17,393 3-40 3.3.2 Data Analysis 3.3.2.1 Long Creek Basin Characteristics and Study Data Depth grids were created for Long Creek and nine tributaries contributing flow to Long Creek. The grids depict the depth of flooding that will be exceeded with a 1-percent chance in any given year (100-year flood) under both existing and future development conditions. The network of streams analyzed is shown in Figure 3.3-2. Figure 3.3-2. Long Creek Basin Stream Network The studied reaches include approximately 15 miles of Long Creek and approximately 14.5 miles of tributary reaches. 3-41 3.3.2.1.1 Long Creek Watershed Depth Grid Flood elevation grids were created interpolating between water surface elevations determined at numerous cross sections along the study reaches. In all, 427 cross sections were used: 196 on Long Creek and 231 on the tributaries. The flood elevation grids were extended at the upstream end of each stream, at the confluence with each tributary, and at relatively large areas where floodwaters are not conveyed but, rather, pond at the elevation on the main stream. Where two stream flood elevation grids overlap the final flood elevation grid uses the greater of the two elevations. Depth grids were created by subtracting the ground elevation in the digital elevation model from the flood elevation at the corresponding cell in the elevation grid. Cells with flood depths less than zero (those outside of the floodplain, for example) were deleted from the flood elevation and flood depth grids. The resulting existing conditions flood depth grid is shown in Figure 3.3-3. Approximately 1423 acres are within the 100-year floodplain. Figure 3.3-4 shows the distribution of floodplain area inundated at 1-foot depth increments. The maximum depth is 17.36 feet and the average (mean) depth is 4.37 feet. Approximately 79 acres, mostly channel area, is inundated at a depth greater than 10 feet. Note that a 10-foot buffer on either side of the channels studied has an area of approximately 70 acres. 3-42 Figure 3.3-3. Existing Conditions Flood Depth Grid Long Creek Basin 250 200 150 100 50 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Flood Depth (feet) Figure 3.3-4. Distribution of Existing Condition Flood Depths 3-43 The future conditions flood depth grid is shown in Figure 3.3-5. Approximately 1560 acres are within the 100-year floodplain, an increase of 137 acres or almost 10 percent. The distribution of floodplain area inundated at various depths is shown in Figure 3.3-6. The maximum depth is 19.18 feet (about 1.6 greater than existing conditions). The mean depth is 5.06 feet (about 0.7 foot greater than existing conditions). The area inundated by more than 10 feet is approximately 140 acres (61 acres or 77 percent more than the existing conditions). Figure 3.3-5. Future Conditions Flood Depth Grid 3-44 Long Creek Basin 250 200 150 100 50 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Flood Depth (feet) Figure 3.3-6. Distribution of Future Condition Flood Depths Subtracting the existing conditions flood depth grid from the future conditions flood depth grid yields a grid showing the increase in 100-year flood depths expected as a result of development within the basin. That grid is shown in Figure 3.3-7. The distribution of changes in 100-year flood depths is shown in Figure 3.3-8. Note that most (approximately 97.5 percent) of the differences are less than two feet. The 100-year flood depth increases are expected to be between 2 and 3 feet in approximately 8 acres just upstream of the Valleydale Road crossing of Gum Branch. The increases in approximately 30 acres in the vicinity of the Interstate 77 and U.S. Highway 21 crossings of Dixon Branch Tributary #1 are expected to be between 2 and 5 feet. 3-45 Figure 3.3-7. Increases in 100-year Flood Depths Long Creek Basin 900 800 700 600 500 400 300 200 100 0 1 2 3 4 5 Difference in Flood Depths (feet) Figure 3.3-8. Differences in 100-year Flood Depths 3-46 3.3.2.1.2 Long Creek Parcel and Building Data Review To determine the parcels and building footprints impacted by Long Creek, the floodplain boundaries from both the 1975 flood study and the 2000 flood study were combined and a buffer of 100-feet added. The buffer was added to ensure that not only those structures and parcels intersecting the parcels were selected, but those that are fairly close are also selected to provide Mecklenburg County with a more complete perspective on the development surrounding Long Creek. There are 1,228 parcels that intersect the floodplain boundary (including the 100-foot buffer) surrounding Long Creek. Some duplicate parcels were identified and reviewed. In all cases, these turned out to be slivers in the GIS data, most likely right-of-ways that have been either returned to the parcel, or offers of dedication that were never acted upon. In all cases, the slivers were merged back into the main parcel. Of the 1,228 parcels, 330 (35%) are identified as “vacant” and an additional 23 parcels had information in the “effective area” field in the county assessor data indicating that a structure was on the parcel although there was no building footprint in the footprint layer. The high percentage of vacant parcels (35% based on 1,228 parcels) provides Mecklenburg County opportunity to manage future development and reduce future damage. There are 1,225 building footprints greater than 500 square feet that intersect the floodplain boundary. Of these, 87 were surveyed as part of the master-elevation- certificate surveys and none were surveyed as part of the “gpsbfe” survey data. Unfortunately of the 87 data points from the master-elevation-certificate surveys, 1 was missing data in either the first floor elevation or the lowest adjacent grade fields rendering the data unusable. An additional 95 parcels matched with survey data from the Flood 3C or Flood 3B survey data. Therefore, a total of 182 of the 1,225 could be assigned a first floor elevation and lowest adjacent grade from the survey data available. For the current inventory analysis, the 23 parcels without a building footprint that were identified as nonvacant based on the square footage in the assessors data will be carried as single structures at the centroid of the parcel for a total of 1,248 “buildings” in the floodplain (including the 100-foot buffer). For the future conditions or “build-out”, a single structure was placed at the centroid of the 330 vacant parcels identified earlier. This structure was established to have the 3-47 HAZUS®MH default floor area and value based on the occupancy class assigned to the approved zoning of the parcel (see Tables A-1 and A-2 in Appendix A). Therefore the total “buildings” within the floodplain for the built-out inventory is assumed to be 1,578. 3.3.3 Detailed Results for the Long Creek Basin To determine the potential impacts of floodplain map modifications, three damage estimates have been developed, as follows: 1. Run 1 – current inventory, original floodplain. Estimated losses based on the current building inventory within the Long Creek watershed (developed from surveyed data and parcel data) and the original 100-year floodplain boundary, based on the 1975 flood study. 2. Run 2 – current inventory, new floodplain. Estimated losses based on the current building inventory, expanded to include structures within the new floodplain that were previously outside the floodplain, and the newly revised floodplain boundary. 3. Run 3 – future inventory, new floodplain. Estimated losses to a projected future inventory that incorporates projected growth (“build out”), relative to the 2000 floodplain boundary. Table 3.3-3 presents the number of buildings damaged by flooding (i.e., non-zero dollar damage) by occupancy under each of the three scenarios. As noted in Section 2 a HAZUS®MH occupancy class was associated with each occupancy type in the Mecklenburg assessor database. As shown in the figure, the number of damaged buildings increases between runs for the majority of building types. The increase in the number of flooded buildings between Run 1 and Run 2 is due to differences in the floodplain boundary between the 1975 flood study and the 2000 flood study map revisions. The increase between Run 2 and Run 3 is attributable to the projected rise in floodplain development. The values shown in Table 3.2-3 are presented to give the reader perspective on the relative number of flooded buildings, which is useful when viewing the subsequent tables. 3-48 Table 3.3-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Long Creek Watershed HAZUS®MH Occupancy Description Code COM1/COM4 Mix of Retail Trade & Professional/Technical Services COM8 Entertainment & Recreation IND2/IND6 Mix of Light Industrial & Construction RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1E Single Family Dwelling, Split Level, with Basement RES2 Manufactured Housing RES3 Multi-Family Dwelling Total No. of flooded buildings Total No. of unflooded buildings Current Inventory, Original Floodplain (Run 1) --- Current Inventory, New Floodplain (Run 2) --- Future Inventory, New Floodplain (Run 3) 1 1 1 1 1 1 7 15 20 71 6 11 11 3 4 21 --1 --1 1 4 27 38 117 1,221 1,210 1,461 The aggregate dollar damage across all building occupancy types is shown in Figure 3.39. As shown, the estimated dollar damage increases from Run 1 to Run 2 and from Run 2 to Run 3. Tables 3.3-3 through 3.3-7 and the associated discussion go into greater detail about the results of the loss estimation. However, it should be noted that the significant escalation of estimated damage based on future development suggests the need for mitigation measures, such as requiring future development to be 1-foot above the future one hundred year flood elevation (as currently proposed by county staff). 3-49 $6,000,000.00 $5,000,000.00 Estimated Damage (Dollars) $4,000,000.00 Structure Content $3,000,000.00 $2,000,000.00 $1,000,000.00 $Run 1 Run 2 Run 3 Building Inventory and Floodplain Scenario Figure 3.3-9. Long Creek Watershed Aggregate Damage Estimation Results Table 3.3-4 presents the overall average damage percentage calculated for building structures by occupancy, through the application of the various depth-damage curves. Table 3.3-4 clearly shows that changes in inventory development greatly affects the average percent damage in Run 3. In Runs 1 and 2, most of the average structure damage levels are less than 20 percent. In Run 3, most of the occupancies have structure damage ranges between 20 and 45 percent. In many cases, the larger percent damage can be attributed to occupancies with a small number of damaged structures, most notable being the occupancy class RES2 where two vacant parcels with land use codes of manufactured housing are the source of the estimated damage. Obviously, the single structure assumption is not valid here and Mecklenburg County should review the land use of the parcels. 3-50 Table 3.3-4. Structure Damage Percent by HAZUS®MH Occupancy Type: Long Creek Watershed HAZUS®MH Occupancy Description Code COM1/COM4 Mix of Retail Trade & Professional/Technical Services COM8 Entertainment & Recreation IND2/IND6 Mix of Light Industrial & Construction RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1E Single Family Dwelling, Split Level, with Basement RES3 Manufactured Housing RES3 Multi-Family Dwelling Current Inventory, Original Floodplain (Run 1) --- Current Inventory, New Floodplain (Run 2) --- Future Inventory, New Floodplain (Run 3) 1.5 9.8 15.8 15.8 0.4 5.3 20.5 11.3 14.4 21.3 9.0 9.0 9.0 47.4 46.9 40.9 --7.2 --21.5 49.5 28.8 Table 3.3-5 shows the dollar damage to building structures that is computed when the damage percentages are multiplied by the structure/parcel valuation. As with the previous table, there are significant differences in the dollar damage between the three scenarios. Between Run 1 and Run 2, there is an increase in total structure damage from $316 thousand to $558 thousand. This corresponds to an increase of $242 thousand, or 77%. As the building inventory used for these scenarios are identical, the difference in damage is attributable to differences in the floodplain between the 1975 flood study and the 2000 revision of the 100-yr floodplain map. Proceeding from Run 2 to Run 3, there is a significant increase in estimated damage from $558 thousand to $5.2 million caused by projected development in the floodplain. This corresponds to an increase of $4.7 million, or 836%. A notable finding from the results of Run 3 is a spike in both the total and average damage to industrial properties and a significant increase in the single-family losses. 3-51 Table 3.3-5. Structure Dollar Damage by HAZUS®MH Occupancy Type: Long Creek Watershed HAZUS®MH Occupancy Code COM1/COM4 COM8 IND2/IND6 RES1A RES1B RES1E RES2 RES3 Total Current Inventory, Current Inventory, New Original Floodplain Floodplain (Run 1) (Run 2) Total Avg. Total Avg. --------$11,749 $11,749 $18,946 $18,946 $163 $163 $2,160 $2,160 $156,452 $10,430 $270,927 $13,546 $65,203 $10,867 $119,334 $10,849 $65,475 $21,825 $96,016 $24,004 --------$17,184 $17,184 $51,073 $51,073 $316,227 $11,712 $558,456 Future Inventory, New Floodplain (Run 3) Total Avg. $6,081 $6,081 $18,946 $18,946 $1,820,738 $260,106 $2,052,027 $28,902 $119,334 $10,849 $1,074,047 $51,145 $18,937 $18,937 $118,153 $29,538 $14,696 $5,228,264 $44,686 Table 3.3-6 presents the overall average damage percentage calculated for building contents by occupancy type. Similar to the structure damage percent results shown in Table 3.3-4, the difference in contents damage percentages between Run 1 and Run 2 is relatively small and Run 3 exhibits a large increase. In general, the contents damage ranges from 10 to 35 percent. Again, many of the outliers primarily occur for building types with a small number of flooded structures. 3-52 Table 3.3-6. Contents Damage Percent by HAZUS®MH Occupancy Type: Long Creek Watershed HAZUS®MH Occupancy Description Code COM1/COM4 Mix of Retail Trade & Professional/Technical Services COM8 Entertainment & Recreation IND2/IND6 Mix of Light Industrial & Construction RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1E Single Family Dwelling, Split Level, with Basement RES2 Manufactured Housing RES3 Multi-Family Dwelling Current Inventory, Original Floodplain (Run 1) --- Current Inventory, New Floodplain (Run 2) --- Future Inventory, New Floodplain (Run 3) 1.5 9.8 15.8 15.8 0.1 4.4 28.7 10.8 16.5 25.7 9.8 10.6 10.6 35.8 27.2 35.7 --5.9 --18.34 33.3 33.5 Table 3.3-7 shows the estimated dollar damage to building contents by occupancy type. Similar to the structure dollar damage shown in Table 3.3-5, there are significant differences in the dollar damage between scenarios. Between Run 1 and Run 2, there is an increase in total estimated contents damage from $157 thousand to $302 thousand. This corresponds to an increase of $145 thousand, or 92%. The increase in damage is due to changes in the floodplain depth and extent between the 1975 flood study and the recent 2000 revision of the 100-yr floodplain map. Between Run 2 to Run 3, there is a significant increase in estimated damage from $302 thousand to $3.2 million attributable to projected growth. This corresponds to an increase of $2.9 million, or 962%. Again, there is a notable spike in both the total and average damage to industrial properties between Runs 2 and 3. Also notable is the increase in the single-family residential contents damage. The significant escalation of estimated structure and contents damage based on future development, suggests the need for mitigation measures within the Long Creek floodplain. 3-53 Table 3.3-7. Contents Dollar Damage by HAZUS®MH Occupancy Type: Long Creek Watershed HAZUS®MH Occupancy Code COM1/COM4 COM8 IND2/IND6 RES1A RES1B RES1E RES2 RES3 Total Current Inventory, Current Inventory, New Future Inventory, New Original Floodplain Floodplain Floodplain (Run 1) (Run 2) (Run 3) Total Avg. Total Avg. Total Avg. --------$12,242 $12,242 $15,509 $15,509 $25,008 $25,008 $25,008 $25,008 $20 $20 $907 $906 $1,295,170 $185,024 $72,002 $4,800 $149,823 $7,491 $1,237,010 $17,423 $34,331 $5,722 $71,278 $6,480 $71,278 $6,480 $28,254 $9,418 $33,615 $8,404 $500,533 $23,835 --------$6,377 $6,377 $7,058 7,058 $21,792 $21,792 $63,210 $15,802 $157,173 $5,821 $302,423 3-54 $7,958 $3,210,827 $21,443 DETERMINATION OF FINANCIAL IMPACTS FROM FLOOD STUDIES LITTLE SUGAR & BRIAR CREEK WATERSHEDS (Report Delivered November 2001) Prepared for: MECKLENBURG COUNTY ENGINEERING & BUILDING STANDARDS Charlotte, NC 28202 3.4 3.4.1 Little Sugar and Briar Creek Analysis Results Summary for the Little Sugar and Briar Creek Basin Two building inventories and two floodplain scenarios maps were combined to develop damage estimates for the three scenarios listed above. Table 3.4-1 shows a summary of the number of flooded buildings by general occupancy classification. The simulation predicted 972, 1,187, and 1,565 damaged buildings from Runs 1, 2, and 3, respectively. Table 3.4-1. Number of Flooded Structures by General Occupancy: Little Sugar and Briar Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) NonResidential Commercial, Industrial, Religious, Education 224 255 363 Residential Single and MultiFamily Residential 748 932 1,202 972 1,187 1,565 Total The dollar damage resulting from the analysis is shown on Figure 3.4-1. The damage for each scenario shown in the figure is an aggregate across all building occupancy types. As shown, there is an increase in estimated damage between Run 1 (structure $56.5 million, contents $93.5 million) and Run 2 (structure $82.1 million, contents $132.0 million). This corresponds to an increase of $25.6 million (45%) for structures and $38.5 million (41%) for contents. The increase demonstrates the effect of changes in the floodplain extent and depth between the 1975 flood study and newly revised (2000) floodplain map. Based on the assumption that the revised floodplain map is more accurate than the 1975 flood study, the estimated damage results from Run 2 are representative of current conditions. A comparison of the aggregate damage from Run 2 and Run 3 highlights the difference in damage between current and future building development conditions. For the analysis in Run 3, damage estimates for parcels that are currently vacant were assumed to be 3-55 developed based on their zoning. The result is a sharp increase in estimated structure damage from $82.1 million to $137.1 million and a corresponding increase in estimated contents damage from $132.0 million to approximately $189.7 million. This corresponds to an increase of $26.7 million (67%) for structures and $27.6 million (44%) for contents. Prior to this analysis, this significant escalation of potential damages based on future development was predicted by county staff and has led to efforts requiring new development to be 1-foot above the one-hundred year base flood elevation, where the BFE includes the increased runoff from the future or ultimate build-out. These results support that effort as the 1-foot requirement would reduce the results of Run 3 to levels more closely resembling the results of the existing development results presented by Run 2 (see Figure 3.4-1). $200,000,000 $180,000,000 Structure Content $160,000,000 Estimate Damage (Dollar) $140,000,000 $120,000,000 $100,000,000 $80,000,000 $60,000,000 $40,000,000 $20,000,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.4-1. Little Sugar & Briar Creeks Aggregate Damage Estimation Results 3-56 Table 3.4-2 shows a summary of the building and content damage results by general occupancy classification. In general, Table 3.4-2 shows that the damages are fairly evenly split between residential and non-residential structures, with slightly more nonresidential damage, in Runs 1 and 2. This trend continues in Run 3 with only a moderate increase in the non-residential occupancies. The contents damage by occupancy generally increases with increasing building damage, again with the moderate increase in non-residential development in Run 3 causing a large increase in content damage to that general occupancy classification. The results are discussed in greater detail later in this report. Table 3.4-2. Summary of Building and Content Damage by General Occupancy: Little Sugar and Briar Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) Structural Damage Total Average Total Average Total Average NonResidential Commercial , Industrial, Religious, Education $31,712,768 $141,575 $49,726,939 $195,006 $87,186,782 $240,184 Residential Single and Multi-Family Residential $24,833,667 $33,200 $32,397,774 $34,762 $49,983,225 $41,583 Content Damage Total Average Total Average NonResidential Commercial , Industrial, Religious, Education $78,165,102 $348,951 $109,683,821 $430,133 $157,323,971 $433,399 Residential Single and Multi-Family Residential $15,321,562 $20,483 $22,348,252 $23,979 $32,373,785 $26,933 3-57 Total Average 3.4.2 Data Analysis 3.4.2.1 Little Sugar & Briar Creeks Basin Characteristics and Study Data Depth grids were created for Little Sugar Creek and seven tributaries, including Briar Creek, contributing flow to Little Sugar Creek. The grids depict the depth of flooding that will be exceeded with a 1-percent chance in any given year (100-year flood) under both existing and future development conditions. The network of streams analyzed is shown in Figure 3.4-2. Figure 3.4-2. Little Sugar Creek Basin Stream Network The studied reaches include approximately 19 miles of Little Sugar Creek and approximately 17 miles of tributary reaches, including 9.7 miles of Briar Creek. Flood elevation grids were created interpolating between water surface elevations determined at numerous cross sections along the study reaches. In all, 684 cross sections were used: 335 on Little Sugar Creek and 349 on the tributaries, including 209 on Briar Creek. The flood elevation grids were extended at the upstream end of each stream, at the confluence with each tributary, and at relatively large areas where 3-58 floodwaters are not conveyed but, rather, pond at the elevation on the main stream. Where two stream flood elevation grids overlap the final flood elevation grid uses the greater of the two elevations. Depth grids were created by subtracting the ground elevation in the digital elevation model from the flood elevation at the corresponding cell in the elevation grid. Cells with flood depths less than zero (those outside of the floodplain, for example) were deleted from the flood elevation and flood depth grids. The resulting existing conditions flood depth grid is shown in Figure 3.4-3. Approximately 2300 acres are within the 100-year floodplain. Figure 3.4-4 shows the distribution of floodplain area inundated at 1-foot depth increments. The maximum depth is 30.37 feet and the average (mean) depth is 6.84 feet. Approximately 555 acres are inundated at a depth greater than 10 feet. Figure 3.4-3. Existing Conditions Flood Depth Grid 3-59 Little Sugar Creek Basin 250 200 150 100 50 0 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 Flood Depth (feet) Figure 3.4-4. Distribution of Existing Condition Flood Depths The future conditions flood depth grid is shown in Figure 3.4-5. Approximately 2500 acres are within the 100-year floodplain, an increase of 200 acres or almost 9 percent. The distribution of floodplain area inundated at various depths is shown in Figure 3.4-6. The maximum depth is 30.60 feet (only 0.23 feet greater than existing conditions). The mean depth is 7.48 feet (0.64 foot greater than existing conditions). The area inundated by more than 10 feet is approximately 709 acres (154 acres or 28 percent more than the existing conditions). 3-60 Figure 3.4-5. Future Conditions Flood Depth Grid Little Sugar Creek Basin Area Inundated (acres) 250 200 150 100 50 0 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 Flood Depth (feet) Figure 3.4-6. Distribution of Future Condition Flood Depths 3-61 Subtracting the existing conditions flood depth grid from the future conditions flood depth grid yields a grid showing the increase in 100-year flood depths expected as a result of development within the basin. That grid is shown in Figure 3.4-7. The distribution of changes in 100-year flood depths is shown in Figure 3.4-8. Note that most (approximately 86 percent) of the differences are less than two feet. Except for a small area in the Little Sugar Creek floodplain just above the confluence with Dairy Branch, the increases exceeding 2 feet occur within the Briar Creek Floodplain. The largest area with increases exceeding 2 feet is approximately 210 acres of Briar Creek floodplain upstream of the Seaboard Coast Line Railroad crossing (just downstream of the confluence with Edwards Branch). Figure 3.4-7. Increases in 100-year Flood Depths 3-62 Little Sugar Creek Basin 1400 1200 1000 800 600 400 200 0 1 2 3 4 5 Difference in Flood Depths (feet) Figure 3.4-8. Differences in 100-year Flood Depths 3.4.2.1.1 Little Sugar & Briar Creek Parcel and Building Data Review To determine the parcels and building footprints impacted by Little Sugar and Briar Creeks, the floodplain boundaries from both the 1975 flood study and the 2000 flood study were combined and a buffer of 100-feet added. The buffer was added to ensure that not only those structures and parcels intersecting the floodplain were selected, but those that are fairly close are also selected to provide Mecklenburg County with a more complete perspective on the development surrounding Little Sugar and Briar Creek. There are 4,657 parcels that intersect the floodplain boundary (including the 100-foot buffer) surrounding Little Sugar and Briar Creek. Some duplicate parcels were identified and reviewed. In all cases, these turned out to be slivers in the GIS data, most likely rightof-ways that have been either returned to the parcel, or offers of dedication that were never acted upon. In all cases, the slivers were merged back into the main parcel. Of the 4,657 parcels, 715 are identified as “vacant” of these parcels of which, 68 parcels had structures on them, typically large structures that covered multiple parcels precluding development on the “vacant” parcels, and an additional 36 parcels had information in the “effective area” field in the county assessor data indicating that a structure was on the parcel. Therefore of the 4,657 parcels, 647 are defined as vacant for this study. Although the percentage of vacant parcels (14% based on 4,657 parcels) does not provide 3-63 Mecklenburg County the opportunities to manage future development and reduce future damage seen in other watersheds, the County should consider reviewing future development conditions. There are 5,278 building footprints greater than 500 square feet that intersect the floodplain boundary. Of these, 568 were surveyed as part of the master-elevation- certificate surveys and another 1,174 were surveyed as part of the “gpsbfe” survey data. Unfortunately of the 568 data points from the master-elevation-certificate surveys, 33 were missing data in either the first floor elevation or the lowest adjacent grade fields rendering the data unusable, of the 1,174 ‘gpsbfe” survey data points, 3 were missing data in either the lowest adjacent grade or the first floor elevation. An additional 31 parcels matched with survey data from the Flood 3C or Flood 3B survey data. Therefore, a total of 1,737 of the 5,278 could be assigned a first floor elevation and lowest adjacent grade from the survey data available. For the analysis, the 36 parcels without a building footprint that were identified as non-vacant based on the square footage in the assessors data will be carried as single structures at the centroid of the parcel for a total of 5,314 “buildings” in the floodplain (including the 100-foot buffer). For the future conditions or “build-out”, a single structure was placed at the centroid of the 647 vacant parcels identified earlier. ®MH HAZUS This structure was established to have the default floor area and value based on the occupancy class assigned to the approved zoning of the parcel (see Tables A-1 and A-2 in Appendix A). Therefore the total “buildings” within the floodplain for the built-out inventory is assumed to be 5,961. 3.4.3 Detailed Results for the Little Sugar & Briar Creek Basins To determine the potential impacts of floodplain map modifications, three damage estimates have been developed, as follows: 1. Run 1 – current inventory, original floodplain. Estimated losses based on the current building inventory within the Little Sugar & Briar Creek watershed (developed from surveyed data and parcel data) and the original 100-year floodplain boundary, based on the 1975 flood study. 3-64 2. Run 2 – current inventory, new floodplain. Estimated losses based on the current building inventory, expanded to include structures within the new floodplain that were previously outside the floodplain, and the newly revised floodplain boundary. 3. Run 3 – future inventory, new floodplain. Estimated losses to a projected future inventory that incorporates projected growth (“build out”), relative to the new (2000) floodplain boundary. Table 3.4-3 presents the number of buildings damaged by flooding (i.e., non-zero dollar damage) by occupancy under each of the three scenarios. As noted in Section 2 a HAZUS®MH occupancy class was associated with each occupancy type in the Mecklenburg assessor database. As shown in the figure, the number of damaged buildings increases between runs for the majority of building types. The increase in the number of flooded buildings between Run 1 and Run 2 is due to differences in the floodplain boundary between the 1975 flood study and the 2000 flood study map revisions. The increase between Run 2 and Run 3 is attributable to the projected increase in floodplain development. The values shown in Table 3.4-3 are presented to give the reader perspective on the relative number of flooded buildings, which is useful when viewing the subsequent tables. 3-65 Table 3.4-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Little Sugar and Briar Creek Watershed HAZUS®MH Occupancy Description Code COM1 Retail Trade COM1/COM4 Mix of Retail Trade & Professional/Technical Services COM2 Wholesale Trade COM3 Personal & Repair Services COM4 Business/Professional/ Technical Services COM5 Banking COM6 Hospital COM7 Medical Office/Clinic COM8 Entertainment & Recreation COM9 Theater EDU2 College, University GOV1 General Government IND2/IND6 Mix of Light Industrial & Construction REL1 Religious RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling, Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement RES3 Multi-Family Dwelling RES4 Temporary Lodging/Hotel/Motel RES5 Institutional, Dormitory Total No. of flooded buildings Total No. of unflooded buildings Current Inventory, Original Floodplain (Run 1) 13 30 Current Inventory, New Floodplain (Run 2) 15 33 Future Inventory, New Floodplain (Run 3) 15 80 86 10 93 14 93 15 30 35 46 2 3 5 28 2 5 5 33 2 5 5 36 3 2 4 2 3 2 4 2 3 2 5 46 3 433 3 535 4 687 56 66 66 42 63 63 97 120 198 120 3 147 6 187 6 --972 1 1,187 1 1,565 4,342 4,127 4,396 3-66 The aggregate dollar damage across all building occupancy types is shown in Figure 3.49. As shown, the estimated dollar damage increases from Run 1 to Run 2 and from Run 2 to Run 3. Tables 3.4-3 through 3.4-7 and the associated discussion go into greater detail about the results of the loss estimation. However, it should be noted that the escalation of estimated damage based on future development suggests the need for mitigation measures, such as requiring future development to be 1-foot above the future one hundred year flood elevation (as currently proposed by county staff). $200,000,000 $180,000,000 Structure Content $160,000,000 Estimate Damage (Dollar) $140,000,000 $120,000,000 $100,000,000 $80,000,000 $60,000,000 $40,000,000 $20,000,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.4-9. Little Sugar & Briar Creek Aggregate Damage Estimation Results Table 3.4-4 presents the overall average damage percentage calculated for building structures by occupancy, through the application of the various depth-damage curves. Table 3.4-4 shows that changes in inventory development have relatively minor affects to the average percent damage in Run 3. Slight reductions in the average percent damage may indicate that many of the parcels are on the edges of the floodplain. In Runs 1 and 2, most of the average structure damage levels are between 15 and 40 percent. In Run 3, 3-67 most of the occupancies have structure damage ranges between 15 and 55 percent. It is notable that structure damage over 50% is typically deemed destroyed by the Federal Insurance and Mitigation Administration. Structures receiving over 50% estimated damage are likely to be excellent acquisition candidates. Table 3.4-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Little Sugar and Briar Creek Watershed HAZUS®MH Occupancy Description Code COM1 Retail Trade COM1/COM4 Mix of Retail Trade & Professional/Technical Services COM2 Wholesale Trade COM3 Personal & Repair Services COM4 Business/Professional/ Technical Services COM5 Banking COM6 Hospital COM7 Medical Office/Medical Clinic COM8 Entertainment & Recreation COM9 Theater EDU2 College, University GOV1 General Government IND2/IND6 Mix of Light Industrial & Construction REL1 Religious RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling, Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement RES3 Multi-Family Dwelling RES4 Temporary Lodging/Hotel/Motel RES5 Institutional, Dormitory Current Inventory, Original Floodplain (Run 1) 19.6 37.5 Current Inventory, New Floodplain (Run 2) 23.7 43.9 Future Inventory, New Floodplain (Run 3) 23.7 47.4 48.9 12.1 50.0 13.4 50.0 14.6 50.6 49.6 50.6 2.1 33.8 32.5 5.1 31.0 36.4 5.1 31.0 36.4 35.6 40.3 37.9 24.5 50.9 2.3 9.6 24.8 56.2 2.8 12.9 24.8 56.2 2.4 33.3 26.6 21.8 29.7 23.3 27.3 26.0 13.8 12.8 12.8 13.1 14.4 14.4 35.4 39.2 38.9 23.4 23.5 25.2 16.9 26.8 16.9 --- 14.6 14.6 3-68 Table 3.4-5 shows the dollar damage to building structures that is computed when the damage percentages are multiplied by the structure/parcel valuation. As with the previous table, there are significant differences in the dollar damage between the three scenarios. Between Run 1 and Run 2, there is an increase in total structure damage from $56.4 million to $82.1 million. This corresponds to an increase of $25.7 million, or 46%. As the building inventories used for these scenarios are identical, the difference in damage is attributable to differences in the floodplain between the 1975 flood study and the 2000 revision of the 100-yr floodplain map. Proceeding from Run 2 to Run 3, there is a significant increase in estimated damage from $82.1 million to $137.2 million, suffered by projected development in the floodplain. This corresponds to an increase of $55 million, or 67%. It is notable that Run 3 has large increases in all general occupancies (commercial, industrial, and residential) with the greatest increase occurring in the commercial classification. Table 3.4-5. Structure Dollar Damage by HAZUS®MH Occupancy Type: Little Sugar and Briar Creek Watershed HAZUS®MH Occupancy Code COM1 COM1/COM4 COM2 COM3 COM4 COM5 COM6 COM7 COM8 COM9 EDU2 GOV1 IND2/IND6 REL1 RES1A RES1B RES1D RES1E RES3 RES4 RES5 Total Current Inventory, Original Floodplain (Run 1) Total Avg. $663,289 $51,022 $2,836,14 $94,539 $12,829,022 $149,175 $265,707 $26,571 $5,005,997 $166,867 $20,413 $10,206 $626,919 $208,973 $2,395,638 $479,128 $2,471,302 $88,260 $914,618 $304,873 $2,834,044 $1,417,022 $22,618 $5,654 $5,506 $2,753 $139,722 $46,574 $5,709,561 $13,186 $2,963,594 $52,921 $528,275 $12,578 $8,341,520 $85,995 $7,290,716 $60,756 $681,811 $227,270 ----$56,546,435 $58,175 Current Inventory, New Future Inventory, New Floodplain floodplain (Run 2) (Run 3) Total Avg. Total Avg. $1,049,513 $69,968 $1,049,513 $69,968 $3,512,784 $106,448 $13,320,542 $166,507 $13,704,382 $147,359 $13,704,382 $147,359 $352,158 $25,154 $606,288 $40,419 $18,055,517 $515,872 $25,117,738 $546,038 $47,105 $23,553 $47,105 $23,553 $973,964 $194,793 $973,964 $194,793 $2,807,263 $561,453 $2,807263 $561,453 $3,910,239 $118,492 $4,310,940 $119,748 $921,767 $307,256 $921,767 $307,256 $2,970,575 $1,485,287 $2,970,575 $1,485,287 $27,704 $6,926 $41,541 $8,308 $7,490 $3,745 $19,849,047 $431,501 $152,655 $50,885 $232,594 $58,149 $7,569,859 $14,149 $15,476,071 $22,527 $2,131,449 $32,295 $2,131,449 $32,295 $992,481 $15,754 $992,481 $15,754 $11,176,158 $93,135 $15,549,887 $78,535 $10,236,720 $69,638 $15,542,229 $83,114 $1,233,523 $205,587 $1,233,523 $205,587 $291,107 $291,107 $291,107 $291,107 $82,124,414 $69,187 $137,170,007 $87,649 3-69 Table 3.4-6 presents the overall average damage percentage calculated for building contents by occupancy type. Similar to the structure damage percent results shown in Table 3.4-4, the difference in the range of contents damage percentages between Run 1 and Run 2 is relatively small, while Run 3 exhibits a large increase over Run 2. general, the contents damage ranges from 15 to 55 percent. Table 3.4-6. Contents Damage Percent by HAZUS®MH Occupancy Type: Little Sugar and Briar Creek Watershed HAZUS®MH Occupancy Code COM1 COM1/COM4 COM2 COM3 COM4 COM5 COM6 COM7 COM8 COM9 EDU2 GOV1 IND2/IND6 REL1 RES1A RES1B RES1D RES1E RES3 RES4 RES5 Description Retail Trade Mix of Retail Trade & Professional/Technical Services Wholesale Trade Personal & Repair Services Business/Professional/ Technical Services Banking Hospitals Medical Office/Medical Clinic Entertainment & Recreation Theater College, University General Government Mix of Light Industrial & Construction Religious Single Family Dwelling, 1 Story, No Basement Single Family Dwelling, 2 Story, No Basement Single Family Dwelling, Split Level, No Basement Single Family Dwelling, Split Level, with Basement Multi-Family Dwelling Temporary Lodging/Hotel/Motel Institutional, Dormitory Current Inventory, Original Floodplain (Run 1) 19.6 37.5 Current Inventory, New Floodplain (Run 2) 23.7 43.9 Future Inventory, New Floodplain (Run 3) 23.7 46.8 49.4 49.1 50.5 50.2 50.5 50.5 50.4 49.3 50.3 2.1 52.3 32.5 5.1 40.7 36.4 5.1 40.7 36.4 47.7 53.3 54.1 24.5 50.9 76.4 11.5 24.8 56.2 88.1 17.5 24.8 56.2 86.9 49.2 26.6 25.9 29.7 27.4 27.3 28.6 18.2 16.5 16.5 15.8 17.2 17.2 33.2 36.5 33.4 39.8 23.5 46.4 16.9 48.9 16.9 ---- 14.6 14.6 3-70 In Table 3.4-7 provides the estimated dollar damage to building contents by occupancy type. Similar to the structure dollar damage shown in Table 3.4-5, there are significant differences in the dollar damage between scenarios. Between Run 1 and Run 2, there is an increase in total estimated contents damage from $93.5 million to $132 million. This corresponds to an increase of $38.5million, or 41%. The increase in damage is due to changes in the floodplain depth and extent between the 1975 flood study and the recent 2000 revision of the 100-yr floodplain map. Between Run 2 to Run 3, there is a significant increase in estimated damage from $132 million to $189.7 million attributable to projected growth. This corresponds to an increase of $57.6 million, or 44%. While the overall increase in contents damage is relatively small (40 percentile), the total estimated damages (over $100 million) warrant the review of mitigation measures. Table 3.4-7. Contents Dollar Damage by HAZUS®MH Occupancy Type: Little Sugar and Briar Creek Watershed HAZUS®MH Occupancy Code COM1 COM1/COM4 COM2 COM3 COM4 COM5 COM6 COM7 COM8 COM9 EDU2 GOV1 IND2/IND6 REL1 RES1A RES1B RES1D RES1E RES3 RES4 RES5 Current Inventory, Current Floodplain (Run 1) Total Avg. $1,405,096 $108,084 $5,709,197 $190,307 $44,370,422 $515,935 $620,701 $62,070 $7,787,242 $259,575 $27,782 $13,891 $226,823 $75,608 $5,989,095 $1,197,819 $4,676,604 $167,022 $1,642,654 $547,551 $3,667,253 $1,833,626 $393,589 $98,397 $3,269 $1,635 $205,391 $68,464 $3,375774 $7,796 $2,117,439 $37,811 $325,111 $7,741 $2,875,908 $29,649 $6,627,329 $55,228 $1,439,985 $479,995 ----- Total $93,486,664 Current Inventory, New Future Inventory, New Floodplain Floodplain (Run 2) (Run 3) Total Avg. Total Avg. $2,241,986 $149,466 $2,241,986 $149,466 $7,071,234 $214,280 $26,814,251 $335,178 $47,375,736 $509,417 $47,375,736 $509,417 $760,341 $54,310 $1,059,197 $70,613 $28,478,770 $813,679 $39,683,716 $862,689 $64,110 $32,055 $64,110 $32,055 $475,264 $95,053 $475,264 $95,053 $7,018,157 $1,403,631 $7,018,157 $1,403,631 $7,413,281 $224,645 $8,440,504 $234,458 $1,655,493 $551,831 $1,655,493 $551,831 $3,843,924 $1,921,962 $3,843,924 $1,921,962 $450,887 $112,722 $1,019,744 $203,949 $5,034 $2,517 $14,684,775 $319,234 $224,403 $74,801 $341,914 $85,478 $4,488,817 $8,390 $8,099,175 $11,789 $1,340,818 $20,315 $1,340,718 $20,315 $602,298 $9,560 $602,298 $9,560 $5,031,146 $41,926 $6,654,119 $33,607 $10,270,354 $69,866 $15,062,556 $80,548 $2,605,200 $434,200 $2,605,200 $434,200 $614,818 $614,818 $614,818 $614,818 $96,180 $132,032,072 3-71 $111,232 $189,697,756 $121,213 DETERMINATION OF FINANCIAL IMPACTS FROM FLOOD STUDIES FOUR MILE CREEK AND ROCKY BRANCH WATERSHEDS (Report Delivered December 2001) Prepared for: MECKLENBURG COUNTY ENGINEERING & BUILDING STANDARDS Charlotte, NC 28202 3.5 Four Mile Creek and Rocky Branch Analysis 3.5.1 Results Summary for the Four Mile Creek and Rocky Branch Basins Two building inventories and two floodplain boundary maps were combined to develop damage estimates for the three scenarios listed above. Table 3.5-1 shows a summary of the number of flooded buildings by general occupancy classification. The simulations predicted 7, 23, and 71 damaged buildings from Runs 1, 2, and 3, respectively. Table 3.5-1. Number of Flooded Structures by General Occupancy: Four Mile Creek and Rocky Branch Watersheds General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) NonResidential Commercial, Industrial, Religious, Education 1 1 4 Residential Single and MultiFamily Residential 6 22 67 7 23 71 Total The dollar damage resulting from the analysis is shown on Figure 3.5-1. The damage for each scenario shown in the figure is an aggregate across all building occupancy types. As shown, there is an increase in estimated damage between Run 1 (structure $443 thousand, contents $246 thousand) and Run 2 (structure $847 thousand, contents $471 thousand). This corresponds to an increase of $404 thousand (91%) for structures and $225 thousand (91%) for contents. The increase demonstrates the effect of changes in the floodplain extent and depth between the 1975 flood study and newly revised (2000) floodplain map. Based on the assumption that the revised floodplain map is more accurate than the 1975 flood study, the estimated damage results from Run 2 are representative of current conditions. A comparison of the aggregate damage from Run 2 and Run 3 highlights the difference in damage between current and future building development conditions. For the analysis in Run 3, damage estimates for parcels that are currently vacant were assumed to be 3-72 developed based on their zoning. The result is a sharp increase in estimated structure damage from $847 thousand to $3.2 million and a corresponding increase in estimated contents damage from $471 thousand to approximately $2.4 million. This corresponds to an increase of $2.4 million (281%) for structures and $1.9 million (407%) for contents. Prior to this analysis, this significant escalation of potential damages based on future development was predicted by county staff and has led to efforts requiring new development to be 1-foot above the one-hundred year base flood elevation, where the BFE includes the increased runoff from the future or ultimate build-out. These results support that effort as the 1-foot requirement would reduce the results of Run 3 to levels more closely resembling the results of the existing development results presented by Run 2 (see Figure 3.5-1). $3,500,000 $3,000,000 Structure Content Estimated Damage (Dollars) $2,500,000 $2,000,000 $1,500,000 $1,000,000 $500,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.5-1. Four Mile Creek and Rocky Branch Watersheds Aggregate Damage Estimation Results 3-73 Table 3.5-2 shows a summary of the building and content damage results by general occupancy classification. In general, Table 3.5-2 shows that the damages are predominantly residential, with only one non-residential structure being impacted in Run 1 and Run 2. While more non-residential structures are impacted in Run 3, the residential damages clearly dominate the total losses. The contents damage by occupancy is dominated by the residential contents damage, reflecting the structure damages above. The results are discussed in greater detail later in this report. Table 3.5-2. Summary of Building and Content Damage by General Occupancy Four Mile Creek and Rocky Branch Watersheds General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) Structural Damage Total Average Total Average Total Average $20,491 $30,388 $30,388 $369,756 $92,439 $70,406 $817,082 $37,140 $2,856,089 $42,628 NonResidential Commercial, Industrial, Religious, Education $20,491 Residential Single and Multi-Family Residential $422,435 Content Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $7,119 $7,119 $14,371 $14,371 $818,610 $204,652 Residential Single and Multi-Family Residential $239,108 $39,851 $456,423 $20,746 $1,572,883 $23,476 3.5.2 Data Analysis 3.5.2.1 Four Mile Creek and the Rocky Branch Basin Characteristics and Study Data Four Mile Creek is a major tributary to McAlpine Creek. Depth grids were created for Four Mile Creek and its tributary, Rocky Branch. The grids depict the depth of flooding that will 3-74 be exceeded with a 1-percent chance in any given year (100-year flood) under both existing and future development conditions. The streams analyzed and the McAlpine Creek basin are shown in Figure 3.5-2. Figure 3.5-2. McAlpine Creek Basin Stream Network The studied reaches include approximately 9.8 miles of Four Mile Creek and approximately 1.6 miles of Rocky Branch. Flood elevation grids were created interpolating between water surface elevations determined at numerous cross sections along the study reaches. In all, 164 cross sections were used: 129 on Four Mile Creek and 35 on Rocky Branch. The flood elevation grids were extended at the upstream end of each stream, at the confluence of Four Mile Creek and Rocky Branch, and at relatively large areas where floodwaters are not conveyed but, rather, pond at the elevation on the main stream. Where the two stream flood elevation grids overlap the final flood elevation grid uses the greater of the two elevations. Although McAlpine Creek was not included in this study, the elevation expected at the confluence of Four Mile and McAlpine Creeks was used for the reach of Four Mile Creek where that elevation was greater than the flood elevation grid for Four Mile Creek. 