ROAD SAFETY AUDIT MAJOR HIGHWAY MEDIAN CROSS-OVER CRASHES ROUTE 213 METHUEN FINAL REPORT Prepared for Prepared by MS Transportation Systems, Inc. Framingham, Massachusetts May 2008 ROAD SAFETY AUDIT MAJOR HIGHWAY MEDIAN CROSS-OVER CRASHES ROUTE 213 METHUEN May 2008 Prepared for Massachusetts Highway Department Prepared by MS Transportation Systems, Inc. 300 Howard Street P.O. Box 967 Framingham, Massachusetts 01701 508-620-2832 508-620-6897 (fax) www.mstransportationsystemsinc.com TABLE OF CONTENTS Page Introduction 1 RSA Team RSA Process 4 4 RSA Field Audit 8 Analysis/Discussion 11 Summary of RSA Findings 15 Appendix 30 Agenda Prompt List Traffic Volume Data Cross-Over Crash Data Barrier “hit” Record FHWA Approval Letters Existing and Proposed route Survey Cross-Section Info Route 213 sign Replacement Project Sheets MS Transportation Systems, Inc. Page i Route 213 Methuen Median Cross-Over RSA Introduction Lane departure crashes are one of the primary fatal crash types in Massachusetts. The Commonwealth exceeds the national average for the proportion of fatal lane departure crashes and was designated a lead state in lane departure crashes by the American Association of State Highway and Transportation Officials (AASHTO). The Massachusetts Highway Department (MassHighway) conducted a study of the problem and found that during 2002-2004, lane departure crashes accounted for 25 percent of all injury crashes and nearly half, 46 percent, of all fatal crashes. As part of the effort in implementing Commonwealth’s Strategic Highway Safety Plan (SHSP) and specifically reducing lane departure crashes and the number of highway fatalities, MassHighway is completing a Road Safety Audit (RSA) Review Project focused on median crossing (or median cross-over) crashes on its major access controlled highways. Road Safety Audits are a formal safety performance examination on existing or future roadways by an independent audit team. These audits are being conducted to identify any roadway deficiencies that may exist and to recommend specific countermeasures that may be implemented to reduce median cross-over crashes and enhance overall safety along the highway. A RSA was conducted for the Route 213 Connector in Methuen as part of this project. This highway connects I-93 (Interchange No. 48) with I-495 (Interchange No. 47). While the entire route was reviewed, under particular focus was the roadway section between Interchange No. 5 with I-495 and the Route 213 Interchange No. 3 (Howe Street). This section had experienced a number of median cross-over crashes, over the past several years including a fatal crash. In December 2005, a quick action project in response to several cross-over crashes included installing a 3-strand cable median barrier on this portion of the road section in each direction. However, subsequent to the installation, a relatively large number of crashes (barrier-hits) have occurred in this section although the cross-over crashes were eliminated. The purpose of this Route 213 Methuen RSA is therefore, to evaluate both the recent installation of the median barrier as well as consider decisions for the remaining portions of the route. Exhibit 1 indicates the project location relative to the larger highway system while the aerial photographs shown on the subsequent two pages highlight the roadway sections under this examination. The recommendations contained in this report reflect the overall consent of the RSA team and do not necessarily reflect the official views of MassHighway. MS Transportation Systems, Inc. Page 1 Route 213 Methuen Median Cross-Over RSA MS Transportation Systems, Inc. Page 2 Route 213 Methuen Median Cross-Over RSA Int 4 Int 3 Int 1 Int 5 Int 2 Route 213 Connector RSA Project Area MS Transportation Systems, Inc. Page 3 Route 213 Methuen Median Cross-Over RSA RSA Team The following individuals participated in of the Route 213 Methuen Road Safety Audit: Brett Loosian, MHD District Maintenance Timothy White, FHWA Neil Boudreau, MHD Highway Safety David Phaneuf, MHD Boston Bonnie Polin, MHD Safety Management Unit Michael Galvin, MHD Boston Lisa Schletzbaum, MHD Safety Management Unit Major Kevin J. Kelly, Mass State Police John Gregg, MHD District Traffic Chris Neaves, MHD District Projects Frank Suszynski, MHD District Projects William J. Scully, MS Transportation Systems (RSA Consultant) RSA Process The general process outlined in the guideline1 was essentially followed although with some variation that are described in the following sections. Exhibit 2 presents the overall audit process that was contained in the guidelines. Data including summary crash records for the 2004-2007 period, four (4) detailed crash reports of cross-over crashes, and available record highway plans were obtained and reviewed by the RSA consultant. In addition, maintenance repair records related to the cable barrier since its installation were provided by MassHighway. Field visits were conducted by the RSA team members. A video was recorded while driving the roadway by the RSA Consultant. The site visits were completed prior to a RSA team meeting. • RSA Meeting A meeting was held on December 6, 2007 at the MassHighway District 4 Office. At the meeting, the RSA consultant provided a brief overview of the RSA purpose, a summary of the roadway section’s characteristics and results of the review to date. The RSA team listed previously was present at the meeting. Approximately half of the team members had conducted a field visit prior to the meeting. District personnel are very familiar with the route under study. The video record of the Route 213 Connector taken while driving the corridor was viewed. During and following the video, discussions related to the ongoing issues and possible solutions occurred. The RSA team provided input on the key items observed in the field and those items that were listed on the RSA Median Cross-Over Prompt List. Following the RSA meeting, the RSA consultant compiled the information, completed the analysis and circulated the draft report to team members. Members of the RSA team met again on April 6, 2008 to review the draft recommendation and discuss final barrier options and cost implications. 1 MS Transportation Systems, Inc., Road Safety Audits, Median Cross-Over Crashes, Audit Guidelines, Prepared for MassHighway, October 2007. MS Transportation Systems, Inc. Page 4 Route 213 Methuen Median Cross-Over RSA Step 1 Select Team interdisciplinary members 3-6 members ensure "fresh" look Step 2 Confirm with District RSA locations audit schedule coordinate TMPs, team Step 3 Research Background Material Step 6 Complete Audit Evaluation design criteria alignments visibility median characteristics shoulder/off-road conditions Step 7 Draft Audit Report crash reports as-built plans traffic data (volumes, speeds) photos, aerials be concise identify team members summarize problems/issues identify potential actions circulate to RSA team Step 8 Meeting with Agency discuss results and recommendations Step 4 Pre-Audit Meetings explain procedure review background material finalize field schedules review prompt list Step 9 Finish Report/Submit to Agency finalize the draft report and submit Step 5 Conduct Field Visits observe different conditions record site conditions photo log conduct drive-thrus use prompt list Source: MS Transportation Systems, Inc. Road Safety Audits, Median Cross-Over Crashes Audit Guidelines, October 2007 MS Transportation Systems, Inc. Exhibit 2 Road Safety Audit Process Median Cross-Over Crashes Page 5 Route 213 Methuen Median Cross-Over RSA • Analysis Procedures As previously indicated, the RSA analysis generally followed the procedure outlined in Exhibit 2 with some variations and took into consideration the methods published by the Federal Highway Administration2 and those included in training materials3. Tasks included: • Obtaining and reviewing crash and other traffic characteristic data and available record plans. • Conducting site reconnaissance and collecting a current record of condition via photos and video, • identify potential hazardous issues, and • Identify and evaluate potential actions to address the noted issues. While the steps shown in Exhibit 2 provided overall guidance, a number of variations were incorporated as the RSA was conducted. This was due in part to the project location being a high speed, high volume section of access controlled highway. With these characteristics, there are limited areas to safely stop and gather along the section without potentially hindering traffic flow or the safety of the RSA team. One difference was the number of people involved in the project. Rather than an RSA team of 3-6 as is generally recommended in the FHWA guidelines, it was felt that more people who were familiar with the highway section may provide critical input early on. Consequently, there were 12 people involved in the Route 213 RSA. With the team size and general character with the corridor, the team members who visited the site prior to the team meeting did so either individually or in small groups. A video recording of a drive-thru in both directions was collected by the RSA consultant and used at the meeting to review conditions. Since it was decided that there would not be stopping on the highway, a traffic control (TMP) was not required. Background material and plans were transmitted to the RSA consultant to compile and review prior to the initial RSA team meeting. Information was transmitted to RSA team members prior to the meeting as well. The meeting occurred after team members had visited the project site. Once the initial meeting was conducted, the RSA consultant gathered the input completed the analysis and prepared draft documents for team member review. Prior to finalizing the report, the RSA team met again to review and reach consent on the recommendations. 2 3 Federal Highway Administration, FHWA Road Safety Audit Guidelines, Publication No. FHWA SA-06-06, Washington, D.C., 2006. Federal Highway Administration, Resource Center, Road Safety Audits Mini-Workshop, Jeffrey Shaw, PE, PTOE, presented to New England ITE Section, September 19, 2006. MS Transportation Systems, Inc. Page 6 Route 213 Methuen Median Cross-Over RSA In assessing the issues identified by the RSA Team, the relative seriousness and potential risk relative to crash frequency and severity were determined. Using the guidelines of FHWA4 as input and with some adjustments for this specific RSA, the relative frequency criteria and severity criteria was identified and is presented in Table 1 and Table 2. TABLE 1 FREQUENCY RATING ESTIMATED Exposure high medium high medium low high Probability high high medium medium high low low medium low medium low low EXPECTED CRASH FREQUENCY (PER AUDIT ITEM) 5 or more crashes per year FREQUENCY RATING Frequent 1 to 4 crashes per year Occasional Less that 1 crash per year, but more than 1 crash every 5 years Infrequent Less than 1 crash every 5 years Rare TABLE 2 SEVERITY RATING Typical Crashes Expected (per audit item) Expected Crash Severity High-speed crashes; head on and rollover crashes Moderate-speed crashes; fixed object or off-road crashes Crashes involving medium to low speeds; lane changing or sideswipe crashes Crashes involving low to medium speeds; typical of rear-end or sideswipe crashes Probable fatality or incapacitating injury Moderate to severe injury Severity Rating Extreme High Minor to moderate injury Moderate Property damage only or minor injury Low Taking into consideration both frequency and severity, the relative risk of a particular audit item was rated. The risk ratings are shown in Table 3. For each safety issue identified, the potential seriousness of the issue as well as possible mitigation measures have been indicated. 4 Federal Highway Administration, Resource Center, Road Safety Audits Mini-Workshop, Jeffrey Shaw, PE, PTOE, presented to New England ITE Section, September 19, 2006. MS Transportation Systems, Inc. Page 7 Route 213 Methuen Median Cross-Over RSA TABLE 3 CRASH RISK ASSESSMENT Frequency Rating Low Frequent Occasional Infrequent Rare Crash Risk Ratings: C B A A Severity Rating Moderate High D C B A A: minimal risk level B: low risk level C: moderate risk level Extreme E D C B F E D C D: significant risk level E: high risk level F: extreme risk level RSA Field Audit Field visits were conducted by the RSA team members between November 29 and December 6, 2007. In general, the field visits included a number of “drive-thrus” in each direction noting physical conditions and the “feel” of the driver. The Prompt List developed as part of the RSA process was used as a guide. The prompt list for this specific study location is included in the appendix. The field visits showed the following in no order of importance: A 3-strand cable (straight line) barrier was put in place from I-495 (Exit 5) to Exit 3 on each side of the median. The cable is installed less than a few feet off pavement edge (maybe 1 foot+/-), The inside shoulder is about one to two feet in width with minimal offpavement leveling area provided (another 1 foot +/-) before a downslope begins. No rumble strip exists on the inside edge of the pavement. On the November 28, 2007 field visit, it was noted that there were 3 recent hits on the barrier in the WB direction and 4 hits in the EB direction. (subsequent visits showed that most repairs to these locations had been completed). One EB “hit” was noted in the field opposite the end of ramp/merge area from the Exit 3 EB on-ramp, Another EB “hit” was noted in the area just before the spilt for the I-495 north and south on ramps. MS Transportation Systems, Inc. Page 8 Route 213 Methuen Median Cross-Over RSA A rumble strip is in place on the outside shoulder in both directions. The median appears relatively narrow (i.e. 50 feet or less). (Plans were subsequently checked and verified a width between 40 and 50 feet). The median is depressed and grassed – there appears to be drainage structures in the center of the median (plans checked subsequently and verified drainage). The current pavement markings and surface are in good condition. Resurfacing within the past few years is apparent (this was later verified by Department). There is no recovery zone in the median of the road section between Exits 3 and 5. There is no barrier between Exits 1 and 3. This road section typically includes the same width median, grass and slope as in the section east of Interchange No. 3. A significant edge drop off along median, particularly in the westbound direction, was apparent west of Exit 3. Major exit guide signs for Interchange No. 4 indicate exits are in ½ mile (westbound) and 1/3 mile (eastbound between exits 3 and 4). There are no reflectors imbedded in the pavement for lane or edge markings. Reflectors are generally on cable barrier posts but not on every one. The following photographs illustrate some the conditions observed on Route 213 as part of this RSA. MS Transportation Systems, Inc. Page 9 Route 213 Methuen Median Cross-Over RSA Cable barrier installed just off pavement on both sides of median. Above is section of barrier that was struck in westbound direction in the vicinity of Interchange No. 3 (November 28, 2007). Cable barrier knockdown before Interchange No. 4 in eastbound direction (November 28, 2007). MS Transportation Systems, Inc. Page 10 Route 213 Methuen Median Cross-Over RSA Analysis/Discussion Once the plans and traffic data were obtained and the field visits and RSA meeting conducted, the RSA analysis was completed. The following paragraphs briefly summarize the information obtained during the RSA and the key items resulting from the analysis. The Route 213 Connector is approximately 17,000 feet in total length between I-93 and I-495. The median length under study is approximately 15,000 feet (approx. Station 30 to Station 180). The section between Interchange Nos. 3 (Howe Street) and 5 (I-495), where the cable barrier was previously installed, is approximately 7,500 feet long. The roadway which has two travel lanes per direction carries between 55,000 and 62,000 vehicles per day. Speeds are posted at 55 miles per hour (mph) although generally observed travel speeds appear to be in the range of 60 to 65 mph. In general, travel lanes are 12 feet in width. The inside shoulder is approximately one (1) foot in width while the outside shoulder is a full (8 to 10 feet) width. In addition to the two end points (I-93 and I-495), there are three full interchanges within approximately 2 miles. The distance between Interchange Nos. 3 and 4 is less than one-half mile. The existing depressed median ranges in width but is generally between 40 to 50 feet along much of its length. The median is open, grassed with slopes away from the pavement at slightly steeper slopes than 1:6. In general, a closed drainage system runs along the center of the median. The AASHTO guidelines5 include warrant criteria to determine if barrier installation should be considered in a particular location. The most current AASHTO guidelines for a median barrier installation are shown in Exhibit 3. The present guidelines show that a barrier in this location should be considered given the median width and volume levels 55,000 to 62,000 ADT on the Route 213 connector. The guidelines have been under examination as part of ongoing research. When the median barrier was not in place in the eastern section (between Exits 3 and 5), there were a number of cross-over crashes. At least three cross-over crashes occurred in this section between September 2004 and February 2005. These three were reported to have occurred in the vicinity of Exit 4 (Pleasant Valley Street). A fourth cross-over crash was reported in early 2006 without the specific location identified. Since the median barrier was installed in late 2005 between Exits 3 and 5, it has been assumed that this 4th crash occurred west of Exit 3. The detailed reports and narrative descriptions of the crashes are included in the Appendix. 