The Pennsylvania State University HUB-Robeson Addition and Renovation University Park, PA December 19, 2014 © Gilbane Building Co., Inc. Work In Progress • HOLIDAY BREAK SHUTDOWN WORK • • • • • • • • • • • • • • • • • • • • • Level 1 Meeting Room Floors, Q106 Terrazzo, Food Service Day 2 Work, Relo. Starbuck’s Cooler, etc. Level 2 Heating Piping Install Fire Dampers Chilled Water Piping to MB018 Air Handling Units Level 2 AHU 5 Piping MB018 Outside Air Chase Duct Electrical Rough-Ins for Flex Theater Pull Branch Circuits on Level 2 A/V Rough-Ins on Level 2 Hang Terracotta at Flex Theatre Wall Interior Install Metal Coping on Roof Parapet Install Drywall and Framing around B2 Lobby and Offices Install Drywall in Level 2 Bathrooms Hang Level 2 Meeting room Operable Partition Support Steel Pour Main Atrium Stair Risers and Pans Infill Cut in Sprinkler Heads on B2 Ceiling Tile in B2 Lobby Install Level 2 Storefront Framing and Glass Install Railing on Level 1 Pour Terrazzo on Level 1 Lay Plywood Subflooring in Flex Theatre © Gilbane Building Co., Inc. Project Site from the HUB Parking Deck © Gilbane Building Co., Inc. View from Loading Dock © Gilbane Building Co., Inc. View from South Entrance © Gilbane Building Co., Inc. View of Atrium Looking Northwest from Level 1 © Gilbane Building Co., Inc. Loading Dock Metal Panels © Gilbane Building Co., Inc. Guardrail around Level 1 © Gilbane Building Co., Inc. Level 1 Tile Removal for Terrazzo © Gilbane Building Co., Inc. Terracotta on Level 1 Wall above Meeting Room 131 © Gilbane Building Co., Inc. Subflooring in Flex Theater © Gilbane Building Co., Inc. Shotblasting for Tech Lounge Terrazzo © Gilbane Building Co., Inc. Flex Theater Interior Terra Cotta Wall Framing © Gilbane Building Co., Inc. Level B2 Lobby Ceiling and Terrazzo © Gilbane Building Co., Inc. Planned Work • • • • • • • • • • • • • • • • • • • • • • • • • • • • HOLIDAY BREAK WORK!!! Level 2 Heating Piping Install Fire Dampers CHW Piping in MB018 Level 2 AHU 5 Piping MB018 Outside Air Chase Duct Electrical Piping for Flex Theater Pull Branch Circuits on Level 2 Piping on AV racks on Level 2 Hang Terracotta at Flex Theatre Wall Interior Lay Plaza Deck Insulation Lay Green Roof Insulation Install Metal Coping on Roof Parapet Install Drywall and Framing around B2 Lobby and Offices Ceiling Tile in B2 Lobby Install Level 2 Storefront Framing and Glass Pour Terrazzo on Level 1 Prep Q106 for Terrazzo Demolish Temporary Partition on Level 1 and install Storefront Relocate Jamba Juice Condenser Move Starbucks walk in Cooler Rough-in Atrium Lights Bookstore Poke Through Piping Lighting in Credit Union Projector Screen Supports Drywall around the atrium Bulkheads Elevator Shaftwall in Atrium Rough in level 1 Sprinkler © Gilbane Building Co., Inc.