MANOR FARM CARAVAN SITE PROJECT INITIATION DOCUMENT North Norfolk Pathfinder Programme 2010 CONTENTS 1. Pathfinder Background 2. Introduction 3. Scope and overall approach 4. Project organisation 5. Project timescales 6. Project constraints 7. Project controls 8. Quality plan 9. Configuration 10. Reports to Defra 11. Appendices 1 1. Pathfinder Background In late 2004 North Norfolk District Council (NNDC) published the draft Kelling to Lowestoft Shoreline Management Plan. On much of the frontage it was proposed that there would be a change from a policy of defence to one of retreat or doing nothing. While in many respects this move reflected the reality that the North Norfolk coastline has been eroding for thousands of years, it was nevertheless not a change the Council and its communities found acceptable without there being some recognition of the consequences of such a policy change and the need for help in responding to the issues arising from coastal erosion. In the period since 2004 the Council has, with others, lobbied strongly for changes to the proposed arrangements. The outcome was the announcement by Government as part of the Comprehensive Spending Review 2007 of a Coastal Change (formerly Adaptation) Fund. This has been coupled with the publication in June 2009 of a draft Coastal Change Policy. At the same time as publishing this draft Coastal Change Policy the Government invited local authorities in whose areas coastal change and management was a significant issue to bid for funds to trial various approaches to coastal change. North Norfolk District Council submitted a bid under the Coastal Pathfinder Programme and was successful in securing £3 million to trial a number of projects. This project forms part of NNDC’s trial Pathfinder projects. 2 2. Introduction Manor Farm Caravan Park is close to the cliff edge and lies almost entirely within the area identified in the Shoreline Management Plan as at risk before the year 2025. It is reducing in size and this will in time affect the viability of the business. The threat to Manor Farm Caravan Park from coastal erosion was discussed at a community workshop held in September 2007, where people feared that the loss of the site would lead to the loss of “valuable holiday trade”. This element of the Pathfinder programme was therefore developed to manage the impacts of coastal change on a business that plays an important role in the economic (and social) vitality and viability of the Happisburgh community. The project focuses principally on identifying an alternative site and devising a process for facilitating the relocation to it, securing the necessary permissions and overcoming the obstacles. There may be impediments to achieving a solution that is in the community’s best interests (e.g. shortfall in funding, land values or land availability) with recommendations about how these could potentially be overcome. The project will therefore need to identify and analyse these issues, together with possible mechanisms to overcome them; perhaps comparing an ‘ideal’ outcome with the possible ‘pragmatic’ (compromised) outcome. As well as the obvious relationship with the other Happisburgh Pathfinder projects this project is closely linked with the Business support and advice package. Manor Farm Caravan Park, along with other businesses, should go through the business health check, take advantage of the specialist advice available and the support in developing a business plan. There is, however, a further specific fund available to enable this particular business to start to overcome at least some of the problems it is currently facing leading towards a long-term sustainable business solution. The total amount of support available to this business (including that delivered through the business advice and support project) cannot exceed the financial equivalent of €200,000 (in order to comply with ‘state aid’ rules. 3 3. Scope and Overall approach 2.1 Project Aims • (In conjunction with the Pathfinder Business Support Project) to identify options to enable the business to plan for its future and overcome obstacles to secure its long-term survival in the village • Develop and evaluate options for the relocation of the business to a suitable site close to the village • Develop an agreed plan for the relocation of the site If appropriate, within the time, budget and other constraints, assist with the implementation of the relocation of the park 2.2 Scope The project focuses principally on identifying an alternative site and devising a process for facilitating the relocation to it, securing the necessary permissions and overcoming the obstacles. Finding this longer-term solution, however, is likely to be complex and may involve processes that go far beyond the Pathfinder period. In this case the Pathfinder may also be able to provide assistance to help meet the needs of the business as an interim measure; this will include the development of a business plan, exploring the feasibility of the relocation plan, appraising the various options and developing a business case for the relocation over a longer time frame. It might also be able to support interim measures, such as temporary replacement of the vans most immanently on an adjacent field. 