ROAD SAFETY AUDIT MAJOR HIGHWAY MEDIAN CROSS-OVER CRASHES ROUTE 140 TAUNTON-LAKEVILLE Prepared for Prepared by MS Transportation Systems, Inc. Framingham, Massachusetts May 2009 ROAD SAFETY AUDIT MAJOR HIGHWAY MEDIAN CROSS-OVER CRASHES ROUTE 140 TAUNTON-LAKEVILLE Final Report May 2009 Prepared for Massachusetts Highway Department Prepared by MS Transportation Systems, Inc. Consultant Engineers and Planners 300 Howard Street P.O. Box 967 Framingham, Massachusetts 01701 Tel: 508-620-2832 Fax: 508-620-6897 www.mstransportationsystemsinc.com Route 140 Taunton-Lakeville Road Safety Audit TABLE OF CONTENTS Page INTRODUCTION 1 RSA PROCESS 3 ANALYSIS 8 SUMMARY OF RSA FINDINGS/POTENTIAL ACTIONS 12 RECOMMENDATIONS 19 APPENDIX 22 MS Transportation Systems, Inc. Page i Route 140 Taunton-Lakeville Road Safety Audit INTRODUCTION Lane departure crashes are one of the primary fatal crash types in Massachusetts. The Commonwealth exceeds the national average for the proportion of fatal lane departure crashes and was designated a lead state in lane departure crashes by the American Association of State Highway and Transportation Officials (AASHTO). The Massachusetts Highway Department (MassHighway) conducted a study of the problem and found that during 2002-2004, lane departure crashes accounted for 25 percent of all injury crashes and nearly half, 46 percent, of all fatal crashes. As part of the effort in implementing the safety plan and specifically reducing lane departure crashes, the MassHighway is completing a Road Safety Audit (RSA) Review Project specifically focused on median crossing (or median cross-over) crashes on its major highways. Road safety audits are a formal safety performance examination on existing or future roadways by an independent audit team. These specific audits are being conducted in locations where cross-over experience has been or has the potential to be of concern and where the RSA team has judged that factors exist that could affect the safety risk. During the audit, the RSA team works to identify opportunities for enhancing safety and to recommend specific enhancements intended to reduce median cross-over crashes and improve the overall safety along the highway. A RSA was conducted as part of this project section of Route 140 Taunton-Lakeville and Figure 1 shows the corridor section under study. The study section is from south of the Stevens Street interchange (No. 11) in Taunton to the County Street interchange (No. 9) in Lakeville. The study section also includes the Myricks Street (Route 79) Interchange No. 10. The purpose of this Route 140 Taunton-Lakeville RSA was to identify current conditions on the highway section under study that could potentially affect safety risk and to recommend a set of actions to address the identified safety factors. Recommendations contained in this report reflect the overall consent of the RSA team and do not necessarily reflect the official views of MassHighway. MS Transportation Systems, Inc. Page 1 Stevens Street 91 Forest Street Int. No. 11 140 Route 79 Int. No. 10 Route 24 140 Highland Avenue Myricks Street County Street Int. No. 9 Freetown Street - Interchange N Project Location W S Route 140 Road Safety Audit Taunton, Massachusetts MS Transportation Systems, Inc. E 1 : 25,000 Framingham, Massachusetts FIGURE 1 Route 140 Taunton-Lakeville Road Safety Audit RSA Process The general process outlined in the guideline1 was essentially followed although with some minor variations incorporated in the overall procedure. These were due in part to the project location being a high speed, high volume section of an access controlled highway. With these characteristics, there are limited areas to safely stop and gather as a group along the section without potentially hindering traffic flow or the safety of the project. Given the RSA team size (noted below) and general character with the corridor, the team members who visited the site prior to the team meeting did so either individually or in smaller groups. A video recording of a drive-thru in both directions was collected by the RSA consultant and used at the meeting to review conditions as a group. Background material and plans were transmitted to the RSA consultant to compile and review prior to the initial RSA team meeting. Crash and traffic volume data were transmitted to RSA team members prior to the meeting as well. Once the initial RSA team meeting was conducted, the RSA consultant gathered the input, completed the analysis and prepared a draft document for team members to review. Data including summary crash records for the 2004-2007 period, two (2) detailed crash descriptions of cross-over crashes, and available record highway plans were obtained and reviewed by the RSA consultant. • RSA Team The following individuals participated in the Route 140 Taunton-Lakeville Road Safety Audit: Edward C. Feeney, MassHighway District 5 Traffic Timothy White, FHWA Jim Hadfield, SRPEDD Jackie Schmidt, SRPEDD Timothy Kochan, MassHighway District 5 Planning Erin Kinahan, MassHighway, District 5 Projects Erin K. Sullivan, MSP Middleboro Lisa Schletzbaum, MassHighway, Safety Management Unit Bonnie Polin, MassHighway, Safety Xian Chen, MassHighway Jessica Stanley, MassHighway William J. Scully, MS Transportation Systems (RSA Consultant) Team members represented various agencies, disciplines and expertise. • RSA Meeting A meeting was held on September 25, 2008 at the MassHighway District 5 Office. At the meeting, the RSA consultant provided a brief overview of the RSA purpose, a summary of the roadway section’s characteristics and the results of the review to date in terms of geometry, volume and crash data researched and the field visit observations. 