Ministry of Defence Defence Standard 00-42 Issue 3 Publication Date 14 March 2008 Reliability and Maintainability (R&M) Assurance Guide Part 3 R&M Case DEF STAN 00-42 Part 3 Issue 3 Unclassified Contents 0 Introduction.........................................................................................................................................vi 1 Scope....................................................................................................................................................1 2 Warning ................................................................................................................................................1 3 Related Documents .............................................................................................................................2 4 Definitions ............................................................................................................................................2 5 The Principles of The R&M Case ........................................................................................................3 5.1 Introduction..........................................................................................................................................3 5.2 R&M Strategy Overview ......................................................................................................................6 5.3 R&M Case Review................................................................................................................................7 6 The Application of the R&M Case Through the System Life Cycle..................................................7 6.1 Introduction..........................................................................................................................................7 6.2 Initial R&M Case...................................................................................................................................8 6.3 Tender Stage R&M Case and Case Reports ......................................................................................9 6.4 R&M Case and Case Reports - Post Contract Award .....................................................................10 6.5 Purchaser’s R&M Activities During Procurement ...........................................................................10 6.6 In-Service R&M Case.........................................................................................................................10 6.7 Modifications .....................................................................................................................................11 6.8 Progressive Assurance of R&M........................................................................................................11 6.9 The R&M Programme Plan................................................................................................................12 7 Providing the Evidence .....................................................................................................................13 8 Guidance On How To Present The Evidence...................................................................................13 9 Guidance on How to Assess the Adequacy of Evidence................................................................15 Annex A – General Requirements for the R&M Case and R&M Case Report .........................................18 A.1 R&M Case...........................................................................................................................................18 A.1.1 System Description ...........................................................................................................................18 A.1.2 R&M Requirements............................................................................................................................18 A.1.3 R&M Risk Areas .................................................................................................................................18 A.1.4 R&M Strategy .....................................................................................................................................19 A.1.5 The Evidence Framework..................................................................................................................19 A.1.6 R&M Claims........................................................................................................................................19 A.1.7 Limitations on Use.............................................................................................................................19 A.1.8 Conclusions and Recommendations ...............................................................................................19 A.2 R&M Case Reports ............................................................................................................................19 Annex B – Examples of R&M Risks at the Different Stages of a Systems Life Cycle ............................21 Annex C - CHECKLIST OF POINTS FOR ASSESSING THE ADEQUACY OF EVIDENCE ........................23 Annex D - R&M Risk Reduction Process ...................................................................................................24 ii Unclassified Unclassified DEF STAN 00-42 Part 3 Issue 3 Annex E - R&M Case Evidence Framework ...............................................................................................27 Unclassified iii Unclassified DEF STAN 00-42 Part 3 Issue 3 Foreword AMENDMENT RECORD Amd No Date Text Affected Signature and Date REVISION NOTE This standard is raised to Issue 3 to update its content. HISTORICAL RECORD This standard supersedes the following: Defence Standard (Def Stan) 00-42 part 3 Issue 2 dated 6 June 2003 ARRANGEMENT OF DEFENCE STANDARD 00-42 The proposed arrangement of the complete series of Def Stans comprising Def Stan 00-42 is shown below. Part 1 – One-shot devices/systems Part 2 – CANCELLED Part 3 – Reliability and Maintainability (R&M) Case Part 4 – Testability Part 5 – In-Service Reliability Demonstrations Part 6 – Maintainability Demonstrations a) This standard provides requirements for accommodating Ministry of Defence (MOD) R&M practices and procedures throughout the life of the project b) This standard has been produced on behalf of the Defence Material Standardization Committee (DMSC) by the Committee for Defence Equipment Reliability and Maintainability (CODERM). It reflects the conclusions of consultations among various authorities within the MOD and within industry. c) This standard has been agreed by the authorities concerned with its use and is intended to be used whenever relevant in all future designs, contracts, orders etc. and whenever practicable by amendment to those already in existence. If any difficulty arises which prevents application of the Def Stan, UK Defence Standardization (DStan) shall be informed so that a remedy may be sought. d) Any enquiries regarding this standard in relation to an Invitation To Tender (ITT) or a contract in which it is incorporated are to be addressed to the responsible technical or supervising authority named in the ITT or contract. e) Compliance with this Def Stan shall not in itself relieve any person from any legal obligations imposed upon them. iv Unclassified Unclassified DEF STAN 00-42 Part 3 Issue 3 f) This standard has been devised solely for the use of the MOD and its contractors in the execution of contracts for the MOD. To the extent permitted by law, the MOD hereby excludes all liability whatsoever and howsoever arising (including, but without limitation, liability resulting from negligence) for any loss or damage however caused when the standard is used for any other purpose. g) This Part of the standard has been developed to reflect current policy within Defence Acquisition. This Part of Def Stan 00-42 provides a description of the principles of progressive R&M assurance, and provides guidance on the content and the ownership of the R&M Case through the life of a system. The R&M Case is intended to be used throughout the procurement chain from Prime Contractor - Contractor down to individual sub-contractors and sub-suppliers. h) Annex A to this Part of the standard sets out the general requirements for the content of the R&M Case and R&M Case Report. This report provides a summary of the R&M evidence provided by various activities and a reasoned argument why the system will satisfy the R&M requirements. Unclassified v DEF STAN 00-42 Part 3 Issue 3 Unclassified 0 Introduction 0.1 Reliability and Maintainability (R&M) are vital performance characteristics that affect the operational availability, effectiveness, safety and the whole life costs of defence materiel. The provision of defence materiel with acceptable levels of R&M is therefore essential to the achievement of operational availability and effectiveness, economy of in-service maintenance support and optimised life cycle costs. 0.2 The R&M achievements of a system depend on all aspects of that system, including components, processes, hardware, software, people and the man/machine interfaces. R&M engineering is a systems engineering discipline and so R&M programmes must adequately address all these aspects. 0.3 To satisfy the R&M requirements, they must be fully understood and a suitable strategy with defined Project Management tasks must be developed. This should include the identification of R&M risk areas and consideration of how these risks will be managed. The strategy should be flexible in its approach to providing progressive R&M assurance, in that the results of R&M activities should be reviewed periodically against the R&M requirements and the R&M programme modified as necessary. 0.4 Def Stan 00-40 Part 1 recognises that different systems and technologies require particular or unique engineering activities. It now requires that the following objectives shall be satisfied: a) The R&M requirements of the Purchaser shall be determined and demonstrated to be understood by the Purchaser and Contractor; b) A programme of activities shall be planned and implemented to satisfy the requirements, and investigate the risks identified in 0.3 above; c) The Purchaser shall be provided with progressive assurance that the R&M requirements are being, or will be, satisfied and that confidence is building. The Contractor shall determine and agree with the Purchaser (Procuring Authority) which activities are required to fulfil the second objective. The third objective is to be satisfied by the provision of progressive assurance. It is intended that this assurance will be provided by means of a R&M Case. 0.5 The R&M Case is fully defined in Clause 5. It will remain with the system throughout its life and record all R&M evidence and data from design activities, trials, etc, through to in-service including field data. 0.6 Progress is monitored via R&M Case Reports which are periodic evaluations of the R&M Case and fully defined in Clause 5. 0.7 This Def Stan provides the Purchaser and Contractors with guidance on how to manage the R&M Case and also provides guidance on assessing and judging the adequacy of the outputs from R&M methods used in the programme. The R&M Case is produced by a process that progresses and records achievement in an Evidence Framework set against the Contractor’s target R&M measures. 0.8 vi Throughout this standard, the term R&M includes Testability, Durability and Availability. Unclassified Unclassified DEF STAN 00-42 Part 3 Issue 3 Standards for Defence – RELIABILITY AND MAINTAINABILITY ASSURANCE GUIDE - PART 3: R&M CASE 1 Scope 1.1 This part of the Def Stan provides a description of the principles of the R&M Case and provides guidance on its content and application through the life of a system. The R&M Case is intended to be used throughout the acquisition cycle from concept throughout the Concept, Assessment, Demonstration, Manufacture, In-Service and Disposal (CADMID) acquisition cycle phases. This part of the Def Stan is not intended to provide guidance on how to contract for progressive R&M assurance or the R&M Case. 1.2 This Def Stan has five main Sections which describe: a) The principles of the R&M Case (Clause. 