Shoreline Management Plan 6 Action Plan for web April 2013.xls Policy Unit ID 1 Kelling Hard to Cromer (Policy Unit 6.01-6.04) Policy Unit Name Action Action Description (Location) Referenc Lead Organisation Implementation Date Status Update March 2013 e 6.02 Sheringham 6.03 Sheringham to Cromer NNDC/05 Maintenance / refurbishment of existing sea wall at Sheringham with particular attention to toe protection. A project appraisal report will need to be developed in order to progress these NNDC/06 Maintain accesses and local defences at Runton Gaps. NNDC Ongoing Progressing NNDC Ongoing Progressing NNDC/07 Review Cromer Coast Defence Strategy Study 6.04 NNDC N/A Complete NNDC Jun-12 Complete Cromer NNDC/08 A project appraisal report will need to be developed in order to progress the refurbishment of defences. 6.04 Cromer Staged refurbishment process is underway with annual schemes funded through revenue coast protection works. Condition monitored and actions taken under the Coast Protection maintenance budget when required. Cromer coast protection refurbishment scheme budget has obtained consent. Design consultants have been appointed and engineering contractor will be procured during 2013. Works anticipated to start on site Oct/Nov 2013. Cromer coast protection refurbishment scheme budget has obtained consent. Design consultants have been appointed and engineering contractor will be procured during 2013. Works anticipated to start on site Oct/Nov 2013. Please see Multiple Unit Actions and Water Framework Directive/Habitats Directive Actions for other activities which may be relevant to this location Appendix 1.a SMP Action Monitor Page 1 Shoreline Management Plan 6 Action Plan for web April 2013.xls Policy Unit ID 6.07 2 Cromer East to Bacton Gas Terminal (Policy Unit 6.05 – 6.09) Policy Unit Name Action Action Description (Location) Reference Overstrand to Mundesley NNDC/01 NNDC/11 6.08 Mundesley Lead Organisation Implementation Date Identify an economic baseline and options for the continued defence of Trimingham. Maintain/refurbish defences at Mundesley to ensure the planned 50 year lifespan. A project appraisal report will need to be developed in order to progress the works. Please see Multiple Unit Actions and Water Framework Directive/Habitats Directive Actions for other activities which may be relevant to this location NNDC NNDC Jan-12 Ongoing Appendix 1.a SMP Action Monitor Status Progressing Progressing Update March 2013 To be considered as part of Cromer to Winterton Management Plan. Outcomes of Cromer to Winterton Management Plan will recommend future works schedule. Continued maintenance through NNDC coastal budget. Page 1 Shoreline Management Plan 6 Action Plan for web April 2013.xls Policy Unit ID 3 Bacton Gas Terminal to Eccles (Policy Unit 6.10 - 6.12) Policy Unit Name Action Action Description (Location) Reference NNDC/02 6.1 Bacton Gas Terminal Lead Organisation Implementation Date Liaise with operators of Bacton Gas Interconnector site so to understand the lifespan of the site and any implication this may have on the SMP as a whole. Please see Multiple Unit Actions and Water Framework Directive/Habitats Directive Actions for other activities which may be relevant to this location NNDC Ongoing Appendix 1.a SMP Action Monitor Status Progressing Update March 2013 Discussions with operators of Bacton gas interconnector site have commenced. Operators are contributing financially to the Cromer to Winterton Management Plan. Page 1 Shoreline Management Plan 6 Action Plan for web April 2013.xls Policy Unit ID 4 Eccles to Winterton Beach Road (Policy Unit 6.13) Policy Unit Name Action Action Description (Location) Reference EA/02 6.13 Eccles to Winterton Beach Road 6.13 Eccles to Winterton Beach Road 6.13 Eccles to Winterton Beach Road EA/04 EA/05 Lead Organisation Implementation Date Monitor Eccles to Winterton beach recharge materials for shell fragments to ensure low levels of calcium are present to prevent negative impacts on dune habitats. Stage 3B beach recharge and groyne replacement Sea Wall and groyne maintenance. Status EA Most likely Sept-14 Progressing EA Most likely Sept-14 Progressing EA Ongoing Progressing Update March 2013 Recharge materials considered as part of procurement of recharge operations contracts and monitored during operations. 