5 American Association of State Highway and Transportation Officials, Roadside Design Guide, Washington, D.C., 2002, Chapter 6 Update 2006. MS Transportation Systems, Inc. Page 11 Route 213 Methuen Median Cross-Over RSA 80 AVERAGE DAILY TRAFFIC (thousands) 70 BARRIER RECOMMENDED 60 BARRIER CONSIDERED 50 40 BARRIER OPTIONAL 30 20 10 0 0 10 20 30 40 MEDIAN WIDTH (feet) MS Transportation Systems, Inc. 50 60 70 Exhibit 3 Median Barrier Criteria Roadside Design Guide Chapter 6 Update 2006 Page 12 Route 213 Methuen Median Cross-Over RSA Reasons provided by operators for crossing the median varied with no meaningful trends identified. Whatever the reason that was indicated by an operator for losing control, it does not take much to cross the median on Route 213 given the speeds and width of the median. In addition to being a high volume, high speed highway with a “narrow” median, a number of other characteristics are likely to also contribute to the safety conditions and crash experience that has occurred on the Connector. One noted characteristic is the close spacing of Interchanges Nos. 3 to 5. The close spacing influences the level of lane changing maneuvers and speed variations. The high tension cable system installed on Route 213 in late 2005 was the Trinity CASS TL-3 system between Interchanges No. 3 (Howe Street) and No. 5 (I-495). The cost for installation including the end treatments was $363,079.40. Of the total cost, $141,600 was for materials only. It was installed along both sides of the median in close proximity of the pavement edge (within 1-2 feet) due to the grades of the foreslope not meeting the 1:6 criteria. Posts for this installation were driven and set at 16 feet spacing. The installation of the median barrier in the eastern section has successfully eliminated the median cross-over crashes and reduced the severity of the crashes in this section of road. However, the placement of the barrier being within 1 to 2 feet of the pavement edge does not provide the errant motorist any forgiveness or chance to recover before striking the barrier. Several of the recent hits observed in the field visits have occurred in close proximity of the on-ramps and merge areas that are likely to be creating significant lane changing. The cable barriers are a flexible type of barrier in which motorists tend to not be redirected back onto the roadway but contained within the barrier with the expected maximum deflection will be between 11 to 12 feet. The cable barriers are typically installed as far away from the travel way as possible taking into account the total width of the median and the potential deflection. However, with the current barrier placement on Route 213 within one to two feet from the paved area, there is the distinct possibility of motorists protruding into the high speed lane once stopped as the inside shoulder is also 1 to 2 feet in width. In other words, a motorist that hits the barrier in its current location within a few feet of the paved area may not totally leave the travel way even with some deflection in the barrier. Again, while the barrier installation has virtually eliminated median cross-over crashes on Route 213, there has, been an increase in the total number of reported crashes on the roadway. Since the barrier was installed through November 2007, there were 47 recorded hits in approximately 2 years time based on maintenance records. Not all of these recorded maintenance hits have been reported as crashes. Some of the reports MS Transportation Systems, Inc. Page 13 Route 213 Methuen Median Cross-Over RSA had little information while one was identified as possible snowplow damage. The hits have affected in some cases a single post to as many as 18 posts and cable. Total costs for repairs including labor and materials for this nearly two year period was $68,970. The hits are occurring in both directions of travel. One area of concentration has been in close proximity of the Interchange No. 3 eastbound on-ramp. In this location, the acceleration lane may be somewhat short and quickly approaches the Interchange No. 4 eastbound deceleration lane. Other states that have utilized cable barriers have identified annual maintenance costs of approximately $7-10,000 per mile. According to officials with the Missouri DOT, these cost includes repair, traffic control and periodic re-tensioning. Converting the two year MassHighway repair costs for the Route 213 section that has the cable barrier in place to an annual dollar per mile ($24,285), shows that it significantly exceeds the experience in other States by more than double. It would appear that most of this can be attributed to the placement of the barrier in relation to the pavement and having a minimal width inside shoulder. Recent crash data (post-median barrier) indicates that the number of crashes are trending up on Route 213 from 2006 to 2007. The data does, however, show that most of the injury related crashes during this time period have occurred in the section west of Exit 3. As discussed above, one cross-over crash has been reported in 2006-2007. Finally, it was noted by the RSA team members that the crashes into the Route 213 barrier (average 23.5/year in both directions based on maintenance hit records) require the closure of the high speed lane for a period of time to repair the barrier largely due to its placement. With high volume levels experienced on Route 213, this can create problems for the repair team and significant congestion and delays to motorists and potentially affect the I-495 and/or I-93 operations. This issue becomes exacerbated with the high frequency of hits. MS Transportation Systems, Inc. Page 14 Route 213 Methuen Median Cross-Over RSA Summary of RSA Findings Based on the field review, the review of crash data and discussions among the RSA team members, the issues related to the safe operating conditions of the Route 213 Connector in Methuen were identified. While a positive action was taken in late 2005 by MassHighway by installing the barrier to eliminate cross-over crashes, the particular placement of the cable barrier has led to a new set of problems including higher crash frequency, high repair costs and motorists delays during repair periods. A number of items were identified as potentially contributing to safety issues although each with varied levels of seriousness. These major ones include: ¾ ¾ ¾ ¾ ¾ slope of median is steeper than 1:6, existing cable barrier too close to the pavement in the eastern section, narrow inside shoulder, no barrier in the western section of the Connector, and close spacing of interchanges affect lane changing. In addition to the above, the horizontal alignment in areas such as in the WB direction near Exit 2 felt somewhat uncomfortable in the “drive-thru”. The risk rating incorporated a qualitative assessment that considered the reported frequency of crashes, the potential severity of a crash if one occurs and a judgment of the risk level that a particular issue or deficiency could contribute to a vehicle leaving the travel lane, not being able to recover and then crossing the median. An overall summary listing of the issues identified as part of this RSA are shown in Table 4 along with the assigned risk rating and actions to consider. Suggested actions were identified that were intended to either improve upon actions previously taken, reduce all crashes on the Route 213 Connector and/or reduce the severity of the crashes were identified based on the specific issue. The following paragraphs include discussion pertaining to the issues and the potential actions to consider for implement. A. Route Section Summary • Route 213 Connector – West Section (between Exit 1 and 3) The west section does not presently have a barrier in place at this time as shown in the following photograph. The depressed median width in this section is generally between 40 and 50 feet similar to the eastern section. Recent survey data on the corridor shows the median grades to be slightly steeper than a 1:6 slope. In addition, it was noted that in this western section, there were several locations where a significant existing edge MS Transportation Systems, Inc. Page 15 Route 213 Methuen Median Cross-Over RSA TABLE 4 SUMMARY OF SAFETY ISSUES Safety Issue Risk Rating Preliminary Suggestions Narrow median with no barrier on western section E Cable barrier installed too close to pavement on eastern section (btwn Exits 3-5) E Remove existing barrier and reinstall further away from paved area Slope of median > 1: 6 – affects recovery along entire routes C-D One option is to add fill and regrade the existing median Narrow inside shoulder provided that affects warning and recovery potential D-E Provide a consistent inside shoulder of at least 2 feet in width Install rumble strip Consider a striped strip Install imbedded markers Inside edge has significant drop off on west section B Provide more fill and regrade consider installing the angled safety edge “quick” off to Exit 4 WB from I-495 C Provide additional advance warning to motorists exiting I-495 Inadequate warning of I-495 lane split affects lane change C Provide advance signage immediately after Exit 4 on-ramp with clear indication of lane usage Interchange spacing too close between exits 3 and 5 WB curve at Exit 2 feels uncomfortable and differential with EB section may affect opposing motorists C-D C Install cable barrier on west section Add safety warning signs Consider reduction in posted speed Improve delineation with posts, signage or markers drop off from the pavement existed. Combining the 1) lack of inside shoulder 2) the foreslope being steeper than 1:6 and 3) the edge drop off, the section has the high probability of an errant vehicle unable to recover safely. With the above noted conditions, the generally observed speeds (i.e. 60-65 mph) and the narrow median width (40-50 feet), the potential for median cross-over crashes is high. As noted previously, the reported cross-over crash discussed previously is presumed to have occurred in the west section as it was reported after the cable barrier had been installed in the eastern section. The crash report was not specific as to the exact location. In addition, the drive-thru in the westbound direction in the vicinity of Exit 2 felt slightly uncomfortable through the curve. This could be due to a number of factors including the combination of the curve radius, the amount of super-elevation in place, the differential MS Transportation Systems, Inc. Page 16 Route 213 Methuen Median Cross-Over RSA Median without barrier on western section of Route 213. in elevation between the eastbound and westbound surfaces and/or the level of motorist guidance through this section. Using the AASHTO recommended criteria for median barriers, the combination of route volumes and median width, a barrier is warranted as shown in Exhibit 4. However, there are other actions that could be considered as well, although the potential effect of each option will vary in its ability to prevent or reduce median cross-over crashes by themselves. The options for the west section include: Install median barrier in an appropriate location away from the pavement edge. Provide a consistent inside shoulder with a minimum of 2 feet (ideally 4 feet), Install rumble strip within the wider inside shoulder, Consider imbedded reflectors along the edge line, Flatten out the grade of the median to 1:6 or flatter, and Install delineators in westbound direction on curve near Interchange No. 2 MS Transportation Systems, Inc. Page 17 80 AVERAGE DAILY TRAFFIC (thousands) 70 BARRIER RECOMMENDED 60 BARRIER CONSIDERED 50 40 BARRIER OPTIONAL 30 20 10 0 0 10 20 30 40 50 60 70 MEDIAN WIDTH (feet) Median Barrier Warrant Analysis Route 213 Road Safety Audit Methuen, Massachusetts MS Transportation Systems, Inc. Framingham, Massachusetts Exhibit 4 Route 213 Methuen Median Cross-Over RSA • Route 213 Connector East Section (between Exit 3 and 5) In the east section, the surface and median conditions are similar to the western section. In response to a series of cross-over crashes that occurred in 2004 and 2005, cable median barriers were installed in this section. As noted previously, the barrier was installed on both sides of the median in close proximity to the pavement surface as the grade of the median was steeper than a 1:6 slope. However, the barrier placed within 2 feet of the pavement edge combined with a narrow shoulder has contributed to a high frequency of crashes and a greater level of repairs than would normally be expected. Given the characteristics of the eastern section of Route 213, the actions listed above for the west section would, therefore, also apply to the east section of the Connector with the existing barrier placement being modified to be further from the roadway. Some of the noted actions would be considered singularly while several would need to be combined. For example, for rumble strips to be installed on the inside shoulder, the shoulder needs to be widened to at least a consistent two (2) foot width, preferably four (4) feet. Installing a new barrier or relocating the existing barrier does not require widening the inside shoulder, though it may require regrading the slope of the median. In contrast to the western section, the eastern section of the Connector appears to experience more substantive issues related to lane changing and speed variation due to the close spacing of the three interchanges. Speeds are currently posted at 55 mph so further reduction doesn’t appear achievable nor be effective. Field drive-thru identified potential problems with inadequate advance warning to motorists and abrupt lane changes, both of which could contribute to lane departure crashes. Consequently, additional signage and other safety measures could be considered in addressing these issues. B. Barrier Selection In deciding on the type of barrier, recommended guidelines in selection are included in Table 5 taken from the AASHTO Roadside Design Guide6. The cable barrier that was installed in the east section of the Route 213 Connector is a Trinity CASS TL-3 cable system. This type of system has been used on medians that typically have a slope of 1:6 or flatter in addition to having sufficient width to accommodate the maximum deflection (approx. 12 feet) assuming posts set at 16 to 20 feet apart. Some states have installed similar systems on 1:5 slopes (Missouri) as well as locations with narrower medians but shorter post spacing (Rhode Island). 6 American Association of State Highway and Transportation Officials, Roadside Design Guide, Washington, D.C., 2002, Chapter 6 Update 2006. MS Transportation Systems, Inc. Page 19 Route 213 Methuen Median Cross-Over RSA TABLE 5 CRITERIA FOR BARRIER SELECTION Criteria Comments 1. Performance Capability Barrier must be structurally able to contain and redirect design vehicle. Expected deflection of barrier should not exceed available deflection distance. Slope approaching the barrier and distance from traveled way may preclude use of some barrier types. 