Work In Progress
• HOLIDAY BREAK SHUTDOWN WORK
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
Level 1 Meeting Room Floors, Q106 Terrazzo, Food Service Day 2 Work, Relo. Starbuck’s Cooler, etc.
Level 2 Heating Piping
Install Fire Dampers
Chilled Water Piping to MB018 Air Handling Units
Level 2 AHU 5 Piping
MB018 Outside Air Chase Duct
Electrical Rough-Ins for Flex Theater
Pull Branch Circuits on Level 2
A/V Rough-Ins on Level 2
Hang Terracotta at Flex Theatre Wall Interior
Install Metal Coping on Roof Parapet
Install Drywall and Framing around B2 Lobby and Offices
Install Drywall in Level 2 Bathrooms
Hang Level 2 Meeting room Operable Partition Support Steel
Pour Main Atrium Stair Risers and Pans Infill
Cut in Sprinkler Heads on B2
Ceiling Tile in B2 Lobby
Install Level 2 Storefront Framing and Glass
Install Railing on Level 1
Pour Terrazzo on Level 1
Lay Plywood Subflooring in Flex Theatre
© Gilbane Building Co., Inc.
Project Site from the HUB Parking Deck
© Gilbane Building Co., Inc.
View from Loading Dock
© Gilbane Building Co., Inc.
View from South Entrance
© Gilbane Building Co., Inc.
View of Atrium Looking Northwest from
Level 1
© Gilbane Building Co., Inc.
Loading Dock Metal Panels
© Gilbane Building Co., Inc.
Guardrail around Level 1
© Gilbane Building Co., Inc.
Level 1 Tile Removal for Terrazzo
© Gilbane Building Co., Inc.
Terracotta on Level 1 Wall above Meeting
Room 131
© Gilbane Building Co., Inc.
Subflooring in Flex Theater
© Gilbane Building Co., Inc.
Shotblasting for Tech Lounge Terrazzo
© Gilbane Building Co., Inc.
Flex Theater Interior Terra Cotta Wall
Framing
© Gilbane Building Co., Inc.
Level B2 Lobby Ceiling and Terrazzo
© Gilbane Building Co., Inc.
Planned Work
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
HOLIDAY BREAK WORK!!!
Level 2 Heating Piping
Install Fire Dampers
CHW Piping in MB018
Level 2 AHU 5 Piping
MB018 Outside Air Chase Duct
Electrical Piping for Flex Theater
Pull Branch Circuits on Level 2
Piping on AV racks on Level 2
Hang Terracotta at Flex Theatre Wall Interior
Lay Plaza Deck Insulation
Lay Green Roof Insulation
Install Metal Coping on Roof Parapet
Install Drywall and Framing around B2 Lobby and Offices
Ceiling Tile in B2 Lobby
Install Level 2 Storefront Framing and Glass
Pour Terrazzo on Level 1
Prep Q106 for Terrazzo
Demolish Temporary Partition on Level 1 and install Storefront
Relocate Jamba Juice Condenser
Move Starbucks walk in Cooler
Rough-in Atrium Lights
Bookstore Poke Through Piping
Lighting in Credit Union
Projector Screen Supports
Drywall around the atrium Bulkheads
Elevator Shaftwall in Atrium
Rough in level 1 Sprinkler