ROAD SAFETY AUDIT MAJOR HIGHWAY MEDIAN CROSS-OVER CRASHES I-95 DANVERS-TOPSFIELD Prepared for Massachusetts Highway Department Prepared by MS Transportation Systems, Inc. Framingham, Massachusetts March 2009 ROAD SAFETY AUDIT MAJOR HIGHWAY MEDIAN CROSS-OVER CRASHES I-95 DANVERS-TOPSFIELD FINAL REPORT March 2009 Prepared for Massachusetts Highway Department Prepared by MS Transportation Systems, Inc. Consulting Engineers and Planners 300 Howard Street, P.O. Box 967 Framingham, Massachusetts 01701 Tel: (508) 620-2832 Fax: (508) 620-6897 www.mstransportationsystemsinc.com I-95 Danvers-Topsfield Road Safety Audit TABLE OF CONTENTS Page INTRODUCTION 1 RSA PROCESS 3 ANALYSIS 8 SUMMARY OF RSA FINDINGS/POTENTIAL ACTIONS 13 RECOMMENDATIONS 22 APPENDIX 26 MS Transportation Systems, Inc. Page i I-95 Danvers-Topsfield Road Safety Audit INTRODUCTION Lane departure crashes are one of the primary fatal crash types in Massachusetts. The Commonwealth exceeds the national average for lane departure crashes and was designated a lead state in lane departure crashes by the American Association of State Highway and Transportation Officials (AASHTO). The Massachusetts Highway Department (MHD) conducted a study of the problem and found that during 2002-2004, lane departure crashes accounted for 25 percent of all injury crashes and nearly half, 46 percent, of all fatal crashes. As part of the effort in implementing the safety plan and specifically reducing lane departure crashes, the MassHighway is completing a Road Safety Audit (RSA) Review Project specifically focused on median crossing (or median cross-over) crashes on its major highways. Road safety audits are a formal safety performance examination on existing or future roadways by an independent audit team. These specific audits are being conducted in locations where cross-over experience has been or has the potential to be of concern and where the RSA team has judged that factors exist that could affect the safety risk. During the audit, the RSA team works to identify opportunities for enhancing safety and to recommend specific enhancements intended to reduce median cross-over crashes and improve the overall safety along the highway. An RSA was conducted for the I-95 in Danvers and Topsfield as part of this overall effort. The roadway section under study, shown in Figure 1, was between Interchange (approximately 1,000 south of No. 49) and Interchange No. 53 a distance of 7.4 miles. This section had experienced a number of median related crashes that included several reported cross-over incidents. The purpose of this I-95 Danvers-Topsfield RSA was to review current safety characteristics on the highway section under study, identify potential risk factors and to recommend a set of actions to enhance the safe operation of the highway section under study. Recommendations contained in this report reflect the overall consent of the RSA team and do not necessarily reflect the official opinions of MassHighway. MS Transportation Systems, Inc. Page 1 MS Transportation Systems, Inc. Middleton 95 95 95 Interchang e 51 Interchang e 52 Interchang e 53 Topsfield Interchang e 49 Interchang e 50 Danvers W I-95 Road Safety Audit Danvers-Topsfield, Massachusetts S N E Project Location Figure 1 I-95 Danvers-Topsfield Road Safety Audit RSA PROCESS In conducting the RSA, the overall procedures outlined in the Median Cross-Over RSA Guideline Report1 with some modifications given the characteristics of the facility being reviewed. The process included identifying RSA team members; conducting field visits; holding a RSA team meeting and then completing an assessment of the data and findings from the field visits and meetings to render recommended actions for MassHighway to consider. Data including recent traffic volume data, summary crash records for the 2004-2007 period, detailed crash reports of cross-over crashes, and available record highway plans were obtained and reviewed by the RSA consultant. In addition, maintenance records related to the cable barrier since late 2006 were provided by the Department. Field visits were conducted by the RSA team members. A video recording of the sections under study was taken by the RSA Consultant. The site visits were completed prior to the RSA team meeting that was held on July 31, 2008 at the MassHighway District 4 offices. At that meeting, the RSA consultant provided a brief overview of the RSA purpose, a summary of the roadway section’s characteristics and results of the review to date. The RSA team provided input and discussed the key items noted in the field and that were listed on the RSA Median Cross-Over Prompt List. Issues and concerns were noted. Following the RSA meeting, the RSA consultant compiled the information, completed the analysis and circulated the draft report. • RSA Team The following were members of the I-95 Danvers-Topsfield Road Safety Audit: Lyris Liautaud, MassHighway Design Bonnie Polin, MassHighway Safety Kaiyan Jiang, MassHighway Design Efi Pagitsas, Boston Region MPO Andrew Hirshfield, MassHighway Traffic Tim White, Federal Highway Admin. • Paul Fletcher, Mass State Police “A” Brett Loosian, MassHighway District 4 Maint. John Gregg, MassHighway District 4 Traffic Lisa Schletzbaum, MassHighway Safety William J. Scully, MS Transportation Systems (RSA Consultant) RSA Team Meeting The RSA team meeting took place on July 31, 2008 at the District 4 offices in Arlington. The team included engineers, planners and a representative from the State Police barrack that has jurisdiction of I-95 in Danvers and Topsfield. Represented were MassHighway (Boston and District), as well as the State Police. A list of the team members at the meeting with contact information is included in the Appendix. As stated 1 MS Transportation Systems, Inc., Road Safety Audits, Median Cross-Over Crashes, Audit Guidelines, Prepared for MassHighway, October 2007. MS Transportation Systems, Inc. Page 3 I-95 Danvers-Topsfield Road Safety Audit previously, overall characteristics and conditions of the study section were presented. A video and still photographs were reviewed by the RSA team and a discussion of the potential safety opportunities for enhancement followed. The key items discussed at that meeting included the following: While the overall geometric design of the highway appears efficient and results in a comfortable drive, the condition also contributes to high speeds. The RSA team did not have data available, but the Mass State Police stated that the 80-85 mph range was likely. There are two segments in the study section that contain horizontal curves and downgrades following long straight sections. These are: northbound on approach to Interchange No. 51; and the