Shared Use Path Grade Separation Feasibility Study RIVER STREET BRIDGE B-16-006=C-01-005 (4F3) over Charles River Prepared For Prepared By 60 K Street Boston MA, 02127 December 2010 Rehabilitation of the River Street Bridge MassDOT Project Number 605527 Bike & Pedestrian Underpass Feasibility Study TABLE OF CONTENTS 1.0 Introduction 1 1.1. General 1 1.2. Scope of Study 2 1.3. Existing Conditions 2 1.3.1 3 2.0 2.1 Existing Volumes Feasibility Assessment 6 Design Parameters [for Underpass Options] 6 3.0 Description of Alternative Approaches to Underpass Features 9 3.1. Alternative #1 –Tunnel Through Abutment 9 3.1.1. Tunnel: Structural Impacts 9 3.1.2. Tunnel: Geotechnical Considerations 10 3.1.3. Tunnel: Utility Impacts 11 3.1.4. Tunnel: Environmental Permitting Considerations 12 3.1.5. Tunnel: Architectural/Cultural Impacts 15 3.1.6. Tunnel: Cost Impacts 15 3.1.7. Tunnel: Schedule Impacts 16 3.1.8. Tunnel: Traffic Impacts 17 3.1.9. Tunnel: Recreational Considerations 17 3.2. 3.1.10. Tunnel: Safety Considerations 17 Alternative #2 – Boardwalk Beneath Arch 18 3.2.1. Boardwalk: Structural Impacts 18 3.2.2. Boardwalk: Geotechnical Considerations 18 3.2.3. Boardwalk: Utility Impacts 19 3.2.4. Boardwalk: Environmental Permitting Impacts 19 3.2.5. Boardwalk: Architectural/Cultural Impacts 21 3.2.6. Boardwalk: Cost Impacts 21 3.2.7. Boardwalk: Schedule Impacts 22 3.2.8. Boardwalk: Traffic Impacts 23 3.2.9. Boardwalk: Recreational Considerations 23 i Rehabilitation of the River Street Bridge MassDOT Project Number 605527 Bike & Pedestrian Underpass Feasibility Study 3.2.10. Boardwalk: Safety Considerations 23 3.3. Alternative #3 – At Grade Enhancements 23 4.0 Summary of Findings 25 4.1. Alternative #1 25 4.2. Alternative #2 25 4.3. Alternative #3 25 Appendix A – Exhibits A-1 Appendix B – Cost Estimates B-1 Appendix C – Evaluation of Alternatives ii C-1 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study 1.0 Introduction 1.1. General The River Street and Western Avenue bridges over the Charles River are scheduled for major rehabilitation work in 2011 under MassDOT‘s Accelerated Bridge Program (“the Project”). The bridges provide major connections between Cambridge and Boston over the Charles River. In addition to the roadway network connectivity for motorized vehicles, pedestrians and bicyclists enjoy a network of paths and sidewalks around the Charles River Basin alongside the roadways and bridges. In the fall of 2009, a pedestrian and bike usage study was completed to measure the patterns and volumes of the bike path around the Charles River. Appreciable volumes of non-motorized users were observed using the various paths and bridges around the river. While there are no established "volume warrants" or "accident warrants" for pedestrian and bike crossings at major roadways where underpass/overpass should be considered, MassDOT’s Project Development & Design Guide has written design guidance that discusses in general terms how to design and scope non-motorized transportation facilities (Shared Use Paths and Greenways, 2006). The policy guidance indicates consideration should be given to separating motorized and non-motorized users at intersections, where feasible, in the interest of safety and capacity. Further, comments received at public meetings concerning the Project indicate that a number of stakeholders are interested in exploring potential options for developing grade separated crossings at Western Avenue and River Street. This report specifically addresses the possibility of creating grade separated crossings at River Street in accordance with MassDOT policy guidelines and in response to public comments. A separate report has been prepared to address the feasibility of grade-separated motorized & non-motorized traffic in the vicinity of the River Street Bridge. MassDOT recognizes that the pending major rehabilitation Project may provide optimal circumstances to consider grade separation between vehicles, pedestrians and bicyclists, and directed its design consultant, Hardesty & Hanover, to study the benefits and issues associated with developing grade separation prior to design work for the rehabilitation project getting substantially underway. 1 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study 1.2. Scope of Study The scope of this assessment is to determine how the bridge approaches can be designed to accommodate a shared use grade separated crossing that improves intersection capacity and safety for all users at each end of the bridge and the implications associated with accommodating the grade separation. The feasibility assessment follows the guidelines located in the Shared Use Paths and Greenways section of the 2006 MassDOT's Project Development & Design Guide (PD&DG) and the American Association of State Highway and Transportation Officials' 1999 Guide to Development of Bicycle Facilities. According to MassDOT's PD&DG, overpass and underpass options should be considered for highly volume path and roadway crossings. Due to the existing topography along the Charles River and the proposed bridge structures, it is more cost effective to provide underpasses than overpasses. Therefore, this feasibility study only discusses the feasibility of providing grade separation by underpass. The assessment initially presents the structural considerations associated with incorporating underpass features as part of the rehabilitation Project, and then addresses other factors that influence the overall feasibility of including underpasses in the current design effort, including environmental considerations, utility infrastructure, historical context sensitivity, effects on traffic and recreational uses, schedule, and cost considerations. Two conceptual approaches to accommodating underpasses are considered; a tunnel through the bridge approaches and a boardwalk style path through the bridge arch. As noted previously, this report focuses on the River Street Bridge, while a companion report addresses the feasibility of incorporating underpasses into the rehabilitation of the Western Avenue Bridge. 1.3. Existing Conditions Originally constructed in 1925, the River Street Bridge is a three span concrete arch structure founded on mass concrete and spread footings which bear on natural granular soils and clay, located below existing fill and organics or river bed sediments. The River Street Bridge carries vehicular and non-motorized traffic across the Charles River over a distance of 329 feet. The bridge is a “contributing element” associated with the Charles River Basin National Historic District; its intrinsic form and architectural features are an integral part of the larger historic setting in which it is located. Due to its deteriorating condition, it is currently under design for major rehabilitation work, with the express understanding that such rehabilitation be undertaken in a manner that respects the historic “character-defining features” of the bridge and its immediate environs. This report does not detail existing conditions concerning the bridge structure 2 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study itself, but rather focuses on the physical characteristics of the shared path system as it approaches the bridge. The paths around the Charles River Basin are used by pedestrians, bicyclists, runners, skaters, and various other users as an alternative of commuting and for recreation. The paths meet River Street at Memorial Drive in Cambridge and Soldier’s Field Road in Boston at signalized intersections. Where the paths cross River Street, typical sidewalk ramps are provided to accommodate bicycles and persons with disabilities, and marked crosswalks demarcate the shared use path zone as it traverses the roadway. Pedestrian indications with push buttons are provided for shared use path users to obey to cross the roadway on the Cambridge Side of the bridge. However, on the Boston Side, at the intersection of River Street and Soldiers Field Road, the intersection is not marked or signalized for pedestrians. Further, in some locations there are “pinch points” in which sidewalks or paths are undersized relative to demand for pedestrian and bicycle access, and unsafe conditions exist in particular areas. In particular, the southern corner of the intersection of River Street and Soldiers Field Road is of significant concern and is regularly referred to as “the narrows”, indicative of the major pinching of pedestrian traffic between the Soldiers Field Road access ramp and the Charles River seawall. Due to the proximity of the Charles River and heavily-used roadways, there is limited land area available to provide enhanced pedestrian and bicycle facilities. On the Cambridge side of the river, the existing shared use pathway is directly supported by a granite block retaining wall north of the bridge, while the path is supported by an earthen embankment to the south of the bridge. The existing path is 11’ wide on the Cambridge side of the river. On the Boston side of the river, this condition is reversed, with the shared use path supported by a granite block wall to the south of the bridge, and by an earthen embankment to the north. The existing path is between 8’ and 9’, with a pinch point as narrow as 7’ near “the narrows”, mentioned above, on the Boston side of the river. Some additional land area is available on the Cambridge side of the river. However this “available” land supports grass and street trees, providing a desirable buffer between motorized and non-motorized travel ways. 1.3.1 Existing Volumes The River Street Bridge provides three travel lanes for motorists and carries approximately 20,700 vehicles per day (March 2010). Non-motorist counts were conducted in September 2009 and May 2010 as part of the Charles River Basin Pedestrian and Bicycle Study for Pathways and Bridges. Two-hour counts were conducted on a typical weekday evening peak and weekend midday peak. Counts were conducted from 4:30-6:30 pm on Wednesday, Sept. 23, 2009 and Tuesday, May 11, 2010 and from 12:00-2:00 pm on Saturday, Sept. 26, 2009 and Sunday, May 16, 2010. Non-motorist users were counted crossing the River Street Bridge and along the adjacent shared use path system. The count results are provided in the table below. 