1 MS Transportation Systems, Inc., Road Safety Audits, Median Cross-Over Crashes, Audit Guidelines, Prepared for MassHighway, October 2007. MS Transportation Systems, Inc. Page 3 Route 140 Taunton-Lakeville Road Safety Audit The RSA team members listed above were present at the meeting. The video record of the Route 140, taken while driving the corridor was viewed. During and following the video, additional discussions related to the possible factors related to the cross-median crashes and possible solutions to prevent or alleviate similar characteristics in the future. The RSA team provided input on the background supporting data and the key items observed in the field and those items that were listed on the RSA Median Cross-Over Prompt List. Key items noted at the meeting included the following: Pavement surface appears old, with “scarring” and a large number of skidmarks. The sense by the enforcement personnel was that speeds are generally in excess of 70 mph even with fairly consistent enforcement. The RSA team members experienced with the corridor noted that fatigue may be a factor in this study section and combined with “dark”, straight sections of highway can contribute to the likelihood of an event or incident in the study section. Vehicle queues at the Route 24 northbound ramp from Route 140 is problematic although it may be improving with the recent Route 24 improvements. Guide signage is less than optimum for rest area and interchanges – including the signage for Route 79 in the southbound direction. Deer crossings are common in this section. Following the RSA meeting, the RSA consultant compiled the information, completed the analysis and circulated the draft report to team members. • Analysis Procedures As previously indicated, the RSA analysis generally followed the procedure described in the previously referenced Guideline with some variations and also took into consideration the methods published by the Federal Highway Administration2 (FHWA) and those included in FHWA training materials3. The basic tasks included: • 2 3 Obtaining and reviewing crash and other traffic characteristic data and available record plans. Federal Highway Administration, FHWA Road Safety Audit Guidelines, Publication No. FHWA SA-06-06, Washington, D.C., 2006. Federal Highway Administration, Resource Center, Road Safety Audits Mini-Workshop, Jeffrey Shaw, PE, PTOE, presented to New England ITE Section, September 19, 2006. MS Transportation Systems, Inc. Page 4 Route 140 Taunton-Lakeville Road Safety Audit • • • Conducting site reconnaissance and collecting a current record of condition via photos and video, Identifying potentially hazardous issues, and Identifying and evaluating potential actions to address the noted issues. In assessing the issues identified by the RSA Team, the relative seriousness and potential risk relative to crash frequency and severity were determined. Using the guidelines of FHWA4 as input and considering characteristics of this specific RSA, the relative frequency criteria and severity criteria were identified and are presented in Table 1 and Table 2, respectively. TABLE 1 FREQUENCY RATING ESTIMATED Exposure high medium high medium low high Probability high high medium medium high low low medium low medium low low EXPECTED CRASH FREQUENCY (PER AUDIT ITEM) 5 or more crashes per year FREQUENCY RATING Frequent 1 to 4 crashes per year Occasional Less that 1 crash per year, but more than 1 crash every 5 years Infrequent Less than 1 crash every 5 years Rare Source: FHWA RSA Training Workshop TABLE 2 SEVERITY RATING Typical Crashes Expected (per audit item) Expected Crash Severity High-speed crashes; head on and rollover crashes Moderate-speed crashes; fixed object or off-road crashes Crashes involving medium to low speeds; lane changing or sideswipe crashes Crashes involving low to medium speeds; typical of rear-end or sideswipe crashes Probable fatality or incapacitating injury Moderate to severe injury Severity Rating Extreme High Minor to moderate injury Moderate Property damage only or minor injury Low Source: FHWA RSA Training Workshop 4 Federal Highway Administration, Resource Center, Road Safety Audits Mini-Workshop, Jeffrey Shaw, PE, PTOE, presented to New England ITE Section, September 19, 2006. MS Transportation Systems, Inc. Page 5 Route 140 Taunton-Lakeville Road Safety Audit Taking into consideration both frequency and severity, the relative risk of a particular audit item was rated. The risk ratings are shown in Table 3. For each safety issue identified, the potential seriousness of the issue as well as possible mitigation measures have been indicated. TABLE 3 CRASH RISK ASSESSMENT Frequency Rating Low Frequent Occasional Infrequent Rare Severity Rating Moderate High C B A A D C B A Source: FHWA RSA Training Workshop Crash Risk Ratings: A: minimal risk level B: low risk level C: moderate risk level • Extreme E D C B F E D C D: significant risk level E: high risk level F: extreme risk level RSA Field Audit Field audits were conducted prior to the RSA meeting held on September 25, 2008. The field audits included several drive-thrus in each direction of travel as well as through the interchanges. A Prompt List developed for median cross-over RSA’s was used for guidance. The Prompt List is included in the Appendix. The following were noted during the audit: • The study section consists of two travel lanes per direction. • The inside shoulder appears to be between 1 and 2 feet in width. • Rumble strips exist in both inside and outside shoulders. • The median is largely open, fairly wide and designed generally as a “depressed” median. • The