3-75 Depth grids were created by subtracting the ground elevation in the digital elevation model from the flood elevation at the corresponding cell in the elevation grid. Cells with flood depths less than zero (those outside of the floodplain, for example) were deleted from the flood elevation and flood depth grids. The resulting existing conditions flood depth grid is shown in Figure 3.5-3. Approximately 475 acres are within the 100-year floodplain. Figure 3.5-4 shows the distribution of floodplain area inundated at 1-foot depth increments. The maximum depth is 17.31 feet and the average (mean) depth is 5.27 feet. Approximately 64 acres are inundated at a depth greater than 10 feet. Figure 3.5-3. Existing Conditions Flood Depth Grid: Four Mile Creek and Rocky Branch 3-76 Four Mile Creek Basin 80 Area Inundated (acres) 70 60 50 40 30 20 10 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Flood Depth (feet) Figure 3.5-4. Distribution of Existing Condition Flood Depths: Four Mile Creek and Rocky Branch The future conditions flood depth grid is shown in Figure 3.5-5. Approximately 516 acres are within the 100-year floodplain, an increase of 41 acres or approximately 9 percent. The distribution of floodplain area inundated at various depths is shown in Figure 3.5-6. The maximum depth is 21.62 feet (4.31 feet greater than existing conditions). The mean depth is 6.13 feet (0.86 feet greater than existing conditions). The area inundated by more than 10 feet is approximately 95 acres (31 acres or almost 50 percent more than under existing conditions). 3-77 Figure 3.5-5. Future Conditions Flood Depth Grid Four Mile Creek and Rocky Branch Four Mile Creek Basin 70 Area Inundated (acres) 60 50 40 30 20 10 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Flood Depth (feet) Figure 3.5-6. Distribution of Future Condition Flood Depths Four Mile Creek and Rocky Branch 3-78 Subtracting the existing conditions flood depth grid from the future conditions flood depth grid yields a grid showing the increase in 100-year flood depths expected as a result of development within the basin. That grid is shown in Figure 3.5-7. The distribution of changes in 100-year flood depths is shown in Figure 3.5-8. Note that most (more than 98 percent) of the differences are less than two feet. Most of the increases exceeding 2 feet occur within the Four Mile Creek floodplain upstream of the Old Monroe Road crossing. Figure 3.5-7. Increases in 100-year Flood Depths 3-79 Four Mile Creek Basin 600 Area Affected (acres) 500 400 300 200 100 0 1 2 3 4 5 Difference in Flood Depths (feet) Figure 3.5-8. Differences in 100-year Flood Depths: Four Mile Creek and Rocky Branch 3.5.2.1.1 Four Mile Creek and Rocky Branch Parcel and Building Data Review To identify the parcels and building footprints impacted by Four Mile Creek and the Rocky Branch, the floodplain boundaries from both the 1975 flood study and the 2000 flood study were combined and a buffer of 100-feet added. The buffer was added to ensure that not only those structures and parcels intersecting the parcels were selected, but those that are fairly close are also selected to provide Mecklenburg County with a more complete perspective on the development surrounding Four Mile Creek. There are 1,098 parcels that intersect the floodplain boundary (including the 100-foot buffer) surrounding Four Mile Creek and the Rocky Branch. Some duplicate parcels were identified and reviewed. In all cases, these turned out to be either slivers in the GIS data, most likely right-of-ways that have been either returned to the parcel, or offers of dedication that were never acted upon. In all cases, the slivers were merged back into the main parcel. Of the 1,098 parcels, 182 (17%) are identified as “vacant”. An additional 38 parcels had information in the “effective area” field in the county assessor data indicating that a structure was on the parcel, but had no footprint in the footprint database. Although the percentage of vacant parcels (17% based on 1,098 parcels) does not provide Mecklenburg County the opportunities to manage future development and reduce future 3-80 damage seen in other watersheds, the County should consider reviewing future development conditions. There are 864 building footprints greater than 500 square feet that intersect the floodplain boundary. Of these, 70 were surveyed as part of the master-elevation-certificate surveys, but none were surveyed as part of the “gpsbfe” survey data. Unfortunately, of the 70 data points from the master-elevation-certificate surveys, 5 were missing data in either the first floor elevation or the lowest adjacent grade fields, rendering the data unusable. No additional parcels were matched with survey data from the Flood 3C or Flood 3B survey data. Therefore, a total of 65 of the 864 could be assigned a first floor elevation and lowest adjacent grade from the survey data available. For the analysis, the 38 parcels without a building footprint that were identified as non-vacant based on the square footage in the assessors data, were carried as single structures at the centroid of the parcel for a total of 902 “buildings” in the floodplain (including the 100-foot buffer). For the future conditions or “build-out”, a single structure was placed at the centroid of the 182 vacant parcels identified earlier. This structure was established to have the HAZUS®MH default floor area and value based on the occupancy class assigned to the approved zoning of the parcel (see Tables A-1 and A-2 in Appendix A). Therefore the total “buildings” within the floodplain for the built-out inventory is assumed to be 1,084. 3.5.3 Detailed Results Four Mile Creek and Rocky Branch Basins To determine the potential impacts of floodplain map modifications, three damage estimates have been developed, as follows: 1. Run 1 – current inventory, original floodplain. Estimated losses based on the current building inventory within the Four Mile Creek and Rocky Branch watersheds (developed from surveyed data and parcel data) and the original 100-year floodplain boundary, based on the 1975 flood study. 2. Run 2 – current inventory, new floodplain. Estimated losses based on the current building inventory, expanded to include structures within the new floodplain that were previously outside the floodplain, and the newly revised floodplain boundary. 3-81 3. Run 3 – future inventory, new floodplain. Estimated losses to a projected future inventory that incorporates projected growth (“build out”), relative to the new (2000) floodplain boundary. Table 3.5-3 presents the number of buildings damaged by flooding (i.e., non-zero dollar damage) by occupancy under each of the three scenarios. As noted in Section 2, a HAZUS®MH occupancy class was associated with each occupancy type in the Mecklenburg assessor database. As shown in the figure, the number of damaged buildings increases between runs. The increase in the number of flooded buildings between Run 1 and Run 2 is due to differences in the floodplain boundary between the 1975 flood study and the 2000 flood study map revisions. The increase between Run 2 and Run 3 is attributable to the projected increase in floodplain development. The values shown in Table 3.5-3 are presented to give the reader perspective on the relative number of flooded buildings, which is useful when viewing the subsequent tables. 3-82 Table 3.5-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Four Mile Creek and Rocky Branch Watersheds HAZUS®MH Occupancy Description Code COM1/COM4 Mix of Retail Trade & Professional/Technical Services COM4 Business/Professional/ Technical Services COM8 Entertainment & Recreation RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling, Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement Total No. of flooded buildings Total No. of unflooded buildings Current Inventory, Original Floodplain (Run 1) 0 Current Inventory, New Floodplain (Run 2) 0 Future Inventory, New Floodplain (Run 3) 1 1 1 1 0 0 2 1 6 43 2 9 9 0 2 2 3 5 13 7 23 71 895 879 1,013 The aggregate dollar damage across all building occupancy types is shown in Figure 3.59. As shown, the estimated dollar damage increases from Run 1 to Run 2 and from Run 2 to Run 3. Tables 3.5-4 through 3.5-7 and the associated discussion go into greater detail about the results of the loss estimation. However, it should be noted that the escalation of estimated damage based on future development suggests the need for mitigation measures, such as requiring future development to be 1-foot above the future one hundred year flood elevation (as currently proposed by county staff). 3-83 $3,500,000 $3,000,000 Structure Content Estimated Damage (Dollars) $2,500,000 $2,000,000 $1,500,000 $1,000,000 $500,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.5-9. Four Mile Creek And Rocky Branch Aggregate Damage Estimation Results Table 3.5-4 presents the overall average damage percentage calculated for damaged building structures by occupancy, through the application of the various depth-damage curves. Table 3.5-4 shows that changes in inventory development have relatively minor effects on the average percent damage in Run 3 with the exception of RES1A and RES1E. Slight reductions in the average percent damage may indicate that many of the additional impacted parcels are on the edges of the floodplain. In Runs 1 and 2, most of the average structure damage levels are between 10 and 20 percent. In Run 3, most of the occupancies have structure damage ranges between 10 and 30 percent. 3-84 Table 3.5-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Four Mile Creek and Rocky Branch Watersheds HAZUS®MH Occupancy Description Code COM1/COM4 Mix of Retail Trade & Professional/Technical Services COM4 Business/Professional/ Technical Services COM8 Entertainment & Recreation RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling, Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement Current Inventory, Original Floodplain (Run 1) --- Current Inventory, New Floodplain (Run 2) --- Future Inventory, New Floodplain (Run 3) 21.4 15.3 22.7 22.7 --- --- 11.4 16.9 12.7 26.3 9.5 8.0 8.0 --- 2.0 2.0 35.0 36.3 40.5 Table 3.5-5 shows the dollar damage to building structures that is computed when the damage percentages are multiplied by the structure/parcel valuation. As with the previous table, there are significant differences in the dollar damage between the three scenarios. Between Run 1 and Run 2, there is an increase in total structure damage from $443 thousand to $847 thousand. This corresponds to an increase of $405 thousand, or 91%. As the building inventories used for these scenarios are identical, the difference in damage is attributable to differences in the floodplain between the 1975 flood study and the 2000 revision of the 100-yr floodplain map. Proceeding from Run 2 to Run 3, there is a significant increase in estimated damage from $847 thousand to $3.2 million, suffered by projected development in the floodplain. This corresponds to an increase of $2.4 million, or 280%. It is notable that the primary increases occur in the residential occupancies (RES1A through RES1E). 3-85 Table 3.5-5. Structure Dollar Damage by HAZUS®MH Occupancy Type: Four Mile Creek and Rocky Branch Watersheds HAZUS®MH Occupancy Code COM1/COM4 COM4 Current Inventory, Current Inventory, New Future Inventory, New Original Floodplain Floodplain floodplain (Run 1) (Run 2) (Run 3) Total Avg. Total Avg. Total Avg. --------$89,552 $89,552 $20,490 COM8 $20,490 $30,388 $30,388 $30,388 $30,388 --- --- --- --- $249,816 $124,908 RES1A $19,069 $19,069 $73,414 $12,236 $1,610,742 $37,459 RES1B $23,678 $11,839 $95,139 $10,571 $95,139 $10,571 RES1D --- --- $5,422 $2,711 $5,422 $2,711 RES1E $379,689 $126,563 $643,108 $128,622 $1,144,786 $88,060 $442,926 $63,275 $847,470 $36,847 $3,225,844 $45,434 Total Table 3.5-6 presents the overall average damage percentage calculated for damaged building contents by occupancy type. Similar to the structure damage percent results shown in Table 3.5-4, the difference in the range of contents damage percentages between Run 1 and Run 2 is relatively small, while Run 3 exhibits a large increase over Run 2. In general, the contents damage ranges from 10 to 55 percent. Table 3.5-6. Contents Damage Percent by HAZUS®MH Occupancy Type: Four Mile Creek and Rocky Branch Watersheds HAZUS®MH Occupancy Code COM1/COM4 COM4 COM8 RES1A RES1B RES1D RES1E Description Mix of Retail Trade & Professional/Technical Services Business/Professional/ Technical Services Entertainment & Recreation Single Family Dwelling, 1 Story, No Basement Single Family Dwelling, 2 Story, No Basement Single Family Dwelling, Split Level, No Basement Single Family Dwelling, Split Level, with Basement Current Inventory, Original Floodplain (Run 1) --- Current Inventory, New Floodplain (Run 2) --- Future Inventory, New Floodplain (Run 3) 21.4 10.6 21.5 21.5 --18.9 --13.2 57.1 30.8 9.2 9.3 9.3 --- 4.7 4.7 40.0 40.3 37.6 3-86 Table 3.5-7 provides the estimated dollar damage to building contents by occupancy type. Similar to the structure dollar damage shown in Table 3.5-5, there are significant differences in the dollar damage between scenarios. Between Run 1 and Run 2, there is an increase in total estimated contents damage from $246 thousand to $471 thousand. This corresponds to an increase of $225 thousand, or 91%. The increase in damage is due to changes in the floodplain depth and extent between the 1975 flood study and the recent 2000 revision of the 100-yr floodplain map. Between Run 2 to Run 3, there is a significant increase in estimated damage from $471 thousand to $2.4 million attributable to projected growth. This corresponds to an increase of $1.9 million, or 408%. The total increase in estimated damages (nearly $2 million) warrant the review of mitigation measures. Table 3.5-7. Contents Dollar Damage by HAZUS®MH Occupancy Type Four Mile Creek and Rocky Branch Watersheds HAZUS®MH Occupancy Code COM1/COM4 COM4 COM8 RES1A RES1B RES1D RES1E Total Current Inventory, Current Inventory, New Future Inventory, New Current Floodplain Floodplain Floodplain (Run 1) (Run 2) (Run 3) Total Avg. Total Avg. Total Avg. --------$180,261 $180,268 $7,119 $7,119 $14,371 $14,371 $14,371 $14,371 --------$623,970 $311,985 $10,675 $10,675 $37,988 $6,331 $994,998 $21,977 $11,511 $5,756 $55,169 $6,130 $55,169 $6,130 ----$6,333 $3,166 $6,333 $3,166 $216,922 $72,307 $356,933 $71,387 $566,384 $43,568 $246,277 $35,175 $470,794 3-87 $20,469 $2,391,492 $33,683 DETERMINATION OF FINANCIAL IMPACTS FROM FLOOD STUDIES McDOWELL CREEK WATERSHED (Report Delivered December 2001) Prepared for: MECKLENBURG COUNTY ENGINEERING & BUILDING STANDARDS Charlotte, NC 28202 3.6 McDowell Creek Analysis 3.6.1 Results Summary for the McDowell Creek Basin Two building inventories and two floodplain scenarios maps were combined to develop damage estimates for the three scenarios listed above. Table 3.6-1 shows a summary of the number of flooded buildings by general occupancy classification. The simulation predicted 25, 66, and 159 damaged buildings from Runs 1, 2, and 3, respectively. Table 3.6-1. Number of Flooded Structures by General Occupancy: McDowell Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) NonResidential Commercial, Industrial, Religious, Education 0 0 15 Residential Single and MultiFamily Residential 25 66 144 25 66 159 Total The dollar damage resulting from the analysis is shown on Figure 3.6-1. The damage for each scenario shown in the figure is an aggregate across all building occupancy types. As shown, there is an increase in estimated damage between Run 1 (structure $385 thousand, contents $181 thousand) and Run 2 (structure $2.6 million, contents $1.6 million). This corresponds to an increase of $2.2 million (577%) for structures and $1.4 million (762%) for contents. The increase demonstrates the effect of changes in the floodplain extent and depth between the 1975 flood study and newly revised (2000) floodplain map. Based on the assumption that the revised floodplain map is more accurate than the 1975 flood study, the estimated damage results from Run 2 are representative of current conditions. A comparison of the aggregate damage from Run 2 and Run 3 highlights the difference in damage between current and future building development conditions. For the analysis in Run 3, damage estimates for parcels that are currently vacant were assumed to be 3-88 developed based on their zoning. The result is a sharp increase in estimated structure damage from $2.6 million to $8.8 million and a corresponding increase in estimated contents damage from $1.6 million to approximately $8.1 million. This corresponds to an increase of $6.2 million (238%) for structures and $6.5 million (418%) for contents. Prior to this analysis, this significant escalation of potential damages based on future development was predicted by county staff and has led to efforts requiring new development to be 1-foot above the one-hundred year base flood elevation, where the BFE includes the increased runoff from the future or ultimate build-out. These results support that effort as the 1-foot requirement would reduce the results of Run 3 to levels more closely resembling the results of the existing development results presented by Run 2 (see Figure 3.6-1). $10,000,000 $9,000,000 Structure Content $8,000,000 Estimated Damage (Dollars) $7,000,000 $6,000,000 $5,000,000 $4,000,000 $3,000,000 $2,000,000 $1,000,000 $0 Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.6-1. McDowell Creek Watershed Aggregate Damage Estimation Results 3-89 Table 3.6-2 shows a summary of the building and content damage results by general occupancy classification. In general, Table 3.6-2 shows that initially damages are concentrated in the residential occupancy classification in Runs 1 and 2. While there is a significant increase in the losses to residential occupancies in Run 3 there is also a substantial increase in losses to non-residential occupancies due to “development” of the vacant parcels. As expected for Run 1 and Run 2, the contents damage by occupancy generally increases with increasing building damage. With Run 3, however, the nonresidential content damages exceed the damages resulting from the residential occupancy classification. The results are discussed in greater detail later in this report. Table 3.6-2. Summary of Building and Content Damage by General Occupancy: McDowell Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) Structural Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $0 $0 $0 $0 $2,766,921 $276,921 Residential Single and Multi-Family Residential $385,125 $15,405 $2,607,031 $39,500 $6,046,288 $40,579 Content Damage Total Average Total Average Total Average $0 $0 $0 $4,705,929 $470,593 $7241 $1,560,572 $23,645 $3,375,608 $22,655 NonResidential Commercial, Industrial, Religious, Education $0 Residential Single and Multi-Family Residential $181,029 3-90 3.6.2 Data Analysis 3.6.2.1 McDowell Creek Basin Characteristics and Study Data Depth grids were created for McDowell Creek and six tributaries, including Torrence Creek, contributing flow to McDowell Creek. The grids depict the depth of flooding that will be exceeded with a 1-percent chance in any given year (100-year flood) under both existing and future development conditions. The network of streams analyzed is shown in Figure 3.6-2. Figure 3.6-2. McDowell Creek Basin Stream Network The studied reaches include approximately 9.2 miles of McDowell Creek and approximately 10.9 miles of tributary reaches. Flood elevation grids were created interpolating between water surface elevations determined at numerous cross sections along the study reaches. In all, 266 cross sections were used: 119 on McDowell Creek and 147 on the tributaries. The flood elevation grids were extended at the upstream end of each stream, at the confluence with each tributary, and at relatively large areas where floodwaters are not conveyed but, 3-91 rather, pond at the elevation on the main stream. Where two stream flood elevation grids overlap, the final flood elevation grid uses the greater of the two elevations. Depth grids were created by subtracting the ground elevation in the digital elevation model from the flood elevation at the corresponding cell in the elevation grid. Cells with flood depths less than zero (those outside of the floodplain, for example) were deleted from the flood elevation and flood depth grids. The resulting existing conditions flood depth grid is shown in Figure 3.6-3. Approximately 1270 acres are within the 100-year floodplain. Figure 3.6-4 shows the distribution of floodplain area inundated at 1-foot depth increments. The maximum depth is 22.25 feet and the average (mean) depth is 5.06 feet. Approximately 160 acres are inundated at a depth greater than 10 feet. The future conditions flood depth grid is shown in Figure 3.6-5. Approximately 1440 acres are within the 100-year floodplain, an increase of 170 acres or approximately 13 percent. Figure 3.6-3. Existing Conditions Flood Depth Grid McDowell Creek Watershed 3-92 McDowell Creek Basin 200 180 160 140 120 100 80 60 40 20 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Flood Depth (feet) Figure 3.6-4. Distribution of Existing Condition Flood Depths McDowell Creek Watershed The distribution of floodplain area inundated at various depths is shown in Figure 3.6-6. The maximum depth is 27.71 feet (5.46 feet greater than existing conditions). The mean depth is 6.31 feet (1.25 feet greater than existing conditions). The area inundated by more than 10 feet is approximately 340 acres (180 acres or more than double the existing conditions). 3-93 Figure 3.6-5. Future Conditions Flood Depth Grid McDowell Creek Watershed McDowell Creek Basin 200 Area Inundated (acres) 180 160 140 120 100 80 60 40 20 0 1 3 5 7 9 11 13 15 17 19 21 23 25 27 Flood Depth (feet) Figure 3.6-6. Distribution of Future Condition Flood Depths McDowell Creek Watershed 3-94 Subtracting the existing conditions flood depth grid from the future conditions flood depth grid yields a grid showing the increase in 100-year flood depths expected as a result of development within the basin. That grid is shown in Figure 3.6-7. The distribution of changes in 100-year flood depths is shown in Figure 3.6-8. Note that most (approximately 95 percent) of the differences are less than three feet, and two-thirds of those are less than two feet. Most of the increases exceeding 2 feet occur within the McDowell Creek floodplain downstream of the confluence with Torrence Creek. The areas with increases exceeding 2 and 3 feet are within the floodplains of the two tributaries to Torrence Creek upstream of the Interstate 77 crossings. Figure 3.6-7. Increases in 100-year Flood Depths McDowell Creek Watershed 3-95 McDowell Creek Basin 600 500 400 300 200 100 0 1 2 3 4 5 6 7 8 9 10 11 12 13 Difference in Flood Depths (feet) Figure 3.6-8. Differences in 100-year Flood Depths McDowell Creek Watershed 3.6.2.1.1 McDowell Creek Parcel and Building Data Review To determine the parcels and building footprints impacted by inundation from McDowell Creek, the floodplain boundaries from both the 1975 flood study and the 2000 flood study were combined and a buffer of 100-feet added. The buffer was added to ensure that not only those structures and parcels intersecting the parcels were selected, but those that are fairly close were also selected to provide Mecklenburg County with a more complete perspective on the development surrounding McDowell Creek. There are 1,657 parcels that intersect the floodplain boundary (including the 100-foot buffer) surrounding McDowell Creek. Some duplicate parcels were identified and reviewed. In all cases, these turned out to be slivers in the GIS data, most likely right-ofways that have been either returned to the parcel, or offers of dedication that were never acted upon. In all cases, the slivers were merged back into the main parcel. Of the 1,657 parcels, 454 (27%) are identified as “vacant”, and an additional 17 parcels had information in the “effective area” field in the county assessor data indicating that a structure was on the parcel, although no building footprint was available. The percentage of vacant parcels (27% based on 1,657 parcels) provides Mecklenburg County with significant opportunities to manage future development and reduce future damage within the watershed. 3-96 There are 971 building footprints greater than 500 square feet that intersect the floodplain boundary. Of these, 59 were surveyed as part of the master-elevation-certificate surveys, but none were surveyed as part of the “gpsbfe” survey data. Unfortunately, of the 59 data points from the master-elevation-certificate surveys, 5 were missing data in either the first floor elevation or the lowest adjacent grade fields rendering the data unusable. Therefore, a total of 54 of the 971 were assigned a first floor elevation and lowest adjacent grade from the survey data available. For the analysis, the 17 parcels without a building footprint that were identified as non-vacant based on the square footage in the assessors data were carried as single structures at the centroid of the parcel, for a total of 988 “buildings” in the floodplain (including the 100-foot buffer). For the future conditions or “build-out”, a single structure was placed at the centroid of the 454 vacant parcels identified earlier. ®MH HAZUS This structure was established to have the default floor area and value based on the occupancy class assigned to the approved zoning of the parcel (see Tables A-1 and A-2 in Appendix A). Therefore the total “buildings” within the floodplain for the built-out inventory is assumed to be 1,442. 3.6.3 Detailed Results for the McDowell Creek Basin To determine the potential impacts of floodplain map modifications, three damage estimates have been developed, as follows: 1. Run 1 – current inventory, original floodplain. Estimated losses based on the current building inventory within the McDowell Creek watershed (developed from surveyed data and parcel data) and the original 100-year floodplain boundary, based on the 1975 flood study. 2. Run 2 – current inventory, new floodplain. Estimated losses based on the current building inventory, expanded to include structures within the new floodplain that were previously outside the floodplain, and the newly revised floodplain boundary. 3. Run 3 – future inventory, new floodplain. Estimated losses to a projected future inventory that incorporates projected growth (“build out”), relative to the new (2000) floodplain boundary. 3-97 Table 3.6-3 presents the number of buildings damaged by flooding (i.e., non-zero dollar damage) by occupancy under each of the three scenarios. As noted in Section 2, a HAZUS®MH occupancy class was associated with each occupancy type in the Mecklenburg assessor database. As shown in the figure, the number of damaged buildings increases between runs for the majority of building types. The increase in the number of flooded buildings between Run 1 and Run 2 is due to differences in the floodplain boundary between the 1975 flood study and the 2000 flood study map revisions. The increase between Run 2 and Run 3 is attributable to the projected increase in floodplain development. The values shown in Table 3.6-3 are presented to give the reader perspective on the relative number of flooded buildings, which is useful when viewing the subsequent tables. Table 3.6-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: McDowell Creek Watershed HAZUS®MH Occupancy Code Description COM1/COM4 Mix of Retail Trade & Professional/Technical Services COM8 Entertainment & Recreation IND2/IND6 Mix of Light Industrial & Construction RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling, Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement RES3 Multi-Family Dwelling Total No. of flooded buildings Total No. of unflooded buildings Current Inventory, Original Floodplain (Run 1) --- Current Inventory, New Floodplain (Run 2) --- Future Inventory, New Floodplain (Run 3) 7 --- --- 1 --- --- 2 6 14 79 13 31 31 2 2 2 4 14 32 --25 5 66 5 159 963 922 1,283 3-98 The aggregate dollar damage across all building occupancy types is shown in Figure 3.69. As shown, the estimated dollar damage increases from Run 1 to Run 2 and from Run 2 to Run 3. Tables 3.6-4 through 3.6-7 and the associated discussion go into greater detail about the results of the loss estimation. However, it should be noted that the escalation of estimated damage based on future development suggests the need for mitigation measures, such as requiring future development to be 1-foot above the future one hundred year flood elevation (as currently proposed by county staff). $10,000,000 $9,000,000 Structure Content $8,000,000 Estimated Damage (Dollars) $7,000,000 $6,000,000 $5,000,000 $4,000,000 $3,000,000 $2,000,000 $1,000,000 $0 Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.6-9. McDowell Creek Watershed Aggregate Damage Estimation Results Table 3.6-4 presents the overall average damage percentage calculated for building structures by occupancy, through the application of the various depth-damage curves. Table 3.6-4 shows that changes in inventory development have minor impacts on the average percent damage for most residential occupancy classifications, but development greatly increases the average damage percentage in the non-residential classification 3-99 (Run 3). Slight reductions in the average percent damage may indicate increased impact on parcels that are on the edges of the floodplain. In Runs 1 and 2, most of the average structure damage levels are between 8 and 30 percent. In Run 3, most of the occupancies have structure damage ranges between 12 and 70 percent. It is notable that structure damage over 50% of market value is considered “substantial damage”3 by the Federal Insurance and Mitigation Administration. Structures receiving over 50% estimated damage are likely to be excellent acquisition candidates. Table 3.6-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: McDowell Creek Watershed HAZUS®MH Occupancy Description Code COM1/COM4 Mix of Retail Trade & Professional/Technical Services COM8 Entertainment & Recreation IND2/IND6 Mix of Light Industrial & Construction RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling, Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement RES3 Multi-Family Dwelling Current Inventory, Original Floodplain (Run 1) --- Current Inventory, New Floodplain (Run 2) --- Future Inventory, New Floodplain (Run 3) 68.1 --- --- 8.0 --- --- 26.1 15.5 22.9 24.5 8.4 13.5 13.5 11.4 14.8 14.8 31.9 34.3 38.4 --- 18.7 18.7 Table 3.6-5 shows the dollar damage to building structures that is computed when the individual building damage percentages are multiplied by the structure/parcel valuation. As with the previous table, there are significant differences in the dollar damage between the three scenarios. Between Run 1 and Run 2, there is an increase in total structure damage from $385 thousand to $2.6 million. This corresponds to an increase of $2.2 million, or 577%. As the building inventories used for these scenarios are identical, the 3 According to NFIP guidelines, structures suffering “substantial damage” must be brought up to current floodplain management standards for new (post-FIRM) construction (i.e., removed from the 3-100 difference in damage is attributable to differences in the floodplain between the 1975 flood study and the 2000 revision of the 100-yr floodplain map. Proceeding from Run 2 to Run 3, there is a significant increase in estimated damage from $2.6 million to $8.8 million, suffered by projected development in the floodplain. This corresponds to an increase of $6.2 million, or 762%. It is notable that Run 3 has large increases in the losses to nonresidential occupancies attributable to future development, additionally, there is a significant increase in the single-family residential occupancy classification. Table 3.6-5. Structure Dollar Damage by HAZUS®MH Occupancy Type McDowell Creek Watershed HAZUS®MH Occupancy Code COM1/COM4 COM8 IND2/IND6 RES1A RES1B RES1D RES1E RES3 Total Current Inventory, Current Inventory, New Future Inventory, New Original Floodplain Floodplain floodplain (Run 1) (Run 2) (Run 3) Total Avg. Total Avg. Total Avg. --------$1,991,394 $284,485 --------$87,463 $87,463 --------$688,064 $344,032 $89,272 $14,879 $328,632 $23,474 $2,678,708 $33,908 $116,914 $8,993 $669,171 $21,586 $669,171 $21,586 $29,184 $14,592 $38,038 $19,019 $38,038 $19,019 $149,755 $37,439 $1,030,274 $73,591 $2,199,456 $66,233 ----$540,916 $108,183 $540,916 $108,183 $385,125 $15,405 $2,607,031 $39,500 $8,813,209 $55,429 Table 3.6-6 presents the overall average damage percentage calculated for building contents by occupancy type. Similar to the structure damage percent results shown in Table 3.6-5, the difference in the range of contents damage percentages between Run 1 and Run 2 is relatively small, ranging from 10 to 30 percent. Run 3 exhibits a large increase over Run 2, notably in the non-residential occupancies. Damages in the residential occupancies do not vary much between Run 2 and Run 3. Overall, the estimated damage percent ranges between 15 and 40 percent. Table 3.6-6. Contents Damage Percent by HAZUS®MH Occupancy Type McDowell Creek Watershed Current Inventory, Current Inventory, Future Inventory, flood hazard area or elevated to or above the level of the base flood elevation, or floodproofed if it is nonresidential). 3-101 HAZUS®MH Occupancy Code Description COM1/COM4 Mix of Retail Trade & Professional/Technical Services COM8 Entertainment & Recreation IND2/IND6 Mix of Light Industrial & Construction RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling, Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement RES3 Multi-Family Dwelling Original Floodplain (Run 1) --- New Floodplain (Run 2) --- New Floodplain (Run 3) 42.3 --- --- 35.5 --- --- 38.2 17.2 27.1 28.3 9.7 17.4 17.4 14.7 16.1 16.1 21.3 32.9 34.3 --- 29.7 29.7 Table 3.6-7 provides the estimated dollar damage to building contents by occupancy type. Similar to the structure dollar damage shown in Table 3.6-5, there are significant differences in the dollar damage between scenarios. Between Run 1 and Run 2, there is an increase in total estimated contents damage from $181 thousand to $1.6 million. This corresponds to an increase of $1.4 million, or 762%. The increase in damage is due to changes in the floodplain depth and extent between the 1975 flood study and the recent 2000 revision of the 100-yr floodplain map. Between Run 2 to Run 3, there is a significant increase in estimated damage from $1.6 million to $8.1 million attributable to projected growth. This corresponds to an increase of $6.5 million, or 418%. The overall increase in contents damage is relatively large (400 percentile), and the total estimated damages (over $8.1 million) warrant the review of mitigation measures. 