C20 SEQUENCE DEVELOPMENT Version 4 04/24/00

advertisement
C20 Sequence Development – Version 4 04/24/00
C20 SEQUENCE DEVELOPMENT
Version 4 04/24/00
03/10/00
03/27/00
04/12/00
04/24/00
Draft for review
Added ODC ID, DS #,
MAPS_HR set up
Final background
sequence information
Added Contingency
Files
1
C20 Sequence Development – Version 4 04/24/00
1 C20 PREDICTED TIME ORIENTED LISTING.......................................................3
2 ACTIVITY CONSTRAINTS.......................................................................................4
3 INSTRUMENT INITIAL STATE.................................................................................5
4 INSTRUMENT SETUP................................................................................................5
4.1 MAPS Low.............................................................................................................5
4.2 MAPS High.............................................................................................................6
4.3 Fomalhaut................................................................................................................7
4.3.1 Step 1..............................................................................................................7
4.3.2 Step 2..............................................................................................................8
4.3.3 Step 3..............................................................................................................9
4.3.4 Step 4............................................................................................................10
4.3.5 Step 5............................................................................................................11
4.3.6 Step 6............................................................................................................12
4.3.7 Step 7............................................................................................................13
4.3.8 Step 8 – HSP characterization.....................................................................14
4.4 HDAC Conditioning.............................................................................................15
5 INSTRUMENT STATE AT END OF SEQUENCE...............................................15
6 PLANNED REAL-TIME AND CONTINGENCY COMMANDS.......................16
6.1 Turn On..................................................................................................................16
6.2 Contingencies.......................................................................................................16
7 FLIGHT SOFTWARE VERSION AND PATCHES.............................................16
8 MAPPING OF ACTIVITIES TO DS AND BACKGROUND..............................17
8.1 Activity in the Background Sequence.................................................................17
8.2 Activity in Distributed Sequence.........................................................................17
9 EXPECTED SCIENCE DATA RETURN...............................................................17
10 DEVELOPMENT AND TEST PROCEDURES..................................................18
11 SEQUENCE VALIDATION...................................................................................18
12 SASF SUBMITTED TO JPL..................................................................................18
13 TEST NOTES...........................................................................................................18
2
C20 Sequence Development – Version 4 04/24/00
1 C20 PREDICTED TIME ORIENTED LISTING
START TIME
(SCET)
2000-153T08:51:10.000
2000-153T08:51:10.000
2000-153T16:41:10.000
2000-163T21:31:20.000
2000-164T22:21:19.000
2000-165T22:36:18.000
2000-166T02:35:53.000
2000-167T03:21:53.000
2000-167T11:01:17.000
2000-169T22:21:16.000
2000-171T22:21:16.000
2000-172T22:31:16.000
2000-173T13:36:16.000
2000-175T00:46:16.000
2000-175T15:46:16.000
2000-175T22:00:00.000
2000-175T22:00:00.000
2000-175T23:00:00.000
2000-176T00:30:00.000
2000-176T08:30:00.000
2000-176T08:30:00.000
2000-177T00:41:16.000
2000-177T18:06:16.000
2000-178T09:56:17.000
2000-183T20:36:21.000
2000-184T21:54:20.000
2000-185T17:26:23.000
2000-186T20:26:19.000
2000-190T12:46:29.000
ACTIVITY
UVIS_Turn_On
UVIS_Pim
UVIS_Maps
UVIS_Maps_HR
UVIS_Maps_HR
UVIS_Maps_HR
UVIS_Sleep
UVIS_Maps
UVIS_Maps_HR
UVIS_Maps_HR
UVIS_Maps_HR
UVIS_Maps_HR
UVIS_Maps_HR
UVIS_Maps_HR
UVIS_Maps_HR
UVIS_HSP_On
UVIS_Hdac_Cond
UVIS_Maps
UVIS_AlphaPsA_1
UVIS_Maps
UVIS_HSP_Off
UVIS_Maps_HR
UVIS_Maps_HR
UVIS_Maps_HR
UVIS_Maps_HR
UVIS_Maps_HR
UVIS_Maps_HR
UVIS_Maps_HR
UVIS_Maps_HR
3
DURATION
7:50:00
0:10:00
012T09:54:43
0:59:31
0:59:31
0:59:31
001T00:46:00
008T18:38:07
0:59:31
0:59:31
0:59:31
0:59:31
0:59:31
0:59:31
0:59:31
0:00:03
1:00:00
1:30:53
8:00:00
015T15:29:07
0:00:03
0:59:31
0:59:31
0:59:31
0:59:31
0:59:31
0:59:31
0:59:31
0:59:31
C20 Sequence Development – Version 4 04/24/00
UVIS activities during C20
UVIS activities around AlphaPsA observation
2 ACTIVITY CONSTRAINTS
The MAPS low rate is limited to 74 bps.