southbound approach to Interchange No. 49. In these two segments, RSA team members noted that crashes occurred in these areas in which a combination of the speeds, geometry condition and level of guidance appear to have led to “missing” the curve and entering the median. There was further discussion that the data currently available to the RSA team not being accurate enough to clearly cite that the curves are definitively the problem, although that is the perception and recollection. Sun glare is another problem that affects visibility at different times of the day. While there was clear evidence of a substantial number of median cross-over crashes (41% of the total median related crashes), there was much discussion of whether a barrier should be considered given the average width of the median in the study section. • Analysis Procedures As previously indicated, the RSA analysis generally followed the procedure described in the previously referenced Guideline with some variations and also took into consideration the methods published by the Federal Highway Administration2 and those included in training materials3. The basic tasks included: • 2 3 Obtaining and reviewing crash and other traffic characteristic data and available record plans. Federal Highway Administration, FHWA Road Safety Audit Guidelines, Publication No. FHWA SA-06-06, Washington, D.C., 2006. Federal Highway Administration, Resource Center, Road Safety Audits Mini-Workshop, Jeffrey Shaw, PE, PTOE, presented to New England ITE Section, September 19, 2006. MS Transportation Systems, Inc. Page 4 I-95 Danvers-Topsfield Road Safety Audit • • • Conducting site reconnaissance and collecting a current record of condition via photos and video, Identifying opportunities for enhancement, and Identifying and evaluating potential actions to address the noted issues. In assessing the issues identified by the RSA Team, the relative seriousness and potential risk relative to crash frequency and severity were determined. Using the guidelines of FHWA as input and considering characteristics of this specific RSA, the relative frequency criteria and severity criteria were identified and are presented in Table 1 and Table 2, respectively. ESTIMATED Exposure high medium high medium low high Probability high high medium medium high low low medium low medium low low TABLE 1 FREQUENCY RATING EXPECTED CRASH FREQUENCY (PER AUDIT ITEM) 5 or more crashes per year FREQUENCY RATING Frequent 1 to 4 crashes per year Occasional Less that 1 crash per year, but more than 1 crash every 5 years Infrequent Less than 1 crash every 5 years Rare Source: FHWA RSA Training Workshop TABLE 2 SEVERITY RATING Typical Crashes Expected (per audit item) High-speed crashes; head on and rollover crashes Moderate-speed crashes; fixed object or off-road crashes Crashes involving medium to low speeds; lane changing or sideswipe crashes Crashes involving low to medium speeds; typical of rear-end or sideswipe crashes Expected Crash Severity Probable fatality or incapacitating injury Moderate to severe injury Severity Rating Extreme High Minor to moderate injury Moderate Property damage only or minor injury Low Source: FHWA RSA Training Workshop MS Transportation Systems, Inc. Page 5 I-95 Danvers-Topsfield Road Safety Audit Taking into consideration both frequency and severity, the relative risk of a particular audit item was rated. The risk ratings are shown in Table 3. For each safety issue identified, the potential seriousness of the issue as well as possible mitigation measures have been indicated. TABLE 3 CRASH RISK ASSESSMENT Frequency Rating Frequent Occasional Infrequent Rare Severity Rating Low Moderate High Extreme C B A A D C B A E D C B F E D C Source: FHWA RSA Training Workshop Crash Risk Ratings: A: minimal risk level B: low risk level C: moderate risk level • D: significant risk level E: high risk level F: extreme risk level RSA Field Audit Field audits were conducted by the RSA team members between on or before July 31, 2008. In general, the field visits included “drive-throughs” in each direction of the study section noting physical conditions and the “feel” of the driver. The Prompt List developed as part of the RSA process was used as a guide. The prompt list is included in the appendix for background. The field audits showed the following: There are four travel lanes per direction within the project area. With the exceptions noted below, the overall alignment of the study section can be characterized as gentle with several horizontal curves. While overall this portion of I-95 has a gentle overall alignment, there are two curves that affect the degree of driver comfort, the southbound curve south of Interchange No. 50 is slightly discomforting to motorist in high speed lane – a similar feeling occurs in the northbound direction south of Interchange No. 51. North of Interchange No. 51, the highway is fairly tangent and level providing a high degree of driver comfort. The median varies in width and slope through out study section from gentle depressed slope to relatively steep east to west downgrade. Inside shoulders are 2 to 3 feet in width with a rumble strip in place. Rumble strips also exist in outside shoulder. Recessed reflectors exist in lane lines. Pavement surface is in good condition. MS Transportation Systems, Inc. Page 6 I-95 Danvers-Topsfield Road Safety Audit Pavement markings are in good condition. There are no delineator posts or other guidance provided along the median. Speeds are posted at 65 miles per hour. There was physical evidence (i.e. tire tracks) of several median entries noted. In general, it was noted that the drive along the study section even during peak periods is generally free with four lanes of capacity available. MS Transportation Systems, Inc. Page 7 I-95 Danvers-Topsfield Road Safety Audit ANALYSIS In completing the RSA of I-95 in Danvers-Topsfield, findings were compiled from the field audits, the review of the data input provided by team members. The following sections summarize the results from each of the key components of the assessment. I-95 in the Danvers-Topsfield area is a major north-south highway serving the communities to the north of Boston. The section under study is approximately 7.4 miles long consisting of 4 travels lanes per direction with 10 foot outside shoulders. There are five (5) interchanges located in the study section. Interchange No. 53 is actually in Boxford. Inside shoulders were noted in the field as being between 1 and 3 feet in general depending on location. Rumble strips are present in both shoulders. There is no other delineation of the median other than the inside edge line. Reflectorized markers (slotted in pavement) have been