Our Goal is FOR ALL STAKEHOLDERS TO HAVE A SUCCESSFUL PROJECT with us and that together we keep people and structures safe and economically viable to serve the needs of our community. We strive for: EXCELLENT CUSTOMER SERVICE! and QUALITY INSPECTIONS! JAN. 13th, 2016 OUR NEXT MEETING IS Feb. 10th I. Customer Service Reminder – Supervisor / Manager II. Consistency Questions 1) What is our policy on elevator inspections? Mullis Per NCOSFM, We inspect RESIDENTIAL elevators to the last part, for the electrical systems installed to meet Article 620. Note that Type NM Cable and SE Cable are not permitted for any of the wiring methods. The Building Inspector is required to inspect the rest of the installation and obtain a letter of Certification from the contractor installing the elevator. For COMMERCIAL elevators we stop at the disconnects in the machine room. We do inspect the pit for wiring installed there to meet 620, such as the receptacle and light. NCDOL will let you know if they are on site as to what point they start their inspection. Ron Chilton 2) A 200 ampere, 277/480 volt feeder is installed in 50 feet of 2½", Schedule 80, PVC Rigid Nonmetallic Conduit on the south side of a steel building. During the winter months, the outdoor temperature differs by as much as 50 degrees (°F). How much will the conduit expand in length with this change of temperature? And would an expansion type of fitting be required? Barnes The answer depends on the characteristics of the conduit run. Based on the 50 degree temperature differential, the conduit will change about 1 inch in length. Where a length changes greater than 0.25 (1/4) inch occurs in a straight run of PVC conduit between securely fastened conduit termination points such as boxes or cabinets, an expansion fitting(s) must be installed to provide for the movement that will occur in the run of conduit. Expansion fittings must be installed in accordance with the manufacturer’s instructions and the conduit securing and supporting means must allow for the calculated movement of the conduit. Reference: 352.44 & Table 352.44/UL product category is “Conduit Fittings” (DWTT) 3) 2011 NEC 250.32 Buildings or Structures Supplied by a Feeder(s) or Branch Circuit(s) requires that an EGC be installed with the feeder conductors and bonded to the subpanel in the outbuilding. In addition, a GEC is to be installed to all available electrodes at the separate structure. If there are no available electrodes and a ground rod is driven and an appropriately sized GEC installed, is it required that this ground rod be supplemented as required in Article 250.53(A)(2), or can the one ground be considered supplemented by the main structure’s electrode system using the EGC to bond them together? Dellinger No. Based on 250.121 in the 2011 NEC the equipment grounding conductor cannot be used as a grounding electrode conductor. It should be noted that the NEC does not prohibit a single grounding electrode system from being used at more than one building or structure but it is certainly intended that the electrode system be “at” the building or structure being supplied. For instance, two ground rods being used to ground a dwelling service and a feeder run to a detached structure located adjacent to the dwelling. In the 2014 NEC, 250.121 has been revised by adding an exception that permits a wire-type EGC to also be used as a GEC. In this case the conductor is being used as a “bonding jumper” to connect two electrodes together in addition to being the EGC which is certainly similar to the conductor being a GEC and an EGC. The combined use conductor has to meet all requirements for both the GEC and EGC. See 250.50, 250.121 4) In many sections of Article 680 (swimming pools) there is a requirement for an insulated equipment grounding conductor. In some cases, as in a single family dwelling, the branch circuit for a pool pump may be allowed to be run in NM cable as long as it is in the interior of the dwelling. Please explain why an insulated equipment grounding conductor is required otherwise? I understand why UF cable is not allowed for pool equipment on the outside of the building but why the requirement for the insulation. I do realize that once cable is eliminated, the equipment grounding conductor will almost always be insulated anyway but it is spelled out for a reason. Hartman Section 680.21(A)(4) permits a cable assembly to contain an uninsulated equipment grounding conductor if enclosed within the outer sheath assembly to supply the pool pump motor. All other equipment grounding conductors must be insulated to provide extra protection against deterioration of the equipment grounding conductor. Loss of the equipment grounding conductor can affect the equipotential grounding plane for the pool area and create a potential capacitance with possible shock and disorientation issues. 