VICTOR VALLEY COMMUNITY COLLEGE DISTRICT MEASURE JJ BOND PROGRAM Citizens’ Bond Oversight Committee (Information Only – No Action Required) PROGRAM STATUS REPORT I. SEPTEMBER 14, 2011 PROGRAM UPDATE The following summarizes major activities completed since the June 15, 2011 report. II. PROGRAM BUDGET SUMMARY (Attachment A) The attached Bond Program Budget Summary has been revised to reflect current priorities and plans and includes reconciled bond revenues, expenditures and balances through June 30, 2011. The project list has been updated to incorporate the Board approved projects that will be funded by the remaining Series 1 revenues. The total committed program budget is $138,126,162 (line 73), which exceeds revenue by $1,354,135. However, the budget includes a 2.5% program contingency of $1,848,051 (line 15). The program budget balance (line 75) of $493,916 is the remaining contingency. III. PROJECT SUMMARY Eastside Public Safety Training Center: Project Awarded: August 11, 2009 Design-Build Team: Highland Partnership/Carrier-Johnson Architects Contract Amount: $ 25,000,000 Revised Project Budget: $ 31,536,982 Project Completion: Construction Completion – December 2011