ROAD SAFETY AUDIT MAJOR HIGHWAY MEDIAN CROSS-OVER CRASHES I-495 Littleton Prepared for Massachusetts Highway Department Prepared by MS Transportation Systems, Inc. Framingham, Massachusetts December 2008 ROAD SAFETY AUDIT MAJOR HIGHWAY MEDIAN CROSS-OVER CRASHES I-495 LITTLETON December 2008 Prepared for Massachusetts Highway Department Prepared by MS Transportation Systems, Inc. Consulting Engineers and Planners 300 Howard Street, P.O. Box 967 Framingham, Massachusetts 01701 Tel: (508) 620-2832 Fax: (508) 620-6897 www.mstransportationsystemsinc.com I-495 Littleton Road Safety Audit TABLE OF CONTENTS Page INTRODUCTION 1 RSA PROCESS 3 ANALYSIS 7 SUMMARY OF RSA FINDINGS/POTENTIAL ACTIONS 10 RECOMMENDATIONS 14 APPENDIX 18 MS Transportation Systems, Inc. Page i Route I-495 Littleton Road Safety Audit INTRODUCTION Lane departure crashes are one of the primary fatal crash types in Massachusetts. The Commonwealth exceeds the national average for lane departure crashes and was designated a lead state in lane departure crashes by the American Association of State Highway and Transportation Officials (AASHTO). The Massachusetts Highway Department (MHD) conducted a study of the problem and found that during 2002-2004, lane departure crashes accounted for 25 percent of all injury crashes and nearly half, 46 percent, of all fatal crashes. As part of the effort in implementing the safety plan and specifically reducing lane departure crashes, the MassHighway is completing a Road Safety Audit (RSA) Review Project specifically focused on median crossing (or median cross-over) crashes on its major highways. Road safety audits are a formal safety performance examination on existing or future roadways by an independent audit team. These specific audits are being conducted in locations where cross-over experience has been or has the potential to be of concern and where the RSA team has judged that factors exist and safety risk could be affected. The team works to identify opportunities for enhancing safety and to recommend specific enhancements that may be implemented to reduce median crossover crashes and improve the overall safety along the highway. An RSA was conducted for the I-495 in Littleton as part of this overall effort. The roadway section under study, shown in Figure 1, was essentially between Interchange No. 29 at Route 2 and Interchange No. 31 at Route 119 a distance of approximately 3 miles. This section had experienced a fatal cross-median crash. The purpose of this I-495 Littleton RSA was to assess current safety characteristics on the highway section under study and to recommend a set of actions to enhance the safe operation of the highway section under study. Recommendations contained in this report reflect the overall consent of the RSA team and do not necessarily reflect the official views of MassHighway. MS Transportation Systems, Inc. Page 1 Interchange 31 Interchange 30 495 Route 2A Route 119 Littleton Route 2 495 Interchange 29 - interchanges N Project Location W S I-495 Road Safety Audit Littleton, Massachusetts MS Transportation Systems, Inc. E 1 : 25,000 Framingham, Massachusetts FIGURE 1 Route I-495 Littleton Road Safety Audit RSA PROCESS The overall procedures outlined in the Median Cross-Over RSA Guideline Report1 were followed with some modifications given the characteristics of the facility being reviewed. The process included identifying RSA team members; conducting field visits; holding a RSA team meeting and then completing an assessment of the data and findings from the field visits and meetings to render recommended actions for MassHighway to consider. Data including recent traffic volume data, summary crash records for the 20042007 period, detailed crash reports of cross-over crashes, and available record highway plans were obtained and reviewed by the RSA consultant. Field visits were conducted by the RSA team members. A video recording of the sections under study was taken by the RSA Consultant. The site visits were completed prior to the RSA team meeting that was held on July 22, 2008 at the MassHighway District 3 offices. At that meeting, the RSA consultant provided a brief overview of the RSA purpose, a summary of the roadway section’s characteristics and results of the review to date. The RSA team provided input and discussed the key items noted in the field and that were listed on the RSA Median Cross-Over Prompt List. Issues and concerns were noted. Following the RSA meeting, the RSA consultant compiled the information, completed the analysis and circulated the draft report. • RSA Team The following were members of the I-495 Littleton Road Safety Audit: Kathryn Cook, MassHighway, Traffic Intern Edward Pomfred, MassHighway, Traffic Intern Bonnie Polin, MassHighway Sgt. Eugene O’Neill, Mass State Police Robert Babb, MassHighway, District 3 Chris Hogan, MassHighway, District 3 William J. Scully, MS