OFFICERS' REPORTS TO DEVELOPMENT COMMITTEE - 18 DECEMBER 2014 Each report for decision on this Agenda shows the Officer responsible, the recommendation of the Head of Planning and in the case of private business the paragraph(s) of Schedule 12A to the Local Government Act 1972 under which it is considered exempt. None of the reports have financial, legal or policy implications save where indicated. PUBLIC BUSINESS - ITEM FOR DECISION PLANNING APPLICATIONS Note :- Recommendations for approval include a standard time limit condition as Condition No.1, unless otherwise stated. (1) BACTON - PF/14/1181 - Variation of condition 1 of planning permission ref: SM5180 to permit revised road layout, and changes to design, including elevations, to units 57-74; Rainbows End Chalet Park, Mill Lane for Tingdene Holiday Parks Ltd Major Development - Target Date: 09 January 2015 Case Officer: Miss C Ketteringham Full Planning Permission CONSTRAINTS Public Rights of Way Footpath Rural Residential Conversion Area (HO9) Coastal Erosion Constraint Area Countryside Archaeological Site Coastal Erosion Risk Area - 100 years Coastal Erosion Risk Area - 50 years Settlement Boundary RELEVANT PLANNING HISTORY SM 5180 - Erection of 110 units of holiday accommodation Approved 02/06/1965 PLA/19740580 PF - Erection of recreational facilities and shop Refused 16/09/1974 PLA/20001260 PF - Variation of seasonal occupancy restriction (condition 2 of permission reference: SM 5180) Approved 21/12/2000 PLA/20001693 PF - Continued use of two holiday chalets as temporary managers accommodation Temporary Approval 22/02/2001 PLA/20020026 PF - Continued use of two chalets as managers' accommodation Temporary Approval 08/11/2002 PLA/20021382 PF - Conversion of four chalets to managers' dwelling Approved 08/11/2002 PLA/20030245 PF - Erection of Detached One and a Half Storey Manager's Dwelling Withdrawn by Applicant 11/03/2013 PLA/20041773 PF - Continued use of two chalets for manager's accommodation Temporary Approval 02/12/2004 Development Committee 1 18 December 2014 PLA/20041841 PF - Variation of condition 1 of planning permission reference 20001260 to allow all year round occupation of holiday chalets Refused 16/12/2004 PLA/20060131 PF - Construction of pitched roofs and cladding of external walls to chalets Approved 17/03/2006 PLA/20060525 PF - Variation of condition 1 of planning permission reference 20001260 to permit all-year holiday occupancy Approved 13/06/2006 PLA/20080439 PF - Erection of one and a half storey building to provide ground floor reception/office/spa with manager's accommodation above Refused 13/05/2008 PF/10/0557 HOU - Erection of extensions to chalets and pitched roofs with sun terraces Approved 24/09/2010 PF/11/0653 PF - Erection of 15 beach huts and refuse bin enclosure Refused 31/08/2011 DE20/14/0090 ENQ - Erection of additional holiday chalets 22/05/2014 THE APPLICATION Is to vary condition 1 of planning permission (SM 5180 approved) to permit a revised layout of the site, design and position of 18 chalets. The replacement chalets are in semi-detached pairs, replacing on the layout two blocks of four and 10 single chalets. Twelve of the revised layout are repositioned on the eastern (seaward) side of the chalet park, six are relocated to western side of the park either side of the entrance. The original plans show the layout plan approved in 1965. A later plan was approved as an amendment but it is not clear that this was ever implemented. REASONS FOR REFERRAL TO COMMITTEE Required by the Head of Planning having regard to the planning history of the site, concerns of residents and the comments raised by Bacton Parish Council. PARISH COUNCIL Bacton Parish Council - comment as follows: • • • The provision of a S106 agreement to mitigate towards the additional traffic along Mill Lane until the furthest boundary at Rainbows End. The additional traffic flow is of grave concern especially as owners utilise these buildings as their main residence and live there most of the year. To work with the Parish Council and Norfolk County Council in a proactive matter to provide a regulated footpath south from Rainbows End to the beach. REPRESENTATIONS 2 letters commenting on the proposals have been received the comments are. 1. 2. Parking is not shown on the plans The original plans shown are the 1965 plans and should be an 1972 amended plan. Development Committee 2 18 December 2014 19 letters have been received objecting to the proposal 1. The unmade Mill Lane leading to the site is in a poor state of repair and will worsen with the increased traffic. 2. New layout is not in keeping with the rest of the site and will look out of place. 3. The proposed chalets are of a poorer design quality and build. They are basically mobile homes on a base. 4. The office is not shown on the plans, where will that go? 5. Parking not shown. 6. Already inadequate parking for owners and visitors. 7. Utilities are already a problem, water pressure is low and drains regularly get blocked. 8. Cannot rent properties for holiday lets with construction work on site. 9. Chalet Park will double in size. 10. Inadequate waste bin storage 11. Poor lighting on chalet park 12. Crime could rise as more places to hide. 13. Confusion over chalet numbering. 14. Green land within the chalet park will be destroyed. 15. Poor visibility at the point Mill Lane joins the road. 16. The plans eradicate the features that make the chalet park attractive its non-commercial nature, the clear views to the green field and the sea. 17. Large office building on the site, which does not have planning permission, is not shown. 18. Several properties have been sublet for residential use, this does not comply with planning permission. CONSULTATIONS Highways Authority - no objection subject to a condition on parking. HUMAN RIGHTS IMPLICATIONS It is considered that the proposed development may raise issues relevant to Article 8: The Right to respect for private and family life. Article 1 of the First Protocol: The right to peaceful enjoyment of possessions. Having considered the likely impact on an individual's Human Rights, and the general interest of the public, approval of this application as recommended is considered to be justified, proportionate and in accordance with planning law. CRIME AND DISORDER ACT 1998 - SECTION 17 The application raises no significant crime and disorder issues. POLICIES North Norfolk Core Strategy (Adopted September 2008): SS 2 - Development in the Countryside CT 6 - Parking provision EN 4 - Design MAIN ISSUES FOR CONSIDERATION 1. Principle of development 2. Design 3. Layout/relationship with existing development 4. Access 5. Parking Development Committee 3 18 December 2014 APPRAISAL Rainbows End Chalet Park is located within the Countryside Policy area close to the settlement boundary of Bacton. Access to the chalet park is from the unsurfaced, unadopted Mill Lane which joins onto the Walcott Road. Mill Lane serves over 65 other properties besides the chalet park. Rainbows End has an extant planning permission for 110 chalets of which 56 have been built with 54 not previously constructed. The application is partly retrospective as a pair of those remaining 54 chalets have already been erected on the site. The revised layout is a repositioning of 12 chalets on the eastern, outside edge of the chalet park roadway and relocating six of those chalets to the west side around the Rainbow End entrance. Currently all the 56 existing chalets are arranged around the outside of the chalet park leaving the central area, (apart from a few car parking spaces), as a grassed open space giving the chalet park a natural open feel. However, the open space is divided into two by the existing roadway layout. The outstanding 54 chalets with planning permission are arranged around or inside the roadway. Most of the lower open space would remain open under the existing and proposed layout. It is acknowledged that the effect of building the remaining chalets will have an impact on the occupants of the some of the existing chalets. While there may be winners and losers in terms of views, as members will be aware loss of a view is not a material planning consideration. In landscape terms the revised layout for the repositioning of the twelve chalets on the eastern side of the park raises no concerns. The six chalets by the entrance will be more prominent from Mill Lane but again raises no landscape concerns. Two of the proposed chalets, close to the entrance and the southern boundary are regarded as too close to the boundary with a neighbour to the south and unlikely to meet the Basic Residential Amenity Criteria guidelines between neighbours. The agent has been advised of this. An amended plan has been requested and it is anticipated this may be satisfactorily resolved. As regards the appearance of the chalets, although disputed by some of the objectors they are very similar to the original chalets. However, they are not of the same conventional construction, but are a building that is prefabricated elsewhere and erected on site. There are some cosmetic differences with door and window placements and materials. Although the buildings will not be identical to the existing chalets, the appearance is broadly the same and the appearance of the new chalets would not be out of place in this location. The existing and proposed parking has not been shown on the revised plan, the agent has indicated that the parking layout will be submitted prior to the Committee meeting. The existing parking spaces are tarmac or shingle which is rather a harsh surface treatment for this Chalet Park. A grid system that allowed the grass to grow through would be a softer, more appropriate surface treatment going some way to preserving the natural open appearance of the park. This has been suggested to the agent. The site office is currently located close to chalets numbered 59 and 60, it is currently unauthorised. The agent has indicated that a planning application to relocate the site office will be submitted shortly. Although close to the area of likely Coastal Erosion, none of the chalets in the revised chalet layout are within the area at risk. In fact the revised layout would remove four of the approved chalets to outside the area at risk of coastal erosion within the next 100 years. Development Committee 4 18 December 2014 In respect of the objectors’ concerns regarding the condition of the road, it is unclear who owns any part of Mill Lane. The condition of the road as suitable to serve the development would have been an issue dealt with under the original planning permission. While it would be desirable for the road to be maintained, it appears to be outside the applicants' control. Furthermore, there is an extant permission on the site for the additional units. In conclusion, there is an extant planning permission on the site to build the number of chalets proposed. The appearance of the chalets is not significantly different from those already on the site and is considered better than those that could be built under the extant permission. There is also a minor benefit in that a few of the chalets would be removed from the area at risk from Coastal Erosion. While the position of the chalets is a little different this is not so significant as to alter the character of the approved chalet park, to have an overall adverse landscape impact or be significantly detrimental to the amenities of existing chalet occupiers. Taking into account the extant permission, the proposal is considered to comply with the policies of the Development Plan. Accordingly, the application is recommended for approval subject to a satisfactory revised siting for units 59 and 60, and parking layout being submitted and agreed. RECOMMENDATION: Delegated to the Head of Planning to approve; Subject to an acceptable revised siting for units 59 and 60, a satisfactory parking layout and the imposition of appropriate conditions. (2) HORNING - PO/14/1297 - Erection of single-storey dwelling; 2 Clover Hill, Letheringtons Lane for Mr R Kalynuk Minor Development - Target Date: 10 December 2014 Case Officer: Mrs K Brumpton Outline Planning Permission CONSTRAINTS Horning Knackers Wood Catchment Boundary Countryside RELEVANT PLANNING HISTORY PLA/20031290 PF - Erection of bungalow and double garage Refused 23/09/2003 PLA/20021539 PF - Erection of bungalow and garage Refused 29/11/2002 PLA/20041343 PF - Erection of bungalow and double garage Refused 01/10/2004 PO/13/0741 PO - Erection of single-storey dwelling Refused 22/10/2013 THE APPLICATION Seeks outline planning permission to erect a single storey dwelling, with all matters reserved. The site is part of the garden serving the applicant's dwelling, 2 Cloverhill. Development Committee 5 18 December 2014 REASONS FOR REFERRAL TO COMMITTEE At the request of Councillor Barbara McGoun having regard to the NPPF's presumption for sustainable development and the personal circumstances of the applicants; in particular to both Mr and Mrs Kalynuk's health and their current financial situation with their bank. PARISH COUNCIL Does not wish to make a comment REPRESENTATIONS 1 letter of objection received, raising the following points; • Contrary to policy as it is outside of the settlement boundary • Would encroach upon the undeveloped Countryside, typified by Letheringtons Lane which does not have pavements or other facilities • Approval would encourage ribbon development along the lane in exactly the form which the Town and Country Planning Acts were originally introduced to prevent • Both of the existing 2 bungalows have been fully developed within their curtilages • Applicant cites a necessity for special adaption for health reasons but there seems no reason why the existing bungalow could not be adapted • The financial misfortune cited as the need for the development is not a reason for planning exception • Letters of 'support' are merely evidence of disablement and not letters of support or encouragement for the council to breach planning policy CONSULTATIONS Anglian Water - Awaiting response County Council Highway Authority - no objection. Although any proposal which would significantly increase the vehicular use of the single-track Letherington's Lane would be likely to attract an objection, in this instance it is not reasonable to extend this objection to a further single dwelling proposed at this particular location. Accordingly, subject to an appropriate condition and informative note being appended to any consent notice issued, I would not wish to object to the granting of permission. The condition would request full details of the visibility splays, access and parking/turning provision. Environmental Health - object. There are currently capacity issues at Horning Water Recycling Centre (WRC). Anglian Water are due to conduct works on the WRC, however until such a time that these works have taken place and confirmation has been received that they are adequate the erection of a dwelling and subsequent increase upon the foul drainage system would be an unacceptable form of development and contrary to the aims of the Water Framework directive. Landscape Officer - object. Given that we have a problem with any new dwelling in the Horning catchment area with the Sewage Treatment Works being at and over capacity, the application would have to be subject to a Habitats Regulations Assessment under Section 61 of the Conservation of Habitats and Species Regulations 2010 (as amended). As a Competent Authority under these Regulations we have a statutory duty to have regard to the requirements of the Regulations when determining planning applications. At the moment we do not have sufficient information to determine that the proposal would not result in significant likely effects to the conservation interests of the Broads Special Area of Conservation (SAC) therefore I would object to the application. If members were minded to be approve the application at committee we would need to carry out an Appropriate Assessment prior Development Committee 6 18 December 2014 to determination to ensure that the development would not result in significant likely effects on the Broads SAC. In addition any subsequent