The MAPS high rate is limited to 500 bps.
The Fomalhaut activity is limited to 240 Mbit.
The Hdac conditioning activity is limited to 210 bps.
4
C20 Sequence Development – Version 4 04/24/00
3 INSTRUMENT INITIAL STATE
Latest ODC ID
IEB Buffer in Use
Instrument Configuration
32
N/A
Off
4 INSTRUMENT SETUP
4.1 MAPS Low
CHANNEL
HDAC
HSP
FUV
EUV
CHANNEL SETUP
Integrating: Yes
Hvps: On
Photometer mode: Yes
Compression: No
Integration: 8
Integrating: No
Hvps: N/A
Integration: N/A
Compression: N/A
Integrating: Yes
Hvps: Level_1
Pulse: Off
Slit: Low_Res
Integration: 32sec
Compression: Sqrt_9
Number Of window: 1
Window 1 Description
Coord: (0,0) (1023, 63)
Xbin: 8, Ybin: 64
Integrating: Yes
Hvps: Level_1
Pulse: Off
Slit: Occultation
Integration: 32sec
Compression: Sqrt_9
Number Of window: 1
Window 1 Description
Coord: (0,0) (1023, 63)
Xbin: 8 , Ybin: 64
RATE (pps, bps )
0.00023719, 2.06448
0.0, 0.0
0.00424528, 36.9509
0.00424528, 36.9509
Under this configuration the data rate is 75.966 bits/second.
5
C20 Sequence Development – Version 4 04/24/00
4.2 MAPS High
CHANNEL
HDAC
HSP
FUV
EUV
CHANNEL SETUP
Integrating: Yes
Hvps: On
Photometer mode: Yes
Compression: no
Integration: 8
Integrating: No
Hvps: N/A
Integration: N/A
Compression: N/A
Integrating: Yes
Hvps: Level_1
Pulse: Off
Slit: Low_Res
Integration: 1080 sec
Compression: Sqrt_9
Number Of window: 1
Window 1 Description
Coord: (0,0) (1023, 63)
Xbin: 2, Ybin: 2
Integrating: Yes
Hvps: Level_1
Pulse: Off
Slit: Low_Res
Integration: 1080 sec
Compression: Sqrt_9
Number Of window:1
Window 1 Description
Coord: (0,0) (1023, 63)
Xbin:1, Ybin: 2
Under this configuration the data rate is 420.626 bits/sec.
6
RATE (pps, bps)
0.00023719, 2.06448
0.0, 0.0
0.0161, 140.14
0.0322, 280.28
C20 Sequence Development – Version 4 04/24/00
4.3 Fomalhaut
One Fomalhaut activity consists in 7 steps described below. The total duration is 60
minutes. The observation will be repeated 3 times during the 8 hours of
observation. For the remaining of the time we will conduct some HSP tests, staying
within the SSR allocation. The HSP testing has 5 steps: 600 seconds at 1ms
integration time, 600 seconds at 2 ms, 600 seconds at 4 ms, 600 seconds at 8 ms
and TBD seconds at 2 ms.
4.3.1 Step 1
The step duration is 10 minutes.