Transportation systems (RSA Consultant) • Christine Breen, MassHighway, Design Timothy White, FHWA Lisa Schletzbaum, MassHighway, Safety Management Unit Mark Johnson, MassHighway, District 3 Eric Nascimento, MassHighway, District 3 RSA Team Meeting The RSA team meeting took place on July 22, 2008 at the District 3 offices in Worcester. The team included engineers, planners and a representative from the State Police barrack that has jurisdiction of I-495 in Littleton. Represented were MassHighway (Boston and District), the Federal Highway Administration (FHWA) as well as the State 1 MS Transportation Systems, Inc., Road Safety Audits, Median Cross-Over Crashes, Audit Guidelines, Prepared for MassHighway, October 2007. MS Transportation Systems, Inc. Page 3 Route I-495 Littleton Road Safety Audit Police. Contact information of the RSA team is in the Appendix. As stated previously, overall characteristics and conditions of the study section were presented. A video and pictures were reviewed and a discussion of the potential safety opportunities for enhancement followed. The major discussion at the RSA meeting centered on the fact that only one (1) of twenty-eight median related crashes was reported as a cross-median crash and that the current geometric design of the section under study appears to be more than sufficient to 1) have minimal or no cross-over events and 2) largely has a clear zone area where errant motorists can safely recover or stop with relatively low damage crashes. The short sections of mounds were noted as contributing to roll-over type of crashes although noted by some team members, the mounds may have served to reduce the chance of a cross-over event. The most significant factors raised at the RSA team meeting were: High travel speeds and driver behavior in terms of following too closely and decisions on changing lanes. Guardrails are terminated somewhat soon on the overpasses when roadside slopes are still relatively steep for a greater distance than what is protected. In addition, it was noted that there was limited guidance or information in delineating the median location for motorists. • Analysis Procedures As previously indicated, the RSA analysis generally followed the procedure described in the previously referenced Guideline with some variations and also took into consideration the methods published by the Federal Highway Administration2 and those included in training materials3. The basic tasks included: • • • • 2 3 Obtaining and reviewing crash and other traffic characteristic data and available record plans. Conducting site reconnaissance and collecting a current record of condition via photos and video, Identifying opportunities for enhancement, and Identifying and evaluating potential actions to address the noted issues. Federal Highway Administration, FHWA Road Safety Audit Guidelines, Publication No. FHWA SA-06-06, Washington, D.C., 2006. Federal Highway Administration, Resource Center, Road Safety Audits Mini-Workshop, Jeffrey Shaw, PE, PTOE, presented to New England ITE Section, September 19, 2006. MS Transportation Systems, Inc. Page 4 Route I-495 Littleton Road Safety Audit In assessing the issues identified by the RSA Team, the relative seriousness and potential risk relative to crash frequency and severity were determined. Using the guidelines of FHWA as input and considering characteristics of this specific RSA, the relative frequency criteria and severity criteria were identified and are presented in Table 1 and Table 2, respectively. TABLE 1 FREQUENCY RATING ESTIMATED Exposure high medium high medium low high Probability high high medium medium high low low medium low medium low low EXPECTED CRASH FREQUENCY (PER AUDIT ITEM) 5 or more crashes per year FREQUENCY RATING Frequent 1 to 4 crashes per year Occasional Less that 1 crash per year, but more than 1 crash every 5 years Infrequent Less than 1 crash every 5 years Rare Source: FHWA RSA Training Workshop TABLE 2 SEVERITY RATING Typical Crashes Expected (per audit item) High-speed crashes; head on and rollover crashes Moderate-speed crashes; fixed object or off-road crashes Crashes involving medium to low speeds; lane changing or sideswipe crashes Crashes involving low to medium speeds; typical of rear-end or sideswipe crashes Expected Crash Severity Probable fatality or incapacitating injury Moderate to severe injury Severity Rating Extreme High Minor to moderate injury Moderate Property damage only or minor injury Low Source: FHWA RSA Training Workshop Taking into consideration both frequency and severity, the relative risk of a particular audit item was rated. The risk ratings are shown in Table 3. For each safety issue identified, the potential seriousness of the issue as well as possible mitigation measures have been indicated. MS Transportation Systems, Inc. Page 5 Route I-495 Littleton Road Safety Audit TABLE 3 CRASH