2012 Environmental Monitoring report complete. Next recharge programmed for 2014. Outcomes of Cromer to Winterton Management Plan will assit in future planning and scheme implementation. Stage 3B works currently programmed Outcomes of Cromer to Winterton Management Plan will assit in future planning and scheme implementation. Maintenance works in progress Winter 2013. Please see Multiple Unit Actions and Water Framework Directive/Habitats Directive Actions for other activities which may be relevant to this location Appendix 1.a SMP Action Monitor Page 1 Shoreline Management Plan 6 Action Plan for web April 2013.xls 5 Winterton South of Beach Road to Scratby (Policy Unit 6.14) Policy Unit ID Policy Unit Name (Location) Action Reference GYBC/01 6.14 Winterton to Scratby NNDC/14 6.14 Winterton to Scratby Action Description Lead Organisation Implementation Date Continue to review rapid retreat rates at Winterton Ness to establish any need for a specific study. Monitor dune erosion to pro-actively implement exit plan if required. Maintain defences at Cart Gap to prevent outflanking. A project appraisal report will need to be developed in order to progress the works. Please see Multiple Unit Actions and Water Framework Directive/Habitats Directive Actions for other activities which may be relevant to this location GYBC NNDC Ongoing Ongoing Appendix 1.a SMP Action Monitor Status Progressing Progressing Update March 2013 Ness and northern beach good condition with wide beach. Erosion south of ness with some loss of forward dune(Hemsby) Rock armour placed at end of Cart Gap sea wall and monitored. To be considered as part of Cromer to Winterton Manageent Plan Page 1 Shoreline Management Plan 6 Action Plan for web April 2013.xls Policy Unit ID 6 California to Caister (Policy Unit 6.15 - 6.16) Policy Unit Name Action Action Description (Location) Reference 6.15 California to Caisteron-Sea 6.16 Caister-on-Sea GYBC/02 GYBC/03 Lead Organisation Implementation Date Maintenance of existing rock bund, groynes and sea wall Status Update March 2013 Fluctuating beach levels exposing dilapidated groynes Maintenance to (and if necessary replace) existing seawalls, reefs and groynes Please see Multiple Unit Actions and Water Framework Directive/Habitats Directive Actions for other activities which may be relevant to this location GYBC Ongoing GYBC Ongoing Appendix 1.a SMP Action Monitor Progressing Explore requirement to complete missing section of wave return wall. Page 1 Shoreline Management Plan 6 Action Plan for web April 2013.xls Policy Unit ID 7 Great Yarmouth - Gorleston (Policy Unit 6.17 – 6.18) Policy Unit Name Action Action Description (Location) Reference Lead Organisation Implementation Date Status Update March 2013 Please see Multiple Unit Actions and Water Framework Directive/Habitats Directive A ti f th ti iti hi h Appendix 1.a SMP Action Monitor Page 1 Shoreline Management Plan 6 Action Plan for web April 2013.xls Policy Unit ID 8 Gorleston - Hopton (Policy Unit 6.19 – 6.20) Policy Unit Name Action Action Description (Location) Reference Lead Organisation Implementation Date Status Update March 2013 Please see Multiple Unit Actions and Water Framework Directive/Habitats Directive Actions for other activities which may be relevant to this location Appendix 1.a SMP Action Monitor Page 1 Shoreline Management Plan 6 Action Plan for web April 2013.xls Policy Unit ID 9 Hopton (south) to Lowestoft (north) (Policy Unit 6.21 – 6.23) Policy Unit Name Action Action Description (Location) Reference WDC/07 6.21 Hopton to Corton WDC/08 6.21 Hopton to Corton WDC/09 6.21 Hopton to Corton WDC/15 6.21 Hopton to Corton WDC/16 6.22 Corton WDC/05 6.23 Corton to Lowestoft 6.23 Corton to Lowestoft 6.23 Corton to Lowestoft WDC/06 WDC/17 Lead Organisation Implementation Date Study to be completed to inform the future management and monitoring of RAF Hopton bunker. Implement agreed solution for the management/removal of the RAF Hopton bunker. Manage defences to improve public safety and amenity through appropriate removal of redundant defences. Manage failed coastal defences at Corton with reference to public safety and amenity. Sustain defence and access in the short to medium term at Corton Village. May be extended if management approach is altered by strategy or by early failure Study to be competed to inform the future management and monitoring of Eleni V oil burial sites. Implement agreed solution for the management of the Eleni V oil burial sites. Manage failed coastal defences at Gunton with reference to public safety and amenity. Please see Multiple Unit Actions and Water Framework Directive/Habitats Directive Actions for other activities which may be relevant to this location WDC Status tbc Progressing tbc Planned / Programmed tbc Planned / Programmed Update March 