ROAD SAFETY AUDIT MAJOR HIGHWAY MEDIAN CROSS-OVER CRASHES I-495 Haverhill Prepared for Massachusetts Highway Department Prepared by MS Transportation Systems, Inc. Framingham, Massachusetts February 2009 ROAD SAFETY AUDIT MAJOR HIGHWAY MEDIAN CROSS-OVER CRASHES I-495 HAVERHILL FINAL REPORT February 2009 Prepared for Massachusetts Highway Department Prepared by MS Transportation Systems, Inc. Consulting Engineers and Planners 300 Howard Street, P.O. Box 967 Framingham, Massachusetts 01701 Tel: (508) 620-2832 Fax: (508) 620-6897 www.mstransportationsystemsinc.com I-495 Haverhill Road Safety Audit TABLE OF CONTENTS Page INTRODUCTION 1 RSA PROCESS 3 ANALYSIS 8 SUMMARY OF RSA FINDINGS/POTENTIAL ACTIONS 12 RECOMMENDATIONS 18 APPENDIX 23 MS Transportation Systems, Inc. Page i I-495 Haverhill Road Safety Audit INTRODUCTION Lane departure crashes are one of the primary fatal crash types in Massachusetts. The Commonwealth exceeds the national average for lane departure crashes and was designated a lead state in lane departure crashes by the American Association of State Highway and Transportation Officials (AASHTO). The Massachusetts Highway Department (MHD) conducted a study of the problem and found that during 2002-2004, lane departure crashes accounted for 25 percent of all injury crashes and nearly half, 46 percent, of all fatal crashes. As part of the effort in implementing the safety plan and specifically reducing lane departure crashes, the MassHighway is completing a Road Safety Audit (RSA) Review Project specifically focused on median crossing (or median cross-over) crashes on its major highways. Road safety audits are a formal safety performance examination on existing or future roadways by an independent audit team. These specific audits are being conducted in locations where cross-over experience has been or has the potential to be of concern and where the RSA team has judged that factors exist and safety risk could be affected. The team works to identify opportunities for enhancing safety and to recommend specific enhancements that may be implemented to reduce median crossover crashes and improve the overall safety along the highway. An RSA was conducted for the I-495 in Haverhill as part of this overall effort. The roadway section under study, shown in Figure 1, was essentially between Interchange No. 48 at Route 125 Connector and Interchange No. 49 at Routes 110/113 a distance of approximately 1.1 miles. This section had experienced a fatal cross-median crash in the vicinity of Interchange No. 48. The purpose of this I-495 Haverhill RSA was to assess current safety characteristics on the highway section under study and to recommend a set of actions to enhance the safe operation of the highway section under study. Recommendations contained in this report reflect the overall consent of the RSA team and do not necessarily reflect the official views of MassHighway. MS Transportation Systems, Inc. Page 1 495 Interchange 49 Route 110 Route 113 Haverhill Interchange 48 Route 125 Connector 495 Route 125 N Project Location W S I-495 Road Safety Audit Haverhill, Massachusetts MS Transportation Systems, Inc. E 1 : 25,000 Framingham, Massachusetts FIGURE 1 I-495 Haverhill Road Safety Audit RSA PROCESS In conducting the RSA, the overall procedures outlined in the Median Cross-Over RSA Guideline Report1 with some modifications given the characteristics of the facility being reviewed. The process included identifying RSA team members; conducting field visits; holding a RSA team meeting and then completing an assessment of the data and findings from the field visits and meetings to render recommended actions for MassHighway to consider. Data including recent traffic volume data, summary crash records for the 2004-2007 period, detailed crash reports of cross-over crashes, and available record highway plans were obtained and reviewed by the RSA consultant. Field visits were conducted by the RSA team members. A video recording of the sections under study was taken by the RSA Consultant. The site visits were completed prior to the RSA team meeting that was held on October 1, 2008 at the MassHighway District 4 offices. At that meeting, the RSA consultant provided a brief overview of the RSA purpose, a summary of the roadway section’s characteristics and results of the review to date. The RSA team provided input and discussed the key items noted in the field and that were listed on the RSA Median Cross-Over Prompt List. Issues and concerns were noted. Following the RSA meeting, the RSA consultant compiled the information, completed the analysis and circulated the draft report. • RSA Team The following were members of the I-495 Haverhill Road Safety Audit: Anthony Komornick, MVPC John Gregg, MassHighway, Traffic Chris Leahy, MassHighway, District 4 Xian Chen, MassHighway William J. Scully, MS Transportation systems (RSA Consultant) • Paul Fletcher, Mass State Police Frank Welch, MassHighway, District 4 Lisa Schletzbaum, MassHighway, Safety Christine Breen, MassHighway Timothy White, FHWA Slave Podluzny, MassHighway District 4 RSA Team Meeting The RSA team meeting took place on October 1, 2008 at the District 4 offices in Arlington. The team included engineers, planners and a representative from the State Police barrack that has jurisdiction of I-495 in Haverhill. Represented were MassHighway (Boston and District), staff for Merrimack Valley Planning Commission, as 1 MS Transportation Systems, Inc., Road Safety Audits, Median Cross-Over