3-102 Table 3.6-7. Contents Dollar Damage by HAZUS®MH Occupancy Type McDowell Creek Watershed HAZUS®MH Occupancy Code COM1/COM4 COM8 IND2/IND6 RES1A RES1B RES1D RES1E RES3 Total Current Inventory, Current Inventory, New Future Inventory, New Current Floodplain Floodplain Floodplain (Run 1) (Run 2) (Run 3) Total Avg. Total Avg. Total Avg. --------$4,008,677 $572,668 --------$194,186 $194,186 --------$503,066 $251.533 $48,936 $8,156 $200,247 $14,303 $1,551,313 $19,637 $64,795 $4,984 $440,781 $14,219 $440,781 $14,219 $18,874 $9,437 $20,790 $10,395 $20,790 $10,395 $48,424 $12,106 $525,008 $37,501 $988,978 $30,906 ----$373,746 $74,749 $373,746 $74,749 $181,029 $7,241 $1,560,572 3-103 $23,645 $8,081,537 $50,827 DETERMINATION OF FINANCIAL IMPACTS FROM FLOOD STUDIES McMULLEN CREEK WATERSHED (Report Delivered December 2001) Prepared for: MECKLENBURG COUNTY ENGINEERING & BUILDING STANDARDS Charlotte, NC 28202 3.7 3.7.1 McMullen Creek Analysis Results Summary for the McMullen Creek Basin Two building inventories and two floodplain scenarios maps were combined to develop damage estimates for the three scenarios listed above. Table 3.7-1 shows a summary of the number of flooded buildings by general occupancy classification. The simulation predicted 115, 159, and 205 damaged buildings from Runs 1, 2, and 3, respectively. Table 3.7-1. Number of Flooded Structures by General Occupancy: McMullen Creek Watershed General Occupancy Description NonResidential Commercial, Industrial, Religious, Education Residential Single and MultiFamily Residential Total Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) 3 7 10 112 152 195 115 159 205 The dollar damage resulting from the analysis is shown on Figure 3.7-1. The damage for each scenario shown in the figure is an aggregate across all building occupancy types. As shown, there is an increase in estimated damage between Run 1 (structure $2.1 million, contents $1.2 million) and Run 2 (structure $3.6 million, contents $2.1 million). This corresponds to an increase of $1.5 million (70%) for structures and $852 thousand (69%) for contents. The increase demonstrates the effect of changes in the floodplain extent and depth between the 1975 flood study and newly revised (2000) floodplain map. Based on the assumption that the revised floodplain map is more accurate than the 1975 flood study, the estimated damage results from Run 2 are representative of current conditions. A comparison of the aggregate damage from Run 2 and Run 3 highlights the difference in damage between current and future building development conditions. For the analysis in Run 3, damage estimates for parcels that are currently vacant were assumed to be 3-104 developed based on their zoning. The result is a sharp increase in estimated structure damage from $3.6 million to $7.5 million and a corresponding increase in estimated contents damage from $2.1 million to approximately $5.2 million. This corresponds to an increase of $3.8 million (106%) for structures and $3.1 million (150%) for contents. Prior to this analysis, this significant escalation of potential damages based on future development was predicted by county staff and has led to efforts requiring new development to be 1-foot above the one-hundred year base flood elevation, where the BFE includes the increased runoff from the future or ultimate build-out. These results support that effort as the 1-foot requirement would reduce the results of Run 3 to levels more closely resembling the results of the existing development results presented by Run 2 (see Figure 3.7-1). $8,000,000 $7,000,000 Structure Content Estimated Damage (Dollars) $6,000,000 $5,000,000 $4,000,000 $3,000,000 $2,000,000 $1,000,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.7-1. McMullen Creek Watershed Aggregate Damage Estimation Results 3-105 Table 3.7-2 shows a summary of the building and content damage results by general occupancy classification. In general, Table 1-2 shows that initially damages are concentrated in the residential occupancy classification in Runs 1 and 2. While there is a significant increase in the losses to residential occupancies in Run 3, there is substantial “development” of vacant parcels zoned for non-residential occupancies increasing losses in this general occupancy class to nearly one-third of the total losses (structure and content). As expected for Run 1 and Run 2, the contents damage by occupancy generally increases with increasing building damage. With Run 3, however, the non-residential content damages become a significant percentage of the overall contents damage. The results are discussed in greater detail later in this report. Table 3.7-2. Summary of Building and Content Damage by General Occupancy: McMullen Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) Structural Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $105,083 $35,028 $153,089 $21,870 $1,759,865 $175,986 Residential Single and Multi-Family Residential $2,036,883 $18,186 $3,491,773 $22,972 $5,731,306 $29,391 Content Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $106,928 $35,643 $176,381 $25,197 $2,201,389 $220,139 Residential Single and Multi-Family Residential $1,124,836 $10,043 $1,908,588 $12,557 $3,011,254 $15,442 3-106 3.7.2 Data Analysis 3.7.2.1 McMullen Creek Basin Characteristics and Study Data McMullen Creek is a major tributary to McAlpine Creek. Depth grids were created for McMullen Creek and McMullen Creek Tributary. The grids depict the depth of flooding that will be exceeded with a 1-percent chance in any given year (100-year flood) under both existing and future development conditions. The streams analyzed and the McAlpine Creek basin are shown in Figure 3.7-2. Figure 3.7-2. McAlpine Creek Basin Stream Network McMullen Creek Watershed The studied reaches include approximately 10.9 miles of McMullen Creek and approximately 0.7 mile of McMullen Creek Tributary. Flood elevation grids were created interpolating between water surface elevations determined at numerous cross sections along the study reaches. In all, 180 cross sections were used: 163 on McMullen Creek and 17 on McMullen Creek Tributary. The flood elevation grids were extended at the upstream end of each stream, at the confluence of McMullen Creek and the tributary, and at relatively large areas where 3-107 floodwaters are not conveyed but, rather, pond at the elevation on the main stream. Where the two stream flood elevation grids overlap the final flood elevation grid uses the greater of the two elevations. Although McAlpine Creek was not included in this study, the elevation expected at the confluence of McMullen and McAlpine Creeks was used for the reach of McMullen Creek where that elevation was greater than the flood elevation grid for McMullen Creek. Depth grids were created by subtracting the ground elevation in the digital elevation model from the flood elevation at the corresponding cell in the elevation grid. Cells with flood depths less than zero (those outside of the floodplain, for example) were deleted from the flood elevation and flood depth grids. The resulting existing conditions flood depth grid is shown in Figure 3.7-4. Approximately 650 acres are within the 100-year floodplain. Figure 3.7-5 shows the distribution of floodplain area inundated at 1-foot depth increments. The maximum depth is 26.68 feet occurring near the confluence with McAlpine Creek The average (mean) depth is 5.56 feet. Approximately 75 acres are inundated at a depth greater than 10 feet. 3-108 Figure 3.7-3. Existing Conditions Flood Depth Grid McMullen Creek Watershed McMullen Creek Basin 80 70 60 50 40 30 20 10 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 Flood Depth (feet) Figure 3.7-4. Distribution of Existing Condition Flood Depths McMullen Creek Watershed 3-109 The future conditions flood depth grid is shown in Figure 3.7-5. Approximately 685 acres are within the 100-year floodplain, an increase of 35 acres or approximately 5 percent. The distribution of floodplain area inundated at various depths is shown in Figure 3.7-6. The maximum depth is 28.28 feet (1.6 feet greater than existing conditions). The mean depth is 6.01 feet (0.45 foot greater than existing conditions). The area inundated by more than 10 feet is approximately 108 acres (33 acres or 44 percent more than under existing conditions). Figure 3.7-5. Future Conditions Flood Depth Grid McMullen Creek Watershed 3-110 McMullen Creek Basin 80 70 60 50 40 30 20 10 0 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 Flood Depth (feet) Figure 3.7-6. Distribution of Future Condition Flood Depths McMullen Creek Watershed Subtracting the existing conditions flood depth grid from the future conditions flood depth grid yields a grid showing the increase in 100-year flood depths expected as a result of development within the basin. That grid is shown in Figure 3.7-7. The distribution of changes in 100-year flood depths is shown in Figure 3.7-8. Note that, as indicated in Figure 3.7-7, the differences are less than two feet. Most of the increases exceeding 1 foot occur near the confluence with McAlpine Creek. Those increases result from the increase in the backwater elevations from McAlpine Creek. 3-111 Figure 3.7-7. Increases in 100-year Flood Depths McMullen Creek Watershed McMullenCreek Basin 600 500 400 300 200 100 0 1 2 Difference in Flood Depths (feet) Figure 3.7-8. Differences in 100-year Flood Depths McMullen Creek Watershed 3-112 3.7.2.1.1 McMullen Creek Parcel and Building Data Review To determine the parcels and building footprints impacted by inundation from McMullen Creek, the floodplain boundaries from both the 1975 flood study and the 2000 flood study were combined and a buffer of 100-feet added. The buffer was added to ensure that not only those structures and parcels intersecting the parcels were selected, but those that are fairly close were also selected to provide Mecklenburg County with a more complete perspective on the development surrounding McMullen Creek. There are 1,427 parcels that intersect the floodplain boundary (including the 100-foot buffer) surrounding McMullen Creek. Some duplicate parcels were identified and reviewed. In all cases, these turned out to be slivers in the GIS data, most likely right-ofways that have been either returned to the parcel, or offers of dedication that were never acted upon. In all cases, the slivers were merged back into the main parcel. Of the 1,427 parcels, 95 (6.7%) are identified as “vacant”, and an additional 102 parcels had information in the “effective area” field in the county assessor data indicating that a structure was on the parcel, although no building footprint was available. The percentage of vacant parcels (6.7% based on 1,427 parcels) shows that Mecklenburg County has only a few opportunities left to manage future development and reduce future damage within the watershed. There are 1,592 building footprints greater than 500 square feet that intersect the floodplain boundary. Of these, 125 were surveyed as part of the master-elevation- certificate surveys, and an additional 192 were surveyed as part of the “gpsbfe” survey data. Unlike other watersheds, only one (1) of the 125 data points from the masterelevation-certificate surveys was missing data in either the first floor elevation or the lowest adjacent grade fields rendering the data unusable. Of the “gpsbfe” survey data points, all contained sufficient data for utilization in the study. For the analysis, the 102 parcels without a building footprint that were identified as non-vacant based on the square footage in the assessors data were carried as single structures at the centroid of the parcel, for a total of 1,694 “buildings” in the floodplain (including the 100-foot buffer). For the future conditions or “build-out”, a single structure was placed at the centroid of the 95 vacant parcels identified earlier. This structure was established to have the HAZUS®MH default floor area and value based on the occupancy class assigned to the approved 3-113 zoning of the parcel (see Tables A-1 and A-2 in Appendix A). Therefore the total “buildings” within the floodplain for the built-out inventory is assumed to be 1,789. 3.7.3 Detailed Results for the McMullen Creek Basin To determine the potential impacts of floodplain map modifications, three damage estimates have been developed, as follows: 1. Run 1 – current inventory, original floodplain. Estimated losses based on the current building inventory within the McMullen Creek watershed (developed from surveyed data and parcel data) and the original 100-year floodplain boundary, based on the 1975 flood study. 2. Run 2 – current inventory, new floodplain. Estimated losses based on the current building inventory, expanded to include structures within the new floodplain that were previously outside the floodplain, and the newly revised floodplain boundary. 3. Run 3 – future inventory, new floodplain. Estimated losses to a projected future inventory that incorporates projected growth (“build out”), relative to the new (2000) floodplain boundary. Table 3.7-3 presents the number of buildings damaged by flooding (i.e., non-zero dollar damage) by occupancy under each of the three scenarios. As noted in Section 2, a HAZUS®MH occupancy class was associated with each occupancy type in the Mecklenburg assessor database. As shown in the figure, the number of damaged buildings increases between runs for the majority of building types. The increase in the number of flooded buildings between Run 1 and Run 2 is due to differences in the floodplain boundary between the 1975 flood study and the 2000 flood study map revisions. The increase between Run 2 and Run 3 is attributable to the projected increase in floodplain development. The values shown in Table 3.7-3 are presented to give the reader perspective on the relative number of flooded buildings, which is useful when viewing the subsequent tables. 3-114 Table 3.7-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: McMullen Creek Watershed HAZUS®MH Occupancy Description Code COM1/COM4 Mix of Retail Trade & Professional/Technical Services COM2 Wholesale Trade COM4 Business Professional Technical COM8 Entertainment & Recreation IND2/IND6 Mix of Light Industrial & Construction REL1 Religious RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling, Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement RES3 Multi-Family Dwelling Total No. of flooded buildings Total No. of unflooded buildings Current Inventory, Original Floodplain (Run 1) 0 Current Inventory, New Floodplain (Run 2) 1 Future Inventory, New Floodplain (Run 3) 1 0 0 1 0 1 2 2 2 2 1 2 3 0 35 1 44 1 75 26 35 35 19 27 27 10 16 27 22 115 30 159 31 205 1,579 1,535 1,584 The aggregate dollar damage across all building occupancy types is shown in Figure 3.79. As shown, the estimated dollar damage increases from Run 1 to Run 2 and from Run 2 to Run 3. Tables 3.7-4 through 3.7-7 and the associated discussion go into greater detail about the results of the loss estimation. However, it should be noted that the escalation of estimated damage based on future development suggests the need for mitigation measures, such as requiring future development to be 1-foot above the future one hundred year flood elevation (as currently proposed by county staff). 3-115 $8,000,000 $7,000,000 Structure Content Estimated Damage (Dollars) $6,000,000 $5,000,000 $4,000,000 $3,000,000 $2,000,000 $1,000,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.7-9. McMullen Creek Watershed Aggregate Damage Estimation Results Table 3.7-4 presents the overall average damage percentage calculated for building structures by occupancy, through the application of the various depth-damage curves. Table 3.7-4 shows that changes in inventory development have minor impacts on the average percent damage for most residential occupancy classifications (except RES1A), but development greatly increases the average damage percentage in the non-residential classification (Run 3). In Runs 1 and 2, most of the average structure damage levels range widely between 4 and 50 percent. This trend is continued in Run 3, where most of the occupancies have structure damage ranges between 4 and 50 percent, but development has increased the number of structures impacted. It is notable that structure damage over 50% of market value is considered “substantial damage”4 by the Federal 4 According to NFIP guidelines, structures suffering “substantial damage” must be brought up to current floodplain management standards for new (post-FIRM) construction (i.e., removed from the flood hazard area or elevated to or above the level of the base flood elevation, or floodproofed if it is nonresidential). 3-116 Insurance and Mitigation Administration. Structures receiving over 50% estimated damage are likely to be excellent acquisition candidates. Table 3.7-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: McMullen Creek Watershed HAZUS®MH Occupancy Code Description COM1/COM4 Mix of Retail Trade & Professional/Technical Services COM2 Wholesale Trade COM4 Business Professional Technical COM8 Entertainment & Recreation IND2/IND6 Mix of Light Industrial & Construction REL1 Religious RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling, Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement RES3 Multi-Family Dwelling Current Inventory, Original Floodplain (Run 1) --- Current Inventory, New Floodplain (Run 2) 2.5 Future Inventory, New Floodplain (Run 3) 2.5 ----- 0.2 --- 0.2 45.3 50.1 52.4 52.3 21.9 17.6 27.4 --14.8 1.1 18.5 1.1 24.0 9.1 9.9 9.9 4.8 6.8 6.8 30.4 30.2 37.6 11.8 16.5 17.0 Table 3.7-5 shows the dollar damage to building structures that is computed when the individual building damage percentages are multiplied by the structure/parcel valuation. As with the previous table, there are significant differences in the dollar damage between the three scenarios. Between Run 1 and Run 2, there is an increase in total structure damage from $2.1 million to $3.6 million. This corresponds to an increase of $1.5 million, or 70%. As the building inventories used for these scenarios are identical, the difference in damage is attributable to differences in the floodplain between the 1975 flood study and the 2000 revision of the 100-yr floodplain map. Proceeding from Run 2 to Run 3, there is a significant increase in estimated damage from $2.6 million to $8.8 million, suffered by projected development in the floodplain. This corresponds to an increase of $3.8 million, 3-117 or 106%. It is notable that Run 3 has large increases in damages across nearly every occupancy classification. Table 3.7-5. Structure Dollar Damage by HAZUS®MH Occupancy Type McMullen Creek Watershed Current Inventory, Current Inventory, New Future Inventory, New HAZUS®MH Original Floodplain Floodplain floodplain Occupancy (Run 1) (Run 2) (Run 3) Code Total Avg. Total Avg. Total Avg. COM1/COM4 ----$19,812 $19,812 $19,812 $19,812 COM2 ----$30 $30 $30 $30 COM4 ----$57,975 $28,988 $988,293 $494,146 COM8 $55,501 $27,750 $71,121 $35,560 $57,975 $28,988 IND2/IND6 $49,582 $49,582 $71,121 $35,560 $689,604 $229,868 REL1 ----$4,152 $4,152 $4,152 $4,152 RES1A $491,070 $14,031 $786,575 $17,877 $2,228586 $29,714 RES1B $383,836 $14,763 $538,353 $15,382 $538,353 $15,382 RES1D $110,595 $5,821 $217,491 $8,055 $217,491 $8,055 RES1E $349,003 $34,900 $542,873 $33,930 $1,316,824 $48,771 RES3 $702,379 $31,926 $1,406.480 $46,883 $1,430,051 $46,131 Total $2,141,966 $18,626 $3,644,863 $22,924 $7,491,171 $36,542 Table 3.7-6 presents the overall average damage percentage calculated for building contents by occupancy type. Similar to the structure damage percent results shown in Table 3.7-4, the difference in the range of contents damage percentages between Run 1 and Run 2 is varies over a large range from 7 to 50 percent. Run 3 exhibits similarities to Run 2 with slight increases on many of the residential occupancies, but with large increases in the non-residential occupancies. Overall, the average estimated contents damage percent ranges between 1 and 50 percent. 3-118 Table 3.7-6. Contents Damage Percent by HAZUS®MH Occupancy Type McMullen Creek Watershed HAZUS®MH Occupancy Description Code COM1/COM4 Mix of Retail Trade & Professional/Technical Services COM2 Wholesale Trade COM4 Business Professional Technical COM8 Entertainment & Recreation IND2/IND6 Mix of Light Industrial & Construction REL1 Religious RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling, Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement RES3 Multi-Family Dwelling Current Inventory, Original Floodplain (Run 1) --- Current Inventory, New Floodplain (Run 2) 2.5 Future Inventory, New Floodplain (Run 3) 2.5 ----- 0.2 --- 0.2 41.7 50.1 52.4 52.4 29.7 25.3 40.5 --16.3 1.1 21.5 1.1 28.0 10.5 11.4 11.4 7.4 10.3 10.3 27.2 28.0 29.0 11.7 16.1 17.0 Table 3.7-7 provides the estimated dollar damage to building contents by occupancy type. Similar to the structure dollar damage shown in Table 3.7-5, there are significant differences in the dollar damage between scenarios. Between Run 1 and Run 2, there is an increase in total estimated contents damage from $1.2 million to $2.1 million. This corresponds to an increase of $852 thousand, or 69%. The increase in damage is due to changes in the floodplain depth and extent between the 1975 flood study and the recent 2000 revision of the 100-yr floodplain map. Between Run 2 to Run 3, there is a significant increase in estimated damage from $2.1 million to $5.2 million attributable to projected growth. This corresponds to an increase of $3.1 million, or 150%. The overall increase in contents damage is relatively large (150 percentile), and the total estimated damages (over $5.2 million) warrant the review of mitigation measures. 3-119 Table 3.7-7. Contents Dollar Damage by HAZUS®MH Occupancy Type McMullen Creek Watershed HAZUS®MH Occupancy Code COM1/COM4 COM2 COM4 COM8 IND2/IND6 REL1 RES1A RES1B RES1D RES1E RES3 Current Inventory, Current Inventory, New Future Inventory, New Current Floodplain Floodplain Floodplain (Run 1) (Run 2) (Run 3) Total Avg. Total Avg. Total Avg. ----$39,881 $39,881 $39,881 $39,881 ----$103 $103 $103 $103 --------$1,558,131 $779,065 $73,261 $36,630 $76,527 $38,264 $76,527 $38,264 $33,668 $33,668 $53,766 $26,883 $520,643 $173,578 ----$6,103 $6,103 $6,103 $6,103 $264,890 $7,568 $459,203 $10,436 $1,302,487 $17,366 $217,653 $8,371 $309,772 $8,851 $309,722 $8,851 $83,846 $4,413 $165,500 $6,130 $165,500 $6,130 $178,497 $17,850 $271,367 $16,960 $515,466 $19,091 $379,949 $17,270 $702,746 $23,425 $718,030 $23,162 Total $1,231,764 $10,711 $2,084,969 3-120 $13,113 $5,212,643 $25,428 DETERMINATION OF FINANCIAL IMPACTS FROM FLOOD STUDIES MCKEE CREEK WATERSHED (Report Delivered January 2002) Prepared for: MECKLENBURG COUNTY ENGINEERING & BUILDING STANDARDS Charlotte, NC 28202 3.8 3.8.1 McKee Creek Analysis Results Summary for the McKee Creek Basin Two building inventories and two floodplain scenarios maps were combined to develop damage estimates for the three scenarios listed above. Table 3.8-1 shows a summary of the number of flooded buildings by general occupancy classification. The simulation predicted 2, 23, and 62 damaged buildings from Runs 1, 2, and 3, respectively. Table 3.8-1. Number of Flooded Structures by General Occupancy: McKee Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) NonResidential Commercial, Industrial, Religious, Education 0 0 0 Residential Single and MultiFamily Residential 2 23 62 2 23 62 Total The dollar damage resulting from the analysis is shown on Figure 3.8-1. The damage for each scenario shown in the figure is an aggregate across all building occupancy types. As shown, there is an increase in estimated damage between Run 1 (structure $8.2 thousand, contents $3.7 thousand) and Run 2 (structure $217 thousand, contents $112 thousand). This corresponds to an increase of $209 thousand (2,548%) for structures and $108 thousand (2,928%) for contents. The increase demonstrates the effect of changes in the floodplain extent and depth between the 1975 flood study and newly revised (2000) floodplain map. Based on the assumption that the revised floodplain map is more accurate than the 1975 flood study, the estimated damage results from Run 2 are representative of current conditions. A comparison of the aggregate damage from Run 2 and Run 3 highlights the difference in damage between current and future building development conditions. For the analysis in Run 3, damage estimates for parcels that are currently vacant were assumed to be 3-121 developed based on their zoning. The result is a sharp increase in estimated structure damage from $217 thousand to $1.8 million and a corresponding increase in estimated contents damage from $112 thousand to approximately $1.1 million. This corresponds to an increase of $1.6 million (739%) for structures and $938 thousand (838%) for contents. Prior to this analysis, this significant escalation of potential damages based on future development was predicted by county staff and has led to efforts requiring new development to be 1-foot above the one-hundred year base flood elevation, where the BFE includes the increased runoff from the future or ultimate build-out. These results support that effort as the 1-foot requirement would reduce the results of Run 3 to levels more closely resembling the results of the existing development results presented by Run 2 (see Figure 3.8-1). $2,000,000 $1,800,000 Structure Content $1,600,000 Estimated Damage (Dollars) $1,400,000 $1,200,000 $1,000,000 $800,000 $600,000 $400,000 $200,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.8-1. McKee Creek Watershed Aggregate Damage Estimation Results 3-122 Table 3.8-2 shows a summary of the building and content damage results by general occupancy classification. In general, Table 1-2 shows all damages are concentrated in the residential occupancy classification in Runs 1, Run 2, and Run 3. The differences between Run 1 and Run 2 can be attributed to changes in the flood depths resulting from differences in the 1975 and 2000 flood studies. While the average loss is still low ($9,000) the addition of 21 structures being flooded greatly increases the total loss. The flood study is the same for Run 2 and Run 3, however new “development” in Run 3 causes significant increases in building and contents damages. The results are discussed in greater detail later in this report. Table 3.8-2. Summary of Building and Content Damage by General Occupancy: McKee Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) Structural Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $0 $0 $0 $0 $0 $0 Residential Single and Multi-Family Residential $8,200 $4,100 $217,095 $9,439 $1,822,089 $29,389 Content Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $0 $0 $0 $0 $0 $0 Residential Single and Multi-Family Residential $3,699 $1,850 $111,998 $4,869 $1,050,155 $16,938 3-123 3.8.2 Data Analysis 3.8.2.1 McKee Creek Basin Characteristics and Study Data Depth grids were created for McKee Creek. The grids depict the depth of flooding that will be exceeded with a 1-percent chance in any given year (100-year flood) under both existing and future development conditions. The location of McKee Creek relative to nearby stream systems is shown in Figure 3.8-2. Approximately 3.14 miles of McKee Creek were studied. Figure 3.8-2. McKee Creek and Nearby Stream Systems Flood elevation grids were created interpolating between water surface elevations determined at numerous cross sections along the study reaches. In all, 50 cross sections were used to study McKee Creek. The flood elevation grids were extended at the upstream end of the reach and at relatively large areas where floodwaters are not conveyed but, rather, pond at the elevation on the main stream. Depth grids were created by subtracting the ground elevation in the digital elevation model from the flood elevation at the corresponding cell in the elevation grid. Cells with flood depths less than zero (those outside of the floodplain, for example) were deleted from the flood elevation and flood depth grids. 3-124 The resulting existing conditions flood depth grid is shown in Figure 3.8-3. Approximately 168 acres are within the 100-year floodplain. Figure 3.8-4 shows the distribution of floodplain area inundated at 1-foot depth increments. The maximum depth is approximately 11.39 feet. The average (mean) depth is 2.98 feet. Less than 0.15 acre is inundated at a depth greater than 10 feet. Figure 3.8-3. Existing Conditions Flood Depth Grid 3-125 McKee Creek 45 Area Inundated (acres) 40 35 30 25 20 15 10 5 0 1 2 3 4 5 6 7 8 9 10 11 12 Flood Depth (feet) Figure 3.8-4. Distribution of Existing Condition Flood Depths The future conditions flood depth grid is shown in Figure 3.8-5. Approximately 202 acres are within the 100-year floodplain, an increase of 34 acres or a little more than 20 percent. The distribution of floodplain area inundated at various depths is shown in Figure 3.8-6. The maximum depth is 14.58 feet (more than 3 feet greater than existing conditions). The mean depth is 4.77 feet (about 1.8 feet greater than existing conditions). The area inundated by more than 10 feet is approximately 4.43 acres (about 4.3 acres or 30 times more than the existing conditions). 3-126 Figure 3.8-5. Future Conditions Flood Depth Grid Mckee Creek 40 Area Inundated (acres) 35 30 25 20 15 10 5 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Flood Depth (feet) Figure 3.8-6. Distribution of Future Condition Flood Depths 3-127 Subtracting the existing conditions flood depth grid from the future conditions flood depth grid yields a grid showing the increase in 100-year flood depths expected as a result of development within the basin. That grid is shown in Figure 3.8-7. The distribution of changes in 100-year flood depths is shown in Figure 3.8-8. Note that most (over 70 percent) of the differences are more than two feet; more than 15 percent of the differences exceed three feet (the mean depth under existing conditions). Figure 3.8-7. Increases in 100-year Flood Depths 3-128 McKee Creek 120 Area Affected (acres) 100 80 60 40 20 0 1 2 3 4 Difference in Flood Depths (feet) Figure 3.8-8. Differences in 100-year Flood Depths 3.8.2.1.1 McKee Creek Parcel and Building Data Review To determine the parcels and building footprints that may be potentially impacted by inundation from McKee Creek, the floodplain boundaries from both the 1975 flood study and the 2000 flood study were combined and a buffer of 100-feet added. The buffered boundary was used to select intersecting parcel and every building footprint contained within those parcels. This process was selected because it allows Mecklenburg County to identify all structures that are considered close to the floodplain. Structures outside the flood depth grids do not impact the results of this analysis because they will have no net damage, but knowing what structures are nearby was deemed advantageous to Mecklenburg County. There are 345 parcels that intersect the floodplain boundary (including the 100-foot buffer) surrounding McKee Creek. Some duplicate parcels were identified and reviewed. In all cases, these turned out to be slivers in the GIS data, most likely right-of-ways that have been either returned to the parcel, or offers of dedication that were never acted upon. In all cases, the slivers were merged back into the main parcel. Of the 345 parcels, 136 (39%) are identified as “vacant”, no parcels had information in the “effective area” field in the county assessor data indicating that a structure was on the parcel, although no 3-129 building footprint was available. The percentage of vacant parcels (39% based on 345 parcels) shows that Mecklenburg County has significant opportunities to manage future development and reduce future damage within the watershed. Within the 354 parcels, there are 223 building footprints greater than 500 square feet that are near the buffered floodplain boundary. Of these, none were surveyed as part of the master-elevation-certificate surveys or the “gpsbfe” survey data. Since there were no parcels identified as non-vacant based on square footage information within the assessors data, the final count of buildings for this analysis is 223. For the future conditions or “build-out”, a single structure was placed at the centroid of the 136 vacant parcels identified earlier. ®MH HAZUS This structure was established to have the default floor area and value based on the occupancy class assigned to the approved zoning of the parcel (see Tables A-1 and A-2 in Appendix A). Therefore the total “buildings” within the floodplain for the built-out inventory is assumed to be 359. 3.8.3 Detailed Results for the McKee Creek Basin To determine the potential impacts of floodplain map modifications, three damage estimates have been developed, as follows: 1. Run 1 – current inventory, original floodplain. Estimated losses based on the current building inventory within the McKee Creek watershed (developed from surveyed data and parcel data) and the original 100-year floodplain boundary, based on the 1975 flood study. 2. Run 2 – current inventory, new floodplain. Estimated losses based on the current building inventory, expanded to include structures within the new floodplain that were previously outside the floodplain, and the newly revised (2000) floodplain boundary. 3. Run 3 – future inventory, new floodplain. Estimated losses to a projected future inventory that incorporates projected growth (“build out”), relative to the new floodplain boundary. Table 3.8-3 presents the number of buildings damaged by flooding (i.e., non-zero dollar damage) by occupancy under each of the three scenarios. As noted in Section 2, a 3-130 HAZUS®MH occupancy class was associated with each occupancy type in the Mecklenburg assessor database. As shown in the figure, the number of damaged buildings increases between runs for the majority of building types. The increase in the number of flooded buildings between Run 1 and Run 2 is due to differences in the floodplain boundary between the 1975 flood study and the 2000 flood study map revisions. The increase between Run 2 and Run 3 is attributable to the projected increase in floodplain development. The values shown in Table 3.8-3 are presented to give the reader perspective on the relative number of flooded buildings, which is useful when viewing the subsequent tables. Table 3.8-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: McKee Creek Watershed HAZUS®MH Occupancy Description Code RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1E Single Family Dwelling, Split Level, with Basement Total No. of flooded buildings Total No. of unflooded buildings Current Inventory, Original Floodplain (Run 1) 1 Current Inventory, New Floodplain (Run 2) 9 Future Inventory, New Floodplain (Run 3) 39 1 14 14 0 0 9 2 23 62 221 200 297 The aggregate dollar damage across all building occupancy types is shown in Figure 3.89. As shown, the estimated dollar damage increases from Run 1 to Run 2 and from Run 2 to Run 3. Tables 3.8-4 through 3.8-7 and the associated discussion go into greater detail about the results of the loss estimation. However, it should be noted that the escalation of estimated damage based on future development validates the need for additional mitigation measures, such as requiring future development to be 1-foot above the future one hundred year flood elevation (as currently proposed by county staff). 3-131 $2,000,000 $1,800,000 Structure Content $1,600,000 Estimated Damage (Dollars) $1,400,000 $1,200,000 $1,000,000 $800,000 $600,000 $400,000 $200,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.8-9. McKee Creek Watershed Aggregate Damage Estimation Results Table 3.8-4 presents the overall average damage percentage calculated for building structures by occupancy, through the application of the various depth-damage curves. Table 3.8-4 shows that the differences between the 2000 flood study and the 1975 flood study had a significant impact on the average damage (%) to the existing structures. In Runs 1 has an average damage level between 3 and 10 percent. Run 2 increases the lowest values for the average structure damage levels closing the range for all occupancies to 9 and 11 percent. Table 3.8-4 also shows that new “development” also greatly impacts the average damage (%) with the structure damage ranging between 9 and 40 percent. Run 3 show additional damage in the RES1A occupancy and adds the RES1E occupancy to increase the average damage level range between 10 and 40 percent. It is notable that structure damage over 50% of market value is considered 3-132 “substantial damage”5 by the Federal Insurance and Mitigation Administration. Structures receiving over 50% estimated damage are likely to be excellent acquisition candidates. Table 3.8-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: McKee Creek Watershed HAZUS®MH Occupancy Code Description RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1E Single Family Dwelling, Split Level, with Basement Current Inventory, Original Floodplain (Run 1) 3.9 Current Inventory, New Floodplain (Run 2) 10.3 Future Inventory, New Floodplain (Run 3) 21.4 9.4 9.4 9.4 --- --- 39.8 Table 3.8-5 shows the dollar damage to building structures that is computed when the individual building damage percentages are multiplied by the structure/parcel valuation. As with the previous table, there are significant differences in the dollar damage between the three scenarios. Between Run 1 and Run 2, there is an increase in total structure damage from $8.2 thousand to $217 thousand. This corresponds to an increase of $209 thousand, or 2,548%. As the building inventories used for these scenarios are identical, the difference in damage is attributable to differences in the floodplain between the 1975 flood study and the 2000 revision of the 100-yr floodplain map. Proceeding from Run 2 to Run 3, there is a significant increase in estimated damage from $217 thousand to $1.8 million, suffered by projected development in the floodplain. This corresponds to an increase of $1.6 million, or 739%. All losses are related to single-family dwellings (RES1 classification). 5 According to NFIP guidelines, structures suffering “substantial damage” must be brought up to current floodplain management standards for new (post-FIRM) construction (i.e., removed from the flood hazard area or elevated to or above the level of the base flood elevation, or floodproofed if it is nonresidential). 