3 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study Table 1.3.1 Overview of Non-Motorized Vehicle Usage Fall 2009 Counts Spring 2010 Counts Weekday PM Counts Weekend Midday Counts Weekday PM Counts Weekend Midday Counts River Street Bridge 289 users 217 users 244 users 331 users Path on Cambridge side 377 users 466 users 383 users 1367 users Path on Boston side 247 users 348 users 248 users 769 users During the Spring 2010 counts, Memorial Drive was closed to motor vehicle traffic. Additionally, according to the Charles River Basin Pedestrian and Bicycle Study for Pathways and Bridges, "because of the varying nature of large-scale events and fundraisers that occur during the spring and summer weekends in the Basin, count figures from some bridge and path locations changed dramatically from September to May." As part of the count program, the non-motorist users were categorized into 4 categories: bicyclists, pedestrians, runners, and others. The following table provides the breakdown of the counts by users and location within the path system. Table 1.3.2 Breakdown of Non-Motorized Vehicle Usage Fall 2009 Counts Weekday PM Counts Saturday Midday Counts Spring 2010 Counts Weekday PM Counts Saturday Midday Counts River Street Bridge Bicyclists 96 (33%) 74 (34%) 107 (44%) 135 (41%) Pedestrians 96 (33%) 80 (37%) 49 (20%) 99 (30%) Runners 95 (33%) 62 (28%) 85 (35%) 87 (26%) 2 (1%) 1 (1%) 3 (1%) 10 (3%) Other 4 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study Path on Cambridge side Bicyclists 105 (28%) 148 (32%) 148 (38%) 630 (46%) Pedestrians 58 (15%) 144 (31%) 64 (17%) 493 (36%) Runners 213 (56%) 171 (36%) 170 (44%) 149 (11%) 1 (1%) 3 (1%) 1 (1%) 95 (7%) Other Path on Boston side Bicyclists 159 (64%) 171 (49%) 138 (55%) 202 (26%) Pedestrians 22 (9%) 88 (25%) 39 (16%) 498 (65%) Runners 63 (26%) 80 (23%) 64 (26%) 51 (7%) 3 (1%) 9 (3%) 7 (3%) 18 (2%) Other 5 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study 2.0 Feasibility Assessment As described in the subsequent sections, Hardesty & Hanover explored several alternative approaches to enhancing pedestrian and bicycle facilities. These include two underpass options (a tunnel and a boardwalk that passes under the roadway via one of the bridge arches) and an at-grade option that would involve modifications to existing crossings including shared use path improvements, reduction of crossing distance and conflicts and other safety enhancements aimed specifically at benefiting non-motorized users of the local transportation network. Due to demands of path connectivity, it should be noted that all feasible improvements to the at-grade shared use path crossings of River Street will be considered as part of the rehabilitation project whether or not grade separation is ultimately determined to be a feasible option. While it is desirable on shared use path networks to provide separation from motor vehicle traffic and minimize the number of street crossings, providing grade-separation may not be appropriate or desirable. The Shared Use Paths and Greenways section of the 2006 MassDOT's PD&DG provides a set of factors for the designer to consider when determining whether grade separation is an appropriate option at a given location. The factors to consider for all alternatives are: • 2.1 The suitability of the existing topography for grade separation; • The effectiveness of signage of traffic signal control as an alternative for the crossing given the context of the location; • Any changes in alignment that may be necessary to achieve the grade separation; • The opportunities of limitations placed on path connectivity to the surrounding area by the grade separation; • The context in which the path is set, in consideration of safety and security issues; • The volume, mix of vehicles, and speed of cross-traffic on the roadway; and • The volume and mix of path users. Design Parameters [for Underpass Options] Certain parameters were observed to develop conceptual designs for providing underpass features. These are based on the Shared Use Paths and Greenways section of the 2006 MassDOT's PD&DG. 6 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study The conceptual alternatives presented in this feasibility analysis adhere to the following parameters governing design and anticipated use of a path system that introduces an underpass feature to allow non-motorized traffic to cross River Street in the vicinity of both of its abutments (i.e., on the Boston side and on the Cambridge side): Joint use of the path by all users. Separating such uses would take up additional space within a constrained footprint, and may be interpreted as ‘favoring’ one mode over another relative to the water and buffering from traffic; Two-way travel, to accommodate any combination of turning movements and links to adjacent pedestrian/bicycle facilities; Maximum grades less than or equal to 5% to comply with Americans with Disabilities Acts (ADA) and the Massachusetts Architectural Access Board (AAB) standards Design speed of no more than 20 mph by bicyclists. Average walking speeds are 3.5 feet per second, and for safety reasons, it is desirable to discourage higher speed bicycling on congested shared paths. Due to the increased speeds associated with the down slope and the limited sight lines at the entrances to proposed tunnel sections of the underpass, a 20 mph design speed is used on the approaches to the tunnel sections. The design speed used where the underpass joins the existing path is 15 mph Minimum radius for horizontal curves of 100-feet to accommodate a reasonable bicycle design speed (no maximum is established; larger radii would only serve to encourage bicycles to go faster and would take up more space Minimum desirable vertical clearance of 10-feet for underpasses. Lower heights have been determined to discourage pedestrian and bicycle use. Minimum tunnel width (horizontal clearance) of 16-feet to accommodate shared use and two way travel with some buffer between the travel way and vertical walls. Narrower widths would discourage pedestrian and bicycle use, and create more conflicts between users. Minimum path width of 10-feet to accommodate shared use and two way travel. Ideally shared paths should be designed to be 12-16 feet in width, but in an effort to reduce the overall footprint, a narrower path was assumed. Recognition of the design flood elevation of the Charles River of 108.5 feet (MDC Vert. Datum). Conceptual designs remain above this elevation to ensure that the path is accessible (i.e., not flooded) under ordinary circumstances, and to reduce the need for pumping systems. 7 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study While a number of variations on these parameters could be considered, each deviation would have a negative impact on providing an equivalent level of accessibility to all users, or would result in a larger footprint and correspondingly greater environmental impacts. 8 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study 3.0 Description of Alternative Approaches to Underpass Features As noted above, Hardesty and Hanover considered three fundamentally different approaches to accommodating through pedestrian and bicycle movements: a tunnel (Alternative #1), a boardwalk (Alternative #2), and at-grade improvements (Alternative #3). Further description of each of these alternatives is provided below. 