Crashes, Audit Guidelines, Prepared for MassHighway, October 2007. MS Transportation Systems, Inc. Page 3 I-495 Haverhill Road Safety Audit well as the State Police. A list of the team members contact information are included in the Appendix. As stated previously, overall characteristics and conditions of the study section were presented. The drive-through video and photographs were reviewed and a discussion of the potential safety opportunities for enhancement followed. Highlights of the discussion include the following: • • The long range recommendation (from the I-495 Study) is to widen the highway to four lanes per direction up to Interchange No. 49. Short term recommendations from that study include lengthening the acceleration lanes by modifying the markings. • The River Street (Route 113) area experiences high traffic related to the nearby development. The ramp exit is unsignalized and as a result, there are long delays and queuing by motorists on the off-ramp. The queuing extends to the mainline of I-495 during the PM peak hour. • The merges and weave sections on the southbound direction at both interchanges have some issues that relate to distance, high volumes and visibility. Analysis Procedures As previously indicated, the RSA analysis generally followed the procedure described in the previously referenced Guideline with some variations and also took into consideration the methods published by the Federal Highway Administration2 and those included in training materials3. The basic tasks included: • • • • 2 3 Obtaining and reviewing crash and other traffic characteristic data and available record plans. Conducting site reconnaissance and collecting a current record of condition via photos and video, Identifying opportunities for enhancement, and Identifying and evaluating potential actions to address the noted issues. Federal Highway Administration, FHWA Road Safety Audit Guidelines, Publication No. FHWA SA-06-06, Washington, D.C., 2006. Federal Highway Administration, Resource Center, Road Safety Audits Mini-Workshop, Jeffrey Shaw, PE, PTOE, presented to New England ITE Section, September 19, 2006. MS Transportation Systems, Inc. Page 4 I-495 Haverhill Road Safety Audit In assessing the issues identified by the RSA Team, the relative seriousness and potential risk relative to crash frequency and severity were determined. Using the guidelines of FHWA as input and considering characteristics of this specific RSA, the relative frequency criteria and severity criteria were identified and are presented in Table 1 and Table 2, respectively. TABLE 1 FREQUENCY RATING ESTIMATED Exposure high medium high medium low high Probability high high medium medium high low low medium low medium low low EXPECTED CRASH FREQUENCY (PER AUDIT ITEM) 5 or more crashes per year FREQUENCY RATING Frequent 1 to 4 crashes per year Occasional Less that 1 crash per year, but more than 1 crash every 5 years Infrequent Less than 1 crash every 5 years Rare Source: FHWA RSA Training Workshop TABLE 2 SEVERITY RATING Typical Crashes Expected (per audit item) High-speed crashes; head on and rollover crashes Moderate-speed crashes; fixed object or off-road crashes Crashes involving medium to low speeds; lane changing or sideswipe crashes Crashes involving low to medium speeds; typical of rear-end or sideswipe crashes Expected Crash Severity Probable fatality or incapacitating injury Moderate to severe injury Severity Rating Extreme High Minor to moderate injury Moderate Property damage only or minor injury Low Source: FHWA RSA Training Workshop Taking into consideration both frequency and severity, the relative risk of a particular audit item was rated. The risk ratings are shown in Table 3. For each safety issue identified, the potential seriousness of the issue as well as possible mitigation measures have been indicated. MS Transportation Systems, Inc. Page 5 I-495 Haverhill Road Safety Audit TABLE 3 CRASH RISK ASSESSMENT Frequency Rating Frequent Occasional Infrequent Rare Severity Rating Low Moderate High Extreme C B A A D C B A E D C B F E D C Source: FHWA RSA Training Workshop Crash Risk Ratings: A: minimal risk level B: low risk level C: moderate risk level • D: significant risk level E: high risk level F: extreme risk level RSA Field Audit Field audits were conducted by the RSA team members between on or before October 1, 2008. In general, the field visits included “drive-throughs” in each direction of the study section noting physical conditions and the “feel” of the driver. The Prompt List developed as part of the RSA process was used as a guide. The prompt list is included in the appendix for background information. The RSA field audits took place by team members prior to the RSA team meeting and revealed the following: There are three travel lanes per direction. Posted speeds were noted at 65 mph. The alignment of the roadway section under study is essentially straight with slight vertical changes. The inside shoulder is less than a minimum desired width of 4 feet. Rumble strips exist in both inside and outside shoulders, however, the rumble strips are narrow (i.e. 4-6 inches in width). Embedded markers are located in lane lines. The “open median” is generally located south of the river and can be characterized as depressed. The open median is fairly wide but a portion of it in the immediate area of Interchange No. 48 (Route 125 Connector) is considered crossable. MS Transportation Systems, Inc. Page 6 I-495 Haverhill Road Safety Audit Pavement