Cabinet 14 February 2011 Agenda Item No_____15________ INSTALLATION OF PHOTOVOLTAIC PANELS AT VICTORY LEISURE CENTRE Summary: This report contains a business case for installing photo-voltaic panels on the roof of Victory Leisure Centre. Conclusions: Recommendations: There are two options for Members to consider in relation to the level of capital investment required to take forward such a scheme. The financial implications of both schemes have been fully evaluated and the larger scheme would deliver a better return on the investment and secure more revenue savings in the medium to long term. However neither option is without risk, particularly in relation to the future of the FIT scheme over a 25 year period, and the financial returns are not significant. In the early years of the scheme the revenue impact would be cost neutral and clearly this would be an iconic project for North Norfolk in shifting some of our energy consumption to sustainable sources over a period of time which is likely to see large price rises. Cabinet are asked to consider whether they would wish to proceed with the scheme and to consider the two options as outlined within the report. Cabinet member(s): Ward(s) affected: Eric Seward All Helen Dixon, 01263 516271 Helen.dixon@north-norfolk.gov.uk Contact Officer, telephone number, and e-mail: 1. Introduction/background At Cabinet on 10 January 2011 members requested that a business case be prepared for the above proposed capital project. This can be found below and has been completed according to the Council’s Guide to Project Management; this project is classed as a medium-sized project in the above guidance. 2. The Project Proposal Department / Service (leading) Environmental Health Head of Service Nick Baker Project Manager Helen Dixon (until external Project Manager appointed) Cabinet Project Sponsor Project Scope Summary of what the project will cover / include (and perhaps clarification of what it does not include.) 14 February 2011 Nick Baker Installation of photo voltaic panels on the roof of the Victory Leisure Centre and claim the Feed in Tariff for the electricity generated by the panels: 1. Write project specification. 2. Carry out building survey. 3. Appoint external project manager. 4. Apply for planning permission and permission to connect to the national grid 5. Agree return of cost savings from energy bills with DC Leisure. 6. Procure equipment (OGC framework or EU tender process). 7. Install panels. 8. Register for, and claim Feed In Tariff. Two different size panel options are available and considered in this document: 46.5kWp 99.9kWp Objectives and Outcomes What corporate objectives does this project seek to deliver? Have you considered sustainability? Financial benefits What financial benefits should be obtained on completion of this project? Environmental sustainability and biodiversity: We will lead the district by example in promoting environmental sustainability through a range of actions including reducing carbon emissions...and achieve these aims by better management of our own property, and through policy development. YES Have you considered the equality impact? YES Claiming the Feed in Tariff will generate income for the Council over the 25 year lifetime of the tariff in 2 ways: 1. Generation payment per kW electricity generated 2. DC Leisure will also save money on their electricity bills; by using the electricity generated by the panels they will need to buy less from their grid supplier. An agreement with DC Leisure will need to be put in place so that these cost savings are passed onto the Council. The exact benefits will depend on which size option is chosen. Details of both options are presented in the Business Case below. Cabinet Other benefits What else will this project help to achieve? 14 February 2011 The Council will reduce its carbon footprint through consuming less grid electricity. Again, the exact benefits will depend on which size option is chosen. Details of both options are presented in the Business Case below. Will this project involve any other internal service? YES Will this project involve any other external body or persons? YES If Yes list them here FIT provider. Property Services. Development Control. Leisure and Cultural Services. DC Leisure. External project manager. Supplier and installer of panels. Distribution Network Operator. Cost How much will this project cost to complete? Give breakdown of costs as much as possible including final £. Resources What or who is essential to the success of this project? £10k or under? £10 £50k £50k £100k Over £100k Y Please see table in section 3.5 Does this include internal staff time costs or backfill? N Does this include Venues, refreshments, meeting costs? Y Does this include costs incurred by other services? N Does this include Communication and correspondence costs? Y Does this cost include any ICT upgrades/changes? N Does this include equipment costs? Y Appointing an external project manager to oversee the project. Contract manager at NNDC. Agreement with DC Leisure regarding cost savings from electricity bills. Gaining planning permission and permission to connect to the national grid. Installation of panels before 31.03.12 Cabinet Timescales When do you anticipate this project would start and finish? List any key milestones. 