2013 Study to be incorporated into the Gorleston to Lowestoft Study. Is expected to follow the Gorleston to Lowestoft Study. WDC WDC WDC WDC tbc tbc Progressing Progressing WDC tbc Progressing WDC tbc Planned / Programmed WDC tbc Progressing Appendix 1.a SMP Action Monitor Works scheme is expected to follow on from Gorleston to Lowestoft Strategy then PAR. Locally funded through repairs and maintenance or local capital tasks. Now unlikely to include Pathfinder funding. Locally funded through repairs and maintenance or local capital tasks. Cliff groundwater control funded by Pathfinder. Approach to management will be informed by Gorleston to Lowestoft strategy. Study to be incorporated into the Gorleston to Lowestoft Study. Is expected to follow the Gorleston to Lowestoft Study. Locally funded through repairs and maintenance or local capital tasks. Now unlikely to include Pathfinder funding. Page 1 Shoreline Management Plan 6 Action Plan for web April 2013.xls 10 Lowestoft (north) to Ness Point (Policy Unit 6.24) Policy Policy Unit Name Action Action Description Unit ID (Location) Reference WDC/04 6.24 Lowestoft North (to Ness Point) 6.24 Lowestoft North (to Ness Point) 6.24 Lowestoft North (to Ness Point) 6.24 Lowestoft North (to Ness Point) WDC/11 WDC/12 WDC/18 Lead Organisation Implementation Date A project appraisal report will need to be developed in order to progress repair/removal of defences. Design and implementation of to scour protection and structure improvements - Phase 1. Design and implementation of to scour protection and structure improvements - Phase 2. High effort to sustain / maintain / remove ageing and increasingly exposed / derelict defences to deliver a HTL policy. Please see Multiple Unit Actions and Water Framework Directive/Habitats Directive Actions for other activities which may be relevant to this location Status Update March 2013 Is expected to follow the Gorleston to Lowestoft Study. tbc Planned / Programmed WDC tbc Planned / Programmed WDC tbc Planned / Programmed WDC WDC tbc Appendix 1.a SMP Action Monitor Progressing Phase 1 for southren 67% is expected to be justified by Gorleston to Lowestoft Study. Phase 2 will be subject to findings of later strategic reviews. Locally funded through repairs and maintenance or local capital tasks. Page 1 Shoreline Management Plan 6 Action Plan for web April 2013.xls 11 Multiple Policy Unit Actions Policy Policy Unit Name Action Unit ID (Location) Reference 6.01-13 Kelling Hard to Sheringham NNDC/15 NNDC/03 6.05 6.13 Cromer - Winterton Beach Road NNDC/09 6.06 6.07 Overstrand Mundesley 6.06 6.07 Overstrand Mundesley 6.06, 6.08, 6.10 6.16, 6.19, 6.20, 6.22 Overstrand, Mundesley, Bacton Gas Terminal, Caister-on-Sea, Goleston to Hopton, Corton NNDC/10 G/12 NNDC/13 6.08 6.11 Mundesley - Ostend NNDC/12 6.09 6.12 Mundesley to Eccles Action Description Include SMP policies in local searches Lead Organisation Implementation Date Update March 2013 Complete at NNDC NNDC N/A Complete Cromer to Winterton Management Plan to explore the sustainability of the mix of policies with consideration to NNDC Jan-12 current understanding of coastal processes and identify actions required for plan Removal of groynes and revetment as they become a health and safety problem NNDC Not determined between Overstrand and Mundesley. Maintain defences from Overstrand to Mundesley in the NNDC Not determined absence of an adaptation strategy. Develop consistent medium to long-term plans for relocation of services and facilities that will Local Authories/EA be lost to erosion, e.g. outfalls, with service and Ongoing highways in line with Defra utilities providers Coastal Change Policy and resulting pathfinder studies. Maintain defences in the absence of an adaptation strategy. NNDC Ongoing Removal of groynes and revetment as they become a health and safety problem. Status NNDC Not determined Appendix 1.a SMP Action Monitor Complete Progressing Progressing Progressing Planned / Programmed Progressing Progressing Contract for study awarded with planned completion June 2013. Management Plan will require further developemtn and community engagment. Updated action incorporates SMP actions EA/06 & 07. Outcomes of Cromer to Winterton Management Plan will advise on timescales and effective life of current coast protection assets. Local policy assessing when redundant defences can/should be removed needs development. Outcomes of Cromer to Winterton Management Plan will recommend future works schedules and funding shortfalls. Infrastructure to be identified in action G/13. Protocols to be established on a district/county basis for the establishment of protocols for timely actions. WDC frontage to be addressed in the Gorleston to Lowestoft Strategy. Outcomes of Cromer to Winterton Management Plan will recommend future works schedule. Note change on policy coverage due to discrepancy between location and policy units, policy units 6.06-6.07 covered by NNDC/10 Outcomes of Cromer to Winterton Management Plan will advise on timescales and effective life of current coast protection assets. Local policy assessing when redundant defences can be removed needs to be developed. Page 1 Shoreline Management Plan 6 Action Plan for web April 2013.xls GYBY/05 6.14, 6.16. 