3-133 Table 3.8-5. Structure Dollar Damage by HAZUS®MH Occupancy Type McKee Creek Watershed HAZUS®MH Occupancy Code RES1A RES1B RES1E Total Current Inventory, Current Inventory, New Future Inventory, New Original Floodplain Floodplain floodplain (Run 1) (Run 2) (Run 3) Total Avg. Total Avg. Total Avg. $1,405 $1,405 $75,430 $8,381 $1,158,830 $29,714 $75,430 $8,381 $141,665 $10,119 $141,665 $10,119 --------$521,594 $57,955 $8,200 $4,100 $217,095 $9,439 $1,822,089 $29,389 Table 3.8-6 presents the overall average damage percentage calculated for building contents by occupancy type. Run 1 has an average damage percent for contents between 2 and 9 percent. Increases in the content damage for Run 2 narrows the range to between 10 and 11 percent. Run 3 exhibits large increases over the damage percentages seen in Run 2. Overall, the average estimated contents damage percent ranges between 10 to 40 percent. Table 3.8-6. Contents Damage Percent by HAZUS®MH Occupancy Type McKee Creek Watershed HAZUS®MH Occupancy Description Code RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1E Single Family Dwelling, Split Level, with Basement Current Inventory, Original Floodplain (Run 1) 2.7 Current Inventory, New Floodplain (Run 2) 10.7 Future Inventory, New Floodplain (Run 3) 26.8 8.9 10.0 10.0 --- --- 37.8 Table 3.8-7 provides the estimated dollar damage to building contents by occupancy type. Similar to the structure dollar damage shown in Table 3.8-5, there are significant differences in the dollar damage between scenarios. Between Run 1 and Run 2, there is an increase in total estimated contents damage from $3.7 thousand to $112 thousand. This corresponds to an increase of $108 thousand, or 2,928%. The increase in damage is due to changes in the floodplain depth and extent between the 1975 flood study and the recent 2000 revision of the 100-yr floodplain map. Between Run 2 to Run 3, there is a 3-134 significant increase in estimated damage from $112 thousand to $1.1 million attributable to projected growth. This corresponds to an increase of $938 thousand, or 838 %. Table 3.8-7. Contents Dollar Damage by HAZUS®MH Occupancy Type McKee Creek Watershed HAZUS®MH Occupancy Code RES1A RES1B RES1E Total Current Inventory, Current Inventory, New Future Inventory, New Current Floodplain Floodplain Floodplain (Run 1) (Run 2) (Run 3) Total Avg. Total Avg. Total Avg. $500 $500 $36,949 $4,105 $727,621 $18,657 $3,204 $3,204 $75,049 $5,361 $75,049 $5,361 --------$247,485 $27,498 $3,704 $3,704 $111,998 3-135 $4,869 $1,050,155 $16,938 DETERMINATION OF FINANCIAL IMPACTS FROM FLOOD STUDIES BACK CREEK WATERSHED (Report Delivered January 2002) Prepared for: MECKLENBURG COUNTY ENGINEERING & BUILDING STANDARDS Charlotte, NC 28202 3.9 3.9.1 Back Creek Analysis Results Summary for the Back Creek Basin Two building inventories and two floodplain scenarios maps were combined to develop damage estimates for the three scenarios listed above. Table 3.9-1 shows a summary of the number of flooded buildings by general occupancy classification. The simulation predicted 4, 4, and 14 damaged buildings from Runs 1, 2, and 3, respectively. Table 3.9-1. Number of Flooded Structures by General Occupancy: Back Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) NonResidential Commercial, Industrial, Religious, Education 0 0 1 Residential Single and MultiFamily Residential 4 4 13 4 4 14 Total The dollar damage resulting from the analysis is shown on Figure 3.9-1. The damage for each scenario shown in the figure is an aggregate across all building occupancy types. As shown, there is an increase in estimated damage between Run 1 (structure $51 thousand, contents $29 thousand) and Run 2 (structure $63 thousand, contents $42 thousand). This corresponds to an increase of $12 thousand (23%) for structures and $13 thousand (45%) for contents. The increase demonstrates the effect of changes in the floodplain extent and depth between the 1975 flood study and newly revised (2000) floodplain map. Based on the assumption that the revised floodplain map is more accurate than the 1975 flood study, the estimated damage results from Run 2 are representative of current conditions. A comparison of the aggregate damage from Run 2 and Run 3 highlights the difference in damage between current and future building development conditions. For the analysis in Run 3, damage estimates for parcels that are currently vacant were assumed to be 3-136 developed based on their zoning. The result is a sharp increase in estimated structure damage from $63 thousand to $564 thousand and a corresponding increase in estimated contents damage from $42 thousand to approximately $578 thousand. This corresponds to an increase of $500 thousand (790%) for structures and $536 thousand (1,200%) for contents. Prior to this analysis, this significant escalation of potential damages based on future development was predicted by county staff and has led to efforts requiring new development to be 1-foot above the one-hundred year base flood elevation, where the BFE includes the increased runoff from the future or ultimate build-out. These results support that effort as the 1-foot requirement would reduce the results of Run 3 to levels more closely resembling the results of the existing development results presented by Run 2 (see Figure 3.9-1). $700,000 $600,000 Structure Content Estimated Damage (Dollars) $500,000 $400,000 $300,000 $200,000 $100,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.9-1. Back Creek Watershed Aggregate Damage Estimation Results 3-137 Table 3.9-1 shows a summary of the building and content damage results by general occupancy classification. In general, Table 3.9-2 shows all damages are concentrated in the residential occupancy classification in Runs 1 and 2. While there is a significant increase in the losses to residential potential occupancies in Run 3, “development” of vacant parcels zoned for non-residential occupancies adds a single structure that accounts for slightly less than half of the total losses (structure and content). As expected for Run 1 and Run 2, the contents damage by occupancy generally increases with increasing building damage. With Run 3, however, the non-residential content damages from the aforementioned structure accounts for over half of the contents damage. The results are discussed in greater detail later in this report. Table 3.9-2. Summary of Building and Content Damage by General Occupancy: Back Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) Structural Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $0 $0 $0 $0 $163,812 $163,812 Residential Single and Multi-Family Residential $51,615 $29,031 $63,339 $15,835 $399,978 $30,768 Content Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $0 $0 $0 $0 $329,754 $329,754 Residential Single and Multi-Family Residential $29,031 $7,258 $42,141 $10,535 $248,370 $19,105 3-138 3.9.2 Data Analysis 3.9.2.1 Back Creek and Back Tributary Basin Characteristics and Study Data Back Creek is located in east-central Mecklenburg County, just south of the Mallard Creek Basin. Depth grids were created for Back Creek and Back Creek Tributary. The grids depict the depth of flooding that will be exceeded with a 1-percent chance in any given year (100-year flood) under both existing and future development conditions. The streams analyzed and the location relative to the Mallard Creek basin are shown in Figure 3.9-2. Figure 3.9-2. Back Creek and Back Creek Tributary The studied reaches include approximately 4.6 miles of Back Creek and approximately 2.3 miles of Back Creek Tributary. Flood elevation grids were created interpolating between water surface elevations determined at numerous cross sections along the study reaches. In all, 100 cross sections were used: 71 on Back Creek and 29 on Back Creek Tributary. The flood elevation grids were extended at the upstream end of each stream, at the confluence with Back Creek Tributary, and at relatively large areas where floodwaters are not conveyed 3-139 but, rather, pond at the elevation on the main stream. Where two stream flood elevation grids overlap the final flood elevation grid uses the greater of the two elevations. Depth grids were created by subtracting the ground elevation in the digital elevation model from the flood elevation at the corresponding cell in the elevation grid. Cells with flood depths less than zero (those outside of the floodplain, for example) were deleted from the flood elevation and flood depth grids. The resulting existing conditions (1975 flood study) flood depth grid is shown in Figure 3.9-3. Approximately 210 acres are within the 100-year floodplain. Figure 3.9-4 shows the distribution of floodplain area inundated at 1-foot depth increments. The maximum depth is approximately 10.30 feet. The average (mean) depth is 2.98 feet. Approximately 24 acres are inundated at a depth greater than 5 feet. Figure 3.9-3. Existing Conditions Flood Depth Grid 3-140 Back Creek and Back Creek Tributary 60 Area Inundated (acres) 50 40 30 20 10 0 1 2 3 4 5 6 7 8 9 10 11 Flood Depth (feet) Figure 3.9-4. Distribution of Existing Condition Flood Depths The future conditions flood depth grid is shown in Figure 3.9-5. Approximately 234 acres are within the 100-year floodplain, an increase of 24 acres or a little more than 10 percent. The distribution of floodplain area inundated at various depths is shown in Figure 3.9-6. The maximum depth is 10.88 feet (about 0.5 foot greater than existing conditions). The mean depth is 3.70 feet (about 0.7 foot greater than existing conditions). The area inundated by more than 5 feet is approximately 60 acres (36 acres or 150 percent more than the existing conditions). 3-141 Figure 3.9-5. Future Conditions Flood Depth Grid Back Creek and Back Creek Tributary 50 Area Inundated (acres) 45 40 35 30 25 20 15 10 5 0 1 2 3 4 5 6 7 8 9 10 11 Flood Depth (feet) Figure 3.9-6. Distribution of Future Condition Flood Depths 3-142 Subtracting the existing conditions flood depth grid from the future conditions flood depth grid yields a grid showing the increase in 100-year flood depths expected as a result of development within the basin. That grid is shown in Figure 3.9-7. The distribution of changes in 100-year flood depths is shown in Figure 3.9-8. Note that most (approximately 95 percent) of the differences are less than two feet. The 100-year flood depth increases are expected to exceed 2 feet in approximately 11.6 acres within the Back Creek floodplain. Figure 3.9-7. Increases in 100-year Flood Depths 3-143 Back Creek and Back Creek Tributary 140 Area Affected (acres) 120 100 80 60 40 20 0 1 2 3 4 Difference in Flood Depths (feet) Figure 3.9-8. Differences in 100-year Flood Depths 3.9.2.1.1 Back Creek Parcel and Building Data Review To determine the parcels and building footprints that may be potentially impacted by inundation from Back Creek, the floodplain boundaries from both the 1975 flood study and the 2000 flood study were combined and a buffer of 100-feet added. The buffered boundary was used to select intersecting parcel and every building footprint contained within those parcels. This process was selected because it allows Mecklenburg County to identify all structures that are considered close to the floodplain. Structures outside the flood depth grids do not impact the results of this analysis because they will have no net damage, but knowing what structures are nearby was deemed advantageous to Mecklenburg County. There are 204 parcels that intersect the floodplain boundary (including the 100-foot buffer) surrounding Back Creek. Some duplicate parcels were identified and reviewed. In all cases, these turned out to be slivers in the GIS data, most likely right-of-ways that have been either returned to the parcel, or offers of dedication that were never acted upon. In all cases, the slivers were merged back into the main parcel. Of the 204 parcels, 75 (37%) are identified as “vacant”, an additional parcel had information in the “effective area” field in the county assessor data indicating that a structure was on the parcel, although no building footprint was available. The percentage of vacant parcels (37% 3-144 based on 204 parcels) shows that Mecklenburg County has significant opportunities to manage future development and reduce future damage within the watershed. Within these 204 parcels, there are 307 building footprints greater than 500 square feet that are near the buffered floodplain boundary. Of these, none were surveyed as part of the master-elevation-certificate surveys or the “gpsbfe” survey data. For the analysis, the parcel without a building footprint that was identified as non-vacant based on the square footage in the assessors data was carried as single structure at the centroid of the parcel, for a total of 308 “buildings” in the floodplain (including the 100-foot buffer). For the future conditions or “build-out”, a single structure was placed at the centroid of the 75 vacant parcels identified earlier. This structure was established to have the HAZUS®MH default floor area and value based on the occupancy class assigned to the approved zoning of the parcel (see Tables A-1 and A-2 in Appendix A). Therefore the total “buildings” within the floodplain for the built-out inventory is assumed to be 383. 3.9.3 Detailed Results for the Back Creek Basin To determine the potential impacts of floodplain map modifications, three damage estimates have been developed, as follows: 1. Run 1 – current inventory, original floodplain. Estimated losses based on the current building inventory within the Back Creek watershed (developed from surveyed data and parcel data) and the original 100-year floodplain boundary, based on the 1975 flood study. 2. Run 2 – current inventory, new floodplain. Estimated losses based on the current building inventory, expanded to include structures within the new floodplain that were previously outside the floodplain, and the newly revised (2000) floodplain boundary. 3. Run 3 – future inventory, new floodplain. Estimated losses to a projected future inventory that incorporates projected growth (“build out”), relative to the new floodplain boundary. Table 3.9-3 presents the number of buildings damaged by flooding (i.e., non-zero dollar damage) by occupancy under each of the three scenarios. As noted in Section 2, a 3-145 HAZUS®MH occupancy class was associated with each occupancy type in the Mecklenburg assessor database. As shown in the figure, the number of damaged buildings increases between runs for the majority of building types. The increase in the number of flooded buildings between Run 1 and Run 2 is due to differences in the floodplain boundary between the 1975 flood study and the 2000 flood study map revisions. The increase between Run 2 and Run 3 is attributable to the projected increase in floodplain development. The values shown in Table 3.9-3 are presented to give the reader perspective on the relative number of flooded buildings, which is useful when viewing the subsequent tables. Table 3.9-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Back Creek Watershed HAZUS®MH Occupancy Description Code COM1/COM4 Mix of Retail Trade & Professional/Technical Services RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1E Single Family Dwelling, Split Level, with Basement Total No. of flooded buildings Total No. of unflooded buildings Current Inventory, Original Floodplain (Run 1) 0 Current Inventory, New Floodplain (Run 2) 0 Future Inventory, New Floodplain (Run 3) 1 2 2 10 2 2 2 0 0 1 4 4 14 304 304 369 The aggregate dollar damage across all building occupancy types is shown in Figure 3.99. As shown, the estimated dollar damage increases from Run 1 to Run 2 and from Run 2 to Run 3. Tables 3.9-4 through 3.9-7 and the associated discussion go into greater detail about the results of the loss estimation. However, it should be noted that the escalation of estimated damage based on future development validates the need for mitigation measures, such as requiring future development to be 1-foot above the future one hundred year flood elevation (as currently proposed by county staff). 3-146 $700,000 $600,000 Structure Content Estimated Damage (Dollars) $500,000 $400,000 $300,000 $200,000 $100,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.9-9. Back Creek Watershed Aggregate Damage Estimation Results Table 3.9-4 presents the overall average damage percentage calculated for building structures by occupancy, through the application of the various depth-damage curves. Table 3.9-4 shows that changes in inventory development have minor impacts on the average percent damage for most residential occupancy classifications, but development increases the average damage percentage in the non-residential classification and the RES1E classification (Run 3). In Runs 1 and 2, the average structure damage levels range between 10 and 20 percent. In Run 3, the structure damage ranges expand to between 10 and 50 percent. It is notable that structure damage over 50% of market value is considered “substantial damage”6 by the Federal Insurance and Mitigation 6 According to NFIP guidelines, structures suffering “substantial damage” must be brought up to current floodplain management standards for new (post-FIRM) construction (i.e., removed from the flood hazard area or elevated to or above the level of the base flood elevation, or floodproofed if it is nonresidential). 3-147 Administration. Structures receiving over 50% estimated damage are likely to be excellent acquisition candidates. Table 3.9-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Back Creek Watershed HAZUS®MH Occupancy Code Description COM1/COM4 Mix of Retail Trade & Professional/Technical Services RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1E Single Family Dwelling, Split Level, with Basement Current Inventory, Original Floodplain (Run 1) --- Current Inventory, New Floodplain (Run 2) --- Future Inventory, New Floodplain (Run 3) 39.2 15.9 20.4 22.4 12.3 14.7 14.7 --- --- 48.2 Table 3.9-5 shows the dollar damage to building structures that is computed when the individual building damage percentages are multiplied by the structure/parcel valuation. As with the previous table, there are significant differences in the dollar damage between the three scenarios. Between Run 1 and Run 2, there is an increase in total structure damage from $51 thousand to $63 thousand. This corresponds to an increase of $12 thousand, or 23%. As the building inventories used for these scenarios are identical, the difference in damage is attributable to differences in the floodplain between the 1975 flood study and the 2000 revision of the 100-yr floodplain map. Proceeding from Run 2 to Run 3, there is a significant increase in estimated damage from $63 thousand to $564 thousand, suffered by projected development in the floodplain. This corresponds to an increase of $500 thousand, or 790%. It is notable that Run 3 has increased damages across nearly every occupancy classification. 3-148 Table 3.9-5. Structure Dollar Damage by HAZUS®MH Occupancy Type Back Creek Watershed HAZUS®MH Occupancy Code COM1/COM4 RES1A RES1B RES1E Total Current Inventory, Current Inventory, New Future Inventory, New Original Floodplain Floodplain floodplain (Run 1) (Run 2) (Run 3) Total Avg. Total Avg. Total Avg. --------$163,812 $163,812 $17,431 $8,716 $22,384 $11,192 $288,892 $28,889 $34,184 $17,092 $40,955 $20,478 $40,955 $20,478 --------$70,131 $70,131 $51,615 $29,031 $63,339 $15,835 $563,791 $40,271 Table 3.9-6 presents the overall average damage percentage calculated for building contents by occupancy type. Similar to the structure damage percent results shown in Table 3.9-4, the difference in the range of contents damage percentages between Run 1 and Run 2 is varies from 15 to 30 percent. Run 3 has an increased range of damage due to development in the COM1/COM4 and RES1E occupancy classifications. Overall, the average estimated contents damage percent ranges between 15 and 55 percent. Table 3.9-6. Contents Damage Percent by HAZUS®MH Occupancy Type Back Creek Watershed HAZUS®MH Occupancy Code Description COM1/COM4 Mix of Retail Trade & Professional/Technical Services RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1E Single Family Dwelling, Split Level, with Basement Current Inventory, Original Floodplain (Run 1) --- Current Inventory, New Floodplain (Run 2) --- Future Inventory, New Floodplain (Run 3) 39.2 17.1 29.0 28.7 14.2 18.9 18.9 --- --- 54.3 3-149 Table 3.9-7 provides the estimated dollar damage to building contents by occupancy type. Similar to the structure dollar damage shown in Table 3.9-5, there are significant differences in the dollar damage between scenarios. Between Run 1 and Run 2, there is an increase in total estimated contents damage from $29 thousand to $42 thousand. This corresponds to an increase of $13 thousand, or 45%. The increase in damage is due to changes in the floodplain depth and extent between the 1975 flood study and the recent 2000 revision of the 100-yr floodplain map. Between Run 2 to Run 3, there is a significant increase in estimated damage from $42 thousand to $578 thousand attributable to projected growth. This corresponds to an increase of $536 thousand, or 1,272%. Interestingly, while overall increase in contents damage is relatively large (1,270 percentile), the total estimated damages ($536 thousand) is relatively low when compared to other watersheds in Mecklenburg County. Table 3.9-7. Contents Dollar Damage by HAZUS®MH Occupancy Type Back Creek Watershed HAZUS®MH Occupancy Code COM1/COM4 RES1A RES1B RES1E Total Current Inventory, Current Inventory, New Future Inventory, New Current Floodplain Floodplain Floodplain (Run 1) (Run 2) (Run 3) Total Avg. Total Avg. Total Avg. --------$329,754 $329,754 $9,343 $4,671 $15,873 $7,936 $182,597 $18,260 $19,689 $9,844 $26,269 $13,1334 $26,269 $13,134 --------$39,504 $39,504 $29,031 $7,258 $42,141 3-150 $10,535 $578,124 $41,295 DETERMINATION OF FINANCIAL IMPACTS FROM FLOOD STUDIES SIX MILE CREEK WATERSHED (Report Delivered January 2002) Prepared for: MECKLENBURG COUNTY ENGINEERING & BUILDING STANDARDS Charlotte, NC 28202 3.10 Six Mile Creek Analysis 3.10.1 Results Summary for the Six Mile Creek Basin Two building inventories and two floodplain scenarios maps were combined to develop damage estimates for the three scenarios listed above. Table 3.10-1 shows a summary of the number of flooded buildings by general occupancy classification. The simulation predicted 23, 33, and 90 damaged buildings from Runs 1, 2, and 3, respectively. Table 3.10-1. Number of Flooded Structures by General Occupancy: Six Mile Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) NonResidential Commercial, Industrial, Religious, Education 1 2 2 Residential Single and MultiFamily Residential 22 31 88 23 33 90 Total The dollar damage resulting from the analysis is shown on Figure 3-10-1. The damage for each scenario shown in the figure is an aggregate across all building occupancy types. As shown, there is an increase in estimated damage between Run 1 (structure $473 thousand, contents $246 thousand) and Run 2 (structure $729 thousand, contents $410 thousand). This corresponds to an increase of $256 thousand (54%) for structures and $164 thousand (67%) for contents. The increase demonstrates the effect of changes in the floodplain extent and depth between the 1975 flood study and newly revised (2000) floodplain map. Based on the assumption that the revised floodplain map is more accurate than the 1975 flood study, the estimated damage results from Run 2 are representative of current conditions. A comparison of the aggregate damage from Run 2 and Run 3 highlights the difference in damage between current and future building development conditions. For the analysis in Run 3, damage estimates for parcels that are currently vacant were assumed to be 3-151 developed based on their zoning. The result is a sharp increase in estimated structure damage from $729 thousand to $3.0 million and a corresponding increase in estimated contents damage from $410 thousand to approximately $1.9 million. This corresponds to an increase of $2.3 million (313%) for structures and $1.5 million (361%) for contents. Prior to this analysis, this significant escalation of potential damages based on future development was predicted by county staff and has led to efforts requiring new development to be 1-foot above the one-hundred year base flood elevation, where the BFE includes the increased runoff from the future or ultimate build-out. These results support that effort as the 1-foot requirement would reduce the results of Run 3 to levels more closely resembling the results of the existing development results presented by Run 2 (see Figure 3-10-1). $3,500,000 $3,000,000 Structure Content Estimated Damage (Dollars) $2,500,000 $2,000,000 $1,500,000 $1,000,000 $500,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.10-1. Six Mile Creek Watershed Aggregate Damage Estimation Results 3-152 Table 3.10-2 shows a summary of the building and content damage results by general occupancy classification. In general, Table 1-2 shows the majority of damages are concentrated in the residential occupancy classification in Runs 1, 2 and 3. Run 2 shows that differences between the 1975 and 2000 flood study nearly double the damages (structure and contents). As expected, there is a significant increase in the losses to residential occupancies in Run 3, because of “development” of vacant parcels. The results are discussed in greater detail later in this report. Table 3.10-2. Summary of Building and Content Damage by General Occupancy: Six Mile Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) Structural Damage Total Average Total Average Total Average $6,778 $20,584 $10,292 $20,584 $10,292 $21,196 $708,383 $22,851 $2,988,182 $33,957 NonResidential Commercial, Industrial, Religious, Education $6,778 Residential Single and Multi-Family Residential $466,305 Content Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $8,947 $8,947 $27,170 $13,585 $27,170 $13,585 Residential Single and Multi-Family Residential $236,637 $10,756 $382,903 $12,352 $1,863,987 $21,182 3.10.2 Data Analysis 3.10.2.1 Six Mile Creek and Flat Branch Basin Characteristics and Study Data Depth grids were created for Six Mile Creek and Flat Branch. The grids depict the depth of flooding that will be exceeded with a 1-percent chance in any given year (100-year 3-153 flood) under both existing and future development conditions. The streams analyzed and the location relative to the McAlpine Creek basin are shown in Figure 3.10-2. Figure 3.10-2. Six Mile Creek and Flat Branch The studied reaches include approximately 8.9 miles of Six Mile Creek and approximately 3.0 miles of Flat Branch. Flood elevation grids were created interpolating between water surface elevations determined at numerous cross sections along the study reaches. In all, 148 cross sections were used: 109 on Six Mile Creek and 39 on Flat Branch. The flood elevation grids were extended at the upstream end of each stream, at the confluence with Flat Branch, and at relatively large areas where floodwaters are not conveyed but, rather, pond at the elevation on the main stream. Where two stream flood elevation grids overlap the final flood elevation grid uses the greater of the two elevations. Depth grids were created by subtracting the ground elevation in the digital elevation model from the flood elevation at the corresponding cell in the elevation grid. Cells with flood depths less than zero (those outside of the floodplain, for example) were deleted from the flood elevation and flood depth grids. 3-154 The resulting existing conditions flood depth grid is shown in Figure 3.10-3. Approximately 895 acres are within the 100-year floodplain. Figure 3.10-4 shows the distribution of floodplain area inundated at 1-foot depth increments. There are two small pits, totaling less than 0.5 acre, in the floodplain on the right side of the lower reach of Six Mile Creek. The maximum depth (not within the pits) is approximately 16.57 feet. The average (mean) depth is 4.55 feet. Approximately 69 acres are inundated at a depth greater than 10 feet. Figure 3.10-3. Existing Conditions Flood Depth Grid 3-155 Six Mile Creek and Flat Branch 160 Area Inundated (acres) 140 120 100 80 60 40 20 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 Flood Depth (feet) Figure 3.10-4. Distribution of Existing Condition Flood Depths The future conditions flood depth grid is shown in Figure 3.10-5. Approximately 970 acres are within the 100-year floodplain, an increase of 75 acres or a little more than 8 percent. The distribution of floodplain area inundated at various depths is shown in Figure 3.10-6. The maximum depth (not within the pits) is 17.89 feet (about 1.3 feet greater than existing conditions). The mean depth is 5.08 feet (about 0.5 foot greater than existing conditions). The area inundated by more than 10 feet is approximately 102 acres (33 acres or approximately 48 percent more than the existing conditions). 3-156 Figure 3.10-5. Future Conditions Flood Depth Grid Six Mile Creek and Flat Branch 140 Area Inundated (acres) 120 100 80 60 40 20 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Flood Depth (feet) Figure 3.10-6. Distribution of Future Condition Flood Depths 3-157 Subtracting the existing conditions flood depth grid from the future conditions flood depth grid yields a grid showing the increase in 100-year flood depths expected as a result of development within the basin. That grid is shown in Figure 3.10-7. The distribution of changes in 100-year flood depths is shown in Figure 3.10-8. Note that the differences are less than two feet. Approximately two-thirds of the differences are less than 1 foot. Figure 3.10-7. Increases in 100-year Flood Depths 3-158 Six Mile Creek and Flat Branch 700 Area Affected (acres) 600 500 400 300 200 100 0 1 2 Difference in Flood Depths (feet) Figure 3.10-8. Differences in 100-year Flood Depths 3.10.2.1.1 Six Mile Creek Parcel and Building Data Review To determine the parcels and building footprints that may be potentially impacted by inundation from Six Mile Creek, the floodplain boundaries from both the 1975 flood study and the 2000 flood study were combined and a buffer of 100-feet added. The buffered boundary was used to select intersecting parcel and every building footprint contained within those parcels. This process was selected because it allows Mecklenburg County to identify all structures that are considered close to the floodplain. Structures outside the flood depth grids do not impact the results of this analysis because they will have no net damage, but knowing what structures are nearby was deemed advantageous to Mecklenburg County. There are 533 parcels that intersect the floodplain boundary (including the 100-foot buffer) surrounding Six Mile Creek. Some duplicate parcels were identified and reviewed. In all cases, these turned out to be slivers in the GIS data, most likely right-of-ways that have been either returned to the parcel, or offers of dedication that were never acted upon. In all cases, the slivers were merged back into the main parcel. Of the 533 parcels, 154 (29%) are identified as “vacant”, an additional parcel had information in the “effective area” field in the county assessor data indicating that a structure was on the parcel, although no building footprint was available. The percentage of vacant parcels (29% 3-159 based on 533 parcels) shows that Mecklenburg County has significant opportunities to manage future development and reduce future damage within the watershed. Within these 533 parcels, there are 411 building footprints greater than 500 square feet that are near the buffered floodplain boundary. Of these, none were surveyed as part of the master-elevation-certificate surveys or the “gpsbfe” survey data. For the analysis, the parcel without a building footprint that was identified as non-vacant based on the square footage in the assessors data was carried as single structure at the centroid of the parcel, for a total of 412 “buildings” in the floodplain (including the 100-foot buffer). For the future conditions or “build-out”, a single structure was placed at the centroid of the 154 vacant parcels identified earlier. ®MH HAZUS This structure was established to have the default floor area and value based on the occupancy class assigned to the approved zoning of the parcel (see Tables A-1 and A-2 in Appendix A). Therefore the total “buildings” within the floodplain for the built-out inventory is assumed to be 566. 3.10.3 Detailed Results for the Six Mile Creek Basin To determine the potential impacts of floodplain map modifications, three damage estimates have been developed, as follows: 1. Run 1 – current inventory, original floodplain. Estimated losses based on the current building inventory within the Six Mile Creek watershed (developed from surveyed data and parcel data) and the original 100-year floodplain boundary, based on the 1975 flood study. 2. Run 2 – current inventory, new floodplain. Estimated losses based on the current building inventory, expanded to include structures within the new floodplain that were previously outside the floodplain, and the newly revised (2000) floodplain boundary. 3. Run 3 – future inventory, new floodplain. Estimated losses to a projected future inventory that incorporates projected growth (“build out”), relative to the new floodplain boundary. Table 3.10-3 presents the number of buildings damaged by flooding (i.e., non-zero dollar damage) by occupancy under each of the three scenarios. As noted in Section 2, a 3-160 HAZUS®MH occupancy class was associated with each occupancy type in the Mecklenburg assessor database. As shown in the figure, the number of damaged buildings increases between runs for the majority of building types. The increase in the number of flooded buildings between Run 1 and Run 2 is due to differences in the floodplain boundary between the 1975 flood study and the 2000 flood study map revisions. The increase between Run 2 and Run 3 is attributable to the projected increase in floodplain development. The values shown in Table 3.10-3 are presented to give the reader perspective on the relative number of flooded buildings, which is useful when viewing the subsequent tables. Table 3.10-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Six Mile Creek Watershed HAZUS®MH Occupancy Description Code COM8 Entertainment and Recreation RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement RES3 Multi-Family Dwelling Total No. of flooded buildings Total No. of unflooded buildings Current Inventory, Original Floodplain (Run 1) 1 Current Inventory, New Floodplain (Run 2) 2 Future Inventory, New Floodplain (Run 3) 2 4 8 49 17 21 21 1 1 1 0 1 16 0 23 0 33 1 90 389 379 476 The aggregate dollar damage across all building occupancy types is shown in Figure 3.10-9. As shown, the estimated dollar damage increases from Run 1 to Run 2 and from Run 2 to Run 3. The majority of damage are to residential structures with only some development occurring in the non-residential occupancies. Tables 3.10-4 through 3.10-7 and the associated discussion go into greater detail about the results of the loss 3-161 estimation. However, it should be noted that the escalation of estimated damage based on future development validates the need for mitigation measures, such as requiring future development to be 1-foot above the future one hundred year flood elevation (as currently proposed by county staff). $3,500,000 $3,000,000 Structure Content Estimated Damage (Dollars) $2,500,000 $2,000,000 $1,500,000 $1,000,000 $500,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.10-9. Six Mile Creek Watershed Aggregate Damage Estimation Results Table 3.10-4 presents the overall average damage percentage calculated for building structures by occupancy, through the application of the various depth-damage curves. Table 3.10-4 shows that the damage (shown in percent) does not change significantly for the existing occupancies within the floodplain. New development, shown in Run 3, shows the impact of flooding on new development. In Run 1 the average structure damage levels range between 1 and 20 percent. Run 2 adds the RES1E occupancy to the flooded structures and therefore the average structure damage levels range from 2 to 30 percent. In Run 3, most of the occupancies have structure damage ranges between 2 and 40 percent. It is notable that structure damage over 50% of market value is considered 3-162 “substantial damage”7 by the Federal Insurance and Mitigation Administration. Structures receiving over 50% estimated damage are likely to be excellent acquisition candidates. Table 3.10-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Six Mile Creek Watershed HAZUS®MH Occupancy Code Description COM8 Entertainment and Recreation RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling, Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement RES3 Multi-Family Dwelling Current Inventory, Original Floodplain (Run 1) 8.7 Current Inventory, New Floodplain (Run 2) 13.1 Future Inventory, New Floodplain (Run 3) 13.1 19.0 14.9 19.7 9.5 10.6 10.6 1.0 2.7 2.7 --- 28.2 39.7 --- --- 37.5 Table 3.10-5 shows the dollar damage to building structures that is computed when the individual building damage percentages are multiplied by the structure/parcel valuation. As with the previous table, there are significant differences in the dollar damage between the three scenarios. Between Run 1 and Run 2, there is an increase in total structure damage from $473 thousand to $729 thousand. This corresponds to an increase of $256 thousand, or 54%. As the building inventories used for these scenarios are identical, the difference in damage is attributable to differences in the floodplain between the 1975 flood study and the 2000 revision of the 100-yr floodplain map. Proceeding from Run 2 to Run 3, there is a significant increase in estimated damage from $729 thousand to $3 million, suffered by projected development in the floodplain. This corresponds to an increase of $2.3 million, or 313%. It is notable that Run 3 has large increases in damages across nearly every occupancy classification intersecting the floodplain. 7 According to NFIP guidelines, structures suffering “substantial damage” must be brought up to current floodplain management standards for new (post-FIRM) construction (i.e., removed from the flood hazard area or elevated to or above the level of the base flood elevation, or floodproofed if it is nonresidential). 3-163 Table 3.10-5. Structure Dollar Damage by HAZUS®MH Occupancy Type Six Mile Creek Watershed HAZUS®MH Occupancy Code COM8 RES1A RES1B RES1D RES1E RES3 Total Current Inventory, Current Inventory, New Future Inventory, New Original Floodplain Floodplain floodplain (Run 1) (Run 2) (Run 3) Total Avg. Total Avg. Total Avg. $6,778 $6,778 $20,584 $10,292 $20,584 $10,292 $131,457 $32,864 $180,017 $27,502 $1,413,367 $28,844 $334,125 $19,654 $475,044 $22,621 $475,044 $22,621 $724 $724 $2,712 $2,712 $2,712 $2,712 ----$50,610 $50,610 $934,596 $58,412 --------$162,464 $162,464 $473,083 $20,569 $728,967 $22,090 $3,008,766 $33,431 Table 3.10-6 presents the overall average damage percentage calculated for building contents by occupancy type. The estimated damage for contents will typically follow the same general trend as seen in Table 3.10-4. Run 1 has an estimated damage percentage ranging from 1 to 20 percent. This range shifts and increases from 5 to 30 percent for Run 2 indicating the increased loss due to changes in the flood study. Run 3, shows the impact from development with the expected range of content damage increasing from 5 to nearly 100 percent. The most significant increase is in the multi-family dwelling occupancy however, the estimated development occurs within a single parcel and therefore could be easily managed. Table 3.10-6. Contents Damage Percent by HAZUS®MH Occupancy Type Six Mile Creek Watershed HAZUS®MH Occupancy Code COM8 RES1A RES1B RES1D RES1E RES3 Description Entertainment and Recreation Single Family Dwelling, 1 Story, No Basement Single Family Dwelling, 2 Story, No Basement Single Family Dwelling, Split Level, No Basement Single Family Dwelling, Split Level, with Basement Multi-Family Dwelling Current Inventory, Original Floodplain (Run 1) 8.7 Current Inventory, New Floodplain (Run 2) 13.1 Future Inventory, New Floodplain (Run 3) 19.6 14.7 23.8 9 11.6 11.6 7 6.6 6.6 1.8 29.5 44.8 --- --- 99.5 3-164 13.1 Table 3.10-7 provides the estimated dollar damage to building contents by occupancy type. Similar to the structure dollar damage shown in Table 3.10-5, there are significant differences in the dollar damage between scenarios. Between Run 1 and Run 2, there is an increase in total estimated contents damage from $246 thousand to $410 thousand. This corresponds to an increase of $164 thousand, or 67%. The increase in damage is due to changes in the floodplain depth and extent between the 1975 flood study and the recent 2000 revision of the 100-yr floodplain map. Between Run 2 to Run 3, there is a significant increase in estimated damage from $410 thousand to $1.9 million attributable to projected growth. This corresponds to an increase of $1.5 million, or 361%. Table 3.10-7. Contents Dollar Damage by HAZUS®MH Occupancy Type Six Mile Creek Watershed HAZUS®MH Occupancy Code COM8 RES1A RES1B RES1D RES1E RES3 Total Current Inventory, Current Inventory, New Future Inventory, New Current Floodplain Floodplain Floodplain (Run 1) (Run 2) (Run 3) Total Avg. Total Avg. Total Avg. $8,947 $8,947 $27,170 $13,585 $27,170 $13,585 $72,589 $18,147 $93,932 $11,741 $858,803 $17,527 $163,151 $9,597 $259,113 $12,339 $259,113 $12,339 $893 $893 $3,347 $3,347 $3,347 $3,347 ----$26,512 $26,512 $526,960 $32,935 --------$215,764 $215,764 $245,580 $10,677 $410,074 3-165 $12,426 $1,891,157 $21,013 DETERMINATION OF FINANCIAL IMPACTS FROM FLOOD STUDIES CLEMS BRANCH WATERSHED (Report Delivered January 2002) Prepared for: MECKLENBURG COUNTY ENGINEERING & BUILDING STANDARDS Charlotte, NC 28202 3.11 Clems Branch Analysis 3.11.1 Results Summary for the Clems Branch Basin Two building inventories and two floodplain scenarios maps were combined to develop damage estimates for the three scenarios listed above. Table 3.111-1 shows a summary of the number of flooded buildings by general occupancy classification. The simulation predicted no damaged buildings from Runs 1, 2, and 3, respectively. Table 3.11-1. Number of Flooded Structures by General Occupancy: Clems Branch Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) NonResidential Commercial, Industrial, Religious, Education 0 0 0 Residential Single and MultiFamily Residential 0 0 0 0 0 0 Total The resulting analysis shows that no structures were impacted in any of the runs. This means the differences between Run 1 and Run 2, essentially the difference between the 1975 flood study and the 2000 flood study applied to the existing inventory, did not add any structures or increase the flooding within any structures. The differences between Run 2 and Run 3, essentially new development within the floodplain, also did not add any structures within the floodplain. It should be cautioned that the methodology applies new development to the centroid of the vacant parcel. Of the 10 vacant parcels adjacent to the floodplain, Mecklenburg County can ensure the new development does not encroach into areas impacted by the 100-year boundary. 