RISK ASSESSMENT Frequency Rating Frequent Occasional Infrequent Rare Severity Rating Low Moderate High Extreme C B A A D C B A E D C B F E D C Source: FHWA RSA Training Workshop Crash Risk Ratings: A: minimal risk level B: low risk level C: moderate risk level • D: significant risk level E: high risk level F: extreme risk level RSA Field Audit Field audits were conducted by the RSA team members on or before July 22, 2008. In general, the field visits included “drive-throughs” in each direction of the study section noting physical conditions and the “feel” of the driver. The Prompt List developed as part of the RSA process was used as a guide. The prompt list is included in the appendix for background information. The RSA field audits took place by team members prior to the RSA team meeting. Unfortunately, much of study section was under reconstruction at the time of the field visits. The reconstruction project includes resurfacing and new pavement markings. The road section near Interchange No. 30 and 31 had previously been resurfaced. In addition to noting the reconstruction section, the field audits identified the following: Three (3) travel lanes per direction are provided. Speed limits are posted at 65 miles per hour (mph). The section of road just south of Interchange No. 29 to approximately 3,000 feet north of the interchange was under reconstruction. The section of road that appears “finished” (north of Route 2) had a relatively narrow inside shoulder (1-2 feet) without a rumble strip or reflector posts along the median. The geometry of the highway results in a generally comfortable ride. The median is fairly level and open along much of the section under study but fairly wide providing a sizeable recovery zone. It was noted that the guardrail on the overpass at Route 2 seems to end abruptly in areas that the roadside slope still appears steep. MS Transportation Systems, Inc. Page 6 Route I-495 Littleton Road Safety Audit ANALYSIS In completing the RSA of I-495 in Littleton, findings were compiled from the field audits, the review of the data, and input provided by team members. The following paragraphs summarize the results from each of the key components of the assessment. The section of I-495 under study is approximately 3 miles in length with three (3) lanes per direction separated by a median. The section includes three interchanges: No. 29 at Route 2, No. 30 at Route 110/2A and No, 31 at Route 119. There is one mile separation between the Route 2 and Route 110 interchanges. There is a 2 mile distance between Interchange Nos. 30 and 31. Currently, the road section near Route 2 is being reconstructed. The project includes new pavement, markings and possibly related items such as reflectors. The rehabilitation project is progressing and is expected to be completed by Spring 2009. I-495 bridges over Route 2 creating a vertical curve in combination with a slight horizontal curve at the interchange. Speeds are posted at 65 miles per hour. The section of highway in the area of the two interchanges north of Route 2 shows an inside shoulder of approximately 1-2 feet in width and no rumble strip or imbedded reflectors in place at the time of this analysis. In addition, this section of I-495 does not have the reflective delineator posts installed alongside the median. Figure 2 – View of the median from the northbound direction. MS Transportation Systems, Inc. Page 7 Route I-495 Littleton Road Safety Audit Once north of the Route 2 interchange, there is a long straight section in the northbound direction before entering a large radius curve on the approach to the Route 119 exit. For the most part, the median is open and fairly flat. Exceptions are in the vicinity of bridge columns where short sections of guardrail have been installed. The width of the median (measured from presumed edge line to edge line) was between 92 and 95 feet. Figure 3 Tangent section in northbound direction. Based on the recent MassHighway traffic counts, the roadway carries on average 110,000 to 117,000 vehicles per day in the study section. Figures 4 and 5 illustrate the directional volume over the course of the day for the sections north and south of Route 2. As can be seen in the diagrams, daily volumes exceed 110,000 south of Route 2 while are greater than 117,000 north of Route 2. While there are two distinct peak hours (AM and PM commuter periods), there is little difference in volumes by direction. Peak hour – peak direction volumes are between 4,500 and 5,000 vehicles. Data available as part of the MassHighway crash records system indicated that between 2004 and 2007, there were 28 reported crashes related to the median. Of the 28, only one crash (3.5%) was identified as a cross-median crash. The one cross-median crash resulted in a fatality. In most crashes, the cited driver contributing cause for the crash was non-reported. Other