surface condition was considered to be above average. Lighting is not present in the study section. The separation of Interchanges 48 and 49 was noted as less than ideal. Signage for the interchanges is generally adequate, however, other warning type signage (i.e. merge ahead) may be needed in spots. MS Transportation Systems, Inc. Page 7 I-495 Haverhill Road Safety Audit ANALYSIS In completing the RSA of I-495 in Haverhill, findings were compiled from the field audits, the review of the data, and input provided by team members. The following paragraphs summarize the results from each of the key components of the assessment. The section of I-495 under study is approximately 1.1 miles in length with three (3) lanes per direction separated by a median. The section includes two interchanges: No. 48 at the Route 125 Connector and No. 49 at Route 110. There is approximately one half (0.5) mile separation between the northbound on-ramp from Interchange No. 48 and the northbound off-ramp at Interchange No. 49. The I-495 alignment in the project area is largely straight and slight vertical change. Speeds are posted at 65 miles per hour. The section of highway in the study area for the most part, has an inside shoulder less than 4 feet in width but accommodates rumble strip. There are embedded reflectors in place along the lane lines. Approximately 0.3 miles north of the Interchange No. 48 northbound on-ramp is a 700 foot bridge spanning the Merrimack River. A concrete median barrier begins about 85 feet south of the bridge and continues for 800 feet. North of the bridge, the median is heavily vegetated and guardrail is in place for much of the remaining study section. In addition, this section of I-495 does not have the reflective delineator posts installed alongside the median. The low level of guidance was cited as a potential contributing factor to median related entries particularly during times of low visibility. Figure 2 – I-495 interchange with the Route 125 Connector. MS Transportation Systems, Inc. Page 8 I-495 Haverhill Road Safety Audit The width of the median (measured from presumed edge line to edge line) in the project area is approximately 100 feet. There is only about 200 feet of the median considered “open” north of the Interchange No. 48 ramps due to either guardrail or vegetation in that area. This section south of the overpass, however, has a much longer section of “open” median and was considered crossable by the RSA team members given the southbound geometry, the difference in south-north elevation and the topography of the median. South of the interchange overpass, approximately 1,800 feet of the median is considered open. While the rumble strips were in place in each direction, they were noted as narrow (i.e. 6 inches), which is not the current construction standard. Figure 3 – Northbound approach to the Connector exit. Note elevation difference between two directions. Based on the recent MassHighway traffic counts, the roadway study section carries an average of 124,000 vehicles per day in the study section. Figure 4 illustrates the directional volume over the course of the day for the sections north and south of Route 2. There are two distinct peak hours (AM and PM commuter periods), as well as differences by direction. Peak hour two-way volumes in the AM were approximately 7,800 hour with southbound being the predominant direction. During the PM peak hour, two-way volumes are approximately 9,100 with the northbound direction being higher. Truck volume on this section of I-495 is relatively high with 6% trucks over the course of the day. This equates to more than 7,400 trucks. MS Transportation Systems, Inc. Page 9 I-495 Haverhill Road Safety Audit Figure 4 - I-495 Hourly Traffic Volumes North of Route 125 Connector Figure 5 –The Merrimack River crossing south of Exit 49 in the northbound direction MS Transportation Systems, Inc. Page 10 I-495 Haverhill Road Safety Audit Data available as part of the MassHighway crash records system indicated that between 2004 and 2007, there were 24 reported crashes related to the median. Of the 24, only one crash (4%) was identified as a cross-median crash. However, the one cross-median crash resulted in a fatality. For a relatively short section of highway, it has averaged six median entry crashes per year. Other key findings in the data include: ¾ Seventeen (17) of the 24 crashes or 71% were initiated in the Southbound direction. ¾ Thirty-eight percent (38%) of the reported crashes occurred when the road surface was wet or icy. ¾ Driver related problems (i.e. driving too fast, following too closely) were noted in thirty-three percent (33%) of the crashes. ¾ Of the 24 total crashes, 71% of them (17crashes) resulted in personal injury or the fatality. Figure 6 – Evidence of median entry at the Connector NB exit. MS Transportation Systems, Inc. Page 11 I-495 Haverhill Road Safety Audit SUMMARY OF RSA FINDINGS/POTENTIAL ACTIONS Based on the field review, the review of crash data and discussions among the RSA team members, the issues related to the safe operating conditions of the I-495 in the Haverhill area were identified. While the actual number of median crossings has been of low, the RSA team determined that a number of factors or issues of concern exist at this time that potentially have an effect on the risk. These factors, which also consider the crash type (i.e. cross-over, median related), are listed in Table 4 along with the assigned risk rating. TABLE 4 SUMMARY OF