southbound direction is higher than the northbound direction. • Speeds are posted at 65 miles per hour. • There is no lighting along the section. MS Transportation Systems, Inc. Page 6 Route 140 Taunton-Lakeville Road Safety Audit • There is a rest/parking area in both directions north of the Route 79 interchange (Interchange No. 10). At the time of the field audit, advance signs for the parking areas and signage immediately at the areas were limited. Subsequent to the field audit, new signs were installed providing information between 1 and ½ mile in advance as well as at the facility itself. • Acceleration and deceleration lanes appear adequate in terms of length but markings could be improved for guidance. MS Transportation Systems, Inc. Page 7 Route 140 Taunton-Lakeville Road Safety Audit ANALYSIS Existing Conditions Route 140 Taunton-Lakeville is a major highway that provides east-west movement in Southeastern Massachusetts. Route 140 also serves the major cities of New Bedford and Fall River as well as the regional shopping area and educational facilities in Dartmouth. The section included in this study is approximately seven (7) miles in length from just south of the Stevens Street interchange in Taunton to the County Street (Interchange No. 9) in Lakeville. The photographs in Figures 2 and 3 show these sections and the overall horizontal alignments. The roadway in this area consists of two (2) travel lanes per direction. The roadway also has a full (10 foot) outside shoulder and an inside shoulder largely in the range of 1 to 2 feet, Rumble strips have been installed on both the inside and outside shoulders. The alignment is mostly straight with a few large radius curves and can be characterized as “gentle”. It was noted that the speed limits are posted at 65 miles per hour (mph). Including the Stevens Street interchange at the northern unit of the study section, there are three interchanges in the study section. Interchange spacing is 2.6 miles or more. The unpaved portion of the median is approximately 90 to 100 feet in width. The length of the “open” median in the study section is approximately 5.3 miles. Figures 4 and 5 present photographs that depict the current conditions along the study section. Figure 2 – Route 140 from Steven Street to Route 79 MS Transportation Systems, Inc. Figure 3 – Route 140 from Route 79 to County Street Page 8 Route 140 Taunton-Lakeville Road Safety Audit As was noted in the field visits, the rest/parking areas on each side of the highway are not ideally signed both in terms of advanced warning and more specific entry points and the exit and merge locations. Figure 4 – Route 140 Southbound Figure 5 – Route 140 Northbound North of County Street Interchange MS Transportation Systems, Inc. Page 9 Route 140 Taunton-Lakeville Road Safety Audit A review of available safety data was completed as part of this RSA. The review of data included crash data reported for the years 2004 to 2007. The summary table and spot map are included in the appendix. Key aspects noted in the data included the following: A total of 24 median related crashes reported between 2004 and 2007 or approximately 6 crashes per year. Of the total, 6 or 25% were cross-median crashes. The reported fatal crash was classified as a median crash. Based on the data available, eleven (11) of the 24 total reported median related crashes occurred in close proximity to the interchange with Route 79. Approximately 63% of total reported median related crashes resulted in personal injuries or fatalities. Five of the six cross-median crashes resulted in personal injuries. Of the reported median – related crashes, half were initiated in the northbound direction. Four of the six cross-median crashes were initiated in the northbound direction. Only four of the 24 crashes (16%) occurred under wet or icy surface conditions. Half (50%) of the median related crashes were reported under dark (night) conditions. In assessing the characteristics of the crashes, there was no one reason that stood out among the possible contributing causes. It is generally acknowledged that drivers may leave the roadway as a result of the following four reasons: Driver Error Collision Avoidance Roadway Condition Vehicle Component Failure High speeds were cited in three (3) crashes while five (5) crashes were at least partially attributed to fatigue. The traffic volumes on Route 140 in this section have been estimated at 35,000 on an average weekday. Historical truck traffic count data were obtained from MassHighway that showed a 3% truck percentage of the total volume for both the peak hour and daily periods. This amounts to approximately 100 truck trips over the day. MS Transportation Systems, Inc. Page 10 Route 140 Taunton-Lakeville Road Safety Audit Figure 6 Route 140 Taunton-Lakeville Traffic Volume In summary, the RSA has identified a number of physical and operational characteristics as being a potential contributing factor to the safety issues although each with varied levels of seriousness. The major one is: ¾ The median is open and although being relatively wide, the experience indicates that it is highly crossable. In addition, whether the crash was categorized as a cross-median or simply a median entry, most of the crashes have resulted in personal injuries as well as one fatal crash. The next section will discuss the key issues or factors identified by the RSA team and the potential actions to consider for addressing them. MS Transportation Systems, Inc. Page 11 Route 140 Taunton-Lakeville Road Safety Audit Summary of RSA Findings/Potential Actions Based on the field review, the review of crash data and discussions