5) The new inspector is turning my jobs down for using 30 amp breakers on 4500 watt water heaters. 4500 X 125% = 5625/240= 23.4375. Article 240 does allow you go to the next standard size breaker which is a 25 amp breaker. Article 422 does allow you to use 150% anything over 13 amps or so. 4500/240 = 18.75 18.75 X 150% = 28.125. So why should the new inspectors keep turning my job down when this meets the minimum code by using a 30 amp breaker? Kale As stated the job should have been approved by the inspector. Your calculations are correct. If a 208v system is used, then we would have a different outcome. Additionally, we have to follow the nameplate data and installation instructions. 6) When installing a service for a pond pump, am I allowed to mount it like a typical saw service or am I required to build something more permanent? King A permanent power pole needs to be a substantial structure to support the service. Duke and others have condition requirements that need to be followed. For installations in the Duke Energy service area see website: http://www.duke- energy.com/pdfs/Service-RequirementsManual.pdf 7) I was recently failed on a TU inspection for power to a commercial remodel site due to the fact that I had not installed a 120 volt GFCI protected receptacle. The building had temp power from an exterior SS and all I needed energized at the time was the HVAC equipment. Was this correct? Simpson The GFCI is a requirement of the State Electrical Code. 10.8 TEMPORARY POWER 10.8.1 Scope. The provisions of this section apply to the utilization of portions of the wiring system within a building to facilitate construction. 10.8.2 Provisions for Temporary Power. The Code enforcement official shall give permission and issue a permit to energize the electrical service when the provisions of 10.8 and the following requirements have been met: 1) The service wiring and equipment, including the meter socket enclosure, shall be installed, the service wiring terminated, and the service equipment covers installed. 2) The portions of the electrical system that are to be energized shall be complete and physically protected. 3) The grounding electrode system shall be complete. 4) The grounding and the grounded conductors shall be terminated in the service equipment. 5) At least one receptacle outlet with ground fault circuit interrupter protection for personnel shall be installed with the circuit wiring terminated. 6) The applicable requirements of the North Carolina Electrical Code apply. 8) I have a client that wishes to repair the wiring to his older residence. It was installed in knob and tube in the thirties and has deteriorated over the years and now the insulation is bad and crumbling throughout. The question is, he wishes to replace the existing wiring but does not want to install additional receptacles to meet current code. What will be the extent of the requirements when the wall finish will not be replaced? Bathrooms? Kitchens? Thanks Rains For systems that met the code at the time it was installed repairs can be made to the wiring per our State Codes. If you add wiring or replace devices, fixtures, etc. you will need to follow the current code. Our closest policy reference is below. SUBJECT: Remodel Jobs CODE REFERENCE: Policy SUBMITTED BY: Electrical Department EFFECTIVE DATE: Immediately – 01/06/10, revised 9/3/15 PROBLEM: How much replacement wiring is required on a remodel job? SOLUTION: If the existing wiring met code at the time of installation, none is required. All new wiring shall meet current code. Changes in layout of walls or kitchen and bath cabinetry shall meet current code. 9) I installed a 4500 kw water heater, using #10 copper wire, 30 amp OCP. I called for inspection and the inspector turned me down because the manufacture installation instructions recommended a 25 amp OCP. He made me change the OCP before I could pass. Was he correct? West We must follow the installation instructions as well as the code (110.3 B). The key word here is recommended, we may need to confirm this with manufacturer and the NRTL. If we can’t then 25 amp seems to be our best option. 