installed in the lane lines. The roadway alignment in the study section is largely straight including a nearly 2.0 mile long tangent section. Two large radius horizontal curves on the north (south of Interchange 51) and south (south of Interchange 50) exist at the ends of that 2 mile tangent section. The overall pavement section appears to be in good condition as well as the markings currently in place. Most of the median is “open” with 6.3 miles or 85% of the total 7.4 mile long study section in this category. The open median width was determined along the study section and measured for the most part between 80 and 88 feet. South of Interchange No 49, the median narrows to approximately 35 feet. Field visits identified evidence of median entries along the study section, particularly noted between Interchanges Nos. 49 and 51. Approximately half of the open median length is in this particular area. Figure 2 – Median Section of I-95 MS Transportation Systems, Inc. Page 8 I-95 Danvers-Topsfield Road Safety Audit The median is a depressed design for most of the corridor section. For the most part, the slope of the median appears to be 6:1 or flatter, which would be consistent with the typical section plans that were the basis of the initial design. In several areas, there is a small elevation differential between the northbound and southbound directions. In these areas, the median has a somewhat longer straight down slope from one side to the other but maintains the depressed design close to the center of the median. There are several overpasses that exist along the study section and the columns supporting the bridge crossings (i.e. Route 1) are not all protected from the driving public with the placement of guardrail. The columns may in fact be outside the 30 foot clear zone but still pose a risk as the median has been determined to be crossable. The pavement edge along the median appeared adequate with no significant drop off noticeable. Posted speed limits in the study section were noted at 65 miles per hour (mph). General observations by the State Police suggest that speeds in the 80-85 mph range would not be unlikely. The high speeds along with the combined long tangent, downgrade sections prior to the curves appear to be a contributing factor to higher risks. Figure 3 – Northbound on I-95 approaching Route 62 Interchange MS Transportation Systems, Inc. Page 9 I-95 Danvers-Topsfield Road Safety Audit Figure 4 – Example of inside shoulder with rumble strip Data available as part of the MassHighway crash records system indicated that between 2004 and 2007, there were 27 reported crashes related to the median. Of the 27, 41% or 11 were identified as cross-median crashes. The 11 cross-median crashes Figure 5 – Approaching curve in Northbound direction prior to Interchange No. 49 resulted in personal injuries in 82% of the crashes. There was one fatal crash reported which was also a cross-median crash. The fatality occurred south of Interchange No. 51 with a vehicle in the northbound direction initiating the event. In most crashes, the cited cause for the cross-median crashes were either the driver “swerving”, reckless, failing to stay in proper lane or speed. Five (19%) of the total median related crashes involved “falling asleep or fatigue”, while six weather related crashes (22%) with wet road surface were noted. Three (3) of the crossmedian crashes occurred during dark conditions. There was no significant directional difference in reported crashes. Figure 6 - Unprotected bridge columns in median at Route 1 Overpass Conditions that were noted in the crash reports varied. There were no predominant factors or causes for the crashes. Included were inattention or equipment problems in addition to the previously noted causes. MS Transportation Systems, Inc. Page 6 I-95 Danvers-Topsfield Road Safety Audit Traffic volumes collected in 2007 show I-95 in the project area carrying approximately 80,000 vehicles per day. Peak hour flows in the peak direction as high as 5,300 vehicles. As shown in Figures 8 and 9, there is both a distinct peaking pattern of volume on I-95 as well as a directional flow pattern that clearly reflects commuter activity to and from Boston and its surrounding areas. Available truck volume data for I-95 in the project area indicated that truck volume over the course of the day represents 5% of the total volume equating to approximately 4,000 trucks on an average weekday. It was also noted by the RSA team that a “reduced salt area” exists between the Route 1 interchange (Exit 50) to Route 133 north of the study section. Signs were not observed in the study area. Figure 7 - Small elevation differential between directions MS Transportation Systems, Inc. Page 11 I-95 Danvers-Topsfield Road Safety Audit Figure 8 – I-95 Traffic Volumes North of Route 1 Figure 9 – I-95 Traffic Volumes North of Route 62 MS Transportation Systems, Inc. Page 12 I-95 Danvers-Topsfield Road Safety Audit SUMMARY OF RSA FINDINGS/POTENTIAL ACTIONS Based on the field review, the review of crash data and discussions among the RSA team members, the issues related to the safe operating conditions of the I-95 in the Danvers-Topsfield area were identified. There were a number of factors or issues of concern that were identified as potentially having an effect on the risk and these are listed in Table 4 along with the assigned risk rating. TABLE 4 SUMMARY OF FACTORS THAT POTENTIALLY AFFECT THE RISK OF SAFETY RELATED EVENTS Factor or Issue Risk Rating Median is “open” throughout project area except for approaches to overpasses and the protection of some structures E Geometry of curves approaching end of long tangent (long straight section of highway north of Int. 49 (SB direction) and south of Int. 51 (NB direction) prior to curves E Difference in elevation in areas of curves – SB south of Int. 50 and NB south of Int. 51 (relates to curve geometry factor also) E Median is not delineated D High travel speeds exist on section C Inside shoulder is narrow D Driver fatigue affected by long, straight road section D Sun Glare – SB south of Int. 51 in AM and NB north of Int. 50 in PM B Some bridge columns unprotected – at Route 1 overpasses B Low salt area - not signed B Given the high traffic volume on the study section and the high number of cross-median events (3-4 per year) the “open” median factor was assigned a risk factor of ‘E’. Although the width would appear sufficient to contain the errant vehicles, the speeds combined with the geometry (i.e. elevation differences, horizontal curves), the data clearly shows that once a motorist makes a mistake or becomes “errant” and enters the median, there is a high probability that the motorist will cross the median and enter the opposing direction of flow. The long straight sections just prior the two noted horizontal curves with the downgrades and differences in elevation between the two directions of flow also contribute to the MS Transportation Systems, Inc. Page 13 I-95 Danvers-Topsfield Road Safety Audit likelihood of crossing the median in the two curved sections. assigned for this factor. A risk rating of ‘E’ was Other than the median edge line, there is no other visible delineation of the median. The rumble strip exists but the inside shoulders are only 1 to 3 feet in width. While the pavement markings are in good condition and a rumble strip exists in the inside shoulder, there is a relatively high number of median entries over this section (approx. 