among the RSA team members, the issues related to the safe operating conditions of the Route 140 in the Taunton-Lakeville area were identified. There were a number of factors or issues of concern that were identified as potentially having an effect on the risk and these are listed in Table 4 along with the assigned risk rating. TABLE 4 SUMMARY OF FACTORS THAT POTENTIALLY AFFECT THE RISK OF SAFETY RELATED EVENTS Factor or Issue Risk Rating Open, crossable median E Inside shoulder is narrow C Markings for deceleration and acceleration lanes were less than optimum in terms of guidance D Rest area entry and exit – less than ideal warning or guidance C Speeding and driver behavior is significant in section C Southbound sign for Route 79 placement inadequate B Dark, unlit corridor that is long and straight C Driver fatigue C As shown in Table 4, there are number of risk factors that have been identified that potentially contribute to cross-median crashes. Included in this listing is the “open” median. While the median is fairly wide, there have been a relatively high proportion of total median related crashes being actually cross-median crashes. The risk rating assigned to this factor was ‘E’ in this case due to the frequency of median entries, crossmedian crashes and the potential of very severe results of the cross-median crashes. Other factors include the inside shoulder being less than the 4 feet minimum width although in the Route 140 Taunton-Lakeville section, it is wide enough to support the rumble strip. However, a four foot wide shoulder would provide a greater chance of recovering within the paved area. A rating of ‘C’ was assigned to this factor. The markings for the acceleration/deceleration lanes were found to be less than ideal and a rating of ‘D’ was assigned to this factor. Inadequate markings in the areas of the interchange including deteriorated markings or markings that result in the perception that lanes are not sufficiently long. A rating of ‘C’ was assigned for the factor related to MS Transportation Systems, Inc. Page 12 Route 140 Taunton-Lakeville Road Safety Audit exiting from the parking areas as it could result in inappropriate lane changing in the merge area although the general visibility along the highway in these areas is fairly good. This can influence the motorists behavior in a negative way resulting in “quick lane-changing”. The RSA team also noted the high speeds/driver behavior in the section as being a contributing factor to median entries and affecting the risk of crossmedian crashes. This factor was assigned a rating of ‘C’. Signage is also less than ideal relative to the Route 79 (or County Street) interchange, particularly in the southbound direction approaching the exit. Similar to the signage at the parking areas, this factor was rated a ‘B’. The last set of risk factors noted by the RSA team members familiar with the corridor was that this highway section is a notably dark corridor in the non-daylight hours. Without such items as adequate route delineation or advance guide signage, the dark route, which also has long, straight sections, can contribute to negative effect of driver fatigue (factor) and an increasing chance of run off road crashes. These factors were given a rating of ‘C’. Suggested actions identified are intended to reduce all crashes on the Route 140 and/or reduce the severity of the crashes were identified based on the specific issue. The following paragraphs include discussion pertaining to the issues and the potential actions to consider for implement. Given that this RSA program is focused on crossmedian crashes, median barriers were first evaluated. Additional actions are outlined later in the report. • Consideration of a Median Barrier One of the more significant actions to be considered is to install median barriers in the current “open” areas. A barrier can be considered when there is a higher than desirable chance or a greater risk for median cross-over crashes to occur and that have or could result in fatalities and/or a high proportion of injury related crashes. In addition, a barrier could be considered when the consequences or severity of a crash without a barrier are worse than if the barrier were in place. Factors that generally come into play in deciding on whether a median should be installed involve the following: High volumes and speeds Truck volumes and mix Narrow median MS Transportation Systems, Inc. History of cross-median crashes High risk of catastrophic event Page 13 Route 140 Taunton-Lakeville Road Safety Audit These items have been reviewed relative to the Route 140 section under study. Figure 7 presents a review of the corridor in relation to the median warrant criteria presented in the AASHTO RDG5. As can be seen in the diagram with the median width (as measured from edge line to edge line) is 100 feet and an estimated volume of 35,000 vehicles on an average day, the intersection of the two items is in the area of the chart where it is to the right of “barrier optional”. As shown in the chart, the intersecting point falls to the right of the chart “barrier optional”. In addition to the chart and related warrant criteria, which is a guideline, further consideration was given to the following: One-quarter of all the reported median entry crashes in the four (4) year analysis period were classified as cross-median. Most (83%) of the cross-median crashes resulted in personal injuries. A significant number of median related crashes were attributed in part to fatigue. Consequently, based on the above findings, the analysis of the data, the field drive-thru and discussion of the conditions by the RSA team members, it was suggested that a median barrier be considered for installation in the section of Route 140. The selection of the barrier is discussed in greater detail in the next section followed by the complete set of Route 140 RSA recommendations. A. Barrier Selection Once a decision is made to install a barrier, the type must be determined. There are a number of barrier types that can be considered in addressing the median cross-over crashes. These include the following: ♦ ♦ ♦ ♦ Weak post W-Beam Box Beam Generic Low Tension Cable High Tension Cable Barrier ♦ Strong post W-Beam ♦ Thrie Beam ♦ Concrete (Jersey) In deciding on the type of barrier, there are a number of criteria suggested in the AASHTO Roadside Design Guide. These criteria used in selecting a barrier type are listed in Table 5. 