5) b) The application of the R&M Case through the system life cycle (Clause. 6) c) Providing the evidence (Clause. 7) d) Guidance on how to present the evidence (Clause. 8) e) Guidance on how to assess the adequacy of the evidence (Clause. 9) The activities required for the achievement of R&M will depend on the nature and maturity of the system and are likely to vary significantly from one project to another. 1.3 Annex A describes the general requirements for the R&M Case and R&M Case Report. The guidelines in Annex A should not be considered as being prescriptive in nature as they are generic and do not attempt to be exhaustive. 1.4 Annex B provides examples of R&M risks at different stages of a system’s life cycle. 1.5 Annex C provides a checklist of points for assessing the adequacy of evidence. The checklist should not be considered to be prescriptive or exhaustive; it is generic and provides guidance to supplement the generic guidance provided in Clause 9. 1.6 Annex D describes the R&M risk reduction process shown in Figure 8 using illustrative examples where appropriate. 1.7 4.3. 2 Annex E describes the R&M Evidence Framework, expanding on the information given in Clause Warning The Ministry of Defence (MOD), like its contractors, is subject to both United Kingdom and European laws regarding Health and Safety at Work. All Defence Standards either directly or indirectly invoke the use of processes and procedures that could be injurious to health if adequate precautions are not taken. Defence Standards or their use in no way absolves users from complying with statutory and legal requirements relating to Health and Safety at Work. Unclassified 1 Unclassified DEF STAN 00-42 Part 3 Issue 3 3 Related Documents 3.1 The publications shown below are referred to in the text of this standard. Publications are grouped and listed in alpha numeric order. Designation Title British Standard 4778 Part 3 Glossary of International Terms (Availability, Reliability, Section 3.2 1991 (IEC 50(191 and Maintainability) 1990; Defence Standard 00-40 (Part 1) Reliability and Maintainability Management: Responsibilities and Requirements for Programmes and Plans; Defence Standard 00-40 (Part 7) Reliability and Maintainability NATO Terminology ; Defence Standard 00-49 Reliability and Maintainability MoD Guide to Terminology – Definitions; Defence Standard 00-60 Part 3 Logistic Support Analysis for Software. 3.2 The following publications may be helpful when using this document: IEC61508 IEC 61508 (Part 3) Functional Safety of Electrical/Electronic/programmable electronic safety-related systems, Part 3: software requirement; The TickIT Guide British Standards Institute; Defence Standard 00-40 through 00-49 Series of R&M Standards and Guides; Defence Standard 00-56 Safety Management; Defence Standard 00-60 Integrated Logistic Support. 3.3 A reference in this standard to any related document means that, for any dependent ITT or contract, the extant edition and all amendments of the document at the date of the ITT or contract applies unless a specific edition is indicated. 3.4 In consideration of 3.2 above, users of this standard shall be fully aware of the issue and amendment status of all related documents, particularly when forming part of an ITT or contract. Responsibility for their correct application rests with those users. 3.5 DStan can advise regarding where related documents are obtained from. Requests for such information can be made to the DStan Helpdesk. How to contact the helpdesk is shown on the outside rear cover of Def Stans. 4 Definitions 4.1 The R&M Case is defined as: “A reasoned, auditable argument created to support the contention that a defined system will satisfy the R&M requirements”. Starting with the initial statement of requirement, it will subsequently include identified perceived and actual risks, strategies and an Evidence Framework referring to associated, supporting and mitigating information. The R&M Evidence Framework will include data from design activities, trials, etc, through to in-service including field data as appropriate, recording any changes. It will, thus, manifest itself as a top-level control document, summarised periodically through the issue of R&M Case Reports linked to the Evidence Framework, record progress and remain with the equipment/system throughout its life until disposal. The R&M Case is, therefore, a progressively expanding body of evidence (see also Clause 5). 4.2 R&M Case Reports are periodic evaluations of the R&M Case (usually at predetermined points in the programme as agreed in the Evidence Framework). They report on the evidence, arguments and conclusions drawn since the last report (ideally referring out to all other forms of evidence including papers 2 Unclassified Unclassified DEF STAN 00-42 Part 3 Issue 3 and data sources wherever possible), providing an assessment of overall R&M achievement/progress and a review and evaluation of the R&M Strategy and Plan. They may be used to provide sufficient detail to allow a decision whether to proceed from one phase of a project cycle to the next. 4.3 The R&M Evidence Framework is a matrix of R&M risks that includes: a) Requirements for evidence to mitigate the risks; b) Activities necessary to obtain the required evidence; c) The evidence acceptance criteria; d) References to the evidence actually provided and confirmation of its acceptance (or rejection). It provides traceability of the R&M Case process through the life of the system. It is equally applicable to the Purchaser’s and Contractor’s risks and is typically presented in the form of a matrix. 4.4 A system is defined as “a combination of physical components, software, procedures and human resources organised to achieve a function”. 4.5 For the purposes of this Def Stan, definitions and clarifications of the terms is provided by: Defence Standard 00-49: Reliability and Maintainability, MOD Guide to Terminology. 4.6 Supplementary definitions are given in: British Standard 4778 Part 3 Section 3.2 1991 (IEC 50(191) 1990). 5 5.1 The Principles of The R&M Case Introduction 5.1.1 As a reasoned, auditable argument created to support the contention that a defined system satisfies the R&M requirements, the R&M Case provides an audit trail of the engineering considerations from requirements through to evidence of compliance. It provides the traceability of why certain activities have been undertaken and how they can be judged as successful. It is initiated at the Concept Phase, revised progressively during the system life cycle and will be summarised in R&M Case Reports at predefined milestones. Figure 1 illustrates the concept of building and arguing claims in the R&M Case using the evidence sources. 5.1.1.1 In practice, the collation of all documentation may be unmanageable, particularly where there are many and diverse sources of evidence. An acceptable solution is to present the R&M Case as the body of accumulated R&M Case Reports, which in turn refer out to source evidence (this is illustrated in Figure 2). 5.1.1.2 A number of specialist methods and techniques exist that may be used to generate evidence of software reliability; these are broadly divided into confidence-building claims based on analysis of the software development process, and techniques that generate direct evidence of the software’s reliability. 5.1.1.3 All the analyses, strategies, plans, evidence, assumptions, arguments and claims that make up the R&M Case are to be found within the boundary indicated by the dotted line in Figure 2. Unclassified 3 DEF STAN 00-42 Part 3 Issue 3 Unclassified Figure 1 – The Development of Claims Figure 2 – The Concept of the R&M Case 5.1.1.4 The Evidence Framework captures the current set of compliance and mitigation activities (and their success criteria) to address the R&M risks. It will typically be presented in the form of a matrix. The number, 4 Unclassified Unclassified DEF STAN 00-42 Part 3 Issue 3 content, objectives and timescales of the R&M Case Reports are determined and prescribed by the Evidence Framework. This starts with the initial work on the R&M Strategy & Plan and is updated throughout the project. Each R&M Case Report will reflect the latest state of the Evidence Framework (this is illustrated in Figure 3). This element of the R&M Case will contain details of the initial requirement and justification of the proposed solution. Figure 3 – Establishing and Developing the Evidence Framework 5.1.2 Figure 4 shows the relationship between the R&M activities and the overall process. It also shows that the evidence produced from the R&M activities may provide input to the Safety Case and the Logistic Support Analysis Record (LSAR) Unclassified 5 DEF STAN 00-42 Part 3 Issue 3 Unclassified General Delivery Process R&M Process Requirement R&M Requirements Analysis Analysis Evidence Summaries Requirements and System Description R & M Case R & M REQUIREMENTS SYSTEM DESCRIPTION REASONED ARGUMENT Strategy Strategy Feedback on Results EVIDENCE FRAMEWORK Feedback on Results Project Plans: eg. ILS Plan Project Risk Safety R&M Quality R&M Programme Plan Safety Case Report LSAR Activities: eg. Specify Design Analyse Qualify Produce R&M Activities: eg. Specify Design Analyse Test Acceptance Provide Output Figure 4 - The Relationship between the R&M Process, the overall Delivery Process and the Evidence Produced 5.2 R&M Strategy Overview 5.2.1 All projects are to have and maintain an over arching R&M strategy in the R&M Programme Plan. This is to ensure that the capability being procured demonstrates the required R&M characteristics through out its life. The strategy should also detail how the R&M characteristics will continue to be monitored inservice. 5.2.2 The Purchaser must determine the R&M requirements and their measurement base. The R&M requirements should include the anticipated system usage and its environment. In the absence of specific 6 Unclassified Unclassified DEF STAN 00-42 Part 3 Issue 3 direction from the Purchaser, the onus shall be on the Contractor to take the initiative and propose appropriate R&M design targets and a measurement base. 5.2.3 Through analysis of the R&M requirements, the Contractor should decide upon a robust but practicable design philosophy for the eventual solution. The consideration of the risks to achievement of the R&M requirements will result in a strategy for managing the risks and delivering the necessary assurance. The programme of activities must include verification and 'feedback' in order to mature the R&M strategy and Programme Plan in response to emerging evidence. 5.2.4 5.3 A description of the R&M strategy is given in Annex D. R&M Case Review 5.3.1 The R&M Case must be reviewed and updated if: a) The system is modified. b) There are changes in how or where the system is used. c) There are changes to interfacing systems d) There are changes in the R&M requirements. e) There is a deviation between actual performance and design intention 6 6.1 The Application of the R&M Case Through the System Life Cycle Introduction 6.1.1 The balance of effort on the development of the R&M Case during the CADMID life cycle of a typical system is illustrated at Figure 5. 6.1.2 The lines with arrows indicate how the main effort changes during the life cycle. Information will flow in the direction of the arrows at that stage; it will also flow backwards and forwards, particularly during the ‘selecting solutions’, ‘demonstrating solutions’ and ‘producing solutions’ phases. This flow of information will be part of the communications between the Purchaser and the Contractor. Following the “producing solutions” phase the main effort would remain with the Contractor if contracted to manage support of the system ‘in-service.’ 6.1.3 The role of the R&M Case in the identification and mitigation of R&M risks and in the build up of confidence in the achievement of R&M has already been discussed. The R&M Case is a living document, starting with the conception of a system, to meet a capability and continues to be developed through a number of stages of increasing detail throughout the project. The content and emphasis of the R&M Case will vary throughout the life cycle depending on the current R&M Risks. 