Appendix B(1) Management Summaries of Completed Audit Assignments Report No. NN/12/03 – Final Report issued 25 October 2011 Audit Report on Waste Management Audit Opinion Limited Assurance given Rationale supporting award of opinion The audit work carried out by Internal Audit indicated that: • Weaknesses in the system of internal controls are such as to put the client’s objectives at risk. • The level of non-compliance puts the client’s objectives at risk. • A number of weaknesses have been identified with the monitoring arrangements regarding the new Waste Management and Grounds Maintenance Contract, which has resulted in one high and six medium priority recommendations being raised. • The previous report (NN110 - Waste Management) issued in April 2011, was awarded Adequate Assurance with one medium priority recommendation having been raised. However, since the previous review focused on the arrangements for monitoring the previous contract, and the procurement of - and plans for monitoring the new contract, it is not deemed appropriate to provide a direction of travel indicator. Summary of Findings Contract Monitoring The contract between the Council and Kier for the provision of Environmental Services and Grounds Maintenance commenced on 1st April 2011. A summarised operation guide is in place, which outlines key performance indicators (KPIs) and high-level contract monitoring arrangements, this is being developed as the contract continues. The KPIs within the contract require revision in order to make them more meaningful in respect of the current working arrangements and to improve the management information. Payments to Kier have been appropriately authorised and are in line with contractual specifications. Variations have been authorised, although the Council and Kier are still determining whether these should be invoiced as they arise or on a quarterly basis. Income due to the Council for garden waste collections has not been paid over to the Council since the contract commenced on 1st April 2011. Due to initial issues, these charges were not issued to customers until June 2011. The Council is in the process of establishing reconciliation and recovery processes with Kier for this income on a monthly basis. There are also issues with reconciling income from bulky waste collections collected by Kier, which are also still under review. Control processes for receipt of grounds maintenance income require review, in particular bowling green leases and validating pitch and putting income. Issues remain with the interface between the Council’s M3 and Kier’s Whitespace waste management systems regarding the ability to confirm the accuracy of service activity by both parties. Data validation checks are still progressing to try to resolve the matter. A grounds maintenance visit schedule for 2011/12 inspections has not been established. Contractor meetings are being held and budget monitoring controls exist. The claim for reimbursement of mixed recyclable credits covering the period April-July 2011 had been promptly submitted to Norfolk County Council in August 2011. Whilst it was evident that recovery action was taking place in respect of trade waste customers, potential weaknesses exist through the absence of independent checking of recovery action as well as the inconsistent retention of supporting documentation. Performance Information Environmental Services performance indicators mirror the KPIs outlined within the Waste Management and Grounds Maintenance contract, although issues with the KPIs exist as previously stated. Issues with the data collection arrangements have been identified. Risk Management Risks have been identified by Environmental Services and will be subject to review in October 2011. Mitigation plans have been documented to reduce the impact and likelihood of risks identified. It must be noted that risks identified relate to the pre-Kier contract for Environmental Services. We have noted throughout audit testing that the key issues identified within this audit are being progressed and monitored (i.e. garden waste income recovery and system interfacing), hence no recommendation has been raised. The following number of recommendations has been raised: Adequacy and Effectiveness Assessments Area of Scope Adequacy of Controls Contract Monitoring Performance Information** Risk Management Total Effectiveness of Controls Recommendations Raised* Amber Amber High 1 Medium 6 Low 0 Green **Amber 0 0 0 Green Green 0 0 0 1 6 0 ** Recommendations have been raised within the ‘Contract Monitoring’ section which impact on the ‘Performance Information’ area of the audit. High Priority Recommendations We have raised one high priority recommendation as a result of this audit. This is in the following area: Contract Management – Garden Waste and Bulky Waste Income Process • All income due from Kier in respect of garden waste income since commencement of the contract on 1st April 2011 should be paid over to the Council as soon as practicable. The Council should also ensure it recovers all income for bulky waste collections since the transfer of responsibility for income collection (i.e. from 1st August 2011). Reconciliations for income should be undertaken on a monthly basis. Supporting records should be provided to the Council by Kier which clearly outline the payments received for garden and bulky waste collections, which should then be reconciled to M3 prior to raising an invoice to Kier for recovery of the income collected. • Written