7 per year). Consequently, not having the median delineated was assigned a risk rating of ‘D’ while the narrow inside shoulder was assigned a ‘D’ given that there is some relatively flat area immediately adjacent to the inside shoulder to help with recovery. The high travel speeds along with the above noted physical conditions increases the risk of median entries, it was assigned a ‘C’ rating. Sun glare and the low salt zone were also noted as potentially contributing factors but likely having a smaller effect and were assigned a ‘B’ rating. Fatigue was also noted as a driver contributing cause and the long straight sections of road may again potentially contribute to “lulling” the motorists, particularly if tired. A risk rating of ‘D’ was assigned to this factor as a number of crashes cited fatigue as one cause. Once the potential issues had been identified and risk ratings assigned, suggested actions intended to reduce the injuries and fatalities resulting from cross-median crashes specifically and median related crashes in general were developed. Given that this RSA is focused on cross-median events, the initial action evaluated was the potential installation of a median barrier. • Consideration of a Median Barrier One of the more significant actions to be considered is to install median barriers in the current “open” areas. A barrier can be considered when there is a higher than desirable chance of or a greater risk for median cross-over crashes to occur and that have or could result in fatalities and/or a high proportion of injury related crashes. In addition, a barrier could be considered when the consequences or severity of a crash without a barrier would be worse than if the barrier were in place. Factors that generally come into play in deciding on whether a median should be installed involve the following: MS Transportation Systems, Inc. Page 14 I-95 Danvers-Topsfield Road Safety Audit High volumes and speeds Truck volumes and mix Narrow median History of cross-median crashes High risk of catastrophic event These items have been reviewed relative to the I-95 section under study. While not having a narrow median, the I-95 study section has a high volume, 5% trucks and a history of cross-median crashes. Figure 10 presents a review of the corridor in relation to the median warrant criteria presented in the AASHTO RDG4. As can be seen in the diagram, with the median (as measured from edge line to edge line) is approximately 80 to 88 feet and a volume of over 80,000 vehicles on an average day, the intersection of the two items would be off the chart where a barrier can be “optional”. In addition to the chart and related warrant criteria, which is a guideline, further consideration was given to the following: The high volume-high speed presents the potential for a greater number of errant vehicles entering the median. Of the total median related crashes, a high proportion of cross-median (41%) over the three (3) year period and the median appears to be crossable. Cross-over crashes have resulted in predominantly personal injuries or fatalities. Fatigue and weather conditions also appear to have an effect (possibly in combination with the dark, late night driving) in the median and cross-median crashes. Based on the evaluation and input from RSA team members, the likelihood of crossmedian events could be higher in the areas of the two horizontal curves following the long tangent sections. Consequently, based on the analysis of the data, the field drive-thru and discussion of the conditions by the RSA team members, it has been concluded that a median barrier be considered at a minimum, in the sections of this route that include the changes in horizontal alignment and are currently open. These are the downgrade, curved sections approaching Interchange No. 49 (southbound) and Interchange No. 51 (northbound). The barrier would be included in tangent sections on both sides of the curve. 4 American Association of State Highway and Transportation Officials, Roadside Design Guide, Washington, D.C., 2002, Chapter 6 Update 2006. MS Transportation Systems, Inc. Page 15 median width 80-88 feet 80 AVERAGE DAILY TRAFFIC (thousands) 70 BARRIER RECOMMENDED 60 BARRIER CONSIDERED 50 40 BARRIER OPTIONAL 30 20 10 0 0 10 20 30 40 50 60 70 MEDIAN WIDTH (feet) Median Barrier Warrant Analysis Interstate 95 Road Safety Audit Danvers-Topsfield, Massachusetts MS Transportation Systems, Inc. NOT TO SCALE Framingham, Massachusetts Figure 10 I-95 Danvers-Topsfield Road Safety Audit The approximate lengths of barrier in these two areas (Sections 1 and 3) would be in the range of 1.1 to 1.2 miles. These areas are shown in Figure 11. Also shown in the figure is the tangent section between the two curves at 1.1 mile in length. If all three sections are covered by the barrier, it would total approximately 3.4 miles in length. The remaining open area of the study section north of Interchange No. 51 could be monitored and if cross-over crashes persist following the installation of barriers in the two noted areas, then extending the barriers could be considered. While the RSA team discussed the likely lower risks of crossing the median pertaining to the more level, tangent highway sections, it is also recognized that the current method of identifying crash locations is an approximation at best and that leaving gaps in areas of similar risk may not adequately address the issue. At the same time, installing guardrail along the entire study section would cost more then one million dollars. A cable barrier has been shown to be less costly, however, the latest research indicates that anchored sections of cable barriers should not exceed approximately one mile. Consequently, there are installation options in terms of length and timeframe for the I-95 corridor. Final decisions can be made as funding availability and design details are determined. The selection of the barrier is discussed in greater detail in the next section followed by the complete set of I-95 RSA recommendations. • Barrier Selection Once a decision is made to install a barrier, the type must be determined. There are a number of barrier types that can be considered in addressing the median cross-over crashes. Not all of these types are typically or currently used by MassHighway but they are available and include the following: ♦ ♦ ♦ ♦ Weak post W-Beam Box Beam Generic Low Tension Cable High Tension Cable Barrier ♦ Strong post W-Beam ♦ Thrie Beam ♦ Concrete (Jersey) In deciding on the type of barrier, there are a number of criteria suggested in the AASHTO Roadside Design Guide5. These criteria used in selecting a barrier type are included in Table 5. 