3.1. Alternative #1 –Tunnel Through Abutment For purposes of exploring the tunnel option, a concrete box culvert was assumed to reduce costs and minimize the overall length of the construction period. This concrete box culvert structure would penetrate the bridge’s approach retaining walls, immediately behind the mass concrete abutments. This option would necessitate placing earthen fill into the Charles River to support the construction of a 10-foot wide bituminous path approaching the tunnel structure. Retaining walls would be used to reduce encroachment into the Charles River to the extent possible. As noted previously, portions of the existing shared use path is directly supported by a granite block wall on both the Cambridge and Boston sides of the river. Stair access is recommended adjacent to the intersections down to the tunnel opening to enable pedestrians to return to grade if desired. New construction of storm drainage structures and possible pumping stations as well as re-configuration of existing storm drainage structures would be required. While the sketch plans provided in Appendix A illustrate an earthen embankment, retaining walls would be recommended to support the approaches to the underpasses and minimize the permanent area of disturbance. Reference Appendix A, pages A-1 & A-2 3.1.1. Tunnel: Structural Impacts There is little vertical height at the abutments to accommodate a box culvert with 10-ft clear opening. With the floor of the box set at the flood elevation, there is just enough room for the box to fit beneath the bottom of pavement. With this minimal cover, exposure to high concentrated live loads becomes a concern and is likely to complicate the structural design of the box. Other concerns are related to stability of the bridge during excavation to install the tunnel. The bridge is backfilled between the arches with soil. Care needs to be taken during excavation for the tunnel to retain the soil and limit lateral movement of the soil during construction. The construction activities should consider proper staging of construction coupled with a survey monitoring program for movements. Extensive use of soldier pile retaining wall systems will be required as they are likely the only system that can be installed within the narrow confines between 9 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study and around various obstructions. Utilities and high groundwater will make traditional retaining walls with footings challenging. Another structural issue is the resulting structural dimensions of the box culvert. The next section, utility impacts, is related to and has a dependency on the success of the box culvert structural design, and the assumptions made in this assessment. 3.1.2. Tunnel: Geotechnical Considerations The following geotechnical items need to be considered relative to construction of the tunnel: • Subsurface Conditions. Subsurface conditions generally consist of fill (at the abutments) overlying natural sand and gravel, clay, glacial till and bedrock. The thickness of these deposits is variable, the organics and clay are compressible soils, and the depth to till and bedrock is unknown. The bottom of the proposed tunnel box will likely be in the fill and/or organic soils. If these unsuitable soils are not removed or if the foundations do not extend into the more competent sand and gravel or clay layer, there is potential that differential settlement will occur that results in cracking and overall poor performance of the tunnel structure. • Groundwater. The bottom of the tunnel box will be located at the flood level of the Charles River. Construction of the box will need to consider placement of a tremie slab and/or methods of groundwater control. • Utilities. There are a number of utilities that will need to remain active throughout construction. These utilities will need to be protected, and in some cases, relocated. • Obstructions. Construction of the tunnel will need to consider the location of the mass concrete foundations and former cofferdams that were left in place following construction of the bridge in the 1920s. • Method of Construction. As noted above, the top of the tunnel box will be close to the existing roadway grade, therefore, the most practical method for construction will be cut-and-cover. • Support of Excavation. We anticipate that soldier piles and timber lagging may be the most feasible method of earth support in order to make adjustments to avoid obstructions during installation and conflicts with existing utilities and foundations. We anticipate soldier piles will be installed in 30-inch predrilled holes as close as 4 feet on center and may need to extend up to 50 to 60 feet below roadway grade. At least one 10 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study level of bracing may be required. The soldier piles will need to be designed to support lateral soil loads to retain soil below the roadway as well as vertical compression loads from temporary roadway decking. • Construction Staging. It is anticipated that the majority of work will need to be performed at night and the work areas decked over during daytime commuter hours. Alternatively, it may be possible to excavate and construct the tunnel box in stages (i.e. close down one lane or one-half the roadway). • Special Handling of Excavated Soils. The organic soils may contain elevated levels of contaminants, normally associated with automotive emissions. Special handling and transportation to an off-site disposal facility will need to comply with local, state, and federal environmental regulations. • Subsurface Explorations. Prior to proceeding with design of the tunnel box and the support of excavation system, borings will need to be performed, as a minimum, at each end of each tunnel box. The available boring data is from the 1920s, which was obtained using non-standard methods in comparison to those that are used today (i.e. ASTM) and the data is based on borings taken in the river rather than at the ends of the bridge where the tunnel boxes are proposed. 3.1.3. Tunnel: Utility Impacts Numerous significant underground utilities exist at the underpass locations, including 30” water mains, 30” natural gas mains, electrical, telephone, traffic signal, and sewerage authority facilities. Vertically, it appears that there is not enough elevation to route a concrete box culvert beneath the 30” water mains while maintaining the floor of the culvert at the design flood elevation of 108.5. Nor can the elevation of the box floor be increased due to the pavement elevation at the approaches. Significant vertical and horizontal re-alignment of the 30-inch water mains and gas mains will be required at both sides of the bridge. Investigation and location verification of active and abandoned utilities is a critical step in completing a final design. Another option to vertical utility offset beneath the tunnel may be under river jacking/boring of the lines. At this time, jacking/boring new water and gas main alignments beneath the Charles River is considered to be such a significant detrimental cost and schedule impact that it is not further analyzed in this study other than to mention it as a possibility. 11 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study Alternatively, placing the tunnel at lower than flood elevations in order to provide utility clearance is also possible. However, the engineering, construction, and maintenance additional cost is substantial. At this level of analysis, it appears the cost premium to configure the underpass surface at less than flood levels would accelerate short term and long term maintenance costs and user comfort and safety. 3.1.4. Tunnel: Environmental Permitting Considerations As originally envisioned, the bridge reconstruction project was expected to occur within its existing footprint, and simply repair the bridges in place without any alterations to the immediate environs. This approach was assumed in recognition of the historic status of the River Street Bridge and its surroundings. This subsection addresses additional permitting requirements or modified permitting requirements that would result from incorporation of tunnel structures and pedestrian/bicycle approaches to the tunnel. 