6.19 Caister-on-Sea to Lowestoft Ness WDC/02 6.18 6.24 Gorleston to Lowestoft Ness WDC/01 6.20 6.22 Hopton to Corton WDC/03 6.20 6.22 6.20 6.24 New Action - Remnant discharges from Eleni V were uncovered during winter 2012/13. Locations were recorded however further inclement conditions prevented action being completed before further scouring and deposition. Winterton to Scratby, Caister-onSea, Gorleston to Hopton GYBC/04 6.18 6.24 Monitor and review remnants form Eleni V. Hopton to Corton Hopton to Lowestoft WDC/14 North (to Ness point) Review monitoring of any changes resulting from the development of the Outer Harbour and action in response to findings. Undertake Gorleston to Lowestoft Study which includes a review of policies at Corton and Hopton and considers Hold the Line at north Lowestoft and management of derelict defences. Community engagement regarding coastal change and adaptation A project appraisal report for Corton and Hopton will need to be developed in order to progress the management of defences. Review and update coastal asset monitoring plan. GYBC Ongoing Progressing EA/GYBC Ongoing Progressing Completed annually via the Partner Moniroring Agreement. WDC procurement significantly delayed. Now intended to be via EA or other framework WDC tbc Progressing WDC tbc Progressing WDC tbc Planned / Programmed WDC tbc Planned / Programmed Appendix 1.a SMP Action Monitor Gorleston to Lowestoft Strategy to consider community engagement to be delivered through Waveney District Council (Pathfinder) and Great Yarmouth Borough Council. Is subject to findings of the Gorleston to Lowestoft Study. WDC is considering if this can be incorporated into o wider Environment Agency AIMS project. Page 2 Shoreline Management Plan 6 Action Plan for web April 2013.xls WDC/10 6.21 6.22 Hopton to Corton G/02 All N/A G/13 All N/A G/18 All N/A All EA/01 Identify and implement adaptation & mitigation works through Pathfinder with appropriate community engagement . Identify a standard approach to the assessment of social, economic and environmental sustainability for inclusion in the scope of Coastal Strategies. Such an approach may assist in identifying when transitional policies such as hold the line to managed realignment or managed realignment to no active intervention change. Develop and maintain a joint coastal dataset to record spatial and temporal information. Information should include coastal and flooding events, surveys, implementation of adaptation measures, property, heritage assets, infrastructure assets Communicate the completion of the SMP to the Regional Assembly to ensure appropriate reflection of the policy aims in the Regional Plan. Coastal change monitoring programme WDC tbc Progressing EA tbc Planned / Programmed The Treasury Green Book is the current methodology used for economic, social and environmental assessments and is recognised across government sectors. Communities have queried if this approach correctly identifies and attributes sufficient value to economic and social costs/benefits. As this is the standard method used by government in the assessment of funding of coast protection schemes it is required to be used during the development of coastal polices. However, it is necessary to continue to lobby government and government agencies as to the perceived failings of the methodology and seek greater recognition for tangible and in-tangle assets in the cost/benefit ratio. NNDC continues to lobby as appropriate opportunities arise as to this matter. Review of existing information is required and agreement of how datasets are to be stored, organised and maintained. Updated action incorporates SMP action EH/01. Resource requires to be identified and allocated. Regional Assembly now discontinued. EA Not required EA Cancelled Progressing Ongoing G/17 N/A Progressing EA N/A All tbc Being addressed through WDC pathfinder