Audit Committee 18 September 2012 Agenda Item No_____10________ Progress Report on Internal Audit Activity, April to September 2012 Summary: This report examines progress made between April and early September 2012 in relation to delivery of the Annual Audit Plan for 2012/13, and includes abbreviated management summaries in respect of the audit reviews which have been finalised in the course of this period. Conclusions: Adequate assurance levels have been awarded in respect of the three audits completed in the first five months of the financial year. It is further noted that the Annual Audit Plan has been subject to some rescheduling of assignments (the timing of 5 of the original 16 assignments featuring in the Plan have been revised), whilst job budgets for 3 reviews have been adapted to accommodate changes to audit scopes – all revisions were at the request of management. The Plan has also now been expanded to incorporate an additional audit of the new Revenues and Benefits Shared Services Partnership focusing on Data Transfer, Governance and Risk. Following discussions with management, this work is to be delivered in two phases. Phase 1 has already been undertaken and an audit letter was produced in July 2012 commenting on the data transfer arrangements. To date, we have been able to absorb the above changes to the Plan without any adverse impact on our ability to deliver all assignments within the financial year and hereby confirm that we are on schedule as we approach the half yearly stage. Recommendations: It is recommended that the Committee notes the outcomes of the three audits completed between April and August, together with recent amendments made to the Annual Audit Plan for 2012/13. Cabinet member(s): All All Wards: Contact Officer, telephone number, and e-mail: Sandra King, Head of Internal Audit 01508 533863 scking@s-norfolk.gov.uk Audit Committee 18 September 2012 1. Background 1.1 The Annual Internal Audit Plan was approved by the Audit Committee on 6 March 2012. This report represents the first progress update on the Annual Audit Plan for 2012/13. 2. Amendments to the Annual Audit Plan 2.1 Following our previous report to the Committee in March, some changes to the Plan have occurred, all of which were initiated by management. The key changes to planned provisions have involved: 2.2 • Expansion of the Property Services audit to include extra focus on the Measured Term Contract for the provision of coastal repairs and other minor coastal works, which led to the job budget being increased from 14 to 19 days to afford coverage of this additional element. • In the course of formulating the 2012/13 Audit Plan in February 2012, the Corporate Leadership Team requested that an audit be developed to examine data verification and governance arrangements applying to the newly formed Revenues and Benefits Shared Services Partnership between North Norfolk District Council and the Borough Council of Kings Lynn and West Norfolk. Although the Audit Strategy for 2012/13 alluded to this fact, the Annual Plan approved by the Audit Committee in March 2012 did not contain specific provisions as such to undertake such an audit. As a result of meetings with management in April 2012, there has since been agreement to carry out this work by way of two phases. A budget of 14 days has been provided and so far, Phase 1 completed in July 2012 has utilised 2.5 days of those made available for this purpose. We envisage the second phase will be performed in September / October 2012. • The Corporate Leadership Team had further sought to reduce the job budgets in relation to 2 computer audits, namely reviews of the Cash Receipting Application and the Council’s IT Project Management arrangements. Having revisited the scopes of these two pieces of work, we have been able to commute the job budgets and still ensure that assurances can be produced, tailored to management’s specific requirements. • It has also proved necessary to re-schedule some of our assignments in order to secure maximum benefit from audit input and minimise disruption to service areas. The re-timetabling of planned work is noted in Appendix B to this report. The resultant revisions to the Plan have led to a 14 day increase overall in the total audit days to be delivered in 2012/13. The Audit Committee had approved 212 days in March 2012, whereas this figure has since risen to 226 days. Audit Committee 18 September 2012 3. Delivery of Programmed Audit Work in accordance with the Revised Annual Audit Plan 3.1 As demonstrated in Appendix B, 80 days of programmed work had been completed at the time of writing this report. This figure equates to 35% of the revised audit planned days earmarked for completion in 2012/13. The status of individual audits can be summarised thus: • Three assignments have been completed and final reports issued (Audit Nos. NN/13/01, NN/13/02 and NN/13/03); • A draft report has been provided in relation to Audit No. NN/13/15 and management responses are currently awaited; • The audit fieldwork has been completed for 3 additional audits (Audit Nos. NN/13/04, NN/13/13 and NN/13/14) with corresponding draft reports imminent. • We have circulated the audit brief for Audit No. NN/1306 and should be commencing audit fieldwork shortly. • An ad-hoc review (Audit No. NN/13/17) has also been requested by the Corporate Management Team, which is being carried out in two stages. To date, Phase 1 has been finalised with an audit letter produced and circulated. 4. Outcomes of Work Undertaken 4.1 With reference to work completed between April and early September 2012, as mentioned above, we have been able to finalise three audits during this period and their respective management summaries are attached at Appendix C to the report. 4.2 In the case of the Property Services & Coastal Protection audit (Audit No. NN/13/01) and the Strategic Housing & Homelessness review (Audit No. NN/13/02), we were able to confirm that the adequate assurance levels awarded this year were consistent with the audit opinions provided the last time these areas were examined. In relation to the audit of Corporate Policy, Planning and Performance Management (Audit No. NN/13/03), this was the first time that we had analysed operational arrangements and it is pleasing to note that we were able to give an adequate assurance level to the provisions in place. 4.3 With reference to the additional audit commissioned by the Corporate Leadership Team applying to the Revenues and Benefits area, when carrying out Phase 1, we examined data transfer developments, in particular conducting verification checks on the accuracy and adequacy of the data transfer from the existing North Norfolk District Council Civica Revenues and Benefits System to a new OpenRevenues (Civica) platform, which in the future will be used jointly as part of the overall partnership arrangements. Although our audit comprised high level verification of systems totals and did not include looking at individual accounts / account balances, we have been able to conclude that: • Data integrity checks have been applied to all systems parameters appearing on Civica with any discrepancies fully investigated. Audit Committee 18 September 2012 • Data integrity checks have been applied to all systems parameters following transfer of North Norfolk District Council data to the OpenRevenues system, before going live, with any discrepancies fully investigated. • Aged debt balances should be agreed between North Norfolk District Council and the Borough Council of Kings Lynn and West Norfolk before transfer of data as part of the former merger. • Documentary evidence should be retained in support of all integrity checks, including evidence of independent check and agreement of outcomes from both North Norfolk District Council and the Borough Council of Kings Lynn and West Norfolk. • The Steering Group should sign off all agreed balances. We are intending as part of our work in relation to Phase 2 to evaluate the status of the Partnership, including governance arrangements and an overview of IT provisions. The Phase 1 letter was issued to management in July 2012. 5. Conclusion 5.1 Good progress has been made with the delivery of the Audit Plan to date, and all current work scheduled is underway as expected. 6. Recommendation 6.1 That members note the outcomes of the three completed audits and the recent amendments made to the Annual Audit Plan for 2012/13. Appendices attached to this report: Appendix B – Review Work delivered in accordance with the Annual Audit Plan for 2012/13 plus Ad-Hoc Work requested by Management Appendix C – Abbreviated Management Summaries of Completed Audit Assignments Appendix C (1) NN/13/01 Property Services and Coastal Protection Appendix C (2) NN/13/02 Strategic Housing and Homelessness Appendix C (3) NN/13/03 Corporate Policy, Planning and Performance Management