CHANNEL
HDAC
HSP
FUV
EUV
CHANNEL SETUP
Integrating: Yes
Hvps: On
Photometer mode: Yes
Compression: No
Integration: 0.125sec
Integrating: Yes
Hvps: On
Integration: 2msec
Compression: Sqrt_9
Integrating: Yes
Hvps: Level_1
Pulse: Off
Slit: Occultation
Integration: 1sec
Compression: Sqrt_9
Number Of window: 1
Window 1 Description
Coord: (0,0), (1023, 63)
Xbin: 1024,Ybin: 1
Integrating: Yes
Hvps: Level_1
Pulse: Off
Slit: Occultation
Integration: 1sec
Compression: Sqrt_9
Number Of window: 1
Window 1 Description
Coord: (0,0) (1023,63)
Xbin: 1024, Ybin: 1
RATE (pps, bps)
0.01518, 132.126
0.52875, 4602.24
0.067924, 591.215
0.067924, 591.215
Under this configuration the data rate is 5916.79 bits/second. The data volume is
3.55 Mbit per iteration.
7
C20 Sequence Development – Version 4 04/24/00
4.3.2 Step 2
The step duration is 20 minutes,
CHANNEL
HDAC
HSP
FUV
EUV
CHANNEL SETUP
Integrating: Yes
Hvps: On
Photometer mode: Yes
Compression: No
Integration: 0.125sec
Integrating: Yes
Hvps: On
Integration: 2msec
Compression: Sqrt_9
Integrating: Yes
Hvps: Level_1
Pulse: Off
Slit: Occultation
Integration: 60sec
Compression: Sqrt_9
Number Of window: 1
Window 1 Description
Coord: (0,0), (1023, 63)
Xbin: 1,Ybin: 1
Integrating: Yes
Hvps: Level_1
Pulse: Off
Slit: Occultation
Integration: 60sec
Compression: Sqrt_9
Number Of window: 1
Window 1 Description
Coord: (0,0) (1023,63)
Xbin: 1, Ybin: 1
RATE (pps, bps)
0.01518, 132.126
0.52875, 4602.24
1.15924, 10090.071
1.15924, 10090.071
Under this configuration the data rate is 24914.5 bits/second. The data volume is
29.90 Mbit per iteration.
8
C20 Sequence Development – Version 4 04/24/00
4.3.3 Step 3
The duration of this step is 10 minutes.
CHANNEL
HDAC
HSP
FUV
EUV
CHANNEL SETUP
Integrating: Yes
Hvps: On
Photometer mode: Yes
Compression: no
Integration: 0.125sec
Integrating: Yes
Hvps: On
Integration: 2msec
Compression: Sqrt_9
Integrating: Yes
Hvps: Level_1
Pulse: Off
Slit: Occultation
Integration: 1sec
Compression: Sqrt_9
Number Of window: 1
Window 1 Description
Coord: (0,0), (1023, 63)
Xbin: 1,Ybin: 64
Integrating: Yes
Hvps: Level_1
Pulse: Off
Slit: Occultation
Integration: 1sec
Compression: Sqrt_9
Number Of window: 1
Window 1 Description
Coord: (0,0) (1023,63)
Xbin: 1, Ybin: 64
RATE (pps, bps)
0.01518, 132.126
0.52875, 4602.24
1.08679, 9459.44
1.08679, 9459.44
Under this configuration the data rate is 23653.25 bits/second. The data volume is
14.20 Mbit per iteration.
9
C20 Sequence Development – Version 4 04/24/00
4.3.4 Step 4
The step duration is 5 minutes.
CHANNEL
HDAC
HSP
FUV
EUV
CHANNEL SETUP
Integrating: Yes
Hvps: On
Photometer mode: Yes
Compression: No
Integration: 0.125sec
Integrating: Yes
Hvps: On
Integration: 2msec
Compression: Sqrt_9
Integrating: Yes
Hvps: Level_1
Pulse: Off
Slit: Low_Res
Integration: 1sec
Compression: Sqrt_9
Number Of window: 1
Window 1 Description
Coord: (0,0), (1023,
63)
Xbin: 1024,Ybin: 1
Integrating: Yes
Hvps: Level_1
Pulse: Off
Slit: Low_Res
Integration: 1sec
Compression: Sqrt_9
Number Of window: 1
Window 1 Description
Coord: (0,0) (1023,63)
Xbin: 1024, Ybin: 1
RATE (pps, bps)
0.01518, 132.126
0.52875, 4602.24
0.067924, 591.215
0.067924, 591.215
Under this configuration the data rate is 5916.79 bits/second. The data volume is
1.775 Mbit per iteration.
10
C20 Sequence Development – Version 4 04/24/00
4.3.5 Step 5
The duration of this step is 5 minutes.
