Daniel A Grabauskas Commiss~nBr Secretary {If . / J31 ft1t ' j} r(: j;rr?'Y tf /Jf /~ To: Secretary Daniel A. Grabauskas, EOT Through: Commissioner John Cogliano, MHO From: Stephen H. Clark, Administrative Law Judge Date: March 24, 2005 Re: Report and Recommendation / V· P I~-fr J!I V ~ ' I (\l ~ Y ,,~ I am pleased to submit for your consideration and approval the attached report and recommendation. McCourt, a general contractor under MIlD contract #95284 engaged to construct City Square Park and associated roadways in Charlestown, appealed the Department's refusal to pay it 529,280.00 for the furnishing and instaUation of a granite seat waD in ODe part of the park. The appeal has merit and should be aUowed. The plan details ofthe contract establish that the cODtract intended that payment for the disputed section of granite seat wall should have been paid under Item 719.12 ("Granite Seat Wall"), as McCourt contends. The Department was not entitled to rely on what the project designer subjectively intended when it drew up the plan details. Accordingly, I recommend that the Department pay McCourt for 97.6LF of granite seat wan instaned at the bid price of S300ILF, or 529,280.00. Massachusetts Highway Department· Ten Park PIIlZiJ, Boston, MA 02116·3973' (617) 973-7800 I) INTRODUCTION McCourt Construction Company, Inc. (McCourt) seeks payment of $29,280.00 under Massachusetts Highway Department (Department) contract #95284 (Contract) for work of supplying, fabricating and installing 97.6 linear feet of curvilinear granite wall functioning as a bench (“Granite Seat Wall”) at City Square Park in Charlestown. A 97.6 linear foot portion of the Granite Seat Wall, which faces inward toward a fountain in the center of the park, abuts a granite and concrete retaining wall, thus forming a double wall (“Granite Double Wall”). McCourt appeals from the Department’s refusal to pay it the bid price of $300/ LF for the 97.6 LF of installed Granite Seat Wall under payment item 719.12 (“Granite Seat Wall”). The Department’s refusal was based on its contention that payment for constructing the Granite Seat Wall where it abutted a 97.6 linear foot section of a Granite Double Wall should be paid for under payment item 719.11 (“Granite Double Wall”). McCourt’s appeal has merit. The Contract plans and specifications, construed as a whole, support McCourt. The Contract’s plans and plan details, upon inspection, show plainly that the Granite Seat Wall should have been paid under item 719.12 (“Granite Seat Wall”). That structure is not included under pay item 719.11 (“Granite Double Wall”) because the plan detail for the Granite Double Wall expressly incorporates by reference the plan detail for Granite Seat Wall to be built in accordance with a separate plan detail. Because the Contract’s special provisions contain a payment item for that plan detail work—Item 719.12 (“Granite Seat Wall”)—McCourt correctly understood that the Contract intended all such work was to be paid under the same payment item. I conclude that the work of constructing 97.6 LF of Freestanding Granite Seat Wall along the Granite Double Wall should be paid under item 719.12 (“Granite Seat Wall”) at the bid price of $300/foot. I recommend that the Department pay McCourt $29,280.00 ($300 X 97.6). BACKGROUND Statement of the Appeal McCourt filed an appeal to the Board of Contract Appeals (Board) on April 28, 2003 following denial by the Department of its claim for compensation under pay item 719.12 for 97.6 LF of Granite Seat Wall. The Contract is governed by the Standard Specifications for Highways and Bridges (1988 ed) (Standard Specifications), as well as the Department’s 1977 Construction Standards. A hearing was held on February 5, 2004 before Acting Chief Administrative Law Judge John McDonnell. Present were John McDonnell Isaac Machado, Esq. Stephen Frick Acting Chief Administrative Law Judge Deputy Chief Counsel, MHD McCourt Construction, Project Manager The following documents were admitted into evidence. Ex. #1 Ex.