ROAD SAFETY AUDIT MAJOR HIGHWAY MEDIAN CROSS-OVER CRASHES I-91 HOLYOKE – WEST SPRINGFIELD Prepared for Prepared by MS Transportation Systems, Inc. Framingham, Massachusetts February 2009 ROAD SAFETY AUDIT MAJOR HIGHWAY MEDIAN CROSS-OVER CRASHES I-91 HOLYOKE – WEST SPRINGFIELD Final Report February 2009 Prepared for Massachusetts Highway Department Prepared by MS Transportation Systems, Inc. Consulting Engineers and Planners 300 Howard Street P.O. Box 967 Framingham, Massachusetts 01701 508-620-2832 508-620-6897 (fax) www.mstransportationsystemsinc.com I-91 Holyoke – West Springfield Road Safety Audit TABLE OF CONTENTS Page INTRODUCTION 1 RSA PROCESS 3 ANALYSIS 8 SUMMARY OF RSA FINDINGS/POTENTIAL ACTIONS 12 RECOMMENDATIONS 20 APPENDIX 28 MS Transportation Systems, Inc. Page i I-91 Holyoke-West Springfield Road Safety Audit INTRODUCTION Lane departure crashes are one of the primary fatal crash types in Massachusetts. The Commonwealth exceeds the national average for lane departure crashes and was designated a lead state in lane departure crashes by the American Association of State Highway and Transportation Officials (AASHTO). The Massachusetts Highway Department (MHD) conducted a study of the problem and found that during 2002-2004, lane departure crashes accounted for 25 percent of all injury crashes and nearly half, 46 percent, of all fatal crashes. As part of the effort in implementing the safety plan and specifically reducing lane departure crashes, the MassHighway is completing a Road Safety Audit (RSA) Review Project specifically focused on median crossing (or median cross-over) crashes on its major highways. Road safety audits are a formal safety performance examination on existing or future roadways by an independent audit team. These specific audits are being conducted in locations where cross-over experience has been or has the potential to be of concern and where the RSA team has judged that factors exist that could affect the safety risk. During the audit, the RSA team works to identify opportunities for enhancing safety and to recommend specific enhancements intended to reduce median cross-over crashes and improve the overall safety along the highway. An RSA was conducted for the interstate highway (I-91) in Holyoke-West Springfield as part of this overall effort. The roadway section under study, shown in Figure 1, was between Interchange No. 13 at Route 5 to Interchange No. 18 although most of the focus area was south of Interchange No. 16. This section had experienced a number of median related crashes that included several reported cross-over incidents. The purpose of this I-91 Holyoke-West Springfield RSA was to assess current safety conditions and recommend a set of actions to enhance the safe operation of the highway section under study. Recommendations contained in this report reflect the overall consent of the RSA team and do not necessarily reflect the official views of MassHighway. MS Transportation Systems, Inc. Page 1 Interchange No. 18 91 5 Interchange No. 17 141 Interchange No. 16 202 Holyoke 5 W. Springfield Interchange No. 15 Interchange No. 14 90 91 5 West Springfield Interchange No. 13 Note: Interchange No. 18 (not shown) is 7miles north of No. 17 N Project Location W E ` S I-91 Road Safety Audit Holyoke-West Springfield, Massachusetts MS Transportation Systems, Inc. 1 : 25,000 Framingham, Massachusetts FIGURE 1 Interchange No. 18 91 5 Interchange No. 17 141 Interchange No. 16 202 Holyoke 5 W. Springfield Interchange No. 15 Interchange No. 14 90 91 5 West Springfield Interchange No. 13 Note: Interchange No. 18 (not shown) is 7miles north of No. 17 N Project Location W E ` S I-91 Road Safety Audit Holyoke-West Springfield, Massachusetts MS Transportation Systems, Inc. 1 : 25,000 Framingham, Massachusetts FIGURE 1 I-91 Holyoke-West Springfield Road Safety Audit RSA PROCESS In conducting the RSA, the overall procedures outlined in the Median Cross-Over RSA Guideline Report1 were followed. Some modifications to the process were made given the characteristics of the facility being reviewed. The process included identifying RSA team members; conducting field visits; holding a RSA team meeting and then completing an assessment of the data and findings from the field visits and meetings to render recommended actions for MassHighway to consider. Data including recent traffic volume data, summary crash records for the 2004-2007 period, detailed crash narratives of the eleven (11) cross-over crashes, and available record highway plans were provided and reviewed by the RSA consultant. Field visits were conducted by the RSA team members. A video recording of the sections under study was taken by the RSA Consultant. The site visits were completed prior to the RSA team meeting. At that meeting, the RSA consultant provided a brief overview of the RSA purpose, a summary of the roadway section’s characteristics and results of the review to date. The RSA team provided input and discussed the key items noted in the field and that were listed on the RSA Median Cross-Over Prompt List. Issues and concerns were noted. Following the RSA meeting, the RSA consultant compiled the information, completed the analysis and circulated the draft report. • RSA Team The following individuals participated in the I-91 Holyoke-West Springfield Road Safety Audit: Lt. Steven Hughes, State Police Sam Gregorio, MassHighway, District 2 Bao Lang, MassHighway, District 2 Khyati Parmar, PVPC Hal Piligian, MassHighway, District 2 Trung Vo, MassHighway, District 2 Robert Fay, MassHighway Lyris Liautaud, MassHighway Lt. Lawrence Ashman, State Police • Lisa Schletzbaum, MassHighway Safety Xian Chen, MassHighway Gary Roux, PVPC John Donoghue, MassHighway, District 2 Ken Wanar, MassHighway William Goulet, MassHighway, District 2 Kathryn Cook, MassHighway William J. Scully, MS Transportation Systems (RSA Consultant) RSA Team Meeting The RSA team meeting took place on June 18, 2008 at the District 2 offices in Northampton. At the meeting, the RSA consultant provided a brief overview of the RSA 1 MS Transportation Systems, Inc., Road Safety Audits, Median Cross-Over Crashes, Audit Guidelines, Prepared for MassHighway, October 2007. MS Transportation Systems, Inc. Page 3 I-91 Holyoke-West Springfield Road Safety Audit purpose, a summary of the roadway section’s characteristics and results of the review to date. The RSA team listed above was present at the meeting. The video record of I-91 taken while driving the corridor was viewed. During and following the video, discussions related to issues and potential factors that could affect safety along the corridor and possible solutions to reduce this risk were conducted. The RSA team provided input on the key items observed in the field and those items that were listed on the RSA Median Cross-Over Prompt List. Much of the meeting was discussing observations from the field visits, but also some historical perspectives by the State Police Representatives. The key items noted during the meeting included the following: The clear zone in the median is open and appeared to be in good condition. Signage, in general, seemed to be adequate. The spacing between Interchange Nos. 14 and 15 appears to be somewhat “tight”. This can affect merging and weaving operations. High truck volumes were observed. The southbound merge area in the vicinity of Interchange No. 16 is a significant issue. Opportunities to encourage motorists to remain in certain lanes should be identified. Sunglare occurs during certain periods that have a significant effect on visibility and movement. The fatal cross-over crash occurred south of the turnpike interchange – large open, crossable median – the possibility of a barrier was discussed. • Analysis Procedures As previously indicated, the RSA analysis generally followed the procedure described in the previously referenced Guideline with some variations and also took into consideration the methods published by the Federal Highway Administration2 and those included in training materials3. 