www.meckpermit.com Pre-Construction Meeting Checklist Project Name: ___________________________ Permit #:______________________ General Notes: 1. The pre-construction meeting (scheduled at least 5 business days before start of construction), is scheduled by a Special Inspection Firm (SIF) or GC by telephone call directly to the assigned building inspector for that area. The Registered Design Professional in Responsible Charge (RDPIRC), the Structural Engineer or Record, all Designated Special Inspectors (DSI), the General Contractor (GC), and the Building Inspector for that area shall attend this meeting, typically conducted at the jobsite. Smaller limited projects like retaining walls or racking only permits may be performed by conference call at the inspector’s discretion. In the event a RDPIRC or DSI changes during the course of construction a new Pre-construction meeting is required. 2. The DSI shall upload the Statement of Special Inspection (SSI) to meck-si.com, statement of Special Inspections must be uploaded before a meeting date will be given by the inspector. The Contractor or DSI shall then contact the Building Inspector to establish the Pre-Construction meeting date and time. The Pre-Construction meeting is conducted by the DSI with meeting notes to be taken by the DSI and uploaded to meck-si.com within 5 business days of the meeting. Meeting minutes shall include: a written summary of the items discussed, sign in sheet listing all parties contact information, agreement statement on frequency of report uploading to meck-si.com for specific project timeline. 3. The Pre-Construction Meeting is for the entire project not phased work. If additional permits are required for this project then multiple Pre-Construction meetings may be omitted and the meeting conducted at one time for all site permits. If subsequent Preconstruction meetings are omitted, the first pre-construction meeting minutes along with the Statement of Special inspection for each subsequent phase of work are to be uploaded to meck-si.com by permit number, noting the date of the original Pre-Construction meeting and the name of the Building Inspector who conducted the meeting covering multiple permits. The following items are to be covered at the Pre-Construction meeting: Where to find the requirement for Special Inspections; including but not limited to mecksi.com, and the NCSBC Chapter 17. How to log on to meck-si.com. The parties involved and their responsibilities to complete the SI Process. Registered Design Professional in responsible charge (RDPIRC) Owner General Contractor (GC) Special inspection Firm (SIF) Authorized Special inspector (ASI) Designated Special Inspector (DSI) PEOPLE PRIDE PROGRESS PARTNERSHIPS 700 North Tryon Street Charlotte, North Carolina 28202 (704) 336-3545 Fax (704) 336-3839 www.meckpermit.com www.meckpermit.com What documents are required to be complete, and who will complete them. Conforming Log – ASI/DSI Non-conforming log - ASI/DSI Final Report – DSI RDPIRC sign off letter- RDPIRC Test results – ASI/DSI Other SI Documents –Any party The Statement of Special Inspections completed, reviewed and uploaded to meck-si.com. Modifications to the Statement of Special Inspections need to be approved by the plan reviewer for the project. The approval process for DSI and ASI as provided on meck-si.com. Verify the Special Inspection Firm (SIF) has no conflict of interest with the Contractor (The GC or permit holder cannot hire the SIF). Include in the minutes that employs the SIF. The owner hires the SIF (note: exceptions for owner/builder projects in those cases the owner who has the permit is allowed to hire the SIF). The Pre-Construction Minutes must be uploaded within five business days of the meeting date. All other Special Inspections (SI) documents must be uploaded within ten business days of the reported event to meck-si.com unless agreed to during the PC meeting. The SI will upload any deficiencies noted during construction within 10 days and document resolution to those items, site log must list deficiencies if the ASI or SI leaves the job, if deficiencies is corrected per specifications while on site no deficiency log entry required. No Final Inspections can be requested until all Final Reports have been completed and uploaded, the RDPIRC letter has been completed, and the Department has determined that it is acceptable. GC should request a SI closeout inspection when ready and prior to the needing any final Inspections. All SI documentation must be made available to the Building Inspector upon request. If Structural members are being fabricated off site, the DSI shall verify that the fabricator conforms to the requirements set forth in NCSBC Section 1704.2.2. At the conclusion of the Fabricator’s work, the Fabricator shall submit a Fabricator’s Certificate of Compliance to the DSI. PEOPLE PRIDE PROGRESS PARTNERSHIPS 700 North Tryon Street Charlotte, North Carolina 28202 (704) 336-3545 Fax (704) 336-3839 www.meckpermit.com www.meckpermit.com Each contractor responsible for construction of a main wind or seismic-forceresisting system, designated seismic system or wind-or seismic-resisting component listed in the statement of special inspections shall submit a written statement to the building official (upload to Meck-Si by the ASI/DSI) and the owner prior to the commencement of work. Statement shall contain acknowledgement of awareness of the special requirements contained in the Statement of Special Inspections as required by Section 1709. A separate Non-Conforming Work Log on failed tests or inspections including mitigating actions and date items passed are required to be kept onsite until it is uploaded to meck-si.com (paper copy). Non-Conforming Work is also known as a Discrepancy. Non-Conforming work is work within the scope of the SI that was not done in conformance to the approved Contract Documents, the Referenced Standard, or the SSI. Non-Conforming Work procedure is as follows: any work deemed to be NonConforming shall be immediately brought to the attention of the GC. This information and all related documents shall be uploaded to meck-si.com and tagged as Non-Conforming. If these Discrepancies are not corrected by the completion of that phase of work, the Discrepancies shall be brought to the attention of the Building Inspector and the RDPIRC. The DSI is responsible for resolving or documenting the resolution of all Discrepancies. All covered items must pass Special Inspections before work proceeds. Any deviations from the approved plans and specifications must be approved by the RDPIRC and/or the designer of record responsible for that area of work. Should the Special Inspections fail to be performed per the SSI or County inspections fail to be performed, the Department may issue a Stop Work Order. Any work performed by a DSI or ASI who losses their certification, license, or otherwise is removed from the approved meck-si.com list, will not be permitted to upload any documents to meck-si.com. If it is determined that any documents have been uploaded to meck-si.com by a DSI, ASI, or RDPIRC with expired credentials; that work product may be subject to removal at the discretion of the Department. Only non-conforming work related to the scope of SI shall be included in any documents uploaded to meck-si.com. All other non-conforming work unrelated to the scope of SI, or part of the contractor quality control program, shall be maintained separately. For additional information or full Department requirements, refer to www.meck-si.com. Rev. 11/5/2013 PEOPLE PRIDE PROGRESS PARTNERSHIPS 700 North Tryon Street Charlotte, North Carolina 28202 (704) 336-3545 Fax (704) 336-3839 www.meckpermit.com