5 American Association of State Highway and Transportation Officials, Roadside Design Guide, Washington, D.C., 2002, Chapter 6 Update 2006. MS Transportation Systems, Inc. Page 17 INT. NO. 51 OPTIONAL BARRIER AREA 2 APPROX. 1.1 MILES PROPOSED BARRIER AREA 3 APPROX. 1.1 MILES INT. NO. 50 PROPOSED BARRIER AREA 1 APPROX. 1.2 MILES PROPOSED BARRIER LOCATION Proposed Median Barrier Locations Interstate 95 Road Safety Audit Danvers-Topsfield, Massachusetts MS Transportation Systems, Inc. NOT TO SCALE Framingham, Massachusetts Figure 11 I-95 Danvers-Topsfield Road Safety Audit Criteria 1. Performance Capability 2. Deflection 3. Site Conditions TABLE 5 CRITERIA FOR BARRIER SELECTION Comments Barrier must be structurally able to contain and redirect design vehicle. Expected deflection of barrier should not exceed available deflection distance. Slope approaching the barrier and distance from traveled way may preclude use of some barrier types. 4. Compatibility Barrier must be compatible with planned end anchor and capable of transitioning to other barrier systems (such as bridge railings). 5. Cost Standard barrier systems are relatively consistent in cost, but highperformance railings can cost significantly more. 6. Maintenance A. Routine Few systems require a significant amount of routine maintenance. B. Collision Generally, flexible or semi-rigid systems require significantly more maintenance after a collision than rigid or high-performance railings. C. Material Storage The fewer different systems used, the fewer inventory items/storage space required. Simpler designs, besides costing less, are more likely to be reconstructed properly by field personnel. Occasionally, barrier aesthetics are an important consideration in selection. The performance and maintenance requirements of existing systems should be monitored to identify problems that could be lessened or eliminated by using a difference barrier type. D. Simplicity 7. Aesthetics 8. Field Experience Source: AASHTO, Roadside Design Guide, 2002, Chapter 5 Roadside Barriers. Based on extensive research and trials over the past five years, the high tension cable barrier system has become more prominent in the U.S. The cable (flexible) barrier has its advantages from a cost and aesthetic perspective over the various guardrail systems or concrete barrier. The median slope and/or recovery area also affects the use and placement of any barrier including guardrail. In addition to the cable barrier systems, the alternative types of guardrail were reviewed for potential application on this route. Considerations included the volume of traffic, relative amount of truck traffic and travel speeds. Based on these, the most applicable types of guardrail for this route include the W-beam with strong post or the strong post thrie-beam. These rails are appropriate for high speed highways and high volumes with a relatively high proportion of truck traffic. Costs for each are somewhat similar though the thrie-beam has a higher cost. It’s been noted that the thrie beam rail is typically used on the median side of the freeways in the MS Transportation Systems, Inc. Page 19 I-95 Danvers-Topsfield Road Safety Audit Commonwealth where a barrier was determined necessary. The concrete barrier would generally be applicable in urban sections with limited median widths available. As a result of this review, it was determined that the median barrier options that are valid for consideration for I-95 in this section are the cable barrier and strong post guard rail. Maintenance issues are also an important consideration in decisions regarding median barrier installations. The maintenance issues that are of concern include: Barrier hits per mile Frequency of hits Cost recovery Cable downtime Repair effect on traffic Maintaining tension with cable system Mowing median Final selection of the barrier type should be based on the costs, physical condition of the median, the ability to maintain a recovery zone, likely maintenance or repair requirements, and compatibility with future planned pavement widening. The key points of the cable barrier or guardrail are summarized below. Cable Barrier While the low tension generic cable system has been in existence for more than 50 years, most of the recent cable system research and installation is focused on the high tension systems. There are currently six (6) manufacturers with systems approved by the Federal Highway Administration (FHWA) for use under certain conditions. There are 3-rope or 4-rope cable systems as shown in the following two photographs. 3 Cable CASS System on Route 213 MS Transportation Systems, Inc. 4 – Rope Brifen System on I-495 Page 20 I-95 Danvers-Topsfield Road Safety Audit This barrier type can be installed on slopes of 6:1 or flatter with little constraint on placement. There are certain systems (i.e. Brifen and Gibraltor 4 rope) that have been approved for slopes as steep as 4:1. In addition to the lower installation costs, the cable barrier can usually be located sufficiently away from the pavement area to allow for recovery zone and a minimal number of hits. Guardrail The guardrail could be placed toward or in the center of the median where slopes are 10:1 or flatter (i.e. I-93 Braintree, Route 128 Needham) as well as at the edge of a steep slope or where minimal recovery zones exist. With the guardrail placed within several feet of the pavement edge, a clear zone (or recovery area) would be eliminated at least on one side of the median if guardrail is applied on only one side of the median. Per mile costs of the basic types of median barrier treatment to be considered for this route are summarized in Table 6. Shown in the table are estimated per mile costs of installing a cable barrier, a double faced W-beam guardrail and a double faced thriebeam guardrail. As can be seen, the cable barrier is expected to be the lower cost option. It should be noted that the estimated costs for the cable barrier are largely based on recent limited