2 3 Federal Highway Administration, FHWA Road Safety Audit Guidelines, Publication No. FHWA SA-06-06, Washington, D.C., 2006. Federal Highway Administration, Resource Center, Road Safety Audits Mini-Workshop, Jeffrey Shaw, PE, PTOE, presented to New England ITE Section, September 19, 2006. MS Transportation Systems, Inc. Page 4 I-91 Holyoke-West Springfield Road Safety Audit The basic tasks included: • • • • Obtaining and reviewing crash and other traffic characteristic data and available record plans. Conducting site reconnaissance and collecting a current record of condition via photos and video, Identifying opportunities for enhancement, and Identifying and evaluating potential actions to address the noted issues. In assessing the issues identified by the RSA Team, the relative seriousness and potential risk relative to crash frequency and severity were determined. Using the guidelines of FHWA as input and considering characteristics of this specific RSA, the relative frequency criteria and severity criteria were identified and are presented in Table 1 and Table 2, respectively. ESTIMATED Exposure high medium high medium low high Probability high high medium medium high low low medium low medium low low TABLE 1 FREQUENCY RATING EXPECTED CRASH FREQUENCY (PER AUDIT ITEM) 5 or more crashes per year FREQUENCY RATING Frequent 1 to 4 crashes per year Occasional Less that 1 crash per year, but more than 1 crash every 5 years Infrequent Less than 1 crash every 5 years Rare Source: FHWA RSA Training Workshop TABLE 2 SEVERITY RATING Typical Crashes Expected (per audit item) High-speed crashes; head on and rollover crashes Moderate-speed crashes; fixed object or off-road crashes Crashes involving medium to low speeds; lane changing or sideswipe crashes Crashes involving low to medium speeds; typical of rear-end or sideswipe crashes Expected Crash Severity Probable fatality or incapacitating injury Moderate to severe injury Severity Rating Extreme High Minor to moderate injury Moderate Property damage only or minor injury Low Source: FHWA RSA Training Workshop MS Transportation Systems, Inc. Page 5 I-91 Holyoke-West Springfield Road Safety Audit Taking into consideration both frequency and severity, the relative risk of a particular audit item was rated. The risk ratings are shown in Table 3. For each safety issue identified, the potential seriousness of the issue as well as possible mitigation measures have been indicated. TABLE 3 CRASH RISK ASSESSMENT Frequency Rating Frequent Occasional Infrequent Rare Severity Rating Low Moderate High Extreme C B A A D C B A E D C B F E D C Source: FHWA RSA Training Workshop Crash Risk Ratings: A: minimal risk level B: low risk level C: moderate risk level • D: significant risk level E: high risk level F: extreme risk level RSA Field Audit Field audits were conducted by the RSA team members on or before June 18, 2008. In general, the field visits included “drive-throughs” in each direction of the study section noting physical conditions and the “feel” of the driver. The Prompt List developed as part of the RSA process was used as a guide. The prompt list completed by District 2 staff is included in the appendix for background. The field audits showed the following: There are three (3) travel lanes per direction between Interchange No. 13 and 16 – north of Interchange No. 16, two lanes are provided per direction. Speeds are posted at 65 mph. The inside shoulder appears to be 4 feet in width but may be somewhat narrower in certain areas. The median is primarily a “depressed” median south of Interchange No. 16. From Interchange No 16 to north of Interchange No. 17, the median slopes relatively steeply down from the higher southbound direction to the northbound direction. Guardrail is placed at the inside edge of the southbound direction adjacent to the high speed lane. MS Transportation Systems, Inc. Page 6 I-91 Holyoke-West Springfield Road Safety Audit Some pavement rutting was noted south of Interchange No. 16. It was also noted that in some areas there was a noticeable edge drop-off. Rumble strip exists on inside and outside shoulder. South of the Interchange No. 14 (Mass Turnpike), there is a long downgrade in the southbound direction to the Interchange No. 13 (Route 5). In general, driving the mainline and merging from on-ramps felt relatively comfortable with some exceptions. These exceptions included the area between Interchange No. 15 SB on-ramp to Interchange No. 14 off-ramp; No. 13 NB on-ramp; and the No. 17 SB on-ramp. MS Transportation Systems, Inc. Page 7 I-91 Holyoke-West Springfield Road Safety Audit ANALYSIS In completing the I-91 RSA in Holyoke and West Springfield, findings were compiled from the field audits, the review of the data and input provided by team members. The following sections summarize the results from each of the key components of the assessment. The section of I-91 under study is approximately 15 miles in total length although about 7 miles of the total are located between Interchange No. 16 and 18 where the median is largely not crossable due to guardrail in place and/or thick vegetation. Between Interchange No. 13 and 16, the roadway cross-section has three lanes per direction separated by a median. At Interchange No. 16, the highway transitions from three to two lanes in the northbound direction while adding a third travel lane in the southbound direction. There are six interchanges within the study section including Interchange No. 14 that connects with the Massachusetts Turnpike. Speed limits are posted at 65 miles per hour. There is high elevation tower pole lighting provided in the area of Interchange 16. Rumble strips are provided in both the inside and outside shoulders. The strips are located just off the edge lines. Embedded reflectors (raised markers) are provided in the lane lines in both directions as well. There are no reflectorized delineator posts provided along the median in the study section. The section between Interchange No. 13 in West Springfield (at Route 5) to approximately the Turnpike overpass is generally characterized as a long (7,300 feet), fairly straight section of highway on an upgrade from south to north. In this area, there are 3 lanes per direction and the median width is approximately 60 to 65 feet until close to Interchange No. 13 where it narrows to between 45 to 50 feet. As indicated above, Interchange No. 14 provides access to the Turnpike. Field observations and discussions at the RSA meeting noted the “feel” of closeness and some driver discomfort between Interchange Nos. 14 and 15 (Lower Westfield Road) due to the high volume merging and weaving that occurs. The distance between the two successive ramps is approximately 2,800 feet in the northbound direction and 2,100 feet in the southbound direction. There is a lane drop in the northbound direction approaching Exit 16. Motorist guidance for the lane drop is in the form of two standard roadside lane drop W4-2 signs (one on each side of the paved way) approximately ½ mile prior to the exit with one reminder W4-2 sign on the east side of the highway just prior to the exit. The