Urban Ring Phase 2 Proposed Circumferential Transit Project Urban Ring

advertisement
Urban Ring Phase 2
Proposed Circumferential Transit Project
Urban Ring
Citizens Advisory Committee Meeting
July 28, 2009
1
Urban Ring Phase 2
Agenda
„
2
Notice of Project Change
z
Alignment changes
z
Phasing plan
z
Special Review Procedure
„
Boston MPO Regional Transportation Plan
„
Urban Ring Phase 2 implementation
„
Discussion
Urban Ring Phase 2
NPC – Alignment Changes
„
„
3
Mystic River Crossing: Everett – Sullivan Square
z
DCR – concerns about environmental impacts
z
Longer travel time (Rt 16, Rt 28 in mixed traffic)
z
City of Boston redesign of Sullivan Sq – potential for
bus connection to T station
z
Retain Assembly Square service
Allston Connection
z
Railyard-level alignment through Allston Landing
z
Stadium Way – Barry’s Corner – North Harvard St.
Urban Ring Phase 2
NPC – Alignment Changes
„
„
Review Columbia Point Service
z
JFK Library, proposed Kennedy Institute for US Senate
z
Proposed Columbia Point master plan, mixed use
development
z
UMass Boston master plan, potential bus lanes
LMA Connection
z
4
Identify interim surface routing
Urban Ring Phase 2
Ev e re tt
Wellington
Downtown
Chelsea
Station
Me df or d
So merv i lle
RDEIR/
DEIS
Alignment
Assembly
Square
Chel sea
Sullivan
Square
Harvard
Square
Ea s t
Bo s t o n
New
Lechmere
Airport
Ca mbri dg e
Logan
West
Garage
Cambridgeport
Kendall /
MIT
Al ls to n
World
Trade
Center
Yawkey
Broadway
BU Bridge
LMA
Ruggles
Washington
Street
Br o ok lin e
So uth B o s to n
Newmarket
Dudley
Square
Ro xb ury
JFK/UMass
5
Urban Ring Phase 2
Do rch es t er
Ev e re tt
Me df or d
So merv i lle
Chel s ea
Northern Tier
First Implementation Stage
NPC
Alignment
Ea s t
Bo s t o n
Ca mbri dg e
Logan
West
Garage
Al ls to n
Kendall /
MIT
Southern Tier
Br o ok lin e
S o uth B o s to n
Ro xb ury
6
Urban Ring Phase 2
Do rch es t er
Urban Ring Phase 2 – Phasing Plan
„
Northern Tier: Logan Airport – Kendall Square
- $486 m (2009 $)
z
„
7
First BRT implementation phase
Southern Tier - $2,220 m (2009 $)
z
Early actions – service improvements, low-cost
infrastructure improvements
z
Major infrastructure items – Fenway/LMA tunnel,
Charles River crossing, Allston connection
Urban Ring Phase 2
Northern Tier: Logan – Kendall
„
Benefits
z
Cost-effectiveness
z
Environmental justice
z
Economic development
z
Service characteristics/
independent utility
z
„
8
Me df or d
So merv i lle
Chel sea
Ea st
Bo st o n
Logan
West
Garage
Ca mbri dg e
Feasibility/ROW and
abutter issues
Issues, impediments
z
Resolution of Sullivan
Square redesign
z
CSX property needs
Urban Ring Phase 2
Kendall /
MIT
Southern Tier – Early Actions
Service Improvements
9
„
Evaluate potential service improvements
(constrained by MBTA/EOT finances)
„
Work with MBTA to review and rationalize bus routes
and service, identify potential to enhance service in
Urban Ring corridor
„
Work with MBTA, municipalities to identify
opportunities for
z
Bus signal priority
z
Queue jump lanes
z
Enhanced amenities in corridor – shelters, traveler
information
Urban Ring Phase 2
Southern Tier – Early Actions
Potential Low-Cost Infrastructure Investments
„
Albany St bus lanes - $1 m
„
Mountfort St. corridor
improvements - $14 m
„
LMA – interim surface
improvements – TBD
„
Ruggles Station
improvements - $33 m
„
„
„
„
10
B
Ca m b r i d g e
Albany Street
Buslanes
Alls to n
Mountfort Street
Corridor
Improvements
Melnea Cass Blvd. busway
- $27 m
Albany Street bus lanes $1-2 m
Mass Ave bus lanes - $1-2
m
Columbia Point bus lanes –
TBD
Urban Ring Phase 2
Melnea Cass Blvd.
