Location reference: Corton Policy Unit reference: 6.22 SUMMARY OF PLAN RECOMMENDATIONS AND JUSTIFICATION Plan: The exposure of this coastline means that technically it is already becoming increasingly difficult to hold the present shoreline position, with beaches becoming almost impossible to retain. This is due to the prominent position of this frontage, relative to the shoreline either side, with it being some distance forward of its natural position. There is also insufficient economic justification for providing defence against ongoing erosion. Continued defence at this location will also increasingly interrupt sediment movement along this coastline, which will be to the detriment of Gunton Warren and Lowestoft. The long-term Plan for Corton is therefore to allow the cliffs to retreat, allow a more natural shoreline position to be attained. However, there will be loss of property and associated infrastructure within the village; therefore it may be acceptable to manage this retreat where this can be economically justified and is not detrimental to processes and environmental gains. Notwithstanding this, measures to manage risk and mitigate the displacement of people and loss of property and assets will need to be developed and put in place. Policies to implement Plan: From present day: The policy option in the short term is to hold the line to protect the village frontage through routine and reactive maintenance of the existing defences, i.e. the rock armour, sea wall and cliff slope protection, where this is physically possible, and funding allows. The actual timing of wall failures is estimated to be between 2025 and 2030, but to comply with the long-term Plan they would not be replaced should there be a major failure in advance of that date. This approach will minimise cliff erosion, and should continue to protect assets within the village. However, any measures to accommodate changes in defence practice and loss of property in the medium-term need to be established during this period. Investigations will thus be undertaken to identify technical options and an appropriate package of social mitigation measures, in preparation for the transition to the medium to long term policy option of managed realignment (see sections below). Only when such adequate mitigating social measures are identified, which will limit the impact on the lives of individuals and the community, would the long-term change to a managed realignment policy option be implemented. These measures will need to consider the predicted loss of The Street in the long term. The Coastal Strategy will need to identify various responsibilities for addressing the future loss of infrastructure (access, sewers, gas etc) including the effect on properties in the hinterland. This short term policy option is not detrimental to the achievement of the longterm Plan, as it is expected that coastal response in the absence of defence would be rapid. Medium-term: The maintenance of defences along this frontage will become more difficult, and therefore much more expensive, as the Corton coast continues to develop as a promontory and becomes more exposed. It will also be detrimental to The above provides the local details in respect of the SMP-wide Plan; therefore the above must be read in the context of the wider-scale issues and policy implications, as presented in the preceding sections and Appendices to this Plan document. achievement of a naturally functioning shoreline. The medium-term Plan is therefore to cease maintenance of the defences and allow cliff erosion so that a more natural shoreline (i.e. less of a promontory) is achieved. Management of the abandoned defences may be a key influence in the delivery of strategic benefits and will also impact upon beach access opportunity. There will be loss of cliff top assets of up to 40 properties under this policy option; therefore a requirement will be for measures identified in the short term stage of the plan to be put in place prior to this time that will enable appropriate relocation of people, properties and facilities. To achieve the Plan the shoreline needs to reach a position generally in line with shoreline on either side. As the shoreline erodes towards that position, there may be justification for occasional intervention to help manage the retreat. Defence measures that temporarily slow (rather than halt) erosion are likely to be acceptable, provided that these do not prevent the alongshore transport of beach sediment and do not result in the development of this area as a promontory, i.e. phases of retreat should be allowed for. Therefore the policy option is to allow retreat through managed realignment. Long-term: In the long-term the policy option is to allow cliff retreat. This will deliver technical and environmental benefits, but a number of assets will be lost, with over 100 properties being lost; however the commitment to social mitigation measures developed in the short term will lessen the socio-economic impact of this policy option. As the shoreline reaches a position more in line with the adjacent cliffs, beaches should be healthier and it is expected that erosion rates would slow. As a result, management of the shoreline could be more easily achieved, through measures such as groynes, without being detrimental to adjacent areas. Therefore the policy option is to allow retreat through managed realignment. The above provides the local details in respect of the SMP-wide Plan; therefore the above must be read in the context of the wider-scale issues and policy implications, as presented in the preceding sections and Appendices to this Plan document. Location reference: Corton Policy Unit reference: 6.22 PREDICTED IMPLICATIONS OF THE PLAN FOR THIS LOCATION Time Period By 2025 Property & Land Use No loss of property or land behind the existing defences. Nature Conservation No variance; continued exposure of SSSI cliffs. Landscape No landscape objectives identified. Historic Environment No loss. Amenity & Recreational Use Little/ no beach present – no change in beach access. No loss of community or recreational facilities landward of defences. By 2055 Loss of less than circa 20 houses and less than circa 20 commercial properties and associated infrastructure/ services. Improved exposure of SSSI cliffs and sediment linkage alongshore. No landscape objectives identified. Some loss of high importance area seaward of Corton Church. Narrow beach retained but relocation of access required. Opportunity for and quality of use will depend upon how defence debris is managed after failure. Coast Road (the Street) will be severed. Loss of some seafront facilities. Loss of seafront caravan sites/ holiday camps. By 2105 Cumulative loss of less than approximately 90 houses and less than 25 commercial properties and associated infrastructure/ services. Loss of Methodist Church, school, village hall and Public House. Further loss of seafront caravan sites/ holiday camps. Further loss of main coast road. Naturally functioning system. Improved exposure of SSSI cliffs and sediment linkage alongshore. No landscape objectives identified. Further loss of high importance archaeological area. Narrow beach retained but relocation of access required. Loss of further seafront facilities.