6.1.4 Examples of typical generic risks at the different stages of the system’s life cycle are listed at Annex B. In addition there will be risks that are specific to individual projects. Unclassified 7 Identifying Solutions Purchaser Producing Solutions Demonstrating Solutions Purchaser Supporting Solutions Unclassified Purchaser Selecting Solutions Concept DEF STAN 00-42 Part 3 Issue 3 Contractor Contractor Purchaser Contractor Purchaser Contractor Contractor Purchaser Disposal Key: Purchaser - Main Effort Purchaser Purchaser - Monitoring Figure 5 - Example of Change of Balance of Effort over System Life Cycle 6.2 Initial R&M Case 6.2.1 The Purchaser must determine the R&M requirements and their measurement base. The R&M requirements should include the anticipated system usage and its environment. In the absence of specific direction from the Purchaser, the onus will be on the Contractor to take the initiative and propose R&M 8 Unclassified Unclassified DEF STAN 00-42 Part 3 Issue 3 design targets and measurement base. Where necessary references to other documents or evidence will also be included. 6.2.2 It is essential that all the R&M stakeholders are consulted at this stage to ensure that the requirements are captured fully. Specialist advice and the use of R&M modelling techniques will probably be necessary. The Purchaser should also begin identifying R&M risks to be included in the overall project risk register. 6.3 Tender Stage R&M Case and Case Reports 6.3.1 On receipt of an ITT containing the Initial R&M Case, the Contractor will analyse the R&M requirements and develop a strategy to satisfy these requirements. Strategy development should consider the following: a) Understanding the requirements b) Analysis of requirements to define system R&M targets c) Consideration of existing evidence d) Ensuring an appropriate development process (and/or architecture for software intensive programmes) is in place. e) Identification of risk areas (within the overall project risk register). f) Pass / fail criteria. g) Fall-back activities 6.3.2 The development of the R&M strategy will lead to a plan of R&M activities and an outline Assessment Phase R&M Case Report. The content of the R&M Programme Plan (to be included in the Tender) will be based on the work to achieve the R&M requirements and mitigate the R&M risks. At this stage the R&M Case Report should discuss the development of the strategy for providing R&M assurance and document the justification for the proposed activities within the R&M programme. The objective of developing the strategy is to provide confidence to the Contractor and the Purchaser that the risk of failing to meet the R&M requirements is minimised, before committing resources. 6.3.3 It is essential that the Contractor fully understands the requirements. These requirements should be considered in the widest sense, in that they should not only include R&M requirements, but also other aspects such as system usage, its environment, the man/machine interfaces, and supportability, all of which will have an impact on system R&M. To gain this understanding, the Contractor will be involved in dialogue with the Purchaser. This dialogue will result in a definitive statement of the Purchaser’s requirement and all the usage and environmental conditions thereof. This statement, articulated in the Contractor’s R&M Programme Plan, must give confidence that the first objective of the R&M programme (ref. Def Stan 00-40 Pt1 para d) has been fulfilled. 6.3.4 The R&M requirements must be analysed and understood to determine the Contractor’s target R&M measures. The Contractor’s target value is thus a design aim, to give margin over the R&M requirement. All the requirements that affect the system R&M must be analysed to determine their impact at system and subsystem level and the results of these analyses form part of the R&M Case. For example, the Purchaser’s requirements for the environment may be relevant to the system as a whole, but due to their location, some items will experience very different environmental conditions. (See Def Stan 00-40, Part 1, Annex A.). 6.3.5 The Contractor shall outline the design philosophy and principal design features (referencing and justifying software development processes where appropriate), and then identify the R&M risk areas for the proposed design. The key aspects that should be considered are: a) System maturity (e.g. a new concept versus systems which already exists); b) The likely R&M performance; Unclassified 9 DEF STAN 00-42 Part 3 Issue 3 Unclassified c) Time-scales; d) Cost. 6.3.6 The risks may be determined using a checklist and techniques such as brainstorming, but relevant engineering experience and judgement will have a significant input. These R&M risks should be aggregated with other contract risks into the overall Project Risk Management Plan. The R&M risks and the strategy for their management form part of the R&M Case. 6.3.7 At the bid stage the R&M Case Report should also include a partially completed Evidence/Acceptance Framework consisting of the proposed R&M activities, their ‘success criteria’, and the project milestone(s) at which this evidence will be produced. The Evidence Framework will be updated as the contract progresses, with references to the outputs from the activities. The ‘success criteria’ will be the criteria by which the R&M Case Reports will be judged as providing the necessary evidence. The criteria may be quantitative and/or qualitative evidence, i.e. numeric and/or non-numeric. For example: a) The success criterion for an improvement in reliability activity might be to grow the system reliability to 0.95. b) The success criterion for a failure consequence activity might be to identify and eliminate all single point mission-critical failures. c) The success criterion for a software development activity might be to demonstrate a robust development and fault avoidance strategy. 6.4 R&M Case and Case Reports - Post Contract Award 6.4.1 Following Contract Award, the Contractor will review the Assessment Phase R&M Case with a view to updating the R&M Programme Plan to accommodate any differences between the content of the ITT and the Contract itself. At this stage the R&M Programme Plan and the success criteria are formalised. Thereafter, the R&M Case will contain the evidence that the Programme Plan has been followed, reviewed and evaluated. In addition, it will contain (in the form of data, assumptions and arguments) the evidence that has been collected and details of the Evidence Framework. At the appropriate milestone in the contract specified by the Purchaser, the R&M Case should contain sufficient evidence that the applicable requirements have been achieved and that those still outstanding will be achieved with requisite confidence. This confidence is based on the provision of progressive assurance that the requirements will be achieved at the appointed time. 6.4.2 It is essential that the management of R&M is not separated from the design and project management activities. To this end, it is recommended that the lead for the achievement of R&M should rest with the Design and Development or Project Manager. 6.5 Purchaser’s R&M Activities During Procurement 6.5.1 During procurement the Purchaser should study the R&M Case Reports produced by the Contractor and monitor the mitigation of the R&M risks and the progressive achievement of the R&M requirements. 6.5.2 Provision should be made in the contract for an R&M Case Report review and acceptance process, led by the R&M Panel. 6.6 In-Service R&M Case 6.6.1 Once the system enters service it is important that the R&M performance of the system be maintained and monitored. Actual performance of the system and changes in the way that it is used or the environment in which it is used, must be carefully monitored and recorded. Significant changes should be analysed and corrective action undertaken to restore the levels of R&M identified and incorporated into the R&M Case where feasible and justifiable. This should be managed using a Data Reporting, Analysis and Corrective Action System (DRACAS), which in turn forms part of the R&M Case evidence. 10 Unclassified Unclassified DEF STAN 00-42 Part 3 Issue 3 6.6.2 The foundation for the In-Service R&M Case will depend on allocated responsibilities for management of the system in service. Should the original Contractor be allocated responsibility, it is expected that the extant R&M Case continues. If the Purchaser is responsible, then it is acceptable that the In-Service R&M Case develops to the previous interpretation of the procurement R&M Case, but capturing all evidence from earlier R&M activities and demonstrations. 6.7 Modifications It is possible that the system will require modifications whilst in-service, involving action by a Contractor. Should this happen, the Contractor may be required to build a discrete R&M Case using the Purchaser’s R&M Case as a base line. The Purchaser’s monitoring actions and the results will be captured in the InService R&M Case. 6.8 Progressive Assurance of R&M 6.8.1 In every project there will be potential for shortfalls in R&M performance. The recognition of R&M risks should prompt the selection of a programme of specific R&M activities as well as the core design proving activities, which will mitigate the risks. The objective is to build up a body of evidence, which provides assurance that the R&M requirements are being achieved. 6.8.2 The risks of not achieving the R&M requirements should be evaluated and managed by the application of risk management practice, which conventionally involves “scoring” of each risk in accordance with a set of criteria defined at the start of the project. The risk management process will commence at the bid stage and continue through the development, manufacture and in-service stages. This is an active process, which will react to changing levels of risk, and the emergence of new risks as the project progresses. 6.8.3 Figure 6 is presented as an illustration of the manner in which the level of R&M risks change during the course of a project. The vertical axis represents the level of R&M risks identified at any point in the project. As the body of R&M evidence increases, the R&M risks reduce and progressive assurance is obtained. The horizontal axis represents the time into the project, from the bid stage ‘a’, through project start ‘b’, to formal acceptance ‘c’, entry into service ‘d’, mid-life improvement and beyond. 6.8.4 The figure illustrates two types of product development: new development and modified Commercial Of The Shelf (COTS). At time ‘a’ (Bid Stage) the level of R&M risk is relatively high, but as the project progresses this level decreases until at ‘c’ (Acceptance) the body of evidence is sufficient to assure the R&M performance at entry into service. The body of evidence (assurance) should continue to build in-service as successful trials and usage are recorded and the residual R&M risks can be seen to reduce still further. 6.8.5 It must be recognised that the R&M risks will not always decrease. There will be occasions when the selection of a different design option, technology insertion or mid-life improvement will render a proportion of the evidence obsolete, and fresh evidence will need to be generated accordingly. Also there will be periods when no evidence is being provided, for example during testing, prior to the release of the test results. Unclassified 11 DEF STAN 00-42 Part 3 Issue 3 Unclassified New Development Solution Modified COTS Solution Re-design Increases Risk R&M Risks Mid-Life Improvement (technology insertion) Increases Risk plateau (awaiting further evidence) EVIDENCE INCREASING RISKS REDUCING a Bid Stage b Project Start c Acceptance d Entry Into Service e Mid-Life Improvement Time Into Project Figure 6 - Illustration of progressive Assurance Process 6.9 The R&M Programme Plan 6.9.1 The R&M Programme Plan and the R&M Case Report are two important documents that support the achievement of R&M. The R&M Programme Plan should contain a clear description of the management and organisational structure for R&M and a systematic programme of technical activities for satisfying the requirements and providing progressive R&M assurance. This should include the maintenance and updating of the R&M Case. 6.9.2 At the assessment stage, the Contractor’s R&M Case Report may be a section or annex to the R&M Programme Plan. During the contract, the Contractor’s R&M Case Report may be submitted at predefined project milestones with a progress report, and finally submitted at the end of the contract as evidence that the R&M requirements have been satisfied. 