reserved matters application should be supported by an Arboricultural Implications Assessment, Tree Survey and Tree Protection Plan to ensure that the trees on and adjacent to the site are adequately protected. HUMAN RIGHTS IMPLICATIONS It is considered that the proposed development may raise issues relevant to Article 8: The Right to respect for private and family life. Article 1 of the First Protocol: The right to peaceful enjoyment of possessions. It is considered that refusal of this application as recommended may have an impact on the individual Human Rights of the applicant. However, having considered the likely impact and the general interest of the public, refusal of the application is considered to be justified, proportionate and in accordance with planning law. CRIME AND DISORDER ACT 1998 - SECTION 17 The application raises no significant crime and disorder issues. POLICIES North Norfolk Core Strategy (Adopted September 2008): Policy SS2: Development in the Countryside (prevents general development in the countryside with specific exceptions). Policy EN 4: Design (specifies criteria that proposals should have regard to, including the North Norfolk Design Guide and sustainable construction). Policy EN 6: Sustainable construction and energy efficiency (specifies sustainability and energy efficiency requirements for new developments). Policy EN 9: Biodiversity and geology (requires no adverse impact on designated nature conservation sites). Policy EN 13: Pollution and hazard prevention and minimisation (minimises pollution and provides guidance on contaminated land and Major Hazard Zones). Policy CT 5: The transport impact on new development (specifies criteria to ensure reduction of need to travel and promotion of sustainable forms of transport). Policy CT 6: Parking provision (requires compliance with the Council's car parking standards other than in exceptional circumstances). National Planning Policy Framework (NPPF) Water Framework Directive (WFD) Habitats and Species Regulations 2010 (as amended) MAIN ISSUES FOR CONSIDERATION 1. Principle of Development 2. Capacity of Horning's Water Recycling Centre APPRAISAL Introduction The site lies within an area of Countryside where new residential dwellings are not normally permitted under Policy SS 2. The site is currently used as a garden by the applicants and is largely laid to lawn, with several trees around the edge of the site. Sited north of the A1062, it falls outside of Horning's residential area and lies close to the border with the Broads Authority. In addition to the applicant's own bungalow, there is another bungalow sited to the south of 2 Cloverhill, which sits on the corner of the A1062 and Letherington's Lane. Development Committee 7 18 December 2014 With all matters reserved this application focuses upon the principle of a new single storey dwelling at the site, and follows the previous refusal issued under PO/13/0741. Policy EN 4 With both the applicant's and neighbour's dwelling single storey, another single storey dwelling could prove to be acceptable in terms of design. This is partially dependent on the number of trees to be retained. The new dwelling would not be readily visible from anywhere except Letherington's Lane, and could be sited to relate well to the existing bungalows. At approximately 35m by 17m it is anticipated that the plot is large enough to accommodate a design which would not result in any significantly detrimental impact upon the immediate neighbour. Policy EN 4 could therefore be complied with. Any reserved matters application would require the submission of an arboricultural report to detail which trees would remain and which, if any, would be removed. It would also need to demonstrate how the dwelling would be constructed around the trees to remain. Policies CT 5 and CT 6 The additional traffic generated by a new dwelling is considered acceptable, and with appropriate visibility splays a new access onto Letherington's Lane could also be acceptable under Policy CT 6. The site appears large enough to be able to provide sufficient parking, complying with Policy CT 5. Policy EN 6 With a suitable condition added, compliance with Policy EN 6 can also be achieved. Policy SS 2 and NPPF As mentioned above new dwellings are not normally permitted under Policy SS 2, however the applicants consider that there are good grounds to justify a departure from policy. They consider the location to be sustainable, therefore complying with the NPPF. Whilst it is noted that the site is close to Horning's development boundary, and that Horning is classified as a Service Village within the Core Strategy, NNDC have an up to date Core Strategy. The guidance within the NPPF in para 12 states that "Proposed development that accords with an up-to-date Local Plan should be approved, and proposed development that conflicts should be refused unless other material considerations indicate otherwise". Both of the applicants are now disabled, suffering from a variety of health issues. One applicant's mobility is deteriorating. The supporting information states that they "need a disabled friendly dwelling", with a doctors letter stating that one of the applicants "would benefit from living in a house that has been specifically adapted for her disabilities" and in their view both of the applicants would benefit from remaining within her/his practice area due to the complexity of their medical problems. Their situation has been made more difficult as they feel they have been victims of malpractice at a bank, which appears to have been investigated by the Financial Ombudsman. Although these issues are material considerations, they do not, in Officer's opinion, amount to sufficient justification to deviate from either Policy SS 2 or the NPPF. Development Committee 8 18 December 2014 Policies EN 9 and EN 13 The Anglian Water Waste Water Recycling Centre (WRC) Knackers Wood serves this area. It is currently considered to be at capacity and no development should be approved which would result in an increase in nutrient loading from the WRC to the river. Further nutrient loading would have a negative impact upon the Special Area of Conservation (SAC), Special Protection Area (SPA) and Site of Special Scientific Interest (SSSI) further downstream. Whilst works are proposed which should increase the capacity, these may not be completed until March 2015 and it is uncertain what capacity will be freed up. Development that could increase the flows to the Water Recycling Works therefore needs to be avoided. Clearly a new dwelling would increase the flows to the WRC, and is therefore considered unacceptable at this time and would fail to comply with the objectives of Policies EN 9 and EN 13 and the Water Framework Directive. Conclusion The proposal is considered to be contrary to Policies SS 2, EN 9, EN 13 of the adopted Core Strategy, the NPPF, WFD and the Habitats and Species Regulations 2010 (as amended) and is therefore recommended for refusal. RECOMMENDATION: Refuse, for the following reasons; The District Council adopted the North Norfolk Core Strategy on 24 September 2008, and subsequently adopted Policy HO 9 on 23 February 2011, for all planning purposes. The following policy statements are considered relevant to the proposed development: Policy SS 2: Development in the Countryside EN 9 - Biodiversity and geology Water Framework Directive Habitats and Species Regulations 2010 (as amended) The National Planning Policy Framework (the NPPF)(published 27 March 2012) is also material to the determination of the application. The site lies within an area designated as Countryside, where there is a general presumption against residential development. In the opinion of the Local Planning Authority the case put forward by the applicant does not provide sufficient justification to permit the erection of an additional dwelling in the Countryside contrary to Policy SS 2 of the adopted Core Strategy. Furthermore the applicant has failed to demonstrate that the development would not result in additional flows of wastewater. If it does, it would have a detrimental impact on the receiving watercourse due to capacity limitations at Horning Knackers Wood Water Recycling Centre. The proposed development is therefore contrary to NPPF paragraph 109 which states ‘The planning system should contribute to and enhance the natural and local environment by preventing both new and existing development from contributing to or being put at unacceptable risk from, or being adversely affected by unacceptable levels of soil, air, water or noise pollution or land stability. As such the proposal is also contrary to the Water Framework Directive. Allowing this development is likely to have an adverse impact on the biodiversity and natural habitats associated with the receiving watercourse such that it is also contrary to Policy EN 9 and Policy EN 13 of the adopted Core Strategy, in addition to the Development Committee 9 18 December 2014 Water Framework Directive and Habitats and Species Regulations 2010 (as amended). (3) OVERSTRAND - PM/14/0854 - Erection of ten dwellings; Land at Hillingdon Park for A G Brown Ltd Major Development - Target Date: 08 October 2014 Case Officer: Mrs M Moore Reserved Matters CONSTRAINTS Tree Preservation Order Tree Preservation Order - Consultation Area Unclassified Road Conservation Area Residential Area Settlement Boundary RELEVANT PLANNING HISTORY E 4725 - Building site Approved 4/07/1966 E4919 - Construction of Estate Roads and Sewers Approved 21/03/1967 PM/13/0790 PM - Erection of ten dwellings Withdrawn by Applicant 05/09/2013 THE APPLICATION This is a reserved matters application for the erection of the remaining ten dwellings across the site following outline approval for 35 dwellings granted in July 1966, under planning permission reference E 4725. A further approval was granted in March 1967 for the construction of estate roads and sewers. The only matters for consideration under this application are appearance, landscaping, layout and scale. The remaining dwellings would be infill plots within the existing development, grouped as a site of four dwellings, a site of three dwellings and three single plots. The proposed dwellings would comprise a mix of two, three and four bedroom properties. Nine of the dwellings would be single-storey, with the remaining dwelling being one-and-a-half storey. The scheme proposes brick, flint, render and clad elevations and tiled roofs. Various amended plans have been submitted proposing changes to the appearance, layout and scale of some of the dwellings and to ensure compatibility between the elevation, floor and site layout plans. The Agent has also submitted amended plans to re-locate the garage for Plot number 6 and to change the dwelling at Plot number 10 from a one-and-a-half storey dwelling to a single-storey dwelling. The application is accompanied by the following documents: • Design and Access and Heritage Statement • Arboricultural Impact Assessment, Tree Protection Plan, Method Statement and Landscaping Schedule Development Committee 10 18 December 2014 • • Ecological Survey Sustainable Construction Checklist REASONS FOR REFERRAL TO COMMITTEE The application was deferred for a site visit at a previous meeting. PARISH COUNCIL Response on first amended plans: Whilst there is no objection to the individual applications, there is great concern regarding the number of trees proposed to be felled, and also the dispersal of surface water given that there are problems with drainage in the area. A comment was also added that a staggered development would be helpful. Concerns regarding the adequacy of the drainage system should be strongly stressed. Response awaited in respect of amended plans. The Committee will be updated verbally. REPRESENTATIONS 71 letters of objection received from 36 representees and 9 comments from 3 representees. The objections broadly cover issues relating to the drainage (surface and foul), roads and other infrastructure, damage/disturbance during and after construction, proposals not respecting the front building line, highway safety, cliff erosion, design/materials, neighbour amenity, loss of trees, wildlife, status of the outline application, failure to comply with a restrictive covenant and inaccuracies/comments of submitted planning documents. A more detailed summary of these objections is as follows: • Existing sewage and surface water issues; • Existing infrastructure issues including pressure on drains. Development would exacerbate issues; • Developers of remaining plots must assume full responsibility of bringing all services up to adoptable standards; • Existing drains not maintained and broken. Problems with burst water drains and problems after rain etc; • Proximity of, or building of, proposed buildings on sewers and gas services; • Roads are unadopted. Concern regarding responsibility for maintenance and upkeep of roads and pavement; • Condition of road and pavements poor. Kerbstones sunk and uneven; • Impact of tree felling on existing substructure, roads, paths, services etc from ground movement; • Impact on amenities from existing infrastructure problems with mains water, electrical services needing repair after numerous power cuts, gas and telephone connections not working; • Highway Safety concerns; • Highway safety on Pauls Lane from additional traffic; • Traffic burden/congestion from additional properties and additional cars; • Vehicle manoeuvre access/egress concerns; • Garages blocking line of sight for vehicles coming out of driveways- danger to vehicles/pedestrians; • Sufficient parking should be provided to ensure no parking on road; • Loss of amenity/disruption/damage during construction (especially noise, construction traffic, parking of builders’ vehicles, dust, working hours, vermin control and damage to roads/drains, land heavy and subsidence etc). Timings of work. Construction period; • Building line has been ignored; Development Committee 11 18 December 2014 • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • Encroachment on established building line by buildings and fencing; Encroachment on building lines/pavement would obscure sight lines and give claustrophobic feel; Secure by Design Document should not be disregarded, especially in relation to sight lines and security issues. Policing implications; Hillingdon Park has a visually open aspect. The need to retain trees has brought building structures forward right up to the footpath out of line and keeping with existing properties and adversely affecting the visual impact and the character of the existing development and neighbourhood. Proposals not harmonious or sympathetic; Tree removal and subsequent land heave/settling/subsidence/landslip/impact on soil stability with consequent additional drain off to cliffs and cliff erosion. An established tree will absorb from the ground an average of fifty thousand litres of water per annum. Survey required as done for proposed development Mundesley Road, Overstrand; Climate change impacts; Impact on fluvial and pluvial erosion; Unacceptable design, layout, appearance, materials, scale, height, type, positioning and density; Only bungalows should be constructed; Plots 7, 8 and 9 would give a blank frontage and oppressive look not in keeping with existing. Would give impression of walking down a street of attached dwellings; Fencing details required; Neighbour amenity issues including overlooking, overbearing, loss of privacy, loss of sun/ light, overshadowing, overdevelopment, overcrowding, noise, smell, nuisance and artificial light concerns, loss of peace, quiet, tranquillity and impact on ambiance. Invasion of privacy and quality of life. Health, safety and sanity concerns; To make changes to original approval would destroy character of estate and create loss of privacy, noise disturbance and issues with highway safety through obstruction caused by new builds; Failure to comply with the Council’s Design Guide and Basic Amenity Criteria; Close proximity of new dwellings, garages and fencing to existing dwellings; Loss of view; Health concerns with sewage water not being properly contained and controlled; Sound buffering problems from loss of trees