Audit Committee 8 March 2011 Agenda Item No___11__________ Progress Report on Internal Audit Activity, 23 November 2010 – 15 February 2011 Summary: This report provides the Audit Committee with an update on current progress achieved in relation to the delivery of the Annual Audit Plan for 2010/11, following on from previous reports presented in September and December 2010. In line with our terms of reference, this report provides a brief summary of the audit work completed at this stage together with further details of the performance and effectiveness of the Internal Audit function, whilst the remaining audit work to be completed within the Annual Audit Plan, will be presented alongside the Head of Internal Audit’s Annual Audit Opinion in June 2011. Conclusions: At this stage, 87% of planned work has been delivered for the year, culminating in the issue of 9 final audit reports. Of the other projects featuring in the Annual Audit Plan, it should be noted that a further final report is due to be issued shortly, two draft reports are under preparation, fieldwork relating to 3 reviews is in progress and an audit brief has been prepared for the 1 remaining assignment, with the fieldwork set to commence on 3 March 2011. An additional ad-hoc review requested by management has also been completed and subject to a final audit report – and this involved 3 extra days of audit input. Recommendations: It is recommended that the Committee notes the progress made in delivering the Annual Audit Plan. Cabinet member(s): Ward(s) affected: All All Sandra C King, Head of Internal Audit scking@s-norfolk.gov.uk 01508 533863 Contact Officer, telephone number, and e-mail: 1. Appendix A highlights the current progress made in delivering the Annual Audit Plan. At this stage, 87% of the total planned work we had expected to deliver in Audit Committee 8 March 2011 year is now completed; the only case where fieldwork is yet to be significantly progressed is in respect of the work to support the Annual Governance Statement audit. This audit is intentionally undertaken very late in the financial year to ensure that audit coverage is provided across the full year, and thus our work can most effectively support the Council’s External Auditors. Work on the remaining audit assignments is nearing completion. 2. This progress report follows on from those reports presented to the Committee in September and December 2010, which provided Management Summaries of those audits completed during the timeframes specified in the respective activity reports. Summaries pertaining to two additional audit assignments completed between November 2010 and February 2011 are included at Appendix B. It should also be noted that the key findings in respect of the Computer Audit Needs Assessment for the period 2011-12 to 2013-14 are referenced within the Annual and Strategic Audit Plans, also presented to the Committee today. The outcomes for the residual assignments – Council Tax and National Non Domestic Rates, Housing and Council Tax Benefits, the Waste Management Contract, Corporate Governance and Risk Management, Planning and Development Control, plus Work to Support the 2010/11 Annual Governance Statement, will be incorporated in the Head of Internal Audit’s Annual Report and Opinion in June 2011. 3. In addition to the two audit assignments completed since November 2010, Internal Audit has also undertaken an ad-hoc piece of work requested by management to review certain aspects of procurement processes within the Property Services Department. This audit generated two findings which related to deficiencies in the internal control environment. Given that the work was not performed with the intention of conducting a detailed systems review but instead to examine specific elements of working practices, it has not been feasible to award an overall assurance level with regards to this work. However, the main findings of our review are included for the Committee’s reference at Appendix C. Appendices attached to this report: Appendix A –Review of work delivered in accordance with the Annual Audit Plan for 2010-11, plus Ad-Hoc work requested by management Appendix B – Management Summaries in respect of completed audit assignments Appendix C – Findings arising from a review of specific processes in the Property Services Department