Shoreline Management Plan 6 Action Plan Update 2014 Policy Policy Unit Action

advertisement
Shoreline Management Plan 6 Action Plan Update 2014
Cancelled Actions (All Policy Units)
Policy
Unit
6.13
Policy Unit
Name
Eccles to
Winterton
Beach
Road
Action
Reference
EA/02
Action Description
6.09 6.12
Mundesley
to Eccles
NNDC/12
6.08 6.11
Mundesley
- Ostend
NNDC/13
6.21
Hopton to
Corton
WDC/08
Removal of
groynes and
revetment as they
become a health
and safety
problem.
Maintain defences
in the absence of
an adaptation
strategy.
Implement agreed
solution for the
management/remo
val of the RAF
Hopton bunker.
Monitor Eccles to
Winterton beach
recharge materials
for shell fragments
to ensure low
levels of calcium
are present to
prevent negative
impacts on dune
habitats.
Lead
Organisation
EA
Implementation
Date
Most likely
Sept-14
Status
Update 2014
Cancelled
NNDC
Not determined
Cancelled
This is
completed
through the EA
monitoring
programme see EA/ 01 and
through the
implementation
of the beach
recharge
scheme EA/04.
CANCELLED Combined with
NNDC/ 09.
NNDC
Ongoing
Cancelled
CANCELLED Combined with
NNDC/ 10.
WDC
TBC
Cancelled
CANCELLED don’t know what
action will be
required from
the Gorleston to
Lowestoft Study.
1
6.21
Hopton to
Corton
WDC/09
6.20 6.22
Hopton to
Corton
WDC/01
6.20 6.22
Hopton to
Corton
WDC/03
6.20 6.22
Hopton to
Corton
WDC/01
6.20 6.22
Hopton to
Corton
WDC/03
Manage defences
to improve public
safety and amenity
through
appropriate
removal of
redundant
defences.
Community
engagement
regarding coastal
change and
adaptation
A project appraisal
report for Corton
and Hopton will
need to be
developed in order
to progress the
management of
defences.
Community
engagement
regarding coastal
change and
adaptation
A project appraisal
report for Corton
and Hopton will
need to be
developed in order
to progress the
management of
WDC
TBC
Cancelled
CANCELLED don’t know what
action will be
required from
the Gorleston to
Lowestoft Study.
WDC
TBC
Cancelled
CANCELLED Amalgamated
into G/ 15.
WDC
TBC
Cancelled
CANCELLED don’t know what
action will be
required from
the Gorleston to
Lowestoft Study.
WDC
TBC
Cancelled
CANCELLED Amalgamated
into G/ 15.
WDC
TBC
Cancelled
CANCELLED don’t know what
action will be
required from
the Gorleston to
Lowestoft Study.
2
defences.
6.23
Corton to
Lowestoft
WDC/06
6.20 6.24
Hopton to
Lowestoft
North (to
Ness
point)
Hopton to
Lowestoft
North (to
Ness
point)
Lowestoft
North (to
Ness
Point)
WDC/14
6.20 6.24
6.24
Implement agreed WDC
solution for the
management of the
Eleni V oil burial
sites.
Review and update WDC
coastal asset
monitoring plan.
TBC
Cancelled
CANCEL Dependent on
WDC/ 05.
TBC
Cancelled
WDC/14
Review and update WDC
coastal asset
monitoring plan.
TBC
Cancelled
WDC/04
A project appraisal
report will need to
be developed in
order to progress
repair/removal of
defences.
TBC
Cancelled
CANCELLED as
part of routine
action of coastal
management
team.
CANCELLED as
part of routine
action of coastal
management
team.
CANCELLED don’t know what
action will be
required from
the Gorleston to
Lowestoft Study.
WDC
3
6.06,
6.08,
6.10 6.16,
6.19,
6.20,
6.22
Overstrand G/12
,
Mundesley
, Bacton
Gas
Terminal,
Caister-onSea,
Gorleston
to Hopton,
Corton
Develop consistent
medium to longterm plans for
relocation of
services and
facilities that will be
lost to erosion, e.g.
outfalls, highways
in line with Defra
Coastal Change
Policy and
resulting pathfinder
studies.
Local
Authorities/E
A with
service and
utilities
providers
4
Ongoing
Cancelled
CANCELLED Amalgamated
with G/ 03 & G/
10
Download