University Project Status Report

advertisement
University Project Status Report
INCEPTION: this phase consists of general ideas, thoughts, suggestions, studies and proposals for new projects.
PLANNING: this phase identifies participants, determines justification for the project, as well as identifies the project's scope, site, and identifying the financial
sources.
PROGRAMMING CONCEPT DESIGN: this identifies the project's background and justification; identifies the needed spaces, space use, types and quality. It also
identifies the infrastructure needs, site amenities, special equipment, estimated budget and project delivery time line. Included is the identification of
resources for maintenance and operation. If any existing space is being vacated due to this project, this phase includes the repurposing of existing spaces.
SELECTION OF CONSULTANTS: This phase involves selecting the professional consultants, the "on call" consultants or the in house professional staff needed to
prepare the design, bid documents and administer project delivery.
DESIGN CONSTRUCTION DOCUMENTS: This phase begins with schematic and design documents that result in the creation of the construction documents that
are used to bid and build the project.
BIDDING: This phase selects from interested contractors or in house shops to provide the construction price to build the project via the state, university,
foundation or in house shop processes of bidding. This is dependent on the scope of the project
CONSTRUCTION: This phase involves building, installing, repairing or replacing items as required by the bid documents.
COMMISSIONING: This phase requires all systems be tested and balanced to check performance based on design criteria.
COMPLETION: Substantial completion - some items are left to be finished (such as punch list items), but the project can be occupied and all warranties are
started. Completion - the project is 100% complete with all close out document and all submittals received.
WARRANTY: This phase runs generally one year after substantial completion to correct any deficienies for all work, materials equipment.
Project Name
Project Type
State R&R
Project Name
Project Type
State R&R
Project Name
Project Type
State R&R
12.5kv/4.2kv Campus Creek Complex - Burt Hall
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Programming Concept Design 50% 15%
Jan 2015
Aug 2015
Manager
J. Carlson
12.5kv/4.2kv Conversion for Anderson Hall
Current Phase
Construction 70%
Total % Complete Construction Start Date Construction Completion Date
75%
May 2014
Aug 3, 2014
Manager
J. Carlson
12.5kv/4.2kv Conversion for Eisenhower-Holton-Holtz
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 25%
**Aug '14
Dec '14
Monday, August 04, 2014
Manager
J. Carlson
Page 1 of 20
Project Name
12.5kv/4.2kv Conversion for Willard Hall
Project Type
State R&R
Current Phase
Construction 10%
Project Name
150 Year Time Capsule Plaza
Project Type
State
Current Phase
Construction
Project Name
Ackert Boiler - Animal Quarters
Project Type
State R&R
Current Phase
Construction 98%
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Total % Complete Construction Start Date Construction Completion Date
25%
June 2014
July 2014
Total % Complete Construction Start Date Construction Completion Date
15%
06/2014
09/14
Total % Complete Construction Start Date Construction Completion Date
97%
After Jan '14
Warranty began
Manager
J. Carlson
Manager
S. Hao
Manager
J. Carlson
Agronomy Farm shop bldg #516 roof repairs and paint/coating
Current Phase
Bidding
Total % Complete Construction Start Date Construction Completion Date
10%
Summer 2014
Aug 2014
Manager
K. Minihan
Ahearn Complex - Life Safety Improvements
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 50%
May 2013
Aug 2014
Manager
J. Sharp
AiM/AssetWorks Implemntatin
Current Phase
Construction
Total % Complete Construction Start Date Construction Completion Date
80%
n/a
5-2014
Manager
V. L'Ecuyer
Anderson 104A Hardwood floor re-finsih
Current Phase
Construction
Total % Complete Construction Start Date Construction Completion Date
7/14/14
Manager
K. Minihan
Anderson Hall 06
Current Phase
Planning
Monday, August 04, 2014
Total % Complete Construction Start Date Construction Completion Date
0%
7-20-2014
7-27-2014
Manager
R. Holle
Page 2 of 20
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
City/University
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Anderson Hall 201
Current Phase
Planning
Total % Complete Construction Start Date Construction Completion Date
0%