distance between the Interchange No. 15 northbound on-ramp to the off-ramp for Interchange No. 16 is 1.4 miles. MS Transportation Systems, Inc. Page 8 I-91 Holyoke-West Springfield Road Safety Audit Figure 2 - I-91 Northbound approach to Interchange No. 15 – Lower Westfield Road In the southbound direction, the third travel lane is picked up with the on-ramp from Interchange No. 16. Signage approaching this area indicates an upcoming merge. Field observations noted mainline motorists shifts to the left approaching the on-ramp although the shift is unnecessary given the third lane addition. It was also noted at the RSA meeting that many motorists using the on-ramp tend to shift left into the center lane immediately upon entering I-91 when that movement is also unnecessary in that immediate area – again given the addition of the third southbound travel lane. All of this results in a chain-reaction of lane changing; under utilization of the road capacity in the immediate area of Interchange No. 16; and added congestion during the peak travel periods. Figure 3 - Southbound and Northbound views of open section between Interchange No. 13 (Route 5) and Interchange No. 14 (Turnpike) MS Transportation Systems, Inc. Page 9 I-91 Holyoke-West Springfield Road Safety Audit The median width (edge line to edge line) for the most part varies from approximately 45 to 66 feet. As indicated previously, the section south of Interchange No. 16 would be considered depressed or nearly flat. In the area of Interchange No. 16 and points north until near Interchange No. 18, the northbound and southbound sections are at different grades (i.e. the southbound direction is higher than the northbound direction). The median in this area is sloped down from the southbound direction to the northbound direction. A guardrail is placed at the pavement edge of the inside (high speed) travel lane in the southbound direction. Closer to Interchange No. 18, the median opens up again with elevations of each direction being similar. In the area of Interchange No. 18, the median width is in the range of 60 to 65 feet. The inside shoulder is mostly four 4 feet in width though in certain stretches varies between 2 to 4 feet in width. Rumble strips have been installed approximately 6 inches off the edge line. Figure 4 – Grade elevation difference NB and SB directions in vicinity of Interchange No. 16 Based on recent MassHighway traffic counts, the roadway carries on average approximately 73,000 vehicles per day near Interchange No. 15 with approximately 80,000 vehicles per day near Route 5. Figure 5 illustrates the directional traffic flow on I91, south of Lower Westfield Road. Peak hour peak direction flows are in the range of 3,000 to 3,500 vehicles per hour. Truck data showed that trucks represent 4% of peak hour traffic and 8% of the daily flows. This approximates 240 trucks during the peak hours and approximately 5,600 to 6,000 trucks over the course of the day. MS Transportation Systems, Inc. Page 10 I-91 Holyoke-West Springfield Road Safety Audit Data available as part of the MassHighway crash records system indicated that between 2004 and 2007, there were 36 reported crashes related to the median. Of the 36, 31 percent or 11 crashes were identified as cross-median crashes. The 11 cross-median crashes resulted in personal injuries or fatalities in 64% of the crashes. The one reported fatal crash occurred in the section south of Interchange No. 14. The total reported median related crashes were split evenly in the northbound and southbound direction. There were several areas of concentration related to the cross median crashes between south of Interchange No. 16 to Interchange No. 14. In most crashes, the cited cause for the cross-median crashes were either the driver “swerving” (22%) or failing to stay in proper lane (22%). Speed and other factors were also cited to a lesser degree. Weather related (27%) resulting in wet road surface were reported in the data. Figure 5 - Observed Directional Traffic Volumes on I-91 Of note, it is estimated that based on the reported crashes and estimated locations, the section of highway between about one mile north of Interchange No. 15 to Interchange No. 13, there were 8.8 median related crashes reported per year. Nine (9) of the eleven (11) cross median crashes appear to have occurred in this section. Conditions that were noted in the crash narratives for cross-median crashes varied. There were no predominant factors or causes for the crashes. Factors or contributing causes included were inattention, over correcting following a maneuver made possibly in error, swerving to avoid an obstruction as well as distraction due to cell phone use. There was also an illegal use of a turn around cited. MS Transportation Systems, Inc. Page 11 I-91 Holyoke-West Springfield Road Safety Audit SUMMARY OF RSA FINDINGS/POTENTIAL ACTIONS Based on the field review, the review of crash data and discussions among the RSA team members, the issues related to the safe operating conditions of the I-91 in the Holyoke – West Springfield area were identified. There were a number of factors or issues of concern that were identified as potentially having an effect on the risk and these are listed in Table 4 along with the assigned risk rating. TABLE 4 SUMMARY OF FACTORS THAT POTENTIALLY AFFECT THE RISK OF SAFETY RELATED EVENTS Factor or Issue Risk Rating Median is “open” from north of Interchange No. 13 (Route 5) to just south of Interchange No. 16 with 6:1 slopes or flatter and considered as easily crossable E Median open south of Interchange No. 18 (approx. 1.5 miles) D On and off-ramp merge areas at Int. No. 13 and between No. 14 and 15 – appear short E Faded pavement markings condition in various locations D Evidence of edge drop-off in areas C Delineation of median thru reflective posts or imbedded markers not evident D Sun glare in SB direction – south of Int. No. 18 in AM, NB direction near Int. No. 13 in PM B Higher than desirable travel speeds – particularly in section between No. 13 and 14 B Int. No. 16 and 17 SB merges are difficult with unnecessary lane changing C Motorists warning of upcoming high volume merges may be inadequate – this includes northbound lane drop at Exit 16 C Winter icing occurs particularly near Int. Nos. 17-18 B The most significant factor on the section of I-91 that was examined is the extent of the “open”, crossable median that has a width in the range of 60 feet. This is primarily in the areas of Interchange Nos. 13 to 14 and the section between Interchange 15 and 16. Closer to Interchange No. 13, the median becomes more narrow. Over the 4 years of data studied, the there was an annual average of more than eight (8) median entries and 2 to 3 cross-median crashes reported. Given the high I-91 volume, the number of cross median crashes and a median judged as easily crossable, the “open” median factor was MS Transportation Systems, Inc. Page 12 I-91 Holyoke-West Springfield Road Safety Audit assigned a high risk factor – ‘E’. The rating would be ‘F’ if all median entry crashes were taken into account rather than only cross-median crashes. In other words, the operational and physical characteristics of the highway sections under study are such that once a motorist makes a mistake or becomes “errant” and enters the median, there is a good chance that the motorist will cross the median and enter the opposing direction of flow. Further, the experience suggests a high probability that this type of event could occur. The “open” median is relatively narrow and flat in addition to being