between Hillingdon Park and Kingswood children's education and activity centre; Loss of trees, including TPO trees; Impact on landscape character; Reference to dismissed appeal at 24 Danish House Gardens, Overstrand due to tree loss and impact on landscape character; Impact of tree felling on water table; Removal of trees in small groups over longer periods would have less impact on environment, sub soil and wildlife than removal of 100+ in one operation; Impact on eco-system from tree removal; Ecological survey excludes or is dismissive of some wildlife; Impacts on wildlife/ecology (including protected species) from loss of trees; Impact on flora; Bats prevalent and may allow a Site of Special Scientific (SSSI) classification; Impact on newts, frogs and toads. Possible pair of Crested Newts reported; Concerns as to the validity of the original permission; Original consent for building line, type of development and materials should be only Development Committee 12 18 December 2014 • • • • • • • • • • • • • • • • • • • • • • one given any consideration; Development contrary to adopted Policy; Non-compliance with Land Registry Documents/Restrictive Covenants on Deeds; Plans and reports inadequate, inaccurate, missing, unclear and misleading; Impact on Conservation Area; Development would hinder vehicular access to garage of number 9; No inclusion of renewable or low-carbon energy technologies and would only meet Code Level 3 for Sustainable Homes; Plot 5 has encroached onto rear boundary line of 28 Hillingdon Park; Maintenance concerns to existing buildings given close proximity; Safety of trees in high winds and risk to life and property; Problems with Home Insurance; Plot 10 site should be cleared and turned into communal gardens/park; Hillingdon Park is becoming a non-park with building on all recreational areas; Process concerns raised. Conflict of interest concerns as the ecological survey undertaken by same company as is advising builder; During protracted and piecemeal development, contractors failed to adhere to design mandate and enforcing authorities to ensure compliance; Hillingdon Park has had enough publicity and scandal about sex in recent years, NNDC needs to ensure that their planning consents to not potentially facilitate or encourage further scandals; Development does not provide for 20% of dwellings to be built for the elderly and incapacitated/infirm and disabled; Alternative proposals put forward. Some of the above objections were similar to comments made on the application. Additional comments made:Intention for properties to be in harmony with trees is too idealistic. Concerns regarding shading, sunlight, amount of sky visible, level of solar gain, appreciation of living close to large trees, interference with Satellite television signals, future growth, seasonal nuisance and pressure to remove trees. Impact on amenity; Impact on trees including TPO trees and removal of Category A high quality trees; Pleased that applicants have noted residents prior concerns and decided to complete the estate in one construction period. Can this be a condition; Final completion of estate will end a lot of uncertainty about the future of the vacant plots. CONSULTATIONS County Council (Highways): Given previous outline consents on this site it would be very difficult to substantiate a highway objection to this proposal to complete development. Hillingdon Park is not adopted by the Highway Authority who have no present intention to change this situation. Conditions required on any approval relating to the provision of the footway extending the existing footways up to and including the complete roadside frontage of the site with Pauls Lane and the provision of on-site car parking areas, as indicated on the site plan. Conservation, Design and Landscape Manager (Conservation and Design): As with the earlier proposals, there can be no Conservation and Design objections to Development Committee 13 18 December 2014 the principle of the proposed development given the extant permission which exists on the site. In terms of detail, the proposed buildings consist predominantly of single-storey structures where they directly abut the existing bungalows, and 1½ storeys on the more peripheral Plot 3. They are therefore considered broadly congruent with the scale and form of the original buildings on site. In saying this, however, it is acknowledged that several of the units step forward of the existing building lines and are therefore not wholly compatible with the original open plan ethos of the development. However, because these lines were only ever loosely defined, and because the main body of Hillingdon Park does not lie within the Overstrand Conservation Area, it is difficult to see how this could form the basis for a sustainable ground for objection. Indeed, based upon recent experience, there is actually an argument which says that narrowing up the street scene and channelling views could add additional depth and interest to the existing layout. Design-wise, the plans for the most part provide for relatively conventional bungalows which display compatible proportions and footprints. At the same time, however, they have been enlivened with the introduction of the occasional glazed gable, and the addition of rendered and boarded elements. Together these should offer a contemporary freshness to the units. Providing there is then a consistency across the roof materials (which echoes the existing dark coloured palette), the new build should visually take its place harmoniously rather than discordantly. In this latter respect, it is not considered that red clay pantiles or slate would be appropriate choices. Plot-by-plot there is nothing within the main house types which particularly jars on the eye elevationally. The latest plans have also now addressed the earlier concerns around garage provision. Therefore, whilst inevitably there remains a slight tension between the original and proposed developments, Conservation & Design maintain that the new units manage to tread a fine line between respecting the past and learning sufficient lessons from it. As a result, the development would add its own layer but not in an adverse way. Certainly there would be no harm caused to the setting of the adjacent conservation area or to any other heritage assets. Condition required for the prior approval of all the facing materials prior to their use on site. Conservation, Design and Landscape Manager (Landscape): The development land at Hillingdon Park has outline planning permission dating to the 1960’s. Building on the site has been sporadic since that time allowing trees to grow on the vacant plots. An area Tree Preservation Order (TPO) covered the site to protect amenity and landscape. Under the Council’s review of TPO’s, Area Orders are being phased out in favour of more descriptive Orders in line with Government Guidelines. The Conservation, Design and Landscape section has discussed the development with the Agent over a long period and concluded that it would be expedient to serve a TPO that facilitated development and protected the woodland character of Hillingdon Park. A Woodland Order was served together with Group and individual Orders where appropriate. The developer has designed the layout of the proposed dwellings to accommodate the character of the area. Although several trees will have to be removed to facilitate the development a comprehensive landscape and planting scheme will assist in restoring Development Committee 14 18 December 2014 the character of the tree cover lost. A total of 160 trees and 140 shrubs will be replanted. The properties will be part of the wooded area and it is proposed to market them as wooded properties which has been successful in other areas. The un-shaded areas of garden are very close to the minimum guidelines but should be acceptable to new residents as they are clearly woodland properties. Appropriate maintenance of the trees will be acceptable under the TPO guidelines. The original building line of the estate will be sacrificed to preserve as many trees as possible bringing the buildings forward to the road. It is considered that this layout will have less effect on the landscape. The ecological survey submitted with the application takes account of the important features on the site and proposes mitigation planting to support species that have been recorded. The biodiversity of the woodland area of plots 1 to 4 will be improved for the invertebrates with the removal of the tipped garden material which is suppressing the herb layer and the planting of the new trees and shrubs in and around the gardens. To make sure that possible bat roosts are maintained it is suggested that bat boxes be placed in suitable locations on the site. The ground soils are predominantly glacial deposits and therefore heave will not be a significant problem. The planting of more trees and shrubs than those removed should mitigate any concerns regarding future coastal erosion in the long term. Conditions required to: ensure compliance with the Arboricultural Method Statement and Landscaping plan; the submission of an on site timetable for the methodology detailing arboricultural supervision; the requirement for all trees to be planted in accordance with British Standard BS 8545; the submission of a scheme for replacement planting on Plot 10; the protection of those trees; shrubs and hedgerows indicated for retention for ten years; the replacement of any new tree or shrub which within a period of ten years from the date of planting dies, is removed or become seriously damaged or diseased, shall be replaced during the next planting; the requirement for development to be constructed in accordance with the submitted Species Mitigation Measures and the provision of bat boxes. Anglian Water Assets affected Anglian Water has assets close to or crossing this site or there are assets subject to an adoption agreement. Therefore the site layout should take this into account and accommodate those assets within either prospectively adoptable highways or public open space. If this is not practicable then the sewers will need to be diverted at the developers cost under Section 185 of the Water Industry Act 1991 or, in the case of apparatus under an adoption agreement, liaise with the owners of the apparatus. It should be noted that the diversion works should normally be completed before development can commence. Wastewater Treatment The foul drainage from this development is in the catchment of Cromer (Runton-Middlebrook Way) Water Recycling Centre that at present has available capacity for these flows. Foul Sewerage Network The sewerage system at present has available capacity for these flows. If the Development Committee 15 18 December 2014 developer wishes to connect to our sewerage network they should serve notice under Section 106 of the Water Industry Act 1991. We will then advise them of the most suitable point of connection. Surface Water Disposal The preferred method of surface water disposal would be to a sustainable drainage system (SUDS) with connection to sewer seen as the last option. Building Regulations (part H) on Drainage and Waste Disposal for England includes a surface water drainage hierarchy, with infiltration on site as the preferred disposal option, followed by discharge to watercourse and then connection to a sewer. The surface water strategy/flood risk assessment submitted with the planning application relevant to Anglian Water is unacceptable as no details of flow rates to the public sewer or evidence that the SUDS hierarchy is followed are provided We would therefore recommend that the applicant needs to consult with Anglian Water and the Environment Agency. We request a condition requiring a drainage strategy covering the issue(s) to be agreed. Head of Coastal Strategy The Coastal management team would object to the use of soakaways for any additional surface water runoff from the proposed dwellings. They would prefer to see the new properties connected to the Anglian Water sewer, so that all surface water is discharged away from site, thus reducing the potential risk of increased groundwater impacting on cliff stability. They would be happy with the Agent’s proposal to install rainwater harvesting tanks that could be used to attenuate the flows, but the overflow into the adopted sewer would be important. Building Control Foul drainage will be straightforward, connecting to the existing foul sewer which is assumed to have the required capacity for the additional plots, these being the same number as originally approved with the outline consent. Surface water disposal will be more difficult – due to the proximity of the site from the cliff edge, Building Control would not be happy with soakaways to the plots closest to the cliff although they may be possible to the plots closest to Pauls Lane. In the first instance, consultation with coast protection is recommended with regards to the acceptability and then if soakaways are not possible, it would be down to Anglian Water to consent to the surface water drainage being connected to the foul system. Due to the small size of the foul sewer in the area, Building Control would imagine that some sort of holding tank or similar would be needed to prevent the system being overloaded in the event of heavy rainfall. Environmental Health Environmental Health are aware that plots 1, 2 and 3 bound the Kingswood Centre at Overstrand, and have noted the concerns of the centre manager. The erection of a 1.8m high close boarded fence to the western boundaries of plots 1 and 3 should be conditioned to help with reducing the noise impact on the properties from the activities carried out at Kingswood. Condition requiring details of the proposed surface water disposal required. Development Committee 16 18 December 2014 Architectural Liaison Officer Having viewed the plans and associated documents dated 26th September 2014, the Officer is happy with the layout of the development and have no recommendations to make in regards to crime and ASB. Norfolk Wildlife Trust It is Norfolk Wildlife Trust's view that if approved there should be conditions to protect and enhance biodiversity. These conditions should follow the recommendations contained in Section 5 of the ecological report that accompanies the application Planning Legal Manager In connection with a current application for approval of reserved matters (PM/14/0854) you had asked for my comments on the status of the historic outline permission for the Hillingdon Park estate and how the current application should be assessed against Core Strategy policies, specifically policy HO1. Your enquiry has also raised issues relating to drainage of the site as our Coastal Protection colleagues have raised concerns if soakaways are to be installed. These issues are not straightforward and I am aware that several objections received in respect of the current reserved matters application query the validity of the outline consent which was approved in 1966. In considering these matters I have received the old “County” files relating to the site, specifically applications E4725 and E4919. I would respond to your enquires as follows: • Application E4725 This was an application to Norfolk County Council (which was then the Planning Authority) for outline permission to develop land described as “proposed building site” at Pauls Lane, Overstrand. There had been a previous application (reference 3354) which had been approved on 12 August 1963. The plan submitted in support of application E4725 was a 1:500 scale plan showing a total of 35 dwellings served by a cul de sac access. The application was approved on 4 July 1966 subject to conditions requiring (amongst other things) submission of details of surface water drainage arrangements. • Application E4919 This application sought approval of the “estate road, sewers and street light” at the Pauls Lane site. The application was approved on 21 March 1967 and the notice of permission referred to “the application as amended by the plan dated January 1967.” I take this to be drawing number 5/679/1 which shows an estate layout of 35 dwellings and also the existing and proposed sewers serving the development. The drawing also shows details of the estate road with dimensions marked and with the positions of a number of soakaways marked. 