Busway
Br o o kl i n e
Interim Surface
Improvements
Fenway/LMA
So ut h
Albany Street
Buslanes
Ruggles Station
Improvements
Southern Tier Potential Early Actions
Mixed Traffic
Buslane
Busway (Surface)
LMA Surface Routing
(ongoing coordination with City of Boston
and area stakeholders)
Ro x b u r y
Massachusetts
Avenue
Buslanes
Do r ch e st e r
Southern Tier
Major Infrastructure Elements
Camb r id g e
„
Fenway/LMA
tunnel - $1,850 m
Charles River
Crossing/ GJRR
Alls to n
Allston
Connection
„
Charles River
crossing - $130 m
Br o o kl i n e
So u
Fenway/LMA
Tunnel
„
Allston connection
- $82 m
Southern Tier
Major Infrastructure Elements
Mixed Traffic
Buslane
Busway (Surface)
Busway (Tunnel)
Busway (Tunnel) Alignment Options
11
Urban Ring Phase 2
R ox b u r y
Dor ch e st e r
Fenway/LMA
Tunnel
„
Cost – up to $1.7 B
„
Benefits
„
z
Travel time, reliability
z
Service to densest
concentration of trip
demand in corridor
Kendall /
MIT
8
line
Major Impediments
z
Tunnel financing
Mixed Traffic
Buslane
Busway (Surface)
Busway (Tunnel)
Proposed Stop
Route Options
12
Urban Ring Phase 2
Roxbury
Area of Ongoing
Analysis
Charles River
Crossing
„
Cost - $ 130 M
„
Benefits
„
z
Travel time savings
z
Reliability
z
Key life science
corridor connection
Cambridge
Kendall /
MIT
Major Impediments
z
CSX negotiation
z
Ongoing CSX
operations
z
Fort Washington, MIT
development parcel
z
BU Academy site
6
kline
Mixed Traffic
Buslane
Busway (Surface)
Busway (Tunnel)
Proposed Stop
Route Options
13
Urban Ring Phase 2
Area of Ongoing
Analysis
Allston
Connection
„
Cost - $ 82 M
„
Benefits
„
z
More direct routing
z
Travel time, reliability
z
Key life science
corridor connection
7
Al l st o n
Major Impediments
z
CSX negotiation
z
Beacon Park Yard
consolidation,
relocation
z
14
Cambridge
Mixed Traffic
Buslane
Harvard development
timing
Urban Ring Phase 2
Busway (Surface)
Busway (Tunnel)
Proposed Stop
Br oo k l i n e
Route Options
Area of Ongoing
Analysis
NPC – Special Review Procedure
„
Administrative Consent Order: EOT – DEP, Sep 1, 2000
z
MIS and ENF by June 1, 2001
z
FEIR w/in 3 years of ACO – OR – EENF requesting MEPA Special Review
Procedure + 1st phased review document by Sep 1, 2003
z
Proposal for low cost measures (Phase 1)
„
Deadlines extended by subsequent ACO amendments,
MEPA actions
„
Existing deadlines
z
15
Urban Ring Phase 2 FEIR/FEIS – December 31, 2009
‹
New Starts application, approval to enter PE
‹
Substantial completion of PE
z
Urban Ring Phase 3 DEIR/DEIS – December 31, 2011
z
Urban Ring Phase 3 FEIR/FEIS – TBD
Urban Ring Phase 2
Boston MPO – Regional Transportation Plan
„
2007 RTP must be updated due to changes to State
Implementation Plan (SIP)
z
16
FHWA, FTA have not accepted “new” Boston Region
Transportation Improvement Programs (TIPs) since SIP changes
„
Draft RTP revision under consideration by Boston MPO
„
Constrained to reasonable financial assumptions –
FHWA, FTA requiring prioritization of projects
„
Draft RTP includes East Boston Haul Road
Urban Ring Phase 2
Boston MPO – Regional Transportation Plan
„
„
„
17
Draft includes SIP commitments
z
Green Line Extension to College Avenue, Union Square
z
Fairmount Branch improvements
z
1,000 new parking spaces
z
Red-Blue Connector design
Proposal under review to flex highway funds to transit
z
Green Line Extension to Route 16
z
Assembly Square Orange Line station supplement
z
Wonderland Station improvements
Total Boston MPO expansion (highway and transit)
program, 2009 – 2030 = $1.9 billion (2009 $)
Urban Ring Phase 2
Next Steps
„
„
Urban Ring consultant procurement
z
Scope under development (informed by MEPA Certificate)
z
Early action analysis – service review, low-cost improvements
z
Planning for Northern Tier – pre-New Starts application work
z
Continued coordination on Southern Tier major infrastructure
elements
Federal Transit Administration (FTA)
z
„
Boston Region MPO
z
18
Continue coordination to maximize overall project in application,
while pursuing early implementation
Next RTP in 2011 – project must be in RTP to apply for New Starts
Urban Ring Phase 2
Discussion
Please visit our website at
www.theurbanring.com
19
Urban Ring Phase 2