procedures should be produced and agreed by both parties for recovering and reconciling income relating to garden and bulky waste collections. Management Responses Management have accepted all recommendations raised. Appendix B(2) Report No. NN/12/05 – Final Report issued 2 November 2011 Audit Report on Accountancy Services Audit Opinion Adequate Assurance given Rationale supporting award of Opinion The audit work carried out by Internal Audit indicated that: • While there is a basically sound system of internal control, there are weaknesses, which may put some of the client’s objectives at risk. • There is evidence that the level of non-compliance with some of the control processes may put some of the client’s objectives at risk. • This opinion results from the fact that we have raised one medium and two low priority recommendations. • The system was previously audited in 2009/10 and was awarded ‘Adequate Assurance’ as a result of us having raised seven recommendations. Although there is evidence of improvement since the last review, the assurance level has remained the same. Hence the direction of travel is unchanged. Summary of Findings Treasury Management An approved Treasury Management Strategy is in place which meets the requirements of the CIPFA Code of Practice and the Prudential Code. A contract is in place with Arlingclose to provide the Council with support and guidance in respect of its Treasury Management activities. An approved counterparty list exists for assisting with decision making. However, in a couple of instances the decision to invest with particular institutions had not been formally documented. Both investments had been made with the most advantageous terms available and had been appropriately approved by Council officers Reconciliations are undertaken between records of investments and the general ledger and to bank statements. All key functions are segregated within the department. Fidelity insurance cover is provided for officers within the Council. Reports are provided to management and members on a six-monthly basis in line with the Treasury Management Strategy. Treasury management records are password protected and held within the Finance shared drive with restricted access. Control Accounts Policies and procedures exist for the completion of control account reconciliations. Control account reconciliations are undertaken on a monthly basis as verified through review of the payroll and the VAT control accounts. No issues of concern were noted. The suspense account was reviewed as part of a separate audit on Receipt, Handling and Banking of Remittances (NN1207) with no issues being raised. Banking Policies and procedures exist for administering the Council’s bank accounts. A bank mandate is in place to notify the bank of authorised signatories. Bank charges are checked and verified to the Council’s records. Bank Reconciliations Bank reconciliations are completed although issues were noted with regards their prompt completion and the absence of independent review in some cases. Asset Register Additions to and disposals from the asset register are correctly processed with supporting documentation retained. Assets are subject to revaluations on a rolling five year programme. The asset register is reconciled to the general ledger at year-end due to limited activity. Budgetary Control Budgets are set according to a timetable and are agreed with service heads prior to being reviewed and approved by Corporate Management Team, Cabinet and Full Council. Budgets are entered onto the general ledger and are reconciled to confirm accuracy. Budget monitoring reports are produced on a monthly basis with variances of +/- £2,000 requiring explanation / remedial action. However, we found that in a couple of cases, explanation / remedial action had not been recorded. Budget monitoring reports are produced for management and Members for periods four (July), six (September), nine (December) and ten (January) which provide updates on the status of the Council’s budget position. There is also formal ongoing monitoring between accountants and budget holders and the monitoring reports are further supplemented by the Revised and Base budget reports which are provided to Cabinet and Full Council. Journal Entries Journal transfers are completed in accordance with laid down procedures, including countersigning those over £100,000 by the Financial Services Manager/Acting Financial Services Manager. Appropriate documentation and audit trail exists to explain and support each journal. A wider issue over access rights to e-financials generally, referred to in the previous report on the work to support the annual governance statement (NN1113), remains outstanding. The Group Accountant had planned to undertake a review of all user access to e-financials by the end of May 2011. We established that a revised deadline has been set of 31st December 2011 for the review to be completed. Progress with this will be covered as part of the next audit of work to support the annual governance statement (NN1212) scheduled to be completed in February 2012 with an appropriate recommendation if the review has not been completed. Performance Information Performance / progress reports are provided to management and members in respect of treasury management activity and budget monitoring. There are no other reporting requirements pertaining to the areas under review. Risk Management The review of Corporate Governance and Risk Management (NN1111) identified issues