1) Subsequent permissions You had helpfully passed to me a list of permissions for the individual dwellings constructed on the site. Interestingly, most of these appear to be applications for “full” permission rather than for approval of matters reserved by the outline permission. From a review of several of these files I am unable to confirm why the applications were made as full applications rather than as reserved matters applications; it may be the case that this was the practice at the time and of course the officers who dealt with those applications have long since retired. Most of the applications were made by the same agents; Pike & Partners of Cromer. Development Committee 17 18 December 2014 I note that an application (01/76/0007/D) was made by another agent and, unlike the Pike & Partners applications, was for approval of matters reserved by the outline permission E4725. This application related to plot 11 and was refused on grounds relating to visual impact and potential effects on trees. The fact that this application was for RMs approval rather than a full application does not appear to have been queried at the time. 2) Current application Application PM/14/0854 seeks approval of reserved matters for the 10 remaining plots of the 35 for which outline permission was granted by the approval of application E4725 in 1966. Assuming that permission to be extant, the only matters for consideration are appearance, landscaping, layout and scale. Notwithstanding that the dwellings already constructed on the site were the subject of full applications (rather than applications for approval of reserved matters) my view is that the original outline permission, E4725, remains extant and that the principle of residential development is thereby established for the remaining plots. That being the case our consideration of the application should be limited to the matters noted above in my view; the overarching policies in the Core Strategy (specifically HO1) which would be applicable to new developments do not fall to be considered. 3) Drainage The permission for estate roads and surface water drainage (E4909) also remains extant in my opinion. However there is a greater awareness of potential coastal erosion than was the case in the 1960s and it is in no-one’s interest for development to be undertaken which may adversely impact on the site and the surrounding area. I am mindful that Coast Protection cannot support soakaways and that the agents for the current application are inclined to an alternative solution involving the installation of surface water harvesting tanks with an overflow into the mains system. To my mind this would be a practical solution which (subject to our Coast Protection colleague’s approval) could be utilised. We should agree, and perhaps reflect in your report to the Development Committee, that this is at variance with the approved drainage scheme (E.4909) but is recommended for approval without prejudice to that extant permission (i.e. it is acknowledged that the developer has the original approval as a fallback but is prepared to move to the agreed alternative of harvesting tanks). HUMAN RIGHTS IMPLICATIONS It is considered that the proposed development may raise issues relevant to Article 8: The Right to respect for private and family life. Article 1 of the First Protocol: The right to peaceful enjoyment of possessions. Having considered the likely impact on an individual's Human Rights, and the general interest of the public, approval of this application as recommended is considered to be justified, proportionate and in accordance with planning law. CRIME AND DISORDER ACT 1998 - SECTION 17 The application raises no significant crime and disorder issues. POLICIES North Norfolk Core Strategy (Adopted September 2008): Rural Residential Conversion Area (HO9) (The site lies within an area where the re-use of an existing good quality building as a dwelling may be permitted). Development Committee 18 18 December 2014 Policy SS 1: Spatial Strategy for North Norfolk (specifies the settlement hierarchy and distribution of development in the district). Policy EN 2: Protection and enhancement of landscape and settlement character (specifies criteria that proposals should have regard to, including the Landscape Character Assessment). Policy EN 4: Design (specifies criteria that proposals should have regard to, including the North Norfolk Design Guide and sustainable construction). Policy EN 8: Protecting and enhancing the historic environment (prevents insensitive development and specifies requirements relating to designated assets and other valuable buildings). Policy EN 9: Biodiversity & geology (requires no adverse impact on designated nature conservation sites). Policy EN 13: Pollution and hazard prevention and minimisation (minimises pollution and provides guidance on contaminated land and Major Hazard Zones). Policy CT 5: The transport impact of new development (specifies criteria to ensure reduction of need to travel and promotion of sustainable forms of transport). Policy CT 6: Parking provision (requires compliance with the Council’s car parking standards other than in exceptional circumstances). MAIN ISSUES FOR CONSIDERATION 1) Principle of the development 2) Scale/design/layout and impact on Conservation Area 3) Landscaping and biodiversity 4) Drainage issues 5) Highway safety 6) Impact on neighbouring dwellings APPRAISAL Determination of this application was deferred at a previous meeting to allow members to visit the site. Principle of development Hillingdon Park is accessed off Pauls Lane and is located within the Settlement Boundary and Residential Area of Overstrand. It adjoins existing residential development to the east and south, a golf course (Royal Cromer Golf Course) to the north and a children's education and activity centre (Kingswood) to the west. The northern boundary of the Overstrand Conservation Area runs through plots 7, 8, 9 and 10, where development proposals are expected to preserve or enhance the character and appearance of the area. The plots themselves are wooded, with trees protected by individual and Group Tree Preservation Orders and a Woodland Order. The Committee will note the comments from the Planning Legal Manager, confirming that both the Outline planning permission and the subsequent permission for the construction of estate roads and sewers, are extant. On that basis, the principle of the development is already accepted and some of the objections raised in respect of the ability of the existing roads etc to cope with the additional demand, cannot be considered under this application. Similarly, some of the objections raised are civil, rather than planning, grounds for objection, such as non-compliance with restrictive covenants etc. Development Committee 19 18 December 2014 Scale/design/layout and impact on Conservation Area As far as the scale of the dwellings is concerned, given that the principle of both single and one-and-a-half-storey properties is established within Hillingdon Park, the current proposals are considered compatible and in keeping with the surrounding area. In terms of the concerns raised that some of the dwellings would step forward of the existing building lines, the Committee will note that the Conservation, Design and Landscape Manager (Conservation and Design) has not raised any objections. Whilst it is recognised that the proposed scheme would not be wholly compatible with the original open ethos of the development, the building lines were only loosely defined, the main body of Hillingdon Park does not lie within a Conservation Area and that the narrowing up of the street scene and the channelling of views could add additional depth and interest to the existing layout. Further, it is recognised that there is a balance to be struck between the siting of the dwellings and the preservation of as many of the significant trees as possible. The proportions and designs of the proposed dwellings are not considered to be out of context with existing dwellings on Hillingdon Park, and there is no objection to the more contemporary approach taken to some of the dwellings, subject to the use of a dark coloured roof tile to ensure cohesion. It is considered that the proposed development would preserve the character and appearance of the Conservation Area, the boundary of which runs through the four plots at the southern end of Hillingdon Park. On balance, it is considered that whilst the scheme would add a more contemporary feel to Hillingdon Park, it would still respect the character of the original 1960's development and would be in compliance with the aims of Policies EN 4 and EN 8 of the adopted North Norfolk Core Strategy. Landscaping and biodiversity Trees on the remaining vacant plots at Hillingdon Park have grown since the approval of the Outline Permission granted in 1966. As such, to enable the remaining plots to be developed, it is inevitable that there will be some tree loss. The Committee will note that the Conservation, Design and Landscape Manager (Landscape) has been consulted and comments that, whilst approximately 120 trees would be felled to accommodate the development, a comprehensive landscaping and planting scheme would result in the replanting of 160 trees and 140 shrubs to assist in restoring the existing woodland character of Hillingdon Park. Subject to the imposition of conditions, the Conservation, Design and Landscape Manager has not therefore raised any objections to the scheme. In respect of biodiversity, an ecological Survey has been submitted and the Committee will note no objection has been raised by the Landscape Officer subject to conditions in this respect. The proposal is acceptable under Policy EN9 of the adopted North Norfolk Core Strategy. Drainage Concerns have been expressed by local residents, Overstrand Parish Council and the Local Member in respect of drainage. The Committee will note that the Head of Coastal Strategy would object to the use of Development Committee 20 18 December 2014 soakaways for any additional surface water runoff from the proposed dwellings given concerns in respect of the potential risk of increased groundwater impacting on cliff stability. The Committee will also note the comments from the Council's Planning Legal Manager, confirming that the permission for estate roads and surface water drainage (E4909) remains extant. In response to the concerns raised, and whilst it would be at variance with the approved drainage scheme (E4909), the Agent is proposing the installation of surface water harvesting tanks with an overflow into the mains system. Given the greater awareness of the potential for coastal erosion than was the case in the 1960s, this is considered to be an appropriate approach, and could be secured by way of a condition on any planning approval. Highway safety Hillingdon Park is an unadopted road and County Council (Highways) have indicated that there is no present intention to change this situation. In the absence of Highway objections given the Outline planning consent, it is not considered that the application could be refused on highway safety grounds. Impact on neighbouring dwellings Concerns have been expressed by the owners of many of those properties adjacent to the proposed dwellings in respect of loss of amenity, loss of privacy, overshadowing, overbearing, loss of daylight, disturbance and noise nuisance etc. It is recognised that the development of the remaining plots would result in some shortfalls in the Basic Amenity Criteria recommendations, with existing properties having windows facing towards the proposed plots. Shortfalls are greatest between the proposed dwelling at Plot 6 and existing dwellings to the east and west, Plot 7 and the existing dwelling to the west and between the dwelling proposed at Plot 10 and the existing dwelling to the east. 28 Hillingdon Park, a single-storey dwelling to the east of the proposed single-storey dwelling at Plot 6, has facing windows serving a living room (classified as a secondary window, as the room is also served by a south facing window) and a kitchen door. Plot number 6 would have an east facing bedroom and bathroom window. In this case, the Basic Amenity Criteria would recommend 15m between two secondary windows and the development would provide circa 3.4m. 4 Hillingdon Park, a single-storey dwelling to the west of the proposed single-storey dwelling at Plot 7, has facing windows serving a garage, bathroom and kitchen. The closest windows at Plot number 7 would serve a living/dining room (classified as a secondary use, as the largest windows serving the room would be to the south and north). The Basic Amenity Criteria would recommend 15m between secondary windows and the development would provide circa 6.7m. With both of the above, it should be recognised that the windows would be at ground floor level; that the secondary windows would not sit directly opposite each other; that a condition could be imposed to ensure boundary treatment is of a suitable height to prevent views between the properties; that dwellings within Hillingdon Park are generally fairly close-knit and that the sites already have outline planning permission for the erection of a dwelling. Development Committee 21 18 December 2014 30 Hillingdon Park, a single-storey dwelling to the west of the proposed single-storey dwelling at Plot 6, has facing windows serving a lounge (classified as a secondary use, as the largest window serving the room is to the south), conservatory, bedroom and bathroom. The living/dining room at Plot number 6 would be served by glazing (classified as a secondary use, as the room would also be served by both north and south facing windows). Whilst the Basic Amenity Criteria would recommend 15m between two secondary windows and the development would only provide circa 4.4m, it is recognised that the glazing would be to the apex only and would therefore be high-level, not allowing overlooking towards number 30. 11 Pauls Lane, a two-storey dwelling to the east of the proposed single-storey dwelling at Plot 10, has facing windows serving a primary living room window at ground floor level and a secondary bedroom window at first floor level. Plot number 10 would have a facing bedroom/study window and a bathroom window. In this case, the Basic Amenity Criteria would recommend 18m between a primary and a secondary window and the development would only provide circa 9.3m. In this instance, it is recognised that the proposed windows would be at ground floor level, that the windows would not sit directly opposite each other, that there is a boundary fence between the sites which would help to prevent views between the properties, that dwellings within the vicinity are generally fairly close-knit and that the site already has outline planning permission for the erection of a dwelling. Inevitably, the proposed development would result in some loss of amenity/overbearing/overshadowing/overlooking/loss of daylight to neighbouring properties, but consideration should be given to the extant outline planning permission which accepts that the sites are building plots, to the existing character of Hillingdon Park where dwellings are generally fairly close-knit and the balance that needs to be struck between developing the site and protecting significant trees. It is considered that the scheme as submitted successfully balances these issues. The proposal is considered to be acceptable and would be in compliance with the aims of Policy EN4 of the adopted North Norfolk Core Strategy. Summary In summary, whilst the proposal has raised some concern with surrounding residents, given that it is accepted that the outline planning permission is extant and subject to the imposition of appropriate conditions it is considered that the proposed erection of the remaining ten dwellings would accord with relevant Development Plan policies. RECOMMENDATION: Delegate authority to the Head of Planning to APPROVE subject to: i) No new material issues being raised following receipt of amended consultation responses from Overstrand Parish Council or Anglian Water ii) Subject to the imposition of specific conditions listed below and all other conditions considered to be appropriate by the Head of Planning. 