2. Deflection 3. Site Conditions 4. Compatibility 5. Cost 6. Maintenance A. Routine B. Collision C. Material Storage D. Simplicity 7. Aesthetics 8. Field Experience Barrier must be compatible with planned end anchor and capable of transitioning to other barrier systems (such as bridge railings). Standard barrier systems are relatively consistent in cost, but high-performance railings can cost significantly more. Few systems require a significant amount of routine maintenance. Generally, flexible or semi-rigid systems require significantly more maintenance after a collision than rigid or high-performance railings. The fewer different systems used, the fewer inventory items/storage space required. Simpler designs, besides costing less, are more likely to be reconstructed properly by field personnel. Occasionally, barrier aesthetics are an important consideration in selection. The performance and maintenance requirements of existing systems should be monitored to identify problems that could be lessened or eliminated by using a difference barrier type. Source: AASHTO, Roadside Design Guide, 2002, Chapter 5 Roadside Barriers. The barrier currently installed on Route 213 includes driven posts spaced at 16 feet. As discussed by the RSA team7, there are a few cable barrier systems that have been developed and approved to date for slopes up to 1:4 with TL-3 ratings and certain placement criteria. From a cost and aesthetic perspective, the cable (flexible) barrier has its advantages over the various guardrail systems or concrete barrier. The median slope and/or recovery area also affects the use and placement of any barrier including guardrail. With regard to the cable barrier, the RSA team has discussed two primary cable alternatives noted below. In addition to the cable barrier systems, team members also suggested that guardrail be considered in the evaluation. The alternative types of guardrail were 7 Note: includes systems manufactured by Brifen and Gibraltor. MS Transportation Systems, Inc. Page 20 Route 213 Methuen Median Cross-Over RSA reviewed for potential application on this route. Considerations included the volume of traffic, relative amount of truck traffic and travel speeds. Based on these, the most applicable types of guardrail for this route include the W-beam with strong post or the strong post thrie-beam. These rails are appropriate for high speed highways and high volumes with a relatively high proportion of truck traffic. Costs for each are similar. Based on the high volume, high speed and narrowness of the median and inside shoulder, the strong post thrie-beam was selected as the preferred rail alternative for this project location. This type of rail for the median is also consistent with MassHighway practices along most of its major highways including the interstate system. Consequently, the barrier options being considered include the follow: ¾ Option 1 - Modifying the existing median grade to a flatter slope of 1:6 minimum from the paved area and reuse the existing Trinity CASS (TL-3) system installed in the eastern section. Only one barrier run would be re-installed and it would ideally be located in the more critical side of the median along its length. It is possible under this option to limit the regrading of the median to the one side where the barrier will be placed. ¾ Option 2 - Minimizing the work on the existing median and install the Brifen TL-4 4-rope Wire Rope Safety Fence (WRSF) or an equivalent8 barrier system that is approved for a 1:4 slope. This option would require removing the existing Trinity CASS cable barrier system in the east section and storing it until finding another location to reuse the material. ¾ Option 3 - The guardrail option to be considered for this study is the modified thrie-beam with strong posts. This rail can be installed within a few feet of the paved area due to its short deflection distance. Similar to Option 2, the existing cable barrier would be removed and stored. Given the median slope, a single line on one side of the median that uses double sided rail was selected under this option for analysis and comparative purposes. Alternatively, two runs of single side rail could be installed with higher costs than the single run double sided option assuming the same roadway sections were treated. In all options, the entire route is recommended to be addressed. For the purpose of this RSA, implementation has been assumed for the section between Station 30 and Station 180. The first option would require median work for approximately 15,000 feet but could 8 Note: Gibraltor manufacturers a similar cable barrier system. Both have been approved by FHWA for certain conditions. Approval letters are in the Appendix. MS Transportation Systems, Inc. Page 21 Route 213 Methuen Median Cross-Over RSA reuse the existing cable and posts currently in use in the eastern section. For analysis purposes, 13,000 feet of the cable and 20 terminal end sections were assumed to be reused in Option 1. Regardless of the options, all the existing cable in the eastern section would need to be removed. Option 1 would require an estimated additional 2,000 feet +/- of cable and an estimated five (5) additional end units. Under Option 1, modifying (regrading) the median is required at least on the one side where it is to be installed to provide a 1:6 slope. The initial cost estimate completed by the District assumed the entire median is addressed which is preferred by the District staff. The regrading effort could be reduced significantly from the initial estimate prepared by the District office if only the side of the median where the barrier would be placed is regraded. The current system includes driven posts. Sockets (or sleeves) could also be used for the posts. While the initial costs to install the posts with sleeves would be greater, the repair time and associated costs would be lower based on experience in other states. With a single line installed, the placement of the cable barrier with posts spaced at 16 feet could be approximately one foot from the center of the drainage ditch for the roadway. This would effectively be approximately 19 feet from the edge of pavement on the side the barrier is placed. This location would be expected to significantly reduce the number of “hits” and associated repairs. Order of magnitude costs for regrading the median along the entire length on both sides was originally estimated at $200,000. A more detailed cost estimate completed by District 4 staff confirmed this cost. Removing the existing barriers is estimated to cost $105,900 which would be similar under each option. The re-installation costs of the Trinity TL-3 barrier in new locations along the entire route are estimated at $236,000. This includes both the reuse of 13,000 feet of cable and posts and the estimated 2,000 feet of new cable and related posts. The total estimated cost for Option 1, including contingency costs (10%) is estimated to be $768,500. Option 2 makes use of the Brifen TL-4 4-rope Wire Rope Safety Fence (WRSF) system (or its equivalent) that has been approved for slopes of 1:4 and meeting the test level 3 (TL-3) criteria. Costs for the Brifen system based on recent MassHighway experience and a more detailed estimate completed by the District 4 staff are estimated at $868,600 including the 10% contingency. This option includes removal of the existing barrier system. The cost also includes drainage maintenance an improvements included in Option 1. One advantage of this system is that major work on flattening the median would be eliminated. In addition, the existing Trinity CASS TL-3 system could potentially be reused by MassHighway elsewhere in the State where the median slopes are flatter than the Methuen location at the current time. MS Transportation Systems, Inc. Page 22 Route 213 Methuen Median Cross-Over RSA According to the FHWA approval (see attached approval letter), using the Brifen system on a 4:1 slope requires it to be installed no further than four (4) feet down a slope steeper than 6:1 from its “break point” and no closer than 10 feet from the bottom of the drainage ditch. While the need to regrade the median is unnecessary under Option 2, it should be noted that its installation on slopes steeper than 6:1 is likely to require placement no more than 4 feet from the “break point” in slope moving away from the paved surface. Based on general conditions of Route 213, it is estimated that placement would be within approximately 6 feet from the existing edge of pavement. As such, maximum deflection of 6 feet is required. To achieve this, post spacing of a Brifen type system would be approximately 5 feet. With shorter post spacing, more posts are necessary. Whether posts are socketed or not, in its costs for this system will tend to be greater than the existing CASS system due to more posts and it is a 4 rope system. However, reusing the existing system will necessitate median grading work. One further note, if at sometime in the future the inside should is widened – the “break point” will likely shift and could require relocating the Brifen type system. The FHWA approval letter with the test details is in the Appendix. Cable barrier systems in general are less costly to install and maintain than rail systems, however, the existing Methuen barrier needs to be relocated to achieve this advantage. Other cited advantages of the cable barrier systems are the aesthetics as well as minimal visibility loss to a driver. A disadvantage of the barrier system when compared to the rail is that once hit, the cable section(s) need to be immediately repaired including redriven posts and retensioning. While the costs to install or reinstall the cable barrier systems is significant, there should also be a corresponding reduction in repair costs and congestion delay costs with better placement when compared to the current condition. This is due to the presumed lower frequency of barrier “hits” and times when travel lanes must be closed to accommodate the repairs time. The guardrail option (Option 3) would still require removal of the existing cable barrier but would not necessarily require modifying the median slope or require widening of the inside shoulder. The rail could be placed within a foot or two of the existing edge of pavement. The guardrail, in general, does potentially affect visibility, however, there should not be a negative effect on this route. A disadvantage in locations of high snow potential and being located in close proximity to pavement surface could be snow storage and its possible encroachment in the travel lane. Noted advantages of the guardrail is the minimum deflection expected and that the integrity and effectiveness of the rail is largely maintained even after being struck. This contrasts with the cable barrier which when hit must be repaired quickly. Vehicles would be redirected back into the travelway, but if not under control, this could potentially MS Transportation Systems, Inc. Page 23 Route 213 Methuen Median Cross-Over RSA result in a serious incident with the likelihood of injury or fatal consequences. If this occurs, the highway would be temporarily closed or at least reduced in throughput capacity for a period of time. The preliminary cost estimate to implement the guardrail is $990,000 including removing the existing cable and a 10% contingency fee. Table 6 summarizes the major installation elements of the barrier options including the estimated costs. TABLE 6 COMPARISON OF POTENTIAL BARRIER OPTIONS Preliminary Cost Estimates Option 1 CASS System with median regrading Work item Median work $198,000 Median drainage work Option 2 – 1:4 Approved type system– no median work $0 2 Option 3 Thrie-beam Guardrail $0 $91,000 $91,000 $105,000 $105,000 $105,000 Reinstall existing barrier $170,000 $0 $0 Install new barrier $66,000 $525,000 $695,000 Misc., safety controls $68,600 $68,600 $100,000 Contingency at 10% $69,900 $79,000 $90,000 $768,5001 $868,6003 $990,0003 Removal of existing barrier Total (rounded) $0 1 Assumes only half the median is regraded. 2 Drainage maintenance work can also be completed under Option 2 though is could be done as a separate project at another time. However, if it was going to be done, it would appear reasonable to do it when the barrier is being installed. 3 Note: the inventory value of the CASS system put in storage is estimated at (est. at $100,000). A planning level comparison of the three (3) barrier options is summarized in Table 7. Of the three barrier options, the two cable options appear to be more cost-effective compared to the guardrail with implementation costs estimated to be $175,000 or more lower than installing the guardrail. With better placement than exists today, the repair and routine maintenance costs of the cable barrier should not be a major factor compared to the guardrail. Based on several factors such as implementation timeframe, cost estimates, considering the width of the median, the FHWA approval guidelines and the future work on Route 213 that could include the shoulder widening, Option 1 appears to be the most appropriate barrier alternative for this specific location at this time. Option 1 is the recommendation of the RSA team. MS Transportation Systems, Inc. Page 24 Route 213 Methuen Median Cross-Over RSA TABLE 7 COMPARISON OF POTENTIAL BARRIER OPTIONS Criteria Option 1 CASS System with median regrading Option 2 – 1:4 Approved type – no median work Option 3 Thrie-beam Guardrail No work required No work required Cost requires modification $768,500 $868,600 $990,000 Maintenance minimal minimal moderate Routine periodic retensioning required immediately periodic retensioning required immediately placed no more than 4 feet from slope of breakpoint - 6-8 ft from edge of pavement periodic replacement of rail not likely needed immediately placed at 2 feet of pavement edge Median slope Repair Placement placed at 1 feet from center of drainage ditch – 19 ft off edge of pavement C. Non-Barrier Actions Non-barrier actions were also identified and examined consistent with the issues listed previously in Table 4. These types of actions beyond the barrier installation were identified and evaluated from an “enhance safety” perspective and/or to further reduce some of the crash types that have occurred. These additional actions are related to addressing deceleration lane movements and conflicts, and lane changing related crashes. They also are designed to improve visibility and overall guidance to motorists. The items and approximate costs of these actions are shown in Table 8. These actions are not all essential nor need to be all done at once if deemed appropriate. Most, if not all, actions are complimentary to the barrier installation. The most significant item in terms of costs would be the reconstruction and/or widening of the inside shoulder to obtain a consistent minimum width of two feet. It would consist of between 30,000 and 34,000 ft of road work (both directions). This action is not essential with the relocation and new installation of the cable barrier or installing the guardrail. Based on the available record plans it would in all likelihood be required in order to install rumble strips. A more thorough engineering evaluation including field survey would be recommended to determine the level of capability and reconstruction necessary. MS Transportation Systems, Inc. Page 25 Route 213 Methuen Median Cross-Over RSA TABLE 8 SUMMARY OF OTHER SUGGESTIONS FOR CONSIDERATION Notes Preliminary Estimated Cost Provide a consistent, two (2) foot $714,4001 Potential Action Improve, widen inside shoulder inside shoulder (4 foot desired) Install rumble strip on inside Requires wider inside shoulder $8,500 shoulder Construct angled safety edge Provides opportunity for errant Typically 1% to 2% vehicle to recover and re-enter of resurfacing cost roadway. Also, minimizes further erosion and edge raveling – short term action could add fill Install imbedded reflectors along Edge line: 1 every 20 feet $34,000 edge line and travel lane line Lane line: 1 every 35 feet $19,400 Install flexible delineators On curve in WB direction near Exit 2 – approximately 1,500 feet Advance warning of I-495 and “Pleasant Valley Street” exit $1,500 Add supplemental roadside guide signage (3 locations) Replace overhead guide sign at Station 161+60 Route 495 On-Ramp Lane Use sign on Route 213 EB just past the Exit 4 on-ramp – similar actions planned as part of MHD project $9,000 $7,600 1 – does not include concrete barrier during construction or other TMP related items, assumes box widening -34,000 ft. While rumble strips have been shown to be an effective safety tool, if