NA
NA
Manager
R. Holle
Anderson Hall 201 Kitchenette renovations
Current Phase
Planning
Total % Complete Construction Start Date Construction Completion Date
0%
NA
NA
Manager
R. Holle
Animal Science Sheep and Meat Goat Center
Current Phase
Total % Complete Construction Start Date Construction Completion Date
Manager
M. Loberg
Annual Space Inventory Update
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 20%
2-2014
November 2014
Manager
V. L'Ecuyer
Bike Parking on campus
Current Phase
Construction
Total % Complete Construction Start Date Construction Completion Date
15%
7/2014
8/2014
Manager
S. Hao
Bluemont 121 Remodel
Current Phase
Bidding
Total % Complete Construction Start Date Construction Completion Date
Fall 2014
Manager
K. Minihan
Bluemont 16 wall around column and outlets
Current Phase
Bidding
Total % Complete Construction Start Date Construction Completion Date
Manager
K. Minihan
Total % Complete Construction Start Date Construction Completion Date
Manager
M. Loberg
Bluemont 241 Fume Hood Adjustments
Current Phase
Monday, August 04, 2014
Page 3 of 20
Project Name
Bluemont 5102 epoxy floor
Project Type
State
Current Phase
Construction
Project Name
Bluemont 5119 epoxy floor
Project Type
State
Current Phase
Construction
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
City/University
8-01-14
8-08-14
Total % Complete Construction Start Date Construction Completion Date
7-24-14
8-1-14
Manager
K. Minihan
Manager
K. Minihan
Boyd Hall Domestic Water Replacement
Current Phase
Construction (95%)
Total % Complete Construction Start Date Construction Completion Date
95%
May 2014
August 2014
Manager
E. Chamberlin
BOYD HALL RE-ROOFING
Current Phase
Construction
Total % Complete Construction Start Date Construction Completion Date
70%
July 9th, 2014 construct August 1, 2014
Manager
D. McMullen
Bushnell Hall - Life Safety Improvements
Current Phase
Bidding (0%)
Total % Complete Construction Start Date Construction Completion Date
50%
May 2013
Aug 2014
Manager
J. Sharp
Call Rm 160 Fume Hood Attachment
Project Type
Current Phase
State / ASI Departmen Construction
Project Name
Total % Complete Construction Start Date Construction Completion Date
Total % Complete Construction Start Date Construction Completion Date
100%
TBD
6/20/2014 Warranty began
Manager
J. Carlson
Calvin 112 Doorbell
Current Phase
Construction
Total % Complete Construction Start Date Construction Completion Date
0
Manager
M. Loberg
Campus Addressing
Current Phase
Construction
Monday, August 04, 2014
Total % Complete Construction Start Date Construction Completion Date
20%
n/a
1-2015
Manager
V. L'Ecuyer
Page 4 of 20
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State (Bond)
Project Name
Project Type
City/University
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
City/University
Cardwell Hall - Room 101 Renovation
Current Phase
Construction (75%)
Total % Complete Construction Start Date Construction Completion Date
90%
Sept.2014
Sep 2014
Manager
D. McMullen
Chem Bio-Chem 4th floor autoclave
Current Phase
Bidding
Total % Complete Construction Start Date Construction Completion Date
Manager
K. Minihan
Chiller Water - Plant/Distrib/CBA Steam 2013
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 15%
May 2014
Aug 2015
Manager
J. Carlson
City Signal Tower on Campus
Current Phase
Total % Complete Construction Start Date Construction Completion Date
Manager
M. Taussig
Colby Water Main Service Replacement
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Programming Concept Design 10% 10%
tbd
tbd
Manager
J. Carlson
Coles Hall HVAC Improvements
Current Phase
Completion
Total % Complete Construction Start Date Construction Completion Date
75
09/01/13
06/15/14
Manager
M. George
Cut out and replace 10X 6' piece of concrete slab at base of entry steps
Current Phase
Inception
Total % Complete Construction Start Date Construction Completion Date
1%
JULY 2014
asap
Manager
D. McMullen
Denison Ave. Cooridor Improvements by Goodnow Hall
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Programming Concept Design (75 5%
5/15/15
TBD
Monday, August 04, 2014
Manager
S. Hao
Page 5 of 20
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
Foundation
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Dicken Hall South Steps
Current Phase
Planning
Total % Complete Construction Start Date Construction Completion Date
0%
5-19-2014
5-26-2014
Manager
R. Holle
Dickens 307/308
Current Phase
Planning
Total % Complete Construction Start Date Construction Completion Date
10%
5/19/2014
6/13/2014
Manager