10) Can I use a metal octagon box supported to the structure to hang a ceiling fan, or will I be required to purchase a fan approved box. Mullis No, boxes must be listed for support. The fan may be supported by the structure independently from the box. See 314.27 C. Remember the residential requirement for a fan support box if we have the extra switch leg. 11) Inspector turned me down for having my switch over the 4th thread step going up to the 2nd floor. So I moved the switch over by the front door 14ft away because I didn’t have the wall space to put it next to the steps [due to pilaster, column support]. He turned me down again because it wasn’t next to the steps but it was on the same level. So what can I do? Barnes The NCRC requires a wall switch at each floor level, and the NEC requires the same. Risers are not a floor level so the installation was prohibited. At the second location the inspector was incorrect in his/her call. 12) I have a hot tub with a perimeter surface 12" wide between the hot tub and a wall. I can't put the EQP bond wire 18"-24" from the tub. What can I do? Dellinger a) move the tub or the house wall????? b) install it as required on the three sides and as far as you can on the 12” side. If the wall could be conductive it to should be bonded. 13) Concerning the TIA on hot tub EQP bonding, are perimeter surfaces only the horizontal surfaces? Hartman No, the TIA states perimeter surfaces. 14) Can a power tool replacement cord be used on dishwashers and disposals? (They are sufficiently rated for the load). Kale The cord needs to be listed for the use and comply with the code. NEC Table 400.4 has SRD, SRDT and SRDE shown for dryers and ranges. NEC 400.4 states that cables other than those in the table will need to be investigated. NEC 422.16 addresses cord use for appliances and states they shall be identified for the purpose. 15) Please explain how an E09 code can be used to restore power to a job that has been disconnected by customer request without having an inspection before restoring power. (such as large breaker replacement, residential service relocation, etc.) King These situations require a RF inspection with the contractor on site to evaluate how the disc/rec. will be handled. When the inspector and contractor reach an agreed to plan the E09 can be issued and the contractor needs to request the final as soon as possible. The inspector should schedule an inspection for the near future as a safeguard in case the contractor does not schedule one. Inspectors need to note the agreement in their RF notes. 16) I was hired to connect an old mobile home. This mobile home had two SO cords that plugged it to an existing service that had 50A receptacles. Is this ok? Rains Current code allows one 50 amp feeder. We would need more info as to what code was in place when this unit was placed. 17) I am pulling a replacement permit for an expired permit 6 years old. It passed the RF but never got the final. Can I get a final on the code the original permit was under or do I need to bring it up to current code? Simpson A new permit and current code would be required. 18) Can EMT be used as a service mast? West Yes, if not carrying the load of the service drop. For drop loading see 230.28. Many utilities have conditions of service that must be followed in addition to the code. 19) In a fountain, do the wire connectors/terminations in a submerged junction box have to be approved for wet locations? Mullis Per 110.3 B they have to be listed for the use. 20) When the 2014 NEC is adopted will 210.8(D) apply to hard wired dishwashers? Barnes No! Per NC Amendment GFCI will not be required. Item 6.4: Remove GFCI requirement for kitchen dishwasher branch circuit. This was not a requirement in the 2011 NEC. – No Cost Impact 210.8 (D) Kitchen Dishwasher Branch Circuit. GFCI protection shall be provided for outlets that supply dishwashers installed in dwelling unit locations. 21) I was recently failed for installing a Hot Tub in a finished residential basement area. I ran a new 20 amp circuit and installed a 20 amp receptacle, the hot tub was supplied with a 20 amp cord with a listed GFCI device as part of the cord end. The inspector failed me stating the receptacle must be the GFCI type, what is the difference? Dellinger NEC 680.43 requires the receptacle to have GFCI protection. The type unit used having its own GFCI does not delete the code requirement. 22) Is the informative Annex B enforceable? [see the 2014 NEC, NOTE 1 on page 787 for max depth of duct bank]? Hartman Annexes are not enforceable per 90.5 D 23) Can cut-in boxes be used to support lights on a sheet rock ceiling? Kale Yes, if all components are rated for the installation. Carefully review the manufacturer’s instructions. No if not, which is most likely. 24) I have a drawing showing receptacles daisy chained with the load in the panel schedule shown as 180 watts per outlet. Also there are some outlets with dedicated circuits with the panel loading shown as 180 watts. Should these dedicated outlets be calculated at the load required for the equipment to be powered by the outlet? And do these outlets qualify for the demand reduction allowed by 220.44? King See NEC 220.14 A. Receptacles for specific loads shall be calculated based on the appliance or load served. No demands apply. 