5 American Association of State Highway and Transportation Officials, Roadside Design Guide, Washington, D.C., 2002, Chapter 6 Update 2006. MS Transportation Systems, Inc. Page 14 80 AVERAGE DAILY TRAFFIC (thousands) 70 BARRIER RECOMMENDED 60 BARRIER CONSIDERED 50 median width 100 feet - ADT 35,000 40 30 BARRIER OPTIONAL 20 10 0 0 10 20 30 40 50 60 70 MEDIAN WIDTH (feet) SOURCE: AASHTO ROADSIDE DESIGN GUIDE CHAPTER 6 UPDATE Analysis of Median Barrier Warrant Route 140 Road Safety Audit Taunton-Lakeville, Massachusetts MS Transportation Systems, Inc. Framingham, Massachusetts Figure 7 Route 140 Taunton-Lakeville Road Safety Audit TABLE 5 CRITERIA FOR BARRIER SELECTION Criteria Comments 1. Performance Capability Barrier must be structurally able to contain and redirect design vehicle. Expected deflection of barrier should not exceed available deflection distance. Slope approaching the barrier and distance from traveled way may preclude use of some barrier types. 2. Deflection 3. Site Conditions 4. Compatibility 5. Cost 6. Maintenance A. Routine B. Collision C. Material Storage D. Simplicity 7. Aesthetics 8. Field Experience Barrier must be compatible with planned end anchor and capable of transitioning to other barrier systems (such as bridge railings). Standard barrier systems are relatively consistent in cost, but high-performance railings can cost significantly more. Few systems require a significant amount of routine maintenance. Generally, flexible or semi-rigid systems require significantly more maintenance after a collision than rigid or high-performance railings. The fewer different systems used, the fewer inventory items/storage space required. Simpler designs, besides costing less, are more likely to be reconstructed properly by field personnel. Occasionally, barrier aesthetics are an important consideration in selection. The performance and maintenance requirements of existing systems should be monitored to identify problems that could be lessened or eliminated by using a difference barrier type. Source: AASHTO, Roadside Design Guide, 2002, Chapter 5 Roadside Barriers. Based on extensive research and trials over the past five years, the high tension cable barrier system has become more prominent in the U.S. The cable (flexible) barrier has its advantages from a cost and aesthetic perspective, over the various guardrail systems or concrete barrier. The median slope and/or recovery area also affects the use and placement of any barrier including guardrail. In addition to the cable barrier systems, the alternative types of guardrail were reviewed for potential application on this route. Considerations included the volume of traffic, relative amount of truck traffic and travel speeds. Based on these, the most applicable types of guardrail for this route include the W-beam with strong post or the strong post thrie-beam. These rails are appropriate for high speed highways and high volumes with a relatively high proportion of truck traffic. Costs for each are somewhat similar though MS Transportation Systems, Inc. Page 16 Route 140 Taunton-Lakeville Road Safety Audit the thrie-beam has a higher cost. The weak post W-beam and box beam can be eliminated due to the slope and type of highway. The concrete barrier would generally be applicable in urban sections with limited median widths available. As a result of this review, it was determined that the median barrier options that are most valid for consideration for Route 140 in this section are the cable barrier and strong post guard rail. Maintenance issues are also an important consideration in decisions regarding median barrier installations. The maintenance issues that are of concern include: Barrier hits per mile Frequency of hits Cost recovery Cable downtime Repair effect on traffic Maintaining tension with cable system Mowing median Final selection of the barrier type should be based on the costs, physical condition of the median, the ability to maintain a recovery zone, likely maintenance or repair requirements, and compatibility with future planned pavement widening. In this case of Route 140 in Taunton-Lakeville, it appears that a barrier could be placed in the median leaving an adequate recovery zone and would have minimal effect on traffic if repair or maintenance is required. The key points of the cable barrier and guardrail systems are summarized below. Cable Barrier While the low tension generic cable system has been in existence for more than 50 years, most of the recent cable system research and installation is focused on the high tension systems. There are currently six (6) manufacturers with systems approved by the Federal Highway Administration (FHWA) for use under certain conditions. Research on these types of barriers is ongoing. There are 3-rope or 4-rope cable systems as shown in the following two photographs. This barrier type can be installed