devoid of any obstruction (i.e. vegetation) that could prevent a crossing. The open median south of Interchange No. 18 was rated ‘D’ due to infrequent crash experience. There were other factors that would also contribute to motorists entering the median in error and possibly crossing the median. These include the level of guidance through pavement markings (faded) and flexible reflective delineators (not installed). The assigned risk rating for these factors was ‘D’. While the inside shoulder has a rumble strip, there was a noticeable edge drop off in areas which would potentially affect the ability of a motorist recovering and re-entering the travel way somewhat controlled. This factor was assigned a rating of ‘C’. There are a number of factors that were identified in relation to the interchanges and some of the merge zones. There was an indication that the merge or weave areas in terms of distance between Interchange Nos. 14 and 15 in both directions was less than desirable. There are 3 on-ramps within a relatively short distance (1.2 miles) between the two interchanges and like Interchange Nos. 14 to 15; the merge zones appear to be short and lacking clarity. There is high volume of weaving occurring or high mainline volumes that entering motorists must merge. This can result in “quick” lane-changing that could cause a chain of events in a short distance. The median width is approximately 60 feet wide in this area and “open. A risk rating of ‘E’ was assigned to this factor. Related to the southbound merge at interchange 16, the southernmost entrance ramp is where an additional southbound travel lane is provided. While this should result in a relatively smooth transition, observations by team members indicated that motorists entering the highway are changing lanes almost immediately in this zone creating conflicts with the high volume of southbound approaching mainline traffic. This factor was rated a ‘C’ in terms of risk. The northbound lane drop at the Exit 16 off-ramp was noted as a factor as the warning of the lane drop may not be adequate given the volume and speeds and if a motorist is MS Transportation Systems, Inc. Page 13 I-91 Holyoke-West Springfield Road Safety Audit “caught” in the right most (exit) lane, it can create a series of lane-changing events. A risk rating of ‘C’ was assigned for this factor. While updated data was not available, general observations by the team and regular observations by the State Police indicated that travel speeds are high and apparently well above posted speeds in the study section. The high speeds and lane-changing decisions by motorists have been identified as contributing causes of the median related crashes. A risk rating of ‘C’ was assigned to this factor. A sun glare issue was also noted along the study section by several RSA team members highly familiar with the study section. The most critical spots identified were south of Interchange No. 18 in the AM peak period and north of Interchange No. 13 during the PM peak hour. This was assigned a risk rating of ‘B’. The last factor listed in Table 4 was that the section of I-91 between Interchanges 17 and 18 was identified by the RSA team as icy during the winter. This area of the highway crosses over the Oxbow/Manhan River in several locations. While there was no concrete evidence in the available crash data that the crashes in this zone were due to the icy conditions, the factor was noted given the familiarity of the study section by team members. A risk rating of ‘B’ was assigned to this factor. Suggested actions were identified to address these factors intended to reduce the injuries and fatalities resulting from cross-median crashes and those related to other median entry crashes as well. Given that this RSA program is focused on cross-median crashes, the initial action reviewed was the potential installation of a median barrier. Later in the report a set of recommended actions to address each factor is presented. • Consideration of a Median Barrier One of the more significant actions to be considered is to install median barriers in the current “open” areas. A barrier can be considered when there is a higher than desirable chance or a greater risk for median cross-over crashes to occur and that have or could result in fatalities and/or a high proportion of injury related crashes. In addition, a barrier could be considered when the consequences or severity of a crash without a barrier are worse than if the barrier were in place. Factors that generally come into play in deciding on whether a median should be installed involve the following: MS Transportation Systems, Inc. Page 14 I-91 Holyoke-West Springfield Road Safety Audit High volumes and speeds Truck volumes and mix Narrow median History of cross-median crashes High risk of catastrophic event These items have been reviewed relative to the I-91 section under study. Figure 6 presents a review of the corridor in relation to the median warrant criteria presented in the AASHTO RDG4. As can be seen in the diagram, with the median (as measured from edge line to edge line) ranging from approximately 45 to 66 feet depending on location and a volume of over 73,000 vehicles on an average day, the intersection of the two items is in the area of the chart where a barrier can be “considered” to “optional”. In addition to the chart and related warrant criteria, which is a guideline, further consideration was given to the following: The high volume presents a likelihood of greater number of errant vehicles entering the median, A high proportion (31%) of cross-median crashes over the four (4) year period in the section between Interchange Nos. 13 and 16 and the median appears to be very crossable. Consequently, based on the analysis of the data, the field drive-thru and discussion of the conditions by the RSA team members, it was recommended by the RSA Team that a median barrier be installed in the sections of this route that are currently open and “crossable”. The selection of the barrier is discussed in the next section followed by the complete set of I-91 RSA recommendations. A. Barrier Selection There are a number of barrier types that can be considered in addressing the median cross-over crashes. These include the following: ♦ ♦ ♦ ♦ Weak post W-Beam Box Beam Generic Low Tension Cable High Tension Cable Barrier ♦ Strong post W-Beam ♦ Thrie Beam ♦ Concrete (Jersey) In deciding on the type of barrier, recommended guidelines in selection are included in Table 5 taken from the AASHTO Roadside Design Guide5. 4 5 American Association of State Highway and Transportation Officials, Roadside Design Guide, Washington, D.C., 2002, Chapter 6 Update 2006. American Association of State Highway and Transportation Officials, Roadside Design Guide, Washington, D.C., 2002, Chapter 6 Update 2006. MS Transportation Systems, Inc. Page 15 median width 45-55 feet 80 median width 60-66 feet AVERAGE DAILY TRAFFIC (thousands) 70 BARRIER RECOMMENDED 60 BARRIER CONSIDERED 50 40 BARRIER OPTIONAL 30 20 10 0 0 10 20 30 40 50 60 70 MEDIAN WIDTH (feet) Source: AASHTO Roadside Design Guide, Chapter 6, Update 2006 Median Barrier Warrant Analysis Interstate-91 Road Safety Audit Holyoke-West Springfield, Massachusetts MS Transportation Systems, Inc. NOT TO SCALE Framingham, Massachusetts Figure 6 I-91 Holyoke-West Springfield Road Safety Audit TABLE 5 CRITERIA FOR BARRIER SELECTION Criteria Comments 1. Performance Capability Barrier must be structurally able to contain and redirect design vehicle. Expected deflection of barrier should not exceed available deflection distance. Slope approaching the barrier and distance from traveled way may preclude use of some barrier types. 