25) NEC 700.12 (B) (6) makes it clear that an Outdoor Generator requires a disconnecting means either at the Generator or where the conductors enter the building. If the building is an assembly occupancy for not less than 1000 persons or a building above 75’ in height with any of the occupancy classes listed in 700.10(D), then we must protect those conductors and equipment from fire by the requirements of 700.10(D) (1) Feeder-Circuit Wiring, and (2) for Feeder-Circuit Equipment. Those conductors have OCP either at the Generator or where they enter the building per 700.12 (B) (6). With that in mind, where is the requirement for the OCP of the conductors from the Generator to the Feeder-Circuit Equipment when the Generator is housed within the said building? Rains While Articles 700 and 445 specify requirements for this system so do Chapters One through Four of the Code as stated in 90.3 Code Arrangement. The source for the answer is NEC 240.21 requiring OCP at the point of supply. This requirement is not amended by the Articles above. 26) When applying the requirements of NEC 210.60 (B) for the placement of outlets in a motel room, how do we count the receptacles when they are ganged together? Simpson The prescribed method would indicate counting each receptacle placement required by 210.52 and then having that same amount of locations to comply with this section. This would be a good place to suggest better language for a code change. 27) Many stadium, parking lot, and roadway installations include metal or concrete light poles to support lighting. Those metal or concrete poles are often used for support of security cameras and /or speakers for public address and audio systems. Does the NEC allow power wiring for lighting and Class 2 wiring for the security and /or audio in the same pole? West Yes, but if the power conductors are run as single conductors in the interior raceway channel of the pole, the Class 2 circuit conductors or CCTV cables will have to be installed in some type of flexible raceway or cable assembly in order to provide adequate isolation/separation of the limited energy circuit conductors from the power circuit conductors. Reference: (2011 & 2014) 410.30(B), 725.136(I)(1), 820.133(A)(1)(c) Exception No. 1 (permanent barrier) 28) Am I required to use a certain color grommet when protecting low voltage cables, I used a yellow grommet and was turned down, stating I could only use black grommet’s. Mullis No color code applies, items must be used as listed and per manufacturer installation instructions. 29) When is an Arc Energy Reducing Maintenance Switch Required? Barnes At 1200 amps or higher. The 2014 Code in 240.87 requires these to lessen the likelihood of an arc fed accident. The devices reduce the clearing time to remove the fault. 30) Are bond bushings required on concentric knockouts on 277/480V systems? If so, is it required on both ends of conduit if concentric so are encountered on both ends? Dellinger Maybe. If both ends concentric, yes one end to be bonded for the raceway. If using the raceway as EGC both ends will need bonding. Boxes are on the market that are listed for bonding with concentric KOs. 31) What is our current policy concerning TCOs when modular offices are not installed but are shown on the plans? Hartman TCO means that area meets the code. The cube farm needs to be installed if on the plans. 32) I wired some exam/procedure rooms in a hospital. These rooms had exam tables not beds. I was turned down for not having receptacles within 6 feet of a sink GFCI protected. When did this change and does this apply to dentist offices to? Kale 210.8 B 5 requires the GFCI in both instances. Exception 2 changed in the 2011 edition. 33) I'm wiring a 480 to 208/120 transformer. I ran EMT for the transformer secondary to a breaker enclosure. I had planned on connecting the system bonding jumper and GEC in the breaker enclosure but the inspector said I could only do this if I ran PVC? Am I or the inspector confused? King Your installation would meet code requirements. Seems the inspector is confused. 34) Is a separate HVAC unit required for an elevator machine room or can the HVAC for the common areas serve this? Rains Not per NEC. Per the building code under 3006.2 a separate unit is required if the equipment is solid state. 35) What size Main Bonding Jumper is required to bond a metal service gutter with 4-200amp services attached all 3-3/0 copper conductors, and the utility company fed it with a 350 kcmil aluminum. I bonded it with a #1/0 al and the inspector failed it and told me it should have been 4/0 aluminum? Simpson The inspector is correct. See 250.28 D 1 and 250.66. 167800x4=671200, 250.66 shows 2/0 copper or 4/0 aluminum. 1/11/16