CHANNEL
HDAC
HSP
FUV
EUV
CHANNEL SETUP
Integrating: Yes
Hvps: On
Photometer mode: Yes
Compression: No
Integration: 0.125sec
Integrating: Yes
Hvps: On
Integration: 2msec
Compression: Sqrt_9
Integrating: Yes
Hvps: Level_1
Pulse: Off
Slit: Low_Res
Integration: 1sec
Compression: Sqrt_9
Number Of window: 1
Window 1 Description
Coord: (0,0), (1023,
63)
Xbin: 1,Ybin: 64
Integrating: Yes
Hvps: Level_1
Pulse: Off
Slit: Low_Res
Integration: 1sec
Compression: Sqrt_9
Number Of window: 1
Window 1 Description
Coord: (0,0) (1023,63)
Xbin: 1, Ybin: 64
RATE (pps, bps)
0.01518, 132.126
0.52875, 4602.24
1.08679, 9459.44
1.08679, 9459.44
Under this configuration the data rate is 23653.25 bits/second. The data volume is
7.096 Mbit per iteration.
11
C20 Sequence Development – Version 4 04/24/00
4.3.6 Step 6
The duration of this step is 5 minutes.
CHANNEL
HDAC
HSP
FUV
EUV
CHANNEL SETUP
Integrating: Yes
Hvps: On
Photometer mode: Yes
Compression: no
Integration: 0.125sec
Integrating: Yes
Hvps: On
Integration: 2msec
Compression: Sqrt_9
Integrating: Yes
Hvps: Level_1
Pulse: Off
Slit: High_Res
Integration: 1sec
Compression: Sqrt_9
Number Of window: 1
Window 1 Description
Coord: (0,0), (1023, 63)
Xbin: 1024,Ybin: 1
Integrating: Yes
Hvps: Level_1
Pulse: Off
Slit: High_Res
Integration: 1sec
Compression: Sqrt_9
Number Of window: 1
Window 1 Description
Coord: (0,0) (1023,63)
Xbin: 1024, Ybin: 1
RATE (pps, bps)
0.01518, 132.126
0.52875, 4602.24
0.067924, 591.215
0.067924, 591.215
Under this configuration the data rate is 5916.79 bits/second. The data volume is
1.775 Mbit per iteration.
12
C20 Sequence Development – Version 4 04/24/00
4.3.7 Step 7
The duration of this step is 5 minutes.
CHANNEL
HDAC
HSP
FUV
EUV
CHANNEL SETUP
Integrating: Yes
Hvps: On
Photometer mode: Yes
Compression: no
Integration: 0.125sec
Integrating: Yes
Hvps: On
Integration: 2msec
Compression: Sqrt_9
Integrating: Yes
Hvps: Level_1
Pulse: Off
Slit: High_Res
Integration: 1sec
Compression: Sqrt_9
Number Of window: 1
Window 1 Description
Coord: (0,0), (1023,
63)
Xbin: 1,Ybin: 64
Integrating: Yes
Hvps: Level_1
Pulse: Off
Slit: High_Res
Integration: 1sec
Compression: Sqrt_9
Number Of window: 1
Window 1 Description
Coord: (0,0) (1023,63)
Xbin: 1, Ybin: 64
RATE (pps, bps)
0.01518, 132.126
0.52875, 4602.24
1.08679, 9459.44
1.08679, 9459.44
Under this configuration the data rate is 23653.25 bits/second. The data volume is
7.096 Mbit per iteration.
Total data volume for three iterations of the Fomalhaut activity is 197 Mbit.