3-166 3.11.2 Data Analysis 3.11.2.1 Clems Branch Basin Characteristics and Study Data Depth grids were created for Clems Branch. The grids depict the depth of flooding that will be exceeded with a 1-percent chance in any given year (100-year flood) under both existing and future development conditions. The location of Clems Branch relative to nearby stream systems is shown in Figure 3.11-1. Approximately 0.6 mile of Clems Branch was studied. Figure 3.11-1. Clems Branch and Nearby Stream Systems Flood elevation grids were created interpolating between water surface elevations determined at 11 cross sections along Clems Branch. The flood elevation grids were extended at the upstream end of the study reach and at relatively large areas where floodwaters are not conveyed but, rather, pond at the elevation on the main stream. Depth grids were created by subtracting the ground elevation in the digital elevation model from the flood elevation at the corresponding cell in the elevation grid. Cells with flood 3-167 depths less than zero (those outside of the floodplain, for example) were deleted from the flood elevation and flood depth grids. The resulting existing conditions flood depth grid is shown in Figure 3.11-2. Approximately 23.5 acres are within the 100-year floodplain. Figure 3.11-3 shows the distribution of floodplain area inundated at 1-foot depth increments. The maximum depth is approximately 9.57 feet. The average (mean) depth is 2.51 feet. Less than 3 acres are inundated at a depth greater than 5 feet. Figure 3.11-2. Existing Conditions Flood Depth Grid 3-168 Clems Branch 7 Area Inundated (acres) 6 5 4 3 2 1 0 1 2 3 4 5 6 7 8 9 10 Flood Depth (feet) Figure 3.11-3. Distribution of Existing Condition Flood Depths The future conditions flood depth grid is shown in Figure 3.11-4. Approximately 28.9 acres are within the 100-year floodplain, an increase of 5.4 acres or more than 20 percent. The distribution of floodplain area inundated at various depths is shown in Figure 3.11-5. The maximum depth is 11.61 feet (more than 2 feet greater than existing conditions). The mean depth is 3.15 feet (about 0.65 foot greater than existing conditions). The area inundated by more than 5 feet is approximately 5.6 acres (about 2.6 acres or approximately 85 percent more than the existing conditions). 3-169 Figure 3.11-4. Future Conditions Flood Depth Grid Clems Branch 7 Area Inundated (acres) 6 5 4 3 2 1 0 1 2 3 4 5 6 7 8 9 10 11 12 Flood Depth (feet) Figure 3.11-5. Distribution of Future Condition Flood Depths 3-170 Subtracting the existing conditions flood depth grid from the future conditions flood depth grid yields a grid showing the increase in 100-year flood depths expected as a result of development within the basin. That grid is shown in Figure 3.11-6. The distribution of changes in 100-year flood depths is shown in Figure 3.11-7. Note that most (over 70 percent) of the differences are less than one foot. The differences are greater than one foot in approximately 8.3 acres in the vicinity of the Lancaster Highway crossing. Figure 3.11-6. Increases in 100-year Flood Depths 3-171 Clems Branch 25 Area Affected (acres) 20 15 10 5 0 1 2 3 Difference in Flood Depths (feet) Figure 3.11-7. Differences in 100-year Flood Depths 3.11.2.1.1 Clems Branch Parcel and Building Data Review To determine the parcels and building footprints that may be potentially impacted by inundation from the Clems Branch, the floodplain boundaries from both the 1975 flood study and the 2000 flood study were combined and a buffer of 100-feet added. The buffered boundary was used to select intersecting parcel and every building footprint contained within those parcels. This process was selected because it allows Mecklenburg County to identify all structures that are considered close to the floodplain. Structures outside the flood depth grids do not impact the results of this analysis because they will have no net damage, but knowing what structures are nearby was deemed advantageous to Mecklenburg County. There are 15 parcels that intersect the floodplain boundary (including the 100-foot buffer) surrounding the Clems Branch. Some duplicate parcels were identified and reviewed. In all cases, these turned out to be slivers in the GIS data, most likely right-of-ways that have been either returned to the parcel, or offers of dedication that were never acted upon. In all cases, the slivers were merged back into the main parcel. Of the 15 parcels, 10 (67%) are identified as “vacant”, an additional parcel had information in the “effective area” field in the county assessor data indicating that a structure was on the parcel, although no building footprint was available. The percentage of vacant parcels (67% based on 15 3-172 parcels) shows that Mecklenburg County has significant opportunities to ensure that damages can be maintained at a zero impact level. Within these 15 parcels, there are 8 building footprints greater than 500 square feet that are near the buffered floodplain boundary. Of these, none were surveyed as part of the master-elevation-certificate surveys or the “gpsbfe” survey data. For the analysis, the parcel without a building footprint that was identified as non-vacant based on the square footage in the assessors data was carried as single structure at the centroid of the parcel, for a total of 9 “buildings” in the floodplain (including the 100-foot buffer). For the future conditions or “build-out”, a single structure was placed at the centroid of the 10 vacant parcels identified earlier. This structure was established to have the HAZUS®MH default floor area and value based on the occupancy class assigned to the approved zoning of the parcel (see Tables A-1 and A-2 in Appendix A). Therefore the total “buildings” within the floodplain for the built-out inventory is assumed to be 19. 3.11.3 Detailed Results for the Clems Branch Basin To determine the potential impacts of floodplain map modifications, three damage estimates have been developed, as follows: 1. Run 1 – current inventory, original floodplain. Estimated losses based on the current building inventory within the Clems Branch watershed (developed from surveyed data and parcel data) and the original 100-year floodplain boundary, based on the 1975 flood study. 2. Run 2 – current inventory, new floodplain. Estimated losses based on the current building inventory, expanded to include structures within the new floodplain that were previously outside the floodplain, and the newly revised (2000) floodplain boundary. 3. Run 3 – future inventory, new floodplain. Estimated losses to a projected future inventory that incorporates projected growth (“build out”), relative to the new floodplain boundary. 3-173 Of the nine buildings that lie near the floodplain, none experience damaging flooding (i.e. non-zero dollar damage). This remains true throughout all three runs. For run three, this means that the centroid of the vacant developable parcels lies outside of the floodplain. The values shown in Table 3.11-2 are presented to give the reader perspective on the number of buildings within the floodplain, and the potential increase due to development in Run 3. Table 3.11-2. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Clems Branch Watershed HAZUS®MH Occupancy Code Description Total No. of flooded buildings Total No. of unflooded buildings Current Inventory, Original Floodplain (Run 1) 0 Current Inventory, New Floodplain (Run 2) 0 Future Inventory, New Floodplain (Run 3) 0 9 9 19 Run 1 and Run 2 shows that increases in the depth of flooding between the 1975 study and the 2000 study did not cause any damage to the existing inventory. Run 3, however, applies the future development of the 10 vacant parcels at the centroid of the parcels. While the analysis itself shows no damage, it is incumbent on Mecklenburg County to utilize the depth grids produced in this analysis to ensure that future development is either outside of the flood boundary or higher than the expected flood depths from the 2000 flood study. 3-174 DETERMINATION OF FINANCIAL IMPACTS FROM FLOOD STUDIES REEDY CREEK WATERSHED (Report Delivered February 2002) Prepared for: MECKLENBURG COUNTY ENGINEERING & BUILDING STANDARDS Charlotte, NC 28202 3.12 Reedy Creek Analysis 3.12.1 Results Summary for the Reedy Creek Basin Two building inventories and two floodplain scenarios maps were combined to develop damage estimates for the three scenarios listed above. Table 3.12-1 shows a summary of the number of flooded buildings by general occupancy classification. The simulation predicted 13, 24, and 62 damaged buildings from Runs 1, 2, and 3, respectively. Table 3.12-1. Number of Flooded Structures by General Occupancy: Reedy Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) NonResidential Commercial, Industrial, Religious, Education 0 0 0 Residential Single and MultiFamily Residential 13 24 62 13 24 62 Total The dollar damage resulting from the analysis is shown on Figure 3.12-1. The damage for each scenario shown in the figure is an aggregate across all building occupancy types. As shown, there is an increase in estimated damage between Run 1 (structure $186 thousand, contents $100 thousand) and Run 2 (structure $351 thousand, contents $208 thousand). This corresponds to an increase of $166 thousand (89%) for structures and $108 thousand (108%) for contents. The increase demonstrates the effect of changes in the floodplain extent and depth between the 1975 flood study and newly revised (2000) floodplain map. Based on the assumption that the revised floodplain map is more accurate than the 1975 flood study, the estimated damage results from Run 2 are representative of current conditions. A comparison of the aggregate damage from Run 2 and Run 3 highlights the difference in damage between current and future building development conditions. For the analysis in Run 3, damage estimates for parcels that are currently vacant were assumed to be 3-175 developed based on their zoning. The result is a increase in estimated structure damage from $351 thousand to $2.0 million and a corresponding increase in estimated contents damage from $208 thousand to approximately $1.1 million. This corresponds to an increase of $1.6 million (483%) for structures and $897 thousand (432%) for contents. Prior to this analysis, this significant escalation of potential damages based on future development was predicted by county staff and has led to efforts requiring new development to be 1-foot above the one-hundred year base flood elevation, where the BFE includes the increased runoff from the future or ultimate build-out. These results support that effort as the 1-foot requirement would reduce the results of Run 3 to levels more closely resembling the results of the existing development results presented by Run 2 (see Figure 3.12-1). $2,500,000 $2,000,000 Structure Estimated Loss (Dollars) Content $1,500,000 $1,000,000 $500,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.12-1. Reedy Creek Watershed Aggregate Damage Estimation Results Table 3.12-2 shows a summary of the building and content damage results by general occupancy classification. Table 3.12-2 shows that damages are concentrated in the 3-176 residential occupancy classification in Runs 1, 2 and 3. Run 2 shows that differences between the 1975 and 2000 flood study nearly double the damages (structure and contents). As expected, there is a significant increase in the losses to residential occupancies in Run 3, because of “development” of vacant parcels. The results are discussed in greater detail later in this report. Table 3.12-2. Summary of Building and Content Damage by General Occupancy: Reedy Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) Structural Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $0 $0 $0 $0 $0 $0 Residential Single and Multi-Family Residential $185,520 $14,271 $351,145 $14,631 $2,048,533 $33,041 Content Damage Total Average Total Average Total Average $0 $0 $0 $0 $0 $7,673 $207,850 $8,660 $1,105,256 $17,827 NonResidential Commercial, Industrial, Religious, Education $0 Residential Single and Multi-Family Residential $99,747 3.12.2 Data Analysis 3.12.2.1 Reedy Creek Basin Characteristics and Study Data Depth grids were created for Reedy Creek and three tributaries contributing flow to Reedy Creek. The grids depict the depth of flooding that will be exceeded with a 1-percent chance in any given year (100-year flood) under both existing and future development conditions. The network of streams analyzed is shown in Figure 3.12-2. 3-177 Figure 3.12-2. Reedy Creek Basin Stream Network The studied reaches include approximately 3.8 miles of Reedy Creek and approximately 4.8 miles of tributary reaches. Flood elevation grids were created interpolating between water surface elevations determined at numerous cross sections along the study reaches. In all, 129 cross sections were used: 59 on Reedy Creek and 70 on the tributaries. The flood elevation grids were extended at the upstream end of each stream, at the confluence with each tributary, and at relatively large areas where floodwaters are not conveyed but, rather, pond at the elevation on the main stream. Where two stream flood elevation grids overlap the final flood elevation grid uses the greater of the two elevations. Depth grids were created by subtracting the ground elevation in the digital elevation model from the flood elevation at the corresponding cell in the elevation grid. Cells with flood depths less than zero (those outside of the floodplain, for example) were deleted from the flood elevation and flood depth grids. 3-178 The resulting existing conditions flood depth grid is shown in Figure 3.12-3. Approximately 414 acres are within the 100-year floodplain. Figure 3.12-4 shows the distribution of floodplain area inundated at 1-foot depth increments. The maximum depth is 16.57 feet. The average (mean) depth is 3.31 feet. Approximately 12 acres are inundated at a depth greater than 10 feet. Figure 3.12-3. Existing Conditions Flood Depth Grid 3-179 Reedy Creek Basin 100 Area Inundated (acres) 90 80 70 60 50 40 30 20 10 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 Flood Depth (feet) Figure 3.12-4. Distribution of Existing Condition Flood Depths The future conditions flood depth grid is shown in Figure 3.12-5. Approximately 484 acres are within the 100-year floodplain, an increase of 80 acres or a little less than 20 percent. The distribution of floodplain area inundated at various depths is shown in Figure 3.12-6. The maximum depth is 18.43 feet (1.86 feet greater than existing conditions). The mean depth is 4.29 feet (about 1 foot greater than existing conditions). The area inundated by more than 10 feet is approximately 25.7 acres (13.7 acres or more than double the existing conditions). 3-180 Figure 3.12-5. Future Conditions Flood Depth Grid Reedy Creek Basin 90 Area Inundated (acres) 80 70 60 50 40 30 20 10 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Flood Depth (feet) Figure 3.12-6. Distribution of Future Condition Flood Depths 3-181 Subtracting the existing conditions flood depth grid from the future conditions flood depth grid yields a grid showing the increase in 100-year flood depths expected as a result of development within the basin. That grid is shown in Figure 3.12-7. The distribution of changes in 100-year flood depths is shown in Figure 3.12-8. Note that most (approximately 73 percent) of the differences are less than two feet. The 100-year flood depth increases are expected to exceed two feet in approximately 132 acres within the Reedy Creek basin. Those increases occur upstream of the Robinson Church Road crossing of Reedy Creek Tributary #2; in most of the Reedy Creek floodplain downstream of the confluence with Reedy Creek Tributary #2; and in the downstream half of the portion of the Reedy Creek Tributary #1 floodplain within Mecklenburg County. Figure 3.12-7. Increases in 100-year Flood Depths 3-182 Reedy Creek Basin 250 Area Affected (acres) 200 150 100 50 0 1 2 3 4 Difference in Flood Depths (feet) Figure 3.12-8. Differences in 100-year Flood Depths 3.12.2.1.1 Reedy Creek Parcel and Building Data Review To determine the parcels and building footprints that may be potentially impacted by inundation from Reedy Creek, the floodplain boundaries from both the 1975 flood study and the 2000 flood study were combined and a buffer of 100-feet added. The buffered boundary was used to select intersecting parcel and every building footprint contained within those parcels. This process was selected because it allows Mecklenburg County to identify all structures that are considered close to the floodplain. Structures outside the flood depth grids do not impact the results of this analysis because they will have no net damage, but knowing what structures are nearby was deemed advantageous to Mecklenburg County. There are 464 parcels that intersect the floodplain boundary (including the 100-foot buffer) surrounding Reedy Creek. Some duplicate parcels were identified and reviewed. In all cases, these turned out to be slivers in the GIS data, most likely right-of-ways that have been either returned to the parcel, or offers of dedication that were never acted upon. In all cases, the slivers were merged back into the main parcel. Of the 464 parcels, 135 (29%) are identified as “vacant”, an additional parcel had information in the “effective area” field in the county assessor data indicating that a structure was on the parcel, 3-183 although no building footprint was available. The percentage of vacant parcels (29% based on 464 parcels) shows that Mecklenburg County has significant opportunities to manage future development and reduce future damage within the watershed. Within these 464 parcels, there are 396 building footprints greater than 500 square feet that are near the buffered floodplain boundary. Of these, none were surveyed as part of the master-elevation-certificate surveys or the “gpsbfe” survey data. For the analysis, the parcel without a building footprint that was identified as non-vacant based on the square footage in the assessors data was carried as single structure at the centroid of the parcel, for a total of 397 “buildings” in the floodplain (including the 100-foot buffer). For the future conditions or “build-out”, a single structure was placed at the centroid of the 135 vacant parcels identified earlier. ®MH HAZUS This structure was established to have the default floor area and value based on the occupancy class assigned to the approved zoning of the parcel (see Tables A-1 and A-2 in Appendix A). Therefore the total “buildings” within the floodplain for the built-out inventory is assumed to be 532. 3.12.3 Detailed Results for the Reedy Creek Basin To determine the potential impacts of floodplain map modifications, three damage estimates have been developed, as follows: 1. Run 1 – current inventory, original floodplain. Estimated losses based on the current building inventory within the Reedy Creek watershed (developed from surveyed data and parcel data) and the original 100-year floodplain boundary, based on the 1975 flood study. 2. Run 2 – current inventory, new floodplain. Estimated losses based on the current building inventory, expanded to include structures within the new floodplain that were previously outside the floodplain, and the newly revised (2000) floodplain boundary. 3. Run 3 – future inventory, new floodplain. Estimated losses to a projected future inventory that incorporates projected growth (“build out”), relative to the new floodplain boundary. 3-184 Table 3.12-3 presents the number of buildings damaged by flooding (i.e., non-zero dollar damage) by occupancy under each of the three scenarios. As noted in Section 2, a HAZUS®MH occupancy class was associated with each occupancy type in the Mecklenburg assessor database. As shown in the figure, the number of damaged buildings increases between runs for the majority of building types. The increase in the number of flooded buildings between Run 1 and Run 2 is due to differences in the floodplain boundary between the 1975 flood study and the 2000 flood study map revisions. The increase between Run 2 and Run 3 is attributable to the projected increase in floodplain development. The values shown in Table 3.12-3 are presented to give the reader perspective on the relative number of flooded buildings, which is useful when viewing the subsequent tables. Table 3.12-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Reedy Creek Watershed HAZUS®MH Occupancy Code Description RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1E Single Family Dwelling, Split Level, with Basement Total No. of flooded buildings Total No. of unflooded buildings Current Inventory, Original Floodplain (Run 1) 7 Current Inventory, New Floodplain (Run 2) 15 Future Inventory, New Floodplain (Run 3) 42 5 8 8 1 1 12 13 24 62 384 373 470 The aggregate dollar damage across all building occupancy types is shown in Figure 3.12-9. As shown, the estimated dollar damage increases from Run 1 to Run 2 and from Run 2 to Run 3. All estimated damage are to residential structures. Tables 3.12-4 through 3.12-7 and the associated discussion go into greater detail about the results of the loss estimation. However, it should be noted that the escalation of estimated damage based on future development validates the need for mitigation measures, such as 3-185 requiring future development to be 1-foot above the future one hundred year flood elevation (as currently proposed by county staff). $2,500,000 $2,000,000 Structure Estimated Loss (Dollars) Content $1,500,000 $1,000,000 $500,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.12-9. Reedy Creek Watershed Aggregate Damage Estimation Results Table 3.12-4 presents the overall average damage percentage calculated for building structures by occupancy, through the application of the various depth-damage curves. Table 3-12.4 shows that the damage (shown in percent) does not change significantly for the existing occupancies within the floodplain between Run 1 and Run 2. New development, shown in Run 3, increases the estimated damage for the RES1A and RES1E occupancies. In Run 1 and Run 2 the average structure damage levels range between 8 and 37 percent. In Run 3, the estimated damage range increases from 9 to 41 percent. It is notable that structure damage over 50% of market value is considered 3-186 “substantial damage”8 by the Federal Insurance and Mitigation Administration. Structures receiving over 50% estimated damage are likely to be excellent acquisition candidates. Table 3.12-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Reedy Creek Watershed HAZUS®MH Occupancy Code Description RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1E Single Family Dwelling, Split Level, with Basement Current Inventory, Original Floodplain (Run 1) 16.3 Current Inventory, New Floodplain (Run 2) 17.8 Future Inventory, New Floodplain (Run 3) 23.2 8.1 9.5 9.5 34.9 36.6 41.1 Table 3.12-5 shows the dollar damage to building structures that is computed when the individual building damage percentages are multiplied by the structure/parcel valuation. As with the previous table, there are significant differences in the dollar damage between the three scenarios. Between Run 1 and Run 2, there is an increase in total structure damage from $186 thousand to $351 thousand. This corresponds to an increase of $166 thousand, or 89%. As the building inventories used for these scenarios are identical, the difference in damage is attributable to differences in the floodplain between the 1975 flood study and the 2000 revision of the 100-yr floodplain map. Proceeding from Run 2 to Run 3, there is a significant increase in estimated damage from $351 thousand to $2 million, suffered by projected development in the floodplain. This corresponds to an increase of $1.7 million, or 483%. 8 According to NFIP guidelines, structures suffering “substantial damage” must be brought up to current floodplain management standards for new (post-FIRM) construction (i.e., removed from the flood hazard area or elevated to or above the level of the base flood elevation, or floodproofed if it is nonresidential). 3-187 Table 3.12-5. Structure Dollar Damage by HAZUS®MH Occupancy Type Reedy Creek Watershed HAZUS®MH Occupancy Code RES1A RES1B RES1E Total Current Inventory, Current Inventory, New Future Inventory, New Original Floodplain Floodplain floodplain (Run 1) (Run 2) (Run 3) Total Avg. Total Avg. Total Avg. $91,779 $13,111 $220,653 $14,710 $1,253,159 $29,837 $44,089 $8,818 $78,396 $9,800 $78,396 $9,800 $49,652 $49,652 $52,096 $52,096 $716,978 $59,748 $185,520 $14,271 $351,145 $14,631 $2,048,533 $33,041 Table 3.12-6 presents the overall average damage percentage calculated for building contents by occupancy type. The estimated damage for contents will typically follow the same general trend as seen in Table 3.12-4. Interestingly, the average estimated damage (percent) does not vary greatly between the three runs. Run 1 and Run 2 are similar in the estimated damage with the exception of the RES1E occupancy. Run 3 resembles Run 2, in terms of percentage and even shows a reduction in the average damage for RES1E due to additional lightly damaged structures. Table 3.12-6. Contents Damage Percent by HAZUS®MH Occupancy Type Reedy Creek Watershed HAZUS®MH Occupancy Code RES1A RES1B RES1E Description Single Family Dwelling, 1 Story, No Basement Single Family Dwelling, 2 Story, No Basement Single Family Dwelling, Split Level, with Basement Current Inventory, Original Floodplain (Run 1) 17.9 Current Inventory, New Floodplain (Run 2) 21.4 Future Inventory, New Floodplain (Run 3) 27.1 8.1 10.7 10.7 38.8 44.4 38.3 Table 3.12-7 provides the estimated dollar damage to building contents by occupancy type. Similar to the structure dollar damage shown in Table 3.12-5, there are significant differences in the dollar damage between scenarios. Between Run 1 and Run 2, there is an increase in total estimated contents damage from $100 thousand to $208 thousand. This corresponds to an increase of $108 thousand, or 108%. The increase in damage is due to changes in the floodplain depth and extent between the 1975 flood study and the recent 2000 revision of the 100-yr floodplain map. Between Run 2 to Run 3, there is a 3-188 significant increase in estimated damage from $208 thousand to $1.1 million attributable to projected growth. This corresponds to an increase of $897 thousand, or 432%. Table 3.12-7. Contents Dollar Damage by HAZUS®MH Occupancy Type Reedy Creek Watershed HAZUS®MH Occupancy Code RES1A RES1B RES1E Total Current Inventory, Current Inventory, New Future Inventory, New Current Floodplain Floodplain Floodplain (Run 1) (Run 2) (Run 3) Total Avg. Total Avg. Total Avg. $50,503 $7,215 $132,113 $8,808 $727,186 $17,314 $21,602 $4,320 $44,149 $5,519 $44,149 $5,519 $27,642 $27,642 $31,588 $31,588 $333,922 $27,827 $99,747 $7,673 $207,850 3-189 $8,660 $1,105,256 $17,827 DETERMINATION OF FINANCIAL IMPACTS FROM FLOOD STUDIES CLARKE CREEK WATERSHED (Report Delivered February 2002) Prepared for: MECKLENBURG COUNTY ENGINEERING & BUILDING STANDARDS Charlotte, NC 28202 3.13 Clarke Creek Analysis 3.13.1 Results Summary for the Clarke Creek Basin Two building inventories and two floodplain scenarios maps were combined to develop damage estimates for the three scenarios listed above. Table 3.13-1 shows a summary of the number of flooded buildings by general occupancy classification. The simulation predicted 1, 1, and 20 damaged buildings from Runs 1, 2, and 3, respectively. Table 3.13-1. Number of Flooded Structures by General Occupancy: Clarke Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) NonResidential Commercial, Industrial, Religious, Education 0 0 0 Residential Single and MultiFamily Residential 1 1 20 1 1 20 Total The dollar damage resulting from the analysis is shown on Figure 3.13-1. The damage for each scenario shown in the figure is an aggregate across all building occupancy types. As shown, there is an increase in estimated damage between Run 1 (structure $173 thousand, contents $118 thousand) and Run 2 (structure $216 thousand, contents $142 thousand). This corresponds to an increase of $43 thousand (25%) for structures and $24 thousand (21%) for contents. The increase demonstrates the effect of changes in the floodplain extent and depth between the 1975 flood study and newly revised (2000) floodplain map. Based on the assumption that the revised floodplain map is more accurate than the 1975 flood study, the estimated damage results from Run 2 are representative of current conditions. It is cautioned that all damages are estimated for a single structure and that the numbers could vary depending on the grid cell from which the estimated depth is taken. 3-190 A comparison of the aggregate damage from Run 2 and Run 3 highlights the difference in damage between current and future building development conditions. For the analysis in Run 3, damage estimates for parcels that are currently vacant were assumed to be developed based on their zoning. The result is an increase in estimated structure damage from $216 thousand to $1.1 million and a corresponding increase in estimated contents damage from $142 thousand to approximately $551 thousand. This corresponds to an increase of $904 thousand (418%) for structures and $409 thousand (288%) for contents. Prior to this analysis, this escalation of potential damages based on future development was predicted by county staff and has led to efforts requiring new development to be 1foot above the one-hundred year base flood elevation, where the BFE includes the increased runoff from the future or ultimate build-out. These results support that effort as the 1-foot requirement would reduce the results of Run 3 to levels more closely resembling the results of the existing development results presented by Run 2 (see Figure 3.13-1). $1,200,000 $1,000,000 Structure Content Estimated Loss (Dollars) $800,000 $600,000 $400,000 $200,000 $Run1 Run2 Run3 Builidng Inventory and Floodplain Scenario Figure 3.13-1. Clarke Creek Watershed Aggregate Damage Estimation Results 3-191 Table 3.13-2 shows a summary of the building and content damage results by general occupancy classification. In general, Table 3.13-2 shows the majority of damages are concentrated in the residential occupancy classification in Runs 1, 2 and 3. Run 2 shows that differences between the 1975 and 2000 flood study nearly double the damages (structure and contents). As expected, there is an increase in the losses to residential occupancies in Run 3, because of “development” of vacant parcels. The results are discussed in greater detail later in this report. Table 3.13-2. Summary of Building and Content Damage by General Occupancy: Clarke Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) Structural Damage Total Average Total Average Total Average $0 $0 $0 $0 $0 $173,044 $216,453 $216,435 $1,120,419 $56,021 NonResidential Commercial, Industrial, Religious, Education $0 Residential Single and Multi-Family Residential $173,044 Content Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $0 $0 $0 $0 $0 $0 Residential Single and Multi-Family Residential $117,825 $117,825 $142,056 $142,056 $551,337 $27,557 3.13.2 Data Analysis 3.13.2.1 Clarke Creek Basin Characteristics and Study Data Clarke Creek is formed by the confluence of the North and South Prongs of Clarke Creek. Depth grids were created for Clarke Creek and five tributaries contributing flow to Clarke Creek. The grids depict the depth of flooding that will be exceeded with a 1-percent 3-192 chance in any given year (100-year flood) under both existing and future development conditions. The network of streams analyzed is shown in Figure 3.13-2. Figure 3.13-2. Clarke Creek Basin Stream Network The studied reaches include approximately 2 miles of Clarke Creek and approximately 13 miles of tributary reaches. Flood elevation grids were created interpolating between water surface elevations determined at numerous cross sections along the study reaches. In all, 180 cross sections were used: 24 on Clarke Creek and 156 on the tributaries. South Prong Clarke Creek and Clarke Creek were analyzed as one continuous reach. The flood elevation grids were extended at the upstream end of each stream, at the confluence with each tributary, and at relatively large areas where floodwaters are not conveyed but, rather, pond at the elevation on the main stream. Where two stream flood elevation grids overlap the final flood elevation grid uses the greater of the two elevations. Depth grids were created by subtracting the ground elevation in the digital elevation model from the flood elevation at the corresponding cell in the elevation grid. Cells with flood depths less than zero (those outside of the floodplain, for example) were deleted from the flood elevation and flood depth grids. 3-193 The resulting existing conditions flood depth grid is shown in Figure 3.13-3. Approximately 869 acres are within the 100-year floodplain. Figure 3.13-4 shows the distribution of floodplain area inundated at 1-foot depth increments. The maximum depth is 19.93 feet. The average (mean) depth is 5.34 feet. Approximately 158.5 acres are inundated at a depth greater than 10 feet. Figure 3.13-3. Existing Conditions Flood Depth Grid 3-194 Clarke Creek Basin 140 Area Inundated (acres) 120 100 80 60 40 20 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Flood Depth (feet) Figure 3.13-4. Distribution of Existing Condition Flood Depths The future conditions flood depth grid is shown in Figure 3.13-5. Approximately 982 acres are within the 100-year floodplain, an increase of 113 acres or approximately 13 percent. The distribution of floodplain area inundated at various depths is shown in Figure 3.13-6. The maximum depth is 22.81 feet (2.88 feet greater than existing conditions). The mean depth is 6.33 feet (about 1 foot greater than existing conditions). The area inundated by more than 10 feet is approximately 220.6 acres (62.1 acres or almost 40 percent more than the existing conditions). 3-195 Figure 3.13-5. Future Conditions Flood Depth Grid Clarke Creek Basin 140 Area Inundated (acres) 120 100 80 60 40 20 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 Flood Depth (feet) Figure 3.13-6. Distribution of Future Condition Flood Depths 3-196 Subtracting the existing conditions flood depth grid from the future conditions flood depth grid yields a grid showing the increase in 100-year flood depths expected as a result of development within the basin. That grid is shown in Figure 3.13-7. The distribution of changes in 100-year flood depths is shown in Figure 3.13-8. Note that all of the differences are less than three feet and most (61 percent) are less than two feet. The 100-year flood depth increases are expected to exceed two feet in approximately 382 acres, mostly in the downstream reaches of Clarke and Ramah Creeks. The increases exceed two feet in small areas just upstream of the Asbury Chapel Road and Ramah Church Road crossings of North Prong Clarke Creek. Figure 3.13-7. Increases in 100-year Flood Depths 3-197 Clarke Creek Basin 450 Area Affected (acres) 400 350 300 250 200 150 100 50 0 1 2 3 Difference in Flood Depths (feet) Figure 3.13-8. Differences in 100-year Flood Depths 3.13.2.1.1 Clarke Creek Parcel and Building Data Review To determine the parcels and building footprints that may be potentially impacted by inundation from Clarke Creek, the floodplain boundaries from both the 1975 flood study and the 2000 flood study were combined and a buffer of 100-feet added. The buffered boundary was used to select intersecting parcel and every building footprint contained within those parcels. This process was selected because it allows Mecklenburg County to identify all structures that are considered close to the floodplain. Structures outside the flood depth grids do not impact the results of this analysis because they will have no net damage, but knowing what structures are nearby was deemed advantageous to Mecklenburg County. There are 249 parcels that intersect the floodplain boundary (including the 100-foot buffer) surrounding Clarke Creek. Some duplicate parcels were identified and reviewed. In all cases, these turned out to be slivers in the GIS data, most likely right-of-ways that have been either returned to the parcel, or offers of dedication that were never acted upon. In all cases, the slivers were merged back into the main parcel. Of the 249 parcels, 122 (49%) are identified as “vacant” and an additional four parcels had information in the “effective area” field in the county assessor data indicating that a structure was on the parcel, although no building footprint was available. The percentage of vacant parcels 3-198 (49% based on 249 parcels) shows that Mecklenburg County has significant opportunities to manage future development and reduce future damage within the watershed. Within these 249 parcels, there are 287 building footprints greater than 500 square feet that are within parcels intersecting the buffered floodplain boundary. Of these, none were surveyed as part of the master-elevation-certificate surveys or the “gpsbfe” survey data. For the analysis, the four parcels without a building footprint that were identified as nonvacant based on the square footage in the assessors data were carried as single structure at the centroid of each parcel, for a total of 291 “buildings” in the floodplain (including the 100-foot buffer). For the future conditions or “build-out”, a single structure was placed at the centroid of the 122 vacant parcels identified earlier. ®MH HAZUS This structure was established to have the default floor area and value based on the occupancy class assigned to the approved zoning of the parcel (see Tables A-1 and A-2 in Appendix A). Therefore the total “buildings” within the floodplain for the built-out inventory is assumed to be 413. 3.13.3 Detailed Results for the Clarke Creek Basin To determine the potential impacts of floodplain map modifications, three damage estimates have been developed, as follows: 1. Run 1 – current inventory, original floodplain. Estimated losses based on the current building inventory within the Clarke Creek watershed (developed from surveyed data and parcel data) and the original 100-year floodplain boundary, based on the 1975 flood study. 2. Run 2 – current inventory, new floodplain. Estimated losses based on the current building inventory, expanded to include structures within the new floodplain that were previously outside the floodplain, and the newly revised (2000) floodplain boundary. 3. Run 3 – future inventory, new floodplain. Estimated losses to a projected future inventory that incorporates projected growth (“build out”), relative to the new floodplain boundary. 3-199 Table 3.13-3 presents the number of buildings damaged by flooding (i.e., non-zero dollar damage) by occupancy under each of the three scenarios. As noted in Section 2, a HAZUS®MH occupancy class was associated with each occupancy type in the Mecklenburg assessor database. As shown in the figure, the number of damaged buildings increases between runs for the majority of building types. The increase in the number of flooded buildings between Run 1 and Run 2 is due to differences in the floodplain boundary between the 1975 flood study and the 2000 flood study map revisions. The increase between Run 2 and Run 3 is attributable to the projected increase in floodplain development. The values shown in Table 3.13-3 are presented to give the reader perspective on the relative number of flooded buildings, which is useful when viewing the subsequent tables. Table 3.13-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Clarke Creek Watershed HAZUS®MH Occupancy Code Description RES1A Single Family Dwelling, 1 Story, No Basement RES1E Single Family Dwelling, Split Level, with Basement Total No. of flooded buildings Total No. of unflooded buildings Current Inventory, Original Floodplain (Run 1) 1 Current Inventory, New Floodplain (Run 2) 1 Future Inventory, New Floodplain (Run 3) 15 --- --- 5 1 1 20 290 290 393 The aggregate dollar damage across all building occupancy types is shown in Figure 3.13-9. As shown, the estimated dollar damage increases from Run 1 to Run 2 and from Run 2 to Run 3. All estimated damages are to residential structures within the Clarke Creek floodplain. Tables 3.13-4 through 3.13-7 and the associated discussion go into greater detail about the results of the loss estimation. However, it should be noted that the escalation of estimated damage based on future development validates the need for mitigation measures, such as requiring future development to be 1-foot above the future one hundred year flood elevation (as currently proposed by county staff). 