FACTORS THAT POTENTIALLY AFFECT THE RISK OF SAFETY RELATED EVENTS Factor or Issue Risk Rating Open median at Interchange No. 48 is considered crossable D Inside paved shoulder width narrow E1 Rumble strips are in place but narrow E1 Median is not delineated with markers E1 Congestion at Interchange No. 49 results in queues extending to northbound main line C The distance separating Interchange No. 48 entrance and 49 exit is relatively short in northbound direction B Accel-decel lanes at interchanges appear short C High level of truck traffic and high speeds affect passenger vehicle driving behavior C The operations of the collector – distributor (C-D) section at Interchange No. 49 affects the merge and lane changing in SB direction B Overgrown vegetation affects sight distances along C-D road just prior to the merge with I-495 B 1 High risk level related to frequency of median entries not solely cross-overs and severity experience Although the open median section is approximately 100 feet in width and there was a low percentage of cross-over crashes reported in the study period, it was felt by the RSA team that south of the overpass (Connector), the possibility of crossing the median was moderately high. The drive thru indicated that the characteristics of the median slopes, the high volume (124,000+ ADT), the horizontal curve on the mainline and a slight elevation difference (SB higher) could increase the likelihood of entering and crossing MS Transportation Systems, Inc. Page 12 I-495 Haverhill Road Safety Audit the median in that particular area. The one cross-over crash that was reported resulted in a fatality. The open median in this section currently presents a moderate level risk for cross-over events and was assigned a rating of ‘D’. Several factors were identified by the RSA team that could affect the potential for a motorist to either enter the median or recover just prior to entering the unpaved portion of the median. These factors include narrow inside shoulders, narrow rumble strips and the median not being delineated with flexible, reflective posts. They were assigned an ‘E’ given the frequency of median entries (6 per year) and the severity experienced in the reported crashes. The congestion that occurs at the Interchange 49 northbound exit ramp results in vehicle queues extending back onto the I-495 mainline. Figure 7 illustrates this characteristic. This creates a potential hazard that can also lead to “quick” or inappropriate lanechanging. The short distance between the on-ramp from the Route 125 Connector to the off-ramp at Interchange 49 also contribute to the potential hazard as there is not a long distance to see the queuing in advance if one is merging from the Connector onramp. The median entries that were reported in this section involved striking the concrete barrier. This queuing factor was given a rating of ‘C’ as crashes did not necessarily occur during the PM peak hour when the queues exist. The distance factor was assigned a ‘B’ rating R o u te 1 1 3 E x it R a m p Q u e u e s fro m R o u te 1 1 3 4 95 Figure 7 - Ramp queuing occurs during PM peak hours extending to the mainline. Two factors relate to the markings and guidance through the acceleration and deceleration lanes as well as indicating the location of the median. Similar to many of the MS Transportation Systems, Inc. Page 13 I-495 Haverhill Road Safety Audit interchanges noted in the I-495 corridor, the acceleration-deceleration lanes appear to be short. A risk rating of ‘C’ was assigned to this factor. In general, there is a lower level of markings provided resulting in a sense of inadequate lanes, particularly the acceleration lanes. One reason for this low level treatment may be due to inadequately wide shoulders carried through the interchange. Another may be the short distances between interchanges, the C-D road system in the southbound direction and the bridge. This could be checked in detail prior to future implementation or maintenance actions. The I-495 Corridor Study4 suggests in general all of the acceleration and deceleration lanes can be increased along the highway through modifying the markings. Similar to the evaluations of other locations along I-495, the high volume of trucks and the overall high speeds will likely affect the comfort of the driver of a passenger vehicle. As a result of this discomfort, a motorist may initiate some maneuvers including “drifting” into the adjacent lanes to gain more separation from the trucks or making intended “quick” lane-changes without due care. This factor was assigned a rating of ‘C’. The final two factors relate to the collector-distributor road system that is along the SB side of the highway. One factor involves the merge at the Interchange 49 southbound on-ramp to I-495. The other was the noted vegetative overgrowth that can affect visibility that may also have an affect on the just noted merge. Figure 8 illustrates the location of these conditions. A factor of ‘B’ was assigned to these two factors in relation to affecting median entries. COLLECTORDISTRIBUTO R ROADW AY HEAVY VEG ETATION M ERGE AREAS Figure 8 - A Collector-Distributor roadway segment exists in the southbound direction ending at Interchange 49. 