MEMORANDUM TO: FR: RE: DA: Richard A. Davey, Secretary & CEO Frank DePaola, Highway Division Administrator Ongoing Work in the MHS Tunnels August 15, 2014 To follow is a summary of maintenance and construction activities performed last week in the Metropolitan Highway System Tunnels. Overnight work: • • • • • • • • • • MassDOT closed the I-93 Southbound Tunnel overnight as part of its regular series of overnight tunnel closures. The closures allow MassDOT to clean, maintain and repair areas of the tunnel not normally accessible when traffic is flowing. Contractors are repairing water infiltration at multiple points within the O’Neill Tunnel (both directions) and on related ramps. Recent work included slurry wall repairs and repair and replacement of fireproofing materials. Water infiltration repair work is also underway in the I-90 Connector Tunnel (both directions) and the Ted Williams Tunnel Eastbound. A contractor working on behalf of the Massachusetts Convention Center Authority is performing ongoing ceiling-related construction in the Prudential Tunnel. The contractor is also installing new fireproofing materials. The contractor continues to repair the walls and remove supplemental steel and concrete, which requires periodic lane closures. The contractor has also begun installing a netting system to catch any debris that could come loose over time as the result of vibrations in the tunnel. The nets are designed to prevent debris from falling to the roadway. A contractor working on behalf of the owner of the Prudential Center continued work on the ceiling of the Prudential Tunnel Westbound. This is a different section of the ceiling than what has been noted above. MassDOT continued the Callahan Tunnel rehabilitation with repairs to the tunnel wall and installation of the wall panel support system. The tunnel re-opened in March; rehabilitation work continues with periodic lane closures and occasional full closures as needed. There were three full overnight closures last week. A contractor performed a routine inspection of portions of the I-93 Southbound Tunnel and related ramps. A contractor also performed a similar inspection on the Northbound side. Contractors are also inspecting the Eastbound and Westbound tunnel sets. A contractor continued repairs to the roadway wearing surface near the entry portal of the Ted Williams Tunnel Westbound. The contractor is also making similar repairs at the Eastbound entry portal. A contractor performed test borings below the roadway near Dalton Street. The work is part of the preparation for the future Dalton Street Bridge replacement project. The work required lane closures in the I-90 Eastbound Tunnel. MassDOT cleaned 15 traffic cameras in the I-93 Northbound Tunnel. • • MassDOT workers replaced a faulty cable on a traffic camera near Ramp ST-SA/CN (Sumner Tunnel to Surface Artery and Sumner Tunnel to I-93 Northbound). A contractor took strain gauge readings as part of the ongoing efforts to monitor thawing of soil frozen in the vicinity of South Station during construction of the I-90 Connector Tunnel. The work required a lane closure in the I-90 Connector Tunnel Eastbound.