reasons, where cited, were either driving too fast or failing to stay in proper lane. Weather could have been a contributing factor in six (21%) crashes with wet road surface. Approximately half of the crashes resulted in property damage only. MS Transportation Systems, Inc. Page 8 Route I-495 Littleton Road Safety Audit Figure 4. I-495 Hourly Traffic Volumes South of Route 2 Figure 5. I-495 Hourly Traffic Volumes North of Route 2 MS Transportation Systems, Inc. Page 9 Route I-495 Littleton Road Safety Audit SUMMARY OF RSA FINDINGS/POTENTIAL ACTIONS Based on the field review, the review of crash data and discussions among the RSA team members, the issues related to the safe operating conditions of the I-495 in the Littleton area were identified. In essence, the RSA team determined that only a few factors or issues of concern exist at this time that were identified as potentially having an effect on the risk and these are listed in Table 4 along with the assigned risk rating. TABLE 4 SUMMARY OF FACTORS THAT POTENTIALLY AFFECT THE RISK OF SAFETY RELATED EVENTS Factor or Issue Risk Rating “Open” roadside slopes >6:1 near Route 2 overpass D Open Median C Narrow inside shoulder without rumble strip C High travel speeds and driver behavior D Short accel/decel lanes marked C Limited motorists guidance of median location C Although the section of I-495 under study experienced significantly high traffic volumes (>100,000 ADT), the RSA team felt the drive through the section was essentially a “comfortable” drive without any substantive difficulties due to the overall geometry. While there is an open median, it is wide and as evident by the low percentage of crossover crashes, appears to be sufficient in “retaining” errant motorists that enter the median. Thus, the open median in this section currently presents a relatively low level risk for cross-over events although the cross-median crash that did occur during the data period resulted in a fatality. Based on infrequent occurrence yet potentially severe result, the open median issue was rated a ‘C’. High travel speeds and driver behavior in terms of lane changing decisions and “following too closely” appears to be the predominant factor in this section based on team discussions and observations. While the cross-median occurrence is low in this section, there is a high frequency of median related crashes. A risk rating of ‘D’ was assigned to this factor. MS Transportation Systems, Inc. Page 10 Route I-495 Littleton Road Safety Audit One item identified as contributing to a higher risk to safety was the extent of guardrail provided in the area of the Route 2 overpass. The sections of rail do not appear to extend far enough to adequately cover areas where the roadside slope is steeper than 6:1. A risk rating of ‘D’ was assigned to this factor primarily due to the potential severity of the crash that is possible if an entry occurred in areas of steep slope. Other factors noted include the narrow width of the inside shoulder and the lack of a rumble strip. The ongoing rehabilitation project may ultimately address these items but confirmation is needed. The final two areas relate to markings and guidance through the acceleration and deceleration lanes as well as indicating the location of the median. In general, there is a low level of markings provided. A reason for this low level treatment may be due to minimal shoulder width carried through the interchange. The section is also under rehabilitation at the present time and final markings may not have been installed yet. This could be checked in greater detail prior to future installation or maintenance actions. Once the issues were identified and ratings assigned, suggested actions intended to reduce the number of and consequences resulting from median related crashes and other types of crashes as well were evaluated. The following paragraphs include a discussion pertaining to the issues and the potential actions to consider for implement. Given that this RSA is focused on cross-median events, the initial action evaluated was the potential installation of a median barrier. • Consideration of a Median Barrier One of the more significant actions that could be considered is to install median barriers in the current “open” areas. Although the RSA team concluded that the open median section did not pose a high risk at this time, the section was evaluated in terms of the median barrier warrants. A barrier can be considered when there is a higher than desirable chance or a greater risk for median cross-over crashes to occur and that have or could result in fatalities and/or a high proportion of injury related crashes. In addition, a barrier could be considered when the consequences or severity of a crash without a barrier are worse than if the barrier were in place. Factors that generally come into play in deciding on whether a median