MECKLENBURG COUNTY Land Use & Environmental Services Agency Code Enforcement 10/7/09 ELECTRICAL CONSISTENCY MEETING QUESTIONS 1. (Q) We were turned down for not having a receptacle on a screened porch. We had one beside the porch on the deck. What was the problem? (A) Balcony/Porch/Deck receptacles are required as per NEC 210.52(E)(3). If the porch was accessible from the inside of the dwelling a receptacle would be required within the porch perimeter. 2. (Q)We passed the plumbing inspection but were turned down for access at the hydromassage tub by the electrical inspector. Why is there a difference? (A) For electrical considerations NEC 680.71 requires a readily accessible GFCI. Readily accessible means - Capable of being reached quickly for operation, renewal, or inspections without requiring those to whom ready access is requisite to climb over or remove obstacles or to resort to portable ladders, and so forth. NEC 680.73 requires that equipment shall be accessible without damaging building structure or finish. Accessible means - Admitting close approach; not guarded by locked doors, elevation, or other effective means. The above differs from the plumbing code requirements. 3. (Q)We were turned down on a service change for the rating of the breakers in an existing sub-panel. How are we responsible for the existing condition? (A) The equipment rating must exceed the available fault current. Generally the fault current decreases as you proceed downstream in the riser system due to the resistance factors of the conductors and equipment. Most plans have the fault current listed at the service or serving transformer. If the bracing of the equipment is reduced a calculation is to be provided showing how the reduction in fault current level has been obtained. The level of the breakers must have been less than the available fault current shown/stated. Protection must be Electrical Consistency Team Meeting October 7th, 2009 Page 2 of 4 maintained throughout the system whether or not equipment is existing. 4. (Q) We have experienced varying enforcement of appropriate GFCI requirements with regards to commercial kitchens. What is the correct approach? (A) NEC 210.8 (B) (2) – Kitchens; GFCI is required in kitchens (an area with a sink and permanent provisions for food preparation and cooking). We require the GFCI per the definition. If the cooking equipment is integral to the business we will consider it as a permanent provision. Installations such as an office break room with a nonattached microwave, refrigerator and sink, will not be considered as integral and therefore will not qualify as a kitchen. Notice that the area has to have both a (1) sink and (2) permanent provisions for food prep and cooking. 5. (Q) What is the correct way to size OCP for a fire pump? (A) While capable of carrying the locked rotor current has long been the standard for most applications. fire pump breakers at the genset are allowed at 250% instead of locked rotor OCP units per NEC 695.4B which refers us to NEC 430.62. 6. (Q) There seems to be confusion on the requirement for fire pump disconnects being sufficiently remote from other disconnects. What is the correct code application? Fire pump disconnects are required to be sufficiently remote from other disconnects per NEC 695.4 (B) (2) (4). If the disconnect is on the generator of the system this requirement may be exempted if the genset is listed for the purpose. (NCDOI interpretation pending) 7. (Q) Are GFCI units required to be accessible? (A) GFCI units are not required to be readily accessible except for hydromassage tub receptacles and circuit breaker types, the rest must be accessible only. (this is expected to change in the next code cycle) 8. (Q) When are selective overcurrent studies required? (A) Supply the inspector with the required sealed Selective OCP studies before electrical systems are energized. See NEC Articles 517, 620, 700, 701 & 708 for specific conditions that require these reports. Electrical Consistency Team Meeting October 7th, 2009 Page 3 of 4 9. (Q) What is the current code requirement for protections when oil filled transformers are in or near the building? (A) The NCBCC RULED IN OUR FAVOR IN THE OIL FILLED TRANSFORMER APPEAL, which should make the issue clearer. NEC 450.26 & .27 are enforceable have been a part of the code for at least back to the1971 edition. Due to the increasing use of infill lots, super block style development, the IBC code definition of inside and outside of the building, and focus on density developments, we are seeing more and more challenges and violations. Per the code we are protecting the buildings from the dangers imposed by oil filled transformers. As an alternate method of compliance we will readily accept Duke Energy’s Standard or FM Global Data Sheets 5-4. We will consider any alternate methods and means submitted per Section 105 of the NC Administrative Code. 10. (Q) We were turned down for not having a disconnect at the building for a temporary & portable genset connection to back up the building service. Why can’t the disconnect be supplied with the genset? Per the NEC the system must include the disconnect, transfer and grounding when installed. Notes for disconnect or transfer on the equipment to be brought in will not be acceptable in that the installation would then be incomplete. 11. (Q) We were turned down because the transfer switch could not carry the entire house load. Why? (A) It would depend on the type of switch used. If manual there is no requirement to carry the full load, if automatic there is. Per the NEC 702.5 Capacity and Rating (A) Available Short-Circuit Current. Optional standby system equipment shall be suitable for the maximum available short-circuit current at its terminals. (B) System Capacity. The calculations of load on the standby source shall be made in accordance with Article 220 or by another approved method. (1) Manual Transfer Equipment. Where manual transfer equipment is used, an optional standby system shall have adequate capacity and rating for the supply of all equipment intended to be operated at one time. The user of the optional standby system shall be permitted to select the load connected to the system. Electrical Consistency Team Meeting October 7th, 2009 Page 4 of 4 (2) Automatic Transfer Equipment. Where automatic transfer equipment is used, an optional standby system shall comply with (2)(a) or (2)(b). (a) Full Load. The standby source shall be capable of supplying the full load that is transferred by the automatic transfer equipment. (b) Load Management. Where a system is employed that will automatically manage the connected load, the standby source shall have a capacity sufficient to supply the maximum load that will be connected by the load management system. UPDATES/PROCESS 1. We continue working with DOI on fire pump interpretations for required separation 2. Bill H1409 is in committee and rewrites are probable 3. We’re still having questions regarding PPE impact on service time. Please remember to structure inspection request to avoid energized equipment and help us inform your clients. 4. The Re Org process is ongoing, brown bags & staff meetings are to be scheduled. 5. Inspectors will try to accommodate AM/PM inspection when possible. If you have to get the inspection per an imperative schedule use the IBA program. 6. LV permit process; P lease help us to be proactive in resolving issues and getting the w ord out inspection result entries – We will not fail or RT other contractors work for unpermitted LV. An electrical CO hold will be issued. When the permit for LV is issued we will release the hold. stickers & notes on jobs – Notes on site and in system should qualify to everyone what’s done and what needs to be done. Notes are to differentiate between interior and exterior LV systems. Notes are to differentiate between LV and Line voltage systems. permit options – a) listed on master permit, b) added to master permit, c) (stand alone) Trade permit.