R. Holle
Durland 2012-2015
Current Phase
Planning
Total % Complete Construction Start Date Construction Completion Date
0%
NA
NA
Manager
R. Holle
Durland Hall 1033
Current Phase
Planning
Total % Complete Construction Start Date Construction Completion Date
0%
NA
NA
Manager
R. Holle
EAST MEMORIAL STADIUM WELCOME CENTER
Current Phase
Programming Concept Design
Total % Complete Construction Start Date Construction Completion Date
5%
summer or Fall 2014 de summer or Fall 2016
Manager
D. McMullen
Edwards Hall D. wing Stair rreplacement
Current Phase
Construction
Total % Complete Construction Start Date Construction Completion Date
35%
July 1 2014
Aug 15, 2014
Manager
T. Bartlett
Eisenhower 011 space remodel convert unassigned space to offices
Current Phase
Construction
Total % Complete Construction Start Date Construction Completion Date
40%
spring 2014
summer 2014
Manager
D. McMullen
ELP - Space Request
Current Phase
Planning
Monday, August 04, 2014
Total % Complete Construction Start Date Construction Completion Date
50
n/a
August 8
Manager
V. L'Ecuyer
Page 6 of 20
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
Foundation
Project Name
Project Type
Foundation
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Engineering Complex Expansion- Phase IV
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 10%
April 2014
Sept 2015
Manager
M. George
Equine Performance Testing Center
Current Phase
Selection of Consultants (20%)
Total % Complete Construction Start Date Construction Completion Date
5%
June 2015
March 2016
Manager
E. Chamberlin
Esienhower 01 remodel
Current Phase
Planning
Total % Complete Construction Start Date Construction Completion Date
10%
5-19-2014
7-19-2014
Manager
R. Holle
Feed Mill - New metal building warehouse for feed tech
Current Phase
Inception
Total % Complete Construction Start Date Construction Completion Date
Manager
D. McMullen
Feed Mill new office location - fourth floor
Current Phase
Inception
Total % Complete Construction Start Date Construction Completion Date
90% LAYOU
TBD
TBD
Manager
D. McMullen
Global Campus Building Sign
Current Phase
Construction
Total % Complete Construction Start Date Construction Completion Date
08/2014
08/2014
Manager
S. Hao
Hale 118 Remodel
Current Phase
Inception
Total % Complete Construction Start Date Construction Completion Date
0%
December 2014
January 2015
Manager
E. Chamberlin
Hale 407/408 Remodel
Current Phase
Construction
Monday, August 04, 2014
Total % Complete Construction Start Date Construction Completion Date
95%
1 June 2014
August 2014
Manager
E. Chamberlin
Page 7 of 20
Project Name
Project Type
N/A
Project Name
Project Type
State
Project Name
Project Type
State
Hale East Upper Roof Warranty Issues
Current Phase
Warranty
Current Phase
Construction
Current Phase
Construction
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
50%
May 21, 2014
August, 21,2014
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 10%
May 2014
May 2016
Project Type
State
Project Name
Total % Complete Construction Start Date Construction Completion Date
Manager
T. Bartlett
Hale Library Sprinkler Replacement
Hale NW 12.5 line relocate
Project Type
State
5%
Manager
M. Loberg
Hale Library Foundation Waterproofing
Project Name
Project Name
Total % Complete Construction Start Date Construction Completion Date
Total % Complete Construction Start Date Construction Completion Date
100%
May 19, 2014
June 13, 2014
Manager
J. Sharp
Manager
M. Loberg
Hazardous Waste Transfer Facility
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 15%
TBD
TBD
Manager
E. Chamberlin
Holton 202 Renovations
Current Phase
Planning
Total % Complete Construction Start Date Construction Completion Date
0%
NA
NA
Manager
R. Holle
Holton Hall Landscape
Current Phase
Inception
Total % Complete Construction Start Date Construction Completion Date
0%
8/2014
9/2014
Manager
S. Hao
Holton Hall Re-Roof
Current Phase
Construction
Monday, August 04, 2014
Total % Complete Construction Start Date Construction Completion Date
40%
7-14-14
8-15-14
Manager
K. Minihan
Page 8 of 20
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
City/University
Project Name
Horticulture Olathe Research ext. service road
Current Phase
Bidding
Total % Complete Construction Start Date Construction Completion Date
90-95%
Aug 1 2014
Sept 1
Manager
T. Bartlett
Housing and Dining Storage Building
Current Phase
Construction
Total % Complete Construction Start Date Construction Completion Date
0%
Aug 2013
Jan 2015
Manager
J. Sharp
Improve electrical lines within the swine unit.