2. Deflection 3. Site Conditions 4. Compatibility 5. Cost 6. Maintenance A. Routine B. Collision C. Material Storage D. Simplicity 7. Aesthetics 8. Field Experience Barrier must be compatible with planned end anchor and capable of transitioning to other barrier systems (such as bridge railings). Standard barrier systems are relatively consistent in cost, but high-performance railings can cost significantly more. Few systems require a significant amount of routine maintenance. Generally, flexible or semi-rigid systems require significantly more maintenance after a collision than rigid or high-performance railings. The fewer different systems used, the fewer inventory items/storage space required. Simpler designs, besides costing less, are more likely to be reconstructed properly by field personnel. Occasionally, barrier aesthetics are an important consideration in selection. The performance and maintenance requirements of existing systems should be monitored to identify problems that could be lessened or eliminated by using a difference barrier type. Source: AASHTO, Roadside Design Guide, 2002, Chapter 5 Roadside Barriers. In general, the cable (flexible) barrier has its advantages from a cost and aesthetic perspective, over the various guardrail systems or concrete barrier. The median slope and/or recovery area also affects the use and placement of any barrier including guardrail. The alternative types of guardrail were reviewed for potential application on this route. Considerations included the volume of traffic, relative amount of truck traffic and travel speeds. Based on these, the most applicable types of guardrail for this route include the W-beam with strong post or the strong post thrie-beam. These rails are appropriate for high speed highways and high volumes with a relatively high proportion of truck traffic. Costs for each are similar. The weak post W-beam and box beam can be eliminated due to the slope and type of highway. The concrete barrier would generally be applicable in urban sections with limited median widths available. As a result, the MS Transportation Systems, Inc. Page 17 I-91 Holyoke-West Springfield Road Safety Audit median barrier options that are valid for consideration for I-91 in this section are the cable barrier and strong post guard rail. Maintenance issues are also an important consideration in decisions regarding median barrier installations. The maintenance issues that are of concern include: Barrier hits per mile Frequency of hits Cost recovery Cable downtime Repair effect on traffic Maintaining tension with cable system Mowing median Final selection of the barrier type should be based on the costs, the ability to maintain a recovery zone, likely maintenance or repair requirements, and compatibility with future planned widening. The key points of the cable barrier or guardrail are summarized below. Cable Barrier While the low tension generic cable system has been in existence for more than 50 years, most of the recent cable system research and installation is focused on the high tension systems. There are currently six (6) manufacturers with systems approved by the Federal Highway Administration (FHWA) for use under certain conditions. There are 3-rope or 4-rope cable systems as shown in the following two photographs. This barrier can be installed on slopes of 6:1 or flatter with little constraint on placement. There are certain systems (Brifen and Gibraltor 4 rope) that have been approved for slopes as steep as 4:1. The placement of the barrier on the steeper slope is somewhat more restrictive. 3 Cable CASS System on Route 213 MS Transportation Systems, Inc. 4 – Rope Brifen System on I-495 Page 18 I-91 Holyoke-West Springfield Road Safety Audit Guardrail The guardrail could be placed in the median where slopes are 10:1 or flatter as well as at the edge of a steep slope or where minimal recovery zones exist. With the guardrail placed within several feet of the pavement edge, a clear zone (or recovery area) would be eliminated at least on one side of the median if guardrail is applied on only one side of the median. It may also be possible to install a single line of double faced barrier either a greater distance from the pavement edge or along one side in this specific project area. This would result in some level of recovery zone maintained in one or both directions. Per mile costs of the basic types of median barrier treatment to be considered for this route are summarized in Table 6. Shown in the table are estimated per mile costs of installing a cable barrier, a double faced W-beam guardrail and a double faced thriebeam guardrail. As can be seen, the cable barrier is expected to be the lower cost option. It should be noted that the estimated costs for the cable barrier are largely based on recent limited applications in the Commonwealth. Construction costs for cable installation could be substantially lower based on experience in other parts of the country. The W-beam rail is a lower cost option compared to the thrie-beam, however, there is slightly greater deflection with the W-beam. TABLE 6 COMPARISON PER MILE COSTS Cable vs. Guardrail Costs/Mile Cable W-beam Thrie beam $144,000 $171,000 $213,000 In total, there is approximately a total of three (3) miles of median candidate for barriers. Costs to implement cable barrier could be approximately $432,000. Using a thrie-beam rail would cost approximately $639,000. MS Transportation Systems, Inc. Page 19 I-91 Holyoke-West Springfield Road Safety Audit Recommendations As a result of the RSA analysis and team input, a set of recommendations have been identified and are summarized in Table 7. These actions are intended to eliminate the chance of cross-median crashes as well as reduce the severity of all crashes and improve the overall safety condition of this section of I-91 in Holyoke – West Springfield. Identified in the table in addition to the risk factor and recommended action are the estimated costs and potential timeframe (i.e. short (0-1 year), medium (1-3 years) and long (>3 years)). The section of I-91 evaluated in this RSA was noted to have significantly long sections of open, relatively narrow, flat and crossable medians. The total length in the 15 mile section (Interchanges 13 to 18) that was in this category was 4.5 miles including south of Interchange No. 16 where there is an estimated three (3) miles of open median. Given the high volume, high proportion of cross-median events and risk factor, it is recommended that a median barrier be installed in these areas. Figures 7 and 8 identify the approximate proposed barrier locations in this specific section. The guardrail in place around bridge columns would remain in place. Turnaround areas for authorized vehicles would also remain but possibly be enhanced for safer use. Due to the width of the median and taking into account costs, aesthetics, deflection and clear zone factors and demonstrated benefits, it is recommended that cable barrier be used for this project. A preliminary total cost is estimated to be $432,000 for the section between Interchanges No. 13 and 16. For the open median area south of Interchange No. 18 (approx 1.5 miles in length), it is also recommended that a barrier be installed although this section was assigned a lower rating. Recent crash frequency in this area is low. Estimated cost for cable barrier in this area is $216,000. As there were a group of factors identified that relate to motorist