4 FST, Inc., I-495 Corridor Transportation Study from Westford to Salisbury, Prepared for EOTPW, June, 2008. MS Transportation Systems, Inc. Page 14 I-495 Haverhill Road Safety Audit Suggested actions identified are intended to reduce the number of and consequences resulting from median related crashes and other types of crashes as well. The following paragraphs include discussion pertaining to the issues and the potential actions to consider for implement. Given the primary objective of this RSA program, the evaluation of a median barrier was first examined. Other actions are presented in a later section of the report. • Consideration of a Median Barrier One of the more significant actions that could be considered for the study section is to install median barriers in the current “open” areas. Although the RSA team found the open median section was fairly wide, the section was evaluated in terms of the median barrier warrants. A barrier can be considered when there is a higher than desirable chance or a greater risk for median cross-over crashes to occur and that have or could result in fatalities and/or a high proportion of injury related crashes. A barrier could also be considered when the consequences or severity of a crash without a barrier are worse than if the barrier were in place. Factors that generally come into play in deciding on whether a median should be installed involve the following: High volumes and speeds Truck volumes and mix Narrow median History of cross-median crashes High risk of catastrophic event These items have been reviewed relative to the I-495 section under study, primarily the median section south of the Interchange No. 48 overpass. Figure 9 presents a review of the corridor in relation to the median warrant criteria presented in the AASHTO RDG5. As can be seen in the diagram, with the median (as measured from edge line to edge line) is approximately 100 feet and a volume of over 120,000 vehicles on an average day, the intersection of the two items is in the area of the chart where a barrier can be “optional”. With the median approximately 100 feet in width, the point of intersection is actually off the chart. 5 American Association of State Highway and Transportation Officials, Roadside Design Guide, Washington, D.C., 2002, Chapter 6 Update 2006. MS Transportation Systems, Inc. Page 15 median width 100 +/- feet ADT 124,000+ 80 AVERAGE DAILY TRAFFIC (thousands) 70 BARRIER RECOMMENDED 60 BARRIER CONSIDERED 50 40 BARRIER OPTIONAL 30 20 10 0 0 10 20 30 40 50 60 70 MEDIAN WIDTH (feet) Median Barrier Warrant Analysis Interstate-495 Road Safety Audit Haverhill, Massachusetts MS Transportation Systems, Inc. NOT TO SCALE Framingham, Massachusetts Figure 9 I-495 Haverhill Road Safety Audit However, in addition to the analyzed AASHTO warrant criteria, which is a guideline, consideration was also given to the following: The southbound curve on the mainline and being higher than the northbound direction creates a certain level of driver discomfort. A clear, open and relatively flat topography of the median south of the overpass for approximately 1,800 feet. A cross-median crash did occur and resulted in a fatality. Consequently, based on the analysis of the data, the field audit and drive-thru and discussion of the conditions by the RSA team members, it was concluded that a median barrier should be considered on this section of I-495 south of the Interchange No. 48 overpass to the point where a guardrail and thick vegetation exists at the southern end of the section. As will be discussed in the next section, however, there are a number of other actions also recommended as part of this RSA. MS Transportation Systems, Inc. Page 17 I-495 Haverhill Road Safety Audit Recommendations As a result of the RSA analysis and team input and although it was concluded that a median barrier be installed at this time in a portion of the project section. All the recommendations have been identified and are summarized in Table 7. These actions are intended to eliminate the chance of cross-median crashes as well as reduce the number and severity of all crashes of this section of I-495 in Haverhill. Identified in the table in addition to the risk factor and recommended action are the estimated costs and potential timeframe (i.e. short (0-1 year), medium (1-3 years) and long (>3 years)). TABLE 7 SUMMARY OF RECOMMENDATIONS Risk Factor Risk Rating Recommended Action Estimated Cost Open median at Interchange No. 48 is considered crossable D Inside paved shoulder width narrow E1 Rumble strips are in place but narrow E1 Median is not delineated with markers Install cable median barrier $50,000 Medium to long term Widen shoulder to minimum of 4 feet TBD Long term – as part of future rehab Install new rumble that meets current practices $4,000 Long term – as part of future rehab and shoulder widening E1 Install flexible, reflective yellow posts $1,700 Short to medium term Congestion at Interchange No. 49 results in queues extending to northbound main line C Install warning signs The exit ramp needs to be treated with signal $8,000 $300,000 Short term Long term The distance separating Interchange No. 48 and 49 is relatively short B Install warning signs $5,000 Short term Accel-decel lanes at interchanges appear short C Add markings where feasible TBD Short term Provide motorist reminders of “safe driving” thru VMS sign program Increased enforcement $10,000 Short term using portable VMS equipment Long term with permanent VMS Install improved markings and signage $5,000 Short term trim and remove vegetation TBD Short term Level of truck traffic and the effect on passenger driving behavior C The collector – distributor section at Interchange No. 49 B Overgrown vegetation affects sight distances along C-D