2.3 Approach The project will be lead by the NNDC Coastal Management Team with Rob Young, Coastal Planner as Project Officer. The owner of the Caravan Park will play a critical role in the development of a business plan and vision to pave the way for the business in the future. The Project Officer will work with the owner in investigating future options and delivering the support. The local community will be involved through the Happisburgh Project Liaison Group. It may be necessary as the project progresses to involve external specialists to provide advice and guidance on options or the implementation of the business plan. 2.4 Options To a large extent the options available will depend upon the desires of the business owner and the outcomes of the business support process, they will also be influenced to a large extent by the timescale. The key options are: a) to identify the most appropriate alternative site solution, develop a business case and secure the necessary consents in order for it to be implemented over a suitable time frame; b) to assist in implementing an interim solution (e.g. securing the necessary consents for a relocation of the static caravans at the cliff top front of the site and helping to meet some of the costs of physical works); or c) to identify the site which offers the best possible outcome for the whole community of Happisburgh and to take the necessary steps to overcome 4 any impediments to securing the relocation of the caravan park to that site (including consideration of the use of compulsory purchase powers). 2.5 Outcomes The project will have the following outcomes: • Initiate implementation of the Manor Farm Caravan Park Business Plan and enable the business to continue implementing the plan beyond the Pathfinder project. • If required by the business plan identify and implement a short term strategy to enable maintained numbers of holiday homes. • Enable the business owner to implement a long term relocation plan for the holiday park. • Maintain vibrancy of other local service businesses in Happisburgh through by maintaining continued viability of the caravan park. 5 4. Project Organisation 4.1 Project Structure The Project will co-ordinated as part of the Pathfinder programme of projects and will be structured as in figure 1. Figure 1. Manor Farm Caravan Park project structure PATHFINDER PROJECT BOARD (Programme management) PROJECT MANAGEMENT TEAM (Rob Young (Coastal Planner) & Rob Goodliffe (Programme Manager)) REFERENCE GROUP (Overseeing Project Development) HAPPISBURGH LIASON GROUP (Overseeing implementation of the project) 4.2 Roles and Responsibilities The owner of Manor Farm Caravan Park will play an essential role in the development and implementation of the project. The project can not develop or be implemented without the leadership and involvement of the caravan park owner. The programme Sponsor is Steve Blatch (Strategic Director, Community Services). The Project Board will be responsible for the overall management of the Manor Farm Caravan Park Project. It consists of officers and councillors, augmented by the Chair of the North Norfolk Business Forum. The reference and project liaison group will play key roles involving the community and will feedback to the Project Board through the pathfinder project team. For information regarding the Project Board and Reference Group please view the Programme Initiation Document. The Manor Farm Caravan Park Project Team will be formed consist of Rob Young (Coastal Planner) as Project Officer and will be supported by the Coastal Management Team. Administrative support will be provided by the Coastal Team Technical Administrative Assistant Marti Tipper. The function of the Project Team is to: 6 • oversee the delivery of the project and provide advice/ideas/input into the project and identify any challenges, issues, risks, lessons learned and costs; • ensure that the tasks identified within the project plan are carried out in accordance with the timetable of the project plan; • ensure the project communication is undertaken as identified in the Programme Communications Matrix and that any further methods are identified; • report progress to the Project Board. 4.3 Interfaces & Community Engagement All the North Norfolk pathfinder projects have been based on public engagement and this will be maintained throughout their implementation. The Communications and Community Engagement Strategy sets out how this will be achieved (see the Programme Initiation Document). Key engagement of the projects in Happisburgh will be public open days to be arranged at key points as the Happisburgh packages of projects are implemented. The Happisburgh Liaison Group will help to share information with residents to keep them updated. The table below summarises the communications required for this project as identified in the Pathfinder Programme communications matrix. Who will be informed NNDC Staff Council Members Project Board Project Team (Internal) Parish Council Reference Group Liaison Group Public Defra How The Briefing Newsletter Members Bulletin Coastal Management Board Coastal issues Forum Newsletter Meetings Meetings Via the Happisburgh Liaison Group and attending meeting where