#2 Ex. #3 McCourt Statement of Claim Contract #95284 McCourt correspondence file1 1 The file consists of (1) June 20, 1995 letter of McCourt to MHD; (2) July 5, 1995 letter reply of designer Halvorson Company to McCourt’s June 20th letter; (3) July 13, 1995 letter of DEM to Department project coordinator enclosing Halvorson letter; (4) July 26, 1995 letter of MHD to McCourt refusing to agree with McCourt’s proposed interpretation set forth in June 20th letter; (5) July 27, 1995 letter of McCourt asserting claim under Subsection 7.16 of the Contract; (6) payment items 719.01 through 719.19 on page 87 of the special provisions of the Contract and details on Contract plan sheet 5; (7) January 27, 1997 letter from McCourt to Department filing claim under item 7.16; (8) December 4, 1997 letter from Department to McCourt denying claim; (9) January 21, 1998 letter of the Engineer to McCourt setting forth position of claims committee denying McCourt’s claim. 2 The matter was taken under advisement at the end of the hearing. On March 1, 2004 the undersigned was appointed Chief Administrative Law Judge. On July 21, 2004, through St. 2004, c. 196, s. 5 (Act), the Legislature abolished the Board and, so far as is pertinent here, conferred its prior functions on the Secretary of Transportation and the Commissioner of the Department (Commissioner). See G.L. c.16, s. 1(b), as appearing in the Act. This report and recommendation, decided with the participation of Mr. McDonnell, is made through the Commissioner to the Secretary. Findings of Fact The record discloses the following facts, which I recommend be adopted. The Contract required McCourt to construct a new park and associated roadways at historic City Square in Charlestown. The Department awarded McCourt a Contract for $1,984,713.00 for the project. The project was completed at a final cost of $2,350,923.43, as shown on the Final Estimate dated February 19, 2003. The project was substantially completed on September 30, 1997. (1) The Contract Department Contract #95284 was for the work of constructing City Square Park, including earthwork, drainage, granite wall installation, paving, fencing, a fountain, artwork, landscaping and related work. The specifications called for bidders experienced in custom granite fabrication and installation, as well as the installation a fountain and site-specific artwork. The Department supervised the creation of the roadway design for the project; the Department of Environmental Management (DEM)2 created the specifications and plans for the new park through its 2 DEM was consolidated with the Metropolitan District Commission in 2003 becoming the Department of Conservation and Recreation (DCR) through St. 2003, c.26, s.63, amending G.L. c. 21, s. 1. 3 consultant, the landscape architect firm of The Halvorson Company (Halvorson). The Department put the Contract out to bid and managed the construction. (2) Location of The Granite Seat Wall The resolution of this appeal requires an understanding of the locations where the Granite Seat Wall was constructed in the new park. The general layout of the area of the park at issue is seen on the plan attached at Exhibit A.3 Generally, that plan shows an elliptical paved area (Ellipse) surrounded by two structures, one colored blue and one yellow. The colored structures are the Granite Seat Wall (yellow) and the Granite Double Wall (blue). Pedestrians may enter the Ellipse on four walkways that cut through those two granite structures. There is a granite fountain at the center of the Ellipse. See Ex. A. The park slopes from south to north. The Ellipse is level, with the result that the Granite Double Wall functions in part as a retaining wall to hold back the earth on the higher, southerly slope. The Granite Double Wall has two structural components. See Ex. A (blue). One component is a retaining wall holding back the hill on the southerly side; the second component is a granite bench, which is built along 97.6 LF of the retaining wall and faces inward toward the center of the Ellipse. The plan detail of the Double Granite Wall, detail 5 of sheet 12 (“5/12”), plainly shows the two structural components. See Ex. B, attached. By contrast, the granite structure on the downhill, northerly side of the Ellipse-and along two of the southerly pedestrian entrance paths--has only one component, the Granite Seat Wall. See Ex. A (yellow). The Granite Seat Wall stands alone in these 3 Note: On Ex. A the top of the page is southeast, not north. 