6.9.3 The R&M Programme Plan should be considered as a live document. Results from engineering activities may indicate that one or more R&M measures are not at the expected level and in order to satisfy the R&M requirements, additional or modified activities must be undertaken. The R&M Programme Plan should be maintained to reflect these changes necessary to satisfy the R&M requirements. 6.9.4 Some activities traditionally considered to be part of an R&M programme are not included to provide R&M assurance, but in order to generate information for other disciplines, such as Safety and Supportability. Although these activities may appear in the R&M programme, they may not necessarily be used to produce the R&M assurance that appears in the R&M Case. 6.9.5 Alternately, evidence from related activities within the support programme may contribute evidence for R&M progressive assurance and risk mitigation. The Integrated Logistic Support (ILS) or Supportability Engineering (SE) programme determines the optimum maintenance strategy for the system. The resulting maintenance programme and corrective maintenance in particular, generates the data for maintainability evaluation within the R&M Case. Such evidence should be included in the R&M Case. 12 Unclassified Unclassified 7 DEF STAN 00-42 Part 3 Issue 3 Providing the Evidence 7.1 During the contract, the R&M Case should bring together all forms of evidence and not just the results from numerical analysis and testing. These forms of evidence may include: a) Performance in previous usage; b) Analysis of Operating Duty Cycle; c) Design Calculations; d) Logistic Support Analysis (LSA); e) Predictions, Modelling; f) Testing; g) Simulation; h) Expert opinion including previous recorded success of the Contractor; i) Correct implementation of best practice; j) Contractor’s R&M Cases; k) Analysis of the software development process. 7.2 During the contract phase, R&M activities will be undertaken in order to generate evidence. It is essential that the activity results (the evidence) are reviewed progressively against their defined ‘success criteria’, and also assessed in terms of meeting the ultimate target R&M measures. If the results indicate that the system R&M performance is not at the expected level for the specific stage of the programme or that the evidence does not satisfy its ‘success criteria’, then the strategy may have to be modified. The R&M Programme Plan would be amended to include additional or modified activities. 7.3 As the contract progresses, evidence will be generated, gathered and evaluated in a series of R&M Case Reports, such that at the end of the contract the Evidence Framework will demonstrate that the R&M requirements have been met. It is difficult to describe the full range of evidence in its many forms that might be provided, however, indicative examples of what the R&M evidence might encompass are shown in Annex E. 7.4 Figure 1 shows that the reasoned arguments in the R&M Case can combine different types of evidence and also build on assumptions. It is important that these assumptions should be declared openly. During the R&M programme, the key assumptions should be validated where possible and this effectively replaces each assumption with evidence. The reasoned arguments enable claims to be made about the expected R&M performance, and these claims, together with their backing evidence, make up the R&M Case. 8 Guidance On How To Present The Evidence 8.1 This section provides guidance on how to present the evidence in the R&M Case. The activities required for the achievement of R&M will depend on the nature and development state of the system and are likely to vary significantly from one project to another. 8.2 Before undertaking an R&M activity it is essential that the objective of the task is fully understood, and success criteria defined. The success criteria should be those by which the activity can be judged, and will substantiate a claim in the R&M Case Report. It should be noted that not all activities lend themselves to a quantified success criteria, and may require qualitative criteria based on the objectives of the activity. For example, the success criteria for modelling are not simply that the predictions and modelling show compliance of the proposed design with the requirements. More important are considerations such as does Unclassified 13 DEF STAN 00-42 Part 3 Issue 3 Unclassified the modelling include representative usage of the system or have all system elements (e.g. software) been included in the modelling. 8.3 Many of the available R&M methods do not deliver R&M assurance directly but when used in combination with other associated methods. For example, an analysis technique such as Fault Tree Analysis may identify a design weakness, but improvement and assurance are only provided when the weakness is addressed at design reviews and corrected with sanctioned follow up action. 8.4 The evidence of R&M assurance does not just result from the generation of the activity results, but also from the implementation of actions arising from the risk identified by the activity. Undertaking the activity at the appropriate time such that it will influence the design is very important. Therefore the evidence from the analysis consists of the documentation showing that actions have been implemented in a timely manner. 8.5 Activities should be carried out in parallel with the design process, so that the analysis can influence the design and reflect the final design. If more than one design option is being considered, then each outcome should be considered separately, so that the implications on reliability and the consequences of failure can be assessed before deciding on the preferred design option. 8.6 The input to the R&M Case from an activity can be considered to include the following parts: a) Objective and Success Criteria (what the activity plans to achieve, and defining how and when the activity has been successful); b) Outputs (the outputs from the activity); c) Assumptions; d) Evidence (how the outputs substantiate claims in the R&M Case Report); e) Development and Maintenance of Evidence (how will the results of the activity be maintained to reflect the latest design). 8.7 For software-intensive systems specific techniques may be required to provide assurance of availability, of the software delivered functions. 8.8 There are two complementary techniques used to achieve software reliability requirements at the design and implementation phase, the results of which may be used to support the R&M Case. These are: a) Fault avoidance. This requires that contractors take steps to avoid faults during software development, and to detect and correct those faults that do occur. b) Fault tolerance. It is unlikely that fault avoidance will succeed completely, and to achieve high reliability it is also necessary to design the software to correct or tolerate errors in service. 8.9 With the use of these design and implementation techniques in place, several numerical analysis techniques may be used to provide evidence of software reliability, which may also be used to support the R&M Case to show that the system satisfies the R&M requirements: a) Reliability growth modelling; b) Statistical testing; c) Performance testing; d) Exhaustive testing; e) Field data and fault data. 14 Unclassified Unclassified 9 DEF STAN 00-42 Part 3 Issue 3 Guidance on How to Assess the Adequacy of Evidence 9.1 The adequacy of evidence is primarily a function of its practical impact on the reduction of R&M risks, i.e. progressive assurance. Whilst it is not necessary to assess the adequacy of specific, detailed R&M tasks in their own right, the visibility, traceability and quality of evidence produced are crucial factors. It is therefore necessary to confirm that the evidence is generated, managed, validated and used within a closed loop system of R&M practices and controls, and that it achieves the principal objectives of Def Stan 00-40 Part 1. Figure 8 illustrates a representative closed loop system (R&M risk reduction process), based upon which, criteria for assessing the adequacy of evidence are derived in this section. 9.2 Figure 7 comprises four main sections from left to right. The left hand section reiterates the principal objectives of Def Stan 00-40 Part 1. These represent the highest level criteria for the adequacy of evidence and need to be borne in mind as key objectives, throughout the risk reduction process. The R&M practices, which are fundamental to assuring R&M, are high level, ‘objectives-oriented’ processes which depend on the appropriate traditional R&M activities, e.g. commercial standards (or tailored R&M activities), for specific analyses, tests and results. The R&M Practices exchange evidence between themselves and output evidence to the other processes, grouped in Figure 7 as R&M controls. These processes are based on ‘Review the Evidence’ and lead to the ‘R&M Strategy’, ‘R&M Plan’ and ‘Manage R&M’. At any stage, inadequate evidence should stimulate a review of the ‘R&M Strategy’ and ‘R&M Plan’. ‘Manage R&M’ provides a control feedback path to all of the R&M Practices (and selected R&M activities within them), to deliver the evidence required. In this way, the R&M Processes are focused at all times on providing progressive assurance that the risks are being managed. The right hand side of Figure 7 identifies the key outputs of the risk reduction process, including the ‘R&M Risk Register’ (which is part of the Project Risk Register), ‘R&M Case & Reports’ and the ‘Assessment of Adequacy’ of the evidence. Note that the latter does not address adequacy of the R&M Case & Reports intrinsically. 9.3 The R&M risk reduction process is applicable at any project phase, and to any contractual arrangement. In the diagram, an ‘alpha’ identifier has been allocated to each process block for reference purposes only. The identifiers do not signify chronological sequence, as the processes are interactive and often concurrent. Depending on the stage in the acquisition cycle for a new, developing or Off The Shelf (OTS) system, both the relevance of different practices and the order in which they are conducted will vary. However, there must always be a Risk Register, R&M Strategy and R&M Plan as core elements of the process. Wherever possible, the two general practices, ‘Collate Existing Evidence’ and ‘DRACAS/In-Service Feedback’ should be on-going, spanning different generations and versions of similar systems. All relevant, available information on the R&M performance and lessons learnt with one system should be used to provide assurance of R&M in similar systems. 9.4 For a particular development contract, entry into the process is achieved by developing an R&M Case, using at least the practices (a) to (e) of Figure 7, including R&M modelling/simulation as an activity. The available evidence (including R&M Risks) is reviewed, an R&M Strategy is determined and R&M Planning and Management implemented to control and monitor R&M activity. Once the process is established for a particular project, the R&M Practices and Controls should be implemented and maintained in the most expedient manner to generate and manage evidence which mitigates R&M risks and provides, within the acquisition cycle, the earliest possible indication that the R&M requirements have been achieved. 