3.1.4.1 Permits Required for In-Kind Reconstruction Due to the nature of the work anticipated for a major rehabilitation project, it was assumed that a number of permits and environmental review would be required for in-kind reconstruction of the bridges. These permits and reviews include: National Environmental Policy Act (NEPA) Categorical Exclusion (if project is constructed with federal funding) Massachusetts Environmental Policy Act (MEPA) consultation or Advisory Opinion (in-kind replacement would not necessarily trigger an Environmental Notification Form) Section 404 Category 2 General Permit (Category 2 triggered due to potential effects on cultural resources; in the absence of effects on cultural resources, only a Category 1, non-reporting, 404 permit would be triggered) Section 401 Water Quality Certification, automatic issuance in conjunction with Orders of Conditions Section 10 of the Rivers and Harbors Act of 1899 - Section 10 empowers the USACE to regulate all work on structures in or affecting the course, condition, or capacity of the navigable waters of the United States. It is our understanding that the USACE has delegated its authority under Section 10 to the USCG for bridge repair and maintenance work in the Charles River (see Appendix A of the PGP for Massachusetts) and a separate Corps review is not required. Chapter 91 Minor Modification (a process that only requires submission of a letter, rather than a formal permit application) 12 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study Local Notices of Intent/Orders of Conditions Massachusetts Historical Commission (MHC) Review (see discussion under Section 3.1.5) Massachusetts Water Resources Authority (MWRA) 8(M) permit for work within (MWRA easements) US Coast Guard (USCG) Construction Letter (provided that a project does not alter navigation characteristics of bridges under USCG jurisdiction, no formal permit application is required) 3.1.4.2 Permits Required for Tunnel Structure and Approaches The incorporation of one or more tunnel structures and pedestrian/bicycle path approaches would introduce substantial in-water work and removal of sediments, alteration of river banks, changes in the floodway geometry, changes to the navigability of the water sheet, direct filling of the river itself (which functions as an anadromous fish run), and significant relocation of MWRA infrastructure. As such, establishing pedestrian underpasses as depicted by the conceptual designs presented in Appendix A would result in changes to the number and types of permits required, and would alter the level of complexity associated with environmental analyses required for those permits that had already been anticipated. Table 3.1 summarizes anticipated permits associated with the inclusion of tunnel structures and approaches, noting changes in the complexity of each permit process for those permits already required for an in-kind reconstruction of the existing bridges. Table 3.1 Summary of Permits and Environmental Reviews Required for Addition of Pedestrian Tunnel and Approaches Permit/ Review Anticipated previously? Comments NEPA No (categorical exclusion; if at most) May require Environmental Assessment due to impacts to 4(f) parkland, water resources and water quality, fisheries, and historic resources. (NEPA review applicable if FHWA funds are used for construction or if ACOE permit is considered a “major federal action” MEPA No – only consultation or Advisory Opinion –no formal public review Alteration of river banks/impacts to parkland, reduction of available water sheet, grading, drainage, fisheries impacts, historic resource impacts & longer construction period (traffic impacts) likely to necessitate full EIR and more extensive analysis and discussion of issues. 13 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study MHC Review Yes – but would have proposed inkind replacement More extensive discussions of alternatives, more involvement in design/ selection of materials. US Army Corps of Engineers Review (Section 10 of the Rivers and Harbors Act and Section 404 of Clean Water Act) Yes – but 404 review was previously less involved; Section 10 was previously assumed to be delegated to the USCG but may now require separate Corps review. More extensive discussions of alternatives justifying discharge of fill material in the Charles River (per EPA’s 404(b)(1) Guidelines) and compensatory mitigation & more in-depth analysis of public interest factors under Section 10 including but not limited to fisheries impacts, water quality impacts, and impacts to historic resources Individual Water Quality Certification (Section 401) No (Order of Conditions would have served as Water Quality Certificate). In-water work, including dredging required to establish retaining wall foundations, will require individual water quality certification. Dredging of greater than 100 cubic yards would require development and approval of a sediment sampling plan, laboratory analysis, and would likely necessitate a dredge material disposal plan. Section 401 application would also involve a comprehensive alternatives analysis (similar to the Corps review) and coordination with fisheries agencies. (Likely fisheries time-of-year restriction would impact construction schedule and increase costs) US Coast Guard Bridge review No – only Letter of Construction Permanent change in horizontal clearance would trigger formal USCG review. See also Corp’s Section 10 discussion above. Chapter 91 License and Permit No Would require issuance of new license (in-kind replacement of existing would not necessitate any Chapter 91 notification, or minor modification letter at most). Wetlands Protection Act Notice of Intent (NOI) /Order of Conditions Yes – but previously less involved Additional documentation would be required to address changes to floodway, impacts to Land Under Water and Bank, increased analysis required to characterize sediment biochemistry, impacts to water quality and wildlife and fisheries habitat (including preparation of wildlife habitat evaluation and potential development of compensatory mitigation plans per 310 CMR 10.60), and impacts to groundwater. Would also require development of more involved Stormwater Management Plan to address increased impervious surfaces and pumping/discharge of groundwater or stormwater that may collect in tunnels. Likely to require increased number of public hearings and longer review timeline. See further discussion under Section 3.1.5 14 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study MWRA 8(M) Yes, but primarily administrative review Relocation of MWRA water lines would necessitate close coordination with MWRA. The cost of such relocation would be the responsibility of MassDOT, and cannot be shifted to MWRA ratepayers. MWRA will not allow existing water lines to be taken out of service between May 15 and September 15 3.1.5. Tunnel: Architectural/Cultural Impacts The Cambridge side improvements will cause a portion of the existing stone wall to be removed and re-constructed. The condition of the wall is such that reconstruction should be included in the proposed work. Current water levels in the basin are kept below historic levels allowing the timber piling and cribbing (supporting the walls) to deteriorate. (This work shall be completed by the Public Archaeology Laboratory. Their work requires most report subtasks to be completed prior to their involvement. ) 3.1.6. Tunnel: Cost Impacts 3.1.6.1 Design/Permitting Cost The greater complexity associated with design and permitting of a new tunnel structure would involve a more intensive level of effort on the part of every facet of the design team, including the structural engineers, geotechnical engineers, traffic engineers (for construction staging), cultural resources specialist and permitting consultant. Differentiating between costs attributable solely to the design of a tunnel structure would itself involve a considerable amount of effort, however a reasonable ballpark would be on the order of $600,000. 3.1.6.2 Construction Cost The soldier pile construction required to support the existing roadway during the box culvert installation may require heavy non-standard equipment. In addition, installation of the drilled soldier pile and lagging earth support walls will likely require night and/or weekend work (at a premium cost) to drill the soldier piles and to construct temporary roadway decking. The existence of known obstructions (such as existing utilities, concrete footings, walls, previous cofferdams, and timber piles) and the potential for unknown obstructions in the fill stratum will add complexity and cost to the construction project. 15 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study A boring program will need to be performed to evaluate existing subsurface conditions at the tunnel boxes. It is presently assumed that the tunnel will be constructed on grade after removal of any unsuitable fill and organic soils. The borings are required to confirm these conditions so that the tunnel boxes do not need to be supported on piles. A cost summary is provided in Section 4 of this analysis, and a detailed breakdown is provided in Appendix B. 3.1.6.3 Operations and Maintenance Costs Additional ongoing costs would be incurred to operate and maintain the tunnel. Such costs may include lighting, periodic inspections and repairs, litter and graffiti removal, periodic surveillance or maintenance of surveillance cameras, pumping of groundwater and ordinary sweeping/cleaning made somewhat more difficult given the low elevation and enclosed nature of the tunnel. 3.1.7. Tunnel: Schedule Impacts 3.1.7.1 Design/Permitting Schedule This alternative would significantly delay the issuance of a construction bid package, due to the additional permitting and design related investigations required. 