Commercial Plan Review Land Use and Environmental Service Agency (Code Enforcement) Electrical Q&A 2009 Fourth Quarter 2009 General: 1. (Q Do we review existing work the same way as new work in regard to submittal requirements, service locations, grouping of mains, number of mains? Yes, the only difference would be that on an existing building the service, etc., may have been installed under an older code. Did it meet code at the time it was installed? For the most part these type projects must be examined on a case by case basis. 2. (Q) Which method of measuring clearance for ATS do we use? The method described in NFPA 110 (7.2.2.1), or the method described in NEC 110-26a? Both, we apply the method described in NFPA 110(7.2.2.1) and use the measurement given NEC 110-26a. 3. (Q) Do we accept 100% rating of breakers and equipment as per NEC 210.20a/215.3/230.42a(1)(2)/240.6, or require the designer to indicate on the drawings and specifications? Only if the designer gives the calculations to back it up. Otherwise he needs to show that the equipment is rated for 100% of the connected load. 4. (Q) Do we attach the oil filled transformer statement to the drawings we review? Commercial electrical plan examiners apply to the field and office set of drawings the “Transformer Statement date 9/28/09” by way of a stamp, sticker, or tape/paste copy. This includes all new projects and any existing building that appears the service size will increase, or transformer be relocated. The Field Inspector and the Chief, or Assistant Chief will resolve any location issues that may arise on site. Fourth Quarter 2009 5. (Q) What stamps are electrical plans examiners required to affix to the drawings? When appropriate for the project: a. Transformer sticker –new buildings -existing buildings with service upgrades b. Selective Overcurrent Coordination Study -all life safety -all legal standby -all hospital essential c. Industrial Machinery d. Listing and Labeling e. Multifamily Residential f. Examiners name & phone number 6. (Q) How should a designer define repair garage for an electrical review when the Building Code defines it different than the Electrical Code? The electrical designer will need to show on the drawings based on NEC 511 the hazardous classification for the building or portion of the building, if it is a major or minor garage and specific details as to the function of the occupancy. 7. (Q) How do electrical reviewers approach parking decks with multilevel fuel dispensing and minor repair in regard to fire barriers (protection)? The NEC does not address multilevel, however NFPA 30A allows only ground level dispensing stations. 8. (Q) Is the electrical designer required to show the available fault current from the utility on the drawings if the voltage is 120/208/three phase? Yes, unless the utility company is Duke Energy. It is the current policy of Duke Energy to mitigate the available fault current to 10,000 amperes at a self-contained metering point. Self-contained meter installations are those where the meter is connected directly to the supply voltage and the meter is in series with the customer load(i.e., current and voltage transformers aren’t used). The service voltage can determine where selfcontained metering may be used. For instance, 277/40V requires transformer rated metering because of the voltage level. Typically 120/240V single phase, 120/208V network, or 120/208V three phase is metered self-contained unless the load is excessive. Other than that, voltage level does not affect the policy. 9. (Q) Do we accept a feeder supplying multiple VAV boxes when the OCP is located inside the equipment? No, the OCP must be located in a disconnect remote from the equipment. Fourth Quarter 2009