guidance, recommendations include improving the markings at the acceleration lanes – merge areas, installing flexible reflective delineator posts along the median and adding signage. The delineator posts are a low cost, short term action that could later supplement the barrier treatment. While reflectors can be part of the barrier system, it would not be effective if the barrier is placed near the center of the median. The major signs recommended include a mix of overhead and large roadside signs. Overhead signs indicating critical merge areas and the northbound lane drop at Exit 16 are suggested. Large roadside signs for STAY IN LANE at the Exit 16 southbound onramp are recommended. Figure 9 illustrates potential legends while Figure 10 presents approximate locations of the signs. MS Transportation Systems, Inc. Page 20 I-91 Holyoke-West Springfield Road Safety Audit TABLE 7 SUMMARY OF RECOMMENDATIONS Risk Factor Risk Rating Recommended Action Estimated Cost Median is “open” from north of Interchange No. 13 (Route 5) to just south of Interchange No. 16 with 6:1 slopes or flatter and considered as easily crossable E Median open south of Interchange No. 18 (approx. 1.5 miles) D Install cable barrier On and off-ramp merge areas at Int. No. 13 and between Nos. 14 and 15 – appear short E Widen shoulder if feasible (or necessary) Extend lanes via markings Faded pavement markings condition in several locations D Install new markings Increase markings maintenance applications Evidence of edge drop-off in areas C Estimated Timeframe Install cable barrier between Int. Nos. 13 and 14, Int. Nos. 15 and 16 – total length approx. 3 miles $432,000 $216,000 short term to medium term $TBD $3,000 long term short term TBD TBD short term medium term Add fill and smooth grade near edge Add angled safety edge TBD (expect low) Est. 1-2% of overall resurface project short term short to medium term long term Delineation of median is nonexistent or less than desirable D Add delinators – approx. 158,000 linear feet $24,000 short term Sun glare in SB direction – south of Int. No. 18 in AM, NB direction near Int. No. 13 in PM B Install SUN GLARE warning signs (3) $7,500 short term Higher than desirable travel speeds – particularly in section between Nos. 13 and 14 C Increase enforcement of speed limits and unsafe motorists behavior TBD short term Int. Nos. 16 and 17 SB merges are difficult with unnecessary lane changing C Install overhead warning signs Improve markings at interchanges $25,000 short term TBD long term Motorists warning of upcoming high volume merges may be inadequate – this also includes NB lane drop near Int. 16 C Install overhead warning signs at key locations (3) Install overhead lane drop sign $60,000 short term $20,000 short term Winter icing occurs particularly near Int. Nos. 17 and 18 B increase winter treatment in this area TBD short term MS Transportation Systems, Inc. Page 21 I-90 MASS TURNPIKE Proposed Cable Barrier - 0.8 Miles BRUSH HILL ROAD I-91 Between Brush Hill Road Overpass and Turnpike BRUSH HILL ROAD Proposed Cable Barrier - 0.5 Miles INTERCHANGE NO. 13 I-91 Between Int. No. 13 and Brush Hill Road Overpass CONCEPTUAL ONLY NOT TO SCALE Proposed Cable Barrier Proposed Location for Cable Median Barrier I-91 Road Safety Audit Holyoke-West Springfield, Massachusetts MS Transportation Systems, Inc. Framingham, Massachusetts Figure 7 Proposed Cable Barrier - 1,900 Feet HOLYOKE MALL I-91 Between Interchange Nos. 14 and 15 INTERCHANGE NO. 16 Proposed Cable Barrier - 1.3 Miles INTERCHANGE NO. 15 I-91 Between Interchange Nos. 15 and 16 CONCEPTUAL ONLY NOT TO SCALE Proposed Cable Barrier Proposed Location for Cable Median Barrier I-91 Road Safety Audit Holyoke-West Springfield, Massachusetts MS Transportation Systems, Inc. Framingham, Massachusetts Figure 8 CHERRY STREET ROUTE 202 STAY IN LANE 1 MILE EXIT ONLY SIGN C - I-91 SB at Interchange No. 16 on-ramp SIGN A - I-91 NB at Interchange No. 16 CAUTION SUN GLARE EARLY AM CAUTION MERGING TRAFFIC AHEAD (Alt. - LATE AFTERNOON) Note: Use of sign SB sourth of Int. No. 18 and NB north of Int. No. 13 SIGN B - see Figure 10 for proposed locations Note: See Figure 10 for approximate placem ent CONCEPTUAL ONLY NOT TO SCALE Potential Sign Legends I-91 Road Safety Audit Holyoke-West Springfield, Massachusetts MS Transportation Systems, Inc. Framingham, Massachusetts Figure 9 B 91 Approach to I-91 SB on-ramp from Route 141 (Interchange No. 17) B 91 At I-91 SB on-ramp from Cherry Street - Route 202 (Interchange No. 16) C I-91 NB approaching Exit 16 91 A CONCEPTUAL ONLY A - Proposed Sign Location Note: See Figure 9 for legends Proposed Location for Signs I-91 Road Safety Audit Holyoke-West Springfield, Massachusetts MS Transportation Systems, Inc. Framingham, Massachusetts Figure 10 I-91 Holyoke-West Springfield Road Safety Audit In addition to the above, SUN GLARE signs were recommended to be installed in southbound direction south of Interchange No. 18 and on the northbound direction north of Interchange No. 13. Improving the markings at the acceleration lanes also include lengthening the lanes as well. It is hoped that lengthening can be accomplished through adjusting the markings rather than needing to also widen the shoulders. This detail would need to be examined in more engineering detail. Examples of improved deceleration lane markings are shown in Figure 11. The use of dotted extension lines is suggested. The current MUTCD illustrates their use for deceleration lanes and weave sections. The updated MUTCD to be released in 2009 is expected to also show dotted extension lines for acceleration lanes as an option. In addition to the markings at the acceleration lanes, overall maintenance of all markings is needed. It is further suggested that the schedule for regular maintenance of pavement markings be reviewed and adjusted (if appropriate) with the goal of maintaining a consistently high level of visibility. It was noted that there was some edge drop-off on the median. This can affect the recovery of an errant motorist. It is recommended in the short term that these areas be filled and smothered to match the pavement surface grade. In the long term, the angled safety edge treatment should be considered when the highway is scheduled for resurfacing. The recurring issue of high travel speeds and driver behavior (i.e. lane changing decisions) requires an emphasis and increase of enforcement. In general and not included in Table 7 is the overall need to provide a variety of information to motorists along the route. This could include advance notice of crash occurrence or significant congestion as well as educational reminders pertaining to driver behavior issues. This type of sign program is an important element in the overall plan to reduce crashes, improve safety and improving driver behavior. This issue and need should be kept in mind as the ITS traffic monitoring and variable message sign (VMS) plan for I-91 is advanced in the project area. Depending on the overall ITS plan for I-91, message boards may be able to provide motorists additional warning of icy roads during the winter – possibly flashing advisory speeds. In addition, the area between Interchange No. 17 and 18 may be particularly vulnerable to this condition due to the mountain range bordering the highway on the west and the river crossings in this stretch of highway. The effects of these factors may result in lower road temperatures and less afternoon sun during the winter. MS Transportation Systems, Inc. Page 26 a-Parallel deceleration lane b-Tapered deceleration lane Neutral area Optional chevron markings Channelizing lines Theoretical gore point Channelizing lines Broken lane markings for one-half of full-width deceleration lane Optional dotted extension of lane line Legend Direction of travel Source: Based on MUTCD Figure 3B-8 Note: Conceptual illustration only Potential Pavement Markings Off-Ramp Diverge Locations I-91 Road Safety Audit Holyoke-West Springfield, Massachusetts MS Transportation Systems, Inc. NOT TO SCALE Framingham, Massachusetts FIGURE 11 I-91 Holyoke-West Springfield Road Safety Audit Appendix • • • • • MS Transportation Systems, Inc. RSA Meeting Agenda RSA Attendees List Median Crash Diagram Crash Data Traffic Volume Data Page 28 Road Safety Audit W. Springfield/Holyoke – I-91 Meeting Location: MassHighway District 2 Office 811 North King Street, Northampton Wednesday, June 18, 2008 1:15 PM – 2:45 PM Type of meeting: Cross Median – Road Safety Audit Attendees: Invited Participants to Comprise a Multidisciplinary Team Please bring: Thoughts and Enthusiasm!! 