road just prior to the merge with I-495 B TBD – to be determined Estimated Timeframe TBD 1 ratings reflect frequency of median entries and experienced severity. MS Transportation Systems, Inc. Page 18 I-495 Haverhill Road Safety Audit As indicated in the table, it is recommended, that a median barrier be installed in the section south of the Route 125 Connector interchange as shown in Figure 10. While the median is relatively wide (100 feet), it did experience a cross-median crash resulting in a fatality. It was also noted that some driver discomfort exists in the southbound direction through this interchange given the horizontal curve, elevation difference in directions and the high volume of weaving and merging traffic that occurs at the interchange in the SB direction. The length of barrier is estimated to be approximately 1,800 feet. If cable is utilized, the estimated cost would be $50,000. OPEN MEDIAN Route 125 Connector INSTALL MEDIAN BARRIER APPROX. 1,800 FEET 495 Figure 10 – Proposed Location of Median Barrier It was also recommended that improved delineation of the median be implemented via reflectorized, flexible posts. In addition, it was recommended that the inside shoulder be set wide enough to effectively accommodate a rumble strip that is re-installed in line with current design practices. Ideally, the inside paved shoulder would be a minimum of four (4) feet in width. The widening is proposed as a long term item as part of any future planned rehabilitation project, given its cost. The incremental cost if done in conjunction with complete rehabilitation or resurfacing project will tend to be lower than implementing a separate box widening. Based on input from RSA team members, drainage adjustments would be implemented at that time as well. The rumble strip would need to be re-installed with the shoulder widening. MS Transportation Systems, Inc. Page 19 I-495 Haverhill Road Safety Audit In addition, it was noted by the RSA team that a reflective markers were not along side the median. It is recommended that this action be implemented in the short to medium term. It is recommended that improved markings be provided for the acceleration and deceleration lanes including the gore areas. This could be accomplished through a combination of markings and signage. Consistent, high visibility markings such as those shown in Figures 11 or 12 should be considered. However, the outside shoulder width may be an issue regarding lengthening the lane lines. The previously noted I-495 study noted that most acceleration-deceleration lanes were deficient and could be corrected by modifying the markings only. This should be examined in more detail by the District engineers when scheduling pavement marking maintenance activities in the future. Travel speeds and driver behavior has been cited and observed to be a problem on I-495 where volumes in the range of 120,000 ADT. Increased enforcement presence is essential in addressing this behavior. This will require additional funding. The high volume of truck traffic also affects driver comfort levels and lane changing behavior. This section of I-495 is a major trucking route and the volume is not expected to reduce. A passive action discussed was the use of VMS signage as a way to encourage more positive driver behaviors such as caution, courtesy, etc. The VMS package could also be used to inform motorists of congestion and downstream delays as a way to also encourage some patience and better drive decision. Standard messages similar to the “click it or ticket” message could be displayed on a regular basis. Other signage improvements are recommended for motorist warning of the potential ramp queues, the short distance between Interchange Nos. 48 and 49 in the northbound direction and along the C-D roadway in the southbound direction. Finally, the vegetation overgrowth that has occurred along the Interchange No. 49 ramps near the C-D road should be trimmed and cut back to maximize visibility. MS Transportation Systems, Inc. Page 20 Broken lane markings for one-half of full-width deceleration lane Channelizing lines Parallel acceleration lane Source: MUTCD Potential Pavement Markings On-Ramp Merge Locations I-495 Road Safety Audit Haverhill, Massachusetts MS Transportation Systems, Inc. NOT TO SCALE Framingham, Massachusetts FIGURE 11 a-Parallel deceleration lane b-Tapered deceleration lane Neutral area Optional chevron markings Channelizin g lines Theoretical gore point Channelizing lines Broken lane markings for one-half of full-width deceleration lane Optional dotted extension of lane line Legend Direction of travel SOURCE: MUTCD Potential Pavement Markings Off-Ramp Deceleration Lanes I-495 Road Safety Audit Haverhill, Massachusetts MS Transportation Systems, Inc. NOT TO SCALE Framingham, Massachusetts FIGURE 12 I-495 Haverhill Road Safety Audit Appendix • • • • • • MS Transportation Systems, Inc. RSA Meeting Agenda RSA Attendees List Median Crash Diagram Crash Data Traffic Volume Data Environmental Constraints Exit 48 and Exit 49 (from I495 study) Page 23 Road Safety Audit Haverhill – Interstate 495 Meeting Location: MassHighway District 4 Office 519 Appleton Street, Arlington Wednesday, October 1, 2008 11:00 AM – 12:30 PM Type of meeting: Cross Median – Road Safety Audit Attendees: Invited Participants to Comprise a Multidisciplinary Team Please bring: Thoughts and Enthusiasm!! 