16 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study 3.1.7.2 Construction Schedule In general due to the more complicated construction program, the overall construction schedule would be increased to allow for establishment of a large open cut trench with a multi-purpose structural roof for bracing horizontal load and to maintain traffic. In addition, due to the anadromous fisheries habitat and significant in-water work activities, it is anticipated that time-of-year restrictions would be placed on any in-water activities (generally March 15-June 15 per MA Wetlands Protection Act regulations although the Corps could require more stringent restrictions based on consultations with the state and federal fisheries resource agencies), while the MWRA will not allow water service to be shut off for relocation of mains between May 15 and September 15. Additionally, it is anticipated that work on the tunnel box will be required to occur during limited night-time hours, and possibly in low headroom conditions below decking. During construction, the complexity and potential for encountering obstructions during installation of the earth support walls and excavation for the tunnel box increases the probability for delays. 3.1.8. Tunnel: Traffic Impacts This alternative will have negative traffic impacts during the tunnel construction under the River Street Bridge approaches. Overnight/Weekend lane closures will be required to make tunnel excavation preparations. It is anticipated that some periods of complete bridge closure will be required to facilitate the extensive utility relocation work, safely accommodate heavy equipment and cranes, and manage construction materials. Although traffic impacts relating to tunnel construction will be periodic, off-peak, and brief, additional staging and phasing will be required to allow for excavation, preparation, and temporary support of the existing roadway during tunnel construction operations. 3.1.9. Tunnel: Recreational Considerations The tunnel option would extend the period during which the shared use pathway would not be accessible during construction, and would increase the length of time that construction equipment may occupy the water sheet, thereby impacting recreational boaters. Once constructed, the tunnel would benefit those path users that choose to use it in lieu of the existing sidewalks and crosswalks. There would be negligible impact to recreational boating once the tunnel and approaches were constructed. 3.1.10. Tunnel: Safety Considerations The benefits associated with separating pedestrians and bicycles from vehicular traffic include eliminating conflict with motor vehicles at intersections, significantly increasing safety. Nonetheless, the introduction of tunnels may present certain 17 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study safety concerns due to the lack of visibility into the tunnels from nearby roads. Such safety concerns can be mitigated to some extent by lighting and periodic surveillance, or even introduction of surveillance cameras (in turn adding capital and operational costs). A number of passageways along the Charles River, both public and private, have been closed due to safety considerations. 3.2. Alternative #2 – Boardwalk Beneath Arch This option consists of constructing a pile supported boardwalk to pass through the outer arches of the bridge. Pathway approaches would also be pilesupported, thereby minimizing the overall amount of direct fill into the Charles River as compared to the tunnel alternative. However, this option would occupy considerably more water sheet. This alternative is an approach similar to the path connectivity constructed at the Boston University Bridge, however its abutments are located considerably landward, such that the boardwalk in that location remains very close to the shoreline. For purposes of this analysis, a boardwalk with 12-foot clear railing to railing was assumed and would be routed beneath the outer arches with the path surface at a minimum elevation of 108.5 (design flood elevation) and a minimum headroom of 10-feet for bicycle compatibility. (Larger horizontal and vertical clearances were assumed for the tunnel alternative to compensate for the effects of total enclosure) A structural challenge of this option is the installation of piling beneath the bridge. Due to the limited headroom and possible long pile embedment lengths, pile splices may be required. Pre-augering of the piles may be required to prevent settlement and damage to the existing arches. (A floating path may also be considered as an alternative to a pile supported boardwalk under the arch. Floating paths were not included at this level of analysis, but may be considered under a future, more detailed analysis of the boardwalk option.) Reference Appendix A, pages A-3 & A-4 3.2.1. Boardwalk: Structural Impacts No structural impacts to the bridge are required by the boardwalk option. Drainage structures will also not be required. However, modification of the existing stone retaining walls, guide rails, and park barriers will be required to meet the boardwalk to the existing path. 3.2.2. Boardwalk: Geotechnical Considerations The following geotechnical items need to be considered relative to construction of the boardwalk: • Subsurface Conditions. Subsurface conditions generally consist of fill (at the abutments) overlying natural sand and gravel, clay, glacial till and 18 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study bedrock. The thickness of these deposits is variable, the organics and clay are compressible soils, and the depth to till and bedrock is unknown. Support of the boardwalk will require installation of pile foundations. • Foundations. We anticipate that foundation loads will be relatively light and (based on historic borings) could derive support primarily in side friction in the natural clay stratum. Feasible foundations include driven timber or composite plastic piles, except below the bridge arches where, due to low headroom conditions, drilled mini-piles may be required. Pile spacing will be specified by the structural boardwalk design, and pile locations will likely need to be pre-augered or pre-excavated to clear potential obstructions from rip-rap and debris along the river banks. Special precautions will need to be used during drilled mini-pile construction (i.e. use of oversized temporary casings and containment booms) to avoid potential loss of drilling fluids or grout to the river. • Pile connections to the boardwalk would have to be incorporated directly into the decking in order to avoid the need for construction of pile caps. • Subsurface Explorations. Prior to proceeding with design of the boardwalk, borings will need to be performed, as a minimum, at each end of the boardwalk. The available boring data is from the 1920s, which was obtained using non-standard methods in comparison to those that are used today (i.e. ASTM) and the data is based on borings taken in the river rather than at the ends of the bridge where the boardwalks are proposed. 3.2.3. Boardwalk: Utility Impacts No significant underground or above ground utility conflicts are anticipated by this alternative. 3.2.4. Boardwalk: Environmental Permitting Impacts Minor filling of open water and disturbance of freshwater wetlands is required by this alternative. The most significant new environmental permitting considerations include impacts to recreational use of the water sheet and alteration of the historic setting. A summary of permits anticipated for reconstruction of the bridge within its current footprint was provided in Section 3.1.5.1. Table 3.2 below lists anticipated permits required for the construction of Pedestrian Boardwalk and its approaches. 