Location reference: Bacton, Walcott and Ostend Policy Unit reference: 6.11 SUMMARY OF PLAN RECOMMENDATIONS AND JUSTIFICATION Plan: The long-term Plan for this area is to allow shoreline retreat once present defences reach the end of their present effective life. This is essential to ensure that problems here and elsewhere are not exacerbated by impairing the movement of beach sediment, which will occur if this shoreline continues to be held in its present position. This policy option will result in the loss of a large number of properties and associated facilities within these settlements. However, the properties and associated facilities located along this length of coast that are at risk from erosion and flooding do not generate sufficient economic benefit to justify prioritised investment in their long-term defence. This area already suffers from low beach levels and it would become increasingly difficult to sustain defences along the present line without considerable investment. For the immediate future defences are to be maintained as far as possible within existing economic justification, whilst measures are put in place to manage this risk and mitigate the displacement of people and loss of property and facilities in the medium-term. There is already overtopping into the Upper Ant, which flows into the Broads, and any worsening of this has the potential to impact on the SPA. Policies to implement Plan: From present day: From the present day, the policy option is to continue to maintain existing defences, i.e. the seawall, groynes and northern end of the timber revetment at Ostend, through a hold the line policy. This will protect most of the assets behind the present defence line, although some properties will become vulnerable to erosion at the southern end of this frontage. The groynes may help to retain some beach material, but the beaches are likely to become lower and narrower than the present day. It will therefore become technically more difficult and thus considerably more expensive to protect beyond this period. Should a more major failure of the existing defences occur, the seawall would not be rebuilt as a permanent structure. However, wherever practicable, temporary structures that assist in delaying the erosion would be used locally (e.g. placement of rock, beach recharge etc) to delay further damage whilst approaches to manage and mitigate losses are developed and supporting economic analyses undertaken In parallel, investigations will be undertaken to identify technical options and establish an appropriate package of social mitigation measures, in preparation for the transition to the medium to long term policy option of managed realignment (see sections below). Only when such adequate mitigating social measures are identified, which minimise the impact on the lives of individuals an communities, would the change to a medium to long term policy option of managed realignment be implemented. As the medium and long term policy is for managed realignment, ongoing monitoring of the sea wall, saline inundation and habitat monitoring will be undertaken starting in the short term, to look at the potential impacts on The Broads SAC/Broadland SPA/Ramsar. Studies to look at the future evolution of The above provides the local details in respect of the SMP-wide Plan; therefore the above must be read in the context of the wider-scale issues and policy implications, as presented in the preceding sections and Appendices to this Plan document. the coast will be carried out. The results of these studies will be considered in the next review of the SMP and appropriate avoidance, mitigation and habitat compensation identified. Due to the rapid response of this shoreline to erode and resume a natural position once defences are no longer in place, this short term policy option is not considered to be detrimental to the long-term Plan. Medium-term: As the long-term Plan is to allow sediment transport along this frontage, this would be a transitional period, whereby once existing defences reach the end of their life they are not replaced, as replacement is unlikely to be economically viable nor would it be technically suitable. It is presently predicted that all defences are likely to have failed by between years 20 and 40. The proposed policy option for this section of coast is therefore managed realignment. . However, this retreat will result in the loss of assets and, as such, defence measures that temporarily slow (rather than halt) erosion might be acceptable, if they can be economically justified, and provided that these do not prevent the alongshore transport of beach sediment and do not result in the development of this area as a promontory. These measures will be used for as long as possible to allow social and economic mitigation measures to be identified to minimise the impact on the lives of individuals and communities. Long-term: Subject to the identification of suitable social and economic mitigation measures, the long-term policy option is to allow the coastline to naturally retreat to ensure sediment supply to this, and downdrift frontages. This will deliver technical and environmental benefits, but a number of assets will be at risk. Therefore there needs to be a continuation of measures to manage losses, including erosion-slowing defences, where this can be justified. The policy is therefore one of managed realignment. Ultimately, the shoreline will reach a position generally in line with adjacent shorelines. The increased throughput of sediment from adoption of similar policy options to the north should help beaches to build along this frontage, so that erosion, and therefore property loss, here should not continue to be accelerated over and above natural rates. Once the shoreline reaches a more sustainable position, it may be acceptable to help retain beaches, if necessary, with structures such as short groynes, provided that these are not detrimental to continued adequate sediment throughput to areas downdrift. These should not halt erosion but would help to manage it in a sustainable manner. Therefore the policy option is managed realignment. The above provides the local details in respect of the SMP-wide Plan; therefore the above must be read in the context of the wider-scale issues and policy implications, as presented in the preceding sections and Appendices to this Plan document. The above provides the local details in respect of the SMP-wide Plan; therefore the above must be read in the context of the wider-scale issues and policy implications, as presented in the preceding sections and Appendices to this Plan document. The above provides the local details in respect of the SMP-wide Plan; therefore the above must be read in the context of the wider-scale issues and policy implications, as presented in the preceding sections and Appendices to this Plan document. Location reference: Bacton, Walcott and Ostend Policy Unit reference: 6.11 PREDICTED IMPLICATIONS OF THE PLAN FOR THIS LOCATION Time Period By 2025 By 2055 Property & Land Use Nature Conservation Landscape Historic Environment Amenity & Recreational Use No loss of property or land behind the existing defences between Bacton and Walcott. Loss of up to circa 35 properties at Ostend. No nature conservation objectives identified. No landscape objectives identified. No heritage objectives identified. Narrow beach present. Cumulative loss of up to circa 195 seafront residential and 20 commercial properties. Loss of associated infrastructure. No nature conservation objectives identified. No landscape objectives identified. No heritage objectives identified. Improved beach but access would need to be relocated, Biodiversity opportunity through management of low-lying land as a saline habitat. No landscape objectives identified. No heritage objectives identified. Beach present but access would need to be relocated. Loss of some caravan park land. Loss of main link road between Walcott and Bacton and also the emergency access route from Bacton Gas Terminal. By 2105 Cumulative loss of between circa 195 and 385 seafront residential and circa 20 to 25 commercial properties and associated infrastructure. Further loss of some caravan park land. Existing link between Walcott and Bacton and also the emergency access route from Bacton Gas Terminal lost by 2055.