the inside shoulder had to be widened to the fullest extent, then the cost-effectiveness at this time would come into question at this time. Particularly since the barrier installation along the full length of the corridor is intended to prevent the cross-over crashes. When the roadway is next scheduled for a major rehabilitation/reconstruction, the inside shoulder and rumble strip could be addressed at that time when a lower incremental unit cost would be expected. The angled safety edge is an action that would not prevent a vehicle from crossing the median, but would maintain the edge of the roadway so that an errant vehicle could potentially recover and re-enter the roadway. Research shows that an edge drop-off of 4 inches or more can create hazard and prevent a vehicle from recovering and reentering the roadway. The angled edge (at 30 degrees) provides a increased chance in a motorist recovering and re-entering the travel way. The technique is relatively new MS Transportation Systems, Inc. Page 26 Route 213 Methuen Median Cross-Over RSA and continues to be under evaluation. Its cost is relatively small as part of an overall construction or resurfacing project (guidelines9 suggest one to two percent of resurfacing project costs). The negative is that the edge must be done at the time of resurfacing and cannot be completed separately as a stand alone action. In the short term, an interim measure would be to add fill as part of regular maintenance of the route in the areas that the drop-off is excessive. The imbedded, reflectorized markers along the edge line is a relatively low cost ($34,000) action that could be accomplished within the existing shoulder area. The marker would provide enhanced guidance to motorists, particularly at night, along the edge which would be beneficial as the effectiveness of the reflectors in the cable posts will be significantly reduced when the cable is moved away from the pavement edge. An added item for the curve near Interchange No. 2 in the Westbound direction is to install flexible reflective delineators to provide more information to motorists. This would be for approximately 1,500 feet. It is estimated to cost $1,500. The final action relates to improved guide signage. These would be in relation to the Pleasant Valley interchange and the necessary lane designations on the approach to the I-495 on-ramps. The first sign would be an additional roadside sign on the I-495 westbound off-ramp to Route 213 providing earlier notice of the Exit 4 off-ramp. A second suggestion was to replace the existing overhead sign in the eastbound direction at Station 161+60 with a new sign that shows lane designations. The existing sign simply indicates I-495 is ½ mile away and does not provide adequate information to the motorist. By the time lane designations are shown or inferred by an existing overhead sign at 185+35, it is late in the decision process of the driver. The RSA Team became aware of a separate sign project planned for Route 213. Plans were obtained and specifically reviewed in relation to the issues identified in this Road Safety Audit. The proposed additional signs proposed for the section between Pleasant Valley Street (Interchange 4) and I-495 (Interchange 5) were determined to 1) be a substantial improvement over existing signage and 2) would address the issues identified. The sign sheets from the 100% Design Plans are included in the Appendix. Finally, two supplemental roadside signs should be considered in the eastbound direction prior to Interchange No. 3 (approx. between Stations 75+00 and 80+00) to provide greater advance warning. These would indicate: 1) “I-495 – 2 miles” and 2) “Pleasant Valley Street – Exit 4”. 9 Transportation Research Board, NCHRP Report 500, Volume 6: A Guide for Addressing Run-Off-Road Collisions, Washington, D.C., 2003. MS Transportation Systems, Inc. Page 27 Route 213 Methuen Median Cross-Over RSA D. Recommendations Based on a review of the issues, the potential actions and factors such as the ease of implementation, cost, the relative contribution to the identified problem and risk rating, a set of recommended actions were developed. These are shown in Table 9. TABLE 9 SUMMARY OF SAFETY ISSUES WITH RECOMMENDATIONS Risk Recommended Safety Issue Rating Actions Narrow median with no barrier on western section E Install cable barrier on west section High Cable barrier installed close to pavement on eastern section (between Exits 3-5) E Remove existing barrier and reinstall further away from paved area Slope of median > 1: 6 – effects recovery along entire routes C-D Add fill and regarded Narrow inside shoulder provided that affects warning and recovery potential D-E Inside edge has significant drop off on west section B “quick” off to Exit 4 WB from I-495 Inadequate warning of I-495 lane split affects lane change Interchange spacing too close between exits 3 and 5 WB curve at Exit 2 feels uncomfortable and differential with EB section may affect opposing motorists Estimated Timeframe Costs Short term $352,050 High Short term $416,450 High Short term included in above costs Program eventually reconstruction Install rumble strip Low Long term cost out at later date Install angled edge as part of reconstruction Low Long term cost out at later date when programmed C Add supplemental roadside sign High Short term low – part of separate sign contract C Replace existing overhead sign at Sta. 161+60 with lane designation sign High Short term low – part of separate sign contract C-D Add supplemental signage (2 roadsides) High Short term low – part of separate sign contract C Install imbedded markers along edge line – both directions – in this section and the entire route Install flexible delineators along length of curve Moderate to high Medium term – should be done when barrier relocated $34,000 Moderate Priority $1,500 Note: Costs do not include traffic control that may be necessary. MS Transportation Systems, Inc. Page 28 Route 213 Methuen Median Cross-Over RSA While a number of actions are identified as high priority, the most important is addressing the barrier. It is recommended the existing barrier installation be modified including relocated further from the pavement surface. It is further recommended that cable barrier be used rather than guardrail. In terms of barrier type, it is recommended that a cable barrier system be installed in the median along the connector’s entire length as discussed herein. This requires the existing barrier to be removed and reset. Following review of the options and more detailed review of construction costs as well as possible future improvements, the RSA team is recommending that for the Route 213 Connector project, the existing Trinity CASS system with driven posts be used. The use of this system will require re-grading the median to restore the original constructed slope of 6:1. The total estimated cost for this action is $768,500. Once the barrier is relocated on the eastern section, imbedded reflectors are recommended to be installed along the edge lines throughout the route in both directions as the barrier posts with reflectors would be well away from the roadway as well as downgrade. Flexible delineator posts are a cost-effective option to embedded reflectors for added guidance, particularly in the short term at a lower cost. Although it is recognized that cost-effective benefits result from the rumble strip installation, the inside shoulder must be fully addressed to accommodate the strip. Given the high cost of widening as a stand alone action, it is recommended that this widening and rumble strip be completed as part of a future (long term) overall reconstruction or rehabilitation project. The angled edge could be addressed at that time as well. The new or supplemental signage will be addressed by a separate sign project scheduled for 2008 or 2009. MS Transportation Systems, Inc. Page 29 Route 213 Methuen Median Cross-Over RSA Appendix ¾ ¾ ¾ ¾ ¾ ¾ ¾ RSA Meeting Agenda Prompt List Traffic Volume Data Cross-Over Crash Data Barrier “hit” Record FHWA Approval Letters Existing and Proposed Route Survey Cross-Section Information ¾ Route 213 Sign Replacement Project Sheets MS Transportation Systems, Inc. Page 30 MS Transportation Systems, Inc. RSA Meeting Agenda Road Safety Audit Methuen – Route 213 Meeting Location: MassHighway District 4 Office 519 Appleton Street, Arlington Thursday, December 6, 2007 10:00 AM – 12:00 PM Type of meeting: Cross Median – Road Safety Audit Attendees: Invited Participants to Comprise a Multidisciplinary Team Please bring: Thoughts and Enthusiasm!! 10:00 AM Welcome and Introductions 10:15 AM Introduction to Road Safety Audits and Cross Median Crashes 10:30 AM Review of Site Specific Material • Crash & Volume Summaries– provided in advance • Existing Geometries and Conditions • Video and Images 11:00 AM Completion of RSA • Identification of Safety Concerns – using RSA Prompt List as a guide • Identification of Possible Countermeasures 12:00 PM Adjourn for the Day – but the RSA has not ended Instructions for Participants: • Before attending the RSA on December 6th participants are encouraged to drive Route 213 in Methuen and complete/consider elements on the RSA Prompt List with a focus on safety factors affecting cross median crashes. • All participants will be actively involved in the process throughout. Participants are encouraged to come with thoughts and ideas, but are reminded that the synergy that develops and respect for others’ opinions are key elements to the success of the overall RSA process. • After the initial RSA meeting, participants will be asked to comment and respond to the document materials to assure it is reflective of the RSA completed by the multidisciplinary team. MS Transportation Systems, Inc. Prompt List MS Transportation Systems, Inc. Road Safety Audit Prompt List Lane Departure – Median Cross Over Incidents Route:__213________ Section ID:___________ Direction of Travel:_______________ Municipality:____Methuen_________________________________ Date of Field Audit:___11/29/07 & 12/04/07 RSA Manager:__W. Scully______________________ Prompt List Issues to be Considered General Topics What is the approximate length of section under study? 17,000 feet in total, approx 7,500 ft has barrier installed How many lanes in direction? 2 Are the general characteristics of the section generally consistent or do they vary? Does the alignment affect the "readability" or "feel" of alignment (i.e. driver recognition) by driver? Road Section Comments consistent in spots - near Exit 2 EB felt different Is crash location or specific area of concern on upgrade, downgrade or level area? Is crash area on an inside or outside of horizontal curve? varies - near on ramps and lane change areas Does superelevation exist in curve section? What is the differential (i.e. vertical dist.) between directional road sections, if any? Any noted drainage or ponding areas in section or crash area? Road Alignment and Cross Section Are there any sudden changes in the highway alignment that could affect the driver? How wide is inside shoulder? generallty little except near Exit 2 not noticeable no narrow - maybe 1 foot +/- What is the slope of the shoulder Does rumble strip exist in inside shoulder? Shoulders no How far is rumble strip from edge line and is this effective? n/a Are there drainage grates in shoulder? not generally , CBs were noted to exist more on ramps Does type or condition of drain stucture create driving hazard? Is there an edge drop off at median? How much in terms of inches? Speed What is the typical observed speed of drivers in that location? conditions not good in places - should have no effect on thru traffic between exists 1 & 3 high 60-65 mph Does typical speed in section "feel" comfortable to driver? How wide is median? less than 50 - old plans indicate close to 40 feet Is median depressed, flat or mounded? General topography should be noted. What is slope of depressed median? Medians slope appears greater than 1:6 Are there any scattered obstructions (i.e. trees, light poles) in the median? Is there any clear "flat" recovery area adjacent to shoulder? MassHighway depressed - slope appears greater than 1:6 no - drainage in center of median none between exits 3 and 5 Is clear zone or clear area too narrow to accommodate recovery? in theory - recovery area could accommodate between Exits 1 and 3 Can clear area or clear zone be widened? Or do constraints exist? no -currently limited by width of median, drainage system and locations of lanes RSA Major Highway Median Cross-Over Prompt List MS Transportation Systems, Inc. Road Safety Audit Prompt List Lane Departure – Median Cross Over Incidents Route:__213________ Section ID:___________ Direction of Travel:_______________ Municipality:____Methuen_________________________________ Date of Field Audit:___11/29/07 & 12/04/07 RSA Manager:__W. Scully______________________ Prompt List Issues to be Considered General Topics What guide signs exist indicating exit ahead? typical advance (1 mile) but 1/3 mile between Exits 3 and 4 Is the distance that these signs are installed from the exit adequate? Signage Is the sign legend clear/understandable to driver? not in every situation i.e. EB Exists 3 to 4, WB I495 to Exit 4) EB approach to I495 lane use - feels too late Are there any signs or items on the roadside that might distract the driver? Interchanges Comments not in every situation i.e. EB Exists 3 to 4, WB I495 to Exit 4) Are these signs/items unwarranted or unclear? Is the exit visible from a safe distance? Merging Is the merging distance long enough to merge properly? short between Exit 3 on ramp and Exit 4 off-ramp Does adequate deceleration lane in terms of length exist? Does merge-diverge area appear to negatively affect the driver movement in crash area? Are the lane and edge markings in adequate condition? Markings markings were adequate at time of field visit Do the travel lanes have the in pavement reflectors placed along the lane lines? If so, note condition. no Does the inside edge line have embedded reflectors? If so, note condition. no In areas of horizontal curves, are chevron warning signs or delineators in place? Signs Markings it may signs not needed, cable posts have reflectors on them and Is the signage in good condition? Signage yes Is the reflectivity in good condition? How is visibility at night? Are there any lights illuminating signage? no Are there any advance warning signs indicating you are approaching a curve? Are they aligned to be visible from a distance? Is the pavement surface in below average condition? Could it have contributed to crash? Physical Pavement Does the pavement surface drain adequately or are there areas of ponding? Are there changes in the surface type in area of crashes? Design Lighting surface condition is good no some change from inside shoulder to travel lane - doesn't appear to be significant Is the pavement section adequately skid resistant? Are there any light poles illuminating areas? no Are these lights working? n/a Would lighting be helpful in this location? Other MassHighway Do oncoming headlights affect motorist visibility? maybe near exit 2 RSA Major Highway Median Cross-Over Prompt List MS Transportation Systems, Inc. Traffic Volume Data Hourly Traffic Volumes - Route 213 Corridor in Methuen 213 West of I-495 (June 22, 2005) Start time 12:00 AM 1:00 AM 2:00 AM 3:00 AM 4:00 AM 5:00 AM 6:00 AM 7:00 AM 8:00 AM 9:00 AM 10:00 AM 11:00 AM 12:00 PM 1:00 PM 2:00 PM 3:00 PM 4:00 PM 5:00 PM 6:00 PM 7:00 PM 8:00 PM 9:00 PM 10:00 PM 11:00 PM 213 West of I- 213 West of I495 (June 22, 495 (June 22, 2005) - EB 2005) - WB TOTAL 274 210 484 159 148 307 104 79 183 91 81 172 161 149 310 538 567 1105 1510 1290 2800 1909 1997 3906 1768 2005 3773 1487 1691 3178 1465 1657 3122 1613 1753 3366 1750 1846 3596 1792 1749 3541 2036 1939 3975 2169 2474 4643 2400 2478 4878 2485 2499 4984 1877 2043 3920 1553 1578 3131 1488 1329 2817 1309 957 2266 798 641 1439 409 413 822 Daily Total 31145 31573 62718 213 West of Rte 28 August 21, 2006) 213 West of 213 West of Rte 28 Rte 28 (August 21, (August 21, Start time 2006) - EB 2006) - WB 12:00 AM 309 184 1:00 AM 209 134 2:00 AM 165 92 3:00 AM 164 109 4:00 AM 227 231 5:00 AM 577 874 6:00 AM 1348 1653 7:00 AM 1707 2401 8:00 AM 1688 2245 9:00 AM 1467 1610 10:00 AM 1416 1529 11:00 AM 1512 1515 12:00 PM 1652 1681 1:00 PM 1561 1817 2:00 PM 1878 1815 3:00 PM 2172 2117 4:00 PM 2647 2101 5:00 PM 2766 2265 6:00 PM 2138 1698 7:00 PM 1519 1423 8:00 PM 1233 1195 9:00 PM 1018 845 10:00 PM 737 561 11:00 PM 572 429 