11:00 AM Welcome and Introductions 11:15 AM Introduction to Road Safety Audits and Cross Median Crashes 11:30 AM Review of Site Specific Material • Crash & Volume Summaries– provided in advance • Existing Geometries and Conditions • Video and Images 12:00 PM Completion of RSA • Identification of Safety Concerns – using RSA Prompt List as a guide • Identification of Possible Countermeasures 12:30 PM Adjourn for the day – but the RSA has not ended Instructions for Participants: • Before attending the RSA on October 1st participants are encouraged to drive Interstate 495 near interchange 48 and 49 and complete/consider elements on the RSA Prompt List with a focus on safety factors affecting cross median crashes. • All participants will be actively involved in the process throughout. Participants are encouraged to come with thoughts and ideas, but are reminded that the synergy that develops and respect for others’ opinions are key elements to the success of the overall RSA process. • After the initial RSA meeting, participants will be asked to comment and respond to the document materials to assure it is reflective of the RSA completed by the multidisciplinary team. ROAD SAFETY AUDIT MEETING I-495 Haverhill October 1, 2008 MassHighway District 4 Offices, Taunton MA Attendance List Name Agency/Dept. Email Bill Scully MS Transportation Systems, Inc. bscullyjr@mac.com Lisa Schletzbaum MHD - Safey lisa.schletzbaum@mhd.state.ma.us Anthony Komornick MVPC AKomornick@mvpc.org Paul Fletcher Mass State Police Paul.Fletcher@Pol.State.ma.us Frank Welch MHD, District 4 Frank.Welch@mhd.state.ma.us John Gregg MHD, Traffic John.Gregg@mhd.state.ma.us Chris Leahy MHD, District 4 Highway Christopher.Leahy@mhd.state.ma.us Christine Breen MHD Christine.Breen@mhd.state.ma.us Xian Chen MHD Xian.Chen@mhd.state.ma.us Tim White FHWA Timothy.A.White@fhwa.dot.gov Slave Podluzny MHD, District 4 Slave.Podluzny@mhd.state.us.ma MS Transportation Systems, Inc. ± FOREST STREET Interstate 495 Median Crashes 1-2 WEST LOWELL AVENUE 3-5 LO WELL AV ENUE 49 N TO NG ET RE ST 6 7 HAVERHILL L EL W UE I SH WA ) " " ) RI V ER STR EE T 110 LO EN AV 8 9 ) " 110 10 § ¦ ¨ 495 11 METHUEN " ) 48 Crash IDs between 12 - 19 Legend 22 20 - 21 R LY EL SH Type of Median Crash 2004 - 2007 * D OA Cross Median, Fatal Crash 23 Median, Non-Fatal Crash Major Roads R FE Interstate K AC Minor Arterial S TR EET Collector Local Municipal Boundary * 2007 crash file has not yet been closed. 0.1 0.2 " ) IM RR ME Principal Arterial 0 RO AD 0.3 Miles 0.4 RY R AD O ) " 125 N RO AD BOSTO NE CK MASSACHUSETTS HIGHWAY SAFETY DIVISION MEDIAN-RELATED CRASH SUMMARY ROADWAY: STUDY PERIOD: I-495 1/1/2004 TO 12/31/2007 09/23/06 TRAVEL DIRECTION SB LIGHT CONDITION Dark- Not lighted WEATHER CONDITION Clear ROAD SURFACE Dry 7:30 PM 8:50 AM 12:21 PM 12/24/04 07/07/07 04/30/07 SB SB SB Dark-Lighted Not Reported Daylight Clear Clear Clear Dry Dry Dry Wednesday 11:40 AM 08/24/05 SB Daylight Clear Dry 2014810 1999816 2114736 Monday Saturday Monday 5:50 PM 3:15 AM 6:50 AM 02/20/06 10/08/05 09/04/06 SB NB NB Dark-Not Lighted Dark-Not Lighted Daylight Clear Rain Clear Dry Wet Wet NO. CRASH NUMBER CRASH DAY TIME OF DAY CRASH DATE 1 2114754 Saturday 11:45 PM 2 3 4 1881083 2228495 2244810 Friday Saturday Monday 5 2040237 6 7 8 9 1915739 Thursday 8:40 PM 01/06/05 NB Dark-Not Lighted Sleet Ice 10 11 2180438 2050290 Saturday Sunday 8:47 PM 4:00 PM 08/26/06 03/26/06 SB SB Dark-Lighted Daylight Clear Clear Dry Dry 12 13 2266266 2249038 Monday Sunday 10:53 PM 3:55 PM 12/03/07 10/28/07 SB SB Dark- Not lighted Daylight Snow Clear Ice Dry 14 15 2059593 2209999 Sunday Wednesday 4:10 PM 11:40 PM 01/01/06 04/04/07 NB SB Dark-Lighted Dark- Not lighted Clear Snow Wet Snow 16 17 1890007 2059737 Friday Monday 9:20 AM 9:53 AM 12/10/04 06/05/06 SB SB Daylight Daylight Clear Clear Dry Dry 18 2014653 Friday 12:10 PM 02/24/06 SB Daylight Clear Dry 19 2059612 Tuesday 3:30 AM 01/31/06 SB Dark-Not Lighted Sleet Ice 20 2014784 Sunday 6:30 AM 02/12/06 SB Dawn Snow Snow 21 1794857 Thursday 6:10 PM 07/15/04 NB Daylight Clear Dry 22 23 24 1761334 1898649* 1999937 Tuesday Saturday Thursday 9:52 PM 12:15 PM 3:03 PM 08/03/04 09/11/04 11/22/05 NB NB SB Dark-Not Lighted Daylight Daylight Clear Clear Rain Dry Dry Wet NOT REPORTED 1 4% DAWN 1 4% CITY: Haverhill LOCATION: Exit 48 REASON FOR VEHICLE RUNNING OFF ROAD LEFT MOVEMENT Driver lost control of the vehicle due to tire blowout and spun into the median guardrail Middle travel lane into median guardrail Vehicle was involved in a multi car crash; vehicle was struck and driver lost control and spun out into the median and struck a tree Right travel lane across all SB lanes into median Driver lost control of the vehicle, entered the median and went behind a guardrail and struck some trees Left travel lane into median Vehicle was struck by another vehicle changing lanes causing the driver to lose control and drive into the median Middle travel lane into median Driver braked and turned left to avoid traffic, lost control of the vehicle, and struck the left guardrail on bridge over Middle travel lane into bridge guardrail Merrimack River Driver stated she was cut off by another vehicle and over-steered to the left and skidded into the median struck a tree and Middle travel lane into median rolled over Driver stated he hydroplaned and spun out into the median Middle travel lane into median Driver lost control of vehicle for unknown reason and spun into the median and struck a tree Middle travel lane into median Driver lost control due to heavy ice on the roadway and struck the left guardrail on the Merrimack River bridge