applications in the Commonwealth. Construction costs for cable installation could be substantially lower based on experience in other parts of the country (examples in Appendix). The W-beam rail is a lower cost option compared to the thriebeam, however, there is slightly greater deflection with the W-beam. TABLE 6 COMPARISON PER MILE COSTS Cable vs. Guardrail Costs/Mile Cable W-beam Thrie beam $144,000 $171,000 $213,000 Based on the above costs, the installation of cable barrier in the three subsections totaling 3.4 miles is estimated to cost approximately $490,000 while use of thrie-beam would result in a cost of approximately $724,000. The next section outlines all of the RSA team recommendations including the median barrier. MS Transportation Systems, Inc. Page 21 I-95 Danvers-Topsfield Road Safety Audit Recommendations As a result of the RSA analysis and team input, a set of recommendations have been identified and are summarized in Table 7. These actions are intended to eliminate the chance of cross-median crashes as well as reduce the severity of all crashes and improve the overall safety condition of this section of I-95 in Danvers-Topsfield. Identified in the table in addition to the risk factor and recommended action are the estimated costs and potential timeframe (i.e. short (0-1 year), medium (1-3 years) and long (>3 years)). TABLE 7 SUMMARY OF RECOMMENDATIONS Risk Factor Risk Rating Recommended Action Estimated Timeframe $331,0001 Medium to long term $490,0001 Medium to long term Median is “open” throughout project area except for approaches to overpasses and protection of some structures E Geometry of curves approaching end of long tangent (long straight section of highway north of Int. 49 (SB direction) and south of Int. 51 (NB direction) prior to curves. E Difference in elevation in areas of curves – SB south of Int. 50 and NB south of Int. 51 (relates to curve geometry factor also) E Barrier would address in most critical areas. see above Median is not delineated D Install reflective delineators see above High travel speeds exist on section C Increase enforcement program Inside shoulder is narrow D Widen to a minimum of 4’ paved $2.2M Long term as part of overall rehab project Driver fatigue affected by long, straight road section D Use VMS to provide effective messages and break monotony TBD Use portable VMS in short term Sun Glare – SB south of Int. 51 in AM and NB north of Int. 50 in PM B Install standard caution signs (2) $5,000 Short term Some bridge columns unprotected – at Route 1 overpasses B Install guardrail around columns of Route 1 overpass $16,000 Short term Low salt area - not signed B Install new signs (assume 6 total) $3,000 Short term 1 Install median barrier in higher risk sections – 2.3 miles (see Figure 11) Install median barrier along section from Int. No. 49 thru Int. No. 51 (3.4 miles) Estimated Cost Install reflective delineators Install curve warning signs or chevron signs on curve $7,000 Short to medium term $5,000 Short term TBD See above Short to medium term Short term Assumes cable barrier MS Transportation Systems, Inc. Page 22 I-95 Danvers-Topsfield Road Safety Audit The I-95 study section has an open median and although it is between 80 to 88 feet wide, there is a high proportion of cross-over crashes. It is recommended that a median barrier be installed in the two most noted areas of concern by the RSA team – those being in the areas of the curves south of Interchange 50 and south of Interchange 51. If cable barrier is installed covering these two higher risk areas as well as the tangent section in between, it is estimated to have a construction cost of approximately $490,000. The designer will need to verify the grades of the median prior to specifying the type and location of cable. In addition to the open median, the design of the study section includes two (2) large radius horizontal curves that exist at the ends of the long tangent section (southbound at Interchange No. 49 and northbound at Interchange No. 51) coupled with the downgrades and directional differences in elevation can contribute to the occurrence of cross-median crashes. Altering the geometry is clearly not feasible, but the installation of the barrier noted above would alleviate this potential risk. It is also recommended that the median be delineated along both sides with flexible, reflective posts. This short term action is estimated to cost $7,000. Also in the short terms, either curve warning signs or chevron signs could be put in place on the two curves noted in the above paragraph. A factor discussed by the RSA team is that having long, straight sections of highway may contribute to driver fatigue or inattention. An action that could be considered to help address this factor is the use of variable message signs (VMS) that could display a variety of messages to inform motorists of operating conditions and other items to enhance driver behavior. The typical flashing of the message may also have a positive effect on driver attention. The VMS system could initially consist of a series of portable sign boards. There is a portable VMS currently located in the vicinity of Interchange No. 52. In the long term, permanent installations as part of a cohesive ITS-VMS plan can be implemented. The costs of the portable VMS boards are estimated at approximately $30 per day, not including the communication costs. The widening of the inside shoulder if installed by itself is a major, high cost ($2.2M) action that while desirable, is best addressed as part of an overall surface rehabilitation project. However, as part of an overall rehab project, the incremental cost to widen the shoulder will be significantly lower. The “sun glare” and “low salt zone” factors can be addressed through signage. Figure 12 illustrates an example of a sign that could be used for these factors. MS Transportation Systems, Inc. Page 23 CAUTION LOW SALT ZONE USE CAUTION SOLAR GLARE IN AM (Alt. - IN PM) CONCEPTUAL ONLY NOT TO SCALE Potential Sign Legends I-95 Road Safety Audit Danvers-Topsfield, Massachusetts MS Transportation Systems, Inc. Framingham, Massachusetts Figure 12 I-95 Danvers-Topsfield Road Safety Audit The high speeds are a factor that can be further addressed through increased, consistent enforcement, but this requires additional personnel. The RSA team recommends additional budget for increased police presence. Lastly, the RSA noted that there are unprotected bridge columns (Route 1 overpasses) in the study section. While not a factor of risk to cross-median crashes, the conditions increases the potential severity of a fix object crash as well as possible damage to the columns. Consequently, it is recommended that guardrail be placed in these areas in the short term. MS Transportation Systems, Inc. Page 25 I-95 Danvers-Topsfield Road Safety Audit Appendix • • • • • MS Transportation Systems, Inc. RSA Meeting Agenda RSA Attendees List Median Crash Diagram Crash Data Traffic Volume Data Page 26 Road Safety Audit Danvers/Topsfield/Boxford – I-95 Meeting Location: MassHighway District 4 Office 519 Appleton Street, Arlington Thursday, July 31, 2008 11:00 AM – 12:30 PM Type of meeting: Cross Median – Road Safety Audit Attendees: Invited Participants to Comprise a Multidisciplinary Team Please bring: Thoughts and Enthusiasm!! 