Current Phase
Construction
Total % Complete Construction Start Date Construction Completion Date
75%
June 15, 2014
July 20, 2014
Manager
T. Bartlett
Jardine Building M
Current Phase
Construction
Total % Complete Construction Start Date Construction Completion Date
25%
01/2014
12/2014
Manager
M. Taussig
Jardine M Site Work
Current Phase
Construction
Total % Complete Construction Start Date Construction Completion Date
0%
10/2014
Dec. 2014
Manager
S. Hao
Justin 119 new office partitioned off in the break room
Current Phase
Inception
Total % Complete Construction Start Date Construction Completion Date
short form O as soon as practical
N/A
Manager
D. McMullen
Kimball Ave. Sidewalk
Current Phase
Programming Concept Design
Total % Complete Construction Start Date Construction Completion Date
June 2015
Manager
M. Taussig
K-State Gardens - Conservatory Garden Master Plan
Project Type
Current Phase
City/University/Found Construction
Monday, August 04, 2014
Total % Complete Construction Start Date Construction Completion Date
5%
7/2014
9/2014
Manager
S. Hao
Page 9 of 20
Project Name
Project Type
Foundation
Project Name
Project Type
Foundation
Project Name
Project Type
State
Project Name
Project Type
City/University
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
Foundation
K-State Directional Signs
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 90%
July 2014
August 2014
Manager
M. Taussig
K-State Gardens Conservatory
Current Phase
Programming Concept Design
Total % Complete Construction Start Date Construction Completion Date
75
NA
NA
Manager
M. Taussig
K-State Student Union renovation
Current Phase
Programming Concept Design
Total % Complete Construction Start Date Construction Completion Date
10%
January 2015
fall 2015
Manager
D. McMullen
K-STATE UNION - FORUM HALL STAGE LIGHTING
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 10%
SUMMER 2014
SUMMER 2014
Manager
D. McMullen
KSU-S APARTMENTS
Current Phase
Programming Concept Design
Total % Complete Construction Start Date Construction Completion Date
CONSULTAN TBD
TBD
Manager
D. McMullen
Lafene Space Audit
Current Phase
Planning
Total % Complete Construction Start Date Construction Completion Date
25%
July 25, 2014
September 1
Manager
V. L'Ecuyer
Leasure 103-4
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 40%
spring 2014
summer 2014
Manager
D. McMullen
Library Annex
Current Phase
Construction(75%)
Monday, August 04, 2014
Total % Complete Construction Start Date Construction Completion Date
85%
Roberta Johnson
Nov. 2014
Manager
D. McMullen
Page 10 of 20
Project Name
Project Type
State
Project Name
Project Type
State (Bond)
Project Name
Project Type
Foundation
Project Name
Project Type
State R&R
Project Name
Project Type
City/University
Project Name
Project Type
Foundation
Project Name
Project Type
Foundation
Project Name
Project Type
State
Library Landscape
Current Phase
Inception
Total % Complete Construction Start Date Construction Completion Date
0%
8/2014
10/2014
Manager
S. Hao
Lovers Lane Street Replacement
Current Phase
Planning 15%
Total % Complete Construction Start Date Construction Completion Date
05%
Manager
J. Carlson
Mark A. Chapman - Nichols Theatre Lighting & Sound Upgrade
Current Phase
Construction 95%
Total % Complete Construction Start Date Construction Completion Date
95%
May 15, 2014
July 1, 2014 warranty begins
Manager
J. Carlson
McCain 112 Costume Shoppe HVAC
Current Phase
Bidding 05%
Total % Complete Construction Start Date Construction Completion Date
15%
Sep 2014
Late Mar 2015
Manager
J. Carlson
McCain Auditorium Stage Lighting
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 15%
June 9th
August 2014
Manager
M. George
McCain Hall - Room 204 remodel - Phase 2
Current Phase
Construction (0%)
Total % Complete Construction Start Date Construction Completion Date
20%
Aug. 15 2014
August 2014
Manager
M. George
McCain Lobby Addition Visioning
Current Phase
Programming Concept Design
Total % Complete Construction Start Date Construction Completion Date