scheme. May be advanced as part of the Gorleston to Lowestoft Study. Ensure compliance with the Marine and Coastal Access Act. NE Ongoing Appendix 1.a SMP Action Monitor Progressing Summer and winter annual 50/100m beach survey transects, Annual aerial photography, lidar and intra red survey, quinquenial bathometric surveys (specifically policy unit 6.13). Updated action incorporates SMP actions EA/01 & 03, NNDC/04 & WDC/13. Local Authorities aware of the Natural England lead project. Coastal access legislation enables creation of new coastal public access and ability for coastal access to adapt as the coast changes. To be incorpoated into new work streams where appropriate. Page 3 Shoreline Management Plan 6 Action Plan for web April 2013.xls G/16 All N/A All N/A G/20 G/01 All N/A G/14 All N/A G/03 All N/A G/06 All N/A Invite the authors/promoters/advisors of the Marine Aggregate Regional Environmental Assessments (MAREA)project to a meeting for dicussions regarding the findings of their recent study. Updating of Action Plan SMP documentation to be considered in the development of Planning Policies and Planning Authorities and a coordinated approach across the frontage would be desirable Communicate the findings of all Coastal Change Pathfinder Studies to coastal authorities and coastal communities. Investigate and develop potential coastal adaptation measures across the frontage with consideration and appropriate input by coastal stakeholders. Seek opportunities and overcome obstacles to enable timely awareness raising and implementation of measures in order to prevent coastal blight and enable and manage agreed Seek Central Government funding for all consultation/stakeholder activities in the development of SMPs and strategies/ schemes. NNDC Ongoing Progressing NNDC Ongoing Progressing NNDC, WDC GYBC Ongoing Progressing NNDC/ GYBC/ WDC Ongoing Progressing NNDC/ GYBC/ WDC/ EA As adaptation measures are required or developed Progressing NNDC/ GYBC/ WDC/ EA Ongoing Appendix 1.a SMP Action Monitor MAREA completed project disemination in the sping on 2011. NNDC to raise as an agenda item that East Anglian Coastal Group consider the merits of a further meeting with Anglian Offshore Dredging Association regrading the MAREA project. MMO delivering licencing process - LA's statutory consultees in thsi process. Action Plan will be updated in line with annual Environment Agency SMP monitoring. NNDC & WDC integrated SMP6 policies into Planning Policy Documents. BA has an adopted planning policies. NNDC & WDC planning policies adopted with GYBC to follow in 2013. Defra developing Coastal Planning How to Guide. Updated action incorporates SMP actions G/07 10 & 19 NNDC completed dissemination of pathfinder lessons through March 2011 conference, Defra Reporting, public accessible archive website and appropriate community wrap up and dissemination activities. NNDC available to provide specific information to interested organisations. WDC & GYBC Pathfinders are on-going and information is disseminated as it NNDC adopted an integrated coastal approach in September 2012 which will seek to develop adaptation initiatives. The Cromer to Winterton Management Plan and Gorleston to Lowestoft Study will inform prioritisation of measures. Updated action incorporates SMP actions G/04, 05, 08, 09 & 11 Stakeholder engagement funds are part of grant in aid capital schemes. Further consideration needs to be given to funding for stakeholder engagement in other areas of coastal management other than flood and coast protection measures. Page 4 Shoreline Management Plan 6 Action Plan for web April 2013.xls G/15 All N/A Maintain communications with all coastal communities throughout the life of the plan to ensure that all members of the public and other organisations are able to appreciate the current situation regarding SMP policy, recent changes on the coast, recent strategy findings, up to date news regarding Government policy etc. NNDC/ GYBC/ WDC/ EA Ongoing Appendix 1.a SMP Action Monitor Progressing Website in development, North Norfolk Coastal Issues Forum to assist in sharing of information and development of knowledge, Suffolk Coastal Issues Forum assisting in guiding coastal activities and involving communities, communication incorporated in development of plans/strategies. Further consideration required to ensure sufficient communication is completed and if there is need for other wider activities such as an annual forum/conference. Page 5 Shoreline Management Plan 6 Action Plan for web April 2013.xls 12 Habitats Regulations