13
C20 Sequence Development – Version 4 04/24/00
4.3.8 Step 8 – HSP characterization
CHANNEL
HDAC
HSP
FUV
EUV
CHANNEL SETUP
Integrating: No
Integrating: Yes
Hvps: On
RATE (pps, bps)
Step 1 – 600 seconds
Integration: 1msec
Compression: No
1.88, 16363.52
Step 2 – 600 seconds
Integration: 2msec
Compression: Sqrt_9
0.52875, 4602.24
Step 3 – 600 seconds
Integration: 4msec
Compression: Sqrt_9
0.2643, 2301.12
Step 4 – 600 seconds
Integration: 8msec
Compression: Sqrt_9
0.1322, 1150.50
Step 5 – 6000 seconds
Integration: 2msec
Compression: Sqrt_9
Integrating: No
Integrating: No
0.52975, 4602.24
The total volume for this activity is 43 Mbits.
14
C20 Sequence Development – Version 4 04/24/00
4.4 HDAC Conditioning
The HADC conditioning activity consists in executing 8 different modulation tables.
The duration of each individual activity is 144 seconds. The activity is repeated 3
time for a total duration of 3456 seconds.
CHANNEL
HDAC
HSP
FUV
EUV
CHANNEL SETUP
Integrating: Yes
Hvps: On
Dwell Time: 9 Seconds
Selected Filament: 1
Compression: No
Table 1
D cell:0,0,0,0,0,0,0,0,0,0,0,0,0,0,0,0
H cell:0,1,0,2,0,3,0,4,0,5,0,6,0,7,0,0
Table 2
D cell:0,1,0,1,0,1,0,1,0,1,0,1,0,1,0,0
H cell:0,1,0,2,0,3,0,4,0,5,0,6,0,7,0,0
Table 3
D cell:0,2,0,2,0,2,0,2,0,2,0,2,0,2,0,0
H cell:0,1,0,2,0,3,0,4,0,5,0,6,0,7,0,0
Table 4
D cell:0,3,0,3,0,3,0,3,0,3,0,3,0,3,0,0
H cell:0,1,0,2,0,3,0,4,0,5,0,6,0,7,0,0
Table 5
D cell:0,4,0,4,0,4,0,4,0,4,0,4,0,4,0,0
H cell:0,1,0,2,0,3,0,4,0,5,0,6,0,7,0,0
Table 6
D cell:0,5,0,5,0,5,0,5,0,5,0,5,0,5,0,0
H cell:0,1,0,2,0,3,0,4,0,5,0,6,0,7,0,0
Table 7
D cell:0,6,0,6,0,6,0,6,0,6,0,6,0,6,0,0
H cell:0,1,0,2,0,3,0,4,0,5,0,6,0,7,0,0
Table 8
D cell:0,7,0,7,0,7,0,7,0,7,0,7,0,7,0,0
H cell:0,1,0,2,0,3,0,4,0,5,0,6,0,7,0,0
Integrating: No
Hvps: N/A
Integrating: No
Hvps: N/A
Integrating: No
Hvps: N/A
RATE (pps, bps)
0.01518, 132.126
0.0, 0.0
0.0, 0.0
0.0, 0.0
Under this configuration the data rate is 132.126 bits/second.
5 INSTRUMENT STATE AT END OF SEQUENCE
Latest ODC ID
IEB Buffer in Use
Instrument Configuration
46
1
MAPS Low rate
15
C20 Sequence Development – Version 4 04/24/00
6 PLANNED REAL-TIME AND CONTINGENCY COMMANDS
6.1 Turn On
The turn on will be accomplished from the background sequence. The IEBs will be
loaded from the background sequence.
6.2 Contingencies
The only contingency identified is a failure to upload the new flight code into the SSR
on DOY 152. The diagram below explains how this contingency is handled.
The contingency IEB does the following: (1) the MAPS is without HDAC; and (2)
the HDAC conditioning starts with one hour of HDAC in photometer mode,
continues with one hour of modulation and then goes back to photometer mode until
the start of the AlphaPSa activity. HSP is still turned on at the start of the HDAC
conditioning activity.