90%
December 2013
July 2014
Manager
E. Chamberlin
McCain Lobby Office
Current Phase
Planing
Monday, August 04, 2014
Total % Complete Construction Start Date Construction Completion Date
0%
NA
NA
Manager
R. Holle
Page 11 of 20
Project Name
Project Type
Foundation
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
Foundation
Project Name
Project Type
City/University
McCain Theatre repair moveable ceiling
Current Phase
Construction
Total % Complete Construction Start Date Construction Completion Date
5%
6-1-2014
1-1-2014
Manager
M. Loberg
Mosier Hall - Alterations for Equine CT Table
Current Phase
Bidding
Total % Complete Construction Start Date Construction Completion Date
20%
May 2014
Dec 2014
Manager
M. George
Mosier Hall - Room F117 Remodel
Current Phase
Bidding
Total % Complete Construction Start Date Construction Completion Date
20%
July 2014
Dec 2014
Manager
M. George
Mosier Hall - SA Lobby Remodel
Current Phase
Programming Concept Design
Total % Complete Construction Start Date Construction Completion Date
5%
May 2015
August 2015
Manager
E. Chamberlin
Mosier Hall Live-In Lab Renovation
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 25%
July 2014
October 2014
Manager
E. Chamberlin
Mosier Hall Room E107 Remodel
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 10%
TBD
TBD
Manager
E. Chamberlin
Multicultural Student Center
Current Phase
Programming Concept Design
Total % Complete Construction Start Date Construction Completion Date
10%
SEPT 2014
TBD
Manager
D. McMullen
NBAF Sanitary Sewer
Current Phase
Construction
Monday, August 04, 2014
Total % Complete Construction Start Date Construction Completion Date
90%
03/2014
07/2014
Manager
M. Taussig
Page 12 of 20
Project Name
New Bldg for College of Business
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 10%
Aug 2014
July 2016
Project Type
State
Project Name
Nichols 26 Dance floor
Project Type
State
Project Name
Current Phase
Planning
Current Phase
Construction
Project Name
Parking Lot D1 Elect Feeder
Project Type
State R&R
Current Phase
Construction 100%
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
0%
NA
NA
Manager
R. Holle
Total % Complete Construction Start Date Construction Completion Date
40%
5-19-2014
9-1-2014
Total % Complete Construction Start Date Construction Completion Date
100%
May 12, 14
Warranty began 6/13/14
Manager
M. Loberg
Manager
J. Carlson
Parking Lots A11 & A12 Reconstuction
Project Type
State- ParkingFees
Project Name
Total % Complete Construction Start Date Construction Completion Date
Nichols Stone replace Ph 3 South side
Project Type
State
Project Name
Manager
M. George
Current Phase
Construction 95%
Total % Complete Construction Start Date Construction Completion Date
95%
Summer 2014
tbd
Manager
J. Carlson
Parsons Machinery Building (SEARC)
Current Phase
Construction
Total % Complete Construction Start Date Construction Completion Date
95%
03/2014
July 2014
Manager
M. George
Peter's Rec Center exterior caulking
Current Phase
Construction
Total % Complete Construction Start Date Construction Completion Date
7-28-14
10-01-14
Manager
K. Minihan
Peter's Rec Center front entrance concrete apron mudjacking
Current Phase
Construction
Monday, August 04, 2014
Total % Complete Construction Start Date Construction Completion Date
8-11-14
8-18-14
Manager
K. Minihan
Page 13 of 20
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Pres Office
Current Phase
Planning
Current Phase
Construction
Current Phase
Construction
Current Phase
Planning
Total % Complete Construction Start Date Construction Completion Date
85%
4-7-2014
NA
Manager
R. Holle
Total % Complete Construction Start Date Construction Completion Date
90%
4-21-2014
NA
Manager
R. Holle
Total % Complete Construction Start Date Construction Completion Date
0%
NA
NA
Manager
R. Holle
Presidents Office Lighting Project
Pure Bred Beef Relocation
Project Type
State
Current Phase
Inception
Project Type
State
NA
President Office and conference room
Project Name
Project Name
5-19-2014