on slopes of 6:1 or flatter with little constraint on placement. There are certain systems (eg. Brifen and Gibraltor 4 rope) that have been approved for slopes as steep as 4:1 as of this writing. MS Transportation Systems, Inc. Page 17 Route 140 Taunton-Lakeville Road Safety Audit 4 – Rope Brifen System on I-495 3 Cable CASS System on Route 213 Guardrail The guardrail could be placed in the median where slopes are 10:1 or flatter as well as at the edge of a steep slope or where minimal recovery zones exist. With the guardrail placed within several feet of the pavement edge, a clear zone (or recovery area) would be eliminated at least on one side of the median if guardrail is applied on only one side of the median. In some locations where the topography of the median is fairly flat, it may be possible to install a single line of double faced barrier a greater distance from the pavement edge in this specific project area. Estimated per mile costs of the basic types of median barrier treatment to be considered for this route are summarized in Table 6. Shown in the table are estimated per mile costs of installing a cable barrier, a double faced W-beam guardrail and a double faced thrie-beam guardrail. As can be seen, the cable barrier is expected to be the lower cost option. The W-beam rail is a lower cost option compared to the thrie-beam, however, there is slightly greater deflection with the W-beam. TABLE 6 COMPARISON PER MILE COSTS Cable vs. Guardrail Costs/Mile Cable $144,000 W-beam $171,000 Thrie beam $213,000 For comparison, installing a Cable Barrier System in the 5.3 mile section east of Route 140 would cost approximately $763,200. The thrie-beam guardrail would cost approximately $1.13M. MS Transportation Systems, Inc. Page 18 Route 140 Taunton-Lakeville Road Safety Audit Recommendations As a result of the RSA analysis and team input, a set of recommendations have been identified and are summarized in Table 7. These actions are intended to reduce the chance of cross-median crashes, reduce the severity of all crashes and improve the overall safety condition of this section of Route 140 in Taunton and Lakeville. Identified in the table in addition to the risk factor and recommended action are the estimated costs and potential timeframe (i.e. short (0-1 year), medium (1-3 years) and long (>3 years)). The major recommendation for the Route 140 section in Taunton-Lakeville is to install a median barrier in the highway section under study. It is estimated that 5.3 miles of median barrier would be installed from immediately south of Stevens Street to the County Street interchange. The barrier should be placed close to the center of the median leaving a clear and adequate width for recovery. This action is estimated to be a medium-term action given the existing condition of the median and the length of barrier required. A preliminary estimate of cable barrier for this section is $763,200. TABLE 7 SUMMARY OF RECOMMENDATIONS Risk Factor Risk Rating Recommended Action Estimated Cost $763,2001 Estimated Timeframe Open, crossable median E Install barrier – approx. 5.3 miles medium term Inside shoulder is narrow C Widen shoulder TBD long term Markings for acceleration lanes were less than desirable D Modify markings – extend length of lanes TBD short term Rest area entry and exit – less than ideal warning or guidance C modify markings Add signs TBD $3,000 short term short term Speeding and driver behavior is significant in section C Increase enforcement TBD short term Southbound sign for Route 79 placement inadequate B Install additional sign ½ mile in advance of exit $3,000 medium term Dark, unlit corridor C Upgrade/install new reflector posts along median $11,000 short term Driver fatigue C Install electronic VMS signage TBD medium to long term 1) assumes cable barrier MS Transportation Systems, Inc. Page 19 Route 140 Taunton-Lakeville Road Safety Audit The inside shoulder was noted as being 1-2 feet width and is recommended to be widened. However, this is more of a long-term action that would be completed as part of the overall rehabilitation or resurfacing project was undertaken. Accomplished as part of a larger rehabilitation project results in a relatively small incremental cost. As part of that future work, the rumble strip would need to be reinstalled as well. The remaining recommendations represent relatively low cost, short term actions that can be taken to enhance awareness, guidance and better driver behavior in the section under study. These include: • Improving the markings for the acceleration-deceleration lanes. An example of the deceleration lane is shown in Figure 8 using dotted lines. These are low cost actions that can be done at the time of normal pavement marking maintenance. The current MUTCD depicts options with dotted lines for deceleration lanes. The upcoming revised MUTCD is expected to include dotted lines for acceleration lanes as well. • Installing or upgrading reflective in pavement markers and delineator posts along the route to alleviate the “darkness” sense and provide improved guidance to motorists. These are low cost actions. • Increasing the emphasis on consistent and high level police presence and speed enforcement. • Using electronic variable message signs (VMS) to inform motorists of roadway/traffic conditions and relevant safe driving information. Through the use of VMS, it may also assist in “breaking up” the monotony to the driver on this long, fairly straight and “dark” corridor. • Lastly, installing an additional sign in the southbound direction in relation to the exit for Route 79 (Myricks Street) to provide adequate, clear notice. MS Transportation