14 February 2011 Start Feb 2011, Finish March 2012. Feb 2011 – write specification for Project Manager and obtain quotes for project management. - obtain building survey to confirm weight of panels can be supported by roof March 2011 – appoint project manager. April – Apply for planning permission - Submit G59 application (permission to connect to the national grid) May – start procurement process. August – appoint successful contractor. Sept - Jan 2012 – install panels. Feb – contact FIT provider and register for FIT. 2.1 Individual Project Risks: Risk Causes Impact Likelihood (1=lowest, 5=highest) Diminished return on investment System failures Timescales slip (e.g. due to supply chain shortages, EU procurement process, FIT registration process) Failure of inverters Unable to claim highest FIT if system not installed by 31.03.12 Additional cost of replacement 4 3 4 5 Project manager needs to be appointed, EU tender procurement / OGC framework process followed and agreement with DCL on savings from electricity bills Inverters expected to fail after 10 years Risk score Mitigation 16 Employ project manager to oversee project. HIGH Ensure penalties in all contracts if slippage. Install <50kWp system to reduce time taken for FIT registration process. 15 HIGH Ensure long warranty. Hold stock of spare inverters. Cost of replacement inverters included in Cabinet 14 February 2011 ROI. Diminished return on investment Increased attractiveness of other investments Other investments would bring better ROI than PV 3 Diminished return on investment Diminishing yield with age of panel Reduced income 1 Unable to agree payback from lower bills with DC Leisure Unable to agree on payback of bill savings with DC Leisure Generate less revenue from bill savings 4 Roof unable to take weight of panels Structure of building Loss of income 4 Diminished return on investment Reduction or loss of FIT payment Loss of guaranteed payments affect ROI 3 5 Few investments currently delivering high rate of return Yield expected to drop off after 15-20 yrs 1 9 MED 5 LOW 4 LOW 4 1 1 New steelframed building, with known construction detailing Coalition gov appears to support FITs; scheme is part of Act of parliament. 4 LOW 4 LOW Compare against other potential investments – see section 3.5 Ensure warranty guarantees at least 80% rated performance at end of period. Involve DCL from start. Acknowledge there will be some disruption and compensate accordingly Get structural engineer to confirm roof can take weight of panels. Ensure installed by 31.03.12 to protect grandfather rights. Scheme will be reviewed in 2013 in favour of most cost effective technologies. System failures Failure of solar panel Loss or reduced income 3 Diminished return on investment Yield reduced through dust and debris Reduced income 3 Theft and Failure/loss of Loss of income / 2 1 1 1 Solar panels rarely fail Panels generally self cleaning by rain if installed at correct tilt Access to roof 3 LOW 3 LOW 3 Ensure long warranty. Ensure annual cleaning maintenance contract included in ROI calculations. No action Cabinet 14 February 2011 vandalism panels cost of repair/replacement Poor solar yield Excessive cloud cover Lower energy output and FIT payment difficult 1 2 Weather trends suggest this is unlikely LOW 2 LOW required. Yields estimated by suppliers have been checked using EST cash back calculator and most conservative used. 3. Business Case 3.1 Background In April 2010 the government introduce a new Feed In tariff (FIT) scheme to financially incentivise the installation of micro-renewable technologies, such as photo voltaic panels. Those eligible to receive the FIT will financially benefit in 3 ways: • Generation tariff – a set rate paid by the energy supplier for each unit (or kWh) of electricity generated. This rate will change each year for new entrants to the scheme (except for the first 2 years), but once you join you will continue on the same tariff for 20 years, or 25 years in the case of solar electricity (PV). • Export tariff - you will receive a further 3p/kWh from your energy supplier for each unit you export back to the electricity grid, that is when it isn’t used on site. The export rate is the same for all technologies. We have not assumed any income from the export tariff as it is anticipated that Victory will use all the electricity generated by the panels. • Energy bill savings – Cost savings on Victory’s electricity bills will be made, because generating electricity to power the centre means DC Leisure won’t have to buy as much electricity from their grid supplier. The amount saved will vary depending how much of the electricity is used on site. The Sustainability Coordinator raised the potential income at the 21 July Environmental Sustainability Board, who requested that further information be sought on potential costs and revenue. The Sustainability Coordinator sent a quote to 6 local companies for PV panels on the Cromer office and Victory Leisure Centre. Two quotes were received in October 2010 from RenEnergy and Mosscliff Environmental. The RenEnergy quotes for two different sized panel options at Victory are considered in this document. 