4 locations since no retaining wall is required. See Ex. A. A plan detail of the Granite Seat Wall is shown on detail 3 of plan 12 (“3/12”). See Ex. C, attached. The parties agree that only one payment item applies to the Granite Seat Wall constructed on the northerly side of the Ellipse, namely Item 719.12 (“Freestanding Granite Seat Wall”).4 The parties agree that the Department has paid McCourt in full to build the Granite Seat Wall at those locations colored yellow on Ex. A. The parties also agree that the physical characteristics of the Granite Seat Wall on the northerly side of the Ellipse are identical to the characteristics of the Granite Seat Wall on the southerly side, where it has been installed in front of the retaining wall. The Granite Seat Wall surrounds the plaza and fountain in the center save where the four pedestrian walks provide access. See Ex. A (yellow and blue). (3) The Special Provisions The proposal the Department offered for bid contained 19 separate pay items relating to granite stonework. The 19 pay items were grouped together within special provisions “Items 719.01 Thru 719.19.” Among the 19 special provisions 3 bear directly on the outcome of this appeal, namely “ITEM 719.10 “ITEM 719.11 “ITEM 719.12 GRANITE WALL GRANITE WALL WITH SEAT GRANITE SEAT WALL LINEAR FOOT LINEAR FOOT” LINEAR FOOT The caption on the bid sheet for Item 719.10 is “Granite Retaining Wall”; for Item 719.11 “Granite Double Wall”; and for Item 719.12 “Freestanding Granite Seat Wall.” Nowhere within the special provisions is there any language that directly or indirectly describes which payment item should be used to pay for the work of building 4 Although labeled “Freestanding Granite Seat Wall” on the bid sheet, plan detail “3/12” does not depict a freestanding structure. The structure drawn on “3/12” and referred to in special provision 719.12 are both labeled “Granite Seat Wall.” I refer to that structure throughout this report as “Granite Seat Wall” for clarity. 5 the 97.6 LF portion of Granite Seat Wall along the Granite Double Wall on the southerly side of the Ellipse. The text of the special provision for “Items 719.01 Thru 719.19” is found at pages 127-135 of the Contract. Those special provisions are devoid of any written specification that describes the work to be done under Items 719.10, 719.11 or 719.12.5 The special provisions are devoted to directives concerning materials, samples to be submitted for approval, the material to be used, construction methods, finishes etc. (4) The Plans and Plan Details The layout plan for the park expressly references plan details (Plan Details). See Ex. A. The plan keys to the plan details of both the Granite Seat Wall and the Granite Double Wall. See Ex. A, referencing Plan Detail “5/12” captioned “Granite Double Wall” [See Ex. B, attached] and Plan Detail “3/12” captioned “Granite Seat Wall” [See Ex. C, attached]. Both Plan Details “5/12” and “3/12” employ the usual practice of indicating materials by symbols incorporated into the plan drawing. See “5/12” and “3/12” showing granite, concrete, gravel backfill, compacted subgrade, stainless steel dowel and brick paving. Plan Detail “3/12,” captioned Granite Seat Wall, is fully drawn with all details and components. See Ex. C. Thus, “3/12” contains every detail needed to build the 5 The only mention in the special provisions of the work to be done under 719.10, 719.11 or 719.12 is under “Measurement,” where the disputed items are referenced as follows: “Quantities of [] Granite Wall, Granite Wall With Seat, Granite Seat Wall [] shall be measured in place and along the centerline of the Item by the Engineer.” Similarly, under the provision for “Payment” there is a reference by implication: “Payment of work shall be paid for at the contract price per unit indicated under items 719.01 [] through 719.19 [] which includes full compensation for providing all materials (including reinforced concrete bases and foundations) [] required to complete the work in accordance with the Drawings and as directed by the engineer.” Other than under these two references there is nothing in the special provisions that bears on the scope the pay items numbered 719.11 and 719.12. 