3-200 $1,200,000 $1,000,000 Structure Content Estimated Loss (Dollars) $800,000 $600,000 $400,000 $200,000 $Run1 Run2 Run3 Builidng Inventory and Floodplain Scenario Figure 3.13-9. Clarke Creek Watershed Aggregate Damage Estimation Results Table 3.13-4 presents the overall average damage percentage calculated for building structures by occupancy, through the application of the various depth-damage curves. Table 3.13-4 shows that the damage (shown in percent) for the RES1A occupancy increases from Run 1 to Run 2 (estimated for a single structure), but decreases slightly for Run 3. The slight reduction is caused by the additional structures (14) impacting the overall average. In Run 1 the estimated average structure damage level is approximately 25 percent, again this is for a single building footprint. Run 2 estimates the damage to that same structure to increase to approximately 31 percent. In Run 3, new development increases the number of structures in the RES1A occupancy and adds several structures in the RES1E classification. The estimated average damage, for Run 3, ranges from approximately 28 percent to 45 percent. It is notable that structure damage over 50% of market value is considered “substantial damage”9 by the Federal Insurance and Mitigation 9 According to NFIP guidelines, structures suffering “substantial damage” must be brought up to current floodplain management standards for new (post-FIRM) construction (i.e., removed from the 3-201 Administration. Structures receiving over 50% estimated damage are likely to be excellent acquisition candidates. Table 3.13-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Clarke Creek Watershed HAZUS®MH Occupancy Code Description RES1A Single Family Dwelling, 1 Story, No Basement RES1E Single Family Dwelling, Split Level, with Basement Current Inventory, Original Floodplain (Run 1) 25.1 Current Inventory, New Floodplain (Run 2) 31.4 Future Inventory, New Floodplain (Run 3) 28.3 --- --- 45.4 Table 3.13-5 shows the dollar damage to building structures that is computed when the individual building damage percentages are multiplied by the structure/parcel valuation. As with the previous table, there are significant differences in the dollar damage between the three scenarios. Between Run 1 and Run 2, there is an increase in total structure damage from $173 thousand to $216 thousand. This corresponds to an increase of $43 thousand, or 25%. As the building inventories used for these scenarios are identical, the difference in damage is attributable to differences in the floodplain between the 1975 flood study and the 2000 revision of the 100-yr floodplain map. Proceeding from Run 2 to Run 3, there is an increase in estimated damage from $216 thousand to $1.1 million, suffered by projected development in the floodplain. This corresponds to an increase of $904 thousand, or 418%. flood hazard area or elevated to or above the level of the base flood elevation, or floodproofed if it is nonresidential). 3-202 Table 3.13-5. Structure Dollar Damage by HAZUS®MH Occupancy Type Clarke Creek Watershed HAZUS®MH Occupancy Code RES1A RES1E Total Current Inventory, Current Inventory, New Future Inventory, New Original Floodplain Floodplain floodplain (Run 1) (Run 2) (Run 3) Total Avg. Total Avg. Total Avg. $173,044 $173,044 $216,453 $216,453 $789,716 $52,648 ---------$330,704 $35,230 $173,044 $173,044 $216,453 $216,453 $1,120,419 $56,021 Table 3.13-6 presents the overall average damage percentage calculated for building contents by occupancy type. The estimated damage for contents will typically follow the same general trend as seen in Table 3.13-4. Run 1 has an estimated damage percentage of 34.2 percent for a single structure within the Clarke Creek floodplain. This range estimated damage for this structure increases to 41.2 percent for Run 2. Run 3, with an increased number of structures in the RES1A classification and the addition of the RES1E classification has a range of contents damage from 24 percent to 44 percent. It is interesting to note the reduction in estimated average damage to the RES1A occupancy (24.1 percent) caused by the addition of a number of structures throughout the floodplain. Table 3.13-6. Contents Damage Percent by HAZUS®MH Occupancy Type Clarke Creek Watershed HAZUS®MH Occupancy Code RES1A RES1E Description Single Family Dwelling, 1 Story, No Basement Single Family Dwelling, Split Level, with Basement Current Inventory, Original Floodplain (Run 1) 34.2 Current Inventory, New Floodplain (Run 2) 41.2 Future Inventory, New Floodplain (Run 3) 24.1 --- --- 48.3 Table 3.13-7 provides the estimated dollar damage to building contents by occupancy type. Similar to the structure dollar damage shown in Table 3.13-5, there are significant differences in the dollar damage between scenarios. Between Run 1 and Run 2, there is an increase in total estimated contents damage from $118 thousand to $142 thousand. This corresponds to an increase of $24 thousand, or 21%. The increase in damage is due to changes in the floodplain depth and extent between the 1975 flood study and the recent 2000 revision of the 100-yr floodplain map. Between Run 2 to Run 3, there is a increase 3-203 in estimated damage from $142 thousand to $551 thousand attributable to projected growth. This corresponds to an increase of $409 thousand, or 288%. Table 3.13-7. Contents Dollar Damage by HAZUS®MH Occupancy Type Clarke Creek Watershed HAZUS®MH Occupancy Code RES1A RES1E Total Current Inventory, Current Inventory, New Future Inventory, New Current Floodplain Floodplain Floodplain (Run 1) (Run 2) (Run 3) Total Avg. Total Avg. Total Avg. $117,825 $117,825 $142,056 $142,056 $375,186 $25,012 --------$176,151 $35,230 $117,825 $117,825 $142,056 3-204 $142,056 $551,337 $27,567 DETERMINATION OF FINANCIAL IMPACTS FROM FLOOD STUDIES MALLARD CREEK WATERSHED (Report Delivered February 2002) Prepared for: MECKLENBURG COUNTY ENGINEERING & BUILDING STANDARDS Charlotte, NC 28202 3.14 Mallard Creek Analysis 3.14.1 Results Summary for the Mallard Creek Basin Two building inventories and two floodplain scenarios maps were combined to develop damage estimates for the three scenarios listed above. Table 3.14-1 shows a summary of the number of flooded buildings by general occupancy classification. The simulation predicted 27, 31, and 125 damaged buildings from Runs 1, 2, and 3, respectively. Table 3.14-1. Number of Flooded Structures by General Occupancy: Mallard Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) NonResidential Commercial, Industrial, Religious, Education 13 14 32 Residential Single and MultiFamily Residential 14 17 93 27 31 125 Total The dollar damage resulting from the analysis is shown on Figure 3.14-1. The damage for each scenario shown in the figure is an aggregate across all building occupancy types. As shown, there is an increase in estimated damage between Run 1 (structure $1.67 million, contents $2.23 million) and Run 2 (structure $1.69 million, contents $2.25 million). This corresponds to an increase of $29 thousand (2%) for structures and $26 thousand (1%) for contents. The increase demonstrates the effect of changes in the floodplain extent and depth between the 1975 flood study and newly revised (2000) floodplain map. Based on the assumption that the revised floodplain map is more accurate than the 1975 flood study, the estimated damage results from Run 2 are representative of current conditions. A comparison of the aggregate damage from Run 2 and Run 3 highlights the difference in damage between current and future building development conditions. For the analysis in Run 3, damage estimates for parcels that are currently vacant were assumed to be 3-205 developed based on their zoning. The result is a sharp increase in estimated structure damage from $1.69 million to $17.2 million and a corresponding increase in estimated contents damage from $2.25 million to approximately $21.2 million. This corresponds to an increase of $15.5 million (917%) for structures and $19 million (841%) for contents. Prior to this analysis, this significant escalation of potential damages based on future development was predicted by county staff and has led to efforts requiring new development to be 1-foot above the one-hundred year base flood elevation, where the BFE includes the increased runoff from the future or ultimate build-out. These results support that effort as the 1-foot requirement would reduce the results of Run 3 to levels more closely resembling the results of the existing development results presented by Run 2 (see Figure 3.14-1). $25,000,000 $20,000,000 Structure Estimated Loss (Dollars) Content $15,000,000 $10,000,000 $5,000,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.14-1. Mallard Creek Watershed Aggregate Damage Estimation Results 3-206 Table 3.14-2 shows a summary of the building and content damage results by general occupancy classification. In general, Table 3.14-2 shows the majority of damages are concentrated in the non-residential occupancy classifications. Run 2 shows that differences between the 1975 and 2000 flood study have very little impact on estimated damages (structure and contents). As expected, there is a significant increase in the losses to residential occupancies in Run 3, because of “development” of vacant parcels, primarily in the non-residential classifications. The results are discussed in greater detail later in this report. Table 3.14-2. Summary of Building and Content Damage by General Occupancy: Mallard Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) Structural Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $1,386,062 $106,620 $1,397,503 $99,822 $13,443,929 $420,123 Residential Single and Multi-Family Residential $279,098 $19,936 $296,340 $17,432 $3,784,529 $40,694 Total Average Content Damage Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $2,134,584 $164,199 $2,149,709 $153,551 $19,495,062 $609,221 Residential Single and Multi-Family Residential $93,744 $6,696 $104,802 $6,165 $1,719,038 $18,484 3-207 3.14.2 Data Analysis 3.14.2.1 Mallard Creek Basin Characteristics and Study Data Depth grids were created for Mallard Creek and ten tributaries contributing flow to Mallard Creek. The grids depict the depth of flooding that will be exceeded with a 1-percent chance in any given year (100-year flood) under both existing and future development conditions. The network of streams analyzed is shown in Figure 3.14-2. Figure 3.14-2. Mallard Creek Basin Stream Network The studied reaches include approximately 10 miles of Mallard Creek and approximately 22.5 miles of tributary reaches. Flood elevation grids were created interpolating between water surface elevations determined at numerous cross sections along the study reaches. In all, 436 cross sections were used: 128 on Mallard Creek and 308 on the tributaries. The flood elevation grids were extended at the upstream end of each stream, at the confluence with each tributary, and at relatively large areas where floodwaters are not conveyed but, rather, pond at the elevation on the main stream. Where two stream flood elevation grids overlap the final flood elevation grid uses the greater of the two elevations. 3-208 Depth grids were created by subtracting the ground elevation in the digital elevation model from the flood elevation at the corresponding cell in the elevation grid. Cells with flood depths less than zero (those outside of the floodplain, for example) were deleted from the flood elevation and flood depth grids. The resulting existing conditions flood depth grid is shown in Figure 3.14-3. Approximately 1300 acres are within the 100-year floodplain. Figure 3.14-4 shows the distribution of floodplain area inundated at 1-foot depth increments. The maximum depth is 25 feet. The average (mean) depth is 6.96 feet. Approximately 413 acres are inundated at a depth greater than 10 feet. Figure 3.14-3. Existing Conditions Flood Depth Grid 3-209 Mallard Creek Basin 160 Area Inundated (acres) 140 120 100 80 60 40 20 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Flood Depth (feet) Figure 3.14-4. Distribution of Existing Condition Flood Depths The future conditions flood depth grid is shown in Figure 3.14-5. Approximately 1403 acres are within the 100-year floodplain, an increase of 103 acres or approximately 8 percent. The distribution of floodplain area inundated at various depths is shown in Figure 3.14-6. The maximum depth is 25 feet (the same as existing conditions). The mean depth is 7.00 feet (about the same as existing conditions). The area inundated by more than 10 feet is approximately 430 acres (about 17 acres or approximately 4 percent more than the existing conditions). 3-210 Figure 3.14-5. Future Conditions Flood Depth Grid Mallard Creek Basin 160 Area Inundated (acres) 140 120 100 80 60 40 20 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Flood Depth (feet) Figure 3.14-6. Distribution of Future Condition Flood Depths 3-211 Subtracting the existing conditions flood depth grid from the future conditions flood depth grid yields a grid showing the increase in 100-year flood depths expected as a result of development within the basin. That grid is shown in Figure 3.14-7. The distribution of changes in 100-year flood depths is shown in Figure 3.14-8. Note that most (97.5 percent) of the differences are less than three feet. Approximately 77.5 percent of the increases are less than one foot. Most of the increases exceeding three feet occur in approximately 25 acres of the Stoney Creek floodplain upstream of the Interstate 85 crossing. The remainder of the increases exceeding three (and ranging up to seven) feet occur upstream of the Interstate 85 crossing of Doby Creek and upstream of the W T Harris Boulevard crossing of Doby Creek Tributary (in the vicinity of the confluence of those two streams). Figure 3.14-7. Increases in 100-year Flood Depths 3-212 Mallard Creek Basin 1200 Area Affected (acres) 1000 800 600 400 200 0 1 2 3 4 5 6 7 8 Difference in Flood Depths (feet) Figure 3.14-8. Differences in 100-year Flood Depths 3.14.2.1.1 Mallard Creek Parcel and Building Data Review To determine the parcels and building footprints that may be potentially impacted by inundation from Mallard Creek, the floodplain boundaries from both the 1975 flood study and the 2000 flood study were combined and a buffer of 100-feet added. The buffered boundary was used to select intersecting parcel and every building footprint contained within those parcels. This process was selected because it allows Mecklenburg County to identify all structures that are considered close to the floodplain. Structures outside the flood depth grids do not impact the results of this analysis because they will have no net damage, but knowing what structures are nearby was deemed advantageous to Mecklenburg County. There are 1,394 parcels that intersect the floodplain boundary (including the 100-foot buffer) surrounding Mallard Creek. Some duplicate parcels were identified and reviewed. In all cases, these turned out to be slivers in the GIS data, most likely right-of-ways that have been either returned to the parcel, or offers of dedication that were never acted upon. In all cases, the slivers were merged back into the main parcel. Of the 1,394 parcels, 474 (34%) are identified as “vacant”, 102 additional parcels had information in the “effective area” field in the county assessor data indicating that a structure was on the parcels, although no building footprint was available. The percentage of vacant parcels 3-213 (34% based on 1,394 parcels) shows that Mecklenburg County has significant opportunities to manage future development and reduce future damage within the watershed. Within these 1,394 parcels, there are 1,476 building footprints greater than 500 square feet that are within parcels intersecting the buffered floodplain boundary. Of these, 69 were surveyed as part of the master-elevation-certificate surveys or the “gpsbfe” survey data. Unfortunately of the 69 data points from the master-elevation-certificate surveys, 9 were missing data in either the first floor elevation or the lowest adjacent grade fields rendering the data unusable. The HAZUS default values were applied to these records. For the analysis, the parcel without a building footprint that was identified as non-vacant based on the square footage in the assessors data was carried as single structure at the centroid of the parcel, for a total of 1,578 “buildings” in the floodplain (including the 100foot buffer). For the future conditions or “build-out”, a single structure was placed at the centroid of the 474 vacant parcels identified earlier. This structure was established to have the HAZUS®MH default floor area and value based on the occupancy class assigned to the approved zoning of the parcel (see Tables A-1 and A-2 in Appendix A). Therefore the total “buildings” within the floodplain for the built-out inventory is assumed to be 2,052. 3.14.3 Detailed Results for the Mallard Creek Basin To determine the potential impacts of floodplain map modifications, three damage estimates have been developed, as follows: 1. Run 1 – current inventory, original floodplain. Estimated losses based on the current building inventory within the Mallard Creek watershed (developed from surveyed data and parcel data) and the original 100-year floodplain boundary, based on the 1975 flood study. 2. Run 2 – current inventory, new floodplain. Estimated losses based on the current building inventory, expanded to include structures within the new floodplain that were previously outside the floodplain, and the newly revised (2000) floodplain boundary. 3-214 3. Run 3 – future inventory, new floodplain. Estimated losses to a projected future inventory that incorporates projected growth (“build out”), relative to the new floodplain boundary. Table 3.14-3 presents the number of buildings damaged by flooding (i.e., non-zero dollar damage) by occupancy under each of the three scenarios. As noted in Section 2, a HAZUS®MH occupancy class was associated with each occupancy type in the Mecklenburg assessor database. As shown in the figure, the number of damaged buildings increases between runs for the majority of building types. The increase in the number of flooded buildings between Run 1 and Run 2 is due to differences in the floodplain boundary between the 1975 flood study and the 2000 flood study map revisions. The increase between Run 2 and Run 3 is attributable to the projected increase in floodplain development. The values shown in Table 3.14-3 are presented to give the reader perspective on the relative number of flooded buildings, which is useful when viewing the subsequent tables. 3-215 Table 3.14-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Mallard Creek Watershed HAZUS®MH Occupancy Description Code COM1 Retail Trade COM1/COM4 Retail Trade and Business/Professional/ Technical Services COM3 Personal and Repair Services COM4 Business/Professional/ Technical Services COM8 Entertainment and Recreation IND1 Heavy Industrial IND2 Light Industrial IND2/IND6 Light Industrial & Construction REL1 Church/Membership Organizations RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement RES2 Manufactured Housing RES3 Multi-Family Dwelling Total No. of flooded buildings Total No. of unflooded buildings Current Inventory, Original Floodplain (Run 1) 2 1 Current Inventory, New Floodplain (Run 2) 3 1 Future Inventory, New Floodplain (Run 3) 3 6 1 1 1 1 1 6 7 7 7 --1 --- --1 --- 5 1 1 --- --- 2 5 5 60 3 5 5 --- 1 1 1 1 19 4 1 27 4 1 31 4 4 125 1,551 1,547 1,927 The aggregate dollar damage across all building occupancy types is shown in Figure 3.14-9. As shown, the estimated dollar damage increases from Run 1 to Run 2 and from Run 2 to Run 3. The majority of damages are to non-residential structures in spite of the fact that for all runs, the residential structures either equal or greatly exceed the number of non-residential structures. For example in Run 1 there are 14 residential and 13 non- 3-216 residential structures. In Run 3 there are 103 residential to 22 non-residential structures. Tables 3.14-4 through 3.14-7 and the associated discussion go into greater detail about the results of the loss estimation. However, it should be noted that the escalation of estimated damage based on future development validates the need for mitigation measures, such as requiring future development to be 1-foot above the future one hundred year flood elevation (as currently proposed by county staff). $25,000,000 $20,000,000 Structure Estimated Loss (Dollars) Content $15,000,000 $10,000,000 $5,000,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.14-9. Mallard Creek Watershed Aggregate Damage Estimation Results Table 3.14-4 presents the overall average damage percentage calculated for building structures by occupancy, through the application of the various depth-damage curves. Table 3.14-4 shows that the damage (shown in percent) does not change significantly for the existing occupancies within the floodplain between Run 1 and Run 2 indicating that the differences between the 1975 flood study and the 2000 flood study did not have a great impact. New development, shown in Run 3, shows the impact of flooding on new development. In Run 1 and Run 2 the average structure damage levels range broadly between 1 and 60 percent. Interestingly enough, Run 3 shows similar impacts as Run 1 3-217 and Run 2 to the existing inventory, but new development shows high damage estimates indicating these parcels are very close to the floodplain. In Run 3, the estimated damages range from 1 to 70 percent with the addition of several non-residential occupancies. It is notable that structure damage over 50% of market value is considered “substantial damage”10 by the Federal Insurance and Mitigation Administration. Structures receiving over 50% estimated damage are likely to be excellent acquisition candidates. Table 3.14-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Mallard Creek Watershed HAZUS®MH Occupancy Code COM1 COM1/COM4 COM3 COM4 COM8 IND1 IND2 IND2/IND6 REL1 RES1A RES1B RES1D RES1E RES2 RES3 Description Retail Trade Retail Trade and Business/Professional/ Technical Services Personal and Repair Services Business/Professional/ Technical Services Entertainment and Recreation Heavy Industrial Light Industrial Light Industrial & Construction Church/Membership Organizations Single Family Dwelling, 1 Story, No Basement Single Family Dwelling, 2 Story, No Basement Single Family Dwelling, Split Level, No Basement Single Family Dwelling, Split Level, with Basement Manufactured Housing Multi-Family Dwelling Current Inventory, Original Floodplain (Run 1) 24.5 60.5 Current Inventory, New Floodplain (Run 2) 25.2 60.5 Future Inventory, New Floodplain (Run 3) 25.2 69.5 16.8 55.1 16.8 55.1 16.8 62.5 23.5 --30.4 ----- 23.5 --30.4 ----- 23.5 19.2 30.4 49.4 25.8 22.3 23.0 29.2 7.8 6.4 6.4 --- 0.5 0.5 28.3 35.3 37.6 45.4 14.1 45.4 14.1 45.4 21.5 Table 3.14-5 shows the dollar damage to building structures that is computed when the individual building damage percentages are multiplied by the structure/parcel valuation. As with the previous table, there are significant differences in the dollar damage between the three scenarios. Between Run 1 and Run 2, there is an increase in total structure 10 According to NFIP guidelines, structures suffering “substantial damage” must be brought up to current floodplain management standards for new (post-FIRM) construction (i.e., removed from the 3-218 damage from $1.67 million to $1.69 million. This corresponds to an increase of $28 thousand, or 2%. As the building inventories used for these scenarios are identical, the difference in damage is attributable to differences in the floodplain between the 1975 flood study and the 2000 revision of the 100-yr floodplain map. Proceeding from Run 2 to Run 3, there is a significant increase in estimated damage from $1.69 million to $17.2 million, suffered by projected development in the floodplain. This corresponds to an increase of $15.5 million, or 917%. Table 3.14-5. Structure Dollar Damage by HAZUS®MH Occupancy Type Mallard Creek Watershed Current Inventory, Current Inventory, New Future Inventory, New HAZUS®MH Original Floodplain Floodplain floodplain Occupancy (Run 1) (Run 2) (Run 3) Code Total Avg. Total Avg. Total Avg. COM1 $69,566 $34,783 $81,007 $27,002 $81,007 $27,002 COM1/COM4 $90,152 $90,152 $90,152 $90,152 $1,578,160 $263,027 COM3 $196,465 $196,465 $196,465 $196,465 $196,465 $196,465 COM4 $17,644 $17,644 $17,644 $17,644 $3,889,066 $648,178 COM8 $995,357 $142,194 $995,357 $142,194 $995,357 $142,194 IND1 --------$5,831,604 $1,166,321 IND2 $16,878 $16,878 $16,878 $16,878 $16,878 $16,878 IND2/IND6 --------$650,169 $650,169 REL1 --------$205,222 $102,611 RES1A $74,140 $14,828 $76,160 $15,232 $2,457,251 $40,954 RES1B $21,197 $7,066 $31,714 $6,343 $31,714 $6,343 RES1D ----$1,008 $1,008 $1,008 $1,008 RES1E $14,982 $14,982 $18,679 $18,679 $1,007,268 $53,014 RES2 $39,342 $9,835 $39,342 $9,835 $39,342 $9,835 RES3 $129,436 $129,436 $129,436 $129,436 $247,946 $61,986 Total $1,665,160 $61,673 $1,693,843 $54,640 $17,228,457 $137,829 Table 3.14-6 presents the overall average damage percentage calculated for building contents by occupancy type. The estimated damage for contents will typically follow the same general trend as seen in Table 3.14-4. Run 1 and Run 2 are virtually identical in terms of estimated damage with one notable exception. Both Run’s have estimated damage percentage ranging from 1 to 86 percent. As expected, the estimated damages for Run 3 range 1 to 86 percent, but shows high content damages in the new development. flood hazard area or elevated to or above the level of the base flood elevation, or floodproofed if it is nonresidential). 3-219 Table 3.14-6. Contents Damage Percent by HAZUS®MH Occupancy Type Mallard Creek Watershed HAZUS®MH Occupancy Code COM1 COM1/COM4 COM3 COM4 COM8 IND1 IND2 IND2/IND6 REL1 RES1A RES1B RES1D RES1E RES2 RES3 Description Retail Trade Retail Trade and Business/Professional/ Technical Services Personal and Repair Services Business/Professional/ Technical Services Entertainment and Recreation Heavy Industrial Light Industrial Light Industrial & Construction Church/Membership Organizations Single Family Dwelling, 1 Story, No Basement Single Family Dwelling, 2 Story, No Basement Single Family Dwelling, Split Level, No Basement Single Family Dwelling, Split Level, with Basement Manufactured Housing Multi-Family Dwelling Current Inventory, Original Floodplain (Run 1) 24.5 60.5 Current Inventory, New Floodplain (Run 2) 25.2 60.5 Future Inventory, New Floodplain (Run 3) 25.2 69.5 85.9 85.9 85.9 55.1 55.1 62.5 23.5 23.5 23.5 --58.7 --- --58.7 --- 48.7 58.7 74.2 --- --- 25.8 27.9 29.6 28.4 10.6 7.8 7.8 --- 1.2 1.2 29.7 40.8 31.2 37.4 1.8 37.4 1.8 37.4 21.2 Table 3.14-7 provides the estimated dollar damage to building contents by occupancy type. Similar to the structure dollar damage shown in Table 3.14-5, there are significant differences in the dollar damage between scenarios. Between Run 1 and Run 2, there is an increase in total estimated contents damage from $2.23 million to $2.25 million. This corresponds to an increase of $26 thousand, or 1%. The increase in damage is due to changes in the floodplain depth and extent between the 1975 flood study and the recent 2000 revision of the 100-yr floodplain map. Between Run 2 to Run 3, there is a significant increase in estimated damage from $2.25 million to $21.2 million attributable to projected growth. This corresponds to an increase of $19 million, or 841%. 3-220 Table 3.14-7. Contents Dollar Damage by HAZUS®MH Occupancy Type Mallard Creek Watershed HAZUS®MH Occupancy Code COM1 COM1/COM4 COM3 COM4 COM8 IND1 IND2 IND2/IND6 REL1 RES1A RES1B RES1D RES1E RES2 RES3 Current Inventory, Current Inventory, New Current Floodplain Floodplain (Run 1) (Run 2) Total Avg. Total Avg. $91,966 $45,983 $107,091 $35,697 $181,476 $181,476 $181,476 $181,476 $502,962 $502,962 $502,962 $502,962 $28,018 $28,018 $28,018 $28,018 $1,313,871 $187,696 $1,313,871 $187,696 --------$16,290 $16,290 $16,290 $16,290 ----------------$47,186 $9,437 $49,588 $9,918 $13,979 $4,660 $18,447 $3,689 ----$1,244 $1,244 $7,845 $7,845 $10,789 $10,789 $16,279 $4,070 $16,279 $4,070 $8,455 $8,455 $8,455 $8,455 Total $2,228,328 $82,531 $2,254,510 3-221 $72,726 Future Inventory, New Floodplain (Run 3) Total Avg. $107,091 $35,697 $3,176,836 $529,473 $502,962 $502,962 $6,175,837 $1,029,306 $1,313,871 $187,696 $7,412,253 $1,482,451 $16,290 $16,290 $488,244 $488,244 $301,677 $150,838 $1,181,899 $19,698 $18,447 $3,689 $1,244 $1,244 $412,087 $21,689 $16,279 $4,070 $89,081 $22,270 $21,214,099 $169,713 DETERMINATION OF FINANCIAL IMPACTS FROM FLOOD STUDIES IRWIN CREEK WATERSHED (Report Delivered July 2002) Prepared for: MECKLENBURG COUNTY ENGINEERING & BUILDING STANDARDS Charlotte, NC 28202 3.15 Irwin Creek Analysis 3.15.1 Results Summary for the Irwin Creek Basin Two building inventories and two floodplain scenarios maps were combined to develop damage estimates for the three scenarios listed above. Table 3.15-1 shows a summary of the number of flooded buildings by general occupancy classification. The simulation predicted 222, 288, and 540 damaged buildings from Runs 1, 2, and 3, respectively. Table 3.15-1. Number of Flooded Structures by General Occupancy: Irwin Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) NonResidential Commercial, Industrial, Religious, Education 62 80 143 Residential Single and MultiFamily Residential 160 208 397 222 288 540 Total The dollar damage resulting from the analysis is shown on Figure 3.15-1. The damage for each scenario shown in the figure is an aggregate across all building occupancy types. As shown, there is an increase in estimated damage between Run 1 (structure $11.17 million, contents $25.89 million) and Run 2 (structure $18.06 million, contents $39.26 million). This corresponds to an increase of $6.9 million (62%) for structures and $13.4 million (52%) for contents. The increase demonstrates the effect of changes in the floodplain extent and depth between the 1975 flood study and newly revised (2000) floodplain map. Based on the assumption that the revised floodplain map is more accurate than the 1975 flood study, the estimated damage results from Run 2 are representative of current conditions. A comparison of the aggregate damage from Run 2 and Run 3 highlights the difference in damage between current and future building development conditions. For the analysis in Run 3, damage estimates for parcels that are currently vacant were assumed to be 3-222 developed based on their zoning. The result is a sharp increase in estimated structure damage from $18.06 million to $46.99 million and a corresponding increase in estimated contents damage from $39.26 million to approximately $63.21 million. This corresponds to an increase of $28.9 million (160%) for structures and $24 million (61%) for contents. Prior to this analysis, this significant escalation of potential damages based on future development was predicted by county staff and has led to efforts requiring new development to be 1-foot above the one-hundred year base flood elevation, where the BFE includes the increased runoff from the future or ultimate build-out. These results support that effort, as the 1-foot requirement would reduce the results of Run 3 to levels more closely resembling the results of the existing development results presented by Run 2 (see Figure 3.15-1). $70,000,000 $60,000,000 Structure Content Estimated Loss ($) $50,000,000 $40,000,000 $30,000,000 $20,000,000 $10,000,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.15-1. Irwin Creek Watershed Aggregate Damage Estimation Results Table 3.15-2 shows a summary of the building and content damage results by general occupancy classification. In general, Table 3.15-2 shows the majority of damages are concentrated in the non-residential occupancy classifications. 3-223 Run 2 shows that differences between the 1975 and 2000 flood study has the general impact of nearly doubling the direct damage from flooding (structure and contents). As expected, there is a significant increase in the losses to residential occupancies in Run 3, because of “development” of vacant parcels, primarily in the non-residential classifications. The results are discussed in greater detail later in this report. Table 3.15-2. Summary of Building and Content Damage by General Occupancy: Irwin Creek Watershed General Occupancy Current Inventory, Original Floodplain (Run 1) Description Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) Structural Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $9,009,667 $145,317 $14,597,630 $182,470 $31,246,516 $218,507 Residential Single and Multi-Family Residential $2,160,318 $13,502 $3,466,881 $16,668 $15,739,958 $39,647 Content Damage Total Average Total Total Average $394,584 $36,978,573 $462,232 $53,294,055 $372,686 $8,927 $2,277,782 $10,951 $9,923,260 $24,996 NonResidential Commercial, Industrial, Religious, Education $24,464,186 Residential Single and Multi-Family Residential $1,428,241 Average 3.15.2 Data Analysis 3.15.2.1 Irwin Creek Basin Characteristics and Study Data Depth grids were created for Irwin Creek and 6 of its tributaries, including Stewart Creek and Kennedy Branch. The grids depict the depth of flooding that will be exceeded with a 1-percent chance in any given year (100-year flood) under both existing and future development conditions. The Irwin Creek stream system is shown in Figure 3.15-2. 3-224 Approximately 22.7 miles of stream were studied, including 10.9 miles of Irwin Creek and 5.3 miles of Stewart Creek. Figure 3.15-2. Irwin Creek Stream System Flood elevation grids were created interpolating between water surface elevations determined at numerous cross sections along the study reaches. In all, 423 cross sections were used: 200 on Irwin Creek; 101 on Stewart Creek; and 122 on the remaining tributaries. The flood elevation grids were extended at the upstream end of each stream, at the confluences of tributaries and Irwin and Stewart Creeks, and at relatively large areas where floodwaters are not conveyed but, rather, pond at the elevation on the main stream. Where the two stream flood elevation grids overlap the final flood elevation grid uses the greater of the two elevations. Depth grids were created by subtracting the ground elevation in the digital elevation model from the flood elevation at the corresponding cell in the elevation grid. Cells with flood depths less than zero (those outside of the floodplain, for example) were deleted from the flood elevation and flood depth grids. The resulting existing conditions flood depth grid is shown in Figure 3.15-3. Approximately 780 acres are within the 100-year floodplain. 3-225 Figure 3.15-4 shows the distribution of floodplain area inundated at 1-foot depth increments. The maximum depth is approximately 31.21 feet. The average (mean) depth is 6.48 feet. Approximately 186 acres are inundated at a depth greater than 10 feet. Figure 3.15-3. Existing Conditions Flood Depth Grid 3-226 Irwin Creek Basin 100 90 80 70 60 50 40 30 20 10 0 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 Flood Depth (feet) Figure 3.15-4. Distribution of Existing Condition Flood Depths The future conditions flood depth grid is shown in Figure 3.15-5. Approximately 1125 acres are within the 100-year floodplain, an increase of 345 acres or about 44 percent. The distribution of floodplain area inundated at various depths is shown in Figure 3.15-6. The maximum depth is 31.37 feet (only 0.16 feet greater than existing conditions). The mean depth is 7.35 feet (0.87 foot greater than existing conditions). The area inundated by more than 10 feet is approximately 297 acres (about 111 acres or about 60 percent more than the existing conditions). 3-227 Figure 3.15-5. Future Conditions Flood Depth Grid Irwin Creek Basin 100 90 80 70 60 50 40 30 20 10 0 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 Flood Depth (feet) Figure 3.15-6. Distribution of Future Condition Flood Depths 3-228 Subtracting the existing conditions flood depth grid from the future conditions flood depth grid yields a grid showing the increase in 100-year flood depths expected as a result of development within the basin. That grid is shown in Figure 3.15-7. The distribution of changes in 100-year flood depths is shown in Figure 3.15-8. Note that about 58 percent of the differences are less than two feet; and about 94 percent are less than 3 feet. The largest area (approximately 273 acres) with a more than two-foot increase in flood depth is along both Irwin and Stewart Creeks upstream of the Southern Railroad crossing of Irwin Creek. The areas just above the MacArthur Avenue crossing (30 acres) and the Interstate Highway 85 and Starita Road crossings (16 acres), all on Irwin Creek, have increases exceeding three feet. Figure 3.15-7. Increases in 100-year Flood Depths 3-229 Irwin Creek Basin 600 Area Affected (acres) 500 400 300 200 100 0 1 2 3 4 5 Difference in Flood Depths (feet) Figure 3.15-8. Differences in 100-year Flood Depths 3.15.2.1.1 Irwin Creek Parcel and Building Data Review To determine the parcels and building footprints that may be potentially impacted by inundation from Irwin Creek, the floodplain boundaries from both the 1975 flood study and the 2000 flood study were combined and a buffer of 100-feet added. The buffered boundary was used to select intersecting parcel and every building footprint contained within those parcels. This process was selected because it allows Mecklenburg County to identify all structures that are considered close to the floodplain. Structures outside the flood depth grids do not impact the results of this analysis because they will have no net damage, but knowing what structures are nearby was deemed advantageous to Mecklenburg County. There are 2,005 parcels that intersect the floodplain boundary (including the 100-foot buffer) surrounding Irwin Creek. Some duplicate parcels were identified and reviewed. In all cases, these turned out to be slivers in the GIS data, most likely right-of-ways that have been either returned to the parcel, or offers of dedication that were never acted upon. In all cases, the slivers were merged back into the main parcel. Of the 2,005 parcels, 638 3-230 (32%) are identified as “vacant” and an additional 21 parcels had information in the “effective area” field in the county assessor data indicating that a structure was on the parcels, although no building footprint was available. The percentage of vacant parcels (32% based on 2,005 parcels) shows that Mecklenburg County has significant opportunities to manage future development and reduce future damage within the watershed. Within these 2,005 parcels, there are 1,896 building footprints greater than 500 square feet that are within parcels intersecting the buffered floodplain boundary. Of these, 345 were surveyed as part of the master-elevation-certificate surveys or the “gpsbfe” survey data. For the analysis, those parcels without a building footprint identified as non-vacant based on the square footage in the assessors data was carried as single structure at the centroid of the parcel, for a total of 1,917 “buildings” in the floodplain (including the 100foot buffer). For the future conditions or “build-out”, a single structure was placed at the centroid of the 638 vacant parcels identified earlier. This structure was established to have the HAZUS®MH default floor area and value based on the occupancy class assigned to the approved zoning of the parcel (see Tables A-1 and A-2 in Appendix A). Therefore the total “buildings” within the floodplain for the built-out inventory is assumed to be 2,555. 3.15.3 Detailed Results for the Irwin Creek Basin To determine the potential impacts of floodplain map modifications, three damage estimates have been developed, as follows: 1. Run 1 – current inventory, original floodplain. Estimated losses based on the current building inventory within the Irwin Creek watershed (developed from surveyed data and parcel data) and the original 100-year floodplain boundary, based on the 1975 flood study. 2. Run 2 – current inventory, new floodplain. Estimated losses based on the current building inventory, expanded to include structures within the new floodplain that were previously outside the floodplain, and the newly revised (2000) floodplain boundary. 3-231 3. Run 3 – future inventory, new floodplain. Estimated losses to a projected future inventory that incorporates projected growth (“build out”), relative to the new floodplain boundary. Table 3.15-3 presents the number of buildings damaged by flooding (i.e., non-zero dollar damage) by occupancy under each of the three scenarios. As noted in Section 2, a HAZUS®MH occupancy class was associated with each occupancy type in the Mecklenburg assessor database. As shown in the figure, the number of damaged buildings increases between runs for the majority of building types. The increase in the number of flooded buildings between Run 1 and Run 2 is due to differences in the floodplain boundary between the 1975 flood study and the 2000 flood study map revisions. The increase between Run 2 and Run 3 is attributable to the projected increase in floodplain development. The values shown in Table 3.15-3 are presented to give the reader perspective on the relative number of flooded buildings, which is useful when viewing the subsequent tables. 