9.5 The principal criteria for assessing the adequacy of evidence are therefore as follows: a) the evidence as a whole is clearly derived from a closed loop R&M risk reduction process such as Figure 7, see Annex D for guidance on the principles of specific process blocks; b) the origin of any specific item of evidence is unambiguously linked to specific R&M Practice(s) and/or Control process(es); c) the links between any specific item of evidence and the R&M Risk Register, Strategy and R&M Plan are shown; d) the evidence from any particular R&M activity is presented in accordance with Para. 8.6; Unclassified 15 (b) Assess R&M Requirements Control Evidence (c) R&M Design Philosophy (d) Allocate R&M Design Targets (e) Assess R&M Risks (l) Review the Evidence Risk Register (f) Design for R&M (g) R&M Status/Design Review (m) R&M Strategy R&M Case and Reports (h) Measure R&M (i) Plan Transition to Production (n) R&M Plan The Purchaser has assurance that the requirements have been satisfied (k) DRACAS/In-Service Feedback (o) Manage R&M Objectives R&M Practices R&M Controls Assessment of Adequacy (j) Plan Transition to In-Service Outputs Unclassified A program of activities has been planned and implemented to satisfy the requirements Key: Insert Annex Title Here(or delete/leave empty if not required) Unclassified Figure 7 – R&M Risk Reduction Process The Purchaser's R&M requirements have been determined and demonstrated to be understood DEF STAN 00-42 Part 3 Issue 3 16 (a) Collate Existing Evidence Unclassified DEF STAN 00-42 Part 3 Issue 3 e) the status of each item of evidence, in terms of its relevance, completeness, accuracy and how it has been used to influence the system and reduce risk, can be readily identified in the Evidence Framework. 9.6 In order to assess the adequacy of evidence, auditable methods/techniques, assumptions, and detailed results will be sought. Consequently, an open, honest dialogue between partners will be of high importance. Judgement will be required to assess the evidence presented, including its visibility, traceability and quality in accordance with the criteria listed above. Annex C provides a checklist of generic points which are not prescriptive, but which should provide additional guidance on assessing the adequacy of evidence in appropriate circumstances. 9.7 Annex D outlines the principles of the process blocks in Figure 8 and provides guidance on the context for assessing the adequacy of evidence against the criteria listed in 9.5. Normally, all of the R&M Control processes, and the relevant R&M Practice processes, need to be considered for a particular system/phase, the selection of any particular process being driven by the need to provide evidence against the R&M risks. Due to the broad scope of the guidance, the Annex does not recommend specific R&M activities but it identifies examples where appropriate to help illustrate a point. Unclassified 17 DEF STAN 00-42 Part 3 Issue 3 Unclassified Annex A – General Requirements for the R&M Case and R&M Case Report A.1 R&M Case The following paragraphs provide the headings and describe the content for sections within the R&M Case. It is not envisaged that this structure will be suitable for every contract, but it is intended to provide guidance on the information that should be contained within the reports A.1.1 System Description The system description should contain the following items: a) System description – this should briefly describe the system’s physical or functional characteristics; b) System boundary – this should describe the system’s physical or functional boundary. Block diagrams may provide a good method of illustrating the boundary of the system considered in the case; c) Usage – this should describe the system’s primary role or function, and any secondary roles. It should include its typical peacetime and wartime mission profiles; d) Environment – this should describe the system’s operating environments; e) Interfaces with other equipment/systems – this should define equipment associated with the inputs, outputs and services to the subject system. Where appropriate, it should also describe such equipment physically near to the installed system; f) Build standard / software version – this should relate to a specific build standard of the system, including software version(s) where appropriate; g) Configuration control – to ensure the report reflects the latest build standard/version, the description should indicate where the latest build standard/version is defined, for example, the Master Record Index; h) Personnel skill levels and training – the skill level and the training required to operate and maintain the system should be described; i) Maintenance policy – this should describe the support regimes for each of the system’s role or mission profiles. A.1.2 R&M Requirements This should reflect the Purchaser’s requirements and the Contractor’s understanding of those requirements. The requirements should be considered in their widest context, in that they should include the environment and usage requirements, as well as the explicitly defined R&M requirements. The Contractor should describe how the requirements have been interpreted for his proposed design solution and developed into contract target R&M measures. A.1.3 R&M Risk Areas Through analysis of the R&M requirements, the Contractor should identify the risk areas associated with the system satisfying the R&M requirements, and the how these risks will be, or have been managed during the contract 18 Unclassified Unclassified DEF STAN 00-42 Part 3 Issue 3 A.1.4 R&M Strategy Based on the risks identified, the maturity of the proposed design solution and the R&M requirements, the Contractor should determine a strategy for meeting the requirements and providing the necessary assurance. This strategy will justify the activities in the Contractor’s R&M programme and identify the success criteria for these activities. A.1.5 The Evidence Framework This section should provide a complete overview or plan of evidence to be provided during the acquisition phase. It should also show when and by whom R&M Case Reports will be issued. Specific entries in the Evidence Framework can be selected by the Purchaser and may be matched to payment milestones for control purposes. A.1.6 R&M Claims Typically, the claims will be that the system will satisfy each of the R&M requirements. This section should provide a reasoned argument why each of the requirements will be met in service, based on the evidence and any assumptions. All assumptions should be listed explicitly. A.1.7 Limitations on Use This section should define the boundaries on system use, which if exceeded will mean the R&M claim may no longer be valid. These limitations will include the system’s operating envelope, the environment and important maintenance activities. A.1.8 Conclusions and Recommendations This section should contain a diary of the conclusions drawn from the R&M evidence accumulated to date, including whether the system is likely to satisfy its R&M requirements. In interim issues, it should recommend whether the project should proceed to its next milestone, or what further work is required to enable the project to progress. In addition, it should recommend what activities should be conducted in the future in order to generate the necessary assurance that the R&M requirements will be satisfied. A.2 R&M Case Reports A.2.1 The remainder of this annex provides guidance on the content of R&M Case Report. The R&M Case Report provides R&M evidence at a specific stage within the R&M Case Evidence Framework. The reports present an argued claim, based on evidence and assumptions that the system will satisfy the R&M requirements. The report is not expected to contain all the evidence produced for that stage, but will summarise and act as a ‘signpost’, indicating where the detailed evidence may be found. A.2.2 This standard jointly refers to R&M, which might be taken to imply that documentary evidence for Reliability and Maintainability will be summarised in a single report. However, this does not mean that the R&M Case Reports must be documented in the same report. If the Evidence Framework requires separate reports, or the Purchaser or Contractor considers that having separate reports will present a clearer picture, or provide a more focused approach, separate Reliability and Maintainability Case Reports are considered perfectly acceptable. A.2.3 Format for R&M Case Report: a) Introduction. Each R&M Case Report should list and cross reference the parent requirements in the Evidence Framework, against which the evidence is to be judged, and be traceable to the original Purchaser’s requirement. b) Body of Evidence. This should index the existing evidence. Every item of evidence should be crossreferenced to the Evidence Framework, and each of the risks to which it mitigates. The following list comprises examples of the type of evidence which should be included: Unclassified 19 DEF STAN 00-42 Part 3 Issue 3 Unclassified • Information from relevant similar systems R&M Cases or in-service experience; • Contractors’ evidence and R&M Case Reports; • Analysis of R&M requirements and operating conditions; • Design Philosophy; • LSA; • Targets; • Risks; • Strategy, including assumptions, arguments, claims; • Plan of R&M Activities; • Outputs from R&M Activities; these should include the relevant design R&M calculations, use of best practice, predictions and modelling, analyses, simulation, testing, DRACAS/In Service Feedback and expert opinion; • On going re-assessment of risks. The body of evidence should also trace the history of reviews and updates of the R&M design philosophy, targets, strategy and plan, which keep these in line with the changing status of the original risks, as well as any new/emerging risks. c) Review of Evidence To Date. This section should provide a balanced review of the body of evidence in terms of its completeness, timeliness and acceptability with regard to the criteria contained in the Evidence Framework. d) Conclusions. The status of the R&M assumptions, evidence, arguments, claims and residual risks should be summarised and discussed. Conclusions should be drawn with regard to the status of the progressive assurance and the activities necessary to mitigate the residual risks. e) Recommendations. The recommendations should be based on current shortfalls in the evidence available and propose changes, as appropriate, to the R&M design philosophy, targets, strategy, and plan in order to maximise the progress towards assuring that the system will satisfy each of the R&M Requirements. 20 Unclassified Unclassified DEF STAN 00-42 Part 3 Issue 3 Annex B – Examples of R&M Risks at the Different Stages of a Systems Life Cycle System Stage Risks will Include Concept Failure of the User to adequately define what they require. Failure to allocate sufficient financial resource to satisfy the Users aspirations. Failure to allocate sufficient time to satisfy the Users aspirations. Failure of the Purchaser to define the requirements adequately. Failure of the Purchaser to define the requirements correctly. Failure of the Purchaser to allocate sufficient resources to achieve requirements. Identifying Solutions Failure of the Purchaser to communicate the requirements to the Contractor. Failure of the Contractor to understand the requirements. Failure of the Contractor to identify all the R&M risks. Failure of the Contractor to produce an appropriate plan to mitigate the R&M risks. Failure of the Purchaser to monitor progress. Failure of the Purchaser to select the most appropriate solution. Failure of the Purchaser to modify the requirements where appropriate. Failure of the Purchaser to communicate the modified requirements to the Contractor. Failure of the Contractor to understand the modified requirements. Failure of the Contractor to identify all the R&M risks. Failure of the Contractor to produce an appropriate plan to mitigate the R&M risks. Failure of the Purchaser to monitor progress. Demonstrating the Solution Failure of the Contractor to work to their plan to mitigate the R&M risks. Failure of the Contractor to monitor and review progress and amend their plan where appropriate. Failure of the Contractor to capture all available data and process it appropriately to produce evidence. Failure of the Contractor to produce sufficient evidence to demonstrate R&M to the satisfaction of the Purchaser. Failure of the Purchaser to monitor progress. Producing the Solution Failure of the Contractor to identify and manage the R&M risks associated with the transition from development to production. Unclassified 21 DEF STAN 00-42 Part 3 Issue 3 System Stage Unclassified Risks will Include Failure of the Contractor to monitor and review progress and amend their plan where appropriate. Failure of the Contractor to demonstrate the R&M of their systems to the satisfaction the Purchaser. Failure of the Purchaser to monitor progress. Supporting the Solution Failure of the Purchaser to ensure that the solution is used, maintained and supported as specified. Failure of the Purchaser to monitor changes in use, environment and support. Failure of the Purchaser to identify the R&M risks that result from a change in use, environment and support. Failure of the Purchaser to mitigate the R&M risks that result from a change in use, environment and support. Disposal Failure of the Purchaser to capture, record and disseminate R&M ‘lessons learnt’ (including evidence) from the project. Note 1: The Purchaser may choose to delegate some/all of the responsibility for managing these risks to a Contractor. Note 2: Risks associated with obsolescence have been included in ‘support’. Note 3: Specific examples of Technical Risk have not been included but should be considered on a case-by-case basis. 