6 Granite Seat Wall.6 The plan at Ex. A shows that “3/12” work is to be done on both the downhill, northerly side of the Ellipse and on the uphill, southerly side. “3/12” makes no cross reference to “5/12” or any other plan or detail. The estimated quantity for Item 719.12 (“Granite Seat Wall”) on the bid sheet is 140 feet. “5/12,” captioned “Granite Double Wall,” is not fully drawn. “5/12” shows that the “Granite Double Wall” has two component parts: (1) a fully drawn plan detail of the retaining wall portion to be built by capping a concrete footing with a shaped granite piece tied by a stainless steel rod, and (2) an outline (not fully drawn) of the Granite Seat Wall to be constructed in front of the retaining wall component. “5/12” depicts the retaining wall component in full detail, but leaves the Granite Seat Wall component blank. See Ex. B. The Granite Seat Wall component of “5/12” is cross-referenced to plan detail “3/12”: an arrow captioned “Granite Seat Wall 3/12” points to the unshaded component. The cross-reference in “5/12” to “3/12” is clear. See Ex. B. “5/12” only shows only the information needed to build the retaining wall component of the Double Granite Wall. The details needed to build the Granite Seat Wall component, shown in outline on “5/12,” are found only on detail “3/12.”7 Nowhere in the Contract documents—specifically including the pages 87-101 of the special provisions governing all specialty stone work---is there any writing directing 6 The shading within “3/12” shows a 1’ 4” wide “granite seat wall,” the front of which is beveled to approximately quarter round. “3/12” also shows the brick paving of the Ellipse, the height above grade, the stainless steel dowel which anchors the granite to the concrete footing, the “compacted gravel borrow” underlying the footing and the “compacted” “subbase.” Where the back of the shaped granite or concrete footing meets grade, the Plan Detail 3 “gravel backfill.” The “granite seat wall,” as drawn, shows a height of ‘12” @ lawns,’ and ‘24” @ beds.’ “3/12” plainly shows that the granite seat wall is not be “freestanding” at all places where it to be built. 7 “5/12” shows that both components of the Double Granite Wall rest on “compacted gravel borrow” on top of a “compacted” “subbase.” “5/12” also shows that, where the back of the retaining wall component meets grade, “gravel backfill” is to be supplied. The estimate quantity for Item 719.11(“Double Granite Wall”) on the bid sheet is 103 feet. 7 the contractor to use a named payment item for the work of building the Granite Seat Wall where it is installed in front of the Granite Double Wall. (3) Estimated and Final Quantities The Contract documents show that McCourt bid as follows on the pay items for 719.10 (“Granite Retaining Wall”); 719.11 (“Granite Double Wall”) and 719.12 (“Freestanding Granite Seat Wall”). ITEM ESTIMATED QUANTITY FINAL QUANTITY UNIT PRICE 719.10 719.11 719.12 100.00 103 LF 140 LF 164.69 97.61 92.99 $250/LF $400/LF $300/LF Halvorson admits that the estimated quantities of 719.10 and 719.12 were incorrect. Its July 5, 1995 letter states “The total quantity of these two bid items is 240 lf, although it appears that the quantities between the two are flipped (719.10 should be (+) 140 lf and 719.12 should (+) 100 lf.” The quantities estimates of provided by Halvorson were substantially incorrect for many bid items.8 DISCUSSION The Legal Standard The familiar principles governing the construction of a written contract, including the interpretation of plans, drawings and plan details included in the contract documents, are well settled. The interpretation of an unambiguous contract is a question of law. See Robert Indus., Inc. v. Spence, 362 Mass. 751, 755 (1973); Freelander v. G. & K Realty 8 Item 390.1 3 Irrigation Sleeve: 40Lf (est), 140 Lf (actual); Item 506 Granite Curb VB Straight: 20 LF (est), 220 LF (actual); Item 706.01 Brick Paving on Mortar Setting Bed: 1,316 SY (est), 500 SY (actual); Item 719.055 Granite Fence Post Base: 30EA (est), 50EA (actual). 