C20- UVIS TURN ON - DOY 153
~153T08:51:10
BACKGROUND
SEQUENCE
~153T16:41:00
~153T12:30:00
- Power on
- PIM
- Load V1.2 from SSR
- Execute RAM code
- Load IEBs
Contingency Window #1
- Trigger MAPS IEB
Contingency Window #2
Contingency:
- V1.2 uplink failed on DOY152
Contingency:
- V1.1 is used rather than V1.2
R/T activities:
- Load V1.1 from SSR and update
R/T activities:
- Load V1.1-compatible IEBs
7 FLIGHT SOFTWARE VERSION AND PATCHES
Flight software version 1.2 will be used.
16
C20 Sequence Development – Version 4 04/24/00
8 MAPPING OF ACTIVITIES TO DS AND BACKGROUND
8.1 Activity in the Background Sequence
ACTIVITY
TURN ON
PIM
SLEEP
OFF SLEEP
NOTES
SEE PARAGRAPH 6.2
SEE PARAGRAPH 6.2
8.2 Activity in Distributed Sequence
ACTIVITY
MAPS
MAPS HR
HSP ON
HDAC COND
DS
0
1
2
2
ODC ID
33
34
N/A
17 TO 24
STARTED VIA
BACKGROUND OR DS
BACKGROUND
BACKGROUND
N/A
ALP[HA PSA
FUV/EUV
APLHA PSA
HSP
HSP OFF
3
35 TO 41
BACKGROUND
ENDED VIA
BACKGROUND
BACKGROUND
N/A
TIMER – CALLS
DS 0
TIMER
4
42 TO 46
BACKGROUND
TIMER
5
N/A
BACKGROUND
N/A – CALLS
DS 0
HDAC PHO.
2
47
BACKGROUND –
CONTIN.GENCY ONLY
9 EXPECTED SCIENCE DATA RETURN
ACTIVITY
ODC_ID
HDAC
HSP
17
FUV
EUV
C20 Sequence Development – Version 4 04/24/00
10 DEVELOPMENT AND TEST PROCEDURES
The following CSTOL procedures were used in the development and testing of the
C20 sequence and IEB.
SCIENCE ACTIVITIES
IEB CREATION
SEQUENCE/IEB TEST
SCIENCE ACTIVITIES –
CONTINGENCY
IEB CREATION - CONTIGNECY
SEQUENCE/IEB TEST CONTINGENCY
c20_alpha_psa_1.prc
c20_alp[ha_psa_2.prc
c20_maps.prc
c20_maps_hr.prc
c20_hdac_cond.prc
c20_hsp_off.prc
c20.prc
c20_test.prc
c20_maps_c.prc
c20_maps_hr_c.prcc
c20_hdac_cond_c.prc
c20_c.prc
Manual test
11 SEQUENCE VALIDATION
Done 03/30/00 and 04/02/00. The names of the files recorded during the sequence
validation are:
Message log file:
f00_nov_09_21_00_24.event_messages
f00_nov_12_02_17_21.event_messages
f00_nov_27_00_54_50.event_messages (contingency)
f00_nov_27_19_25_28.event_messages (contingency)
Telemetry file:
f00_nov_09_21_23_02.tlm
f00_nov_12_02_17_21.tlm
f00_nov_27_00_54_50.tlm (contingency)
f00_nov_27_19_26_16.tlm (contingency)
Note: the system clock was incorrectly set to 11/00 during the testing. Hence the
strange filenames.
12 SASF SUBMITTED TO JPL
The file uvis_b0200b_in.sasf (background sequence) submitted to the OPS DOM,
on 04/06/00 at 18:01 UTC.
The contingency files i1656a_uvisv11load.sasf and i1657a_uvis_v11ieb.sasf
submitted to the OPS DOM ON 04/24/00 at 20:40 UTC
13 TEST NOTES
18
C20 Sequence Development – Version 4 04/24/00
(1) To improve the CM of the IEB file, the original file header should be printed in
the summary files.
(2) Testing the sequence shows that the FUV/EUV set up takes between 10.10
seconds 19.9 seconds (full image).
(3) Need to add an “out of memory” check to the seq2ds utility.
(4) During the first contingency sequence test, when triggering 0 after execution of 2,
noted the creation of 3 FUV and 3 EUV packets. Could not repeat the next day.
19