Systems, Inc. Page 20 a-Parallel deceleration lane b-Tapered deceleration lane Neutral area Optional chevron markings Channelizing lines Theoretical gore point Channelizing lines Broken lane markings for one-half of full-width deceleration lane Optional dotted extension of lane line Legend Direction of travel Source: Based on MUTCD Figure 3B-8 Note: Conceptual illustration only Potential Pavement Markings - Off-Ramp Diverge Locations - Examples of Channelizing Line Applications for Exit Ramp Markings Route 140 Road Safety Audit Taunton-Lakeville, Massachusetts MS Transportation Systems, Inc. NOT TO SCALE Framingham, Massachusetts FIGURE 8 Route 140 Taunton-Lakeville Road Safety Audit Appendix • • • • MS Transportation Systems, Inc. RSA Meeting Agenda RSA Meeting Attendees Median Crash Diagram Crash Summary Data Page 22 Road Safety Audit Taunton/Lakeville – Route 140 Meeting Location: MassHighway District 5 Office 1000 County Street, Taunton Thursday, September 25, 2008 11:00 AM – 12:30 PM Type of meeting: Cross Median – Road Safety Audit Attendees: Invited Participants to Comprise a Multidisciplinary Team Please bring: Thoughts and Enthusiasm!! 11:00 AM Welcome and Introductions 11:15 AM Introduction to Road Safety Audits and Cross Median Crashes 11:30 AM Review of Site Specific Material • Crash Summary– provided in advance • Existing Geometries and Conditions • Video and Images 12:00 PM Completion of RSA • Identification of Safety Concerns – using RSA Prompt List as a guide • Identification of Possible Countermeasures 12:30 PM Adjourn for the Day – but the RSA has not ended Instructions for Participants: • Before attending the RSA on September 25th participants are encouraged to drive Route 140 in Taunton/Lakeville (Interchanges 9-10) and complete/consider elements on the RSA Prompt List with a focus on safety factors affecting cross median crashes. • All participants will be actively involved in the process throughout. Participants are encouraged to come with thoughts and ideas, but are reminded that the synergy that develops and respect for others’ opinions are key elements to the success of the overall RSA process. • After the initial RSA meeting, participants will be asked to comment and respond to the document materials to assure it is reflective of the RSA completed by the multidisciplinary team. ROAD SAFETY AUDIT MEETING Route 140 Taunton-Lakeville September 25, 2008 MassHighway District 5 Offices, Taunton MA Attendance List Name Agency/Dept. Email Bill Scully MS Transportation Systems, Inc. bscullyjr@mac.com Edward C. Feeney MHD edward.feeney@mhd.state.ma.us Erin K. Sullivan MSP Middleboro erin.sullivan@state.ma.us Xian Chen MHD xian.chen@mhd.state.ma.us Jessica Stanley MHD jessica.stanley@mhd.state.ma.us Lisa Schletzbaum MHD - Safety lisa.schletzbaum@mhd.state.ma.us Tim White FHWA timothy.a.white@fhwa.dot.gov Bonnie Polin MHD - Safety bonnie.polin@mhd.state.ma.us Timothy Kochan MHD - District 5 timothy.kochan@mhd.state.ma.us Jim Hadfield SRPEDD jhadfield@srpedd.org Jackie Schmidt SRPEDD jschmidt@srpedd.org Erin Kinahan MHD erin.kinahan@mhd.state.ma.us MS Transportation Systems, Inc. CT ST R EET T C IN M AI N ST R PR E EE ± Route 140 Median Crashes 1 2 TA U N T O N 3 " ) 10 YR KS S EE T LAKEVILLE BED R D ST R EE T FO R PAD EL F O M IC TR ) " ) " EET 140 79 BERKLEY TR DS 12 13 Crash IDs between 4 - 11 14 RO AD 15 HI GH LA ND 16 17 Legend Type of Median Crash 2004 - 2007 * Major Roads Cross Median, Non-Fatal Crash Interstate Median, Fatal Crash Principal Arterial Median, Non-Fatal Crash Minor Arterial Municipal Boundary Collector L AN D H OW RO A D * 2007 crash file has not yet been closed. 0.25 0.5 0.75 Miles 1 HO W LA TY 18 S TR EE T 19 EE T 20 ND RO AD FR E E T O W N S TR Local 0 CO UN 21 22 23 " ) 9 MASSACHUSETTS HIGHWAY SAFETY DIVISION CRASH SUMMARY ROADWAY: Rt. 140 STUDY PERIOD: NO. CITY: 1/1/2004 CRASH DAY CRASH NUMBER TO 12/31/2007 TIME OF DAY CRASH DATE Taunton / Lakeville LOCATION: South of Exit 10 TRAVEL LIGHT WEATHER ROAD REASON FOR VEHICLE MEDIAN OR CROSS DRIVER CONTRIBUTING CRASH DIRECTION CONDITION CONDITION SURFACE RUNNING OFF ROAD LEFT MOVEMENT MEDIAN CRASHES CAUSE SEVERITY 1 1927850 Tuesday 9:28 PM 04/05/05 NB Dark-Not lighted Clear Dry Vehicle 2 tried to pass vehicle 1 but drifted into it due to driver distraction; both vehicles spun out into the median Right travel lane into median Median Failure to keep in proper lane Non-Fatal Injury 2 1992868 Sunday 1:25 AM 09/18/05 NB Dark-Not lighted Cloudy Wet Vehicle was struck by an unknown passing vehicle causing the driver to spin out of control coming to rest in the median Left travel lane into median Median Driving too fast for conditions Non-Fatal Injury 3 1806112 Thursday 6:15 AM 04/29/04 NB Daylight Clear Dry Driver was passing another vehicle and hit it then spun out across the median ending in the SB right ditch NB left lane across median, across all SB lanes into right-hand ditch Cross Median Made an improper turn Non-Fatal Injury 4 2149220 Friday 2:00 AM 01/19/07 SB Dark-Not lighted Rain Wet Driver was on cell phone and drifted off the road to the left and then struck the left guardrail and spun across all SB lanes Right travel lane into median and guardrail Median Not reported Non-Fatal Injury 5 1928310 Friday 7:25 PM 06/17/05 SB Daylight Clear Dry Vehicle was passed on the right causing the driver to swerve and lose control and spin out into another car and then into the median Left travel lane into median Median No improper driving Non-Fatal Injury 6 2051337 Saturday 12:00 AM 03/25/06 SB Dark-Not lighted Sleet, hail Wet Driver fell asleep and drifted into the left guardrail then came to final rest in the median