8 Corp., 357 Mass. 512, 516 (1970). Thus, where the contract at issue is found to be unambiguous, a court will determine the meaning of the contract as a matter of law. In construing an unambiguous contract the judge must consider “the particular language used against the background of other indicia of the parties’ intention,” and must “construe the contract with reference to the situation of the parties when they made it and to the objects sought to be accomplished…. Not only must due weight be accorded to the immediate context, but no part of the contract is to be disregarded.” Starr v. Fordham, 420 Mass. 178, 190 (1995) (internal citation omitted). A contract “should be construed to give it effect as a rational business instrument and in a manner which will carry out the intent of the parties.” Id. at 192, citing Shane v. Winter Hill Fed. Sav. & Loan Ass’n., 397 Mass. 479, 483 (1986). Where a contract consists of separate parts or sections, all of them must be considered together so as to give reasonable effect to each. See S. D. Shaw & Sons, Inc. v. Ruggo, Inc., 343 Mass. 635, 640 (1962). The principal guide to contract interpretation is what appears within the text of the document. See Citation Ins. Co. v. Gomez, 426 Mass. 379, 381 (1998). There is no dispute that these rules of construction apply to both words and to drawings, plans and plan details. Discussion The question for decision is whether or not the Contract required separate payment for the Granite Seat Wall at locations where it fronted on the Granite Double Wall. McCourt contends that the two components of the Granite Double Wall shown on Plan Detail “5/12” are paid by two separate payment items—viz. the retaining wall component is paid through Item 719.11 (“Granite Double Wall”) while the granite bench 9 seat is paid through Item 719.12 (“Granite Seat Wall”). The Department contends that it “intended” that all work shown on “5/12” should be paid under Item 719.11 (“Granite Double Wall”). For the reasons set forth below, I find McCourt’s appeal has merit. Although the parties disagree about what the Contract Plans and Plan Details mean, they do not argue that the Plans or Plan Details at issue are in and of themselves ambiguous. Thus, I accept that the Contract should be construed in accordance with its plain meaning. I look to the contents of the Contract itself in order to determine the intent of the specific Plans and Plan Details that govern the outcome of this appeal. Two critical Plan Details in this Contract require scrutiny: Detail 5 of Plan 12 (“5/12”) and Detail 3 of Plan 12 (“3/12”). Together these two Details explicate the work of constructing the Granite Double Wall on the southerly side of the Ellipse; standing alone neither “3/12” or “5/12” accomplishes that purpose. There is no doubt that at that the Granite Double Wall consists of two component parts: a retaining wall and a granite bench seat as “5/12” clearly shows. See Ex. B. The fact that the retaining wall component—but not the granite bench seat component--is fully drawn on Detail “5/12” is of determinative significance: all information needed to build the retaining wall component is present while none of the information needed to build the granite bench seat appears. The express cross reference in “5/12” to “3/12,” where the granite seat component is fully drawn, indicates that two separate pay items apply. See Ex. B & C, attached. That the Contract intends two separate pay items for the work of the Granite Double Wall is confirmed by the plan details “5/12” and “3/12” read together, as “5/12” indeed instructs. “5/12” requires the contractor to look to “3/12” to build the Granite Seat 10 Wall component of the Double Granite Wall. Nothing in plan detail “5/12,” the specifications or special provisions contradicts the logical conclusion that payment for constructing 97.6 linear feet of Granite Seat Wall in front of the retaining wall portion of the Granite Double Wall should be made in the same manner that all identical work is be paid. The arrow in “5/12” points directly to the unshaded portion of the Double Granite Wall leading to detail “3/12”--“Granite Seat Wall”--and nothing else. Where there is no contravening special provision or plan detail, a contractor reading “5/12” would reasonably conclude that identical Granite Seat Wall work would be paid under the identical item, Item 719.12 (“Granite Seat Wall”). I think that a “competent mechanic or contractor”9 reading “5/12” would at his peril assume that “3/12” work would be paid under “5/12.” Nothing in the special provisions clarifies that “5/12” “intends” for a contractor to bid the Granite Double Wall as if the explicit reference to “3/12” did not exist. A blank, unshaded area on “5/12” to which an arrow labeled “3/12” points indicates Item 719.12 work, and could not be ignored. To the contrary, a