22 Unclassified Unclassified DEF STAN 00-42 Part 3 Issue 3 Annex C - Checklist of Points for Assessing the Adequacy of Evidence C.1 This Annex provides a checklist, which should be considered as a prompt to initiate action where the checklist points have relevance and does not imply a ‘Yes’ and ‘No’ answer. Judgement is required to evaluate the evidence presented. The checklist must not be considered as being prescriptive or exhaustive: it is generic and provides guidance to supplement the general guidance provided in Clause 9 of the standard. CHECKLIST: a) Are the objectives for the activity clearly defined? b) Has the activity been undertaken in a systematic manner and is it complete? c) Has the activity been undertaken at a time that will allow influence on the design? d) Has the usage and environment considered for the activity been documented? e) Has the physical and functional boundary of the activity been defined? f) Are any assumptions defined (e.g. inputs from other systems or services), and are they realistic and reasonable? g) Is justification given for the activity method/technique used, and is it reasonable? h) Who was consulted during the activity, (e.g. user, maintainer, designer etc)? Was this level of consultation reasonable? i) Are the activity recommendations clearly defined, and are they reasonable? j) Does documentary evidence indicate that the recommendations have been implemented? k) Have the activity results been progressively updated to reflect the latest design, and are these being used as an input to design reviews? Unclassified 23 DEF STAN 00-42 Part 3 Issue 3 Unclassified Annex D - R&M Risk Reduction Process D.1 This Annex presents the principles of the process blocks, which are illustrated in Figure 8 (repeated below). It contains guidance on the context for assessing the adequacy of evidence against the criteria of Clause 9.5. The process identifiers and titles from Figure 8 are listed below, followed by an indication of the principles of what the evidence should comprise and how it would relate to other processes. Illustrative examples are included, where appropriate. Normally, all of the R&M Control processes, and the relevant R&M Practice processes, would need to be considered during each acquisition phase: a) Collate Existing Evidence; information from relevant similar system R&M Cases or in-service R&M experience, including both successes and failures; arguments and justification for using it to mitigate risks and generate assurance; confirmation of an on-going commitment to R&M improvement. b) Assess R&M Requirements; interpretation of operating and maintenance scenarios, environmental profiles and the understanding of: • the Purchaser’s R&M Case; • permissible/degraded modes of operation; • mission dependent operational success and failure criteria; • qualitative and quantitative R&M requirements; • storage and transportation needs; • design loads. c) R&M Design Philosophy; a process of continuous improvement and commitment to providing assurance of robust design, eliminating known failure mechanisms or increasing time to failure to an acceptable level; fault avoidance techniques for software development; specific R&M design criteria (e.g. redundancy/fault detection and recovery) necessary to achieve the assessed requirements (b), using lessons learnt from previous systems (a); necessary R&M resources to implement the philosophy. d) Allocate R&M Targets; based on appropriate R&M analysis and modelling, quantitative/qualitative targets allocated to subsystems/components; confirmation that these are practicable, realistic and fully consistent with the R&M requirements. e) Assess R&M Risks; formalised, systematic identification and evaluation of R&M Risks; details of technical and timescale risks with regard to the R&M requirements; input to and maintenance of the R&M Risk Register detailing the current status, whether open or closed, of all identified R&M risks; integration with the Project Risk Register; links to the R&M Strategy (m) and re-evaluation of risks in order to assess the risk reduction available from R&M Practices contained in the Strategy; links with the Evidence Framework. f) Design for R&M; design to meet the R&M Requirements, Design Philosophy, Targets and Strategy (b), (c) and (d) and (m); system description/justification; design margins; confidence in R&M at internal and external interfaces. g) R&M Status/Design Review; evidence of independent assessment and review of design decisions, analyses and tests that impact on R&M, documented to provide an auditable trail; R&M contributions to formal Design Reviews; confirmation that the status of R&M processes and activities are in accordance with the Strategy and Plan. 24 Unclassified (a) Collate Existing Evidence The Purchaser's R&M requirements have been determined and demonstrated to be understood (b) Assess R&M Requirements Control Evidence (c) R&M Design Philosophy (d) Allocate R&M Design Targets (e) Assess R&M Risks (l) Review the Evidence Risk Register (f) Design for R&M (g) R&M Status/Design Review (m) R&M Strategy R&M Case and Reports (h) Measure R&M (i) Plan Transition to Production Unclassified Unclassified A program of activities has been planned and implemented to satisfy the requirements Key: (n) R&M Plan The Purchaser has assurance that the requirements have been satisfied (k) DRACAS/In-Service Feedback (o) Manage R&M Objectives R&M Practices R&M Controls Assessment of Adequacy (j) Plan Transition to In-Service 25 DEF STAN 00-42 Part 3 Issue 3 Outputs DEF STAN 00-42 Part 3 Issue 3 Unclassified h) Measure R&M; results of R&M tests on specific components/subsystems and a representation of the final system, as determined by the Strategy and Plan; software performance testing; confirmation of use and impact of DRACAS (k) to mitigate all recorded failures. i) Plan Transition to Production; plan for the design and validation of manufacturing systems and processes in order to protect critical items, realise the design performance and quality requirements and safeguard a smooth transition to production. j) Plan Transition to In-Service; plan for R&M risk control activities and R&M demonstration plans for the transition to in-service. k) DRACAS/In–Service Feedback; all incidents should be subject to DRACAS; relevant lessons learnt and corrective actions determined from this and previous systems; confirmation that these have been implemented on the system. l) Review the Evidence; this should be a routine review of all evidence arising and conducted, exceptionally, whenever the findings from any of the R&M Practices need to be considered urgently; all items of evidence should be specifically linked to, and traceable with regard to, the R&M Strategy (m), Risk Register (e), R&M Plan (n) and the Evidence Framework. m) R&M Strategy; this forms the response to the assessment of available evidence (l); creation and maintenance of a structure of Assumptions, Claims, Arguments and Evidence needed to assure R&M; definition of appropriate R&M Practices necessary to deliver the evidence; the assumptions must be justified and the claims must be practicable and realistic, based on what has been achieved in the past; the Strategy should be linked to the R&M Requirements and justified by a re-assessment of the R&M Risks (e), assuming the Strategy had been implemented; timescales and acceptance criteria for the required evidence, should be derived; R&M Test Strategy, covering the R&M functional testing provisions, should also be derived; specific requirements for the R&M Plan; definition and development of the Evidence Framework to manage the evidence requirements. n) R&M Plan; this responds to the R&M Strategy by defining a schedule of specific R&M activities, e.g. system R&M modelling, FMEA, accelerated testing etc., in context with the appropriate R&M practices; evidence and justification for the task selection, clearly linked to risk control activities of the strategy; success criteria, including outputs and milestones; R&M management, monitoring and control activities and review schedules; links with the Evidence Framework. o) Manage R&M; to complete the loop, evidence of R&M Management, including status of the plan, should feed into (l). 26 Unclassified Unclassified DEF STAN 00-42 Part 3 Issue 3 Annex E - R&M Case Evidence Framework E.1 The R&M Evidence Framework is a matrix comprising the R&M requirements, the R&M risks associated with achieving and satisfactorily delivering the requirements, and one or more programmes of activities to mitigate such risk and enable the requirements to be delivered. As with the Risk Register the R&M Evidence Framework is a living document which needs to be maintained throughout the acquisition cycle to enable assurance and confidence to be developed in the solution and presented through the population of the R&M Case. E.2 R&M Programme Plan shall comprise a number of discrete activities that, when integrated together, will be employed to add value to the project and mitigate these risks. For each activity; the plan will require: (a) The aim of the activity; (b) The pass and fail criteria for that activity; (c) The method by which success will be measured; (d) The fall back activity in the event of failure. Together these criteria will form part of the evidence framework and in due course populate the R&M Case. E.3 In these early stages of the project such plans will be generic recognising the requirement for development and growth, and later that of prove and demonstrating compliance. Potential contractors will be required to specify exactly how they intend to mitigate the perceived risks accompanied by detailed proposals to provide just such evidence. Where resources are limited alternative strategies will be required, hence the importance of addressing these at the earliest opportunity and recognising that one R&M strategy may not fit all. E.4 The R&M Case Evidence Framework is defined in Clause 4.3. Suitable column headings and contents are described below: Column No. Heading Contents 1 Project Phase Relevant phase in the product life cycle 2 Risk Ref Relative to the Project Risk Register 3 Risk Description and initial Risk Score Relative to the Project Risk Register 4 Risk Cause A description of the underlying cause of the risk 5 Evidence Required Evidence needed to mitigate the risk (information, not deliverable reports) 6 R&M Practice Process required to generate the necessary evidence (usually a combination of traditional R&M and other activities, i.e. not necessarily an individual R&M Activity or Technique) Initial Risk Score This is the R&M Risk Score which, in the examples, is assumed to be on a scale of 0 to 1, for increasing risk Acceptance Criteria 7 Evidence Deliverable document/contents 8 Target Risk Score Acceptable risk score 9 Time Due Time the evidence is due Acceptance Status Unclassified 27 DEF STAN 00-42 Part 3 Issue 3 Unclassified Column No. Heading Contents 10 Evidence References to the latest evidence, including Issue No, and date delivered 11 Approval Signature of approving authority and date of acceptance E5 Two example R&M Case Evidence Frameworks are illustrated below. Each covers a selection of risks at various stages in the system life cycle, assuming the system involves substantial development activity. However, the examples are not intended to cover all the R&M Risks with the system, and should not be used as a template. When creating an Evidence Framework, the system should be considered in its own right. The risk scores are arbitrary and, in practice, should be used to prioritise the R&M activities. 