Assessment & Water Framework Directive Policy Policy Unit Name Action Action Description 6.02, 6.04, 6.17, 6.18, 6.24 6.04; 6.06; 6.08; 6.10; 6.11; 6.12; 6.15; 6.16; 6.18; 6.20; 6.22; 6.23. WFD/01 Various WFD/02 Various 6.08, 6.13 WFD/03 Various 6.08 WFD/04 Mundesley Lead Organisation Implementation Modelling/monitoring to improve EA, NNDC, GYBC, understanding of the WDC implications of long term hold the line policies for alongshore and offshore sediment transport Investigations and monitoring to EA, NNDC, GYBC, help prevent release of WDC contaminants in to aquatic environment as a result of managed realignment and no active intervention policies. Remedial and other mitigation measures should be implemented as necessary. Investigations to improve EA, NNDC understanding of the current use and expected life of existing SPZs identified as potentially at risk by SMP policies. Investigations will be required to: Address concerns relating to the long term change of policy at 6.08 and the potential for saline intrusion into the ground water body and associated impacts; and; concerns relating to the conditional hold the line policies 6.13 where saline inundation could lead tot he loss or contamination of water resources. Research into potential EA, NNDC implications of SMP managed realignment policy unit 6.08 for the River Mun WFD water body. Status Update March 2013 Progressing Modelling for 6.18 & 6.24 to be incorporated into Gorleston to Lowestoft Study. Modelling for 6.04 included in Cromer to Winterton Management Plan. Monitoring to be completed in action EA/01. Progressing Investigations to take place for 6.18; 6.20; 6.22; 6.23 as part of Gorleston to Lowestoft Study. Progressing Cromer to Winterton Study will provide some information to help assess life expectancy of SPZs identifieid. Broads IDB are currently carrying out research into managing ochre and salinity in the Brograve area with Natural England & Broads Authority. Progressing Cromer to Winterton Management Plan will assist in gaining a greater understanding of the short to medium term Hold the Line policy at Mundesley. Norfolk Rivers Trust Catchment Restoration Project may assit, to be investigated. Not determined Not determined Not determined Not determined Appendix 1.a SMP Action Monitor Page 1 Shoreline Management Plan 6 Action Plan for web April 2013.xls 6.11, 6.13 WFD/05 Various All WFD/06 N/A 6.08, 6.10, 6.11. 6.13, 6.15, 6.16, 6.17 HRA/01 Various 6.13 HRA/02 Eccles to Winterton Beach Road 6.13 HRA/03 Eccles to Winterton Beach Road NA HRA/04 NA Research into potential implications of SMP managed realignment policies in units 6.11 and possibly 6.13 for various freshwater bodies and Protected Areas, specifically East Ruston Stream, New Cut, River Thurne, Hickling Broad, Horsey Mere, Martham Broad and the associated Broads Protected Areas. Monitoring to support climate change adaptation need EA, NNDC Undertake monitoring to provide a baseline for the assessment of the potential effects of the SMP policies, and natural changes, on sites of international importance for To model the likely habitat changes in The Broads as a result of the possibility that the policy could change to managed realignment in the long term, if holding the line is no longer sustainable. Undertake assessment work to identify the options for habitat compensation for 6.13 and other conditional policies. Liaison with Joint Nature Conservation Committee, Defra and EC {European Commission?] to define/agree what constitutes habitat compensation. NNDC/EA On hold Cromer to Winterton Management Plan will assist in gaining a greater understanding of the sustainability of the policies for this frontage and therefore assist in understanding potential future implications. Link monitoring and investigations with actions from HRA/01 & HRA/02. Broads IDB are currently carrying out research into managing ochre and salinity in the Brograve area with Natural England & Broads Authority. Progressing See EA/01 monitoring programme. On Hold EA lidar and infra red surveys collected in coastal zone to provide habitat area and changes data. Methodology and funding required to progress action. On hold Methodology and funding required to progress action. On hold Methodology and funding required to progress action. On hold Linked to the conditionality of PU 6.13, therefore not required to be completed in the short term, but to be kept under review. Not determined EA Not determined Not determined EA, NNDC Not determined EA, NNDC Not determined NE Not determined Appendix 1.a SMP Action Monitor Page 2