1:15 PM Welcome and Introductions 1:30 PM Introduction to Road Safety Audits and Cross Median Crashes 1:45 PM Review of Site Specific Material • Crash & Volume Summaries– provided in advance • Existing Geometries and Conditions • Video and Images 2:15 PM Completion of RSA • Identification of Safety Concerns – using RSA Prompt List as a guide • Identification of Possible Countermeasures 2:45 PM Adjourn for the day – but the RSA has not ended Instructions for Participants: • Before attending the RSA on June 18th participants are encouraged to drive Interstate 91 in West Springfield and Holyoke from Interchange 13 to Interchange 18 and complete/consider elements on the RSA Prompt List with a focus on safety factors affecting cross median crashes. • All participants will be actively involved in the process throughout. Participants are encouraged to come with thoughts and ideas, but are reminded that the synergy that develops and respect for others’ opinions are key elements to the success of the overall RSA process. • After the initial RSA meeting, participants will be asked to comment and respond to the document materials to assure it is reflective of the RSA completed by the multidisciplinary team. ROAD SAFETY AUDIT MEETING I-91 Holyoke-West Springfield - June 18, 2008 MassHighway District 2 Offices, Northampton MA Attendance List Name Agency/Dept. Email Bill Scully MS Transportation Systems, Inc. bscullyjr@mac.com Lisa Schletzbaum MassHighway - Safety lisa.schletzbaum@mhd.state.ma.us Khyati Parmar PVPC kparmar@pvpc.org Kathryn Cook MassHighway kathryn.cook@mhd.state.ma.us Robert Fay MassHighway robert.fay@mhd.state.ma.us Samuel Gregorio MHD - District 2 Traffic samuel.gregorio@state.ma.us Gary roux PVPC gmroux@pvpc.org Lt. Steven Hughes State Police/Springfield 413-736-8390 Lt. Lawrence Ashman JP Northampton/B-6 lawrence.ashman@pol.state.ma.us Xian Chen MassHighway xian.chen@state.ma.us John Conoghue MassHighway john.donoghue@mhd.state.ma.us Ken Wanar MassHighway - District 2 ken.wanar@mhd.state.ma.us Lyris Liautaud MassHighway lyris.liautaud@mhd.state.ma.us Hal Piligian MassHighway harold.piligian@mhd.state.ma.us Trung Vo MassHighway trung.vo@state.ma.us William goulet MassHighway Bao Lang MassHighway MS Transportation Systems, Inc. bao.lang@mhd.state.ma.us ± Interstate 91 Median Crashes TREE T PLAIN S 1 EASTHAMPTON NORTHAMPTON ST RE ET E JAR VIS AVE NU TA IN MO UN SS RO U SO TH AM N O PT AD RO RO AD 91 RD ST REET SOUTH HADLEY ET PLEASANT STRE LINE ST R EET 2 § ¦ ¨ SOUTHAMPTON E BRAIN " ) 17 CA NA L ST R M EE T AI N ST RE ET R AD O COUNT Y HOLYOKE " ) 3 16 T BO CA T STREE SOUTH ST ROAD ET RE 4 5 SIM ARD 6 EE T ST R DALE S TREE T ME AD O W TR E ET MAI NS UNTA IN R O AD 15 Crash IDs between 12-21 Type of Median Crash 2004-2007 * T EE " ) R ST Legend DRI VE RY ME GO 11 " ) RO AD EAST MO Cross Median, Fatal Crash Cross Median, Non-Fatal Crash WESTFIELD Crash IDs between 22-31 § ¦ ¨ 90 GR AN B Major Roads Y 14 Median, Non-Fatal Crash Interstate 32 PROSPECT AVENU E Principal Arterial 33 Minor Arterial 34 Collector Municipal Boundary R OAD 0.4 0.8 1.2 Miles 1.6 FAIRVIEW AVEN UE NUE L AVE H HIL S U R B R PE PI OKE HO LYfile OLDcrash * 2007 has not yet been closed. 0 CHICOPEE WEST SPRINGFIELD Local " ) 13 35 AD RO 36 S NT MO 7 8 9 10 CT PE S O PR NE WB UR YS TR EE T MASSACHUSETTS HIGHWAY SAFETY DIVISION CRASH SUMMARY I-91 ROADWAY: NO. CITY: 1/1/2004 STUDY PERIOD: CRASH NUMBER CRASH DATE TO 12/31/2007 TRAVEL LIGHT WEATHER ROAD REASON FOR DIRECTION CONDITION CONDITION SURFACE RUNNING OFF ROAD LEFT WEST SPRINGFIELD AND HOLYOKE LOCATION: EXIT 14 - EXIT 15 VEHICLE MEDIAN OR CROSS DRIVER CONTRIBUTING CRASH MOVEMENT MEDIAN CRASHES CAUSE SEVERITY 1 2160797 1/14/2007 NB Dark - Not Lighted Cloudy Dry Driver was talking on his cell phone, hit the rumble strip and lost control N/B Travel Lanes to S/B Travel Lanes to Right Side Wooded Area Cross Median Cellular Telephone Property Damage Only 2 1852511 2/27/2005 NB Daylight Cloudy Dry Driver attention diverted to passenger, swerved to median, sideswiped another vehicle, crossed the median and was hit by another vehicle S/B Travel Lane to Median to S/B Travel Lane to N/B Travel Lane Cross Median Inattention Non-Fatal Injury 3 2160956 2/14/2007 SB Daylight Sleet, Hail, Freezing Rain Snow Lost control of vehicle on snow covered roadway, hit the guardrail and was struck by another vehicle in the rear Travel Lane to Median Guardrail to Travel Lane Median Swerving due to slippery surface in roadway Property Damage Only 4 2115812 8/21/2006 NB Dawn Clear Dry Unknown vehicle ran off another vehicle from the roadway Travel Lane to Median Guardrail to Median Median Operating vehicle in reckless manner Property Damage Only 5 1915556 1/8/2005 NB Daylight Sleet, Hail, Freezing Rain Snow Vehicle skidded on snowy surface and overturned Travel Lane to Median Median Swerving due to slippery surface in roadway Property Damage Only 6 2010903 6/8/2005 SB Daylight Clear Dry Vehicle changed lanes to an already occupied lane and strike the left rear panel of another vehicle Travel Lane to Median Guardrail Median Failure to keep in proper lane Property Damage Only 7 2259840 11/12/2007 SB Dark - Lighted Clear Dry Vehicle right front tire went flat, lost control and hit the guardrail Travel Lane to Median Guardrail to Travel Lane to Median Guardrail to Travel Lane to Median Guardrail to Right Breakdown Lane Median No Improper Diving Property Damage Only 8 2131996 11/22/2006 SB Daylight Clear Dry Vehicle tried to elude police, attempted to pass in the breakdown lane, lost control and hit the right rear corner of an another vehicle Travel Lane to Right Breakdown Lane to Median to Raised Manhole Cover Median Exceeded Speed Limit Non-Fatal Injury 9 2115847 9/24/2006 SB Dark - Unknown Lighting Clear Dry Lost control of vehicle and overturned S/B Travel Lane to N/B Travel Lane Cross Median Exceeded Speed Limit and Alcohol Non-Fatal Injury 10 2208559 5/10/2007 NB Dark - Lighted Clear Dry Vehicle weaved in and out of traffic, struck a vehicle in the rear and overturned Travel Lane to Median Median Exceeded Speed Limit Non-Fatal Injury 11 2055742 5/30/2006 SB Daylight Clear Dry Lost control of vehicle and veered sharply into median S/B Travel Lane to N/B Breakdown Lane to Trees in the Right Cross Median Failure to keep in proper lane Property Damage Only 12 2165801 2/14/2007 SB Dawn Snow Snow Lost control of vehicle on snow covered roadway Travel Lane to Median Guardrail to the top of the Off-ramp Median Swerving due to slippery surface in roadway Property Damage Only 13 2054702 