1 The development to which this permission relates must be begun not later than the expiration of two years beginning with the date on which this permission is granted. Reason: The time limit condition is imposed in order to comply with the requirements of Development Committee 22 18 December 2014 Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. 2 This permission is granted in accordance with the amended plan for Plot 4 (drawing number 2282-34e) received by the Local Planning Authority on 3 September 2014, the amended plans for Plots 1, 2, 3, 5, 7, 8 and 9 (drawing numbers 2282-40c, 2282-32c, 2282-31e, 2282,35d, 2282-37d (with the exception of the floor plan of Plot 8 included on the drawing), 2282-38d and 2282-39f) received by the Local Planning Authority on 22 September 2014, the amended plan for Plot 6 (drawing number 2282-36e) received by the Local Planning Authority on 26 September 2014, the amended Site Layout plan (drawing number 2282-20o) received by the Local Planning Authority on 29 October 2014 and amended plan for Plot 10 (drawing number 2282-32g) received by the Local Planning Authority on 7 November 2014 Reason: To ensure the satisfactory layout and appearance of the development in accordance with Policy EN 4 of the adopted North Norfolk Core Strategy. 3 Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995, (or any Order revoking, amending or re-enacting that Order with or without modification) no enlargements of or alterations to the dwellings or garages hereby permitted (including the insertion of any further windows or rooflights) shall be undertaken and no further building, structure or means of enclosure within the curtilage of the dwellings shall be erected unless planning permission has been first granted by the Local Planning Authority. Reason: The development of the site in the manner approved will necessarily result in a close knit group of dwellings where the siting, design and extent of any extensions/alterations must be controlled for the benefit of the residential and the visual amenities of the locality, and to protect trees and safeguard the character and setting of the site and surrounding trees from development which may threaten the longevity of trees, in accordance with Policies EN 4 and EN 8 of the adopted North Norfolk Core Strategy. 4 Notwithstanding the details indicated with the application and prior to their first use on site, precise details of the facing materials to be used in the construction of the external walls and roofs of the buildings shall be submitted to and approved by the Local Planning Authority in writing. The development shall then be constructed in full accordance with the approved details. Reason: In order for the Local Planning Authority to be satisfied that the materials to be used will be visually appropriate for the approved development and its surroundings, in accordance with Policies EN 4 and EN 8 of the adopted North Norfolk Core Strategy and Chapter 10 of the North Norfolk Design Guide. 5 Notwithstanding the details submitted with the application and prior to their erection, full details of the location, height, design and materials of all screen walls and fences (to include details of screen walls and fencing between existing and proposed dwellings) shall be submitted to and approved in writing by the Local Planning Development Committee 23 18 December 2014 Authority. Any screen wall and fence as approved shall then be erected concurrently with the erection of the dwelling with which it is related. Reason: In order for the Local Planning Authority to retain control over this aspect of the development in the interests of the relationship to nearby properties and the surroundings of the development in accordance with Policy EN 4 of the adopted North Norfolk Core Strategy and Chapter 10 of the North Norfolk Design Guide. 6 The apex glazing to the southern elevation on Plot 1 and to the western elevation of Plot 6 hereby permitted shall be installed a minimum of 1.8m above the floor of the room which they would serve. The glazing shall thereafter be retained in accordance with this detail. Reason: To prevent undue loss of privacy to the neighbouring property, in accordance with Policy EN 4 of the adopted North Norfolk Core Strategy as amplified by paragraphs 3.3.9-3.3.11 of the North Norfolk Design Guide. 7 Prior to the commencement of the development hereby approved, a scheme indicating surface treatments within plots shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall then be completed in accordance with approved details. Reason: To protect trees on the site, in accordance with the requirements of Policy EN 4 of the adopted North Norfolk Core Strategy. 8 The development be carried out in strict compliance with the amended Landscape Plan number 1141/01/Rev B, received by the Local Planning Authority on 28 August 2014 and in accordance with the amended Arboricultural Method Statement and Landscaping Plans received by the Local Planning Authority on 27 November 2014 (plan drawing numbers 1141/02/Rev D, 1141/03//Rev D and 1141/04 Rev D). Further, prior to the commencement of any development on site, a timetable for the methodology be submitted detailing arboricultural supervision shall be submitted to and approved in writing by the Local Planning Authority. Reason: To ensure that trees on site are protected from damage and to accord with the requirements of Policies EN 2 and EN 4 of the adopted North Norfolk Core Strategy. 9 All trees shall be planted in strict accordance with BS 8545: trees from nursery to independence in the landscape. The planting scheme shall be included in the arboricultural supervision timetable required by Condition number 8. Reason: To ensure that trees on site are protected from damage and to accord with the requirements of Policies EN 2 and EN 4 of the adopted North Norfolk Core Strategy. 10 Notwithstanding details submitted with the application and prior to the commencement of any development on Plot 10, a scheme indicating the species, number and size of new trees and shrubs at the time of their planting for Plot 10 shall Development Committee 24 18 December 2014 be submitted to and approved in writing by the Local Planning Authority. The scheme as approved shall be carried out not later than the next available planting season following the commencement of development or such further period as the Local Planning Authority may allow in writing. Reason: To protect and enhance the visual amenities of the area, in accordance with the requirements of Policy EN 4 of the adopted North Norfolk Core Strategy. 11 The development hereby permitted shall be carried out in strict compliance with Section 5 of the Ecological Survey submitted with the application and completed by C.J. Yardley and dated December 2013. Reason: To ensure that trees on site are protected from damage and to accord with the requirements of Policies EN 2 and EN 4 of the adopted North Norfolk Core Strategy. 12 Prior to the commencement of any development on site, details of the number and position of bat and bird boxes proposed for the development shall be submitted and agreed in writing with the Landscape officer. Unless an alternative timescale is first agreed in writing with the Local Planning Authority, the boxes shall then be erected and maintained for a period of at least ten years from the date of commencement of development, unless the prior written agreement of the Local Planning Authority has been given to any variation. Reason: To ensure that the impact of the development on protected species is appropriately mitigated in accordance with Policy EN 9 of the adopted North Norfolk Core Strategy. 13 No tree, shrub or hedgerow which is indicated on the approved plan to be retained shall be topped, lopped, uprooted, felled or in any other way destroyed, within ten years of the date of this permission, without the prior consent of the Local Planning Authority in writing. Reason: To protect and enhance the visual amenities of the area, in accordance with the requirements of Policy EN 4 of the adopted North Norfolk Core Strategy 14 Any new tree or shrub which within a period of ten years from the date of planting dies, is removed or become seriously damaged or diseased, shall be replaced during the next planting season with another of a similar size and species to the Local Planning Authority's satisfaction, unless prior written approval is given to any variation. Reason: To protect and enhance the visual amenities of the area, in accordance with the requirements of Policy EN 4 of the adopted North Norfolk Core Strategy. 15 Notwithstanding the details indicated on the submitted drawings no works shall commence on site until a detailed scheme for the off-site highway improvement works as indicated on drawing number 2282-20o have been submitted to and Development Committee 25 18 December 2014 approved in writing by the Local Planning Authority in consultation with the Highway Authority. Reason: To ensure that the highway improvement works are designed to an appropriate standard in the interest of highway safety and to protect the environment of the local highway corridor, in accordance with Policy CT 5 of the adopted North Norfolk Core Strategy. 16 Prior to the first occupation of the development hereby permitted the off-site highway improvement works referred to in condition number 15 shall be completed to the written satisfaction of the Local Planning Authority in consultation with the Highway Authority. Reason: To ensure that the highway network is adequate to cater for the development proposed, in accordance with Policy CT 5 of the adopted North Norfolk Core Strategy. 17 Prior to the first occupation of the development hereby permitted the proposed on-site car parking areas shall be laid out in accordance with the approved plans and retained thereafter available for that specific use. Reason: To ensure the permanent availability of the parking manoeuvring area, in the interests of highway safety, in accordance with Policy CT 6 of the adopted North Norfolk Core Strategy. 18 Notwithstanding any details submitted with the application, no development shall be carried out until such time as details of proposed surface water disposal from the dwellings hereby permitted have been submitted to and approved in writing by the Local Planning Authority. The development shall thereafter be carried out in full accordance with the approved details. Reason: To ensure that satisfactory drainage is provided for the development in accordance with Policy EN10 of the adopted North Norfolk Core Strategy. (4) SCOTTOW - PF/14/1334 - Installation and operation of a ground mounted solar photo voltaic array to generate electricity of up to 50MW capacity comprising photo voltaic panels, inverters, security fencing, cameras and other association infrastructure; Former RAF Coltishall, Lamas Road for Scottow Moor Solar Limited Major Development - Target Date: 27 January 2015 Case Officer: Mr G Lyon Full Planning Permission CONSTRAINTS Countryside Conservation Area Archaeological Site Development Committee 26 18 December 2014 Scheduled Ancient Monument Contaminated Land Controlled Water Risk - High (Ground Water Pollution) Controlled Water Risk - Medium (Ground Water Pollution) Tree Preservation Order Airbase Technical Area RELEVANT PLANNING HISTORY PLA/19960183 GF - Renewal of security fence Approved 10/04/1996 PF/10/0063 PF - Erection of a 70m high Wind Monitoring Mast for a period of 3 years Withdrawn by Applicant 17/02/2010 11:08:22 BX/14/0061 BX - Recycling and restoration of runway areas (County reference: C/1/2013/1020) Withdrawn by Applicant 24/11/2014 BX/14/0422 BX - Use of land for fire training purposes including the siting of containers, modular buildings and portable toilets (County ref: Y/1/2014/1003) Approved 19/06/2014 PF/14/0642 PF - Change of use of former munitions stores to B8 storage Approved 18/07/2014 PF/14/1038 PF - Change of use of hanger to B2 and B1 use (general and light industrial use) and associated outside storage Approved 13/11/2014 THE APPLICATION Proposes the erection of a solar farm with a capacity of up to 50MW set across approximately 87 hectares of land on part of the former RAF Coltishall site (now known as Scottow Enterprise Park). The solar farm straddles the District boundaries of North Norfolk and Broadland with the larger part of the site within North Norfolk District. A separate application has been submitted to be determined by Broadland DC (BDC). A 50MW solar farm equates to approximately 200,000 individual solar panels to be installed on site. The panels would be sited on the grassed areas of the former flying field airfield but not on the existing runway or perimeter tracks. The solar farm would be located within six separate fenced areas. The panels would be ground mounted on angled racks with the highest point of the panels rising to approximately 2.6 metres above ground level with rows typically 4m to 6m apart. The site would be enclosed by security/deer fencing (colour and design to be agreed). Within the fenced areas the applicant proposes to house approximately 30 inverter units which convert the direct current generated by the solar panels into alternating current to feed into the electricity grid. The applicant has indicated that a CCTV system will be installed with cameras mounted on 4m columns. However, specific details of the cameras to be installed and their locations is yet to be finalised. The application is supported by a Planning Statement, Design and Access Statement, Heritage Assessment, Landscape and Visual Impact Assessment, Ecological Assessment, Transport Statement, Flood Risk Assessment, Statement of Community Involvement and Environmental Risk Assessment. In addition photomontage/visualisations of the existing site and proposed development have been submitted. An aviation summary and a supplementary statement have also been Development Committee 27 18 December 2014 submitted which are attached at Appendix 1. REASONS FOR REFERRAL TO COMMITTEE To comply with Committee requests for all solar farms to be determined by the Development Committee. PARISH COUNCIL - Scottow Parish supports this application but has continued concerns about traffic movements to and from the site through the Badersfield area. REPRESENTATIONS One representation/comment has been received. Summary of comments: Vitromite Ltd as immediate business neighbours here on the former base respectfully submit that NNDC planning authorities put certain reserved matters in place. To ensure the possibility for the existing high quality runway, touchdowns and perimeter tracks to remain as publicly controlled available asset to allow future business development. Vitromite Ltd are reminded of NNDC and BDC planning policy for the Aerodrome to encourage business (manufacturing, industrial processes and controlled and measured air-craft usage) The planning documents presently on view do not clarify this in air usage terms, but in fact details included in the formal specific planning application documents would exclude the runway from aircraft usage for the term of the lease. Vitromite have need for support in our longer (4-5 year) term business plan which includes creating up to 400 jobs here at the former base to allow some proactive planning for a controlled and publicly agreed humanitarian role for the runway and its ability to be safely utilised. This would not exclude a much welcomed photo voltaic ground array but in its apparent present form the unreserved acceptance of the application would seriously compromise our intentions surrounding the Vitromite business model constructed specifically around former Battle of Britain and Cold War Aerodrome and its assets. Response from Tim Edmunds (Norfolk County Council): The County Council's Cabinet on the 12 May 2014 agreed to expand the scale of ground based solar at the former RAF Coltishall site from 10MW (as set out in the consultation version of its 'Development Vision') to