19 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study Table 3.2 Summary of Permits and Environmental Reviews Required for Addition of Pedestrian Boardwalk Permit/ Review Anticipated previously? Comments NEPA No (categorical exclusion; at most) May require Environmental Assessment due to impacts to 4(f) parkland, water resources and water quality, fisheries, and historic resources. (NEPA review applicable if FHWA funds are used for construction or if ACOE permit is considered a “major federal action” MEPA No – only consultation or Advisory Opinion –no formal public review Introduction of boardwalk element is more likely to be considered an “adverse impact” by MHC, which in turn may make it more difficult to develop a Memorandum of Agreement to stay below MEPA review threshold for historic resources. MEPA may also assert jurisdiction on the premise that a Superseding Order of Conditions may be required for the project. MHC Review Yes – but would have proposed inkind replacement More extensive discussions of alternatives, more involvement in design/ selection of materials. Likely to be viewed more unfavorably than a tunnel structure (which is likely to be viewed unfavorably) US Army Corps of Engineers Review (Section 10 of the Rivers and Harbors Act and Section 404 of Clean Water Act)) Yes – but 404 review was previously less involved; Section 10 was previously assumed to be delegated to the USCG but may now require separate Corps review. More extensive discussions of alternatives justifying introduction of fill from pile-supported structure (assumes the Corps considers the piles to be fill material) and reduction in navigable water sheet and other public interest factors under Section 10. Water Quality Certification (Section 401) To Be Determined If total cumulative fill from piles exceeds 5,000 s.f. of impact to land under water then an individual Water Quality Certification would be required. US Coast Guard Bridge review No – only Letter of Construction Permanent change in horizontal clearance would trigger formal USCG review. See further discussion under Section 3.2.5 20 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study Chapter 91 License and Permit No Would require issuance of new license (in-kind replacement of existing would not necessitate any Chapter 91 notification, or minor modification letter at most). Chapter 91 review would consider impacts to recreational use of the water sheet. Wetlands Protection Act Notice of Intent (NOI) /Order of Conditions Yes – but previously less involved The proposed pile supported boardwalk could be permitted as a Limited Project under 310 CMR 10.53(3)(j). Additional documentation would be required to address alternatives, pile installation techniques including information describing flowage of water and light conditions necessary to maintain aquatic vegetation (if present within footprint). Time of Year restrictions would likely apply. Likely to require increased number of public hearings and longer review timeline. 3.2.5. Boardwalk: Architectural/Cultural Impacts This option effectively eliminates the availability of the outer most arches to accommodate rowing craft in the Charles River. Current marine traffic patterns on the river promote use of the outer arches by skullers and minimal use of the center arch by rowing crews with a coxswain or coach. Should the outer arches be eliminated as an option for navigation, all traffic will be bottlenecked into the center arch, creating a narrow bi-directional navigation pattern accommodating all types of navigation and experience/skill levels. In addition, the Head of the Charles Regatta currently uses the arches of the River Street Bridge for its race course. The cultural impacts of this alternative on the rowing community would be severely negative. The boardwalk alignment required by this alternative places the boardwalk well into the Charles River, nearly out to the centerlines of the outer bridge arches. While a subjective assessment, it is expected that most observers and cultural resource stewards would determine that this alignment would significantly alter the river view in an objectionable manner. 3.2.6. Boardwalk: Cost Impacts 3.2.6.1 Design/Permitting Cost The greater complexity associated with design and permitting of new boardwalk and approach structures would involve a more intensive level of effort on the part of every facet of the design team, including the structural engineers, geotechnical engineers, traffic engineers (for construction staging), cultural resources specialist and permitting consultant. Differentiating between costs attributable solely to the design of a tunnel structure would itself involve a considerable amount of effort, however a reasonable ballpark would be on the order of $600,000 21 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study 3.2.6.2 Construction Cost This alternative requires significant in-water work which typically results in an appreciable price premium over similar land based construction activities. As previously mentioned, installation of the boardwalk on piles will require special equipment and alternative construction methods due to the complexity of installing piles in an environment with such low head room incurring an additional cost premium. In addition, the complexity and potential for encountering unknown obstructions during pile installation activities increases the probability for additional costs to be incurred during construction. A boring program will need to be performed to evaluate existing subsurface conditions at each end of the boardwalk. It is presently assumed that the boardwalk will be supported on pile foundations supported in the natural soils underlying the fill and organic soils. The depth to the top of sand and gravel and to the top of clay should be defined, as well as the relative density in order to provide engineering parameters for design of the piles. This feasibility analysis considers a generic timber structure of the dimensions previously mentioned and assumes construction costs only, for project planning purposes. Plastic piles and plastic decking are also possible, but not included in this analysis. Plastic piles and decking generally have higher construction costs and lower maintenance costs. A cost summary is provided in Section 4 of this analysis, and a detailed breakdown is provided in Appendix B. 3.2.6.3 Operations and Maintenance Costs Lifecycle cost of in-water marine structures varies with chosen construction materials and method of weather/ice protection as well as maintenance practices. Detailed cost comparison of the various available construction materials corresponding to anticipated life cycle maintenance costs is not presented here as it is beyond the scope of this feasibility study. It is only mentioned because the facility is clearly expected to be used heavily by the public and therefore will require regular inspection and maintenance for public safety. 3.2.7. Boardwalk: Schedule Impacts 3.2.7.1 Design/Permitting Schedule This alternative has negative impacts to the contract and design schedule due to the additional permitting and design related investigations required. 22 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study 3.2.7.2 Construction Schedule In general due to the more complicated construction program, the overall construction schedule would be increased to allow for installation of piles to support the boardwalk as well as approach structures. In addition, due to the anadromous fisheries habitat and significant in-water work activities, it is anticipated that time-of-year restrictions would be placed on any in-water activities (generally March 15-June 15 per MA Wetlands Protection Act regulations although the Corps could require more stringent restrictions based on consultations with the state and federal fisheries resource agencies). In addition, the complexity and potential for encountering unknown obstructions during pile installation activities increases the probability for delays during construction. 3.2.8. Boardwalk: Traffic Impacts The boardwalk option causes no significant impact to roadway traffic, but a significant impact to river traffic, both during and after construction. Like normal roadway maintenance and protection of traffic requirements, on the Charles River, coordination of the work effort with river traffic has similar levels of effort and importance. 3.2.9. Boardwalk: Recreational Considerations The boardwalk option would have limited impact on pedestrian, bicyclists and boaters during construction. However, once constructed, the board walk would occupy a large area of the water sheet, and effectively eliminate water access to the span(s) in which the boardwalk(s) were located. To minimize such impacts, consideration could be given to constructing only one boardwalk (if any) per bridge. 3.2.10. Boardwalk: Safety Considerations The benefits associated with separating pedestrians and bicycles from vehicular traffic include eliminating conflict with motor vehicles at intersections, significantly increasing safety. Like the tunnel but to a lesser degree, the boardwalk would place pedestrians and bicyclists in a location that is not as visible to motorists and others as at-grade paths, however only for a very short distance. Lighting of the boardwalk should be considered to increase nighttime safety, however it is anticipated that MHC and others would object to such lighting given how prominent it would appear in relationship to the bridge and water sheet (vs tunnel lighting, which would be largely shielded from view). 