then hit the Middle travel lane into left bridge guardrail across NB lanes right guardrail Driver lost control for unknown reason and hit the median barrier then spun out across all SB lanes into a ditch on the right Left lane into median barrier and across all SB lanes into side of the road ditch Vehicle was cut off by another vehicle and driver lost control and spun out into the median and rolled over Middle travel lane into median Driver lost control of vehicle due to weather conditions and spun into the median and rolled over Left travel lane into median Operator stated that she was cut off which caused her to drive into the left median guardrail Left travel lane into median guardrail Driver was in the left travel lane and struck the left guardrail for unknown reason and then struck another vehicle before Left travel lane into median guardrail then across all NB hitting the right guardrai lanes Driver swerved to avoid a vehicle traveling NB in SB lanes and crashed into the median guardrail Middle travel lane into median guardrail Driver swerved to avoid a tire in the road but struck it which caused one of her tires to blow out and she lost control and rolle Left travel lane into median over in the median Driver was cut off by another vehicle and swerved into the median Middle travel lane into median Car was cut off by an unknown vehicle and swerved in front of a TT unit which struck the vehicle and then went over the Middle travel lane over guardrail and down embankment median guardrail Driver was attempting to change lanes due to a merging truck and lost control possibly due to ice and struck the left guardrail Right travel lane into left guardrail Right travel lane across NB lanes and into median Driver lost control due to snowy conditions and hit the median guardrail guardrail Driver was not able to stop in time and struck the vehicle in front of him, which then struck another vehicle; all three came to Left lane into median rest in median Driver was traveling at extreme speeds and lost control of the vehicle, veered into the median, crossed median and went Left travel lane across median into SB lanes airborne into the SB lanes Driver was cut off and swerved to avoid collision and lost control of the vehicle and struck the median guardrail Right travel lane across NB lanes into median guardrail Vehicle was struck by a truck making an illegal U-turn through the median and came to rest in the middle of the median Left travel lane into median * COULD NOT BE LOCATED BY GEOCODER TOTAL NO. 24 100% DAYLIGHT 11 46% LIGHT CONDITION DARK -NOT LIGHTED DARK-LIGHTED 9 2 38% 8% MEDIAN OR CROSS MEDIAN TOTAL NO. 24 100% MEDIAN CROSS MEDIAN FATAL 23 96% 1 4% 1 4% CRASH SEVERITY NON-FATAL PROPERTY INJURY DAMAGE ONLY 16 7 67% 29% WEATHER CONDITION SNOW RAIN CLEAR 17 3 2 71% 13% 8% SLEET 2 8% ROAD SURFACE DRY WET SNOW ICE 15 63% 4 17% 2 8% 3 13% DRIVER CONTRIBUTING CAUSE TOTAL NO. FATIGUED/ ASLEEP OVER-CORRECTING/ OVER-STEERING FOLLOWED TOO CLOSELY EXCEEDED AUTHORIZED SPEED LIMIT DRIVING TOO FAST FOR CONDITIONS MADE AN IMPROPER TURN NO IMPROPER DRIVING NOT REPORTED OPERATING VEHICLE IN AN ERRATIC, CARELESS, AGGRESSIVE. MANNER 24 100% 1 4% 1 4% 1 4% 1 4% 3 13% 1 4% 8 33% 7 29% 1 4% 2007 CRASH INFORMATION IS NOT COMPLETE CRASH SUMMARY IS BASED ON CRASH REPORTS WITH STATE POLICE NARRATIVES MEDIAN OR CROSS MEDIAN CRASHES Median DRIVER CONTRIBUTING CAUSE No improper driving CRASH SEVERITY Non-Fatal Injury Median Median Median Fatigued/ asleep Not reported Not reported Non-Fatal Injury Property Damage Only Property Damage Only Median No improper driving Non-Fatal Injury Median Median Median No improper driving Not reported Not reported Non-Fatal Injury Non-Fatal Injury Non-Fatal Injury Median Driving too fast for conditions Non-Fatal Injury Median Median No improper driving No improper driving Non-Fatal Injury Non-Fatal Injury Median Median Property Damage Only Property Damage Only Median Median Not reported Not reported Operating vehicle in a reckless, careless manner Not reported Median Median No improper driving Over-correcting/ over-steering Non-Fatal Injury Property Damage Only Non-Fatal Injury Non-Fatal Injury Median Made an improper turn Property Damage Only Median Driving too fast for conditions Non-Fatal Injury Median Driving too fast for conditions Non-Fatal Injury Median Followed too closely Non-Fatal Injury Cross Median Median Median Exceeded authorized speed limit No improper driving No improper driving Fatal Injury Property Damage Only Non-Fatal Injury Rte. I-495 Haverhill, North of Rte. 125 Conn. Tuesday, June 26, 2007 Start Time Northbound Southbound 12:00 AM 566 470 1:00 AM 352 347 2:00 AM 315 283 3:00 AM 300 317 4:00 AM 516 788 5:00 AM 999 2568 6:00 AM 1856 4525 7:00 AM 2619 5257 8:00 AM 2941 4891 9:00 AM 3561 3431 10:00 AM 3804 2911 11:00 AM 3672 2699 12:00 PM 3472 3328 1:00 PM 3454 3354 2:00 PM 3747 3625 3:00 PM 4755 4031 4:00 PM 5027 4112 5:00 PM 5213 3807 6:00 PM 4426 3200 7:00 PM 2895 2489 8:00 PM 2414 2260 9:00 PM 2003 1951 10:00 PM 1535 1452 11:00 PM 918 945 Total 1036 699 598 617 1304 3567 6381 7876 7832 6992 6715 6371 6800 6808 7372 8786 9139 9020 7626 5384 4674 3954 2987 1863 Daily Total 124401 61360 63041 6000 5000 4000 Northbound Southbound 3000 2000 1000 Time of Day PM :0 0 PM 10 8: 00 PM 00 PM 6: 00 4: 00 2: 0 :0 PM PM AM 12 :0 0 AM 10 8: 00 AM 00 AM 6: 00 AM 4: 00 2: :0 0 AM 0 12 Hourly Volumes (Number of Vehicles) Directional Traffic Volumes along I-495 Haverhill North of Rte 125 Conn. Tuesday, June 26, 2007