up to 49.9MW. The expansion of solar at the site has been welcomed by many, including those who had previously petitioned the Council for such a large scale solar farm, and now forms part of the Council's agreed 'Development Vision'. To deliver these expanded aspirations, the Council entered into a contract to lease land to a private sector company to enable them to pursue a scheme of that scale. That Company has subsequently submitted planning applications to both of your authorities. The contract the Council has entered into covers all the land within the peri-track either side of the runway to enable the developer to seek to achieve a 49.9MW scheme so as to maximise income to the Council. No other land (without encroaching actually on to the runway) is appropriate given the constraints of the site. As I understand it, achieving a 49.9MW solar scheme on the land the developer has an option on is very tight - hence the panel density and heights proposed and the fact that the fence line is set back from the runway by 2m and the panels a further 8m from the fence. The solar scheme is a significant element of the Council's 'Development Vision' for the site and will generate income that will enable the Council to operate and maintain the site. It will also contribute towards the investment required at this former airbase to create jobs, protect its heritage and enable public access to be further opened up. Development Committee 28 18 December 2014 I am aware of the representations that have been made concerning a desire for aviation to return to the County Council's site, and thought it appropriate to help clarify the position as far as the County Council as land owner is concerned, which is as set out in the report considered by the Council's Economic Development Sub Committee on 24 November 2014. The Sub Committee agreed the two recommendations contained in the report, also resolving to increase Member involvement in the regeneration of Scottow Enterprise Park through the formation of a Member Working Group (the details of which are due to be considered at their meeting on 19 January 2015). CONSULTATIONS English Heritage - Objection - The proposed development comprises the construction of an 86.64 ha solar farm within former airfield at RAF Coltishall, including landscaping, transformers, substations, security fencing and associated works. The development would be situated within RAF Coltishall Conservation Area, which includes the historic airfield, two scheduled monuments, and a number of locally listed buildings. Following our letter of the 19th November (Our Ref: P00437601) we have now received additional [visualisations] from the applicant for this scheme. We appreciate the effort the applicant has undertaken to produce these visualisations and have been very impressed with the high quality and usability of this data. Having considered all available information, we consider that the proposals would have a direct impact upon the historic airfield and conservation area and impact the setting of nearby designated heritage assets; resulting in a high level of harm to significance. It is our view that amendments to the design scheme should be employed to reduce the scale of the solar farm and lessen the level of adverse impact. We would recommend that the application is withdrawn or the decision deferred to enable consideration of design scheme changes to reduce impact and harm and ensure the economic benefit to the site is secured. See copy of original comments dated 29 November, response from the applicant dated 3 December and further response from English Heritage dated 5 December 2014 at Appendix 1. Environmental Health - No objection subject to conditions - I have noted the information submitted by the applicant and would wish the following conditions to be attached to any permission granted:• • No plant or machinery proposed to be installed on the site, as part of this permission shall be audible above background noise level beyond the boundaries of the site. Except in relation to the construction phase of the development, hereby permitted, no external lighting whatsoever shall be installed on the site unless planning permission has first been granted. In relation to the construction phase of the installation, considering the volume of deliveries to the site, I would also recommend that hours of work be limited to 07:00 – 18:00 Monday to Friday, 07:00 – 13:00 Saturdays, with no Sunday or bank holiday working. Environment Agency - No objection subject to conditions - We have no objection to the application provided that the four conditions regarding the protection of the water environment described below are included if you are minded to grant permission. We also offer advice regarding surface water management. Development Committee 29 18 December 2014 The water environment The geology of the site is comprised of Brickearth, a superficial deposit consisting of clay, silt and sand and is designated as a Secondary B Aquifer. The Brickearth overlies sands and gravels associated with the Wroxham Crag Formation, designated as Principal Aquifer which in turn overlies the Principal Chalk Aquifer. The site is not situated in a Source Protection Zone; however, there are groundwater abstraction boreholes to the north of the site. The site is considered to be of high environmental sensitivity in the northern half of the site and medium sensitivity over the rest. Land Contamination We are aware that the RAF Coltishall site has been subject to previous investigation; Engineering environmental risk assessment executive summary, Jacobs June 2010. However, this has been limited in the proposed development area, generally to the western side. Voluntary LNAPL remediation was carried out in the vicinity of BFI5 and in the northern eastern area where site investigation identified three main areas where LNAPL contamination in groundwater had occurred. At this time it was acknowledged that on the basis of the risk assessment remedial intervention in these areas was not warranted. The proposed development requires shallow piling across the site, cable runs and the construction of a transformer building. We are concerned that there is the potential for these groundworks to find previously undetected contamination within the unsaturated zone and potentially cause the mobilisation of existing groundwater contamination. We require sufficient information to be confident that the development will not cause or promote contamination of the groundwater. The proposed development area should be subject to investigation and assessment, with subsequent remediation, as may be necessary to ensure any residual levels of contaminants found to be present do not pose an unacceptable risk to the groundwater. Groundwater monitoring should also be undertaken before, during and post construction. This monitoring should be targeted and include those areas of the development where LNAPL has previously been identified but not remediated. In some locations it may be possible to utilise existing monitoring boreholes. Environment Agency Position We consider that planning permission could be granted to the proposed development as submitted if the following four planning conditions are included as set out below. Without these conditions, the proposed development on this site poses an unacceptable risk to the environment and we would object to the application. Condition 1 Prior to each phase of development approved by this planning permission no development approved by this planning permission, or such other date or stage in development as may be agreed in writing with the Local Planning Authority, shall take place until a scheme that includes the following components to deal with the risks associated with contamination of the site shall each be submitted to and approved, in writing, by the local planning authority: 1) A preliminary risk assessment which has identified: ï‚· a ll pre vious us e s ï‚· pote ntia l conta m ina nts a s s ocia ted with those uses ï‚· a conce ptua l m ode l of the s ite indica ting s ource s , pa thwa ys a nd re ce ptors ï‚· pote ntia lly una cce pta ble ris ks a ris ing from conta m ina tion a t the s ite . 2) A site investigation scheme, based on (1) to provide information for a detailed Development Committee 30 18 December 2014 assessment of the risk to all receptors that may be affected, including those off site. 3) The results of the site investigation and detailed risk assessment referred to in (2) and, based on these, an options appraisal and remediation strategy giving full details of the remediation measures required and how they are to be undertaken. 4) A verification plan providing details of the data that will be collected in order to demonstrate that the works set out in the remediation strategy in (3) are complete and identifying any requirements for longer-term monitoring of pollutant linkages, maintenance and arrangements for contingency action. Any changes to these components require the express written consent of the local planning authority. The scheme shall be implemented as approved. Condition 2 No commencement of any part of the permitted development or of each phase of development shall take place until a verification report demonstrating completion of works set out in the approved remediation strategy and the effectiveness of the remediation shall be submitted to and approved, in writing, by the local planning authority. The report shall include results of sampling and monitoring carried out in accordance with the approved verification plan to demonstrate that the site remediation criteria have been met. It shall also include any plan (a “long-term monitoring and maintenance plan”) for longer-term monitoring of pollutant linkages, maintenance and arrangements for contingency action, as identified in the verification plan. The long-term monitoring and maintenance plan shall be implemented as approved. Condition 3 No development should take place until a long-term monitoring and maintenance plan in respect of contamination including a timetable of monitoring and submission of reports to the Local Planning Authority shall be submitted to and approved in writing by the Local Planning Authority. Reports as specified in the approved plan, including details of any necessary contingency action arising from the monitoring, shall be submitted to and approved in writing by the Local Planning Authority. Any necessary contingency measures shall be carried out in accordance with the details in the approved reports. On completion of the monitoring specified in the plan a final report demonstrating that all long-term remediation works have been carried out and confirming that remedial targets have been achieved shall be submitted to and approved in writing by the Local Planning Authority. Condition 4 If, during development, contamination not previously identified is found to be present at the site then no further development (unless otherwise agreed in writing with the local planning authority) shall be carried out until the developer has submitted a remediation strategy to the local planning authority detailing how this unsuspected contamination shall be dealt with and obtained written approval from the local planning authority. The remediation strategy shall be implemented as approved. Reason: To protect and prevent the pollution of controlled waters (particularly groundwater associated with the underlying Secondary and Principal Aquifers, from potential pollutants associated with current and previous land uses) in line with National Planning Policy Framework (NPPF; paragraphs 109 and 121), EU Water Framework Directive, Anglian River Basin Management Plan and Environment Agency Groundwater protection: Principles and practice (GP3:2013) position statements. National Planning Policy Framework (NPPF) paragraph 109 states that the planning system should contribute to and enhance the natural and local environment by preventing both new and existing development from contributing to or being put at Development Committee 31 18 December 2014 unacceptable risk from, or being adversely affected by unacceptable levels of water pollution. Government policy also states that planning policies and decisions should also ensure that adequate site investigation information, prepared by a competent person, is presented (NPPF, paragraph 121). Surface water As the site area is over a hectare in Flood Zone 1 a Flood Risk Assessment; SLR, 407.05185.00001, October 2014 has been submitted to support the application. We have assessed the FRA and have no flood risk objections to the proposed development. The solar panels are to be installed so they are raised off the ground and the existing grass will be retained; rainfall will drain down the panels and will soak into the grass. The soil type is Brickearth; clay, silt and sand, therefore it is possible that the water may take time to infiltrate into the soil. Providing that the site is flat the water will pond on the site until it has infiltrated and should not flow off site. If the site is sloped it is possible surface water may run off in lines at the base of the solar panels and may flow downhill and off site. The site is relatively flat so the water should remain on the grass until it infiltrates. There is a slight easterly slope and any overland flows would join the ordinary watercourse to the east. Overall the development will replicate the existing infiltration greenfield drainage as the surface water will be retained on the site and infiltrate into the soil and should not increase flood risk elsewhere. If there are concerns that the water will run off the site then the land beneath the panels could be shaped into a dished topography to ensure the runoff collects beneath the panel and does not run off elsewhere. Alternatively swales and ditches on the eastern boundary could be constructed to collect any overland flows to prevent them running offsite. The soils should not be compacted during construction to inhibit infiltration into the soils. Conservation, Design and Landscape Manager (Conservation and Design) - No objection subject to conditions - The former RAF Coltishall site (including the airfield and runway) was designated a Conservation Area by NNDC in 2010. As part of this process eight buildings were included on the Councils ‘Local List’ in addition to the already designated Ancient Monument Blast Walls and Spitfire Pens. With this in mind RAF Coltishall should be seen as one of the Districts most important military sites of national significance. Whilst the airfield dates back to 1939 prior to the outbreak of WWII, its greatest significance comes from its Cold War development period. The survival of the intact runway hardstanding was an integral part of the decision to designate the base a Conservation Area. As a consequence of this designation, development proposals involving the runway should be viewed in the context of:- • • • Any harm to the character or appearance of the conservation area, as set out by Section 72 of the 1990 Planning (listed buildings and conservation areas) Act 1990, Any harm to the significance of the designated heritage asset as required by paragraph 132, 133 and 134 of the NPPF. North Norfolk Core Strategy Policy EN8 which requires development to preserve or enhance the character and appearance of designated assets which includes conservation areas. Development Committee 32 18 December 2014 In terms of the significance of the runway, RAF Coltishall served as a fighter base during WWII, and more latterly during the Cold War and Gulf Wars. During WWII the base initially had an open grass airfield and in 1944 this was reinforced by the installation of prefabricated pierced metal planking. The first composite runway was constructed in 1949 with large scale modifications in 1957 and 1959 to accommodate V bombers and heavier jet air craft. Unquestionably the runway has been subject to much physical alteration through its lifespan and this development adds to the historic significance and context of the site. The presence of the runway is essential to the wider understanding of the designated heritage asset (the conservation area) and the site as