3.3. Alternative #3 – At Grade Enhancements This alternative involves the incorporation of improvements into the project which promotes bicycle and pedestrian use and improves safety within the existing footprint of the bridge and adjacent shared use pathway network. The at-grade 23 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study enhancements that would be considered include, but may not be limited to: geometric (e.g., sidewalk width and configuration, particularly at corners), visibility/sight triangle, signing and striping, signal timing, and curb ramp improvements. Significantly, part of this alternative is to include design features into the project that will allow the bridge structure to facilitate future construction of an underpass. Compared to the other alternatives, the at-grade enhancements alternative has no impact to any of the areas covered by this feasibility analysis. There are no negative impacts that prelude incorporating pedestrian and structural improvements at the bridge approach intersections into the rehabilitation work provided that these improvements do not encroach into the river and do not adversely impact the historic integrity of the bridge itself and the broader Charles River Basin National Historic District. As part of this alternative, the bridge reconstruction program would include provisions for wall knock-outs at potential tunnel locations with corresponding structural reconstruction and compatible architectural treatments, location and verification of buried utilities. This alternative will be considered as part of the rehabilitation project whether or not grade separation is feasible. 24 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study 4.0 Summary of Findings As previously stated, The Shared Use Paths and Greenways section of the 2006 MassDOT's PD&DG provides a set of factors for the designer to consider when determining whether grade separation is an appropriate option at a given location. The summary of the factors are provided in the following matrix, as well as in a table matrix, attached as Appendix C. 4.1. Alternative #1 - Tunnel Through Abutment The most challenging alternative requires extensive utility locating and utility owner coordination and assistance. The scheme has hidden uncertainties. It also requires additional environmental permitting and review which clearly impacts the desired construction schedule. It is the least intrusive alternative with respect to the river, and its users, and has the potential to further reduce intrusion into the water way with the application of additional retaining walls. The trade off for less impact on the waterway is more impact to utilities, traffic, and greater uncertainty. 4.2. Alternative #2 - Boardwalk Beneath Arch From an up front cost standpoint, the two alternatives presented here are relatively even. However, the boardwalk alternative is likely the most difficult to permit and obtain community approval. Where it trades for less road user impact, it more than makes up for impact on the boating community. It is also therefore likely to be a scheduling problem, although it is not an option that needs to be connected to the already scheduled bridge rehabilitation work. Construction of a boardwalk has the least physical obstacles, with respect to utilities and road users, but is most probable to have insurmountable aesthetic and cultural obstacles. It is also expected to be the alternative with the shortest lifecycle, highest maintenance need, and highest public liability from a user safety standpoint. 4.3. Alternative #3 - At Grade Enhancements The at-grade enhancements alternative, compared to the other considerations, has no appreciable additional construction cost or schedule impacts to the already planned bridge rehabilitation work. Significantly, this alternative would not preclude the potential for constructing either a tunnel or a boardwalk at a future date. Provisions to facilitate construction of a tunnel could be made to the ongoing design for rehabilitation of the bridge. As previously stated, Alternative 3 will be considered as part of the rehabilitation project whether or not grade separation is feasible. 25 Rehabilitation of the River Street Bridge MassDOT Project Number605527 Bike & Pedestrian Underpass Feasibility Study Cost Summary Alternative #1 Concrete Tunnel Alternative #2 Boardwalk Boston (Memorial Drive) $2,225,000 $1,551,000 Cambridge (Soldier’s Field Rd) $2,218,000 $1,656,000 Total Cost $4,443,000 $3,207,000 See Appendix B for itemized breakdown of the construction cost estimate indicated in Table 1, above. 26 Appendix A – Exhibits A-1 Appendix B – Cost Estimates B-1 Project: Job #: Made By: Checked By: MassDOT Bridge Pedestrian/Bicycle Underpass 2589 JLA TL Alternative #1: River Street Boston Side, Tunnel Underpass ENGINEER'S COST ESTIMATE - Feasability Study SEQ NO. PAY ITEM DESCRIPTION PAY UNIT QTY. UNIT PRICE COST ADMINISTRATIVE MOBILIZATION MAINTENANCE & PROTECTION OF TRAFFIC CLEARING SITE SOIL EROSION & SEDIMENT CONTROL FINAL CLEAN UP LS LS LS LS LS LS LS LS LS LS $100,000.00 $75,000.00 $15,000.00 $26,000.00 $38,000.00 $100,000.00 $75,000.00 $15,000.00 $26,000.00 $38,000.00 ROADWAY EXCAVATION BORROW EXCAVATION BASE COURSE HMA, SURFACE COURSE HMA, BASE COURSE REINFORCED CONCRETE CULVERT PIPE INLET MANHOLE HEADWALL CURB SIDEWALK TRAFFIC STRIPING SIGNS BIKE PATH CY CY SY T T LF U U U LF SY LS LS SY 3000 3000 315 45 75 160 4 2 2 140 160 LS LS 360 $138.00 $25.00 $14.00 $88.00 $72.50 $45.00 $3,125.00 $5,000.00 $2,500.00 $31.25 $62.50 $10,000.00 $4,000.00 $42.50 $414,000.00 $75,000.00 $4,410.00 $3,960.00 $5,437.50 $7,200.00 $12,500.00 $10,000.00 $5,000.00 $4,375.00 $10,000.00 $10,000.00 $4,000.00 $15,300.00 LS LF LF LF LF LF LS LS LS 140 $50,000.00 $675.00 $862.50 $912.50 140 LS LS $1,336.00 $20,000.00 $20,000.00 $50,000.00 $94,500.00 $0.00 $0.00 $0.00 $187,040.00 $20,000.00 $20,000.00 STRUCTURAL GEOTECHNICAL INVESTIGATION & MONITORING PRECAST CONCRETE BOX CULVERT, 10'X16' COFFERDAM & DEWATERING OPERATIONS BRIDGE PARAPET EXCAVATION SUPPORT MISC CONCRETE, STAIRWELL RETAINING WALLS, 4 FT HIGH RETAINING WALLS, 6 FT HIGH RETAINING WALLS, 8 FT HIGH RETAINING WALLS, 10 FT HIGH LS LF LS LF SF LS LF LF LF LF LS 80 LS 140 2500 LS $40,000.00 $3,625.00 $150,000.00 $800.00 $250.00 $10,000.00 $500.00 $800.00 $1,000.00 $1,500.00 $40,000.00 $290,000.00 $150,000.00 $112,000.00 $625,000.00 $10,000.00 $0.00 $0.00 $0.00 $0.00 ELECTRICAL/TRAFFIC SIGNAL LIGHTING, TUNNEL STREET LIGHTING TRAFFIC SIGNAL STANDARD TRAFFIC SIGNAL CONTROLLER LS LS U U LS LS $15,000.00 $15,000.00 $12,000.00 $15,000.00 $15,000.00 $15,000.00 $0.00 $0.00 LANDSCAPING FENCE RAILING PLANTING LF LF LS 50 360 LS $60.00 $85.00 $35,000.00 $3,000.00 $30,600.00 $35,000.00 UTILITY UTILITY LOCATION & VERIFICATION WATER MAIN RELOCATION, 30" WATER MAIN RELOCATION, 42" WATER MAIN RELOCATION, 60" GAS MAIN RELOCATION, 30" UNDERGROUND ELECTRICAL RELOCATION UNDERGROUND TELEPHONE RELOCATION TOTAL OF ADMINISTRATIVE ITEMS TOTAL OF ROADWAY ITEMS TOTAL OF UTILITY ITEMS TOTAL OF STRUCTURAL ITEMS TOTAL OF ELECTRICAL ITEMS TOTAL OF LANDSCAPING ITEMS INFLATION (percent, for 2 years) SUBTOTAL ALL CONSTRUCTION ITEMS 2.5% $254,000.00 $167,182.50 $371,540.00 $1,227,000.00 $30,000.00 $68,600.00 $107,000.00 $2,225,322.50 Project: Job #: Made By: Checked By: MassDOT Bridge Pedestrian/Bicycle Underpass 2589 JLA TL Alternative #1: River Street Cambridge Side, Tunnel Underpass ENGINEER'S COST ESTIMATE - Feasability Study SEQ NO. PAY ITEM DESCRIPTION PAY UNIT QTY. UNIT PRICE COST ADMINISTRATIVE MOBILIZATION MAINTENANCE & PROTECTION OF TRAFFIC CLEARING SITE SOIL EROSION & SEDIMENT CONTROL FINAL CLEAN UP LS LS LS LS LS LS LS LS LS LS $100,000.00 $75,000.00 $15,000.00 $26,000.00 $38,000.00 $100,000.00 $75,000.00 $15,000.00 $26,000.00 $38,000.00 ROADWAY EXCAVATION BORROW EXCAVATION BASE COURSE HMA, SURFACE COURSE HMA, BASE COURSE REINFORCED CONCRETE CULVERT PIPE INLET MANHOLE HEADWALL CURB SIDEWALK TRAFFIC STRIPING SIGNS BIKE PATH CY CY SY T T LF U U U LF SY LS LS SY 3000 5000 333 50 75 174 2 0 2 155 210 LS LS 333 $138.00 $25.00 $14.00 $88.00 $72.50 $45.00 $3,125.00 $5,000.00 $2,500.00 $31.25 $62.50 $10,000.00 $4,000.00 $42.50 $414,000.00 $125,000.00 $4,662.00 $4,400.00 $5,437.50 $7,830.00 $6,250.00 $0.00 $5,000.00 $4,843.75 $13,125.00 $10,000.00 $4,000.00 $14,152.50 LS LF LF LF LF LF LS LS LS 120 $50,000.00 $675.00 $862.50 $912.50 120 LS LS $1,336.00 $20,000.00 $20,000.00 $50,000.00 $81,000.00 $0.00 $0.00 $0.00 $160,320.00 $20,000.00 $20,000.00 STRUCTURAL GEOTECHNICAL INVESTIGATION & MONITORING PRECAST CONCRETE BOX CULVERT, 10'X16' COFFERDAM & DEWATERING OPERATIONS BRIDGE PARAPET EXCAVATION SUPPORT MISC CONCRETE, STAIRWELL RETAINING WALLS, 4 FT HIGH RETAINING WALLS, 6 FT HIGH RETAINING WALLS, 8 FT HIGH RETAINING WALLS, 10 FT HIGH LS LF LS LF SF LS LF LF LF LF LS 80 LS 140 2500 LS $40,000.00 $3,625.00 $150,000.00 $800.00 $250.00 $10,000.00 $500.00 $800.00 $1,000.00 $1,500.00 $40,000.00 $290,000.00 $150,000.00 $112,000.00 $625,000.00 $10,000.00 $0.00 $0.00 $0.00 $0.00 ELECTRICAL/TRAFFIC SIGNAL LIGHTING, TUNNEL STREET LIGHTING TRAFFIC SIGNAL STANDARD TRAFFIC SIGNAL CONTROLLER LS LS U U LS LS $15,000.00 $15,000.00 $12,000.00 $15,000.00 $15,000.00 $15,000.00 $0.00 $0.00 LANDSCAPING FENCE RAILING PLANTING LF LF LS 90 280 LS $60.00 $85.00 $35,000.00 $5,400.00 $23,800.00 $35,000.00 UTILITY UTILITY LOCATION & VERIFICATION WATER MAIN RELOCATION, 30" WATER MAIN RELOCATION, 42" WATER MAIN RELOCATION, 60" GAS MAIN RELOCATION, 30" UNDERGROUND ELECTRICAL RELOCATION UNDERGROUND TELEPHONE RELOCATION TOTAL OF ADMINISTRATIVE ITEMS TOTAL OF ROADWAY ITEMS TOTAL OF UTILITY ITEMS TOTAL OF STRUCTURAL ITEMS TOTAL OF ELECTRICAL ITEMS TOTAL OF LANDSCAPING ITEMS INFLATION (percent, for 2 years) SUBTOTAL ALL CONSTRUCTION ITEMS 2.5% $254,000.00 $204,700.75 $331,320.00 $1,227,000.00 $30,000.00 $64,200.00 $107,000.00 $2,218,220.75 Project: Job #: Made By: Checked By: MassDOT Bridge Pedestrian/Bicycle Underpass 2589 JLA TL Alternative #2: River Street Boston Side, Boardwalk Underpass ENGINEER'S COST ESTIMATE - Feasability Study SEQ NO. PAY ITEM DESCRIPTION PAY UNIT QTY. UNIT PRICE COST ADMINISTRATIVE MOBILIZATION MAINTENANCE & PROTECTION OF TRAFFIC CLEARING SITE SOIL EROSION & SEDIMENT CONTROL FINAL CLEAN UP LS LS LS LS LS LS LS LS LS LS $150,000.00 $25,000.00 $15,000.00 $16,000.00 $25,000.00 $150,000.00 $25,000.00 $15,000.00 $16,000.00 $25,000.00 ROADWAY EXCAVATION BASE COURSE HMA, SURFACE COURSE HMA, BASE COURSE REINFORCED CONCRETE CULVERT PIPE INLET MANHOLE HEADWALL CURB SIDEWALK TRAFFIC STRIPING SIGNS BIKE PATH, 10-FT WIDE CY SY T T LF U U U LF SY LS LS SY 54 $138.00 $14.00 $88.00 $72.50 $45.00 $3,125.00 $5,000.00 $2,500.00 $31.25 $62.50 $10,000.00 $4,000.00 $42.