11:00 AM Welcome and Introductions 11:15 AM Introduction to Road Safety Audits and Cross Median Crashes 11:30 AM Review of Site Specific Material • Crash & Volume Summaries– provided in advance • Existing Geometries and Conditions • Video and Images 12:00 PM Completion of RSA • Identification of Safety Concerns – using RSA Prompt List as a guide • Identification of Possible Countermeasures 12:30 PM Adjourn for the Day – but the RSA has not ended Instructions for Participants: • Before attending the RSA on July 31st participants are encouraged to drive Interstate 95 between interchanges 48 and 53 and complete/consider elements on the RSA Prompt List with a focus on safety factors affecting cross median crashes. • All participants will be actively involved in the process throughout. Participants are encouraged to come with thoughts and ideas, but are reminded that the synergy that develops and respect for others’ opinions are key elements to the success of the overall RSA process. • After the initial RSA meeting, participants will be asked to comment and respond to the document materials to assure it is reflective of the RSA completed by the multidisciplinary team. ROAD SAFETY AUDIT MEETING I-95 Danvers-Topsfield July 31, 2008 MassHighway District 4 Offices, Arlington MA Attendance List Name Agency/Dept. Email Bill Scully MS Transportation Systems, Inc. bscullyjr@mac.com Lyris Liautaud MHD Highway Design Lyris.Liautaud@state.ma.us Bonnie Polin MHD Safety Bonnie.Polin@state.ma.us Kaiyan Jiang MHD Highway Design Kaiyan.Jiang@mhd.state.ma.us Efi Pag___________ Boston Region MPO EfiP@CTPS.org Andrew Hirshfield MHD Traffic Andrew.Hirshfield@mhd.state.ma.us Lisa Schletzbaum MassHighway Safety Lisa.Schletzbaum@mhd.state.ma.us Tim White Federal Highway Admin. Timothy.A.White@fhwa.dot.gov Paul Fletcher Mass State Police "A" Paul.Fletcher@state.ma.us Brett Loosian MHD, District 4, Maintenance Brett.Loosian@mhd.state.ma.us John Gregg MHD, District 4, Traffic John.Gregg@mhd.state.ma.us MS Transportation Systems, Inc. IPSW ± Interstate 95 Median Crashes ICH ROA D TR OA D DS HR 1 PO N W IC EE T 53 " ) IP S MAI N ST R EE T IPSWICH ER H IPS IL L R CH WI D OA R OA NORTH ANDOVER HAV 52 " ) BOXFORD Crash IDs between 2-4 D SA 5 TO WASHING LE 6 N STREET M ST RE 7 ET RO W LE 95 EE TR VA L RNP 20 D OA YR LE VA L LOCUST STREET ET RE ST AD 21 RE ST ET PINE STREET ST " ) 47 ET 48 " ) RE LS TR EE T Local RE CABOT RO 22 ST RIVER STREET RE AM EET E PL ST EY RL R EE T 18 FO BO S T O N ST ST R MA Collector * 2007 crash file has not Ryet been closed. U Miles 1 WENHAM BU Minor Arterial 49 " ) REET Median, Non-Fatal Crash 0.75 AD NH ST DAYTON Principal Arterial SS EL N OR TH 19 Cross Median, Non-Fatal Crash 0.5 NEW DANVERS Interstate EE T 16 17 Cross Median, Fatal Crash Municipal Boundary 0.25 " ) EET Major Roads NORTH READING 0 E ST R 50 SUMMER STREET Type of Median Crash 2004-2007 * S TR O WE EA S M APL Legend EL M R TS EET 14 TR ET EE RE STR 15 T ST EST BU R YPO RT TU TY ER MIDDLETON F OR IKE S TR ST S EA DY LIB ET PE O AB Y AD RE ST TR 13 RO EX LS M S ES SC O HO T EE T EE TR LE LE EE SA 12 T E R OA D Crash IDs between 8-11 HS Y BRIDG 51 " ) T TOPSFIELD HIG § ¨ ¦ T EN HO L ST R EET ET MASSACHUSETTS HIGHWAY SAFETY DIVISION CRASH SUMMARY ROADWAY: NO. CITY: DANVERS, TOPSFIELD AND BOXFORD LOCATION: EXIT 50 - 51 I-95 STUDY PERIOD: CRASH NUMBER 1/1/2004 TO CRASH DAY 12/31/2007 TIME OF DAY CRASH DATE TRAVEL LIGHT WEATHER ROAD REASON FOR VEHICLE TYPE OF DRIVER CONTRIBUTING CRASH DIRECTION CONDITION CONDITION SURFACE RUNNING OFF ROAD LEFT MOVEMENT MEDIAN CRASHES CAUSE SEVERITY 1 2052170 Monday 2:45 PM 12/26/05 NB Daylight Clear Dry Unknown vehicle struck another vehicle in the rear, caused the vehicle to cross the median and hit another vehicle S/B Travel Lane to N/B Travel Lane Cross Median Followed too closely 2 2130034 Sunday 12:00 PM 08/20/06 SB Daylight Cloudy Wet Unknown vehicle caused another vehicle to take evasive action and hit the guardrail Travel Lane to Median Guardrail Median Failure to keep in proper lane Property Damage Only 3 2021845 Sunday 12:45 PM 09/18/05 SB Daylight Cloudy Dry Vehicle tire blew out and lost control of vehicle Travel Lane to Median Median No Improper Driving Non-Fatal Injury Non-Fatal Injury 4 1984400 Friday 8:00 PM 01/28/05 SB Dark - Not Lighted Clear Wet Vehicle drifted into median and overturned Travel Lane to Median Median Failure to keep in proper lane Property Damage Only 5 2112454 Tuesday 6:12 AM 05/09/06 SB Daylight Clear Dry Driver suffered a coronary heart failure, vehicle struck a tree and caught on fire S/B Breakdown Lane to N/B Breakdown Lane Cross Median History Heart/Epilepsy/Fainting Non-Fatal Injury 6 2059780 Thursday 3:40 PM 06/22/06 NB Daylight Cloudy Dry Vehicle was cut-off by unknown vehicle and hit the guardrail Travel Lane to Median Median Failure to keep in proper lane Property Damage Only 7 2050306 Monday 1:02 AM 04/17/06 SB Dark - Not Lighted Clear Dry Travel Lane to Median to Travel Lane to Median Median Failure to keep in proper lane Non-Fatal Injury N/B Travel Lane to S/B Right Rock Embankment Cross Median Failure to keep in proper lane Non-Fatal Injury N/B Travel Lane to Median to Travel Lane to S/B Right Tree Line Cross Median Exceeded Speed Limit Non-Fatal Injury 8 2225650 Friday 6:05 PM 08/03/07 NB Daylight Clear Dry Vehicle drifted to the left, the tires left the paved surface, lost control of vehicle and overturned Vehicle changed lanes to an already occupied lane, to avoid collision swerved to the left, hit another vehicle and crossed the median 9 2258069 Wednesday 6:05 PM 07/11/07 NB Daylight Not Reported Dry Driver was operating in erratic manner, collided with another vehicle, crossed the median and overturned 10 2093941 Saturday 10:35 AM 08/26/06 SB Daylight Clear Dry Driver was operating in aggressive manner, hit another vehicle, started to spin out and it was struck by another vehicle Travel Lane to Median Median Operating vehicle in reckless manner Property Damage Only 11 2114665 Wednesday 7:01 AM 05/10/06 SB Daylight Rain Wet Vehicle hydroplaned, crossed the median and struck another