required. Meetings Documents and updates from the Project board Meetings Outlook Articles Pathfinder Newsletter Press articles Local newsletter articles Website Open days/Workshops Quarterly Reports Final Report 7 How Often Monthly Monthly At key stages During scheduled meetings Quarterly Monthly At scheduled meeting or if required Weekly Throughout the project. Minimum once per quarter Ongoing As often as required by the project and the group Quarterly Monthly At key stages When key information is required to be disseminated Updated Weekly At key stages April, July, October 2010, January 2011 June 2011 Who will be informed External government agencies, authorities, & professionals How Conferences/Events Meetings Workshops Periodicals Website Final Report How Often As required Ongoing June 2011 4.4 Dependencies The success of this project is dependent on: • • • the development of a Business Plan through the Pathfinder Business Advice Initiative. the identification and availability of a suitable site for relocation the ability to obtain planning consent to relocate the business Other dependencies between pathfinder projects include: • the possible need to record the existing site as part of the Heritage Project • the need to understand the timescales and what land may become vacant in the future to incorporate in to the cliff top enhancement scheme. 8 5. Project Plan 5.1 Project Timetable The project will progress as outlined in the figure 2. Figure 2 – Project timescales 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. Task Develop project approach Investigate availability, suitability and feasibility of alternative sites Investigate local opinion as to potential locations and issues this may create Manor Farm Caravan Park utilises the Business Advice Project to update/develop a Business Plan Identify and evaluate all the available options for the short, medium and long term Agree the preferred option and the draft process and timescales with the relevant parties Identify how NNDC and the Pathfinder can assist further in implementing the preferred option Test the preferred option with the local community Business owner to pursue the design and planning of the preferred scheme, together with the land acquisition, with appropriate assistance from the pathfinder Implementation of preferred scheme over an agreed timeframe Report to Defra Predicted timescale March – May 2010 April – June 2010 April 2010 May – August 2010 June- September 2010 August – September 2010 September 2010 October 2010 October – December 2010 January 2011 - onwards April – May 2011 5.2 Project plan The project plan will be created and updated using MS Project. The plan will detail all the tasks required to complete the project and will be used to forecast estimated timescales of project completion and aid in the allocation of resources. 9 6. Project Constraints 6.1 Time This project has a defined timeframe and must be completed or have funds committed by April 2011. 6.2 Personnel/contracts Officer time is limited due to other commitments beyond the Pathfinder programme. Bruton Knowles, property advisor and negotiator for NNDC during the pathfinder projects will be available to provide property advice and complete the tasks outlined in the tender brief. Bruton Knowles will also be able to complete additional schemes of work should the need arise, they accept and the funds are available. It may be necessary to engage with external specialists to provide some of the skills required to fulfil the project, this may include for example a planning agent. It will be necessary for other internal departments to assist in the delivery in the programme, particularly, Planning (including Planning Policy), Finance/Procurement, Corporate Monitoring and Communications. Additional internal assistance may be limited due to other commitments. 6.3 Finance The pathfinder projects have been allocated budgets to enable them to be planned and proceed. These allocations may be amended as projects progress. Due to the state aid rules the maximum budget which can be allocated to the Manor Farm Caravan Park Project is he €200,000. This value will be calculated on the exchange rate at the time of aid provision. To enable a budget to be allocated to the project a nominal sum based at an exchange rate of €0.8 to the £1, which calculates at £160,000. This figure will be mostly capital funding with a smaller element of revenue funding for some project management costs. 6.4 Legal Procurement must follow the NNDC Procurement Strategy. The Authority has the powers to acquire land for coastal protection works the under the Coast Protection Act 1949. However for this project these powers are not relevant. However under section 120 of the Local Government Act 1972 acquisition of land can be completed for the purposes of the benefit, improvement or development of their area. State aid rules limit the level of support which can be offered to Manor Farm Caravan Park, please see the information in section 6.2. Delegated authority has been granted by the cabinet of NNDC that the Chief Executive or Strategic Director (Communities) is able to procure works and services within the parameters set out in the Council’s Coastal Change Pathfinder applications. 