should be installed involve the following: High volumes and speeds Truck volumes and mix Narrow median MS Transportation Systems, Inc. History of cross-median crashes High risk of catastrophic event Page 11 Route I-495 Littleton Road Safety Audit These items have been reviewed relative to the I-495 section under study. Figure 6 presents a review of the corridor in relation to the median warrant criteria presented in the AASHTO RDG4. As can be seen in the diagram, with the median (as measured from edge line to edge line) is approximately 92-95 feet and a volume of over 100,000 vehicles on an average day, the intersection of the two criteria falls to the right of the chart where a barrier can be “optional”. In addition to the chart and related warrant criteria, which is a guideline, further consideration was given to the following: A small proportion of the median entries (28) over the four (4) year crash period was experienced. The road geometry is adequate and results in generally a comfortable drive. Consequently, based on the analysis of the data, the field drive-thru and discussion of the conditions by the RSA team members, it was concluded that a median barrier is not warranted on this section of I-495 at this time. 4 American Association of State Highway and Transportation Officials, Roadside Design Guide, Washington, D.C., 2002, Chapter 6 Update 2006. MS Transportation Systems, Inc. Page 12 median width 95-100 feet volume > 100,000 ADT 80 AVERAGE DAILY TRAFFIC (thousands) 70 BARRIER RECOMMENDED 60 BARRIER CONSIDERED 50 40 30 BARRIER OPTIONAL 20 10 0 0 10 20 30 40 50 60 70 MEDIAN WIDTH (feet) Analysis of Median Barrier Warrant I-495 Road Safety Audit Littleton, Massachusetts MS Transportation Systems, Inc. Framingham, Massachusetts Figure 6 Route I-495 Littleton Road Safety Audit Recommendations As a result of the RSA analysis and team input and although it was concluded that a median barrier not be installed at this time based on the history of cross-median crashes. However, should the frequency of cross-median crashes increase, then the barrier installation should be reconsidered. A set of recommendations have been identified and are summarized in Table 7. In general, these actions are intended to reduce the chance of cross-median crashes as well as reduce the number and severity of all crashes of this section of I-495 in Littleton. Identified in the table in addition to the risk factor and recommended action are the estimated costs and potential timeframe (i.e. short (0-1 year), medium (1-3 years) and long (>3 years)). TABLE 7 SUMMARY OF RECOMMENDATIONS Risk Factor “Open” roadside slopes >6:1 near Route 2 overpass Open Median Risk Rating D C Narrow inside shoulder without rumble strip Recommended Action extend guardrail – total of approx. 600 feet in length Estimated Cost $30,000 Short to medium term NO BARRIER PROPOSED AT THIS TIME n/a n/a Widen shoulder Install rumble strip n/a1 n/a1 Could be addressed in on-going construction – need to confirm C 1 2 Estimated Timeframe High travel speeds and driver behavior D Increase enforcement levels TBD short term Short accel/decel lanes marked C provide consistent and more visible markings $6,0002 short term Limited motorists guidance of median location C Install flexible delineator posts $3,000 short term may be included in ongoing rehabilitation project TBD – to be determined example of modified marking plans depicted in Appendix may be able to be incorporated as part of future marking maintenance operation. One factor that was noted at the Route 2 interchange is that the roadside slope in the vicinity of the overpass is fairly steep (i.e. >6:1 slope) and the guardrail that is in place appears to end to soon. With lane changing activity high at this interchange, extending the guardrail would reduce the possibility of median entry crashes in this area. Figure 7 illustrates the general area of the extended guardrail. The estimated cost is $30,000. MS Transportation Systems, Inc. Page 14 495 ROUTE 2 EB ON-RAMP EXTEND GUARDRAIL 200 FEET 495 ROUTE 2 WB ON-RAMP EXTEND GUARDRAIL 400 FEET Proposed Guardrail Extensions in NB Direction at Route 2 Interchange I-495 Road Safety Audit Littleton, Massachusetts MS Transportation Systems, Inc. NOT TO SCALE Framingham, Massachusetts FIGURE 7 Route I-495 Littleton Road Safety Audit Although it was decided that a median barrier is not needed at this time within section, it was recommended that improved delineation of the median be implemented via reflectorized, flexible posts. In addition, it was recommended that the inside shoulder be set wide enough to accommodate a rumble strip. Ideally, the inside shoulder would be a minimum of four (4) feet in width. The ongoing construction project is expected to address this issue and is also expected to incorporate the rumble strips. It is suggested that improved markings be provided at the