Daily Total 30682 30524 213 East of Rte 28 (June 20, 2007) TOTAL 493 343 257 273 458 1451 3001 4108 3933 3077 2945 3027 333 3378 3693 4289 4748 5031 3836 2942 2428 1863 1298 1001 61206 Start time 12:00 AM 1:00 AM 2:00 AM 3:00 AM 4:00 AM 5:00 AM 6:00 AM 7:00 AM 8:00 AM 9:00 AM 10:00 AM 11:00 AM 12:00 PM 1:00 PM 2:00 PM 3:00 PM 4:00 PM 5:00 PM 6:00 PM 7:00 PM 8:00 PM 9:00 PM 10:00 PM 11:00 PM Daily Total 213 East of 213 East of Rte 28 (June Rte 28 (June 20, 2007) - EB20, 2005) - WB TOTAL 245 206 451 146 144 290 111 90 201 96 96 192 188 200 388 587 735 1322 1405 1424 2829 1764 2224 3988 1719 2283 4002 1491 1856 3347 1613 1796 3409 1748 1813 3561 1840 1914 3754 1785 1875 3660 2042 2132 4174 2365 2342 4707 2733 2499 5232 2805 2552 5357 2215 1973 4188 1658 1676 3334 1471 1360 2831 1291 1075 2366 782 726 1508 456 434 890 32556 33425 65981 3000 2500 213 West of I-495 (June 22, 2005) - EB 213 West of I-495 June 22, 2005) - WB 213 West of Rte 28 (August 21, 2006) - EB 213 West of Rte 28 (August 21, 2006) - WB 213 East of Rte 28 (June 20, 2007) - EB 213 East of Rte 28 (June 20, 2007) - WB 2000 1500 1000 500 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 R.R. X-ING #STA. 5212 5021 5023 ROUTE/STR CITY/TOWN LOCATION RTE.213 RTE.213 RTE.213 Source: MHD route book METHUEN METHUEN METHUEN EAST OF RTE.28 WEST OF RTE.28 WEST OF RTE.I-495 1996 1997 1998 1999 2000 2001 2002 2003 50,500 2005 STA. 54,800 5212 5021 5023 56,600 50,300 43,800 2004 63,500 53,200 55,100 55,700 MS Transportation Systems, Inc. Cross-Over Crash Data RT 213 MEDIAN CRASH ANALYSIS FROM 2006 TO 2007 LIGHT CONDITION ALL CRASH TOTAL DARK - ROADWAY DAYLIGHT NOT LIGHTED 13 100% 9 4 69% 31% WEATHER CONDITION CLOUDY CLEAR RAIN NOT REPORTED 10 1 1 1 77% 8% 8% 8% ROAD SURFACE DRY WET 12 1 92% 8% DIRECTION OF TRAVEL WESTBOUND EASTBOUND 9 1 NOT REPORTED 3 69% 8% 23% MANNER OF COLLISION SINGLE VEHICLE SIDESWIPE CRASH SAME DIRECTION 12 1 92% 8% FIRST HARMFUL EVENT LOCATION SHOULDER MEDIAN ROADWAY NOT REPORTED UNPAVED 8 1 1 3 62% 8% 8% 23% FIRST HARMFUL EVENT MOTOR VEHICLE TREE GUARDRAIL MEDIAN BARRIER IN TRAFFIC 8 1 3 1 62% 8% 23% 8% DRIVER CONTRIBUTING CAUSE EXCEEDED AUTHORIZED FAILURE TO KEEP SPEED LIMIT IN PROPER LANE NOT REPORTED 1 1 11 7% 36% 36% CRASH SEVERITY PROPERTY DAMAGE NON-FATAL ONLY INJURY 7 5 1 54% 38% 8% NOT REPORTED AD RO CD 725 93 S B STA TE INT ER 1,450 ET 2,900 Feet MS TR E 2,175 HA EET ET P A LE SA R EE LA W R ST BE NT AL L TS RE T AC E ST RE R EET ET EAST S T NC K HI AY W H G RA MP METHUEN PLEASANT VALLEY STREET Route 213 2006-2007 Median Related Crashes BR AD EE D OA 0 PEL O EL R LR AI R ST W LAWRENCE 21 O RT 11 3 T Municipal Boundary Minor Arterial Principal Arterial Six of the thirteen crashes that were identified were able to be mapped. Crash years 2006 and 2007 have not yet been closed. Only represents crashes that were able to be located and those that involved running off the road left, crossing the median/centerline, or striking the median barrier. EE Interstate Major Roads Route 213 Median Barrier Installed Median Related Crashes Legend BT R ST 3W AN SW -R T ± 495 LO T RE RE 93 T NS SO LS T ER E AT ST CK ST R 495 STATE T IN INTE R S TR E E HO WE JA PA R K INT E TAT E RS ET Y WA T Included below are copies of the narratives from the State Police crash report forms. These four crashes all involved crossing the median into the opposing lanes which took place prior to the installation of the cable . September 26, 2004: VEH 1 TRAVELING ON RT 213 EAST AT UNKNOWN SPEED. FOR SOME UNKNOWN REASON, VEH 1 VEERED TO THE LEFT ACROSS THE MEDIAN, ACROSS THE WESTBOUND LANES OF RT 213 COMING TO REST UP AGAINST AN EMBANKMENT TO THE RIGHT OF THE BDL ON RT 213 EAST. WITNESS CALLED SP ANDOVER AND ADVISED THAT THE OPERATOR HAD EXITED THE VEHICLE, CLIMBED ON HIS HOOD, HOPPED OVER THE FENCE, AND FLED ON FOOT. A SEARCH OF THE AREA WAS NEGATIVE. NUMEROUS ATTEMPTS WERE MADE IN AN ATTEMPT TO CONTACT THE OWNER OF VEH 1. THE OWNER OF VEH 1 NEVER RESPONDED TO MY REQUESTS. DUE TO THE RELATIVELY MINOR DAMAGE TO VEH 1 AND THAT FACT THAT VEH 1 WAS REGISTERED IN NH, NO FURTHER ATTEMPT WAS MADE TO DETERMINE WHO WAS THE OPERATOR. CASE CLOSED. February 26, 2005 VEHICLE # 1 TRAVELING IN LEFT LANE OF ROUTE 213 WEST IN METHUEN. VEHICLE #2 TRAVELING IN RIGHT LANE OF ROUTE 213 EAST. VEHICLE #1 TRAVELING AT LEAST 85 MPH IN THE POSTED 55 MPH. VEHICLE #1 LOSES CONTROL AND SWERVES PARTIALLY INTO THE MEDIAN DUE TO THE EXCESSIVE SPEED. THE OPERATOR THEN SWERVED TO THE RIGHT AND REENTERED ROUTE 213 WEST. THE OPERATOR AGAIN LOST CONTROL AND SWERVED BACK TO THE LEFT, CROSSED THE GRASS MEDIAN, AND STRUCK VEHICLE #2. VEHICLE #1 STRUCK VEHICLE #2 WITH SUCH FORCE THAT VEHICLE 1 WAS COMPLETELY SPLIT IN HALF. THE FRONT END OF VEHICLE #1 CAME TO REST IN THE TRAVEL WAY, WHILE THE REAR END CAME TO REST IN THE MEDIAN. OPERATOR VEHICLE #1 REMOVED FROM THE VEHICLE BY METHUEN FIRE AND TRANSPORTED TO LAWRENCE GENERAL HOSPITAL. OPERATOR VEHICLE #2 TRANSPORTED TO HOLY FAMILY HOSPITAL WITH MINOR INJURIES. BOTH VEHICLES REMOVED BY MARTINEAU'S TOWING. OPERATOR VEHICLE #1 ISSUED CITATION M1010164 FOR OPERATING NEGLIGENTLY SO AS TO ENDANGER, MARKED LANES VIOLATION, AND SPEEDING. November 23, 2004 Vehicle #1 traveling in left lane of Rte 213 east bound at approximately 60 mph. Vehicle #2 traveling in right travel lane at operator stated speed of 65 mph. Operator of vehicle #2 is on her cell phone and loses control of her vehicle striking vehicle #1. Vehicle 31 subsequently travels into median area, rolls over and comes to final rest on its side in westbound lanes of traffic. Operator of vehicle #1 is ejected from vehicle and is found in median area. Vehicle #2 travels into median area and strikes drainage cover. Operator of vehicle #1 is transported to Lawrence General Hospital and then transferred to Beth Israel Hospital where he died during surgery. Tpr. Pultar of Accident Reconstruction and Analysis conducts Kinematics Analysis of accident scene. Operator of vehicle #2 is be cited for marked lanes 89-4A, speeding 90-17, impeded operation 90-13 and Negligent operation of motor vehicle resulting on death 90-24 G(b). *********Accident Reconstruction Report to follow********* January 6, 2006 VEHICLE 1 WAS TRAVELING IN THE LEFT TRAVEL LANE OF ROUTE 213 WEST IN METHUEN. VEHICLE 1 LOST CONTROL AND TRAVELED ACROSS THE MEDIAN AND THE TWO EASTBOUND LANES. VEHICLE 1 CAME TO A STOP AFTER STRIKING THE GUARDRAIL ON THE EASTBOUND SIDE. THE OPERATOR OF VEHICLE 1 SUFFERED MINOR INJURIES AND WAS TRANSPORTATED TO HOLY FAMILY HOSPITAL BY METHUEN FIRE/RESCUE. THE OPERATOR OF VEHICLE 1 STATED THAT AN UNKNOWN VEHICLE HAD CUT HER OFF, CAUSING THE CRASH. THERE WERE NO WITNESS’S TO THE CRASH. MSP COMPSTAT ROUTE 213 01/01/07 – 11/18/07 CRASHES ROUTE 213: Year-to-Date ROUTE: 213 213 213 E 213 N 213 S 213 W TOTAL 2006 1 5 20 1 2007 3 30 2 29 64 26 53 % CHANGE -100% -40% 50% -100% * 12% 21% CRASHES ROUTE 213: By Month MONTH Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov TOTAL 2006 8 6 1 10 4 6 3 5 1 5 4 53 2007 4 4 10 4 2 7 12 6 5 6 4 64 % CHANGE -50% -33% 900% -60% -50% 17% 300% 20% 400% 20% 0% 21% MSP COMPSTAT ROUTE 213 01/01/07 – 11/18/07 CRASHES ROUTE 213: SubClass by Year SUBCLASS Crash - MV PDO Crash - MV PI TOTAL 2006 42 11 53 2007 53 11 64 CRASHES ROUTE 213: Personal Injury Crashes DATE DAY TIME 11/13/2007 8/23/2007 7/18/2007 7/2/2007 6/6/2007 4/24/2007 4/3/2007 3/20/2007 3/9/2007 2/25/2007 2/4/2007 10/31/2006 10/8/2006 9/3/2006 6/12/2006 6/9/2006 4/9/2006 4/5/2006 4/1/2006 2/18/2006 2/2/2006 1/6/2006 Tue Thu Wed Mon Wed Tue Tue Tue Fri Sun Tue Tue Sun Sun Mon Fri Sun Wed Sat Sat Thu Fri 20:10 07:05 16:09 22:04 16:35 15:15 08:10 12:20 17:10 18:59 15:00 08:45 17:02 03:50 21:48 16:50 15:36 19:00 23:00 01:15 13:30 14:30 MANNER OF COLL NUMBER OF VEHS 4 2 1 2 2 1 1 1 2 2 2 1 1 2 1 1 1 1 1 1 1 1 1 1 ROUTE 213 E 213 W 213 E 213 W 213 W 213 E 213 W 213 E 213 W 213 E 213 E 213 213 213 213 E 213 E 213 W 213 W 213 E 213 W 213 W 213 W SUMMARY RT 213 East, Exit 2 RT 213 West, West of BROADWAY RT 213 East & RAMP - RT 213 EB TO RT 495 NB RT 213 West & INTERSTATE 93 RT 213 West &RAMP - RT 213 WB TO RT 93 SB RT 213 East, East of Exit 2 RT 213 West, at RT 93 RT 213 East, 0 of INTERSTATE 93 RT 213 West from 495N 213 East, Exit 4 213 East, Mile Marker Exit 2 213, 100 YD West of Exit 2 Route 213 under rt. 93 RT 213, North of RT 93 RT 213 E Exit 2 RT 213 E Intersecting HOWE ST RT 213 W RT 213 W RT 213 E Intersecting RT 113 213@ RAMP - RT 213 WB TO RT 93 NB: 213W: West Of: @ RAMP - RT 213 WB TO RT 28: 213W: Closest Reference: There is no data to indicate any of the above crashes involved head-on collisions or side-swipe opposite direction collisions. Crashes for which there is no collision data are primarily those at which the State Police assisted local police departments and therefore did not complete the crash report in RAMS. MSP COMPSTAT ROUTE 213 01/01/07 – 11/18/07 CRASHES ROUTE 213: Property Damage Crashes (No head-on or side-swipe opposite direction collisions) DATE DAY TIME 11/13/2007 11/12/2007 11/3/2007 10/28/2007 10/25/2007 10/12/2007 10/11/2007 10/8/2007 10/3/2007 9/28/2007 9/27/2007 9/19/2007 9/16/2007 9/14/2007 8/29/2007 8/21/2007 8/14/2007 8/14/2007 8/13/2007 7/25/2007 7/25/2007 7/23/2007 7/20/2007 7/16/2007 7/12/2007 7/6/2007 7/6/2007 7/2/2007 7/2/2007 6/29/2007 6/27/2007 6/22/2007 6/16/2007 6/3/2007 6/3/2007 5/9/2007 5/8/2007 4/17/2007 4/7/2007 3/30/2007 3/29/2007 3/28/2007 Tue Mon Sat Sun Thu Fri Thu Mon Wed Fri Thu Wed Sun Fri Wed Tue Tue Tue Mon Wed Wed Mon Fri Mon Thu Fri Fri Mon Mon Fri Wed Fri Sat Sun Sun Wed Tue Tue Sat Fri Thu Wed 10:20 11:16 18:35 16:20 14:15 13:10 14:58 03:35 09:04 13:45 11:00 18:00 08:44 06:45 15:00 15:22 18:00 19:07 21:30 19:25 02:00 13:33 23:35 16:10 08:20 10:50 07:30 07:58 18:01 23:35 17:19 21:10 12:51 01:00 18:45 12:22 22:06 17:40 10:53 18:48 14:55 12:46 MANNER OF COLL NUMBER OF VEHS 2 2 1 2 4 1 5 2 4 2 2 1 2 1 1 1 2 2 1 2 3 1 2 2 1 1 2 1 3 1 2 2 1 1 SUMMARY RT 213 East, To 495 NB RT 213 West, West of PLEASANT VALLEY ST RT 213 East & BROADWAY RT 213 East, @ the Loop RT 213 East & PLEASANT VALLEY ST RT 213 East, Ramp to Exit 4 RT 213 East, Exit 4 RT 213 West, PLEASANT VALLEY ST RAMP RT 213 West, @ Rte 28 RT 213 RT 213 East & PLEASANT VALLEY ST RT 213 E Exit 3, RT 213 East & RAMP - RT 213 EB TO RT 495 NB RT 213 East RT 213 East & BROADWAY RT 213 West & RAMP - RT 213 WB TO RT 93 SB RT 213, Ramp to 495N RT 213, Ramp to 495N RT 213 East RAMP TO 495 (N) RT 213 West & RAMP - RT 213 WB TO RT 93 SB RT 213 East, West of Exit 2 RT 213 East, Exit 4 RT 213 West, East of Exit 3 RT 213 West, East of Exit 3 RT 213 East RT 213 West & INTERSTATE 93 South RT 213 East Exit 3, RT 213 & RAMP - RT 213 WB TO HOWE ST RT 213 East, AT 495 RT 213 West & INTERSTATE 93 RT 213 East, 495 RT 213 West Howe St Ramp RT 213 West & INTERSTATE 93 RT 213 East West of Exit 113 RT 213 West, Ramp to 93 S RT 213 East & HOWE STREET RT 213 West & BROADWAY RT 213 East Exit 5, RT 213 East & INTERSTATE 93 RT 213 West Exit 4/ loop RT 213 West WEST OF RT 495 RT 213 West 3/22/2007 3/22/2007 3/20/2007 3/16/2007 3/9/2007 2/18/2007 2/15/2007 2/9/2007 1/24/2007 1/12/2007 1/1/2007 11/14/2006 11/12/2006 11/9/2006 11/1/2006 10/22/2006 10/21/2006 10/13/2006 8/31/2006 8/20/2006 8/20/2006 8/11/2006 8/11/2006 7/22/2006 7/11/2006 7/8/2006 6/23/2006 6/9/2006 6/3/2006 6/3/2006 5/24/2006 5/7/2006 5/5/2006 5/3/2006 4/29/2006 4/12/2006 4/9/2006 4/6/2006 4/5/2006 4/5/2006 4/4/2006 3/8/2006 2/26/2006 2/14/2006 2/13/2006 2/10/2006 1/28/2006 1/27/2006 1/26/2006 1/25/2006 1/25/2006 1/15/2006 1/9/2006 Thu Thu Tue Fri Fri Sun Thu Fri Wed Fri Mon Tue Sun Thu Wed Sun Sat Fri Thu Sun Sun Fri Fri Sat Tue Sat Fri Fri Sat Sat Wed Sun Fri Wed Sat Wed Sun Thu Wed Wed Tue Wed Sun Tue Mon Fri Sat Fri Thu Wed Wed Sun Mon 21:17 17:35 14:47 22:15 07:50 05:25 07:20 14:40 08:50 21:30 06:10 17:50 10:20 18:10 08:50 17:30 07:40 06:55 12:07 09:11 21:00 22:23 00:26 11:35 17:10 02:19 07:32 09:05 23:25 17:40 16:15 08:00 13:30 06:30 11:40 11:30 18:04 02:35 17:30 17:06 21:51 11:22 15:10 07:05 23:00 13:15 11:15 16:14 17:35 04:52 04:50 03:05 15:10 2 2 2 3 3 2 2 1 2 1 1 1 2 2 1 1 1 1 1 1 1 1 2 2 1 2 1 2 2 2 4 1 2 1 1 1 1 1 2 2 2 2 1 1 RT 213 West & RAMP - RT 213 WB TO RT 93 SB RT 213 West & INTERSTATE 93 RT 213 East & RAMP - RT 213 EB TO RT 495 NB RT 213 West, 3 RT 213 West, 1/4 East of Exit 2 213 West, WEST/ WEST OF RT495 213 South, West of Exit 4 213 West, East of exit 3 213 West, Exit 4/ Pleasant Valley Rte 213 South, North of Rte 213 RTE 213 East, Exit 3 Rte 213 EB Exit 4 Rt. 213, on ramp from 495 S 213 West, RT 28 RTE 213 East, Ramp to RTE 495 South ROUTE 213 RTE 213 East, Ramp from RTE 28 ROUTE 213 East, Exit 4 213 West, 1/4 mile East of Exit 3/ HOWE ST 213 West, East of Exit 3 Rte 213 EB Eeast of 495 ROUTE 213 East, West of I - 495 213 East, East of Exit 2 METHUEN: RT 213 W METHUEN: RT 213 W ramp to 93 S RT 213 East, PRIOR TO EXIT #4 METHUEN: RT 213 W METHUEN: RT 213 E METHUEN: RT 213 W NEAR HOWE ST. METHUEN: Intersection of Rt 213 and Rt 93 METHUEN: RT 213 E METHUEN: RT 213 W METHUEN: RT 213 W METHUEN: RT 213 W PRIOR TO EXIT 3 METHUEN: RT 213 W METHUEN: RT 213 W S Intersecting RT 93 METHUEN: RT 213 E METHUEN: RT 213 W METHUEN: RT 213 Intersection of RT 213 & RAMP - RT 213 W TO HOWE ST RT 213 W Intersecting RAMP - RT 213 EB TO RT 495 S RT 213 E METHUEN METHUEN: 213E: 213W: On/Off Ramp: @ RAMP - RT 213 W TO RT 93 N METHUEN: 213N: METHUEN: 213W: East Of: THE LOOP METHUEN: 213W: On/Off Ramp: RT 28 METHUEN: 213E: AT RT 93 RAMP METHUEN: 213W: East Of: @ BROADWAY: East of x-2 METHUEN: 213E: Closest Reference: @ INTERSTATE 93: 213 E: Closest Ref: @ RAMP - RT 213 E TO RT 495 S METHUEN: 213W: West Of: @ BROADWAY: 213E: On/Off Ramp: @ RAMP - RT 28 TO RT 213 EB MS Transportation Systems, Inc. Barrier “hit” Record MASSACHUSETTS HIGHWAY DEPARTMENT DISTRICT FOUR HIGH TENSION CABLE GUARDRAIL City/Town Route Direction Type/Description Application Post spacing Lengths Date of Installation Installed by: Number of Accident History: Accidents MHD Location No. 1 AccRec. A 2 3 4 AccRec. B AccRec. C EWO 1 - Loc 3 Methuen 213 EB & WB CASS/Trinity Highway Safety, Inc. both sides of 40' median 16' 6" O.C. 10 runs, 5 each direction, 3036' longest run Completed 12/22/05 (approx 1 1/2 weeks) DeLucca Fence Co., Inc. Cumulative Total Price Date: Scope: Location: Comment: Repair made by: Est. Price: Date: Scope: Location: Comment: Repair made by: Est. Price: Date: Scope: Location: Comment: Repair made by: Est. Price: Date: Scope: s:/d4/mnt/hwy mnt/guardrail/cable guardrail 12/16/05 approx. 