Pres Res
Current Phase
Planning
Project Type
unknown
5%
Manager
R. Holle
Pres Res
Project Type
State
Project Name
Total % Complete Construction Start Date Construction Completion Date
Total % Complete Construction Start Date Construction Completion Date
0%
3500
NA
Total % Complete Construction Start Date Construction Completion Date
0%
07/2015
06/2016
Manager
R. Holle
Manager
M. Taussig
Putnam Hall Domestic Water Replacement
Current Phase
Construction (75%)
Total % Complete Construction Start Date Construction Completion Date
80%
May 2014
August 2014
Manager
E. Chamberlin
PUTNAM HALL RE-ROOFING
Current Phase
Construction
Monday, August 04, 2014
Total % Complete Construction Start Date Construction Completion Date
99%
MAY 19th, 2014
August 1, 2014
Manager
D. McMullen
Page 14 of 20
Project Name
Project Type
State
Project Name
Rathbone Hall - Room 1073 remodel
Current Phase
Planning (%)
Current Phase
Planning
Project Name
Recreation Center Pavilion
Project Type
Foundation
Current Phase
Inception
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
1%
Summer 2014
Manager
K. Minihan
Rathbone Hall 0047
Project Type
State
Project Name
Total % Complete Construction Start Date Construction Completion Date
Total % Complete Construction Start Date Construction Completion Date
0%
NA
NA
Total % Complete Construction Start Date Construction Completion Date
0%
N/A
N/A
Manager
R. Holle
Manager
M. Taussig
Recycling Center Equipment Building
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 0%
08/2013
12/2013
Manager
M. Taussig
Relpace west fence and repair cross fence ( Stocker Unit)
Current Phase
Construction
Total % Complete Construction Start Date Construction Completion Date
80%
May 20, 2014
Aug 1, 2014
Manager
T. Bartlett
Repair-Replace entry doors at the Flour mill - it appears that the closed needs to be adjusted to allow the door to fully close - - may be other
Current Phase
Inception
Total % Complete Construction Start Date Construction Completion Date
1%
JULY 2014
asap
Manager
D. McMullen
Replace Furrowing House roof
Current Phase
Bidding
Total % Complete Construction Start Date Construction Completion Date
20%
Manager
T. Bartlett
Rocky Ford Irrigation Pump Replacement
Current Phase
Planning 25%
Monday, August 04, 2014
Total % Complete Construction Start Date Construction Completion Date
10%
Nov 2013
May 2015
Manager
J. Carlson
Page 15 of 20
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
Foundation
Project Name
Project Type
State
Project Name
Scholarship House Code Improvements and Mechanical CD's
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 95%
07/2014
08/2014
Manager
M. Taussig
SE Kansas Research/Extension
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 15%
Aug 2014
August 2015
Manager
M. George
SEARC replace metal siding on Mound valley #963
Current Phase
Planning
Total % Complete Construction Start Date Construction Completion Date
20%
Manager
T. Bartlett
Seaton 213 Wood Floor Refinish
Current Phase
Total % Complete Construction Start Date Construction Completion Date
Manager
M. Loberg
Total % Complete Construction Start Date Construction Completion Date
Manager
D. McMullen
SEATON HALL ROOM 142 REMODEL
Current Phase
Planning & estimating
5% concept
TBD
Seaton Hall/Seaton Court Renovation and Expansion, Phase I and II
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 5%
May 2015
May 2016
Manager
E. Chamberlin
Shellenberger Hall - Life Safety Improvements
Project Type
State
Current Phase
Bidding (0%)
Project Name
Solar Car Charging Station
Project Type
State
Current Phase
Inception 15%
Monday, August 04, 2014
Total % Complete Construction Start Date Construction Completion Date
40%
May 2013
Aug 2014
Total % Complete Construction Start Date Construction Completion Date
20%
Sep 2013
Jan 2014
Manager
J. Sharp
Manager
J. Carlson
Page 16 of 20
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
Foundation
Project Name
Project Type
State
Project Name
Project Type
State
Stone House bathroom cabinets and countertops.