with risk management throughout the Council. An exercise on developing risk management is being undertaken by the Interim Accountancy Services Manager and progress with this is being monitored through Internal Audit’s follow up arrangements on progress with outstanding recommendations. The following number of recommendations has been raised: Adequacy and Effectiveness Assessments Area of Scope Adequacy of Controls Effectiveness of Controls Treasury Management Control Accounts Banking Bank Reconciliations Asset Register Budgetary Control Journal Entries Performance Information Risk Management Green Amber** High 0 Medium 0 Low 1 Green Green 0 0 0 Green Green Green Amber 0 0 0 1 0 0 Green Green Green Amber 0 0 0 0 0 1 Green Green Green Green 0 0 0 0 0 0 Amber*** Amber*** 0 0 0 0 1 2 Total Recommendations Raised* **Includes one recommendation raised within area of Bank Reconciliations ***Refer to recommendations raised in audit NN1111 Corporate Governance and Risk Management High Priority Recommendations We have not raised any high priority recommendations as a result of this audit Management Responses Management have accepted all recommendations raised. Appendix B(3) Report No. NN/12/07- Final Report issued 4 November 2011 Audit Report on the Receipt, Handing and Banking of Remittances Audit Opinion Adequate Assurance given Rationale supporting award of Opinion The audit work carried out by Internal Audit indicated that: • While there is a basically sound system of internal control, there are weaknesses, which put some of the client’s objectives at risk. • There is evidence that the level of non-compliance with some of the control processes may put some of the client’s objectives at risk. • The level of assurance is based on the fact that three medium and two low priority recommendations have been raised. • The previous audited of Remittances (NN1015) was awarded an ‘Adequate Assurance’ opinion. Hence the direction of travel indicator remains unchanged. Summary of Findings Policies and Procedures Policies and procedures relating to remittances exist and are available to relevant staff. Payment methods are clearly notified to debtors. Insurances are in place to mitigate the loss of income relating to remittances. Physical Security Income received via the post room is opened in a secure environment before being logged and passed to another department for processing and banking. Access rights to the cash receipting system and telephone payment system is restricted to relevant officers. The Council still use Card Holder Not Present forms (CNP) for processing credit card payments as the current MOTO and telephone payment systems are not capable of adding surcharges. There is an inherent risk with recording card holder payment details for these payments, however no recommendation has been raised as the new cash receipting system (currently being tested) will make the use of CNP forms redundant. Segregation of duties exists in respect to receipt, handling and banking of remittances. However, we were unable to obtain evidence that staff in the Payments Control Team are required to declare any personal interests they may have in customer accounts. Receipting Controls exist over receipt of income through electronic means. Income is banked promptly. Unidentified payments are automatically posted to the suspense account and subsequently reallocated. Income from Tourist Information Centres (TICs) is reconciled to income records on a weekly basis, from review of receipting arrangements we identified that additional controls are required for TIC stock takes. The suspense account and TIC reconciliations are not currently subject to independent review. Posting of Income Income is posted promptly and accurately. Actual cheques requiring departmental authorisation before processing should not be passed to the relevant departments. Delays were also noted in processing these payments. Reconciling Income A recommendation was raised in NN1205 Accountancy Services audit for the monthly bank reconciliation to be undertaken in a timely manner. A monthly cash and deposits reconciliation is undertaken by the Exchequer Services section, although delays with their completion were identified and the reconciliation is not subject to independent review. Performance Information Performance indicators are in place for monitoring of TIC income. Despite this, performance information has not been monitored through the Council’s performance management system, TEN during 2011/12. Risk Management Risks have been identified under the Customer Services service area regarding remittances, in particular, in respect of implementing the new cash receipting system and the potential failure of the telephone payment system. Mitigating controls have been put in place to reduce the impact and likelihood of risks adversely affecting the Council’s objectives. The following number of recommendations has been raised: Adequacy and Effectiveness Assessments Area of Scope Adequacy of Controls Effectiveness of Controls Green Green High 0 Medium 0 Low 0 Amber Amber 0 1 0 Green Green Amber Amber 0 0 1 1 1 0 Green Amber** 0 0 0 Amber Green 0 0 1 Green Green 0 0 0 0 3 2 Policies and Procedures Physical Security Receipting Posting of Income Reconciling Income Performance Information Risk Management Total Recommendations Raised High Priority Recommendations We have not raised any high priority recommendations as a result of this audit Management Responses Management have accepted all recommendations raised.