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $2,295.00 $50,000.00 $675.00 $862.50 $912.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 UTILITY UTILITY LOCATION & VERIFICATION WATER MAIN RELOCATION, 30" WATER MAIN RELOCATION, 42" WATER MAIN RELOCATION, 48" WATER MAIN RELOCATION, 60" GAS MAIN RELOCATION, 30" UNDERGROUND ELECTRICAL RELOCATION UNDERGROUND TELEPHONE RELOCATION STRUCTURAL TIMBER BOARDWALK LS LF LF LF LF LF LS LS $1,336.00 $20,000.00 $20,000.00 SF 4620 $265.00 RETAINING WALLS, 4 FT HIGH RETAINING WALLS, 6 FT HIGH RETAINING WALLS, 8 FT HIGH RETAINING WALLS, 10 FT HIGH LF LF LF LF 0 0 0 0 $500.00 $800.00 $1,000.00 $1,500.00 ELECTRICAL/TRAFFIC SIGNAL LIGHTING, TUNNEL STREET LIGHTING TRAFFIC SIGNAL STANDARD TRAFFIC SIGNAL CONTROLLER LS LS U U LS LS LANDSCAPING FENCE RAILING PLANTING LF LF LS TOTAL OF ADMINISTRATIVE ITEMS TOTAL OF ROADWAY ITEMS TOTAL OF UTILITY ITEMS TOTAL OF STRUCTURAL ITEMS TOTAL OF ELECTRICAL ITEMS TOTAL OF LANDSCAPING ITEMS INFLATION (percent, for 2 years) SUBTOTAL ALL CONSTRUCTION ITEMS 2.5% 40 LS $1,224,300.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $85.00 $15,000.00 $0.00 $3,400.00 $15,000.00 $231,000.00 $2,295.00 $0.00 $1,224,300.00 $0.00 $18,400.00 $75,000.00 $1,550,995.00 Project: Job #: Made By: Checked By: MassDOT Bridge Pedestrian/Bicycle Underpass 2589 JLA TL Alternative #2: River Street Cambridge Side, Boardwalk Underpass ENGINEER'S COST ESTIMATE - Feasability Study SEQ NO. PAY ITEM DESCRIPTION PAY UNIT QTY. UNIT PRICE COST ADMINISTRATIVE MOBILIZATION MAINTENANCE & PROTECTION OF TRAFFIC CLEARING SITE SOIL EROSION & SEDIMENT CONTROL FINAL CLEAN UP LS LS LS LS LS LS LS LS LS LS $150,000.00 $27,000.00 $15,000.00 $16,000.00 $27,000.00 $150,000.00 $27,000.00 $15,000.00 $16,000.00 $27,000.00 ROADWAY EXCAVATION BASE COURSE HMA, SURFACE COURSE HMA, BASE COURSE REINFORCED CONCRETE CULVERT PIPE INLET MANHOLE HEADWALL CURB SIDEWALK TRAFFIC STRIPING SIGNS BIKE PATH, 10-FT WIDE CY SY T T LF U U U LF SY LS LS SY 32 $138.00 $14.00 $88.00 $72.50 $45.00 $3,125.00 $5,000.00 $2,500.00 $31.25 $62.50 $10,000.00 $4,000.00 $42.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $1,360.00 $50,000.00 $675.00 $862.50 $912.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 UTILITY UTILITY LOCATION & VERIFICATION WATER MAIN RELOCATION, 30" WATER MAIN RELOCATION, 42" WATER MAIN RELOCATION, 48" WATER MAIN RELOCATION, 60" GAS MAIN RELOCATION, 30" UNDERGROUND ELECTRICAL RELOCATION UNDERGROUND TELEPHONE RELOCATION STRUCTURAL TIMBER BOARDWALK LS LF LF LF LF LF LS LS $1,336.00 $20,000.00 $20,000.00 SF 4980 $265.00 RETAINING WALLS, 4 FT HIGH RETAINING WALLS, 6 FT HIGH RETAINING WALLS, 8 FT HIGH RETAINING WALLS, 10 FT HIGH LF LF LF LF 0 0 0 0 $500.00 $800.00 $1,000.00 $1,500.00 ELECTRICAL/TRAFFIC SIGNAL LIGHTING, TUNNEL STREET LIGHTING TRAFFIC SIGNAL STANDARD TRAFFIC SIGNAL CONTROLLER LS LS U U LS LS LANDSCAPING FENCE RAILING PLANTING LF LF LS TOTAL OF ADMINISTRATIVE ITEMS TOTAL OF ROADWAY ITEMS TOTAL OF UTILITY ITEMS TOTAL OF STRUCTURAL ITEMS TOTAL OF ELECTRICAL ITEMS TOTAL OF LANDSCAPING ITEMS INFLATION (percent, for 2 years) SUBTOTAL ALL CONSTRUCTION ITEMS 2.5% 60 LS $1,319,700.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $85.00 $15,000.00 $0.00 $5,100.00 $15,000.00 $235,000.00 $1,360.00 $0.00 $1,319,700.00 $0.00 $20,100.00 $80,000.00 $1,656,160.00 Appendix C – Evaluation of Alternatives C-1 Summary Comparison of Alternative Approaches to Shared Use Path Enhancements Note: All data are preliminary and reflect 10% design information. At-Grade Enhancements Element to Be Evaluated Tunnel Underpasses Boardwalk Structure Score/Ranking: A -substantial benefit B - benefit C - neutral/ minor (compared to existing conditions) D - negative impact F - fails Comments Ped/Bike Connectivity C Limited improvements; nonmotorized access still interrupted by signals at intersections C Constructability / Engineering Issues No issues C Utility Impacts negligible Historic / Archeological Impacts A Provides most direct continuity B Uninterrupted, circuitous route somewhat D D On Both Cambridge and Boston Side, construction MAY NOT BE FEASIBLE. Piles to support tunnel structure must be installed at angles to avoid contact with bridge abutments Pile installation beneath bridge arches will be difficult, time consuming, and expensive due to low head room D C Would require relocation of major water and gas mains. Construction season may be limited to activity outside of peak demand for affected utilities. None C D or F (tbd by MHC) D or F (tbd by MHC) No adverse impact anticipated with use of similar materials and incorporation of appropriate details Unknown potential archaeological impacts associated with establishing footings and excavation Negative impacts associated with introduction of new structures interrupting appearance of bridge arches / setting of bridge structures Negative impacts associated with changes to bridge abutments, introduction of new approaches 2795/Rvr&Wstrn but 1 At-Grade Enhancements Element to Be Evaluated Tunnel Underpasses Boardwalk Structure Score/Ranking: A -substantial benefit B - benefit C - neutral/ minor (compared to existing conditions) D - negative impact F - fails Comments C Wetlands/Waterways /Water Quality Impacts and Permitting D F (due to extent of impact to water sheet) No impacts beyond those associated with bridge reconstruction project 26,600 SF filling of Land Under Water for tunnel approaches Will require development of sediment sampling plan Comprehensive discussion of alternatives required for 404, 401 and WPA permit applications; agencies may not concur that the approach is the “Least Environmentally Damaging Practicable Alternative” Will require Chapter 91 license; DEP will consider impacts to boating community Minimal direct alteration of Land Under Water for boardwalk piers (approx 2,000 SF) Comprehensive discussion of alternatives required for 404, 401 and WPA permit applications; agencies may not concur that the approach is the “Least Environmentally Damaging Practicable Alternative” Will require Chapter 91 license; DEP will consider impacts to boating community USCG may not allow significant intrusion into navigable waterway Necessitates USGC review C Safety & Security Not as desirable as gradeseparation from safety perspective Grade separation provides improved safety, however security compromised due to lack of visibility into tunnel from vehicles/passers by C Implications for Other Users D Grade separation provides improved safety, however security compromised due to lack of visibility into tunnel from vehicles/passers by D F (due to footprint of occupied water sheet Limited encroachment into vehicular way No impacts to boating community No impacts to vehicular way No impacts to vehicular way Approaches would occupy a portion of the water sheet, however newlyoccupied water sheet would be close to existing shoreline (minimal impacts to boating community) Bridge design necessitates that the boardwalk extend approx 100 feet from existing seawall and 60 feet from shoreline to clear abutment and pass through arch with sufficient headroom D D C Cost Cost neutral 2795/Rvr&Wstrn D $4,443,000 $3,207,000 2 At-Grade Enhancements Element to Be Evaluated Tunnel Underpasses Boardwalk Structure Score/Ranking: A -substantial benefit B - benefit C - neutral/ minor (compared to existing conditions) D - negative impact F - fails Comments Operation/ Maintenance Issues C Negligible operations and maintenance issues D Periodic inspections required Ongoing pumping 2795/Rvr&Wstrn D cost associated Moderate additional costs associated with construction with Shortest life span among alternatives before total replacement required 3