28 Unclassified Evidence Framework for System ‘X’ Issue: Date: Signature: Acceptance Criteria Risk Ref. Risk Description and initial risk score Risk Cause Evidence Required R&M Practice Assessment RM 003 There is a risk that the system will fail to achieve its specified reliability: 99.9% over a 24 hour BFM. Intrinsic reliability of solution components not assessed/ understood Part Failure Rates Parts count Prediction using in-service experience of similar parts, defaulting to industry standard data sources, e.g. generic failure rate data if no other data available. Initial Score = 0.25 Failure modes and criticality of solution(s) not assessed/ understood Mission critical failure modes and failure rates for single and double faults. FMECA: this information will be provided by the design FMECA, conducted as design practice (OP Procedure 21). Evidence Acceptance Status Target Risk Score Time Due System reliability RBD modelling and analysis for 24 hour BFM, based on 1) to 3) above. Solution does not perform as predicted in service In-Service Demonstration of ARM Monitoring and reporting of in-service defects through Defect Reporting via analysis of DRACAS database. 28 Draft ISRD Plan, including acceptance criteria with regard to the 24 hour BFM requirement. ISRD Report showing compliance with the requirement. 2 weeks prior to Final Design Review 1 year after entry into service DEF STAN 00-42 Part 3 Issue 3 System reliability over 24 hour BFM Approval Signature: Date: 2 weeks prior to Preliminary Design Review, update prior to Critical Design Review Development Tests and DRACAS: a) to support previous assumptions on failure modes and failure rates; b) to trigger further development and testing of unsatisfactory items and, c) to initiate selection of alternative parts. Reliability of solution system not assessed/ understood Evidence Reference: Issue No: Date Delivered: Unclassified Unclassified Project Phase Issue: Date: Signature: Acceptance Criteria Risk Description and initial risk score Risk Cause Evidence Required R&M Practice Assessment (cont) RM 022 There is a risk that the system BIT requirements will not be achieved. No clear approach by the Purchaser to Testability Testability Design Strategy Testability Requirements not verified System integration fails to address wild heat and maintainer access Evidence Target Risk Score Time Due 1) Review BIT Design Strategy in the light of the functional hierarchy developed in the FMECA (see RM001). Internal document providing results of the Review and showing that the Testability Design Strategy is consistent with the functional hierarchy and the BIT requirements for: Start-up Continuous checks Diagnostics Location. 0.2 6 weeks prior to Critical Design Review Testability Evaluation Extension of the FMECA to provide an evaluation of BIT coverage. BIT Evaluation Report showing that the system testability is consistent with BIT requirements for: Start-up Continuous checks Diagnostics Location. 0.1 6 weeks prior to Final Design Review Technology Demonstration Programme (TDP) to include R&M assessments R&M predictions conducted to support the TDP TDP R&M Prediction report 0.1 6 weeks prior to Critical Design Review Initial Score = 0.3 Unclassified RM 023 There is a risk that the integration of latest communications equipment into the design will compromise the R&M performance of the complete system Initial Score = 0.3 Acceptance Status Evidence Reference: Issue No: Date Delivered: Approval Signature: Date: DEF STAN 00-42 Part 3 Issue 3 Risk Ref. DRAFT Unclassified Unclassified Unclassified Project Phase DEF STAN 00-42 Part 3 Issue 3 DEF STAN 00-42 Part 3 Issue 3 30 Evidence Framework for System ‘X’ Evidence Framework for System ‘X’ Issue: Date: Signature: Acceptance Criteria Project Phase Risk Ref. Risk Description and initial risk score Risk Cause Evidence Required R&M Practice Demonstration RM 032 There is a risk that sub system X will require unscheduled replacement Initial Score = .35 Wear out mechanisms not fully understood Evaluation of expected life and determination of any changes necessary to achieve the requirement. RM 044 There is a risk that the chassis will suffer from stress/fatigue during system assembly Initial Score =0.28 Assembly activities include loading that is very different from when system is complete Target Risk Score Time Due Review of life data on similar items and environmental evaluation /stress calculations, to determine ageing factors and critical components. Stress Calculations, justification of (any) necessary design changes and Accelerated Life Test Plan. 0.2 3 months after Contract Award Accelerated Life Testing using the Highly Accelerated Life Test methodology. Accelerated Life Test Report providing assurance for the final design. <0.15 6 months after receipt of test model(s) Evaluation of the Load Case. Report, including analysis and calculation records, showing stress margins. The report will highlight (any) areas of potential overstress and justify changes, if needed, to ensure adequate margins. 0.2 3 months prior to completion of Demonstration Phase Production Reliability Acceptance Test. PRAT Test Plan. PRAT Test Results assuring the integrity of the chassis for manufacture. <0.1 PRAT Plan required before start of Production. PRAT Test Results following completion of PRAT. Final Quality Inspection of Deliverables. Quality Inspection Records. <0.1 During production Evidence Reference: Issue No: Date Delivered: Approval Signature: Date: 28 DEF STAN 00-42 Part 3 Issue 3 Analysis of loads on the chassis when suspended; determination of changes to the chassis design and/or the manufacturing fixture(s) to ensure that the expected life of the chassis is not compromised. Demonstration of manufacture Evidence Unclassified Unclassified Manufacture Acceptance Status Issue: Date: Signature: Acceptance Criteria Risk Ref. Risk Description and initial risk score Risk Cause Evidence Required R&M Practice Concept RM 001 Inadequate/Incorrec t definition of R&M requirements by Purchaser. R&M aspects not addressed within Systems Engineering, therefore impact of R&M on capability not fully understood. R&M requirements are not SMART. Critical R&M System Attributes. Operational Availability Targets. Adequate System Numbers. Initial R&M Targets linked to Operational Availability. Assessment of the impact of R&M on Operational Effectiveness. Failure of the Purchaser to allocate sufficient resources to achieve requirements Purchaser fails to realise the link between R&M and Cost of Ownership Initial risk score = 0.7 The Purchaser fails to consider the impact of the requirements on the need for complex or novel technology Initial risk score = 0.4 Unclassified RM 002 Acceptance Status Evidence Target Risk Score Time Due Capability Gap Analysis. Operational Analysis. Needs & Numbers studies (with R&M input). Availability modelling. Operation Availability Targets within the Sustainability section of the User Requirements Document (URD). First cut R&M targets for insertion into the Systems Requirement Document (SRD). 0.1 Early in the concept phase, prior to Initial Gate Business Case. Assessment of the impact of R&M on Funding. R&M Input into BOI, COEIA and WLC modelling. Realistic estimates of funding and equipment numbers by ensuring Availability and Reliability are included in these early studies as cost drivers. 0.2 Early in the concept phase, prior to Initial Gate Business Case. Assessment of the technology risks. Feasibility studies examining the maturity of the technology likely to be used in the solution options. Reports showing pull through from research. Formulation of technology demonstrator programmes. Input from industry through partnering. 0.2 Evidence Reference: Issue No: Date Delivered: Approval Signature: Date: Unclassified Project Phase DEF STAN 00-42 Part 3 Issue 3 28 Evidence Framework for System ‘Y’ Issue: Date: Signature: Acceptance Criteria Project Phase Risk Ref. Risk Description and initial risk score Evidence Required R&M Practice Purchaser fails to understand the key timescale risks Assessment of the Time-scale risks. Purchaser fails to outline the strategy for R&M assurance R&M supporting evidence is developed in an adhoc manner Target Risk Score Comparison with similar, related or historical projects. Analyses to show the time-scales have been planned in accordance with the technology and technical risks. 0.2 Suitable R&M strategy An R&M strategy agreed by the R&M Concept Panel. A draft R&M strategy paper outlining the elements work and the strategy to mitigate the key risks. Statements of work for R&M assessment phase studies in Initial Gate Business case. Draft ITEAP to outline acceptance criteria. 0.2 RM 003 Failure of the Purchaser to communicate the R&M requirements to the Contractor Reliability predictions based on similar equipment failure rates, and any factors applied due to differences in BFMs, usage, complexity etc. Details of Operational Analysis and Operational Availability studies. Initial R&M Case Report issued to Contractor providing an audit trail of how the R&M requirement was derived. Discussions between Customer and Contractor Clear R&M requirements with the requisite audit trail set out at the start of the R&M Case. Initial R&M risk register. 0.1 Initial Score = 0.4 Time Due Evidence Reference: Issue No: Date Delivered: Approval Signature: Date: Unclassified Unclassified Evidence Unclassified Assessment Acceptance Status Early in the assessment phase, prior to Main Gate Business Case. 28 DEF STAN 00-42 Part 3 Issue 3 Risk Cause DEF STAN 00-42 Part 3 Issue 3 28 Evidence Framework for System ‘Y’ Issue: Date: Signature: Acceptance Criteria Project Phase Risk Ref. Risk Description and initial risk score Risk Cause Evidence Required R&M Practice RM 004 Failure of the Purchaser to select the optimum solution. Selection mechanism fails to rigorously address R&M Reliability estimates of concept options. Target Risk Score Time Due Assessment studies allowing R&M estimates to be input along with other attributes into a structured concept down selection system. Concept down selection reports showing evidence that the R&M has been factored into the selection process. 0.1 In the assessment phase, prior to Main Gate Business Case. An adequate ITT/bid R&M assessment method with sufficient weighting on R&M. Draft R&M assessment questions for ITT marking scheme, ensuring R&M is given equal weighting to performance, time & cost. Final scores from the bid assessment, plus key R&M risks and R&M achievement Milestones necessary to contract for the production of R&M evidence within the R&M case. 0.1 In the assessment phase, prior to Main Gate Business Case. Assessment of the technological risks associated with each option. Assessment of likely software complexity through measurements of the size and complexity of the software Concept down selection reports include assessment of software R&M through life Project R&M Design Guidelines and define how these guidelines are to be contracted against. Obtain Stakeholder acceptance for the Project R&M Design Guidelines Unclassified RM 005 Failure of the Contractor to understand the requirements. Initial Score = 0.6 Contractor fails to formally assess the impact of the environmental constraints on R&M Analysis of the operational environment, and mission and peacetime operation. Contractors R&M Case Report showing the environmental factors and duty cycle loads have been understood and will influence the design. 