Left travel lane into median guardrail and into median Median Fatigued/Asleep Property Damage Only 7 1993306 Monday 9:40 AM 12/05/05 NB Daylight Cloudy Dry Driver lost control of vehicle for unknown reason and traveled across the median and across all SB lanes into SB right shoulder NB left travel lane across median, across all SB lanes into right-hand shoulder Cross Median Failure to keep in proper lane Non-Fatal Injury 8 2244137 Thursday 7:07 AM 08/16/07 NB Daylight Clear Dry Driver crossed the median for unknown reason and struck a vehicle traveling in SB left lane NB left travel lane across median into SB left travel lane Cross Median Not reported Non-Fatal Injury 9 2051299 Saturday 4:10 AM 03/11/06 SB Dark-Not lighted Clear Dry Driver fell asleep and entered median and traveled down the embankment onto Rt. 79 Left travel lane into median and down embankment Median Fatigued/Asleep Non-Fatal Injury 10 2249476 Friday 2:13 PM 11/09/07 SB Daylight Clear Dry Driver drifted onto the left rumble strip and over-corrected and then lost control of the vehicle and it went onto the median and rolled over Left travel lane into median Median Over-correcting/over-steering Fatal Injury 11 2016168 Tuesday 5:20 AM 01/03/06 NB Dark-Not lighted Snow Snow Driver lost control of slippery road and spun into the left guardrail Left travel lane into guardrail Median Driving too fast for conditions Property Damage Only 12 2095525 Thursday 6:45 PM 07/20/06 SB Daylight Clear Dry Driver hit rumble strip and over-corrected and eventually spun out into the median and rolled over and crossed all NB lanes SB left lane across median and across all NB lanes into right guardrail Cross Median Failure to keep in proper lane Non-Fatal Injury 13 2051368 Wednesday 2:31 AM 04/05/06 NB Dark-Not lighted Clear Dry Driver swerved to avoid a deer and entered the median and rolled over Left travel lane into median Median Failure to keep in proper lane Non-Fatal Injury 14 2067951 Sunday 7:32 AM 03/05/06 NB Daylight Clear Dry Driver swerved to avoid a deer and entered the median strip then lost control of the vehicle and spun across all NB lanes and flipped over Right travel lane into median Median Fatigued/Asleep Property Damage Only 15 1888848 Friday 11:20 PM 10/29/04 NB Dark-Not lighted Cloudy Dry Vehicle veered into median then back across all NB lanes into right shoulder Left travel lane into median then across all NB lanes Median Failure to keep in proper lane Property Damage Only 16 1889330 Friday 2:40 AM 11/19/04 NB Dark-Not lighted Clear Dry Driver was distracted or may have fallen asleep and the vehicle crossed the median and all SB lanes and struck a tree in the right shoulder NB right lane across median into SB right shoulder Cross Median Failure to keep in proper lane Property Damage Only 17 2132494 Thursday 7:47 AM 11/23/06 SB Daylight Rain/Cloudy Wet Driver moved left due to a close passing car and a tire went into the median causing the driver to lose control and vehicle struck trees Left travel lane into median Median Failure to keep in proper lane Non-Fatal Injury 18 1885808 Thursday 6:00 AM 01/27/05 SB Dark-Not lighted Snow Snow Driver lost control of vehicle due to conditions and entered the median and flipped over Left travel lane into median Median Driving too fast for conditions Non-Fatal Injury 19 2015892 Wednesday 2:21 PM 02/01/06 NB Daylight Cloudy Dry Vehicle was struck from behind causing it to spin out and come to rest in the median Right travel lane into median Median Followed too closely Property Damage Only 20 1993367 Saturday 8:20 AM 12/10/05 NB Daylight Clear Snow Driver lost control of vehicle while passing in the left lane and struck a tractor trailer then spun out into the median Left travel lane into median Median Driving too fast for conditions Property Damage Only 21 2228118 Monday 4:30 PM 06/25/07 SB Daylight Clear Dry Driver was attempting to avoid a vehicle that swerved into the lane and struck other vehicle and spun out in to median Left travel lane into median Median Not reported Property Damage Only 22 2225187 Friday 10:58 PM 06/22/07 SB Dark-Not lighted Clear Dry Driver was not paying attention and rear ended another vehicle and then veered across the median and across NB lanes to shoulder SB right travel lane across median across NB lanes into right shoulder Cross Median Not reported Non-Fatal Injury 23 2058028 Thursday 1:01 PM 04/20/06 SB Daylight Clear Dry Driver swerved to avoid unknown object in road and then lost control of the vehicle and slid into the median Left travel lane into median Median No improper driving Property Damage Only 24 2114326* Sunday 2:45 AM 10/01/06 NB Dark-Not lighted Clear Dry Driver went into the median for unknown reason and the vehicle rolled over several times Left travel lane into median Median Operating in erratic, reckless, aggressive manner Non-Fatal Injury * Could not be located LIGHT CONDITION TOTAL NO. WEATHER CONDITION DAYLIGHT DARK NOT LIGHTED CLEAR CLOUDY RAIN 24 12 12 15 4 2 3 100% 50% 50% 63% 17% 8% 13% DRY WET 17 4 3 71% 17% 13% MADE IMPROPER TURN NO IMPROPER DRIVING NOT REPORTED TOTAL NO. MEDIAN OR CROSS MEDIAN SNOW/SLEET ROAD SURFACE CRASH SEVERITY MEDIAN CROSS MEDIAN FATAL NON-FATAL INJURY PROPERTY DAMAGE ONLY 24 18 6 1 14 9 100% 75% 25% 4% 58% 38% TOTAL NO. FAILURE TO KEEP IN PROPER LANE SNOW/ ICE DRIVER CONTRIBUTING CAUSE FATIGUED/ASLEEP FOLLOWED TOO CLOSELY OVER-CORRECTING/ OVER- DRIVING TOO FAST STEERING FOR CONDITIONS OPERATING VEHICLE IN AN ERRATIC, CARELESS, AGGRESSIVE. MANNER 24 7 3 1 1 4 1 2 4 1 100% 29% 13% 4% 4% 17% 4% 8% 17% 4% 2007 CRASH INFORMATION IS NOT COMPLETE CRASH SUMMARY IS BASED ON CRASH REPORTS WITH STATE POLICE NARRATIVES