3 several posts hit possible plow damage DeLucca Fence $ 700.00 $ 700.00 $ 1,500.00 $ 2,200.00 $ 200.00 $ 2,400.00 12/18/05 6 posts, 6 caps, 6 straps, 12 spacers, Re-tension cables vehicle hit - accident report DeLucca Fence 01/03/06 1 post (out of alignment) possible plow damage DeLucca Fence 02/26/06 1 post (10 caps, 20 spacers) Location: Comment: Repair made by: Price: 5 6 7 EWO 1 - Loc 2 EWO 1 - Loc 4 EWO 1 - Loc 6 Date: Scope: Location: Comment: Repair made by: Price: 04/01/06 9 posts (18 spacers, 9 caps) Route 213 East - 150' West of Exit 5A Operator Identified - M. Perry DeLucca Fence Date: Scope: Location: Comment: Repair made by: Price: 4/22/2006 (date reviewed) 8 posts (16 spacers,10 caps) Route 213 West - opposite Ramp from I-495 S no acc report DeLucca Fence Date: 4/27/2006 (date reviewed) 3 end posts, 3 line posts, 1 cable assembly (6 spacers, 3 caps) Route 213 East - 500' West of Exit 4 no acc report DeLucca Fence Scope: Location: Comment: Repair made by: Price: 8 9 EWO 1 - Loc 1 EWO 1 - Loc 5 Route 213 East - 1/4 mile West of Exit 4 Vehicle hit - accident report (winter conditions); Operator identified - J Quinlan DeLucca Fence Date: Scope: Location: Comment: Repair made by: Price: 4/27/2006 (date reviewed) 4 posts Route 213 West - 1/4 mile East of Exit 3 no acc report DeLucca Fence Date: Scope: Location: Comment: Repair made by: 05/03/06 4 line posts, 14 caps & straps, 28 spacers Route 213 West - 1/3 mile East to Exit 3 no acc report DeLucca Fence s:/d4/mnt/hwy mnt/guardrail/cable guardrail $ 1,000.00 $ 3,400.00 $ 1,200.00 $ 4,600.00 $ 4,500.00 $ 9,100.00 $ 1,200.00 $ 10,300.00 $ 1,000.00 $ 11,300.00 Price: 10 EWO 1 - Loc 7 Date: Scope: Location: Comment: Repair made by: Price: 11 12 13 14 15 EWO 1 - Loc 8 EWO 1 - Loc 9 EWO 1 - Loc 10 AccRec. D AccRec. E 1,000.00 $ 12,300.00 $ 4,500.00 $ 16,800.00 $ 1,000.00 $ 17,800.00 $ 1,000.00 $ 18,800.00 $ 1,000.00 $ 19,800.00 $ 2,000.00 $ 21,800.00 05/07/06 5 line posts (20 spacers, 10 caps), 4 terminal posts w/sail plate & 1 CRP upper post Route 213 West - 0.3 miles East of Exit 3 Operator Identified - G. Zuniga DeLucca Fence Date: Scope: Location: Comment: Repair made by: Price: 5/11/2006 (date reviewed) 1 line posts (12 spacers, 16 caps) Route 213 West - 400' East of Exit 3 no acc report DeLucca Fence Date: Scope: Location: Comment: Repair made by: Price: 5/24/2006 (date reviewed) 3 line posts (6 spacers, 3 caps) Route 213 West - 100' West of I-495 Overpass no acc report DeLucca Fence Date: Scope: Location: Comment: Repair made by: Price: 5/25/2006 (date reviewed) 3 line posts (6 spacers, 3 caps) Route 213 West - 1/2 mile East of Exit 3 no acc report DeLucca Fence Date: Scope: Location: Comment: Repair made by: Est. Price: 7/25/2006 (date reviewed) 10 line posts, 20 spacers, 14 caps & 12 straps Route 213 East - 300' West of Exit 4 Operator Identified - T. McDuffie DeLucca Fence Date: Scope: 10/12/2006 (date reviewed) 8 line posts, 16 spacers, 8 caps & straps s:/d4/mnt/hwy mnt/guardrail/cable guardrail $ 16 17 18 19 20 AccRec. F EWO 2 - Loc 1 W EWO 3 - Loc 2aW EWO 2 - Loc 2 W EWO 3 - Loc 2bW Location: Comment: Repair made by: Est. Price: Route 213 West - 0.25 Mile East of Exit 3 Operator identified - K. Stoddard DeLucca Fence Date: Scope: Location: Comment: Repair made by: Est. Price: 12/19/2006 (date reviewed) 6 line posts, 12 spacers, 6 caps & straps Route 213 East - 200' East of Exit 3 Operator identified - K. Toto DeLucca Fence Date: Scope: Location: Comment: Repair made by: Price: Date: Scope: Location: Comment: Repair made by: Price: Date: Scope: Location: Comment: Repair made by: Price: Date: Scope: Location: Comment: Repair made by: Price: s:/d4/mnt/hwy mnt/guardrail/cable guardrail $ 1,500.00 $ 23,300.00 $ 1,500.00 $ 24,800.00 $ 1,800.00 $ 26,600.00 $ 1,000.00 $ 27,600.00 $ 1,400.00 $ 29,000.00 1 post with soil plate Route 213 W - before Pleasant Valley O/P at Departure End Anchor Repair DeLucca Fence $ 750.00 $ 29,750.00 9 line posts & appurtenances Route 213 W - 150' West of I-495 Overpass No accident report DeLucca Fence 3 line posts & appurtenances Adjacent to EWO 2 - Loc 2 W DeLucca Fence 6 line posts & appurtenances Route 213 W - 600' West of I-495 Overpass DeLucca Fence 21 22 23 24 25 26 EWO 3 - Loc 2cW EWO 2 - Loc 3 W EWO 3 - Loc 3aW EWO 2 - Loc 4 W EWO 2 - Loc 1 E EWO 2 - Loc 2 E Date: Scope: Location: Comment: Repair made by: Price: Date: Scope: Location: Comment: Repair made by: Price: Date: Scope: Location: Comment: Repair made by: Price: Date: Scope: Location: Comment: Repair made by: Price: Date: Scope: Location: Comment: Repair made by: Price: Date: Scope: Location: Comment: s:/d4/mnt/hwy mnt/guardrail/cable guardrail 1 line post & appurtenances Route 213 W - 0.25 miles East of Exit 4 O/P Also Known as Loc 5W DeLucca Fence $ 425.00 $ 30,175.00 $ 1,200.00 $ 31,375.00 $ 900.00 $ 32,275.00 $ 1,200.00 $ 33,475.00 $ 1,900.00 $ 35,375.00 3 line posts & appurtenances Route 213 W - 150' West of Exit 4 Overpass DeLucca Fence 4 line posts & appurtenances Adjacent to EWO 2 - Loc 3 W DeLucca Fence 4 line posts & appurtenances Route 213 W - 300' East of Howe Street Overpass DeLucca Fence 1 line post & appurtenances Route 213 E - Beginning of Howe Street Overpass DeLucca Fence 5 line posts & appurtenances Route 213 E - 0.30 Mile East of Exit 3 Repair made by: Price: 27 28 29 30 EWO 2 - Loc 3 E EWO 2 - Loc 4 E EWO 2 - Loc 5 E EWO 2 - Loc 6 E Date: Scope: Location: Comment: Repair made by: Price: Date: Scope: Location: Comment: Repair made by: Price: Date: Scope: Location: Comment: Repair made by: Price: Date: Scope: Location: Comment: Repair made by: Price: 31 32 EWO 3 - Loc 6W Loc 8W Date: Scope: Location: Comment: Repair made by: Price: Date: s:/d4/mnt/hwy mnt/guardrail/cable guardrail DeLucca Fence $ 1,400.00 $ 36,775.00 $ 2,300.00 $ 39,075.00 $ 750.00 $ 39,825.00 $ 850.00 $ 40,675.00 $ 3,560.00 $ 44,235.00 2,400.00 $ 46,635.00 9 line posts & appurtenances Route 213 E - 1/4 Mile West of Exit 4 DeLucca Fence Reset Top Cable & incidental work Route 213 E - 150' West of Exit 4 DeLucca Fence 2 line posts & appurtenances Route 213 E - 150' East of Pleasant Valley Street O/P DeLucca Fence 7/25/2006 (date reviewed) 18 line posts, 36 spacers, 18 straps & caps Route 213 E - 0.30 Mile West of Exit 4 ARP forwarded this repair to Contract for payment. Price is reflective of AccRec Bid DeLucca Fence 04/10/07 13 line posts & appurtenances Route 213 West - West of Ex 4 Off ramp & East of Ex 4 O/P DeLucca Fence $ Scope: Location: Comment: Repair made by: Est. Price: 33 34 35 36 37 Loc 9W EWO 3 - Loc 7E EWO 3 - Loc 8E EWO 3 - Loc 9E EWO 3 - Loc 10E Date: Scope: Location: Comment: Repair made by: Est. Price: Date: Scope: Location: Comment: Repair made by: Price: Date: Scope: Location: Comment: Repair made by: Price: 6 posts w-soil plates, 14 line posts & appurtenances Route 213 W - West of Exit 4 O/P Through Accident Recovery DeLucca Fence 4,000.00 $ 50,635.00 $ 1,000.00 $ 51,635.00 $ 425.00 $ 52,060.00 $ 510.00 $ 52,570.00 $ 900.00 $ 53,470.00 $ 600.00 $ 54,070.00 3 line posts & appurtenances Route 213 W - West of Exit 4 O/P Through Accident Recovery DeLucca Fence 1 line post & appurtenances Route 213 E @ Exit 4 O/P DeLucca Fence 1 line post & appurtenances Route 213 E - East of Exit 4 O/P DeLucca Fence Date: Scope: Location: Comment: Repair made by: Price: 03/23/07 3 line posts & appurtenances Route 213 E - West of Route 113 Bridge Also Known as Loc 7 W DeLucca Fence Date: Scope: Location: Comment: Repair made by: Price 04/04/07 3 line posts & appurtenances Route 213 E - West of I-495 O/P s:/d4/mnt/hwy mnt/guardrail/cable guardrail $ DeLucca Fence 38 Run II WB "A" Date: EWO 4 - Loc 1 Scope: Location: Comment: Repair made by: Price: 39 40 Run II WB "B" Date: EWO 4 - Loc 2 Scope: 4-DEL-7914 Location: Comment: Repair made by: Price: Run III EB "A" Date: EWO 4 - Loc 5 Scope: Location: Comment: Repair made by: Price: 41 Run III EB "B" Date: EWO 4 - Loc 7 Scope: Location: Comment: s:/d4/mnt/hwy mnt/guardrail/cable guardrail 7/24/2007, 9/21/07, 11/15/07 6 Complete Post Assemblies (w-1 Reflectorized Cap) & 1 additional Reflectorized cap From Guide Sign "Route 213 Ends 1-1/2 Mile" to Loop Connector Overpass (Buglione Memorial Bridge); Approximately 200-Ft West of the Start of Run Scoped by CJL, DAMAGED 3 TIMES DeLucca Fence $ 1,400.00 $ 55,470.00 $ 1,800.00 $ 57,270.00 $ 425.00 $ 57,695.00 07/24/07 9 Complete Post Assemblies (w-2 Reflectorized Caps) & 3 additional spacers From Guide Sign "Route 213 Ends 1-1/2 Mile" to Loop Connector Overpass (Buglione Memorial Bridge); Approximately 100-Ft West of Overhead Sign "Exit 3 1/2 Mile" Scoped by CJL, Follow-Up with ARP DeLucca Fence 07/24/07 1 Complete Post Assembly (w- Black Cap) & 1 additional Reflectorized cap. From Loop Connector Overpass (Buglione Memorial Bridge) to Pleasant Valley Street Overpass (@ MM 3.382); Approximately 350-Ft East of Start of run Scoped by CJL DeLucca Fence 07/24/07 5 Complete Post Assemblies (w-2 Reflectorized Caps) & 3 additional spacers From Loop Connector Overpass (Buglione Memorial Bridge) to Pleasant Valley Street Overpass (@ MM 3.382); Approximately 250-Ft West of End of run Scoped by CJL 42 Run V EB "A" Repair made by: Price: DeLucca Fence Date: Scope: 07/24/07 1 Complete Post Assembly w-Reflectorized Cap From Turn-Around to I-495 Overpass; Immediately West of End of run Scoped by CJL NOT REPAIRED Location: Comment: Repair made by: Price: 43 Run I EB "A" EWO 4 - Loc 4 Date: Scope: Location: Comment: Repair made by: Price: 44 Run III EB "C" EWO 4 - Loc 6 Date: Scope: Location: Comment: Repair made by: Price: 46 Run IV EB - Loc A Date: Scope: Location: Comment: Repair made by: Price: 47 Run II WB "C" Date: s:/d4/mnt/hwy mnt/guardrail/cable guardrail $ 1,100.00 $ 58,795.00 $ - $ 58,795.00 $ 950.00 $ 59,745.00 $ 950.00 $ 60,695.00 $ - $ 60,695.00 10/15/07 4 Complete Post Assemblies & appurtenances From Howe Street Overpass (@ MM 2.09) to Guide Sign "Route 213 Ends 1-1/2 Mile;" 400-Ft East of Howe Street Overpass Scoped by DFC DeLucca Fence 09/12/07 2 Complete Post Assemblies & 3 Additionals Caps From Loop Connector Overpass (Buglione Memorial Bridge) to Pleasant Valley Street Overpass (@ MM 3.382); Approximately 800-East of Start of Run Scoped by CJL DeLucca Fence 10/28/07 6 Complete Post Assemblies & appurtenances, Splice cable, Retension & related work From Pleasant Valley Street Overpass (@ MM 3.382) to Turn-Around; 300-Ft East of Pleasant Valley Overpass Scoped by JMF Emergency Repair - DeLucca Fence through ARP 11/15/07 EWO 4 - Loc 3 Scope: Location: Comment: Repair made by: Price: M 5 Complete Post Assemblies & appurtenances From Guide Sign "Route 213 Ends 1-1/2 Mile" to Loop Connector Overpass (Buglione Memorial Bridge) - 100' West of "Exit 3 - 1/2 Mile" OHS Scoped by DFC DeLucca Fence ESTIMATED TRAFFIC CONTROL COSTS FOR REPAIR COSTS ACC REC A Assume 1 MSP Detail = 320.00 ACC REC B 2 Arrows @ $25.00 Each Day = 50.00 ACC REC C 3 Signs (16 SF Each) @ 20.00 (split over 6 trips) = 120 ACC REC D 1 Safety Setup = $110.00 ACC REC E Total = $ 600.00 ACC REC F EWO 1 EWO 2 EWO 3 EWO 4 s:/d4/mnt/hwy mnt/guardrail/cable guardrail $ 1,100.00 $ 61,795.00 $ $ $ $ $ $ $ $ $ $ 600.00 600.00 600.00 600.00 600.00 600.00 1,500.00 625.00 625.00 825.00 $ $ $ $ $ $ $ $ $ $ 62,395.00 62,995.00 63,595.00 64,195.00 64,795.00 65,395.00 66,895.00 67,520.00 68,145.00 68,970.00 $ 7,175.00 MS Transportation Systems, Inc. FHWA Approval Letters Memorandum INFORMATION: Cable Barrier Considerations Date: July 20, 2007 From: Jeffrey A. Lindley Associate Administrator In Reply Refer To: HSSD To: Division Administrators Subject: Cable roadside and median barriers may be the most versatile and forgiving barrier systems available for reducing the severity of run-off-road crashes. However with growing use of cable barrier systems over the last decade the increasing variations in the number of cables, cable heights, post spacing, cable pre-stretch, cable tensioning, slope placement, length between anchorages, placement on curves, soil conditions/footing design, and other factors have led to confusion. This memorandum addresses these issues and, although it does not contain all the answers, it offers points to consider when dealing with these issues. It also discusses recently completed research as well as ongoing work that will lead to objective guidance for cable barrier design and placement. An attachment to this memorandum provides links to Web sites with additional cable barrier information. It should be noted that crash testing of any roadside features to the NCHRP Report 350 criteria and the subsequent FHWA acceptance is only a starting point when specifying hardware. Highway agencies should be selective in their choice of hardware and carefully review the FHWA acceptance letters for conditions and cautions that they should consider when designing roadside features. The AASHTO Roadside Design Guide is also a source of information that designers should use to help select and design barrier installations. The FHWA acceptance letters on cable barrier systems may be seen on our Web site at: http://safety.fhwa.dot.gov/roadway_dept/road_hardware/longbarriers.htm. In the drop-down menu select Cable Barrier and click on “Search by Keyword.” Number of Cables and Cable Height: The original US generic three-cable system has been joined by proprietary systems with three and four cables. The additional cable on proprietary systems either enhances TL-3 performance or, if used to increase the overall height of the barrier, can allow for TL-4 performance. The Web site referenced above can be used to identify systems by test level as well as by number of cables. Four cable systems should use an end anchor which provides for a separate anchor connection for each cable, or that has 2 been crash tested at the trailing end. Recent research by the National Crash Analysis Center (NCAC) has shown that adding a fourth cable to the generic three-cable design increases the likelihood that the cable barrier will catch a broader spectrum of vehicles (ref 1). It should be noted that there is a variety of spacings across the various cable barrier system designs. Current efforts are considering whether these spacings will be adequate to accommodate the larger pick-up truck defined in the proposed update to NCHRP Report 350 (ref 2). Post Spacing: Cable barrier systems have been tested and accepted with post spacing ranging from 6.5 feet to 32.5 feet. In general, deflection distance is known to increase with longer spacing between posts. What is not known, but strongly suspected, is that longer post spacing may also affect the propensity for vehicles to penetrate the cable barrier, i.e., by underride or traveling between cables. The FHWA recommends that highway agencies specify the post spacing when cable barrier systems are bid. The conventional range for cable post spacing is 6.5 to 15 feet. High Tension Cable Systems: Tensioning the cables after installation improves the performance of the system by reducing deflection and increasing the potential to capture the impacting vehicle. In high tension systems, cables are tensioned on the order of 5 times greater than in conventional cable systems. Performance problems have been noted when anchor blocks have been too small to accommodate the increased load. Sometimes this does not become apparent until cooler weather further increases the tension to the point where anchor blocks or individual post foundations are pulled out of the ground. Specifications should be included and followed that provide for anchor block masses adequate to accommodate the expected loads. The installation temperature is also a critical factor. Highway agencies should specify a minimum tension at a discreet installation temperature, and plan follow up inspections to ensure the desired tension is maintained. If possible, the temperature of the cable itself, rather than the ambient temperature, should be specified. Cable Pre-Stretch: Pre-stretched cables have advantages including reduced dynamic deflection by reducing the “play” between the individual wire strands in the bundle that forms the cable prior to installation. Slope Placement: The effectiveness of a cable barrier system is influenced by its placement on the side slope and the directions from which it can be hit. Some agencies have placed cable barriers on slopes as steep as 1V:4H if within 4 feet of the break point and others have considered it possible to place the cable barrier anywhere on roadside slopes 1V:6H or flatter. A NCAC study on median cable barrier placement on slopes completed in April 2007 found that placement 4 feet from the center of a v-shape median with 1V:6H side slopes increased the likelihood that mid-sized vehicles would underride the barrier (ref 2). This report notes that placement of the barrier one foot from the bottom of the ditch is, however, generally acceptable on slopes as steep as 1V:6H. [W-beam guardrail should be placed on slopes no steeper than 1:10 and caution should be taken on considering such installations on slopes as steep as 1:6.] 