0.1 Provided with the Tender or early in the demonstration phase. Analysis of duty cycle, loads, temperature levels, vibration levels. Analysis of damage accumulation effects, dust, dirt ingress, moisture etc. Evidence Reference: Issue No: Date Delivered: Approval Signature: Date: Unclassified Evidence Initial Score = 0.5 Demonstration Acceptance Status DEF STAN 00-42 Part 3 Issue 3 28 28 Evidence Framework for System ‘Y’ Issue: Date: Signature: Acceptance Criteria Project Phase Risk Ref. Risk Description and initial risk score Risk Cause Evidence Required R&M Practice Demonstration (cont) RM 006 Failure of the Contractor to recognise all of the R&M risks. Contractor fails to involve R&M staff within formal Risk Identification Identification of all R&M risks. Analysis of the strength of design of critical components against duty cycle loads. Predictions and modelling to identify critical systems. Analysis of interface and integration issues. Initial Score = 0.5 Acceptance Status Evidence Target Risk Score Time Due Comprehensive risk matrix supported by R&M Case reports showing:- <0.15 Early in the design process to influence the design of prototype equipments. Approval Signature: Date: Unclassified Unclassified Unclassified 28 DEF STAN 00-42 Part3 Issue 3 Modelling using the measured inputs (loads), to ensure that the strength of design of mission critical sub-systems and components is adequate to meet the needs of the mission, and have the durability to continue to function for the design life of the equipment. A structured analysis of potential failure modes to ensure that all interface and integration issues are addressed and are not overlooked as causes of unreliability. Reliability modelling, predictions and allocations to determine criticality. Evidence Reference: Issue No: Date Delivered: DEF STAN 00-42 Part 3 Issue 3 28 Evidence Framework for System ‘Y’ Issue: Date: Signature: Acceptance Criteria Project Phase Risk Description and initial risk score Risk Cause Evidence Required R&M Practice RM 007 COTS components fail to perform as expected Unsuitable COTS components used within the design R&M Predictions supported by inservice data for COTS sub systems. Design fails to make use of automated usage and fault reporting HUMS to be implemented effectively and efficiently as part of the design process Initial Score = 0.5 Unclassified RM 008 Platform condition and usage unknown Initial Score = 0.4 Acceptance Status Evidence Target Risk Score Time Due Assessment studies where R&M estimates for COTS sub systems consider existing data and the impact of differences between the new application and that of applicable to the source data. Concept down selection reports include realistic predictions for COTS Sub Systems R&M Performance. 0.15 Provided with the Tender or early in the demonstration phase. HUMS to be an integral part of the design process. Maintainability Analysis Report identifying functions covered by HUMS 0.1 Provided with the Tender or early in the demonstration phase. Evidence Reference: Issue No: Date Delivered: Approval Signature: Date: Unclassified Risk Ref. DEF STAN 00-42 Part 3 Issue 3 28 28 Evidence Framework for System ‘Y’ Issue: Date: Signature: Acceptance Criteria Project Phase Risk Ref. Risk Description and initial risk score Risk Cause Evidence Required R&M Practice Demonstration (cont) RM 009 Failure of the Contractor to produce an adequate plan to mitigate the R&M risks Contractor expects that R&M issues will be addressed by the Purchaser in service Production of a suitable R&M Programme Plan Identification of the R&M risks and the planned R&M activities to mitigate those risks, along with the technical capability, resources and controls / success criteria to ensure it will happen. Initial Score = 0.7 Acceptance Status Time Due Clear R&M Management and organisational Structure. Systematic programme of activities for satisfying the R&M requirements set against the identified R&M risks. R&M activities with clear objectives and success criteria. Planned R&M activities in time to influence design. R&M Target Allocations to subcontractors. Subcontractors R&M Plans and Case. A clear test and evaluation programme. Planned R&M Milestones for R&M achievement with periodic reviews. 0.1 During proposals for ITT and during early development / demonstration phases. Evidence Reference: Issue No: Date Delivered: Approval Signature: Date: 28 DEF STAN 00-42 Part 3 Issue 3 Target Risk Score Unclassified Unclassified Unclassified Evidence DEF STAN 00-42 Part 3 Issue 3 28 Evidence Framework for System ‘Y’ Issue: Date: Signature: Acceptance Criteria Risk Ref. Risk Description and initial risk score Risk Cause Evidence Required R&M Practice Demonstration (cont) RM 010 Failure of the Contractor to produce sufficient evidence to demonstrate R&M requirements have been met to the satisfaction of the Purchaser. Test and evaluation criteria not formally agreed between the Contractor and the Purchaser Sufficient design and test & evaluation data to provide and engineering and statistical confidence that the preproduction prototype design has met the R&M requirements. Contractor fails to develop COTS interfaces that are compatible with the system software architecture Integration testing within the Software Integration Laboratory (SIL) includes Test Analyse Fix process reported by formal DRACAS. Evidence Target Risk Score Time Due Execute, monitor and review R&M Plan activities, amending where appropriate. Contractors R&M Case Reports showing:- 0.1 During demonstration prior to system acceptance and manufacture. DRACAS report from the SIL testing and development activities DRACAS report shows evidence of:- 0.15 During demonstration prior to system acceptance and manufacture. Initial Score = 0.6 RM 011 Reliability of COTS software packages is poor when integrated into the system. Initial Score = 0.7 Acceptance Status Design Changes resulting from the outputs of design studies (stress analysis, FMECAs, etc). Detailed and Effective DRACAS. Component test Results. Sub-system test Results. Test rig results. Reliability Growth Test results. Reliability Demonstration Trials. User Trial results. Performance trial results. Information on design review action. Field data from other users. Design modifications leading to Satisfactory reliability growth Input to R&M prediction reports to cover likely Software failure rates and PM cycles Evidence Reference: Issue No: Date Delivered: Approval Signature: Date: Unclassified Unclassified Project Phase DEF STAN 00-42 Part 3 Issue 3 2828 28 Evidence Framework for System ‘Y’ Issue: Date: Signature: Acceptance Criteria Risk Ref. Risk Description and initial risk score Risk Cause Evidence Required R&M Practice Manufacture RM 012 Failure of the Contractor to identify and manage the R&M risks associated with the transition from development to production. Contractor underestimates the scale of change between prototype and production system. Evidence that lessons learned from preproduction prototype builds have influenced the production process. Sufficient test and evaluation data to provide and engineering and statistical confidence that the production build standard will meet the R&M requirements and show the reliability has not been degraded by the production process. Immature production facility and processes Demonstration of consistent quality of manufacture. (PRAT Test Plan). Evidence of the implementation of effective quality procedures. RM 013 Failures of the Contractor to monitor the production run. Initial Score = 0.4 Evidence Target Risk Score Time Due Mature production and quality processes along side Pre-production prototype design. Procedures for the investigation and rectification of faults, failures and defects. Contractors R&M Case Reports showing:Production confirmatory/qualificatio n trials results. Production Reliability Acceptance Testing (PRAT) first batch results Evidence of changes in production and quality procedures to capture defects. 0.1 Preceding and during first off production phase. Production Reliability Acceptance Test. Final Quality Inspection of Deliverables PRAT Batch Test Results. Quality Inspection Records. <0.1 At agreed points during manufacturing period. Evidence Reference: Issue No: Date Delivered: Approval Signature: Date: Unclassified Unclassified Unclassified Initial Score = 0.5 Acceptance Status 28 DEF STAN 00-42 Part 3 Issue 3 Project Phase DEF STAN 00-42 Part 3 Issue 3 28 Evidence Framework for System ‘Y’ Issue: Date: Signature: Acceptance Criteria Project Phase Risk Description and initial risk score Risk Cause Evidence Required R&M Practice RM 014 COTS components fail to perform as expected Assembly information for COTS equipment is unsuitable for application Demonstration of consistent quality of assembly/integration of COTS components through PRAT Test Plan. Evidence of the implementation of effective quality procedures for assembly and integration Contract does not fully address system support Equipment usage and failure data along with the appropriate analysis to provide reliability estimates and failure trends. Data on repair costs and resources. Initial Score = 0.5 Unclassified In-Service RM 015 Failure of the Purchaser to monitor and mitigate R&M risks that result from change in use, environment and support. Initial Score = 0.5 Acceptance Status Evidence Target Risk Score Time Due Production Reliability Acceptance Test. Final Quality Inspection of Deliverables PRAT Batch Test Results. Quality Inspection Records. 0.1 At agreed points during manufacturing period. Identification of systematic failure modes and the introduction of modifications through PDS. In-service Reliability Demonstration Trial Results. In-Service Reliability Study results. In-service data collection and analysis. At the start and through out inservice period. Evidence Reference: Issue No: Date Delivered: Approval Signature: Date: Unclassified Risk Ref. DEF STAN 00-42 Part 3 Issue 3 40 28 Evidence Framework for System ‘Y’ Issue: Date: Signature: Acceptance Criteria Risk Ref. Risk Description and initial risk score Risk Cause Evidence Required R&M Practice Disposal RM 016 Failure of the Purchaser to capture record and disseminate the R&M lessons learnt System ownership and reporting responsibilities are not defined by the Purchaser. Full dossier of all elements of R&M work from concept through to in-service or disposal. Collation of all requirements documents, R&M data and reports into a corporate data repository. Production of a final LFE report providing insight into effectiveness of the programme and the final R&M estimates achieved. Initial Score = 0.9 Acceptance Status Unclassified Evidence Target Risk Score Time Due Early studies results. Mature URD and SRD. Extracts from TLMP. Outputs from R&M Panels (R&M Strategy etc,). ITEAP and Acceptance reports Fully populated R&M Case with all R&M evidence reports (including in-service). Analysis of lessons learned. 0.2 Ongoing through to inservice and disposal. Evidence Reference: Issue No: Date Delivered: Approval Signature: Date: Unclassified Unclassified Project Phase DEF STAN 00-42 Part 3 Issue 3 28 Evidence Framework for System ‘Y’ DEF STAN 00-42 Part 3 Issue 3 28 ©Crown Copyright 2008 Copying Only as Agreed with DStan Defence Standards are Published by and Obtainable from: Defence Procurement Agency An Executive Agency of The Ministry of Defence UK Defence Standardization Kentigern House 65 Brown Street GLASGOW G2 8EX DStan Helpdesk Tel 0141 224 2531/2 Fax 0141 224 2503 Internet e-mail enquiries@dstan.mod.uk File Reference The DStan file reference relating to work on this standard is . 21/42/3 Contract Requirements When Defence Standards are incorporated into contracts users are responsible for their correct application and for complying with contractual and statutory requirements. Compliance with a Defence Standard does not in itself confer immunity from legal obligations. Revision of Defence Standards Defence Standards are revised as necessary by an up issue or amendment. It is important that users of Defence Standards should ascertain that they are in possession of the latest issue or amendment. Information on all Defence Standards can be found on the DStan Website www.dstan.mod.uk, updated weekly and supplemented regularly by Standards in Defence News (SID News). Any person who, when making use of a Defence Standard encounters an inaccuracy or ambiguity is requested to notify UK Defence Standardization (DStan) without delay in order that the matter may be investigated and appropriate action taken. Unclassified