REPORT ITEM 10 – DEVELOPMENT COMMITTEE 28 MAY 2015 (Marked “to follow” on the agenda) PUBLIC BUSINESS – ITEM FOR DECISION 10. SALTHOUSE – PF/2006/0642 AND PF/2006/0736 – APPLICATION FOR RELEASE OF SECTION 106 PLANNING AGREEMENT Purpose of this Report An application has been received to release this development from the requirement of the Section 106 agreement associated with planning permission granted in relation to the residential conversion of a group of barns at Bards Hill, Salthouse. The application relates to two specific requirements contained in the agreement: 1. The requirement for the developer to pay to the District Council the sum of £92,000 to be used for the provision of off-site affordable housing. The agreement required this sum to be paid in two tranches each of £46,000. The triggers for the payment were the sale of the third and sixth dwelling units 2. The requirement of the above clause to be binding on successors in title This report sets out the background to this agreement, and compares this with the Council’s current policy position, changes to the relevant legislation and the Government’s policy in current National Planning Guidance and makes recommendations as to the way forward. Planning History The relevant planning applications are as follows: 2006/0642- Conversion of Barn (described as “Plot 2”) to form dwelling. Planning permission was granted on 8 June 2006 2006/0736- Conversion of the remaining Barns to five dwellings. Planning permission was granted 15 February 2007, following the completion of the Section 106 agreement. Planning Application 2006/0736 was considered by the Development Committee on 22 June 2006, and was considered against the then-current Local Plan (the development plan in force prior to the North Norfolk Core Strategy). Although outside the development boundary for Salthouse and within the Norfolk Coast Area of Outstanding Natural Beauty and Conservation Area, the buildings were immediately adjacent to the adopted development boundary where the Local Plan policy then in force was supportive of their residential conversion. It was concluded that the site could only be developed under Local Plan policy 29: The Reuse and Adaptation of Buildings in the Countryside, subject to a contribution towards offsite affordable housing secured by a Section 106 agreement. The application was again reported to Development Committee on 20 July 2006 with a recommendation for delegated approval subject to resolution of affordable housing Development Committee 1 28 May 2015 issues, amended design details and the imposition of appropriate conditions. The application was approved on that basis and a Section 106 agreement completed on 8 February 2007. The key provisions were: To secure a developer contribution of £92,000 towards off-site affordable housing Payment in two tranches; £46,000 to be paid within 21 days of completion of the sale of the third and sixth units Agreement expressed to be binding on successors in title to the developers The developer had purchased the Barns and commenced the conversion works prior to the recession in 2008. Four dwellings have been completed apparently to a very high standard and sold, two of the conversions have not been done and the remaining barn is currently up for sale. When the third unit was sold, the purchasers’ solicitors required £46,000 to be retained from the sale price, being 50% of the affordable housing contribution due to NNDC under the terms of the agreement. This sum is held “in escrow” by the developer’s solicitors. The Section 106 Agreement The agreement was signed on 8 February 2007 and, at that time was considered to meet the policy tests to be applied to such agreements; whether the requirements are reasonable, relevant and directly related to the proposed development. A request was made to the Council for the Section 106 agreement to be released as it was clear at that point (2011) that the developer would make a significant loss on the project and that payment of £92,000 contribution was no longer viable. This matter was reported to Development Committee on 12 January 2012, when it was resolved that: … “Consideration of this matter be deferred for a more detailed report following advice from the District Valuer in respect of the figures discussed under private business and that further consideration be given to the legal consequences of the agreement on the present and future occupiers of the barns.” The report in January 2012 concluded with a recommendation that the developers be allowed to proceed with the conversion of the remaining (two) units without being required to pay the first tranche of the affordable housing contribution at that time and that “the viability of providing the second payment be considered when all the barns have been sold and all the cost of the conversion are known.” It is now apparent that the basis of this report was inaccurate, and the developer was in fact then asking to be released from the requirement of the agreement in full, such that no payment of affordable housing contributions are required. Current position on site Work on the site was suspended some time ago, such that four of six barn units have been converted, leaving two units unconverted. The developer has made it clear that the completion of the remaining two barns is not financially viable now or in the foreseeable future and has marketed the barns. Development Committee 2 28 May 2015 In the meantime the Local Member has expressed concerns over the deteriorating appearance of this site and possible safety issues (the unconverted building is adjacent to the road and debris has fallen from the building). Current Policy Context The starting point for considering an application for release or variation of a Section 106 agreement is: Is the obligation still necessary to render the scheme acceptable in planning terms when assessed against current policy at the time when the variation request is made? Therefore the application falls to be considered against the Council’s current Core Strategy document and National Planning Policy Framework and Guidance. Policy HO9 Conversion and Re-use of Rural Buildings as Dwellings states: The conversion and re-use of suitably constructed building in the countryside for permanent residential purposes will be permitted provided that: “(criteria 5) where it is viable to do so, on all schemes resulting in two or more units, not less than 50% of the total number of dwellings proposed are affordable, or an equivalent contribution is made in accordance with the requirements of Policy HO2” In summary, barn conversions in this location are acceptable and affordable housing