acceleration and deceleration lanes including the gore areas. Consistent, high visibility markings such as these shown in Figure 8 or in the Appendix should be considered. Maintaining the minimum outside shoulder width allowed through the interchange may be an issue without widening and could limit the extent of markings. This can be examined in more detail when scheduling pavement marking maintenance activities. If the acceleration lanes are confirmed to be deficient and cannot be corrected by simply modifying the markings, then YIELD signs should be installed on the ramps. Lastly, travel speeds and driver behavior has been cited and observed to be a problem on I-495 where volumes exceed 110,000 ADT. Increased enforcement levels should be funded and provided. MS Transportation Systems, Inc. Page 16 OPTION A OPTION B Broken lane markings for one-half of full-width deceleration lane Channelizing lines Broken lane markings for one-half of full-width deceleration lane Channelizing lines Parallel acceleration lane Potential Pavement Markings On Ramp Merge Locations I-495 Road Safety Audit Littleton, Massachusetts MS Transportation Systems, Inc. NOT TO SCALE Framingham, Massachusetts FIGURE 8 Route I-495 Littleton Road Safety Audit Appendix • • • • • • MS Transportation Systems, Inc. RSA Meeting Agenda RSA Meeting Attendees Median Crash Diagram Crash Summary Data Traffic Volume Data Example of AccelerationDeceleration Lane Markings Page 18 Road Safety Audit Littleton – Interstate 495 Meeting Location: MassHighway District 3 Office 403 Belmont Street, Worcester Tuesday, July 22, 2008 11:00 AM – 12:30 PM Type of meeting: Cross Median – Road Safety Audit Attendees: Invited Participants to Comprise a Multidisciplinary Team Please bring: Thoughts and Enthusiasm!! 11:00 AM Welcome and Introductions 11:15 AM Introduction to Road Safety Audits and Cross Median Crashes 11:30 AM Review of Site Specific Material • Crash & Volume Summaries– provided in advance • Existing Geometries and Conditions • Video and Images 12:00 PM Completion of RSA • Identification of Safety Concerns – using RSA Prompt List as a guide • Identification of Possible Countermeasures 12:30 PM Adjourn for the day – but the RSA has not ended Instructions for Participants: • Before attending the RSA on July 22nd, participants are encouraged to drive Interstate 495 in Littleton from exit 29 – exit 31 and complete/consider elements on the RSA Prompt List with a focus on safety factors affecting cross median crashes. • All participants will be actively involved in the process throughout. Participants are encouraged to come with thoughts and ideas, but are reminded that the synergy that develops and respect for others’ opinions are key elements to the success of the overall RSA process. • After the initial RSA meeting, participants will be asked to comment and respond to the document materials to assure it is reflective of the RSA completed by the multidisciplinary team. ROAD SAFETY AUDIT MEETING I-495 - June 22, 2008 MassHighway District 3 Offices, Worcester MA Attendance List Name Agency/Dept. Email Bill Scully MS Transportation Systems, Inc. bscullyjr@mac.com Kathryn Cook MHD, Traffic Intern kathryn.cook@mhd.state.ma.us Christine Breen MHD, Highway Design christine.breen@mhd.state.ma.us Edward Pomfred MHD, Traffic Intern edward.pomfred@mhd.state.ma.us Timothy White FHWA timothy.white@fhwa.dot.gov Bonnie Polin MHD bonnie.polin@state.ma.us Lisa Schletzbaum MHD, Safety Management Unit lisa.schletzbaum@mhd.state.ma.us Sgt. Eugene O'Neill MSP eugene.oneill@polistate.ma.us Robert Babb MHD, District 3 robert.babb@mhd.state.ma.us Mark Johnson MHD, District 3 mark.johnson@mhd.state.ma.us Chris Hogan MHD, District 3 Eric Nascimento MHD, District 3 MS Transportation Systems, Inc. eric.nascimento@mhd.state.ma.us Interstate 495 Median Crashes " ) ± 31 WESTFORD 26 Crash IDs between 14-25 ) " 15 119 14 BR UC E AR RV A H D R O ST RE ET " ) 30 AD KI NG ST E RE N KI G ST E RE T Crash IDs between 10-13 ) " T 2A GO LD LITTLETON I SM TH ST 9 E RE T ET TAYLOR ST RE § ¦ ¨ 495 SH W 29 Crash IDs between 3-8 O OD Type of Median Crash 2004-2007 * A UE Cross Median, Fatal Crash Interstate Median, Non-Fatal Crash Principal Arterial ) " OW WT NE 2 Y ELE RO OR TAY L AD E ST R E BOXBOROUGH Municipal Boundary EE T K BU L 1 R E Major Roads VE N Median, Property Damage Only TR RS STE FO E N Legend HA R " ) 2 AK LA O NR AD * 2007 crash file has not yet been closed. 