3-232 Table 3.15-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Irwin Creek Watershed HAZUS®MH Occupancy Description Code COM1/COM4 Retail Trade and Business/Professional/ Technical Services COM2 Wholesale Trade COM3 Personal and Repair Services COM4 Business/Professional/ Technical Services COM8 Entertainment and Recreation IND2 Light Industrial IND2/IND6 Light Industrial & Construction REL1 Church/Membership Organizations RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1E Single Family Dwelling, Split Level, with Basement RES3 Multi-Family Dwelling Total No. of flooded buildings Total No. of buildings w/out flooding Current Inventory, Original Floodplain (Run 1) 3 Current Inventory, New Floodplain (Run 2) 3 Future Inventory, New Floodplain (Run 3) 20 31 4 35 5 36 5 16 23 43 1 2 2 5 1 8 1 8 26 1 3 3 116 154 297 1 1 1 12 16 43 31 222 37 288 56 540 1,695 1,629 2,015 The aggregate dollar damage across all building occupancy types is shown in Figure 3.15-9. As shown, the estimated dollar damage increases from Run 1 to Run 2 and from Run 2 to Run 3. The majority of damages are to non-residential structures in spite of the fact that for all runs, the residential structures either equal or exceed the number of nonresidential structures. For example in Run 1 there are 160 residential and 62 non- residential structures. In Run 3 there are 397 residential to 143 non-residential structures. Tables 3.15-4 through 3.15-7 and the associated discussion go into greater detail about the results of the loss estimation. However, it should be noted that the escalation of estimated damage based on future development validates the need for mitigation 3-233 measures, such as requiring future development to be 1-foot above the future one hundred year flood elevation (as currently proposed by county staff). $70,000,000 $60,000,000 Structure Content Estimated Loss ($) $50,000,000 $40,000,000 $30,000,000 $20,000,000 $10,000,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.15-9. Irwin Creek Watershed Aggregate Damage Estimation Results Table 3.15-4 presents the overall average damage percentage calculated for building structures by occupancy, through the application of the various depth-damage curves. Because the first two columns in Table 3.15-4 shows the variation in damage between the 1975 flood study and the 2000 flood study, some occupancies display large increases in damage and others experience on small variations most likely controlled by their locations relative to the floodplains. Damage to new development, estimated in Run 3, contributes to generally increasing damage for all most occupancies. In those cases where the estimated average damage (in percent) drops, it gives an indication that the new development is occurring on the fringe of the floodplain and therefore experiencing lower overall damage. It is notable that structure damage over 50% of market value is 3-234 considered “substantial Administration. damage”11 by the Federal Insurance and Mitigation Structures receiving over 50% estimated damage are likely to be excellent acquisition candidates. Table 3.15-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Irwin Creek Watershed HAZUS®MH Occupancy Description Code COM1/COM4 Retail Trade and Business/Professional/ Technical Services COM2 Wholesale Trade COM3 Personal and Repair Services COM4 Business/Professional/ Technical Services COM8 Entertainment and Recreation IND2 Light Industrial IND2/IND6 Light Industrial & Construction REL1 Church/Membership Organizations RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1E Single Family Dwelling, Split Level, with Basement RES3 Multi-Family Dwelling Current Inventory, Original Floodplain (Run 1) 22.0 Current Inventory, New Floodplain (Run 2) 37.3 Future Inventory, New Floodplain (Run 3) 43.5 43.0 12.0 54.2 11.6 53.2 11.6 43.2 46.5 38.1 3.9 5.6 5.6 10.4 3.8 14.1 21.5 14.1 38.5 4.0 15.1 15.1 21.4 24.8 28.5 9.5 12.5 12.5 32.6 32.8 40.0 25.9 30.3 35.6 Table 3.15-5 shows the dollar damage to building structures that is computed when the individual building damage percentages are multiplied by the structure/parcel valuation. As with the previous table, there are significant differences in the dollar damage between the three scenarios. Between Run 1 and Run 2, there is an increase in total structure damage from $11.17 million to $18.06 million. This corresponds to an increase of $6.89 million, or 62%. As the building inventories used for these scenarios are identical, the 11 According to NFIP guidelines, structures suffering “substantial damage” must be brought up to current floodplain management standards for new (post-FIRM) construction (i.e., removed from the 3-235 difference in damage is attributable to differences in the floodplain between the 1975 flood study and the 2000 revision of the 100-yr floodplain map. Proceeding from Run 2 to Run 3, there is a significant increase in estimated damage from $18.06 million to $46.99 million, suffered by projected development in the floodplain. This corresponds to an increase of $28.92 million, or 160%. Nearly $23 million of this increased damage is created by development in three major occupancy classifications COM1/COM4 (Retail trade/Technical Services), IND2/IND6 (Light Industrial/Construction), and RES1A (1-story single family). Table 3.15-5. Structure Dollar Damage by HAZUS®MH Occupancy Type Irwin Creek Watershed HAZUS®MH Occupancy Code COM1/COM4 COM2 COM3 COM4 COM8 IND2 IND2/IND6 REL1 RES1A RES1B RES1E RES3 Total Current Inventory, Original Floodplain (Run 1) Total Avg. $38,800 $12,933 $5,378,445 $173,498 $60,234 $15,058 $3,487,059 $217,941 $15,330 $15,330 $26,566 $5,313 $1,230 $1,230 $2,003 $2,003 $1,040,384 $8,969 $11,123 $11,123 $216,451 $18,038 $892,359 $28,786 $11,169,985 $50,315 Current Inventory, New Future Inventory, New Floodplain floodplain (Run 2) (Run 3) Total Avg. Total Avg. $65,070 $21,690 $3,233,812 $161,691 $7,576,044 $216,458 $7,706,221 $214,062 $69,643 $13,929 $69,643 $13,929 $6,567,450 $285,541 $7,024,847 $163,369 $37,148 $18,574 $37,148 $18,574 $252,556 $31,569 $252,556 $31,569 $7,035 $7,035 $12,899,606 $496,139 $22,684 $7,561 $22,684 $7,561 $1,974,658 $12,822 $8,730,551 $29,396 $14,686 $14,686 $14,686 $14,686 $309,994 $19,375 $2,052,592 $47,735 $1,167,543 $31,555 $4,942,130 $88,252 $18,064,510 $62,724 $46,986,475 $87,012 Table 3.15-6 presents the overall average damage percentage calculated for building contents by occupancy type. The estimated damage for contents will typically follow the same general trend as seen in Table 3.15-4. Estimated content damage between Run 1 and Run 2 experiences increases reflecting differences between the two flood studies and increases are generally across all occupancies. New development results in increased estimated damage with a few occupancies increasing more than others. flood hazard area or elevated to or above the level of the base flood elevation, or floodproofed if it is nonresidential). 3-236 Table 3.15-6. Contents Damage Percent by HAZUS®MH Occupancy Type: Irwin Creek Watershed HAZUS®MH Occupancy Code COM1/COM4 COM2 COM3 COM4 COM8 IND2 IND2/IND6 REL1 RES1A RES1B RES1E RES3 Description Retail Trade and Business/Professional/ Technical Services Wholesale Trade Personal and Repair Services Business/Professional/ Technical Services Entertainment and Recreation Light Industrial Light Industrial & Construction Church/Membership Organizations Single Family Dwelling, 1 Story, No Basement Single Family Dwelling, 2 Story, No Basement Single Family Dwelling, Split Level, with Basement Multi-Family Dwelling Current Inventory, Original Floodplain (Run 1) 22.0 Current Inventory, New Floodplain (Run 2) 37.3 Future Inventory, New Floodplain (Run 3) 43.5 43.8 53.8 56.5 56.1 55.4 56.1 43.2 46.5 35.5 3.9 5.6 5.6 19.4 3.1 25.6 28.8 25.6 55.5 4.0 15.1 15.1 25.1 31.0 32.6 9.0 16.6 16.6 25.5 19.9 25.1 42.6 52.9 64.0 Table 3.15-7 provides the estimated dollar damage to building contents by occupancy type. Similar to the structure dollar damage shown in Table 3.15-5, there are significant differences in the dollar damage between scenarios. Between Run 1 and Run 2, there is an increase in total estimated contents damage from $25.89 million to $39.26 million. This corresponds to an increase of $13.36 million, or 52%. The increase in damage is due to changes in the floodplain depth and extent between the 1975 flood study and the recent 2000 revision of the 100-yr floodplain map. Between Run 2 to Run 3, there is a increase in estimated damage from $39.26 million to $6.22 million attributable to projected growth. This corresponds to an increase of $23.96 million, or 61%. 3-237 Table 3.15-7. Contents Dollar Damage by HAZUS®MH Occupancy Type Irwin Creek Watershed HAZUS®MH Occupancy Code COM1/COM4 COM2 COM3 COM4 COM8 IND2 IND2/IND6 REL1 RES1A RES1B RES1E RES3 Current Inventory, Current Inventory, New Current Floodplain Floodplain (Run 1) (Run 2) Total Avg. Total Avg. $78,104 $26,035 $130,987 $43,662 $18,663,862 $602,060 $25,920,170 $740,576 $138,586 $34,647 $176,766 $35,353 $5,537,449 $346.090 $10,429,110 $453,440 $21,707 $21,707 $52,601 $26,301 $21,030 $4,206 $230,898 $28,862 $502 $502 $4,696 $4,696 $2,944 $2,944 $33,345 $11,115 $612,310 $5,279 $1,151,532 $7,477 $5,292 $5,292 $9,755 $9,755 $85,530 $7,127 $83,783 $5,236 $725,210 $23,394 $1,032,712 $27,911 Total $25,892,527 $116,633 $39,256,355 3-238 $136,307 Future Inventory, New Floodplain (Run 3) Total Avg. $6,509,663 $325,483 $26,371,884 $732,552 $176,766 $35,353 $10,612,706 $246,807 $52,601 $26,301 $230,898 $28,862 $9,306,192 $357,930 $33,345 $11,115 $4,710,916 $15,862 $9,755 $9,755 $636,795 $14,809 $4,565,795 $81,532 $63,217,315 $117,069 DETERMINATION OF FINANCIAL IMPACTS FROM FLOOD STUDIES ROCKY RIVER BASIN (Report Delivered July 2002) Prepared for: MECKLENBURG COUNTY ENGINEERING & BUILDING STANDARDS Charlotte, NC 28202 3.16 Rocky River Analysis 3.16.1 Results Summary for the Rocky River Basin Two building inventories and two floodplain scenarios maps were combined to develop damage estimates for the three scenarios listed above. Table 3.16-1 shows a summary of the number of flooded buildings by general occupancy classification. The simulation predicted 1, 6, and 28 damaged buildings from Runs 1, 2, and 3, respectively. Table 3.16-1. Number of Flooded Structures by General Occupancy: Rocky River Basin General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) NonResidential Commercial, Industrial, Religious, Education 0 1 3 Residential Single and MultiFamily Residential 1 5 25 1 6 28 Total The dollar damage resulting from the analysis is shown on Figure 3.16-1. The damage for each scenario shown in the figure is an aggregate across all building occupancy types. As shown, there is an increase in estimated damage between Run 1 (structure $2,500, contents $1,040) and Run 2 (structure $112.4 thousand, contents $45.7 thousand). This corresponds to an increase of $110 thousand (4,500%) for structures and $44.5 thousand (4,300%) for contents. The increase demonstrates the effect of changes in the floodplain extent and depth between the 1975 flood study and newly revised (2000) floodplain map. Obviously the very large percentage increase is based on a very small number of structures and should be used with caution. Based on the assumption that the revised floodplain map is more accurate than the 1975 flood study, the estimated damage results from Run 2 are representative of current conditions. A comparison of the aggregate damage from Run 2 and Run 3 highlights the difference in damage between current and future building development conditions. For the analysis in 3-239 Run 3, damage estimates for parcels that are currently vacant were assumed to be developed based on their zoning. The result is a sharp increase in estimated structure damage from $112.4 thousand to $1.26 million and a corresponding increase in estimated contents damage from $45.7 thousand to approximately $1.01 million. This corresponds to an increase of $1.15 million (1,025%) for structures and $0.96 million (2,098%) for contents. As with the comparison between Run 1 and Run 2, the large change in damages is driven by a very small number of structures. Prior to this analysis, this significant escalation of potential damages based on future development was predicted by county staff and has led to efforts requiring new development to be 1-foot above the onehundred year base flood elevation, where the BFE includes the increased runoff from the future or ultimate build-out. These results support that effort, as the 1-foot requirement would reduce the results of Run 3 to levels more closely resembling the results of the existing development results presented by Run 2 (see Figure 3.16-1). $1,400,000 Structure Content $1,200,000 Estimated Loss ($) $1,000,000 $800,000 $600,000 $400,000 $200,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.16-1. Rocky River Basin Aggregate Damage Estimation Results Table 3.16-2 shows a summary of the building and content damage results by general occupancy classification. Table 3.16-2 shows the majority of damages are concentrated in the residential occupancy classifications. Run 2 shows that differences between the 3-240 1975 and 2000 flood study has the general impact of increasing direct damage from flooding (structure and contents) by a factor of 50. As expected, future development increases the residential damages (by a factor of 10), but significant increases are also seen in the non-residential classifications. The results are discussed in greater detail later in this report. Table 3.16-2. Summary of Building and Content Damage by General Occupancy: Rocky River Basin General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) Structural Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $0 $0 >$100 >$100 $205,650 $68,550 Residential Single and Multi-Family Residential $2,446 $2,446 $112,396 $22,479 $1,060,261 $42,410 Content Damage Total Average Total Average Total Average $0 $174 $174 $487,747 $162,582 $1,039 $45,553 $9,111 $517,339 $20,693 NonResidential Commercial, Industrial, Religious, Education $0 Residential Single and Multi-Family Residential $1,039 3.16.2 Data Analysis 3.16.2.1 Rocky River Basin Characteristics and Study Data Depth grids were created for Rocky River, West Branch Rocky River and West Branch Rocky River Tributary, and South Prong West Branch Rocky River and South Prong West Branch Rocky River Tributary. The grids depict the depth of flooding that will be exceeded with a 1-percent chance in any given year (100-year flood) under both existing 3-241 and future development conditions. The Rocky River stream system is shown in Figure 3.16-2. Approximately 14.2 miles of stream were studied. Figure 3.16-2. Rocky River Stream System Flood elevation grids were created interpolating between water surface elevations determined at numerous cross sections along the study reaches. In all, 170 cross sections were used: 48 on Rocky River; 75 on West Branch Rocky River and West Branch Rocky River Tributary; and 47 on South Prong West Branch Rocky River and South Prong West Branch Rocky River Tributary. The flood elevation grids were extended at the upstream end of each stream, at the confluences of tributaries and main streams, and at relatively large areas where floodwaters are not conveyed but, rather, pond at the elevation on the main stream. Where the two stream flood elevation grids overlap the final flood elevation grid uses the greater of the two elevations. Depth grids were created by subtracting the ground elevation in the digital elevation model from the flood elevation at the corresponding cell in the elevation grid. Cells with flood depths less than zero (those outside of the floodplain, for example) were deleted from the flood elevation and flood depth grids. 3-242 The resulting existing conditions flood depth grid is shown in Figure 3.16-3. Approximately 873 acres are within the 100-year floodplain. Figure 3.16-4 shows the distribution of floodplain area inundated at 1-foot depth increments. The maximum depth is approximately 17.88 feet. The average (mean) depth is 4.12 feet. Approximately 258 acres are inundated at a depth greater than 5 feet. Figure 3.16-3. Existing Conditions Flood Depth Grid 3-243 Rocky River Basin 160 140 120 100 80 60 40 20 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Flood Depth (feet) Figure 3.16-4. Distribution of Existing Condition Flood Depths The future conditions flood depth grid is shown in Figure 3.16-5. Approximately 978 acres are within the 100-year floodplain, an increase of 105 acres or about 12 percent. The distribution of floodplain area inundated at various depths is shown in Figure 3.16-6. The maximum depth is 20.16 feet (2.28 feet greater than existing conditions). The mean depth is 5.13 feet (1.01 foot greater than existing conditions). The area inundated by more than 5 feet is approximately 460 acres (about 202 acres or 78 percent more than the existing conditions). 3-244 Figure 3.16-5. Future Conditions Flood Depth Grid 3-245 Rocky River Basin 140 120 100 80 60 40 20 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 Flood Depth (feet) Figure 3.16-6. Distribution of Future Condition Flood Depths Subtracting the existing conditions flood depth grid from the future conditions flood depth grid yields a grid showing the increase in 100-year flood depths expected as a result of development within the basin. That grid is shown in Figure 3.16-7. The distribution of changes in 100-year flood depths is shown in Figure 3.16-8. Note that about 45 percent of the differences are less than two feet; and about 90 percent are less than 3 feet. The increase in 100-year flood depth exceeds two feet for essentially the entire study reach of Rocky River. The increase exceeds three feet on Rocky River upstream of the East Rocky River Road crossing (29 acres) and upstream of a private road crossing, 0.75 mile downstream of East Rocky River Road (16 acres). The difference in flood depth exceeds three feet on West Branch Rocky River upstream of the Grey Road crossing (55 acres). 3-246 Figure 3.16-7. Increases in 100-year Flood Depths 3-247 Area Affected (acres) Rocky River Basin 500 450 400 350 300 250 200 150 100 50 0 1 2 3 4 5 6 7 Difference in Flood Depths (feet) Figure 3.16-8. Differences in 100-year Flood Depths 3.16.2.1.1 Rocky River Parcel and Building Data Review To determine the parcels and building footprints that may be potentially impacted by inundation from Rocky River, the floodplain boundaries from both the 1975 flood study and the 2000 flood study were combined and a buffer of 100-feet added. The buffered boundary was used to select intersecting parcel and every building footprint contained within those parcels. This process was selected because it allows Mecklenburg County to identify all structures that are considered close to the floodplain. Structures outside the flood depth grids do not impact the results of this analysis because they will have no net damage, but knowing what structures are nearby was deemed advantageous to Mecklenburg County. There are 263 parcels that intersect the floodplain boundary (including the 100-foot buffer) surrounding the Rocky River basin. Some duplicate parcels were identified and reviewed. In all cases, these turned out to be slivers in the GIS data, most likely right-of-ways that have been either returned to the parcel, or offers of dedication that were never acted upon. In all cases, the slivers were merged back into the main parcel. Of the 263 parcels, 113 (43%) are identified as “vacant” and an additional 6 parcels had information in the “effective area” field in the county assessor data indicating that a structure was on the 3-248 parcels, although no building footprint was available. The percentage of vacant parcels (43% based on 263 parcels) shows that, although a small population of parcels, Mecklenburg County has significant opportunities to manage future development and reduce future damage within the watershed. Within these 263 parcels, there are 253 building footprints greater than 500 square feet that are within parcels intersecting the buffered floodplain boundary. Of these, none were surveyed as part of the master-elevation-certificate surveys or the “gpsbfe” survey data. The lack of MEC survey’s is supported by the very low damages estimated for the 1975 100-year floodplain boundary (Run 1: 1 structure and less than $4,000 in total damage). For the analysis, the additional 6 parcels without a building footprint identified as nonvacant based on the square footage in the assessors data was carried as single structure at the centroid of the parcel, for a total of 259 “buildings” in the floodplain (including the 100-foot buffer). For the future conditions or “build-out”, a single structure was placed at the centroid of the 113 vacant parcels identified earlier. This structure was established to have the HAZUS®MH default floor area and value based on the occupancy class assigned to the approved zoning of the parcel (see Tables A-1 and A-2 in Appendix A). Therefore the total “buildings” within the floodplain for the built-out inventory is assumed to be 372. 3.16.3 Detailed Results for the Rocky River Basin To determine the potential impacts of floodplain map modifications, three damage estimates have been developed, as follows: 1. Run 1 – current inventory, original floodplain. Estimated losses based on the current building inventory within the Rocky River basin (developed from surveyed data and parcel data) and the original 100-year floodplain boundary, based on the 1975 flood study. 2. Run 2 – current inventory, new floodplain. Estimated losses based on the current building inventory, expanded to include structures within the new floodplain that were previously outside the floodplain, and the newly revised (2000) floodplain boundary. 3-249 3. Run 3 – future inventory, new floodplain. Estimated losses to a projected future inventory that incorporates projected growth (“build out”), relative to the new floodplain boundary. Table 3.16-3 presents the number of buildings damaged by flooding (i.e., non-zero dollar damage) by occupancy under each of the three scenarios. As noted in Section 2, a HAZUS®MH occupancy class was associated with each occupancy type in the Mecklenburg assessor database. As shown in the figure, the number of damaged buildings increases between runs for the majority of building types. The increase in the number of flooded buildings between Run 1 and Run 2 is due to differences in the floodplain boundary between the 1975 flood study and the 2000 flood study map revisions. As noted previously, the current impact is fairly limited (1 structure for Run 1 and 5 structures for Run 2). The increase between Run 2 and Run 3 is attributable to the projected increase in potential development within the floodplain. The values shown in Table 3.16-3 are presented to give the reader perspective on the relative number of flooded buildings, which is useful when viewing the subsequent tables. 3-250 Table 3.16-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Rocky River Basin HAZUS®MH Occupancy Description Code COM2 Wholesale Trade COM8 Entertainment and Recreation RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement Total No. of flooded buildings Total No. of buildings w/out flooding Current Inventory, Original Floodplain (Run 1) ----- Current Inventory, New Floodplain (Run 2) 1 --- Future Inventory, New Floodplain (Run 3) 1 2 --- 2 18 1 2 2 --- 1 1 --- --- 4 1 5 28 258 254 344 The aggregate dollar damage across all building occupancy types is shown in Figure 3.16-9. As shown, the estimated dollar damage increases from Run 1 to Run 2 and from Run 2 to Run 3. The majority of damages are to residential structures and the future development does not greatly increase the number of commercial structure impacted. For example in Run 1 there is 1 residential and no non-residential structures. In Run 3 there are 25 residential to 3 non-residential structures. Tables 3.16-4 through 3.16-7 and the associated discussion go into greater detail about the results of the loss estimation. However, it should be noted that the escalation of estimated damage based on future development validates the need for mitigation measures, such as requiring future development to be 1-foot above the future 100-year flood elevation (as currently proposed by county staff). 3-251 $1,400,000 Structure Content $1,200,000 Estimated Loss ($) $1,000,000 $800,000 $600,000 $400,000 $200,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.16-9. Rocky River Basin Aggregate Damage Estimation Results Table 3.16-4 presents the overall average damage percentage calculated for building structures by occupancy, through the application of the various depth-damage curves. Because the first two columns in Table 3.16-4 shows the variation in damage between the 1975 flood study and the 2000 flood study, some occupancies display large increases in damage and others experience on small variations most likely controlled by their locations relative to the floodplains. Damage to new development, estimated in Run 3, contributes to generally increasing damage for all most occupancies. In those cases where the estimated average damage (in percent) drops, it gives an indication that the new development is occurring on the fringe of the floodplain and therefore experiencing lower overall damage. considered It is notable that structure damage over 50% of market value is “substantial damage”12 by the 12 Federal Insurance and Mitigation According to NFIP guidelines, structures suffering “substantial damage” must be brought up to current floodplain management standards for new (post-FIRM) construction (i.e., removed from the flood hazard area or elevated to or above the level of the base flood elevation, or floodproofed if it is nonresidential). 3-252 Administration. Structures receiving over 50% estimated damage are likely to be excellent acquisition candidates. Table 3.16-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Rocky River Basin HAZUS®MH Occupancy Code Description COM2 Wholesale Trade COM8 Entertainment and Recreation RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement Current Inventory, Original Floodplain (Run 1) ----- Current Inventory, New Floodplain (Run 2) >1.0 --- Future Inventory, New Floodplain (Run 3) >1.0 9.4 >1.0 12.7 26.8 --- 5.3 5.3 --- >1.0 >1.0 --- --- 48.5 Table 3.16-5 shows the dollar damage to building structures that is computed when the individual building damage percentages are multiplied by the structure/parcel valuation. As with the previous table, there are significant differences in the dollar damage between the three scenarios. Between Run 1 and Run 2, there is an increase in total structure damage from $2.4 thousand to $112.4 thousand. This corresponds to an increase of $110.0 thousand, or 4,500%. As the building inventories used for these scenarios are identical, the difference in damage is attributable to differences in the floodplain between the 1975 flood study and the 2000 revision of the 100-year floodplain map. As noted previously, the total number of structures impacted by the changes are very small and therefore may skew the percentages. Changes in the assumptions could lead to variations in the results. Proceeding from Run 2 to Run 3, there is a significant increase in estimated damage from $112.4 thousand to $1.3 million, suffered by projected development in the floodplain. This corresponds to an increase of $1.15 million, or 1,026%. The greatest increase in losses is seen in the residential classification with all but approximately $200 thousand dollars of the estimated losses. Table 3.16-5. Structure Dollar Damage by HAZUS®MH Occupancy Type Rocky River Basin 3-253 HAZUS®MH Occupancy Code COM2 COM8 RES1A RES1B RES1D RES1E Total Current Inventory, Current Inventory, New Future Inventory, New Original Floodplain Floodplain floodplain (Run 1) (Run 2) (Run 3) Total Avg. Total Avg. Total Avg. ---->$100 >$100 >$100 >$100 --------$205,600 $102,800 ----$77,744 $38,872 $743,195 $41,289 $2,446 $2,446 $32,677 $16,338 $32,677 $16,338 ----$1,975 $1,975 $1,975 $1,975 --------$282,413 $70,603 $2,446 $2,446 $112,446 $18,741 $1,265,911 $45.211 Table 3.16-6 presents the overall average damage percentage calculated for building contents by occupancy type. The estimated damage for contents will typically follow the same general trend as seen in Table 3.16-4. Estimated content damage between Run 1 and Run 2 experiences increases reflecting differences between the two flood studies and increases are generally across all occupancies. New development results in increased estimated damage with the addition of some non-residential development and increasing residential losses. Table 3.16-6. Contents Damage Percent by HAZUS®MH Occupancy Type Rocky River Basin HAZUS®MH Occupancy Code COM2 COM8 RES1A RES1B RES1D RES1E Description Wholesale Trade Entertainment and Recreation Single Family Dwelling, 1 Story, No Basement Single Family Dwelling, 2 Story, No Basement Single Family Dwelling Split Level, No Basement Single Family Dwelling, Split Level, with Basement Current Inventory, Original Floodplain (Run 1) ----- Current Inventory, New Floodplain (Run 2) >1.0 --- Future Inventory, New Floodplain (Run 3) >1.0 44.6 --- 9.4 31.3 >1.0 4.9 4.9 --- 2.1 2.1 --- --- 25.8 Table 3.16-7 provides the estimated dollar damage to building contents by occupancy type. Similar to the structure dollar damage shown in Table 3.16-5, there are significant differences in the dollar damage between scenarios. Between Run 1 and Run 2, there is an increase in total estimated contents damage from $1 thousand to $45.7 thousand. This corresponds to an increase of $44.7 thousand, or 4,300%. The increased damage is seen in a small number of structures within the floodplain. The increase in damage is due 3-254 to changes in the floodplain depth and extent between the 1975 flood study and the recent 2000 revision of the 100-yr floodplain map. Between Run 2 to Run 3, there is a increase in estimated damage from $45.7 thousand to $1.01million attributable to projected growth. This corresponds to an increase of $959.3 thousand, or 2,100%. Table 3.16-7. Contents Dollar Damage by HAZUS®MH Occupancy Type Rocky River Basin HAZUS®MH Occupancy Code COM2 COM8 RES1A RES1B RES1D RES1E Total Current Inventory, Current Inventory, New Current Floodplain Floodplain (Run 1) (Run 2) Total Avg. Total Avg. ----$174 $174 ------------$27,868 $13,934 $1,039 $1,039 $15,246 $7,623 ----$2,438 $2,438 --------$1,039 $1,039 $45,727 3-255 $7,621 Future Inventory, New Floodplain (Run 3) Total Avg. $174 $174 $487,573 $243,786 $424,637 $23,591 $15,246 $7,623 $2,438 $2,438 $75,018 $18,754 $1,005,086 $35,896 DETERMINATION OF FINANCIAL IMPACTS FROM FLOOD STUDIES GOOSE CREEK WATERSHED (Report Delivered October 2002) Prepared for: MECKLENBURG COUNTY ENGINEERING & BUILDING STANDARDS Charlotte, NC 28202 3.17 Goose Creek Analysis 3.17.1 Results Summary for the Goose Creek Basin Two building inventories and two floodplain scenarios maps were combined to develop damage estimates for the three scenarios listed above. Table 3.17-1 shows a summary of the number of flooded buildings by general occupancy classification. The simulation predicted 6, 11, and 17 damaged buildings from Runs 1, 2, and 3, respectively. Table 3.17-1. Number of Flooded Structures by General Occupancy: Goose Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) NonResidential Commercial, Industrial, Religious, Education 0 0 0 Residential Single and MultiFamily Residential 6 11 17 6 11 17 Total The dollar damage resulting from the analysis is shown on Figure 3.17-1. The damage for each scenario shown in the figure is an aggregate across all building occupancy types. As shown, there is an increase in estimated damage between Run 1 (structure $45,640, contents $17,300) and Run 2 (structure $135,710, contents $63,890). This corresponds to an increase of $90 thousand (197%) for structures and $46.5 thousand (269%) for contents. The increase demonstrates the effect of changes in the floodplain extent and depth between the 1975 flood study and newly revised 2000 flood study map. Based on the assumption that the revised floodplain map is more accurate than the 1975 flood study, the estimated damage results from Run 2 are representative of current conditions. A comparison of the aggregate damage from Run 2 and Run 3 highlights the difference in damage between current and future building development conditions. For the analysis in Run 3, damage estimates for parcels that are currently vacant were assumed to be developed based on their zoning. The result is an increase in estimated structure damage 3-256 from $135,710 to $348,190 and a corresponding increase in estimated contents damage from $63,890 to approximately $164,780. This represents an increase of $212,480 (157%) for structures and $100,890 (158%) for contents. Prior to this analysis, this escalation of potential damages based on future development was predicted by county staff and has led to efforts requiring new development to be 1-foot above the one-hundred year base flood elevation, where the BFE includes the increased runoff from the future or ultimate build-out. These results support that effort, as the 1-foot requirement would reduce the results of Run 3 to levels more closely resembling the results of the existing development results presented by Run 2 (see Figure 3.17-1). $400,000 $350,000 Structure Content $300,000 Estimated Loss ($) $250,000 $200,000 $150,000 $100,000 $50,000 $Run1 Run2 Building Inventory and Floodplain Scenario Run3 Figure 3.17-1. Goose Creek Watershed Aggregate Damage Estimation Results Table 3.17-2 shows a summary of the building and content damage results by general occupancy classification. In general, Table 3.17-2 shows that the damages are concentrated in the residential occupancy classifications. Run 2 shows that differences 3-257 between the 1975 and 2000 flood study have a relatively significant impact (structure and contents). As expected, there is also a significant increase in the losses to residential occupancies in Run 3, because of “development” of vacant parcels. The results are discussed in greater detail later in this report. Table 3.17-2. Summary of Building and Content Damage by General Occupancy: Goose Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) Structural Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $0 $0 $0 $0 $0 $0 Residential Single and Multi-Family Residential $45,644 $7,607 $135,712 $12,337 $348,193 $9,693 Content Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $0 $0 $0 $0 $0 $0 Residential Single and Multi-Family Residential $17,303 $2,884 $63,890 $5,808 $164,781 $9,693 3.17.2 Data Analysis 3.17.2.1 Goose Creek Basin Characteristics and Study Data The portion of Goose Creek basin above the confluence with Stevens Creek is located in southeastern portion of Mecklenburg County. Depth grids were created for Goose Creek, its major tributary, Stevens Creek, and Stevens Creek Tributary. The grids depict the depth of flooding that will be exceeded with a 1-percent chance in any given year (100- 3-258 year flood) under both existing and future development conditions. The network of streams analyzed is shown in Figure 3.17-2. Figure 3.17-2. Goose Creek Basin Stream Network The studied reaches include approximately 1.9 miles of Goose Creek and approximately 2.8 miles of Stevens Creek and Stevens Creek Tributary. Flood elevation grids were created interpolating between water surface elevations determined at numerous cross sections along the study reaches. In all, 63 cross sections were used: 27 on Goose Creek, 25 on Stevens Creek, and 11 on Stevens Creek Tributary. The flood elevation grids were extended at the upstream end of each stream, at the confluence with each tributary, and at relatively large areas where floodwaters are not conveyed but, rather, pond at the elevation on the main stream. Where two stream flood elevation grids overlap the final flood elevation grid uses the greater of the two elevations. Depth grids were created by subtracting the ground elevation in the digital elevation model from the flood elevation at the corresponding cell in the elevation grid. Cells with flood depths less than zero (those outside of the floodplain, for example) were deleted from the flood elevation and flood depth grids. 3-259 The resulting existing conditions flood depth grid is shown in Figure 3.17-3. Approximately 152 acres are within the 100-year floodplain. Figure 3.17-4 shows the distribution of floodplain area inundated at 1-foot depth increments. The maximum depth is 12.40 feet. The average (mean) depth is 2.72 feet. Approximately 16.8 acres are inundated at a depth greater than 5 feet. Figure 3.17-3. Existing Conditions Flood Depth Grid 3-260 Goose Creek Basin 45 Area Inundated (acres) 40 35 30 25 20 15 10 5 0 1 2 3 4 5 6 7 8 9 10 11 12 13 Flood Depth (feet) Figure 3.17-4. Distribution of Existing Condition Flood Depths The future conditions flood depth grid is shown in Figure 3.17-5. Approximately 171 acres are within the 100-year floodplain, an increase of 19 acres or approximately 12.5 percent. The distribution of floodplain area inundated at various depths is shown in Figure 3.17-6. The maximum depth is 14.18 feet (1.78 feet greater than existing conditions). The mean depth is 3.37 feet (0.65 foot greater than existing conditions). The area inundated by more than 5 feet is approximately 34 acres (17.2 acres more or double the existing conditions). 3-261 Figure 3.17-5. Future Conditions Flood Depth Grid 3-262 Goose Creek Basin Area Inundated (acres) 40 35 30 25 20 15 10 5 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Flood Depth (feet) Figure 3.17-6. Distribution of Future Condition Flood Depths Subtracting the existing conditions flood depth grid from the future conditions flood depth grid yields a grid showing the increase in 100-year flood depths expected as a result of development within the basin. That grid is shown in Figure 3.17-7. The distribution of changes in 100-year flood depths is shown in Figure 3.17-8. Note that about 93 percent of the differences are less than two feet and most (70 percent) are less than one foot. The 100-year flood depth increases are expected to exceed two feet in approximately 12.5 acres, just upstream of the Interstate Highway 485 crossing of Stevens Creek. 3-263 Figure 3.17-7. Increases in 100-year Flood Depths Goose Creek Basin 140 Area Affected (acres) 120 100 80 60 40 20 0 1 2 3 4 5 Difference in Flood Depths (feet) Figure 3.17-8. Differences in 100-year Flood Depths 3-264 3.17.2.1.1 Goose Creek Parcel and Building Data Review To determine the parcels and building footprints that may be potentially impacted by inundation from Goose Creek, the floodplain boundaries from both the 1975 flood study and the 2000 flood study were combined and a buffer of 100-feet added. The buffered boundary was used to select intersecting parcel and every building footprint contained within those parcels. This process was selected because it allows Mecklenburg County to identify all structures that are considered close to the floodplain. Structures outside the flood depth grids do not impact the results of this analysis because they will have no net damage, but knowing what structures are nearby was deemed advantageous to Mecklenburg County. There are 135 parcels that intersect the floodplain boundary (including the 100-foot buffer) surrounding Goose Creek. Some duplicate parcels were identified and reviewed. In all cases, these turned out to be slivers in the GIS data, most likely right-of-ways that have been either returned to the parcel, or offers of dedication that were never acted upon. In all cases, the slivers were merged back into the main parcel. Of the 135 parcels, 22 (16%) are identified as “vacant” and an additional 1 parcel had information in the “effective area” field in the county assessor data indicating that a structure was on the parcels, although no building footprint was available. The percentage of vacant parcels (16% based on 135 parcels) is relatively low compared to other watersheds, but Mecklenburg County still has opportunities to manage future development and reduce future damage within the watershed. Within these 135 parcels, there are 175 building footprints greater than 500 square feet that are within parcels intersecting the buffered floodplain boundary. None of these were surveyed as part of the master-elevation-certificate surveys or the “gpsbfe” survey data. For the analysis, the single parcel without a building footprint that was identified as nonvacant based on the square footage in the assessors data was carried as single structure at the centroid of the parcel, for a total of 176 “buildings” in the floodplain (including the 100-foot buffer). For the future conditions or “build-out”, a single structure was placed at the centroid of the 22 vacant parcels identified earlier. This structure was established to have the HAZUS®MH default floor area and value based on the occupancy class assigned to the approved 3-265 zoning of the parcel (see Tables A-1 and A-2 in Appendix A). Therefore the total “buildings” within the floodplain for the built-out inventory is assumed to be 198. 3.17.3 Detailed Results for the Goose Creek Basin To determine the potential impacts of floodplain map modifications, three damage estimates have been developed, as follows: 1. Run 1 – current inventory, original floodplain. Estimated losses based on the current building inventory within the Goose Creek watershed (developed from surveyed data and parcel data) and the original 100-year floodplain boundary, based on the 1975 flood study. 2. Run 2 – current inventory, new floodplain. Estimated losses based on the current building inventory, expanded to include structures within the new floodplain that were previously outside the floodplain, and the newly revised (2000) floodplain boundary. 