October 2014

advertisement
October 2014
This email is to update you on the City of Charlotte Myrtle/Morehead Drainage project. It has been in the Planning and Design
Phases for a while and is quickly proceeding into the Construction Phase.
Sanders Utility Construction Co., Inc. is the General Contractor and will be performing most of the work and is responsible for
all of the work. Currently they are busy scheduling for beginning the actual construction. On their team is a subcontractor,
Vibratech Inc., who has already begun to document existing conditions of all buildings and roadways. This is very important to
the City and is a contract requirement which is intended to document conditions prior to construction.
This construction project extends along Baxter, McDowell, Morehead and Oriole. Construction Signs are already being placed.
Some project stakeout/surveying has begun. Within two weeks, the Contractor will begin along Baxter. The first thing will be to
place a temporary construction fence in the Kidney Dialysis Center and Wray Ward parking area, which will enclose the actual
excavation area. That will be followed by moving in equipment and then next the actual excavation is scheduled to begin. Since
the construction area is small, the excavated dirt material will be trucked away and materials brought in as needed. Safety for
all is important, motorist in this area are reminded to be alert to changing driving/parking patterns and these additional hauling
and service vehicles.
In about a month, some exploration work will also be scheduled along Morehead to investigate the existing 54” water line so
materials can be ordered for replacing approximately 80 ft. This exploration work will be completed over the weekend. Some
lanes will be closed and through traffic will be directed by construction signs around the work.
In about a month, Oriole St. will be closed at Morehead to through traffic. The Contractor will dig a shaft in the street at this
location to construct a tunnel for a 90” Concrete Drain Pipe to cross Morehead. By tunneling under Morehead, it will remain
open for the majority of this work. This tunnel work will continue through the winter and be completed early spring. The
construction along Oriole Street will be later. Motorist in this area are also reminded to be alert to changing traffic patterns and
construction workers.
Please be aware that there are many things that effect the construction schedule. Weather is a large factor. Material
production and delivery is sometime delayed. Utility conflicts have been addressed, but additional conflicts are sometime out
of the Contractor’s control.
Campo and Associates are administering the contract for the City of Charlotte I am the Construction Manager and Charlie Coley
is the project inspector. Generally, I will be on the project weekly. Generally, Charlie will be on the project whenever the
Contractor is working. Since some of the project will be around the clock, we will have other inspectors as needed.
Charlie can be reached by email or phone:
Charlie.Coley@campoassociates.com
704-961-2882 cell
I can be reached by email or phone:
Timothy.Canup@campoassociates.com
704-213-2107 cell
If you have any questions, do not wish to receive these updates, or know of someone who wants to be added to the list, please
let me know.
Thank you for your continued patience and cooperation.
Tim.
Download