is required on schemes of two or more units, but importantly any contribution is viability tested. The developer has been asked to be released from this agreement on viability grounds. In summary, the information submitted by the developer (July 2014) shows the cost of the project as follows: Purchase price plus cost of conversion of 4 units Sales of 4 completed units Shortfall Sale price of remaining barn LOSS £2.5 million -£1.8million £700,000 -£385.00 £315,000 On this basis, it would appear that the scheme is not viable and therefore the affordable housing contribution should be lifted. Further confirmation on the viability information submitted by the developer has been sought from the District Valuer, and is currently awaited. The Council’s policy position was further amended, with the introduction of the Housing Incentive Scheme in September 2013 (initially for a year) and extended to 30 December 2015. The purpose of the scheme is to incentivise the quick delivery of developments which have been granted planning permission, by increasing the number of dwellings which would be permitted on a development before seeking a contribution towards Development Committee 3 28 May 2015 affordable housing. The Council will allow schemes of up to 9 dwellings (new build and conversions) without seeking contributions to affordable housing. Since this site was last considered by the Development Committee in 2012, the Government has made significant changes both to the legislation relating to Section 106 agreements and also to the relevant national policy, reflecting the Government’s view that “the Planning system ought to proactively drive and support sustainable economic development.” The DCLG document which deals with changes made to the legislative framework for review of Section 106 agreements (April 2013) made clear that “Unrealistic section 106 agreements negotiated in differing economic conditions can be an obstacle to house building . The Government is keen to encourage development to come forward, to provide more homes to meet a growing population and to promote construction and economic growth. Stalled schemes due to economically unviable affordable housing requirements result in no development, no regeneration and no community benefit.” Paragraph 204 of the National Planning Policy Framework (NPPF) states that (Section 106) Planning Obligations should only be sought where they meet all of the following tests: Necessary to make the development acceptable in planning terms; Directly related to the development; and Fairly and reasonably related in scale and kind to the development Paragraph 205 states that “where obligations are being sought or revised, local planning authorities should take account of market conditions over time and, wherever appropriate, be sufficiently flexible to prevent planned development being stalled” More recent changes to the NNPF have set the threshold for requiring contributions towards affordable housing at 10 units. The introduction of this 10 unit threshold was introduced expressly to assist scheme viability and to speed up delivery. This change to the NPPF is a material consideration of significant weight in the consideration of the request for release of this agreement and supersedes the Council’s adopted Core Strategy policy. This stance was adopted by the Council following referral of a report to the Planning Policy and Built Heritage Working Party in January 2015. It is also the case that were the developer or a subsequent purchaser to now apply for Planning permission to convert the remaining barn, when considered against our current policy framework, Officers consider that an affordable housing contribution could not be imposed. Local Member view The Local Member has been made aware that this matter is being reported to Development Committee. Any views received will be reported to the Committee. Conclusions The developer entered into the S106 agreement in 2007 willingly and understood the requirements. Development Committee 4 28 May 2015 However the economic climate has changed significantly as has the relevant legislative and policy framework against which we would consider similar planning applications today. National guidance is clear in that Section 106 agreements should not be unreasonable and must reflect the current economic climate. The development has stalled and it is clear that the developer will not undertake further work to convert the remaining barn unless the development is released from the agreement. Therefore, subject to receipt of the District Valuer’s view on the financial information submitted and confirmation that the scheme is unviable, it is recommended that the development be released from the requirement to provide an off-site affordable housing contribution. This would facilitate the completion of this development, with the benefits of two additional homes and improvement in the appearance of the site which is in a prominent position in the AoNB and Conservation Area. Successors in Title A second issue has been raised by the current owner of one of the converted barns, and relates to the requirement that the Section 106 agreement was expressed to be binding on successors in title to the original developer. This has arisen as the current owner is seeking to sell the unit and solicitors have advised that the issue in relation to the affordable housing contribution has not been resolved, and will potentially impact adversely on future sales of the barns. The Council’s practice with regards to enforcement of section 106 agreements has changed since this Agreement was concluded in 2007 such that provisions relating to developer contributions are now expressed to bind the developers undertaking the project as successors in title, but not individual purchasers of completed dwellings. This is because such clauses are generally related to the viability of the overall development, and primarily in the control of the developers; again this is reflective of current Government policy aimed at reducing obstacles in the development process. In line with our current practice, it is therefore recommended that the successor in title clause within this agreement is lifted. Recommendations It is recommended: 1. That subject to confirmation from the District Valuer that this scheme is not viable, the Head of Planning to be authorised to release the development from providing the off-site affordable housing contribution of £92,000. 2. The successor in title clause also be removed from the agreement. (Source: Roger Howe (Planning Legal Manager) 01263 516016 : Nicola Baker (Head of Planning) 01263 516135) Development Committee 5 28 May 2015