vehicle N/B Travel Lane to S/B Travel Lane Cross Median Swerving due to slippery surface in roadway Property Damage Only 12 1915873 Monday 7:56 AM 03/14/05 NB Daylight Clear Dry Travel Lane to Median Median Exceeded Speed Limit Non-Fatal Injury N/B Travel Lane to Median Guardrail to Travel Lane to S/B Travel Lane Cross Median Operating vehicle in reckless manner Fatal Injury Travel Lane to Far Median Median Distracted Non-Fatal Injury Non-Fatal Injury 13 1919756 Sunday 11:10 PM 05/15/05 NB Dark - Not Lighted Cloudy Dry Driver had a sneezing sequence, hit a patch of ice and struck a police car Vehicle went left, struck the guardrail, sideswiped another vehicle, crossed the median and crashed head-on with a tractor trailer 14 2054550 Sunday 6:15 PM 06/04/06 NB Daylight Clear Dry Driver was startled by a spider, lost control and overturned 15 1769465 Saturday 1:25 AM 07/24/04 SB Dark - Not Lighted Clear Dry Fallen asleep, vehicle sideswiped another vehicle and overturned Travel Lane to Median Median Fatigued/Asleep 16 2014951 Sunday 1:40 PM 03/05/06 SB Daylight Clear Dry Fallen asleep and vehicle overturned Travel Lane to Median Guardrail to Overpass Median Fatigued/Asleep Non-Fatal Injury 17 2014962 Saturday 5:26 PM 02/25/06 SB Dusk Snow Snow Driver felt the rear wheel loose traction, lost control of vehicle and crossed the median S/B Travel Lane to N/B Right Guardrail Cross Median No Improper Driving Non-Fatal Injury 18 2060614 Tuesday 3:00 AM 07/04/06 NB Dark - Not Lighted Clear Dry Fallen asleep and vehicle overturned Travel Lane to Median to Median Guardrail Median Fatigued/Asleep Non-Fatal Injury 19 2059740 Tuesday 1:25 AM 06/06/06 NB Dark - Not Lighted Clear Dry Fallen asleep and vehicle overturned Travel Lane to Median Guardrail to Median Median Fatigued/Asleep Non-Fatal Injury Property Damage Only 20 1919253 Monday 12:20 PM 06/20/05 SB Daylight Clear Dry Lost control of vehicle and sideswiped a tractor Travel Lane to Median Median Failure to keep in proper lane 21 2281303 Wednesday 6:00 AM 02/14/07 NB Daylight Snow Snow Lost control of vehicle, crossed the median and was struck by another vehicle N/B Travel Lane to S/B Travel Lane Cross Median Failure to keep in proper lane Non-Fatal Injury 22 2061113 Thursday 4:55 PM 05/18/06 SB Daylight Clear Dry Vehicle sideswiped another vehicle, crossed the median, overturned and impacted another vehicle while airborne S/B Travel Lane to N/B Right Breakdown Lane Cross Median Exceeded Speed Limit & Drugs Non-Fatal Injury 23 1854184 Monday 6:00 AM 12/20/04 SB Dark - Not Lighted Cloudy Wet Lost control of vehicle, crossed the median and hit another vehicle S/B Travel Lane to N/B Travel Lane Cross Median Failure to keep in proper lane Property Damage Only 24 1999995 Saturday 11:35 AM 10/15/05 SB Daylight Rain Wet Lost control of vehicle due to heavy rain and overturned S/B Travel Lane to N/B Travel Lane Cross Median Driving too fast for condition Non-Fatal Injury 25 2040692 Tuesday 5:20 AM 03/29/05 SB Dark - Not Lighted Rain Wet Median Failure to keep in proper lane Non-Fatal Injury 26 2189809 Friday Not Reported 05/04/07 NB Daylight Clear Dry Vehicle abruptly changed lane and struck the right corner of another vehicle Travel Lane to Median Driver was operating in aggressive manner, hit another vehicle, swerved to the median, entered traffic again and had a further crash Travel Lane to Median to Travel Lane 27 2242408 Thursday 2:05 PM 03/22/07 SB Daylight Clear Dry Fallen asleep, hit another vehicle and caused the vehicle to enter the median LIGHT CONDITION WEATHER CONDITION ROAD SURFACE TOTAL NO. DAYLIGHT DUSK DARK - NOT LIGHTED CLEAR CLOUDY RAIN SNOW NOT REPORTED DRY 27 18 1 8 16 5 3 2 1 19 6 100% 67% 4% 30% 59% 19% 11% 7% 4% 70% 22% ROAD SURFACE SNOW MEDIAN OR CROSS MEDIAN MEDIAN CROSS MEDIAN CRASH SEVERITY PROPERTY DAMAGE WET DRIVER CONTRIBUTING CAUSE NO IMPROPER NON-FATAL INJURY FATAL - INJURY DRIVING ONLY EXCEEDED SPEED LIMIT EXCEEDED SPEED LIMIT & DRUGS FOLLOWED TOO DRIVING TO FAST FOR CONDITION CLOSELY 2 16 11 8 18 1 2 2 1 1 1 7% 59% 41% 30% 67% 4% 7% 7% 4% 4% 4% FAILURE TO KEEP IN PROPER LANE OPERATING VEHICLE IN RECKLESS MANNER DISTRACTED FATIGUED/ ASLEEP DRIVER CONTRIBUTING CAUSE SWERVING DUE TO SLIPPERY SURFACE IN ROADWAY HISTORY HEART/EPILEPSY/ FAINTING 9 3 1 1 1 5 33% 11% 4% 4% 4% 19% 2007 CRASH RECORDS ARE NOT COMPLETE CRASH SUMMARY IS BASED ON CRASH REPORTS WITH STATE POLICE NARRATIVES Median Travel Lane to Median to Travel Lane to Median to First Bridge Support CaisMedian Operating vehicle in reckless manner Non-Fatal Injury Fatigued/Asleep Property Damage Only I-95, North of Rt 1 04/26/2007 Northbound Southbound Direction Direction Start time 12:00 AM 321 169 1:00 AM 152 115 2:00 AM 126 114 3:00 AM 109 177 4:00 AM 168 482 5:00 AM 477 1,799 6:00 AM 1,104 4,486 7:00 AM 1,875 5,295 8:00 AM 1,773 4,244 9:00 AM 1,564 2,964 10:00 AM 1,580 2,248 11:00 AM 1,826 2,059 12:00 PM 1,953 1,897 1:00 PM 2,186 1,848 2:00 PM 3,025 2,059 3:00 PM 3,895 2,319 4:00 PM 4,493 2,138 5:00 PM 4,818 2,212 6:00 PM 3,707 1,782 7:00 PM 2,631 1,172 8:00 PM 1,802 909 9:00 PM 1,427 712 10:00 PM 1,051 529 11:00 PM 644 314 Daily Total 42,707 TOTAL 490 267 240 286 650 2,276 5,590 7,170 6,017 4,528 3,828 3,885 3,850 4,034 5,084 6,214 6,631 7,030 5,489 3,803 2,711 2,139 1,580 958 42,043 84,750 Northbound Direction Southbound Direction 5,000 4,500 4,000 3,500 3,000 2,500 2,000 1,500 1,000 500 Time of Day PM :0 0 PM 10 00 PM 8: 00 PM 6: 00 4: 00 PM PM 2: :0 0 AM 12 :0 0 AM 10 00 AM 8: 6: 00 AM 4: 00 AM 00 2: :0 0 AM 0 12 Hourly Volume (Number of Vehicles) Directional Traffic Volumes along I-95, North of RT 1, Topsfield Thursday, April, 26, 2007 I-95, North of RT-62 (Maple Street) 04/26/2007 Northbound Southbound Direction Direction TOTAL Start time 12:00 AM 330 161 491 1:00 AM 162 99 261 2:00 AM 120 110 230 3:00 AM 112 180 292 4:00 AM 176 460 636 5:00 AM 489 1,807 2,296 6:00 AM 1,163 4,346 5,509 7:00 AM 1,912 4,557 6,469 8:00 AM 1,843 3,641 5,484 9:00 AM 1,589 2,567 4,156 10:00 AM 1,598 2,014 3,612 11:00 AM 1,775 1,830 3,605 12:00 PM 1,949 1,649 3,598 1:00 PM 2,143 1,712 3,855 2:00 PM 2,757 1,812 4,569 3:00 PM 3,667 1,902 5,569 4:00 PM 4,244 1,867 6,111 5:00 PM 4,500 1,900 6,400 6:00 PM 3,602 1,559 5,161 7:00 PM 2,482 1,035 3,517 8:00 PM 1,703 803 2,506 9:00 PM 1,357 650 2,007 10:00 PM 1,044 464 1,508 11:00 PM 668 281 949 Daily Total 41,385 37,406 78,791 Northbound Direction Southbound Direction 5,000 4,500 4,000 3,500 3,000 2,500 2,000 1,500 1,000 500 Time of Day PM 0 PM :0 10 00 PM 8: 00 PM 6: 00 4: 00 2: 0 :0 12 PM PM AM 0 AM :0 10 00 AM 8: 00 AM 6: 00 AM 4: 00 2: :0 0 AM 0 12 Hourly Volume (Number of Vehicles) Directional Traffic Volumes along I-95, North of RT 62, Danvers Thursday, April, 26, 2007