10 It is necessary that all due processes within the council are followed, and should the project deviate from existing policies or conventions it will be assessed and the relevant action taken to ensure that there are no constitutional issues. One element which has arisen is the need for a Corporate Acquisitions Policy. 6.5 Planning Consent/Land Availability Planning consent will be required for any relocation. Discussions have taken place with the owner of the business, together with owners of alternative sites. Land is available for a wholesale relocation of the site (although some sites are known to be unavailable). No detailed studies have yet been undertaken to determine the feasibility of such a move; and their suitability in planning terms has not yet been fully tested. 6.6 Assumptions. It is assumed that Defra wish NNDC to complete the projects as we see fit as indicated by to the open nature of the funding offer. The Coastal Management Team also assumes the general support of the Authority and its departments as a whole in the project delivery. 11 6.7 Risks The following risks have been identified with the pathfinder project programme. The risk matrix can be viewed in Appendix C of the Programme Initiation Document. Ref 1 Date Logged Owner Title 1 18.05.10 RY Time 5 5 Inherent Risk (Likelihood x Impact) 25 2 18.05.10 RY Transparency 3 3 9 The business could be perceived to be favoured by other businesses in similar situations Manor farm will also be required to complete the business advice and planning initiative to ensure that there is a robust business plan for the relocation/adaptation. It must be clear that the manor Farm project has been highlighted as part of the package of measures in Happisburgh to tackle that communities needs. O 3 1 3 3 18.05.10 RY Land availability 4 5 20 No suitable land is available in the village for relocation or adaptation. This will be considered in the business plan and through investigations into the land suitability and availability. If this is the case the project or the parameters of the relocation may need to be considered. O 2 5 10 = Likelihood Impact Low 12 Description Summary of Actions/Mitigation Status The limited timescale of the pathfinders will not enable a full relocation of the park. Provide support to enable the relocation planning and facilitate the relocation to happen over the longer term and the enable the business to adapt in the short term. → 5 Subsequent Likelihood Impact Residual Risk O 1 5 5 = High 7. Project Controls 7.1 Management The project will be documented with the following; project initiation document, project plan, ongoing issues log, quality log, lessons learned log and change log as required. The project initiation document will be agreed by the Project Board. The board will be updated during each stage of the project and will make decisions at key points and advise in the project direction. When ‘exceptions’ occur which require a decision to be made urgently by the project board, information will be circulated via email to members of the Board. The discussions and decision will be recorded in the emails and resolution must be met in a maximum of 5 working days. The minutes of the Liaison Group will be assessed by the Programme Manager and action taken as required. The minutes will be circulated prior to Board meetings and made available to the Reference Group. Bruton Knowles will meet with NNDC on a monthly basis whereby a monthly report will be submitted identifying progress, issues and any other relevant information. 6.2 Financial The project must not exceed the total budget of €200,000 9capital) and Manor Farm Caravan Park must not receive greater than this sum over a three year period. The accounts will be monitored monthly following a report from the Accounts Team by the Programme Manager and reported back to the board. Should the project have an expected under spend of 10% or if there is any predicted overspend, it will be reported to the board. 7. Quality Plan The quality log will include the meetings for the Liaison Group and reports of each of the public open days. Where the quality check reveals the project is off specification or feedback suggest the scope of the project may need amending, the project team with the programme manager will investigate the options and present to the Project Board agree the most appropriate action. The monthly financial report/check and scheduled re assessment of risks and issues logs will be completed prior to Project board meetings. 8. Miscellaneous 8.1 Document Versions Project documents will be saved in the pathfinder folders M:\File System\Pathfinder Programme\Projects\Infrastructure Package\Trimingham village hall of the coastal management section and documents will carry in their title the creation/amendment date to enable current versions to be easily identified. 8.2 Meeting Minutes Meetings will be concisely recorded with Actions, Decisions and Issues highlighted where appropriate. 13 9. Defra Reports The project will be reported quarterly from April 2010 to Defra on the proforma provided. Report will be produced for the end of the month in: • • • • • April 2010 July 2010 October 2010 January 2011 April 2011 14