0 0.1 0.2 0.3 Miles 0.4 Minor Arterial NA S H OCollector BA RO AD Local T MASSACHUSETTS HIGHWAY SAFETY DIVISION CRASH SUMMARY ROADWAY: I-495 STUDY PERIOD: NO. CITY: 1/1/2004 CRASH NUMBER CRASH DATE AND TIME LOCATION: LITTLETON TO 4/12/2008 TRAVEL LIGHT WEATHER ROAD REASON FOR VEHICLE MEDIAN OR CROSS BOXBOROUGH TO WESTFORD TOWN LINES DRIVER CONTRIBUTING CRASH DIRECTION CONDITION CONDITION SURFACE RUNNING OFF ROAD LEFT MOVEMENT MEDIAN CRASHES CAUSE SEVERITY 1 2180577 10/5/2006 Thu 4:55 AM NB Dark - not lighted Clear Dry Vehicle 1 fail to stay in lane, striking the guardrail and vehicle 3 behind struck vehicle 1. Vehicle 3 veer off into median Travel Lane to Median Median Failure to keep in proper lane or running off road Non-fatal injury 2 2130302 12/7/2006 Thu 3:30 PM NB Daylight Clear Dry Vehicle was cut off and swerved into guardrail to avoid striking the other vehicle Travel lane to median Median No Improper Driving Property Damage Only 3 2014665 2/27/2006 Mon 8:40 AM SB Daylight Clear Dry Vehicle tried to merge into traffic from on-ramp, then got struck in the rear end and spun into median Travel Lane to Median Median Not Reported Property damage only 4 1795779 2/8/2004 Sun 11:21 AM SB Daylight Clear Dry Vehicle 1 was struck by Vehicle 2, cause vehicle 1 struck the guardrail on the right then bounces into the median Travel Lane to Right side Guardrail to Median Median Failure to keep in proper lane or running off road Non-fatal injury 5 2066598 5/6/2006 Sat 2:15 PM NB Daylight Rain Wet Unknown NB Travel Lane to Median to SB travel lane Cross Median Not Reported Fatal injury 6 2209071 4/4/2007 Wed 5:10 PM SB Daylight Snow Snow Vehicle drove into median for an unknown reason Travel lane to median Median Not Reported Property Damage Only 7 2114966 7/31/2006 Mon 4:42 AM SB Dawn Clear Dry Vehicle 1 was cut-off by Vehicle 2, lost control of vehicle and spun into median Travel Lane to Median Median No Improper Driving Property damage only 8 2311814 4/12/2008 Sat 7:23 AM NB Daylight Rain Wet Vehicle lost control trying to pass another vehicle Travel lane to median Median Not Reported Non-Fatal Injury 9 2266284 12/16/2007 Sun 7:30 PM NB Dark- Unknown roadway lighting Snow Ice Vehicle was struck by another vehicle and spun into median Travel lane to median Median Not Reported Property Damage Only 10 2254334 5/13/2007 Sun 4:55 AM NB Dusk Not Reported Dry Vehicle lost control, went off the road to the left then cut across all lanes, ending in a ditch on the right side of the road Travel lane to median to right side of road Median Not Reported Property Damage Only 11 2256448 10/24/2007 Wed 12:25 PM SB Daylight Cloudy Dry Vehicle was trying to pass another vehicle, struck the vehicle and spun into the median Travel lane to median Median Not Reported Property Damage Only 12 2298137 3/12/2008 Wed 6:40 PM NB Daylight Cloudy Wet Vehicle swerved to avoid another vehicle and ran into embankment Travel lane to median Median Not Reported Property Damage Only 13 2282413 1/22/2008 Tue 4:05 PM NB Daylight Cloudy Dry Vehicle was struck by another vehicle and spun into median Travel lane to median Median Not Reported Property Damage Only 14 1796022 7/16/2004 Fri 12:00 AM NB Dark - not lighted Clear Dry Vehicle was cut-off by unknown vehicle, lost control of vehicle Travel Lane to Median Median Failure to keep in proper lane or running off road Property damage only 15 2130156 11/13/2006 Mon 5:25 PM NB Dark - not lighted Rain Wet Vehicle was speeding, lost control of vehicle and went into embankment Travel Lane to Median Median Exceeded authorized speed limit Non-fatal injury 16 2059957 6/19/2006 Mon 9:30 AM SB Daylight Clear Dry Vehicle was cut-off by another vehicle, lost control of vehicle and spun into median Travel Lane to Median Median No Improper Driving Property damage only 17 2211377 4/19/2007 Thu 11:04 AM SB Daylight Clear Dry Driver had a seizure, swerved into median and overcorrected back onto road, striking another vehicle and ending up on right side of road Travel lane to median to right side of road Median Not Reported Non-Fatal Injury 18 2256451 10/23/2007 Tue 11:20 AM SB Daylight Clear Dry Vehicle was cut off and swerved into median, striking a tree Travel lane to median Median Not Reported Non-Fatal Injury 19 2237805 4/25/2007 Wed 6:26 AM SB Not Reported Not Reported Dry Vehicle rolled over into median for an unknown reason Travel lane to median Median Not Reported Non-Fatal Injury 20 2238120 9/22/2007 Sat 2:37 PM NB Daylight Clear Dry Vehicle rolled over into the median avoiding a truck Travel lane to median Median Not Reported Non-Fatal Injury 21 2238521 8/7/2007 Tue 4:30 AM NB Dark- not lighted Fog, Smoke, Smog Dry Vehicle rolled over into the median avoiding a truck Travel lane to median Median Not Reported Non-Fatal Injury 22 2220312 6/11/2007 Mon 7:23 PM NB Daylight Clear Dry Vehicle lost control for an unknown reason and rolled over in median Travel lane to median Median Not Reported Non-Fatal Injury 23 2178870 3/16/2007 Fri 3:20 PM NB Daylight Snow Snow Vehicle swerved to avoid another vehicle which had stopped suddenly and lost control due to slippery road conditions Travel lane to median Median Not Reported Non-Fatal Injury 24 2220299 5/28/2007 Mon 1:07 AM NB Dark- not lighted Clear Dry Vehicle lost control for an unknown reason and rolled over in median