competent contractor would justifiably assume that identical structures to be built in various locations within a project are to be paid by a single payment item expressly designated for all such work. Here, where the identical granite seat wall surrounds the Ellipse on both its northerly and southerly sides, and where no construction detail for the Granite Seat Wall is shown in “5/12,” McCourt correctly understood that the Contract intended it to build (and the Department to pay for) the Granite Seat Wall wherever the plans expressly indicated that work. Accordingly, all granite seat wall work must be paid under Item 719.12 (“Granite Seat Wall”). 9 The Standard Specifications (1988 ed.) provide in subsection 2.03: “The Department will prepare plans and specifications giving directions which will enable any competent mechanic or contractor to carry them out.” 11 The Department’s Position The Department adopted the position of the designer Halvorson in its entirety. It first argues that the language of the caption “Granite Double Wall” must be construed to mean that bid Item 719.11 (“Granite Double Wall”) includes payment for both components of the wall shown in “5/12” because the words of the caption infer that the retaining wall and the granite seat wall are both parts of the “double” wall. That argument fails because it ignores what is plainly shown in Plan Details “5/12” and “3/12.” The Contract provides in Subsection 5.04 of the Standard Specifications (1988 ed.) that “In the event of any discrepancy between the plans and the specifications, the plans are to govern.” Here the specifications and special provisions are silent with the result that the plan details read together control. “5/12” and “3/12” construed together show that the Granite Seat Wall, constructed at various locations, is to be paid under its own item.10 Second, the Department argues that Halvorson “intended” that pay item 719.11 (“Granite Double Wall”) include both the retaining wall component and the granite bench component within it. As proof of Halvorson’s “intent” the Department relies on (1) Halvorson’s own statement to that effect and (2) the fact that Halvorson stated that its own internal design cost estimates made before bidding corroborate that intent. But what 10 The argument that the caption “Granite Double Wall” should control the outcome of this appeal is particularly troublesome in the context of the ways in which the captions in this Contract were written. Written Spec Bid Sheet Plan Sheets 719.10 Granite Wall Granite Retaining Wall [None] 719.11 Granite Wall w Seat Granite Double Wall Granite Double Wall 719.12 Granite Seat Wall Freestanding Granite Seat Wall 12 Granite Seat Wall Consultant Interpretation “Granite Seat Wall (with earth)” “Double Wall (3/12 & 5/12)” “Granite Seat Wall (w/o earth)” Halvorson subjectively believed about the plans it drew at the time it drew them does not control. “[T]he crucial question is ‘what [the claimant] would have understood as a reasonable construction contractor,’ not what a drafter of the contract terms subjectively intended.” Corbetta Constr. Co. v. U. S., 461 F.2d 1330, 1336 (Ct. Cl. 1972). Halvorson’s unshared, private cost estimates said to prove Halvorson’s intent that the Granite Double Wall was an item that included the separately referenced work of the Granite Seat Wall was not apparent in the Contract and was never disclosed to bidders. The Department introduced no evidence of Halvorson’s internal cost estimates at the hearing. 11 Accordingly, Halvorson’s arguments—and the Department’s--must fail. CONCLUSION McCourt correctly construed the Contract Plan Details to require all payment for the work of constructing the Freestanding Granite Seat Wall to be made under payment item 719.12. RECOMMENDATION McCourt is entitled to be paid $29,280 under payment item 719.12 for the 97.6 LF of Freestanding Granite Seat Wall it built as part of the Double Granite Wall at the bid price of $300/ LF (300 X 97.6 = $29, 280). Respectfully submitted, Stephen H. Clark Administrative Law Judge 11 The Department therefore failed to explain how comparing the cost of item 719.11 (Granite Double Wall”) and item 719.10 (“Granite Retaining Wall”) “substantiates [the] intent” that the Contract requires that the Granite Seat Wall be paid under Item 719.11. 13