3 A second NCAC report nearing completion analyzed the effectiveness of various placement positions across medians from 16-42 feet wide, side slope ranging from 1V:10H to 1V:4H, for v-shaped and flat bottom cross sections across impact angles from 5 to 25 degrees, speeds of 50 to 100 k/hr, and small and mid-sized passenger cars and pick-up trucks (ref 3). The results of the vehicle dynamics analyses documented in this report suggest that there may be limited placement options for many 3 and 4 cable barrier designs that will provide the likelihood of capturing a broad range of vehicles. Placement on Horizontal Curves: Cable barriers on the inside of horizontal curves can be expected to have increased deflection. Reducing the post spacing may be an effective countermeasure, but objective criteria have not yet been established. High tensioned cable systems should be considered for severe curvilinear alignments. Soil Conditions/Footing Design: For those cable systems that use a concrete footing for their posts, quality control of the footing concrete and reinforcement can be critical. Although the barrier performance may only be slightly affected if the footings pull out of the soil upon impact, the benefit of the extra cost of footings is lost if they have to be replaced after an impact. Cable Splices: It is important to ensure that splice hardware provides for connections that are superior in strength to the cable itself. Obviously, if the splice fails the benefit of the full cable tension may be compromised. Manufacturer’s recommendations from the maker of the splice hardware should be followed. Dynamic Deflection: The “design deflection” noted in each FHWA acceptance letter is the minimum deflection distance that should be provided to fixed object hazards and is based on the test using the 2000P (4400 pound) pickup truck. The deflection distance recorded in FHWA letters is also related to the length of the test installation. For example, if a 300-foot long barrier system is tested and the “design deflection” recorded, the actual deflection under similar impact conditions will be greater if the barrier length between tiedowns exceeds 300 feet. Future crash test criteria will specify a minimum installation length for test sections on the order of 600 feet to better determine the deflection that can normally be expected. For additional information on cable barrier design and testing, please contact Mr. Nicholas Artimovich of the Headquarters Office of Safety Design at nick.artimovich@dot.gov or Mr. Frank Julian of the Resource Center (Atlanta) Safety and Design Team at frank.julian@dot.gov. Please also note the broad range of information available on the Web sites referenced in the attachment. Attachment FHWA:HSSD:NArtimovich:tb:x61331:6/12/07 REVISED: Per Counsel’s Office:dp:7/19/07. REVISED: McDonough/Lupes: 7/20/07 File: s://directory folder/nartimovich/CableMemo0625 cc: HSSD (Reader, HSA; Chron File, HSSD; N.Artimovich, HSSI M.McDonough, HSSD; E.Rice, HSSD) USEFUL LINKS As noted in the memo, research is underway to provide additional guidance on a number of cable barrier topics. Until that work is done, designers may want to review the details found in the report “A Review of Cable/Wire Rope Barrier Design Considerations” by Dr. Dean Alberson, et al, of Texas Transportation Institute. That 2003 report is available on the internet at http://www.ltrc.lsu.edu/TRB_82/TRB2003-002025.pdf . The AASHTO Technology Implementation Group, or TIG Web site (http://tig.transportation.org/?siteid=57&pageid=1031) includes useful links to numerous current design, construction, and maintenance issues, as well as in-service performance evaluations from six States. The FHWA Corporate and Research Technology Web site on Cable Barriers http://www.fhwa.dot.gov/crt/lifecycle/cable.cfm The TRB 2007 paper “Performance Evaluation of Low-Tension Three-Strand Cable Median Barriers.” Summary of the National Crash Analysis Center study using finite element modeling and full scale crash testing to investigate the problem of median cable barrier underride. Report to be distributed by the FHWA this summer. http://pubsindex.trb.org/document/view/default.asp?lbid=802649 Commercial site that includes over 40 links to cable barrier research and policy. http://www.gsihighway.com/research.htm The following reports will be completed in the near future: Ref 1: “Performance Evaluation of Low-Tension, Three-Strand Cable Median Barriers on Sloped Terrains,” prepared by NCAC under FHWA contract DTFH61-02-X-00076, April 2007. Ref 2: NCHRP Project 22-14(2) report – Proposed Update to NCHRP Report 350. Ref 3: “Analyses of Placement Effects on Cable Barrier Systems for Varying Median Cross Sections,” prepared by NCAC under FHWA contract DTFH61-02-X-00076, June 2007. May 9, 2006 400 Seventh St., S.W. Washington, D.C. 20590 In Reply Refer To: HSA-10/B82-B1 Mr. Derek W. Muir Group Managing Director Hill & Smith Ltd. Springvale Business and Industrial Park Bilston, Wolverhampton, West Midlands, WV14 0QL Dear Mr. Muir: In your April 11, 2006, letter, you requested the Federal Highway Administration's (FHWA’s) concurrence that your TL-4 four-rope Brifen Wire Rope Safety Fence (WRSF) would be acceptable as a National Cooperative Highway Research Program (NCHRP) Report 350 test level 3 (TL-3) traffic barrier when placed as described below on a side slope as steep as 1V: 4H. On that same date, your representatives, Dr. Richard McGinnis and Mr. Jerry Emerson, met with Messrs. Artimovich and Powers of my staff and provided them copies of three test reports prepared by the Southwest Research Institute (SwRI) entitled "NCHRP Report 350, “Modified” Test 3-11 Full-Scale Crash Evaluation of a 111-Meter TL-4 (4-Rope) Wire Rope Safety Fence Installed on a 1V: 4H Sloped Median,” (SwRI test no. BCR-2); "NCHRP Report 350, Test 3-10 Full-Scale Crash Evaluation of a 111-Meter TL-4 (4-Rope) Wire Rope Safety Fence Installed on a 1V: 4H Sloped Median,” (SwRI test no. BCR-5); and "NCHRP Report 350, Test 3-10 Full-Scale Crash Evaluation of a 111-Meter TL-4 (4-Rope) Wire Rope Safety Fence Installed on a 1V: 4H Sloped Median,” (SwRI test no. BCR-4). In my March 27, 2005, letter to you (acceptance letter B-82B), the FHWA accepted the Brifen 4-rope TL-4 WRSF as a NCHRP Report 350 TL-4 traffic barrier. This TL-4 design consists of four separate cables, the bottom three of which are interwoven between posts and the top cable is set in a 101-mm deep x 22-mm wide slot cut into the top of each post. Cable heights measured from the ground directly beneath the cables were 480 mm, 630 mm, 780 mm, and 930 mm, respectively. The S-shape posts, 100-mm x 55-mm x 4.55-mm thick, manufactured from ASTM A-36 steel, were spaced on 3.2-m centers. Three tests were conducted with the TL-4 WRSF installed in a 9.8-m (32-feet) wide depressed median with 1V: 4H side slopes. For the first test, the barrier was located 3.7 m (12 feet) up the slope from the ditch bottom and the test vehicle crossed the ditch bottom and started up the 2 backslope before impacting the barrier. For the second and third tests (NCHRP Report 350 tests 3-10 and 3-11) the barrier was located down the foreslope, 1.2 m (4 feet) from the edge of pavement. The first test was a modified 3-11 test in which a 1998 Ford Crown Victoria weighing 1,750 kg (3,859 lb) was directed into the median at a 25° angle and 103.1 km/hr (64.1 mph), went down the slope, across the ditch bottom [located 4.9 m (16 ft) from edge of pavement] and 3.7 m (12 feet) up the far side of the ditch where it then impacted the backside of the WRSF [located 8.5 m (28 ft) from edge of pavement] at a 26.5° angle at 95.6 km/hr (59.4 mph). The vehicle deflected the barrier 2.2 m (7.3 ft) laterally and was safely contained and redirected by the WRSF. Cables were tensioned to 20.0 kN (4500 lb) based on the ambient temperature of 29 degrees Celsius (84 degrees Fahrenheit). Although the barrier in this test was located 3.7 m (12 feet) beyond the ditch bottom, a subsequent analysis prepared by Dr. McGinnis and based on additional data obtained from the SwRI test indicated that the Crown Victoria would have been captured by the WRSF if the barrier had been installed closer to the ditch bottom. After reviewing the bumper trajectory data and the crash test video, my staff agreed that the barrier would likely perform satisfactorily with a minimum 3.0-m (10-foot) offset from the ditch bottom. Enclosure 1 is the test summary sheet for the first test. The use of a non-standard test vehicle for the first test was intended to replicate the FHWAsponsored crash test of a Ford Crown Victoria sedan into a standard 3-rope US cable barrier that was conducted on April 23, 2004 at the Federal Outdoor Impact Laboratory by the National Crash Analysis Center (NCAC). In that test, the cable barrier was located 1.2 m (4 feet) up from the ditch bottom in a median with 1V: 6H side slopes. The test vehicle’s front suspension compressed when it struck the backslope, allowing the bumper to slide underneath the bottom cable. The vehicle then underrode the barrier and continued up the slope with no redirection. A second test conducted by NCAC with a Crown Victoria impacting at the same speed and angle but with the generic cable barrier offset from the ditch bottom by only 0.3 m (one foot) was successful. The second Brifen test was a standard NCHRP Report 350 3-10 test with the TL-4 WRSF located 1.2 m (4 ft) down the 1V: 4H slope from the edge of pavement. A 1998 Suzuki Swift weighing 907 kg (2,000 lb) impacted the WRSF at a 21.1-degree angle at 101.3 km/hr (62.9mph). The maximum dynamic deflection of the barrier was 1.2 m (4.0 ft), and the vehicle was safely contained and redirected by the WRSF. Cables were tensioned to 18.7 kN (4200 lb) based on the ambient temperature of 32 degrees Celsius (90 degrees Fahrenheit). Enclosure 2 is the test summary sheet for this second test. The third Brifen test was a standard NCHRP Report 350 3-11 test with the WRSF again located 1.2 m (4 ft) down the 1V: 4H slope from the edge of pavement. A 1998 Chevrolet C2500 3/4-ton pickup truck weighing 2,139 kg (4,717 lb) impacted the WRSF at a 24.1 degree angle at 101.4 km/hr (63.0 mph). The maximum dynamic deflection of the barrier was 2.7 m (9.0 ft) caused by the rear of the vehicle rotating into the barrier while the vehicle was airborne. The maximum deflection of the barrier caused by the front of the vehicle was 2.3 m (7.6 ft). The vehicle was contained and safely redirected by the barrier. Cables were tensioned to 24.7 kN (5550 lb). The ambient temperature immediately prior to this test was 14 degrees Celsius (48 degrees Fahrenheit). Enclosure 3 is the test summary sheet for the third test. 3 Based on the test results summarized above, your TL-4 Brifen WRSF is acceptable as a TL-3 traffic barrier when placed no farther than 1.2 m (4 feet) down a 1V: 4H slope (for adjacent traffic impacts) and no closer than 10 feet from the ditch bottom for opposite-side impacts. Although the WRSF tested above was the Brifen WRSF TL-4 four-rope system which was successfully tested with the single unit truck on a flat slope, transportation agencies using this design on a 1V: 4H slope should understand that only TL-3 vehicles were used in the crash tests. On such slopes, it is possible that TL-4 vehicles and larger may not be captured or contained by the barrier. I strongly agree with your recommendation that usage be closely monitored through in-service evaluation, since three crash tests alone cannot predict the performance of any traffic barrier for every conceivable combination of barrier type, site conditions, vehicle size, shape, weight, and impact angle and speed. Because the NCHRP Report 350 testing was developed to address a worst practical case scenario, there is always a possibility that some vehicular penetrations will occur when anything less than a high-performance TL-5 or TL-6 barrier is used. Sincerely yours, /original signed by/ John R. Baxter, P.E. Director, Office of Safety Design Office of Safety 3 Enclosures Table 4.1 – Summary of Test Results and Conditions IMPACT 15 General Information Test Agency................................ Southwest Research Institute Test Number ................................ BCR-2 Test Date................................02/28/2006 Test Category .............................. 3-11 Test Article Type ............................................ Longitudinal Barrier Installation Length ...................... 111 m (365 ft) Nom. Barrier Height ................... 930 mm (36.5 in) Type of Primary Barrier ............. Wire Rope Safety Fence, 4-Rope Soil Stable, Dry – Highly Compacted Test Vehicle Type ............................................ Special Designation................................ Special Model ........................................... 1998 Ford Crown Victoria Mass (kg) ................................1750 Inertial Mass(kg) ......................... 1750 Dummy Mass (kg) ...................... NA Gross Static Mass (kg) ................ 1750 0.20 SEC 0.40 SEC 0.60 SEC Impact Conditions Test Article Deflection Speed (km/hr) ............................. 95.6 Dynamic ...................................... 2.2 m (7.3 ft) Angle (degrees)........................... 26.5 Permanent ................................0 m (0 ft) Exit Conditions Vehicle Damage Speed (km/hr) ............................. 59 (calculated) Exterior Angle (degrees) ........................... 11 CDC ............................................ 11LFEW5 Occupant Risk Values VDS ............................................ 11-LFQ-3 Impact Velocity (m/s) Interior x-direction............................ 3.6 OCDI ........................................... LF0000000 y-direction............................ -0.7 Max. Deform. (mm) ................... 0 Ridedown Accelerations (g’s) x-direction............................ -5.8 y-direction............................ 6.7 Post Impact Vehicular Behavior (limited to events <2.000 seconds) Maximum Roll Angle (degrees) ...................... -34.9 @ 1.212 sec. Maximum Pitch Angle (degrees) ..................... -14.3 @ 0.435 sec. Maximum Yaw Angle (degrees) ..................... 38.6 @ 2.000 sec. Table 4.1 – Summary of Test Results and Conditions IMPACT 17 General Information Test Agency................................ Southwest Research Institute Test Number ................................ BCR-5 Test Date................................03/01/2006 Test Category .............................. 3-10 Test Article Type ............................................ Longitudinal Barrier Installation Length ...................... 111 m (365 ft) Nom. Barrier Height ................... 930 mm (36.5 in) Type of Primary Barrier ............. Wire Rope Safety Fence, 4-Rope Soil Stable, Dry – Highly Compacted Test Vehicle Type ............................................ Small car Designation................................ 820C Model ........................................... 1998 Suzuki Swift Mass (kg) ................................907 Inertial Mass(kg) ......................... 907 Dummy Mass (kg) ...................... 75 Gross Static Mass (kg) ................ 982 0.10 SEC 0.20 SEC 0.35 SEC Impact Conditions Test Article Deflection Speed (km/hr).............................. 101.3 Dynamic ...................................... 1.2 m (4.0 ft) Angle (degrees) ........................... 21.1 Permanent................................0 in (0 m) Exit Conditions Vehicle Damage Speed (km/hr).............................. 74 (calculated) Exterior Angle (degrees) ........................... 11 CDC ............................................ 11LFEW5 Occupant Risk Values VDS ............................................ 11-LFQ-2 Impact Velocity (m/s) Interior x-direction ............................ 3.5 OCDI ........................................... LF0000000 y-direction ............................ -3.7 Max. Deform. (mm) ................... 0 Ridedown Accelerations (g’s) x-direction ............................ -9.0 y-direction ............................ 10.3 Post Impact Vehicular Behavior (limited to events <2.000 seconds) Maximum Roll Angle (degrees) ...................... -8.2 @ 1.705 sec. Maximum Pitch Angle (degrees) ..................... -4.0 @ 0.376 sec. Maximum Yaw Angle (degrees)...................... -99.3 @ 2.000 sec. Table 4.1 – Summary of Test Results and Conditions IMPACT 17 General Information Test Agency................................ Southwest Research Institute Test Number ................................ BCR-4 Test Date................................03/01/2006 Test Category .............................. 3-11 Test Article Type ............................................ Longitudinal Barrier Installation Length ...................... 111 m (365 ft) Nom. Barrier Height ................... 930 mm (36.5 in) Type of Primary Barrier ............. Wire Rope Safety Fence, 4-Rope Soil Stable, Dry – Highly Compacted Test Vehicle Type ............................................ ¾ Ton Pickup Designation................................ 2000P Model ........................................... 1998 Chevy C2500 Mass (kg) ................................2139 Inertial Mass(kg) ......................... 2139 Dummy Mass (kg) ...................... NA Gross Static Mass (kg) ................ 2139 0.30 SEC 0.60 SEC 0.90 SEC Impact Conditions Test Article Deflection Speed (km/hr) ............................. 101.4 Dynamic ...................................... 2.7 m (9.0 ft) Angle (degrees) ........................... 24.1 Permanent ................................0 m (0 ft) Exit Conditions Vehicle Damage Speed (km/hr) ............................. 71 (calculated) Exterior Angle (degrees) ........................... 8 CDC ............................................ 11LFEW4 Occupant Risk Values VDS ............................................ 11-LFQ-2 Impact Velocity (m/s) Interior x-direction............................ 2.7 OCDI ........................................... LF0000000 y-direction............................ -2.8 Max. Deform. (mm) ................... 0 Ridedown Accelerations (g’s) x-direction............................ -5.9 y-direction............................ 8.2 Post Impact Vehicular Behavior (limited to events <2.000 seconds) Maximum Roll Angle (degrees) ...................... 16.8 @ 0.679 sec. Maximum Pitch Angle (degrees) ..................... -3.2 @ 1.983 sec. Maximum Yaw Angle (degrees) ..................... 32.9 @ 0.592 sec. 400 Seventh St., S.W. Washington, D.C. 20590 In Reply Refer To: HSA-10/B137C July 12, 2006 Mr.Bill Neusch President, Gibraltar 320 Southland Road Burnet, Texas 78611 Dear Mr. Neusch: In your June 22, 2006, letter, you requested the Federal Highway Administration's (FHWA’s) concurrence that your TL-4 cable barrier system would be acceptable as a National Cooperative Highway Research Program (NCHRP) Report 350 test level 3 (TL-3) traffic barrier when placed as described below on a side slope as steep as 1V: 4H. At that time, you also provided staff members with preliminary test results. On July 11, Mr. Powers received a test report prepared by KARCO Engineering, LLC, entitled “Crash Test Report for Gibraltar TL-4 Cable Barrier System Installed on a 4:1 Sloped Median” and dated June 12, 2006. In my letter dated September 9, 2005, the FHWA accepted a modified Gibraltar cable barrier system as a TL-4 design. This design consisted of three, 3/4-inch diameter 3 X 7 posttensioned galvanized steel cables supported by steel C-posts 3.25 x 2.5 x 0.15-inches thick and 7-ft long. These posts were driven to a depth of 3.5 feet and installed on alternate sides of the cables. The 3 cables are locked in place by a 7/16-inch diameter x 24-inch long galvanized steel hairpin and lock plate that fits inside each post. For your TL-4 design, the bottom, middle, and top cable heights are set at 20 inches, 30 inches, and 39 inches, respectively. A total of four tests were conducted with the TL-4 Gibraltar cable installed in a 7.3-m (24-feet) wide depressed median with 1V: 4H side slopes. For the first test, the barrier was located 2.7 m (9 feet) up the slope from the ditch bottom and the test vehicle crossed the ditch bottom and started up the backslope before impacting the barrier. For the remaining tests (NCHRP Report 350 tests 3-10 and 3-11), the barrier was located down the foreslope, 1.2 m (4 feet) from the edge of pavement. For the first two tests, all line posts were on 30-foot centers. The first test was a modified 3-10 test in which a Geo Metro weighing 874 kg (1926 lb) was directed into the median at a 25° angle and 104.7 km/hr (65.1 mph), went down the slope, across the ditch bottom [located 3.7 m (12 ft) from edge of pavement] and 2.7 m (9 feet) up the far side of the ditch where it then impacted the backside of the cable [located 8.5 m (21 ft) from edge of pavement] at 97.5 km/hr (60.6 mph). The vehicle deflected the barrier 1.5 m (4.9 ft) laterally and was safely contained and redirected by the Gibraltar cable. 2 Enclosure 1 is the summary sheet for this test. The second test was a standard NCHRP Report 350 3-11 test, with the Gibraltar cable, again with a 30-foot post spacing, located 1.2 m (4 ft) down the 1V: 4H slope from the edge of pavement. A Chevrolet C2500 3/4-ton pickup truck weighing 2,038 kg (4,494 lb) impacted the barrier at a 25-degree angle at 98.7 km/hr (61.3 mph). The maximum dynamic deflection of the barrier was not reported. Although the barrier contained the vehicle, cable deflection allowed the pickup truck to impact the backslope of the ditch and it subsequently overturned as it was being redirected by the cable. This test clearly demonstrated that adverse terrain behind a barrier can cause significant instability when barrier deflection allows an impacting vehicle to reach it, even when the barrier itself prevents penetration. Enclosure 2 is the test summary sheet for this test. The third test was a repeat of the failed test, but the post spacing was reduced to 20 feet, and a heavier test vehicle was used, specifically a Dodge Ram 1500 weighing 2222 kg (4898 lbs). This is the new vehicle currently proposed for use in the draft Report 350 update. Impact conditions were 25 degrees and 97 km/h (60.3 mph). In this test, the pickup truck was contained and redirected upright with a maximum cable deflection of 2.6 m (8.6 ft). Test results are shown in Enclosure 3. The final test was a standard NCHRP Report 350 3-10 test with the Gibraltar cable again located 1.2 m (4 ft) down the 1V: 4H slope from the edge of pavement. A Geo Metro weighing 919 kg (2,026 lb) impacted the barrier at a 20-degree angle at 101.6 km/hr (63.2 mph). The maximum dynamic deflection of the barrier was 1.4 m (4.7 ft), and the vehicle was safely contained and redirected by the cable. Enclosure 4 is the test summary sheet for this test. Based on the test results summarized above, your TL-4 Gibraltar cable design is acceptable as a TL-3 traffic barrier when placed no farther than 1.2 m (4 feet) down a 1V: 4H slope (for adjacent traffic impacts) and no closer than 9 feet from the ditch bottom for opposite-side impacts. This offset may be decreased to 8 feet based on computer simulation done by the National Crash Analysis Center on the generic cable barrier and on our review of the vehicle position at that point in your test, provided the maximum down-slope offset remains at 4 feet. Although the tested design was your TL-4 system (successfully tested previously with the single unit truck on a flat slope), transportation agencies using this design on a 1V: 4H slope should understand that it has been tested only to TL-3 when installed on such a slope. Thus, it remains possible that the single-unit TL-4 truck may not be captured or contained by the barrier when installed on a 4:1 slope. Sincerely yours, /original signed by John R. Baxter/ John R. Baxter, P.E. Director, Office of Safety Design Office of Safety 4 Enclosures DATA SHEET NO. 2 SUMMARY OF RESULTS FOR TEST NO. P26133-01 (MODIFIED 3-10) GENERAL INFORMATION TEST AGENCY KARCO ENGINEERING TEST NO. Modified 3-10 DATE 06/12/06 TEST ARTICLE TYPE Gibraltar Cable Barrier System INSTALLATION LENGTH (m) 91.44 m (300 ft.) SIZE AND/OR DIMENSION OF KEY ELEMENTS ¾ in 3 X 7 cable on 30 ft. post spacings SOIL TYPE AND CONDITION 4:1 slope (upslope 25°) TEST VEHICLE 820C TYPE Production DESIGNATION 3-10 MODEL Geo Metro MASS (CURB) 799 kg (1762 Ibs) MASS (TEST INERTIAL) 812 kg (1790 Ibs) DUMMY(s) MASS 75 kg (165 lbs) GROSS STATIC WEIGHT 874 kg (1926 Ibs) IMPACT CONDITIONS 104.7 km/h (65.08 mph) SPEED (km/h) 97.51 km/h (60.60 mph) at impact ANGLE (Deg.) 25 IMPACT SEVERITY (kJ) 34.8 EXIT CONDITIONS SPEED (km/h) N/A* ANGLE (Deg.) N/A* OCCUPANT RISK VALUES FLAIL SPACE VELOCITY (m/sec) X-DIRECTION 5.2 Y-DIRECTION 0.8 THIV (optional) RIDEDOWN ACCELERATION (g’s) X-DIRECTION -7.4 Y-DIRECTION -4.3 PHD (optional) ASI (optional) 0.84 TEST ARTICLE DEFLECTIONS (m) DYNAMIC 1.50 m (4.92 FT.) PERMANENT N/A VEHICLE DAMAGE EXTERIOR VDS 1-FR-4 CDC 01RDMN6 INTERIOR OCDI FR0000000 POST-IMPACT VEHICULAR BEHAVIOR MAXIMUM ROLL ANGLE (Deg.) MAXIMUM YAW ANGLE (Deg.) MAXIMUM PITCH ANGLE (Deg.) 22.7 -41.0 6.7 * Vehicle remained in contact with the cable barrier for the duration of the event. 13 TR-P26133-A DATA SHEET NO. 6 SUMMARY OF RESULTS FOR TEST NO. P26133-02 (Test 3-11) GENERAL INFORMATION TEST AGENCY KARCO ENGINEERING TEST NO. 3-11 DATE 06/12/06 TEST ARTICLE TYPE Gibraltar Cable Barrier System INSTALLATION LENGTH (m) 91.44 m(300 ft.) SIZE AND/OR DIMENSION OF KEY ELEMENTS ¾ in 3 X 7 cable on 30 ft. post spacings SOIL TYPE AND CONDITION 4:1 slope TEST VEHICLE 2000P TYPE PRODUCTION DESIGNATION 3-11 MODEL 2500 MASS (CURB) 2210 kg (4872 Ibs) MASS (TEST INERTIAL) 2038 kg (4494 Ibs) DUMMY(s) MASS N/A GROSS STATIC WEIGHT N/A IMPACT CONDITIONS SPEED (km/h) 98.65 km/h (61.31 mph) ANGLE (Deg.) 25 IMPACT SEVERITY (kJ) 89.5 EXIT CONDITIONS SPEED (km/h) N/A* ANGLE (Deg.) N/A* OCCUPANT RISK VALUES FLAIL SPACE VELOCITY (m/sec) X-DIRECTION 3.3 Y-DIRECTION 5.4 THIV (optional) RIDEDOWN ACCELERATION (g’s) X-DIRECTION -15.1 Y-DIRECTION 10.4 PHD (optional) ASI (optional) 0.49 TEST ARTICLE DEFLECTIONS (m) DYNAMIC PERMANENT N/A VEHICLE DAMAGE EXTERIOR VDS 1-L&T-6 CDC 01RDGN2 INTERIOR OCDI FS0100000 POST-IMPACT VEHICULAR BEHAVIOR MAXIMUM ROLL ANGLE (Deg.) MAXIMUM YAW ANGLE (Deg.) MAXIMUM PITCH ANGLE (Deg.) 258.7 -49.3 35.5 * Vehicle rolled over on the cable barrier. 28 TR-P26133-A DATA SHEET NO. 10 SUMMARY OF RESULTS FOR TEST NO. P26133-03 (Test 3-11) GENERAL INFORMATION TEST AGENCY KARCO ENGINEERING TEST NO. 3-11 DATE 06/14/06 TEST ARTICLE TYPE Gibraltar Cable Barrier System INSTALLATION LENGTH (m) 92.9 m(305 ft.) SIZE AND/OR DIMENSION OF KEY ELEMENTS ¾ in 3 X 7 cable on 20 ft. post spacings SOIL TYPE AND CONDITION 4:1 slope(down slope 25°) TEST VEHICLE 2270P TYPE Production DESIGNATION 3-11 MODEL RAM 1500 MASS (CURB) 2194 kg (4836 Ibs) MASS (TEST INERTIAL) 2222 kg (4898 Ibs) DUMMY(s) MASS N/A GROSS STATIC WEIGHT N/A IMPACT CONDITIONS SPEED (km/h) 97.05 km/h (60.32 mph) ANGLE (Deg.) 25 IMPACT SEVERITY (kJ) 144.7 EXIT CONDITIONS SPEED (km/h) N/A* ANGLE (Deg.) N/A* OCCUPANT RISK VALUES FLAIL SPACE VELOCITY (m/sec) X-DIRECTION 2.7 Y-DIRECTION 8.3 THIV (optional) RIDEDOWN ACCELERATION (g’s) X-DIRECTION -3.6 Y-DIRECTION -3.9 PHD (optional) ASI (optional) 0.35 TEST ARTICLE DEFLECTIONS (m) DYNAMIC 2.61 m (8.58 ft.) PERMANENT N/A VEHICLE DAMAGE EXTERIOR VDS 1-FR-2 CDC 01RDEN2 INTERIOR OCDI FS0000000 POST-IMPACT VEHICULAR BEHAVIOR MAXIMUM ROLL ANGLE (Deg.) MAXIMUM YAW ANGLE (Deg.) MAXIMUM PITCH ANGLE (Deg.) 23.8 -44.3 -17.9 * Vehicle remained in contact with the cable barrier for the duration of the event. 44 TR-P26133-A DATA SHEET NO. 14 SUMMARY OF RESULTS FOR TEST NO. P26133-04 (Test 3-10) GENERAL INFORMATION TEST AGENCY OCCUPANT RISK VALUES KARCO ENGINEERING FLAIL SPACE VELOCITY (m/sec) TEST NO. 3-10 X-DIRECTION 2.8 DATE 06/16/06 Y-DIRECTION 4.9 TEST ARTICLE THIV (optional) TYPE Gibraltar Cable Barrier System RIDEDOWN ACCELERATION (g’s) INSTALLATION LENGTH (m) 91.44 m (300 ft.) ¾ in 3 X 7 cable on 30 ft. post i 4:1 slope (upslope 25°) X-DIRECTION -4.8 Y-DIRECTION -5.6 SIZE AND/OR DIMENSION OF KEY ELEMENTS SOIL TYPE AND CONDITION PHD (optional) TEST VEHICLE 820C ASI (optional) TYPE PRODUCTION TEST ARTICLE DEFLECTIONS (m) 0.63 DESIGNATION 3-10 DYNAMIC 1.43 m ( 4.70 FT.) MODEL Geo Metro PERMANENT N/A MASS (CURB) 858 kg (1892 Ibs) VEHICLE DAMAGE MASS (TEST INERTIAL) 845 kg (1862 Ibs) EXTERIOR DUMMY(s) MASS 75 kg (165 lbs) VDS 1-FR-2 GROSS STATIC WEIGHT 919 kg (2026 Ibs) CDC 01RRGN8 IMPACT CONDITIONS INTERIOR SPEED (km/h) 101.63 km/h (63.16 mph) ANGLE (Deg.) 20 IMPACT SEVERITY (kJ) 39.3 OCDI FS0000000 POST-IMPACT VEHICULAR BEHAVIOR EXIT CONDITIONS MAXIMUM ROLL ANGLE (Deg.) 37.6 SPEED (km/h) N/A* MAXIMUM YAW ANGLE (Deg.) -34.3 ANGLE (Deg.) N/A* MAXIMUM PITCH ANGLE (Deg.) 4.4 *Test vehicle exit conditions occurred beyond the view of the overhead cameras. 61 TR-P26133-A May 15, 2003 Refer to: HSA-10/B-119A Mr. Rodney A. Boyd Trinity Highway Safety Products Division P.O. Box 568887 Dallas, Texas 75356-8887 Dear Mr. Boyd: In his March 31 letter to Mr. Richard Powers of my staff, your representative, Mr. Don Johnson, requested formal Federal Highway Administration (FHWA) acceptance of a modified version of the wire rope traffic barrier called the Cable Safety System (CASS) that was originally accepted for use on the National Highway System (NHS) in my May 13, acceptance letter B119. Whereas the original design used a 3-m post spacing, the modified design used a 5-m spacing for all the CASS line posts. Included with the second letter were copies of a Texas Transportation Institute report dated March 2003, entitled “NCHRP Report 350 test 3-11 of TRINITY Cable Safety System (CASS) with 5m Post Spacing” and videotapes of the crash test. The CASS barrier remained as described in my original acceptance letter, consisting of three 19 mm diameter, pre-stretched 3 x 7 strand steel cables. Mounting heights were 530 mm, 640 mm, and 750 mm above the ground and each cable was tensioned to 24kN using turnbuckles attached to swaged threaded fittings on each end. These cables were supported by 1600-mm long, galvanized 100 x 50 x 4 mm C-channels driven into a Report 350 standard soil. As shown on Enclosure 1, the upper central section of the post web was removed to accept the cables, which are kept separated in a vertical plane by the insertion of plastic spacer blocks, a stainless steel strap, and a plastic cap over the top of each post. In this modified version, the posts were set on 5-m centers rather than 3-m apart as in the initial test. A 2000-kg pickup truck impacted the CASS barrier at 99.4 km/h near the mid-point of a 100-meter long test installation at an impact angle of 25.7 degrees. As seen on the test summary sheet (Enclosure 2), all Report 350 evaluation criteria were met. The cable rail deflected 2.8 meters with the 5-m post spacing. Thus, the CASS barrier, as described above, meets NCHRP Report 350 evaluation criteria as a test level 3 barrier and may be used on the NHS as either a roadside or median barrier when such use is acceptable to the contracting agency. Since it is a proprietary product, the provisions of Title 23, Code of Federal Regulations, Section 635.411 apply to its use on Federally funded projects, except exempt non-NHS projects. The need to use crashworthy (or shielded) terminals emphasized in my May 13 letter for the 3-m post spacing design applies to the 5-m post spacing layout as well. 2 This Acceptance Letter shall not be construed as authorization or consent by the FHWA to use, manufacture, or sell any proprietary device for which ownership may be in question. All FHWA acceptances are based primarily on staff review of the crashworthiness characteristics of the proposed device and we are neither prepared nor required to become involved in issues concerning patent law. Patent issues, if any should arise, are to be resolved by the applicant. Sincerely yours, (original signed by Michael S. Griffith) Michael S. Griffith Acting Director, Office of Safety Design Office of Safety 2 Enclosures 1 in = 25.4 mm 1 ft = 0.305 m 7 Details of CASS post. 0.000 s 20 General Information Test Agency . . . . . . . . . . . . . Test No. . . . . . . . . . . . . . . . . Date . . . . . . . . . . . . . . . . . . . Test Article Type . . . . . . . . . . . . . . . . . . . Name . . . . . . . . . . . . . . . . . . Installation Length (m) . . . . . Material or Key Elements . . . 0.193 s Texas Transportation Institute 400001-TCR2 01/31/03 Guardrail Trinity Cable Safety System (CASS) 101.9 3 Wire Ropes Supported By C-Channel Mild Steel Support Posts Soil Type and Condition . . . . Standard Soil, Dry Test Vehicle Type . . . . . . . . . . . . . . . . . . . Production Designation . . . . . . . . . . . . . 2000P Model . . . . . . . . . . . . . . . . . . 1998 Chevrolet 2500 Pickup Mass (kg) Curb . . . . . . . . . . . . . . . . . 2075 Test Inertial. . . . . . . . . . . . 2050 Dummy . . . . . . . . . . . . . . . N/A Gross Static . . . . . . . . . . . 2050 0.483 s Impact Conditions Speed (km/h) . . . . . . . . . . . . . . . . Angle (deg) . . . . . . . . . . . . . . . . . Exit Conditions Speed (km/h) . . . . . . . . . . . . . . . . Angle (deg) . . . . . . . . . . . . . . . . . Occupant Risk Values Impact Velocity (m/s) x-direction . . . . . . . . . . . . . . . . y-direction . . . . . . . . . . . . . . . . THIV (km/h) . . . . . . . . . . . . . . . . . Ridedown Accelerations (g's) x-direction . . . . . . . . . . . . . . . . y-direction . . . . . . . . . . . . . . . . PHD (g’s) . . . . . . . . . . . . . . . . . . . ASI . . . . . . . . . . . . . . . . . . . . . . . Max. 0.050-s Average (g's) x-direction . . . . . . . . . . . . . . . . y-direction . . . . . . . . . . . . . . . . z-direction . . . . . . . . . . . . . . . . 99.4 25.7 77.4 9.5 2.5 3.3 14.0 -4.4 5.2 6.3 0.36 -2.3 3.0 -1.9 1.208 s Test Article Deflections (m) Dynamic . . . . . . . . . . . . . . . . Permanent . . . . . . . . . . . . . . Working Width . . . . . . . . . . . Vehicle Damage Exterior VDS . . . . . . . . . . . . . . . . . CDC . . . . . . . . . . . . . . . . . Maximum Exterior Vehicle Crush (mm) . . . . . Interior OCDI. . . . . . . . . . . . . . . . . Max. Occ. Compart. Deformation (mm) . . . . . . . Post-Impact Behavior (during 1.0 s after impact) Max. Yaw Angle (deg) . . . . . . Max. Pitch Angle (deg) . . . . . Max. Roll Angle (deg) . . . . . . Summary of results for test 400001-TCR2 (CASS w/5 m spacing), NCHRP Report 350 test 3-11. 2.80 0.11 3.40 11FL1 11FLEW1 100 LF0000000 None 33.4 6.9 18.1 MS Transportation Systems, Inc. Existing and Proposed Route Survey Cross-Section Information MS Transportation Systems, Inc. Route 213 Sign Replacement Project Sheets