3. Run 3 – future inventory, new floodplain. Estimated losses to a projected future inventory that incorporates projected growth (“build out”), relative to the new floodplain boundary. Table 3.17-3 presents the number of buildings damaged by flooding (i.e., non-zero dollar damage) by occupancy under each of the three scenarios. As noted in Section 2, a HAZUS®MH occupancy class was associated with each occupancy type in the Mecklenburg assessor database. As shown in the figure, the number of damaged buildings increases between runs for the majority of building types. The increase in the number of flooded buildings between Run 1 and Run 2 is due to differences in the floodplain boundary between the 1975 flood study and the 2000 flood study map revisions. The increase between Run 2 and Run 3 is attributable to the projected increase in floodplain development. The values shown in Table 3.17-3 are presented to give the reader perspective on the relative number of flooded buildings, which is useful when viewing the subsequent tables. 3-266 Table 3.17-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Goose Creek Watershed HAZUS®MH Occupancy Description Code RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement Total No. of flooded buildings Total No. of unflooded buildings Current Inventory, Original Floodplain (Run 1) 3 Current Inventory, New Floodplain (Run 2) 5 Future Inventory, New Floodplain (Run 3) 9 3 4 4 --- 1 1 --- 1 3 6 11 17 170 165 181 The aggregate dollar damage across all building occupancy types is shown in Figure 3.17-9. As shown, the estimated dollar damage increases from Run 1 to Run 2 and from Run 2 to Run 3. The majority of damages are to residential structures, further review of the parcel data indicated that none of the parcels within the floodplain are zoned for any other use. Tables 3.17-4 through 3.17-7 and the associated discussion go into greater detail about the results of the loss estimation. However, it should be noted that the escalation of estimated damage based on future development validates the need for mitigation measures, such as requiring future development to be 1-foot above the future one hundred year flood elevation (as currently proposed by county staff). 3-267 $400,000 $350,000 Structure Content $300,000 Estimated Loss ($) $250,000 $200,000 $150,000 $100,000 $50,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.17-9. Goose Creek Watershed Aggregate Damage Estimation Results Table 3.17-4 presents the overall average damage percentage calculated for building structures by occupancy, through the application of the various depth-damage curves. Table 3.17-4 shows that the damage (shown in percent) changed for the existing occupancies within the floodplain between Run 1 and Run 2 indicating that the differences between the 1975 flood study and the 2000 flood study impacted some structures currently outside the 1975 100-year study and increased damage for those within the 1975 floodplain. Ironically, new development, shown in Run 3, did not increase the average damage (%) greatly. In Run 1 the estimated damage runs from 5 to 11 percent while in Run 2 the average structure damage levels ranges from less than 1 percent to nearly 31 percent. Interestingly enough, Run 3 shows similar impacts as Run 2 to the existing inventory, but increased losses indicates that some of the new development is within the floodplain. It is notable that structure damage over 50% of market value is 3-268 considered “substantial Administration. damage”13 by the Federal Insurance and Mitigation Structures receiving over 50% estimated damage are likely to be excellent acquisition candidates. Table 3.17-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Goose Creek Watershed HAZUS®MH Occupancy Description Code RES1A Single Family Dwelling, 1 Story, No Basement RES1B Single Family Dwelling, 2 Story, No Basement RES1D Single Family Dwelling, Split Level, No Basement RES1E Single Family Dwelling, Split Level, with Basement Current Inventory, Original Floodplain (Run 1) 11.7 Current Inventory, New Floodplain (Run 2) 12.6 Future Inventory, New Floodplain (Run 3) 13.7 5.1 9.0 9.0 --- 0.7 0.7 --- 30.4 38.8 Table 3.17-5 shows the dollar damage to building structures that is computed when the individual building damage percentages are multiplied by the structure/parcel valuation. As with the previous table, there are significant differences in the dollar damage between the three scenarios. Between Run 1 and Run 2, there is an increase in total structure damage from $45,644 to $135,712. This corresponds to an increase of $90 thousand, or 197%. As the building inventories used for these scenarios are identical, the difference in damage is attributable to differences in the floodplain between the 1975 flood study and the 2000 revision of the 100-yr floodplain map. Proceeding from Run 2 to Run 3, there is a significant increase in estimated damage from $135,712 to $348,193 suffered by projected development in the floodplain. This corresponds to an increase of $212,481 or 156%. As the flood depths are unchanged, the differences between Run 2 and Run 3 can be attributed to the new development within the floodplain. Table 3.17-5. Structure Dollar Damage by HAZUS®MH Occupancy Type Goose Creek Watershed 13 According to NFIP guidelines, structures suffering “substantial damage” must be brought up to current floodplain management standards for new (post-FIRM) construction (i.e., removed from the flood hazard area or elevated to or above the level of the base flood elevation, or floodproofed if it is nonresidential). 3-269 HAZUS®MH Occupancy Code RES1A RES1B RES1D RES1E Total Current Inventory, Current Inventory, New Future Inventory, New Original Floodplain Floodplain floodplain (Run 1) (Run 2) (Run 3) Total Avg. Total Avg. Total Avg. $28,897 $9,632 $52,936 $10,587 $140,144 $15,572 $16,748 $5,583 $43,898 $10,974 $43,898 $10,974 ----$840 $840 $840 $840 ----$38,039 $38,039 $163,311 $54,437 $45,644 $7,607 $135,712 $12,337 $348,193 $20,482 Table 3.17-6 presents the overall average damage percentage calculated for building contents by occupancy type. The estimated damage for contents will typically follow the same general trend as seen in Table 3.17-4. Run 1 has relatively limited damage while Run 2 shows increased damages and additional residential occupancies involved in flooding. The estimated damage in Run 1 varies from 4 to 8 percent, whereas damage in Run 2 runs from 1 percent to 32 percent. As expected, the estimated damages for Run 3 are higher still, ranging from 1 percent to 36 percent. Table 3.17-6. Contents Damage Percent by HAZUS®MH Occupancy Type Goose Creek Watershed HAZUS®MH Occupancy Code RES1A RES1B RES1D RES1E Description Single Family Dwelling, 1 Story, No Basement Single Family Dwelling, 2 Story, No Basement Single Family Dwelling, Split Level, No Basement Single Family Dwelling, Split Level, with Basement Current Inventory, Original Floodplain (Run 1) 8.3 Current Inventory, New Floodplain (Run 2) 10.8 Future Inventory, New Floodplain (Run 3) 12.8 4.3 8.5 8.5 --- 1.6 1.6 --- 31.6 36.4 Table 3.17-7 provides the estimated dollar damage to building contents by occupancy type. Similar to the structure dollar damage shown in Table 3.17-5, there are significant differences in the dollar damage between scenarios. Between Run 1 and Run 2, there is an increase in total estimated contents damage from $17,303 to $63,890. This corresponds to an increase of $47 thousand, or 269%. The increase in damage is due to changes in the floodplain depth and extent between the 1975 flood study and the recent 2000 revision of the 100-yr floodplain map. Between Run 2 to Run 3, there is a significant increase in estimated damage from $63,890 to $164,781 attributable to projected growth. This corresponds to an increase of $101 thousand, or 158%. 3-270 Table 3.17-7. Contents Dollar Damage by HAZUS®MH Occupancy Type Goose Creek Watershed HAZUS®MH Occupancy Code RES1A RES1B RES1D RES1E Total Current Inventory, Current Inventory, New Current Floodplain Floodplain (Run 1) (Run 2) Total Avg. Total Avg. $10,188 $3,396 $22,402 $4,480 $7,115 $2,372 $20,640 $5,160 ----$1,036 $1,036 ----$19,812 $19,812 $17,303 $2,884 $63,890 3-271 $5,808 Future Inventory, New Floodplain (Run 3) Total Avg. $66,789 $7,421 $20,640 $5,160 $1,036 $1,036 $76,315 $25,438 $164,781 $9,693 DETERMINATION OF FINANCIAL IMPACTS FROM FLOOD STUDIES LOWER CLARKE CREEK WATERSHED (Report Delivered October 2002) Prepared for: MECKLENBURG COUNTY ENGINEERING & BUILDING STANDARDS Charlotte, NC 28202 3.18 Lower Clarke Creek Analysis 3.18.1 Results Summary for the Lower Clarke Creek Tributary Basin Two building inventories and two floodplain scenarios maps were combined to develop damage estimates for the three scenarios listed above. Table 3.18-1 shows a summary of the number of flooded buildings by general occupancy classification. The simulation predicted 0, 0, and 2 damaged buildings from Runs 1, 2, and 3, respectively. Table 3.18-1. Number of Flooded Structures by General Occupancy: Lower Clarke Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) NonResidential Commercial, Industrial, Religious, Education 0 0 0 Residential Single and MultiFamily Residential 0 0 2 0 0 2 Total The dollar damage resulting from the analysis is shown on Figure 3.18-1. The damage for each scenario shown in the figure is an aggregate across all building occupancy types. As shown, it is estimated that all structures are outside of the 100-year floodplain or are not damaged when the analysis is performed for Run 1 and Run 2. The increase demonstrates the effect of changes in the floodplain extent and depth between the 1975 flood study and newly revised (2000) floodplain map. While the new maps can be considered more accurate, it appears that changes between the 1975 study and the 2000 study do not impact any structures. A comparison of the aggregate damage from Run 2 and Run 3 highlights the difference in damage between current and future building development conditions. For the analysis in Run 3, damage estimates for parcels that are currently vacant were assumed to be developed based on their zoning. The result is an increase in estimated structure damage from no damage (Run 2) to $125 thousand and a corresponding increase in estimated 3-272 contents damage from no damage to approximately $77 thousand. Prior to this analysis, this significant escalation of potential damages based on future development was predicted by county staff and has led to efforts requiring new development to be 1-foot above the one-hundred year base flood elevation, where the BFE includes the increased runoff from the future or ultimate build-out. These results support that effort as the 1-foot requirement would reduce the results of Run 3 to levels more closely resembling the results of the existing development results presented by Run 2 (see Figure 3.18-1). The results of this analysis indicate that for this watershed, Mecklenburg County could greatly reduce, or potentially eliminate, losses due to new development through effective floodplain management. $140,000 $120,000 Structure Content Estimated Loss ($) $100,000 $80,000 $60,000 $40,000 $20,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.18-1. Clarke Creek Tributary Aggregate Damage Estimation Results Table 3.18-2 shows a summary of the building and content damage results by general occupancy classification. In general, Table 3.18-2 shows the damages are concentrated in the residential occupancy classifications. Run 2 shows that differences between the 1975 and 2000 flood study have no impact on estimated damages (structure and contents). As expected, there is an increase in the losses to residential occupancies in 3-273 Run 3, because of “development” of vacant parcels. It should be noted that these results are for a small number of structures and therefore should be viewed with caution. However, this also indicates a unique opportunity to eliminate the potential for losses. The results are discussed in greater detail in Section 3 of this report. Table 3.18-2. Summary of Building and Content Damage by General Occupancy: Lower Clarke Creek Watershed General Occupancy Description Current Inventory, Original Floodplain (Run 1) Current Inventory, New Floodplain (Run 2) Future Inventory, New Floodplain (Run 3) Structural Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $0 $0 $0 $0 $0 $0 Residential Single and Multi-Family Residential $0 $0 $0 $0 $125,001 $62,500 Content Damage Total Average Total Average Total Average NonResidential Commercial, Industrial, Religious, Education $0 $0 $0 $0 $0 $0 Residential Single and Multi-Family Residential $0 $0 $0 $0 $77,407 $38,704 3.18.2 Data Analysis 3.18.2.1 Clarke Creek Tributary Basin Characteristics and Study Data Clarke Creek Tributary enters Clarke Creek east of Mecklenburg County. The area of Mecklenburg County draining to Clark Creek Tributary is located between the Clarke Creek (to the north) and Mallard Creek (to the south) Basins. Depth grids were created for Clarke Creek Tributary depicting the depth of flooding that will be exceeded with a 1percent chance in any given year (100-year flood) under both existing and future 3-274 development conditions. Clarke Creek Tributary and the adjacent basins are shown in Figure 3.18-2. Figure 3.18-2. Clarke Creek Tributary and Adjacent Basins The studied reach includes approximately 1.5 miles of Clarke Creek Tributary. Flood elevation grids were created interpolating between water surface elevations determined at 25 cross sections along the study reach. The flood elevation grids were extended at the upstream end of the stream and at relatively large areas where floodwaters are not conveyed but, rather, pond at the elevation on the main stream. Depth grids were created by subtracting the ground elevation in the digital elevation model from the flood elevation at the corresponding cell in the elevation grid. Cells with flood depths less than zero (those outside of the floodplain, for example) were deleted from the flood elevation and flood depth grids. The resulting existing conditions flood depth grid is shown in Figure 3.18-3. Approximately 34.8 acres are within the 100-year floodplain. 3-275 Figure 3.18-4 shows the distribution of floodplain area inundated at 1-foot depth increments. The maximum depth is 13.12 feet. The average (mean) depth is 4.68 feet. Approximately 12.0 acres upstream of the Street Avenue crossing are inundated at a depth greater than 7 feet. Figure 3.18-3. Existing Conditions Flood Depth Grid 3-276 Clarke Creek Tributary 12 10 8 6 4 2 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Flood Depth (feet) Figure 3.18-4. Distribution of Existing Condition Flood Depths The future conditions flood depth grid is shown in Figure 3.18-5. Approximately 36.8 acres are within the 100-year floodplain, an increase of only 2 acres or less than 6 percent. The distribution of floodplain area inundated at various depths is shown in Figure 3.18-6. The maximum depth is 13.33 feet (0.21 feet greater than existing conditions). The mean depth is 4.84 feet (0.16 foot more than existing conditions). The area inundated by more than 7 feet is approximately 14.6 acres (2.6 acres or approximately 21.7 percent more than the existing conditions). 3-277 Figure 3.18-5. Future Conditions Flood Depth Grid Clarke Creek Tributary 14 12 10 8 6 4 2 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Flood Depth (feet) Figure 3.18-6. Distribution of Future Condition Flood Depths 3-278 Subtracting the existing conditions flood depth grid from the future conditions flood depth grid yields a grid showing the increase in 100-year flood depths expected as a result of development within the basin. That grid is shown in Figure 3.18-7. The distribution of changes in 100-year flood depths is shown in Figure 3.18-8. Note that about 97 percent of the differences are less than one. The 100-year flood depth increases are expected to exceed one foot in two small areas totaling 1.2 acres. Figure 3.18-7. Increases in 100-year Flood Depths 3-279 Clarke Creek Tributary 40 Area Affected (acres) 35 30 25 20 15 10 5 0 1 2 Difference in Flood Depths (feet) Figure 3.18-8. Differences in 100-year Flood Depths 3.18.2.1.1 Lower Clarke Creek Tributary Parcel and Building Data Review To determine the parcels and building footprints that may be potentially impacted by inundation from Clarke Creek Tributary, the floodplain boundaries from both the 1975 flood study and the 2000 flood study were combined and a buffer of 100-feet added. The buffered boundary was used to select intersecting parcel and every building footprint contained within those parcels. This process was selected because it allows Mecklenburg County to identify all structures that are considered close to the floodplain. Structures outside the flood depth grids do not impact the results of this analysis because they will have no net damage, but knowing what structures are nearby was deemed advantageous to Mecklenburg County. There are 89 parcels that intersect the floodplain boundary (including the 100-foot buffer) surrounding Clarke Creek Tributary. Some duplicate parcels were identified and reviewed. In all cases, these turned out to be slivers in the GIS data, most likely right-ofways that have been either returned to the parcel, or offers of dedication that were never acted upon. In all cases, the slivers were merged back into the main parcel. Of the 89 parcels, 42 (47%) are identified as “vacant” and there were no parcels with information in 3-280 the “effective area” field in the county assessor data indicating that a structure was on the parcels, although no building footprint was available. The percentage of vacant parcels (47% based on 89 parcels) shows that Mecklenburg County has significant opportunities to manage future development and reduce future damage within the watershed. Within these 89 parcels intersecting the buffered floodplain boundary, there are 48 building footprints greater than 500 square feet. Of these, none were surveyed as part of the master-elevation-certificate surveys or the “gpsbfe” survey data. The HAZUS default values were applied to these records. For the analysis, the parcel without a building footprint that was identified as non-vacant based on the square footage in the assessors data was carried as single structure at the centroid of the parcel, for a total of 48 “buildings” in the floodplain (including the 100-foot buffer). For the future conditions or “build-out”, a single structure was placed at the centroid of the 42 vacant parcels identified earlier. This structure was established to have the HAZUS®MH default floor area and value based on the occupancy class assigned to the approved zoning of the parcel (see Tables A-1 and A-2 in Appendix A). Therefore the total “buildings” within the floodplain for the built-out inventory is assumed to be 90. 3.18.3 Detailed Results for the Lower Clarke Creek Tributary Basin To determine the potential impacts of floodplain map modifications, three damage estimates have been developed, as follows: 1. Run 1 – current inventory, original floodplain. Estimated losses based on the current building inventory within the Lower Clarke Creek watershed (developed from surveyed data and parcel data) and the original 100-year floodplain boundary, based on the 1975 flood study. 2. Run 2 – current inventory, new floodplain. Estimated losses based on the current building inventory, expanded to include structures within the new floodplain that were previously outside the floodplain, and the newly revised (2000) floodplain boundary. 3. Run 3 – future inventory, new floodplain. Estimated losses to a projected future inventory that incorporates projected growth (“build out”), relative to the new floodplain boundary. 3-281 Table 3.18-3 presents the number of buildings damaged by flooding (i.e., non-zero dollar damage) by occupancy under each of the three scenarios. As noted in Section 2, a HAZUS®MH occupancy class was associated with each occupancy type in the Mecklenburg assessor database. Should the number of flooded buildings increased between Run 1 and Run 2 this would have been due to differences in the floodplain boundary between the 1975 flood study and the 2000 flood study map revisions. The increase seen between Run 2 and Run 3 is attributable to the projected increase in floodplain development. The values shown in Table 3.18-3 are presented to give the reader perspective on the relative number of flooded buildings, which is useful when viewing the subsequent tables. Table 3.18-3. Number of Flooded Buildings by HAZUS®MH Occupancy Type: Lower Clarke Creek Watershed HAZUS®MH Occupancy Description Code RES1A Single Family Dwelling, 1 Story, No Basement Total No. of flooded buildings Total No. of unflooded buildings Current Inventory, Original Floodplain (Run 1) 0 Current Inventory, New Floodplain (Run 2) 0 Future Inventory, New Floodplain (Run 3) 2 0 0 2 48 48 88 The aggregate dollar damage across all building occupancy types is shown in Figure 3.18-9. As shown, there are no estimated damages in Run 1 or Run 2. As expected, there is estimated dollar damage increases from Run 2 to Run 3. All of the damages are to residential structures and further study indicated that only a few parcels that intersect the floodplain are zoned non-residential. Tables 3.18-4 through 3.18-7 and the associated discussion go into greater detail about the results of the loss estimation. However, it should be noted that the escalation of estimated damage based on future development validates the need for mitigation measures, such as requiring future development to be 1foot above the future one hundred year flood elevation (as currently proposed by county staff). 3-282 $140,000 $120,000 Structure Content Estimated Loss ($) $100,000 $80,000 $60,000 $40,000 $20,000 $Run1 Run2 Run3 Building Inventory and Floodplain Scenario Figure 3.18-9. Clarke Creek Tributary Aggregate Damage Estimation Results Table 3.18-4 presents the overall average damage percentage calculated for building structures by occupancy, through the application of the various depth-damage curves. Table 3.18-4 shows that there is no damage (shown in percent) estimated for Run 1 and Run 2 indicating that the differences between the 1975 flood study and the 2000 flood study do not impact any structures. New development, shown in Run 3, shows the impact of flooding on the new structures. In Run 3, the damages are estimated to be approximately 43% although this is for a very limited number of structures. Due to the low number of structures impacted, Mecklenburg County may be in a position to control the conditions seen in Run 3 through floodplain regulation. It is notable that structure damage over 50% of market value is considered “substantial damage”14 by the Federal Insurance and Mitigation Administration. Structures receiving over 50% estimated damage are likely to be excellent acquisition candidates. Table 3.18-4. Average Structure Damage Percent by HAZUS®MH Occupancy Type: Lower Clarke Creek Watershed 14 According to NFIP guidelines, structures suffering “substantial damage” must be brought up to current floodplain management standards for new (post-FIRM) construction (i.e., removed from the flood hazard area or elevated to or above the level of the base flood elevation, or floodproofed if it is nonresidential). 3-283 HAZUS®MH Occupancy Code RES1A Description Single Family Dwelling, 1 Story, No Basement Current Inventory, Original Floodplain (Run 1) 0 Current Inventory, New Floodplain (Run 2) 0 Future Inventory, New Floodplain (Run 3) 42.9 Table 3.18-5 shows the dollar damage to building structures that is computed when the individual building damage percentages are multiplied by the structure/parcel valuation. As with the previous table, the differences in the dollar damage between the three scenarios help identify the source of the damage. Between Run 1 and Run 2, no losses are estimated and as the building inventories used for these scenarios are identical, the difference in damage, or lack thereof, is attributable to differences in the floodplain between the 1975 flood study and the 2000 revision of the 100-yr floodplain map. Proceeding from Run 2 to Run 3, there is a increase in estimated damage from no damage to $125,000, attributable to projected development in the floodplain. As indicated in previous tables, the estimated damages are to a limited number of structures placed at the centroid of the parcel. This clearly indicates that Mecklenburg County can seek ways to avoid these losses through effective floodplain regulation. Table 3.18-5. Structure Dollar Damage by HAZUS®MH Occupancy Type Lower Clarke Creek Watershed HAZUS®MH Occupancy Code RES1A Total Current Inventory, Current Inventory, New Future Inventory, New Original Floodplain Floodplain floodplain (Run 1) (Run 2) (Run 3) Total Avg. Total Avg. Total Avg. $0 $0 $0 $0 $125,000 $62,500 $0 $0 $0 $0 $125,000 $62,500 Table 3.18-6 presents the overall average damage percentage calculated for building contents by occupancy type. The estimated damage for contents will typically follow the same general trend as seen in Table 3.18-4. Run 1 and Run 2, as expected, show no estimated damage. The estimated damages for Run 3 are approximately 53%, but again this value is for a small number of new structures. 3-284 Table 3.18-6. Contents Damage Percent by HAZUS®MH Occupancy Type Lower Clarke Creek Watershed HAZUS®MH Occupancy Code RES1A Description Single Family Dwelling, 1 Story, No Basement Current Inventory, Original Floodplain (Run 1) 0 Current Inventory, New Floodplain (Run 2) 0 Future Inventory, New Floodplain (Run 3) 53.2 Table 3.18-7 provides the estimated dollar damage to building contents by occupancy type. Similar to the structure dollar damage shown in Table 3.18-5, no losses were estimated for Run 1 and Run 2 indicating that the changes in the floodplain depth and extent between the 1975 flood study and the recent 2000 revision of the 100-yr floodplain map do not impact any structures. Between Run 2 to Run 3, there is an increase in estimated damage from no damage to $77 thousand attributable to projected growth. Table 3.18-7. Contents Dollar Damage by HAZUS®MH Occupancy Type Lower Clarke Creek Watershed HAZUS®MH Occupancy Code RES1A Total Current Inventory, Current Inventory, New Current Floodplain Floodplain (Run 1) (Run 2) Total Avg. Total Avg. $0 $0 $0 $0 $0 $0 $0 3-285 $0 Future Inventory, New Floodplain (Run 3) Total Avg. $77,407 $38,704 $77,407 $38,704 3.19 Beaverdam Creek Analysis 3.19.1 Results Summary for the Beaverdam Basin The analysis for this watershed has not been performed. This page is intentionally left blank as a placeholder for the analysis results at the County’s discretion. 3-286 3.20 Clear Creek Analysis 3.20.1 Results Summary for the Clear Creek Basin The analysis for this watershed has not been performed. This page is intentionally left blank as a placeholder for the analysis results at the County’s discretion. 3-287 3.21 Gar Creek Analysis 3.21.1 Results Summary for the Gar Creek Basin The analysis for this watershed has not been performed. This page is intentionally left blank as a placeholder for the analysis results at the County’s discretion. 3-288 3.22 Paw Creek Analysis 3.22.1 Results Summary for the Paw Creek Basin The analysis for this watershed has not been performed. This page is intentionally left blank as a placeholder for the analysis results at the County’s discretion. 3-289 3.23 Steele Creek Analysis 3.23.1 Results Summary for the Steele Creek Basin The analysis for this watershed has not been performed. This page is intentionally left blank as a placeholder for the analysis results at the County’s discretion. 3-290 4. Recommendations for Data Enhancements During the course of this project, a variety of data was utilized and as such, several data related issues arose. In most cases, assumptions were made and the project moved forward. ABS feels that this project greatly enhanced our knowledge of the issues that municipalities will likely encounter when attempting to use local data in the HAZUS®MH Flood Model. Some of the issues warrant further review and discussion by Charlotte/Mecklenburg staff. To support the discussion within the County, this section of the report will identify a variety of potential enhancements that can be made to the County’s data that will enhance the utilization of the data within the County. As there were so many data layers and databases used, the sections are simplified as much as possible to prevent confusion. As a result, there may be some repetitive recommendations. 4.1 County Tax Assessor Data Enhancement During the processing of the data for the analysis, one potential enhancement was quickly identified. There are several parcels throughout the County that has had more than one building or structure developed upon it. The Assessor data itself, however, does not contain structure specific attributes. For example, there are some parcels with several apartment buildings. The Assessor data, identifies the number of structures, but has a single valuation and a single total floor area for each building. The ideal enhancement would be to provide a unique identifier defined by the parcel number (column one) and the building number (column two). The two columns together uniquely identify a single building and the record contains all attribute data for that distinct structure. This would include the total floor area, the valuation, number of stories and other attributes currently provided by the Assessor. The County Assessor could use the functionality of MS Access or other relational database systems to sum the individual records for each parcel and thereby produce the tax bill for the owner. Another data enhancement would be to improve the definition of the building footing or foundation type. This would require the County Assessor to work with building owners to 4-1 identify the foundation type when paying their taxes, or capture this information as the building changes hands. This information will have great value when the County uses HAZUS ®MH for future analyses. 4.2 Integration of Building Footprints and Parcel Data Two components of the data provided by the County include the countywide parcel data layer that could be joined to the Tax Assessor rolls and the building footprint coverage. As noted earlier in this report, ABS performed an analysis that assigned the parcel identification value to the building footprint data layer. It is recommended that the County perform this effort again, but with a little more manual intervention and the addition of the Building Id as discussed in Section 4.1 above. As noted above, this would allow GIS operators to perform building specific analyses, using parameters unique to the structure from the Assessor rolls. This task is not entirely simple. There will be issues that the County will need to address, such as those buildings that cross multiple parcels. How the building footprint and the parcel numbers are assigned in this case will require some thought. As noted in Section 4.3, this may require revisions to the Parcel coverage. In other cases, the County may need to determine if there is a limit on the size of the structure to be included in this process. ABS eliminated all footprints less than 500 square foot in size. The County may wish to do something similar, or it may want to carry every structure within the data coverage. 4.3 Merging Survey Data and Assignment Data to Building Footprints Similar to the assignment of building footprints and the parcel data, there are opportunities to enhance future analysis efforts by reviewing and assigning the various survey data tables to the building footprint database and data layer. Prior to performing this effort, it is recommended that the County build a master survey database that merges the four datasets used in this analysis together. Duplicate data can be eliminated and the most current and accurate data can be preserved. 4-2 With a master database, the County could then assign the unique identifier for the survey data point to the building footprint it represents. This would greatly enhance the Assessor data already joined by parcel and building Id by providing the flood specific elements such as first floor elevation and lowest adjacent grade. 4.4 Revisit Parcel Boundary Inconsistencies As seen in Figure 4-1 below, there are some parcels within the County’s parcel boundary data layer where the building footprints seem to have been removed from the a parcel layer, and the Assessor data had no associated data. The digital orthophotography supplied by the County was used to aid in the review of these areas. In essence, the parcel level data were no longer attached to the parcel boundary, rather the attributes were attached to smaller footprint-sized polygons. In this analysis it created the potential of an occupied parcel being identified as vacant. Additionally, the survey data did not always include every structure on a given parcel – thereby reducing the potential for accurately capturing the total exposure. For illustration, Figure 4-1 shows a highlighted parcel that has several condominium buildings within its boundary. Some buildings have apparently been cropped out of the parcel boundaries and the associated assessor data assigned to each footprint. Unfortunately, the highlighted area is indicated as a vacant parcel in the Tax Assessor data. For the McAlpine Creek study, the parcel was left as vacant and it was assumed that additional residential construction occurred in the future. This issues raises the potential to either underestimate the existing exposure or the potential to overestimate future development. 4-3 Figure 4-1. ArcView Image of Parcel Data and Survey Points 4.5 Building Valuation For the 305 surveyed structures that intersect a parcel polygon, a comparison of the building valuation with the assessor data showed that the two data sources were at times significantly different. As such, the assessor data were applied for all building valuations. Although this potential valuation problem was avoided for the damage estimation, the data inconsistency may be of interest to Mecklenburg staff. 4-4 A. Reference Tables Table A-1. Mapping of Mecklenburg Use Codes into HAZUS®MH Occupancy Codes Meck. Use Mecklenburg Code Code Description 01 SINGLE FAMILY RESIDENTIAL 02 MANUFACTURED HOME 03 MOBILE HOME 04 CONDO 05 PATIO HOME 06 CONDO HIGH RISE 07 SINGLE FAMILY RESORT 08 --09 TOWNHOUSE 10 COMMERCIAL 11 12 13 14 15 16 17 18 19 20 21 22 Source of HAZUS®MH Applied Occupancy HAZUS®MH Occupancy Structure Code Code Description Damage Curve RES1 Single Family Dwelling FIA RES2 Mobile Home FIA RES2 RES3 RES1 RES3 RES1 Mobile Home Multi-Family Dwelling Single Family Dwelling Multi-Family Dwelling Single Family Dwelling FIA Galveston FIA Galveston FIA ----RES3 Multi-Family Dwelling COM1/COM4 Retail Trade and Business/Professional/ Technical Services CONVENIENCE STORE COM1 Retail Trade CAR WASH COM3 Personal and Repair Services DEPARTMENT STORE COM1 Retail Trade SUPERMARKET COM1 Retail Trade SHOPPING CENTERCOM1 Retail Trade MALL SHOPPING CENTERCOM1 Retail Trade STRIP OFFICE COM4 Business/Professional/ Technical Services OFFICE HIGH RISE COM4 Business/Professional/ Technical Services MEDICAL BUILDING COM7 Medical Office/Clinic MEDICAL CONDO COM4 Business/Professional/ Technical Services RESTAURANTS COM8 Entertainment & Recreation FAST FOODS COM8 Entertainment & A-1 --Galveston Wilmington Wilmington Galveston Wilmington Wilmington Wilmington Wilmington Wilmington Wilmington Wilmington Wilmington Wilmington Galveston 23 24 BANKS OFFICE CONDO 25 COMMERCIAL/SERVICE COM4 26 27 28 29 30 31 SERVICE STATION AUTO SALES/SERVICE PARKING GARAGE MINIWAREHOUSE LAB/RESEARCH DAY CARE COM1 COM1 COM10 COM2 IND1 COM3 32 33 THEATER LOUNGE/NIGHTCLUB COM9 COM8 34 BOWLING ALLEY COM8 35 COMMERCIAL CONDO COM4 37 HOTEL/MOTEL HIGH RISE FURNITURE SHOWROOM HOTEL/MOTEL INDUSTRIAL RES4 Source of Applied HAZUS®MH Occupancy Structure Code Description Damage Curve Recreation Depository Institutions Wilmington Business/Professional/ Wilmington Technical Services Business/Professional/ Wilmington Technical Services Retail Trade Wilmington Retail Trade Wilmington Parking Wilmington Wholesale Trade Wilmington Heavy Industrial Galveston Personal and Repair Galveston Services Theaters Wilmington Entertainment & Wilmington Recreation Entertainment & Wilmington Recreation Business/Professional/ Wilmington Technical Services Temporary Lodging Wilmington COM1 Retail Trade Wilmington RES4 IND2/IND6 Wilmington Galveston LIGHT MANUFACTURING HEAVY MANUFACTURING LUMBERYARD PACKING PLANT/FOOD PREP BOTTLER/BREWERY WAREHOUSE CONDO WAREHOUSE PREFAB WAREHOUSE RURAL HOMESITE COLD STORAGE/FREEZER TRUCK TERMINAL SERVICE GARAGE IND2 Temporary Lodging Light Industrial & Construction Light Industrial Galveston IND1 Heavy Industrial Galveston COM2 IND3 Wholesale Trade Foods/Chemicals/Drugs Wilmington Galveston IND3 COM2 COM2 COM2 RES1 COM2 Foods/Chemicals/Drugs Wholesale Trade Wholesale Trade Wholesale Trade Single Family Dwelling Wholesale Trade Galveston Wilmington Wilmington Wilmington FIA Galveston COM2 COM3 Wholesale Trade Personal and Repair Services Galveston Galveston Meck. Use Code 38 39 40 41 42 43 44 46 47 48 49 50 51 52 53 Mecklenburg Code Description HAZUS®MH Occupancy Code COM5 COM4 A-2 Meck. Use Code 54 55 56 60 61 HAZUS®MH Occupancy Code COM2 ----RES3 RES3 Source of Applied HAZUS®MH Occupancy Structure Code Description Damage Curve Wholesale Trade Wilmington --------Multi-Family Dwelling Wilmington Multi-Family Dwelling Wilmington RES3 RES3 Multi-Family Dwelling Multi-Family Dwelling Galveston Wilmington ----REL1 ----Wilmington Wilmington 64 69 70 Mecklenburg Code Description OFFICE/WAREHOUSE ----GARDEN APARTMENT TOWNHOUSE APARTMENT DUPLEX/TRIPLEX HIGH-RISE APARTMENT ----INSTITUTIONAL 71 CHURCH REL1 72 EDU2 COM6 RES5 RES1 Hospital Institutional Dormitory Single Family Dwelling Galveston Wilmington Wilmington COM3 78 COUNTRY CLUB COM8 79 AIRPORT COM4 Personal and Repair Services Entertainment & Recreation Entertainment & Recreation Business/Professional/ Technical Services Wilmington 77 SCHOOL:COLLEGEPRIVATE HOSPITAL-PRIVATE ORPHANAGE SINGLE FAMILY RESIDENTIAL MORTUARYCEMETERY CLUB-LODGE ----Church/Membership Organizations Church/Membership Organizations Colleges/Universities 82 83 84 86 87 88 89 91 FOREST-PARK PUBLIC SCHOOL PUBLIC COLLEGE OTHER COUNTY OTHER STATE OTHER FEDERAL OTHER MUNICIPAL UTILITY EDU1 EDU2 GOV1 GOV1 GOV1 GOV1 COM4 Wilmington Wilmington Galveston Wilmington Wilmington Galveston Galveston 93 94 96 98 99 PETRO-GAS BLANK BLANK VALUE-IMPR NEW PARCEL COM1 --------- Schools/Libraries Colleges/Universities General Government General Government General Government General Government Business/Professional/ Technical Services Retail Trade --------- 62 63 73 74 75 76 COM8 A-3 Wilmington Wilmington Galveston Galveston Wilmington --------- Table A-2. Estimated Typical Floor Area and Cost per Square Foot by Mecklenburg Occupancy Code County Assessor Occupancy Code 01 02 04 05 06 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 37 38 39 40 41 42 43 47 48 49 Estimated Typical Floor Area from Assessor’s Data (ft2) 2,290 1,450 1,110 1,300 3,860 1,320 9,970 2,070 1,800 91.980 42,240 348,370 27,930 19,750 256,180 15,790 3,270 6,620 2,960 6,480 1,120 87,750 2,560 25,830 164,720 6,230 78,220 8,130 51,080 8,660 59,040 1,050 129,800 24,970 24,220 47,570 59,300 17,470 5,600 3,650 31,800 14,470 A-4 HAZUS®MH Cost Models for Valuation ($/ft2) 63.59 26.38 57.24 54.73 90.19 54.18 41.90 82.68 37.26 37.67 43.57 93.10 39.15 61.26 82.61 76.63 76.26 57.68 80.95 114.01 67.73 34.47 16.01 25.30 18.32 15.19 77.82 57.82 70.11 33.21 24.03 41.77 61.28 38.30 42.96 27.67 32.44 48.76 6.84 28.70 25.70 18.93 County Assessor Occupancy Code 51 52 53 54 55 56 60 61 62 63 64 69 70 71 72 73 74 76 77 78 83 84 86 88 89 91 99 Estimated Typical Floor Area from Assessor’s Data (ft2) 37,520 45,510 8,790 36,680 1,927,640 290,830 11,970 6,890 2,340 44,990 45,410 2,480 7,260 9,690 15,080 43,780 31,210 8,560 4,520 11,420 29,130 30,970 30,080 24,430 17,010 970 4,760 HAZUS®MH Cost Models for Valuation ($/ft2) 42.15 23.32 32.32 29.57 68.63 80.11 36.22 33.54 52.14 44.37 76.74 52.74 54.74 72.81 55.37 86.56 60.13 63.85 49.86 95.73 52.42 69.00 69.94 87.64 81.35 83.00 0.44 Note: See Table A-1 for occupancy code definitions and assignment to HAZUS occupancy classifications A-5 Table A-3. HAZUS®MH Content Value as a Percentage of Structure Value HAZUS®MH Occupancy RES1 RES2 RES3A RES3B RES3C RES3D RES3E RES3F RES4 RES5 RES6 COM1 COM2 COM3 COM4 COM5 COM6 COM7 COM8 COM9 COM10 IND1 IND2 IND3 IND4 IND5 IND6 AGR1 REL1 GOV1 GOV2 EDU1 EDU2 Contents Value (Percent of Structure Value) 50 50 50 50 50 50 50 50 50 50 50 100 100 100 100 100 150 150 100 100 50 150 150 150 150 150 100 100 100 100 150 100 150 A-6 Table A-4. HAZUS®MH Foundation Distribution (default) and Adjusted Foundation Distribution Used in Mecklenburg County Foundation Type HAZUS Default for North Carolina Mecklenburg Adjusted Foundation Distribution Based on Assessor Data Solid Pier (or Pile Wall Post) 0 0 0 1 1 Basement (or Garden Level) Crawlspace 23 35 5 20 A-7 30 Fill 0 Slab on Grade 42 1 42