3.2 Why the Project is Needed The key benefits of the project are: • To generate revenue for the Council over the next 25 years. • To reduce the CO2 emissions generated by the Council over the next 25 years. The project contributes to the Council’s corporate environmental sustainability objective, its Environmental Policy and Strategy and the CO2 reduction target in its Carbon Management Plan. Cabinet 14 February 2011 3.3 Benefits (over 25 year FIT tariff lifetime) 3.3.1 CO2 emissions savings The amount of renewable electricity used by the buildings will be metered and the corresponding CO2 emission saving will be calculated and reported annually. 46.5kWp 99.9kWp Predicted annual CO2 emission saving 20 42 % Council’s CO2 reduction target (to March 2014) 3.2% 6.6% Predicted CO2 savings over 25 years 500 1,050 It should be noted that on a cost per tonne of CO2 saved this project does not represent the best value for money, compared to other projects in the Carbon Management Plan. 3.3.2 Cost savings on electricity bills Once installed DC Leisure will be able to use the ‘free’ electricity generated by the panels during the day and will therefore need to use less grid electricity, resulting in lower bills. The amount of electricity generated will depend on the size of the panels chosen. The Council will need to negotiate an agreement with DC Leisure to ensure that the financial savings gained are passed onto the Council. This could be through a variation to the contract or a separate legal agreement. A cost of 9p per kWh for grid electricity has been assumed in the table below. The net surplus assuming no agreement can be made with DC Leisure can be found in Appendix Q, please note that there is a low risk of this scenario occurring. 3.3.3 Income from Feed in Tariff If the panels are installed and the FIT provider notified by 31.03.12 we would be able to claim the highest rate of feed in tariff which is 31.4p per kW of electricity generated, this has been assumed in the table below. If we miss this deadline then the tariff rate drops to 28.7p per kW, the revised net surplus in this scenario can be found in Appendix Q. Estimates of the amount of electricity likely to be generated have been provided by the supplier and checked with the EST online calculator. 3.4 Benefits realisation 3.4.1 CO2 emissions savings These would start immediately the panels start to generate electricity and would be calculated annually as part of the Carbon footprinting work undertaken by the Sustainability Team to measure our progress towards the corporate CO2 reduction target. 3.4.2 Cost savings on electricity bills DC Leisure is billed monthly by their supplier and so we would want the agreement referred to above to provide a monthly payment to the Council. This would be calculated from the amount of electricity generated by the panels in kW (as recorded by the generation meter onsite) multiplied by the cost saving to DC Leisure in pence per kW. 3.4.3 Income from Feed in Tariff This would start when we submit our first 3 months of generation meter readings to the FIT supplier. Payments will normally be made on a quarterly basis in arrears. 3.5 Implications for NNDC budgets Cabinet 14 February 2011 The table below shows a summary of the capital and revenue implications of each of the proposed schemes. Please note that the annual revenue savings figure shown is the average over the life of the 25 year scheme, the actual anticipated budget movements can be found within Appendix R for the 46.5kWp scheme and Appendix S for the 99.9kWp scheme. The full detail of the costs contained within the table below can be found in Appendix Q. Summary of capital and revenue costs over the 25 year life of the project 46.5kWp 99.9kWp £ £ Equipment costs 154,042 307,750 Cost of support frame for panels 17,000 34,116 Labour costs 28,820 33,300 Planning application fee 170 170 Project management 20,003 37,534 Replacement inverters 30,000 60,000 Install costs for inverters 3,000 6,000 Total capital cost 253,035 478,870 Lost investment income 54,015 14,109 Supplier maintenance costs 61,484 61,484 Building maintenance costs 12,500 25,000 Feed in tariff (FIT) (308,093) (642,300) Energy saving (156,065) (325,358) Total (saving)/cost over scheme life (83,124) (388,195) Average annual revenue budget (saving)/cost (3,325) (15,528) Capital Revenue Less: Based on the estimated capital costs the return on investment (ROI) for the 46.5kWp scheme is 1.31% (£3,325/£253,035 x 100), while the ROI for the larger 99.9kWp scheme is 3.24% (£15,528/£478,870 x 100). Trying to estimate the average rate of return