5/2/2006 NB Dusk Cloudy Wet Vehicle made a sharp quick turn, lost control and collided with two vehicles N/B Travel Lane to S/B Right Breakdown Lane Cross Median Failure to keep in proper lane Non-Fatal Injury 14 2187929 4/18/2007 SB Daylight Clear Dry Vehicle made a lane change and sideswiped another vehicle Travel Lane to Median Median Failure to keep in proper lane Property Damage Only 15 2096284 7/7/2006 NB Daylight Clear Dry Vehicle tried to merge into traffic from on-ramp, crossed median, attempted to return to N/B, struck a drainage cover and vehicle caught on fire N/B Travel Lane to N/B Right Guardrail to S/B Travel Lane to Middle Median Cross Median Failure to keep in proper lane Property Damage Only 16 2242062 8/29/2007 NB Daylight Clear Dry Vehicle front end started to shake and hit guardrail Travel Lane to Median Guardrail Median No Improper Diving Property Damage Only 17 2208583 6/8/2007 SB Dark - Unknown Lighting Clear Dry Vehicle entered a highway from the ramp and rear ended another vehicle S/B On-Ramp to Travel Lane to Median Median Failure to keep in proper lane and Alcohol Non-Fatal Injury 18 2134320 11/17/2006 NB Dark - Lighted Rain Wet Driver saw another vehicle to skid, applied brakes and hydroplaned on wet surface roadway Travel Lane to Median Guardrail Median Swerving due to slippery surface in roadway Non-Fatal Injury 19 1851294 2/15/2005 NB Dark - Lighted Rain Wet Lost control of vehicle on wet roadway Travel Lane to Median Median Swerving due to slippery surface in roadway Non-Fatal Injury 20 1796620 1/8/2005 NB Daylight Sleet, Hail, Freezing Rain Snow Vehicle skidded on snowy surface and overturned Travel Lane to Median Median Swerving due to slippery surface in roadway Property Damage Only 21 2132013 11/30/2006 NB Daylight Cloudy Dry Vehicle rear ended another vehicle and hit the guardrail Travel Lane to Median Guardrail Median Followed Too Closely Property Damage Only 22 2055649* 4/12/2006 NB Daylight Cloudy Dry Driver made an illegal u-turn, didn't yield to upcoming traffic and collided with another vehicle in the rear N/B Travel Lane to S/B Travel Lane Cross Median Failed to yield right of way Property Damage Only 23 1836162 1/11/2005 SB Dark - Lighted Snow Snow Vehicle skidded on snow covered surface, fishtailed and overturned Travel Lane to Median Median Swerving due to slippery surface in roadway Non-Fatal Injury 24 2018401 1/17/2006 SB Daylight Clear Dry Driver blacked out and overturned S/B Travel Lane to N/B Travel Lane Cross Median Illness Non-Fatal Injury 25 2259001 10/22/2007 SB Daylight Clear Dry Vehicle swerved to avoid a ladder, overturned, crossed the median and hit another vehicle S/B Travel Lane to N/B Travel Lane Cross Median Swerving or avoiding due to object in roadway Non-Fatal Injury 26 2010174 7/9/2005 SB Daylight Clear Dry Vehicle rear ended another vehicle while attempting to pass it S/B Travel Lane to N/B Right Breakdown Lane Cross Median Failure to keep in proper lane Non-Fatal Injury 27 2011211 11/17/2005 SB Dark - Not Lighted Clear Dry Driver attempted to change his radio and lost control of the vehicle Travel Lane to Right Guardrail to Median Guardrail Median Inattention Property Damage Only 28 2010505 12/17/2005 NB Daylight Clear Dry Vehicle was cut-off by unknown vehicle Travel Lane to Median Barrier Median Swerving or avoiding due to vehicle in roadway Property Damage Only 29 2189688 4/6/2007 NB Daylight Clear Dry Vehicle weaved in and out of traffic, lost control and skidded into the median N/B On-Ramp to Travel Lane to Median Guardrail to Travel Lane Median Failure to keep in proper lane Property Damage Only 30 2226166 8/4/2007 NB Dark - Not Lighted Clear Dry Vehicle crossed into the lane, struck another vehicle and caused the vehicle to hit the guardrail Travel Lane to Median Guardrail to Travel Lane Median Failure to keep in proper lane Non-Fatal Injury 31 2018060 1/15/2006 SB Dark - Lighted Sleet, Hail, Freezing Rain Snow Vehicle skidded on snowy surface Travel Lane to Median Embankment Median Swerving due to slippery surface in roadway Property Damage Only 32 2118259 10/22/2006 NB Dark - Not Lighted Clear Dry Driver took his eyes off the road, drifted to the left and overcorrected Travel Lane to Median to State Highway Sign Median Over-correcting/Over-steering Property Damage Only 33 2258396 11/20/2007 NB Daylight Snow Snow Vehicle lost traction due to other crashes happening front of him, spin out and hit the guardrail Travel Lane to Median Guardrail to Right Breakdown Lane Median Swerving or avoiding due to vehicle in roadway Property Damage Only 34 2071516 7/20/2006 SB Daylight Cloudy Dry Unknown vehicle made an abrupt lane change, caused another vehicle to brake and hit the guardrail Travel Lane to Median Guardrail to Travel Lane Median Swerving or avoiding due to vehicle in roadway Non-Fatal Injury 35 2069728 8/1/2006 SB Dark - Lighted Clear Dry Vehicle tried to change lanes and struck another vehicle Travel Lane to Right Side Construction Barrel to Travel Lane to Median Median Inattention Property Damage Only 36 2223930 8/1/2007 SB Daylight Clear Dry Driver steered aggressively to avoid slower moving vehicles, lost control, crossed the median and crashed head-on into another vehicle N/B Travel Lane to S/B Travel Lane Cross Median Exceeded Speed Limit Fatal Injury DAYLIGHT DAWN DUSK DARK - LIGHTED DARK - NOT LIGHTED DARK - UNKNOWN LIGHTING CLEAR CLOUDY RAIN 36 20 2 1 7 4 2 21 6 2 3 100% 56% 6% 3% 19% 11% 6% 58% 17% 6% 8% LIGHT CONDITION WEATHER CONDITION TOTAL NO. ROAD SURFACE WEATHER CONDITION MEDIAN OR CROSS MEDIAN SLEET, HAIL CRASH SEVERITY DRIVER CONTRIBUTING CAUSE PROPERTY DAMAGE DRY WET SNOW MEDIAN CROSS MEDIAN FREEZING RAIN NON-FATAL INJURY SNOW FATAL - INJURY ONLY NO IMPROPER EXCEEDED SPEED LIMIT DRIVING 4 26 3 7 25 11 21 14 1 2 3 11% 72% 8% 19% 69% 31% 58% 39% 3% 6% 8% FAILURE TO KEEP IN OPERATING VEHICLE SWERVING DUE TO SLIPPERY DRIVER CONTRIBUTING CAUSE EXCEEDED SPEED LIMIT FAILED TO YIELD AND ALCOHOL RIGHT OF WAY FOLLOWED TOO FAILURE TO KEEP CLOSELY IN PROPER LANE PROPER LANE & ALCOHOL IN RECKLESS MANNER SWERVING OR AVOIDING DUE TO VEHICLE IN ROADWAY SWERVING OR AVOIDING DUE TO OBJECT IN ROADWAY SURFACE IN ROADWAY OVER-CORRECTING/ ILLNESS OVER-STEERING 1 1 1 8 1 1 8 3 1 1 1 3% 3% 3% 22% 3% 3% 22% 8% 3% 3% 3% DRIVER CONTRIBUTING CAUSE INATTENTION CELLULAR TELEPHONE 3 1 8% 3% * Driver intended to reverse driving direction 2007 CRASH INFORMATION ARE NOT COMPLETE CRASH SUMMARY IS BASED ON CRASH REPORTS WITH STATE POLICE NARRATIVES I-91, South of Lower Westfield Road 10/17/2006 Northbound Southbound Direction Direction TOTAL Start time 12:00 AM 316 252 568 1:00 AM 197 166 363 2:00 AM 175 166 341 3:00 AM 176 205 381 4:00 AM 287 348 635 5:00 AM 652 796 1,448 6:00 AM 1,457 1,931 3,388 7:00 AM 2,512 2,895 5,407 8:00 AM 2,427 2,820 5,247 9:00 AM 2,101 1,915 4,016 10:00 AM 2,053 1,830 3,883 11:00 AM 2,006 1,866 3,872 12:00 PM 2,105 1,990 4,095 1:00 PM 2,100 2,150 4,250 2:00 PM 2,370 2,374 4,744 3:00 PM 2,720 2,593 5,313 4:00 PM 3,142 2,673 5,815 5:00 PM 3,403 2,489 5,892 6:00 PM 2,322 1,884 4,206 7:00 PM 1,616 1,240 2,856 8:00 PM 1,265 1,133 2,398 9:00 PM 1,073 1,126 2,199 10:00 PM 787 707 1,494 11:00 PM 565 516 1,081 Daily Total 37,827 36,065 73,892 Directional Traffic Volumes along I-91, South of Lower Westfield Road, Holyoke Tuesday, October, 17, 2006 Northbound Direction Southbound Direction 3,500 3,000 2,500 2,000 1,500 1,000 500 Time of Day PM PM 10 :0 0 8: 00 PM 6: 00 PM 4: 00 PM PM 2: 00 AM 12 :0 0 AM AM 10 :0 0 8: 00 6: 00 AM 4: 00 AM 2: 00 AM 0 12 :0 0 Hourly Volume (Number of Vehicles) 4,000