a whole. Views of the runway and areas of hardstanding and their relationship to surrounding structures are very important. The runway provides the focal point and original purpose to the site as an airfield. ‘The Conservation Area Designation Report’ adopted by the Council identifies three character areas within the site. The runway falls within Character Area 3 ‘The Airfield’ and is integral to the character and appearance and interrelationship of this area of the base. With the above in mind the significance of the runway and airfield is derived from:• • • • • • its historical phases of development, its relationship to the designated and non-designated infrastructure surrounding it, the interrelationship of views to and from as well as around the runway, the historic connections to the aircraft which used it, the association with the conflicts it was operational for, its construction and physical materials. In regards to the proposal, C&D have previously shown our support for new uses being secured for the RAF Coltishall site and certainly do not want to see the site preserved in aspic. We would encourage any use which would ensure the sites future viability provided this use also balances the long-term conservation of the base and the preservation of its heritage assets. The 49.9MW solar array will be split into six blocks and cover almost all the grass areas of the airfield being separated by the existing hardstanding runway and perimeter tracks. The development will therefore dominate the aforementioned ‘Character Area 3’ of the base. The six blocks of arrays have a height of approximately 3.0m and will be encircled by 2.1m high security fencing. With this in mind, there will unquestionably be an impact on the setting of the heritage assets on the base, their interrelationship and importantly the understanding and interpretation of the airfield. The detailed visualisations provided by the applicant are extremely useful in assessing the extent and degree of this impact. Whilst there will be impact on the longer panoramic views into and out of the airfield, these views are not totally lost. The panels being 3.0m in height still allow for some appreciation of the scale and extent of the airfield. There is also sufficient separation distance and buffer zones between the heritage assets and the panels in order that their appreciation at closer proximity remains unaltered. The submission also highlights the reversibility and 25 year lifespans of the proposal as well as the minimal total loss of fabric to the heritage assets. C&D must be mindful that the development is fully reversible and represents no long-term harm to the Conservation Area or the associated heritage assets on the base. It is also important to bear in mind the economic benefit and investment which the site desperately needs. It Development Committee 33 18 December 2014 should also be noted that the installation of the panels does not rule out or prohibit future aviation uses for the base. Whilst the solar arrays will erode our understanding of the positioning and spatial relationship of the designated features, and, to some extent, the evidence of their evolutionary sequence - the site is historically known for its development, technology and functional utilitarian appearance with which the development is not altogether dissimilar to. Provided the short-term impact of the development is offset by seeing the economic benefits of the solar farm invested back into the base and its heritage assets the development will have a positive impact on the site moving forward. In conclusion, whilst there will be harm to setting of the designated heritage assets, this harm is less than substantial due to the reversibility of the development, the ability to still appreciate the scale and extent of the airfield, the interrelationship of the heritage assets and the wider public benefit being secured. In the event of the application being approved the following condition should be attached:Once the solar array has reached the end of its 25year lifespan the panels and associated infrastructure shall be removed as soon as reasonably practicable. Prior to the commencement of development, full details of the 2.1m perimeter fencing shall be submitted to and approved in writing by the LPA. The work shall then be carried out only in strict accordance with the approved details. A section 106 agreement should be put in place which would ensure the economic benefits from the solar development be directed into the conservation, repair and consolidation of the heritage assets of the base. £25,000 was agreed as part of the Section 106 agreement at former RAF West Raynham for the conservation of the Control Tower – a sum equal or similar to this would seem appropriate. By virtue that the proposed will not substantially harm the significance of the designated heritage assets, C&D raise no objection to the application. Conservation, Design and Landscape Manager (Landscape) - The application proposes the erection of solar panels (and associated infrastructure) on the disused airfield of the former RAF Coltishall airbase to produce electricity. The airbase was decommissioned in 2006 and the airfield has not been in use since then. All of the concrete runways and taxiways remain in situ as does the majority of the buildings and other infrastructure associated with the old RAF station. The site has been designated a Conservation Area with the former WWII spitfire pens and cold war blast walls designated a Schedule Ancient Monument. The land surrounding the runways have been left to grass and are intermittently grazed by sheep or mown. The development site area covers 98ha with the actual ground area covered by solar panels being 67ha. A security fence is proposed, set back 2m from the site perimeter (effectively the concrete taxiways) with the solar panels set back a further 8m from the security fence. Currently the access to the site is via the main access drive into the former RAF base. To assist in the assessment of the effects of the development, the application has been supported by a Landscape and Visual Assessment prepared by Luke Broom-Lynne dated 4th October 2014, and an Ecological Assessment prepared by Wild Frontier Ecology dated September 2014. Both documents have been prepared in accordance Development Committee 34 18 December 2014 with recognised standards and procedures by suitably qualified professionals and are considered acceptable in principle. Notwithstanding other policy considerations, the principle of erecting solar panels on the former airfield is not contested. However, there remain some concerns regarding the landscape character and visual impact, and ecological impact. The main concern with the proposed development is the impact on a skylark population of District significance. The ecological assessment has identified that the site of the solar development has around 140 breeding territories of skylark, and the surrounding grassland a further 60 territories. This is an unprecedented number of breeding territories within such a small defined area. The skylark is a Red Listed bird of Conservation Concern due to the dramatic decline the overall population has suffered in the last few decades (primarily as a result of agricultural practices). The proposed development would severely adversely impact the skylark population on the site. The skylark is a Priority Species and is listed under Section 41 of the Natural Environment and Rural Communities (NERC) Act 2006. Priority Species have effectively replaced Biodiversity Action Plan (BAP) Species and are the species of principle importance for the conservation of biodiversity in England. Local Planning Authorities have a statutory duty under the NERC Act to conserve and enhance biodiversity with the S41 species to be used as a guide to implement that duty. Furthermore, the National Planning Policy Guidance states that pursuing the aim of sustainable development means moving from net losses in biodiversity to net gains. There is a current lack of clarity within the Ecological Assessment and submitted draft Mitigation statements as to what the overall impact would be and what mitigation is required, which is suitable or achievable. Some of this lack of clarity is based on the unknown construction timings of the development, which once confirmed may allow adequate mitigation and monitoring to be put in place via a Construction and Ecological Management Plan (CEMP). However, the solar farm will drastically reduce the available habitat for skylark resulting in a severe reduction in the skylark population and likely to put pressure on neighbouring populations as well. Following the ‘mitigation hierarchy’ which is embedded within the core principles of the National Planning Policy Framework, it is likely that both onsite mitigation, in the form of habitat creation/maintenance within the remaining grassland areas in the blue line, and offsite compensation, secured through a financial contribution, will be required to achieve no net loss of this Priority Species. However, as yet there is no confirmation that the required mitigation and compensation is achievable therefore the development fails to comply with the NPPF or local policy EN9 (as the skylark is a protected BAP species). Further concerns arise around the future maintenance of the solar farm and whether this will be mown or grazed by sheep. In Section 3.28 to 3.29 of the Planning Statement it indicates that the grass and scrub of the site is devoid of biodiversity, this is misleading given the value of the site to the local skylark population and to other species such as barn owls, kestrel, and other fauna. The use of the site by wintering bird populations is currently unknown as wintering bird surveys have not yet been completed. Until this survey information has been submitted, the full impacts of the development on ecology have not been assessed. The Design and Access Statement indicates that the security risks posed by the development can be met by a 2m high deer stock fence, this is re-enforced in the Development Committee 35 18 December 2014 Planning Statement which indicates that deer fencing is ‘less intrusive than standard mesh security fencing’ (Section 3.23). The use of deer stock fencing is an established method of security fencing on solar developments and would be appropriate in this location. It is therefore disappointing to see that 2.3m high standard wire mesh fencing is proposed in the plan entitled ‘10_fence and gate’. Although it is acknowledged that the airfield has an associated former industrial use and the proposed use has industrial connotations, the setting is within a rural landscape more befitting of the deer stock fencing. I can see no reason why stock deer fencing cannot be used as suggested in the D&A Statement and the Planning Statement. This would allow small mammals to access the site without the need for mammal gates at regular intervals as well as being less visually intrusive. In terms of the landscape and visual impacts, the submitted LVIA suggests that, subject to the implementation of mitigation planting, the development will not result in significant impacts to the local landscape character or visual receptors. This is generally concurred with, however there are concerns that the proposed mitigation planting may not be secured due to potential changes in the proposed access to the development. Mitigation planting has been proposed on the northern and southern ends of the old runway, as short to mid-range views of the development are possible from nearby public highways and permissive paths. However, there is the potential that a new access be developed from Cemetery Road to the north which may render the planting impractical and have a greater impact on the landscape. The majority of the former RAF base is owned by Norfolk County Council (with the exception of the prison, HMP Bure, and the residential housing). This is depicted by the land within the ‘blue line’ on the Module Layout plan. Any mitigation proposals, both for the landscape and visual impacts and also for the ecology impacts, which will be within the blue line, must be secured through a legal obligation to ensure that the mitigation is implemented and effective for the duration of the development. There is however concern that the use of the remaining land within the County Council ownership is still uncertain and that potential changes to the use may render some of the mitigation impossible, such as landscape planting and skylark mitigation. Section 5.26 of the Planning Statement suggests that the existing recently planted community woodland to west of the proposed solar farm is to be moved to the south of the former runway. Again, this will have knock on effects on the skylark mitigation and the retention of the green spaces as required of the Conservation Area Appraisal (S 4.31 of the Planning Statement). Overall there are a number of concerns about the proposal that have not yet been fully addressed in line with current policy guidelines. To summarise these are: • Skylark mitigation • Wintering bird impacts • Confirmation of type of security fencing • Confirmation from NCC that landscape mitigation is acceptable and deliverable for the timeframe of the solar development It is recommended that these issued be addressed prior to making a decision to ensure that the proposal is compliant with national and local policies. Broadland District Council - No response County Council (Highway) - The Transport Statement contains very little information in relation to traffic generation, however the Planning Statement is a little more forthcoming and helpfully lists not only vehicle numbers but also breaks the figures Development Committee 36 18 December 2014 down by vehicle type. Having regard to the volume and nature of traffic that previously accessed the operational RAF airbase and the fact that traffic to this site has significantly reduced since the base closed, it would not be realistic to recommend refusal of this application on highway grounds. Nevertheless, it is imperative that traffic follows the route indicated within the applicants supporting documents and accordingly I recommend the following condition:- • All traffic associated with the construction of the development will comply with the Traffic Access Route specified within the submitted planning statement and no other local roads unless approved in writing with the Local Planning Authority in consultation with the Highway Authority. Adjacent Parishes Buxton with Lammas Parish Council - Supports the application subject to following conditions: 1. the fencing and solar panels are sited far enough away from the runway (minimum 10 metres) and at a suitable height to allow future aeronautical use of the runway and the taxi-ing of aircraft at both ends of the site. 2. the applicants update their application to include this on their plans before it is approved. 