Current Phase
Planning
Total % Complete Construction Start Date Construction Completion Date
0%
NA
NA
Manager
R. Holle
Stone House North Door replacement
Current Phase
Planning
Total % Complete Construction Start Date Construction Completion Date
0%
5-19-2014
5-23-2014
Manager
R. Holle
Strong Complex Electrical Study
Current Phase
Planning
Total % Complete Construction Start Date Construction Completion Date
0%
NA
12/12/14
Manager
M. Taussig
Strong Complex Electrical Study
Current Phase
Inception
Total % Complete Construction Start Date Construction Completion Date
0%
NA
NA
Manager
M. Taussig
SW Kansas Equipment Shed
Current Phase
Construction
Total % Complete Construction Start Date Construction Completion Date
07/2014
09/2014
Manager
M. Taussig
Swine Nursery Barn
Current Phase
Construction
Total % Complete Construction Start Date Construction Completion Date
0%
7/2014
10/2014
Manager
M. Taussig
Throckmorton 4308 lab renovate to office space
Current Phase
Bidding
Total % Complete Construction Start Date Construction Completion Date
Fall 2014
Manager
K. Minihan
Throckmorton Hall Room 4411
Current Phase
Construction
Monday, August 04, 2014
Total % Complete Construction Start Date Construction Completion Date
100%
4-7-2014
5-9-2014
Manager
R. Holle
Page 17 of 20
Project Name
Throckmorton Stone repair
Project Type
State
Current Phase
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
Private
Project Name
Project Type
State
Total % Complete Construction Start Date Construction Completion Date
Manager
T. Bartlett
Throckmorton telecom room planning - 8 NEW TELECOM ROOMS
Current Phase
Planning 80%
Total % Complete Construction Start Date Construction Completion Date
20%
June 2014 - working wit pending completion of FCP and
Manager
D. McMullen
Trotter Library Remodel
Current Phase
Construction (10%)
Total % Complete Construction Start Date Construction Completion Date
35%
July 2014
September 2014
Manager
E. Chamberlin
Trotter Mara Center Renovations
Current Phase
Inception
Total % Complete Construction Start Date Construction Completion Date
0%
November 2014
December 2014
Manager
E. Chamberlin
Trotter Quiet Room Renovations
Current Phase
Total % Complete Construction Start Date Construction Completion Date
September 2014
October 2014
Manager
E. Chamberlin
Van Zile West Stairs
Current Phase
Construction
Total % Complete Construction Start Date Construction Completion Date
95%
May 26, 2014
June 13, 2014
Manager
M. Loberg
Vanier Football Complex
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 30%
December 2014
August 2015
Manager
E. Chamberlin
Wall and roof repair Forestry Seedling shed
Current Phase
Construction
Monday, August 04, 2014
Total % Complete Construction Start Date Construction Completion Date
95-100%
July 1, 2014
Manager
T. Bartlett
Page 18 of 20
Project Name
Project Type
State
Project Name
Project Type
City/University
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
H&D funds
Project Name
Project Type
State
Project Name
Project Type
State
Project Name
Project Type
State R&R
Waters 38, 38A, 38B Lab Remodel
Current Phase
Programming Concept Design
Total % Complete Construction Start Date Construction Completion Date
10%
Oct. 15, 2014
Manager
M. Loberg
Waters Hall Landscape & Irrigation
Current Phase
Construction
Total % Complete Construction Start Date Construction Completion Date
75%
May 2014
Fall 2014
Manager
S. Hao
Waters Hall Rm 231 General Classroom Renovation
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents
5-18-15
8-24-15
Manager
K. Minihan
Waters Hall Signs
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 95%
07/2014
08/2014
Manager
M. Taussig
Wefald Hall new dormitory and food service complex
Total % Complete Construction Start Date Construction Completion Date
Current Phase
Design & Construction Documents 75%
06/2014
May 2016
Manager
M. Taussig
West Memorial Stadium - Purple Masque Theatre
Current Phase
Construction (15%)
Total % Complete Construction Start Date Construction Completion Date
24%
Nov 15, 2013
Jan 2015
Manager
J. Sharp
Western Kansas AG Research Center Water supply replacement
Current Phase
Planning
Total % Complete Construction Start Date Construction Completion Date
50%
Manager
T. Bartlett
Willard Art Studio Ventilation Rm 320
Current Phase
Construction 95%
Monday, August 04, 2014
Total % Complete Construction Start Date Construction Completion Date
95%
Sept 15, 2013 (NTP)
Jul 14, 2014 (NTP)
Manager
J. Carlson
Page 19 of 20
Project Name
Willard Art Studio Ventilation Rms 319, 203-206, 321,322
Project Type
Current Phase
State - R&R'13 & FY'10 Construction 10%
Project Name
Project Type
State
Total % Complete Construction Start Date Construction Completion Date
15%
Jun '14
Jan '15
Manager
J. Carlson
WKARC Replace Rollup doors on Mechanical shed
Current Phase
Planning
Monday, August 04, 2014
Total % Complete Construction Start Date Construction Completion Date
Manager
T. Bartlett
Page 20 of 20