for investments over the next 25 years is incredibly difficult but if an average return rate of 5% is assumed, if the capital funds were left in the bank rather than being invested in this scheme the interest would amount to £12,652 (£253,035 x 5%) per annum (£316,300 over 25 years) for the 46.5kWp scheme and £23,944 (£478,870 x 5%) per annum (£598,600 over 25 years) for the 99.9kWp scheme. Cabinet 14 February 2011 This information is summarised in the table below: Comparison between rate of return from proposed PV scheme and investment returns 46.5kWp 99.9kWp £ £ Total return from installing PV panels as per above (83,124) (388,195) Investment return @ 5% (316,300) (598,600) Difference 233,176 210,405 These figures differ from the actual lost investment income detailed in the table above due to the cash flows in and out each year. One of the project risks, as highlighted within the risk section of the report, is that the scheme cannot be formerly registered by 31 March 2012, which would mean that rather than receiving 31.4p per kWp the Council would only receive 28.7p per kWp. The impact of this is highlighted within Appendix Q but the effect would be to reduce the FIT income received over the life of the project by approximately £54,000 for the larger 99.9 kWp scheme and £26,000 for the 46.5kWp scheme, which increases the payback period for both schemes. This Appendix also looks at the impact of DC Leisure not agreeing to pass on the energy savings along with some sensitivity analysis regarding the assumptions made in relation to both the amount of energy produced and the levels of energy savings. If the scheme were to be approved in principle there is a risk that there may be abortive costs, as a G59 application needs to be made to have the scheme approved and to gain permission to connect to the national grid. If, for whatever reason, this application is refused then the scheme would not be able to go ahead as the Council would not be able to access the FIT income, which would make the scheme unviable. These costs would not however be expected to exceed £15,000. 3.5 Project Definition 3.5.1 Project deliverables External project manager appointed to manage project. Agreement in place with DC Leisure regarding return of cost savings from electricity bills. Planning permission and permission to connect to the national grid secured. PV panels procured and installed. Registration for FIT and collection of payment. 3.5.2 Constraints The timescale required to claim the highest FIT rate is the main constraint: The panels need to be in place and we need to have registered with a FIT provider by 31.3.12. Given the time required to write a specification and appoint an external project manager, and then the likely planning permission, procurement and installation timescale, a decision needs to be made immediately as to whether this project will be taken forward or not if the highest return on investment is to be achieved. Cabinet 14 February 2011 3.6 Resource requirements In addition to the costs detailed in the project proposal, officer time to write the specification, appoint and manage the project manager will be required. This can be accommodated into the Sustainability Coordinator’s work plan as required. 3.7 Costs/timescales It is anticipated that all costs detailed in the project plan above would be incurred in financial year 2011 – 12 apart from the following: • Maintenance • Replacement Inverters (including installation) • Additional building maintenance 3.8 Risks Please section 2.1 for details of risks. 4. Other Implications and Risks 4.1 Legal There are no legal implications arising from this report. 4.2 Sustainability and reputation Installing photovoltaic panels at Victory Leisure Centre will contribute to our corporate aim of becoming an environmentally sustainable council, however as mentioned in section 3.3.1 the actual CO2 savings are relatively small in terms of the overall cost of the project. 4.3 Equality and diversity There are no equality and diversity issues arising as a result of this project. 5. Conclusions There are two options for Members to consider in relation to the level of capital investment required to take forward such a scheme. The financial implications of both schemes have been fully evaluated and the larger scheme would deliver a better return on the investment and secure more revenue savings in the medium to long term. However neither option is without risk, particularly in relation to the future of the FIT scheme over a 25 year period, and the financial returns are not significant. In the early years of the scheme the revenue impact would be cost neutral and clearly this would be an iconic project for North Norfolk in shifting some of our energy consumption to sustainable sources over a period of time which is likely to see large price rises. 6. Recommendations Cabinet are asked to consider whether they would wish to proceed with the scheme and to consider the two options as outlined within the report. Cabinet 14 February 2011