Travel lane to median Median Not Reported Non-Fatal Injury 25 2323440 3/24/2008 Mon 5:32 PM NB Daylight Clear Dry Vehicle swerved attempting to avoid another vehicle, struck the other vehicle and went into embankment Travel lane to median Median Not Reported Property Damage Only 26 2050445 3/27/2006 Mon 5:40 AM SB Dawn Clear Dry Lost Control of the Vehicle and skidded onto the median Travel Lane to Median Median Driving too fast for conditions Property damage only 27* 2217556 8/7/2007 Tue 9:43 PM NB Dark- lighted roadway Clear Dry Vehicle rolled over into the median avoiding a truck Travel lane to median Median Not Reported Non-Fatal Injury 28* 2306825 3/28/2008 Fri 6:10 AM SB Dawn Sleet, hail (freezing rain or drizzle) Snow Vehicle lost control due to slippery road conditions and hit guardrail, entered traffic again and was struck by another vehicle Travel lane to left side guardrail to travel lane Median Not Reported Non-Fatal Injury * Crash could not be geocoded based on reported location information TOTAL NO. 28 100% CLEAR 15 54% CLOUDY 3 11% WEATHER CONDITION FOG, SMOKE, SMOG RAIN 1 3 4% 11% SNOW 2 7% SLEET, HAIL 1 4% NO IMPROPER DRIVING 3 11% DUSK CRASH SEVERITY TYPE OF CRASH NOT REPORTED 2 7% DRIVER CONTRIBUTING CAUSE PROPERTY DAMAGE ONLY 13 46% NON-FATAL INJURY 14 50% FATAL INJURY 1 4% NOT REPORTED 20 71% FAILURE TO KEEP IN PROPER LANE OR RUNNING OFF ROAD 3 11% DAYLIGHT DARK- NOT LIGHTED DARK- LIGHTED LIGHT CONDITION DARK- LIGHTING UNKNOWN DAWN EXCEEDING AUTHORIZED SPEED LIMIT 1 4% NOT REPORTED 16 5 1 1 3 1 1 57% 18% 4% 4% 11% 4% 4% 2007 and 2008 CRASH INFORMATION IS NOT COMPLETE CRASH SUMMARY IS BASED ON ELECTRONIC CRASH REPORTS WITH POLICE NARRATIVES DRIVING TOO FAST FOR CONDITIONS 1 4% MEDIAN 27 96% CROSS MEDIAN 1 4% I-495, N. of RT-2 4/12/2006 Northbound Southbound Direction Direction Start time 12:00 AM 452 525 1:00 AM 383 426 2:00 AM 531 434 3:00 AM 743 419 4:00 AM 1,440 614 5:00 AM 3,149 1,575 6:00 AM 4,634 3,493 7:00 AM 4,658 5,131 8:00 AM 3,120 5,082 9:00 AM 2,695 3,760 10:00 AM 2,644 2,826 11:00 AM 2,687 2,900 12:00 PM 2,801 2,785 1:00 PM 3,212 2,956 2:00 PM 4,083 3,474 3:00 PM 4,581 3,952 4:00 PM 4,852 4,449 5:00 PM 3,462 4,806 6:00 PM 2,117 2,907 7:00 PM 1,559 2,612 8:00 PM 1,290 1,741 9:00 PM 1,091 1,503 10:00 PM 848 1,106 11:00 PM 608 759 Daily Total 57,640 TOTAL 977 809 965 1,162 2,054 4,724 8,127 9,789 8,202 6,455 5,470 5,587 5,586 6,168 7,557 8,533 9,301 8,268 5,024 4,171 3,031 2,594 1,954 1,367 60,235 117,875 6,000 Northbound Direction Southbound Direction 5,000 4,000 3,000 2,000 1,000 PM :0 0 PM 10 PM 8: 00 PM 6: 00 PM Time of Day 4: 00 PM 2: 00 :0 0 AM 12 :0 0 AM 10 AM 8: 00 AM 6: 00 AM 4: 00 2: 00 :0 0 AM 0 12 Hourly Volume (Number of Vehicles) Directional Traffic Volumes along I-495, North of Route 2, Littleton Wednesday, April 12, 2006 I-495, S. of RT-2 6/27/2007 Northbound Southbound Direction Direction Start time 12:00 AM 540 513 1:00 AM 457 395 2:00 AM 474 322 3:00 AM 572 384 4:00 AM 762 529 5:00 AM 1,422 1,314 6:00 AM 2,757 2,816 7:00 AM 3,983 4,408 8:00 AM 4,192 4,157 9:00 AM 3,625 3,427 10:00 AM 3,250 2,730 11:00 AM 2,850 2,709 12:00 PM 2,808 2,904 1:00 PM 2,860 2,682 2:00 PM 3,258 3,157 3:00 PM 3,925 3,518 4:00 PM 4,227 3,986 5:00 PM 4,242 3,897 6:00 PM 3,572 3,367 7:00 PM 2,147 1,831 8:00 PM 1,669 1,705 9:00 PM 1,413 1,349 10:00 PM 1,120 934 11:00 PM 1,067 773 Daily Total 57,192 TOTAL 1,053 852 796 956 1,291 2,736 5,573 8,391 8,349 7,052 5,980 5,559 5,712 5,542 6,415 7,443 8,213 8,139 6,939 3,978 3,374 2,762 2,054 1,840 53,807 110,999 5,000 Northbound Direction Southbound Direction 4,500 4,000 3,500 3,000 2,500 2,000 1,500 1,000 500 PM :0 0 PM 10 PM 8: 00 PM 6: 00 PM Time of Day 4: 00 PM 2: 00 :0 0 AM 12 :0 0 AM 10 AM 8: 00 AM 6: 00 AM 4: 00 2: 00 :0 0 AM 0 12 Hourly Volume (Number of Vehicles) Directional Traffic Volumes along I-495, South of Route 2, Littleton Wednesday, June 27, 2007 Examples of Channelizing Line Applications for Exit Ramp Markings a-Parallel deceleration lane b-Tapered deceleration lane Neutral area Optional chevron markings Channelizing lines Theoretical gore point Channelizing lines Broken lane markings for onehalf of f ull-width deceleration lane Optional dotted extension of lane line Legend Direction of travel Source: Manual on Uniform Traffic Control Devices Potential Pavement Markings Off Ramp Diverge Locations NOT TO SCALE MS Transportation Systems, Inc. Framingham, Massachusetts Examples of Channelizing Line Applications for Exit Ramp Markings c-Auxiliary lane, such as at cloverleaf interchange Neutral area Optional chevron markings Theoretical gore point Broken lane line markings for full length of acceleration/deceleration lane Channelizing lines Legend Direction of travel Source: Manual on Uniform Traffic Control Devices Potential Pavement Markings On/Off Ramp Merge Locations NOT TO SCALE MS Transportation Systems, Inc. Framingham, Massachusetts