3. the Scottow Enterprise Park (former RAF Coltishall) has its own access to the road network at a convenient point outside Badersfield village and that industrial traffic is not routed through Badersfield, a thriving and private residential village with no connection to the proposed industrial development. Tunstead Parish Council - resolved to have no objection providing a demolition fund is set up by the current owner to ensure complete and immediate clearance of the site after the voltaic panels stop working and preserving the access to and usage of the runway for the future. HUMAN RIGHTS IMPLICATIONS It is considered that the proposed development may raise issues relevant to Article 8: The Right to respect for private and family life. Article 1 of the First Protocol: The right to peaceful enjoyment of possessions. Having considered the likely impact on an individual's Human Rights, and the general interest of the public, approval of this application as recommended is considered to be justified, proportionate and in accordance with planning law. CRIME AND DISORDER ACT 1998 - SECTION 17 The application raises no significant crime and disorder issues. POLICIES North Norfolk Core Strategy (Adopted September 2008): Policy SS2: Development in the Countryside (prevents general development in the countryside with specific exceptions). Policy SS 4: Environment (strategic approach to environmental issues). Policy EN 2: Protection and enhancement of landscape and settlement character (specifies criteria that proposals should have regard to, including the Landscape Character Assessment). Policy EN 4: Design (specifies criteria that proposals should have regard to, including Development Committee 37 18 December 2014 the North Norfolk Design Guide and sustainable construction). Policy EN 7: Renewable energy (specifies criteria for renewable energy proposals). Policy EN 8: Protecting and enhancing the historic environment (prevents insensitive development and specifies requirements relating to designated assets and other valuable buildings). Policy EN 9: Biodiversity and geology (requires no adverse impact on designated nature conservation sites). Policy EN 10: Flood risk (prevents inappropriate development in flood risk areas). Policy EN 13: Pollution and hazard prevention and minimisation (minimises pollution and provides guidance on contaminated land and Major Hazard Zones). Policy EC 4: Redundant defence establishments (specifies criteria for development at redundant defence establishments). Policy CT 5: The transport impact on new development (specifies criteria to ensure reduction of need to travel and promotion of sustainable forms of transport). Policies of Broadland District Council Joint Core Strategy for Broadland, Norwich and South Norfolk 2011 (JCS), amendments adopted January 2014: Policy 1:To address climate change and promote sustainability, all development will be located and designed to use resources efficiently, minimise greenhouse gas emissions and be adapted to a changing climate and more extreme weather. Amongst a series of other items, development will therefore be located to minimise flood risk, mitigating any such risk through design and implementing sustainable drainage. The environmental assets of the area will be protected, maintained, restored and enhanced. Policy 2: All development will be designed to the highest possible standards creating a strong sense of place. In particular, development proposals will respect local distinctiveness including, amongst other items, the landscape character and historic environment. Policy 3: Development will where possible aim to minimise reliance on non-renewable high-carbon energy sources and maximise the use of decentralised and renewable or low-carbon energy sources and sustainable construction technologies. Broadland District Local Plan (Replacement) 2006 saved policies: Policy GS1: New development will only be accommodated within the settlement limits for the Norwich fringe parishes, market towns and villages. Outside these limits, development proposals will not be permitted unless they comply with a specific allocation and/or policy of the Plan. Policy GS3: Sets out general considerations to be taken into account in all new development proposals, including accessibility for all, access and highway safety, residential amenity, the character and appearance of the surrounding area, nature conservation, agricultural land, the historic environment, land drainage, ground conditions and air quality. Policy ENV2: For all development proposals a high standard of layout and design will be required with regard given to the scale, form, height, mass, density, layout, water, energy efficiency, storage of waste, landscape, access, crime prevention and the use of appropriate materials. This will include the consideration of the appearance and treatment of spaces between and around buildings and the wider setting of the development taking into account the existing character of the surroundings. Development Committee 38 18 December 2014 Policy ENV5: Requires, where appropriate the protection and promotion of natural or semi-natural features such as trees and hedges. Where possible, compensating features will be required where development is allowed which would result in the loss of important features. Policy ENV14: Development which would detract from the setting of a listed building will not be permitted. Policy ENV16: The character and appearance of conservation areas will be protected and enhanced. Policy ENV20: All sites of development proposals which appear to raise archaeological issues will be subject to an evaluation of their significance. Policy TRA14: Development will not be permitted where it would endanger highway safety or the satisfactory functioning of the local highway network. Policy CS7: Proposals for renewable energy projects will be permitted unless they would give rise to a significant adverse environmental impact. Policy CS14: Noise levels to be taken into account in the determination of planning applications. Development Management (DPD) Proposed Submission: Policy GC1 – Presumption in favour of sustainable development: When considering development proposals the Council will take a positive approach that reflects the presumption in favour of sustainable development contained in the NPPF. It will always work proactively with applicants jointly to find solutions which mean that proposals can be approved wherever possible, and to secure development that improves the economic, social and environmental conditions in the area Policy GC2 – Location of new development: New development will be accommodated within the settlement limits defined on the proposals map. Outside of these limits development which does not result in any significant adverse impact will be permitted where it accords with a specific allocation and/or policy of the development plan Policy GC4 – Design: Development will be expected to achieve a high standard of design and avoid any significant detrimental impact. Schemes which are of an innovative nature or which reduce reliance on centralised, non-renewable energy sources will be particularly encouraged. Proposals should pay adequate regard to specified criteria. Policy GC5 – Renewable energy: Proposals for renewable energy technology, associated infrastructure and integration of renewable technology will be encouraged where its impacts are (or can be made) acceptable. Policy EN1 – Biodiversity and Habitats: Development proposals will be expected to protect and enhance the biodiversity of the district, avoid fragmentation of habitats and support the delivery of a co-ordinated green infrastructure network. Where harmful impacts may occur, it should be adequately demonstrated that: I. The development cannot be located where it would cause less or no harm; and II. That adequate mitigation is incorporated; and Development Committee 39 18 December 2014 III. That the benefits of the development clearly outweigh the impacts Policy EN2 – Landscape: In order to protect the character of the area, development proposals should have regard to the Landscape Character Assessment SPD and, in particular, considering any impact upon key features stated. Policy EN4 – Pollution: Development proposals will be expected to undertake an assessment of the extent of potential pollution. Where pollution may be an issue, adequate mitigation measures will be required. Development will only be permitted where there will be no significant adverse impact upon amenity, human health or the natural environment. Policy TS3 – Highway Safety: Development will not be permitted where it would result in any significant adverse impact upon the satisfactory functioning or safety of the highway network. Supplementary Planning Document (SPD): Landscape Character Assessment SPD 2013: Identifies this part of the district as falling within Landscape Character Area D3: Coltishall Tributary Farmland. The SPD identifies a series of Landscape Planning Guidelines for this character area: • Seek to conserve the open, rural character of the area • Resist new development that would result in any diminution of the sparsely settled nature of the area or in any reduction in the sense of isolation and tranquillity within the area, which is devoid of large settlements and busy roads • Seek to conserve remaining subtle features of the historic landscape, including hedgerows, characteristic hedgerow trees and tracks • Seek to conserve the landscape setting of churches and halls • Seek to conserve the landscape setting of hamlets and villages • Seek to ensure that any new small-scale development in or on the edges of Tuttington, Lamas and Little Hautbois, responds to existing settlement pattern and built form character • Seek to ensure that any new development in or on the edges of Coltishall RAF base responds to existing settlement pattern and respects the landscape setting of Lamas and Little Hautbois • Seek to ensure new development does not reduce the smooth, predominantly uninterrupted skyline within the area • Seek to conserve wide expansive views contained by distant wooded horizons • Seek to conserve small pits, ponds and extraction sites MAIN ISSUES FOR CONSIDERATION 1. Environmental Impact Assessment 2. National Policy Development Committee 40 18 December 2014 3. Local Policy 4. Principle of the development 5. Landscape 6. Impact on Biodiversity 7. Impact on Residential Amenity 8. Light Pollution 9. Highway Safety 10. Impact on Footpaths 11. Flood Risk 12. Contamination 13. Archaeology & Impact on Listed Buildings and other Historic Assets 14. Renewable Energy and Community Benefits 15. Cumulative Impact Issues APPRAISAL Consideration of the application follows a Committee visit to the site and surrounding area. Environmental Impact Assessment (EIA) Officers have considered the proposal under the Town and Country Planning (Environmental Impact Assessment) Regulations 2011 and guidance within the Planning Practice Guidance (06 March 2014). A Screening Opinion was produced upon receipt of this application concluding that the solar proposal is not considered to be EIA development and the potential impacts could be properly and rigorously assessed through the standard planning process. Following the receipt of consultation replies, Officers remain of the opinion that the proposed solar farm is not EIA development. National Policy Guidance The National Planning Policy Framework (the Framework) came into effect on 27 March 2012. The Framework replaced a series of national policy statements, circulars and guidance, including Planning Policy Statement 22: Renewable Energy, Planning Policy Statement 5: Planning for the Historic Environment and Planning Policy Statement 7: Sustainable Development in Rural Areas. Although the thrust of the previous policy in PPS guidance has been carried forward into the Framework, the wording is more condensed. Significantly, Annex 1 to the Framework reaffirms that planning law requires that applications for planning permission must be determined in accordance with the development plan unless material considerations indicate otherwise. The Core Strategy (CS) was adopted in 2008 and there is no obvious conflict between the Framework and the relevant provisions of the CS in so far as matters relevant to the determination of this application. Chapter 10 of the NPPF - Meeting the challenge of climate change, flooding and coastal change states at paragraph 93: ‘Planning plays a key role in helping shape places to secure radical reductions in greenhouse gas emissions, minimising vulnerability and providing resilience to the impacts of climate change, and supporting the delivery of renewable and low carbon energy and associated infrastructure. This is central to the economic, social and environmental dimensions of sustainable development’. At paragraph 97 the NPPF states: Development Committee 41 18 December 2014 ‘To help increase the use and supply of renewable and low carbon energy, local planning authorities should recognise the responsibility on all communities to contribute to energy generation from renewable or low carbon sources. They should: • • • • • have a positive strategy to promote energy from renewable and low carbon sources; design their policies to maximise renewable and low carbon energy development while ensuring that adverse impacts are addressed satisfactorily, including cumulative landscape and visual impacts; consider identifying suitable areas for renewable and low carbon energy sources, and supporting infrastructure, where this would help secure the development of such sources; support community-led initiatives for renewable and low carbon energy, including developments outside such areas being taken forward through neighbourhood planning; and identify opportunities where development can draw its energy supply from decentralised, renewable or low carbon energy supply systems and for co-locating potential heat customers and suppliers’. More specifically, when assessing development proposals paragraph 98 of the NPPF states: ‘When determining planning applications, local planning authorities should: • • not require applicants for energy development to demonstrate the overall need for renewable or low carbon energy and also recognise that even small-scale projects provide a valuable contribution to cutting greenhouse gas emissions; and approve the application [unless material considerations indicate otherwise] if its impacts are (or can be made) acceptable. Once suitable areas for renewable and low carbon energy have been identified in plans, local planning authorities should also expect subsequent applications for commercial scale projects outside these areas to demonstrate that the proposed location meets the criteria used in identifying suitable areas’. In considering this proposal, officers have taken account of the advice set out within paragraph 14 of the NPPF which states: ‘At the heart of the National Planning Policy Framework is a presumption in favour of sustainable development, which should be seen as a golden thread running through both plan-making and decision-taking. …….. For decision-taking this means: • • approving development proposals that accord with the development plan without delay; and where the development plan is absent, silent or relevant policies are out-of-date, granting permission unless: • any adverse impacts of doing so would significantly and demonstrably outweigh the benefits, when assessed against the policies in this Framework taken as a whole; or • specific policies in this Framework indicate development should be restricted’. Development Committee 42 18 December 2014 The Department for Communities and Local Government published the online Planning Practice Guidance on 06 March 2014. The guidance includes an assessment of the particular planning considerations that relate to large-scale ground-mounted solar photovoltaic farms at Paragraph 13 Reference ID: 5-013-20140306. Particular factors a local planning authority will need to consider include: • • • • • • • encouraging the effective use of land by focussing large scale solar farms on previously developed and non-agricultural land, provided that it is not of high environmental value; that solar farms are normally temporary structures and planning conditions can be used to ensure that the installations are removed when no longer in use and the land is restored to its previous use; the proposal’s visual impact, the effect on landscape of glint and glare and on neighbouring uses and aircraft safety; the need for, and impact of, security measures such as lights and fencing; great care should be taken to ensure heritage assets are conserved in a manner appropriate to their significance, including the impact of proposals on views important to their setting. As the significance of a heritage asset derives not only from its physical presence, but also from its setting, careful consideration should be given to the impact of large scale solar farms on such assets. Depending on their scale, design and prominence, a large scale solar farm within the setting of a heritage asset may cause substantial harm to the significance of the asset; the potential to mitigate landscape and visual impacts through, for example, screening with native hedges; the energy generating potential, which can vary for a number of reasons including, latitude and aspect Other relevant National Planning Guidance includes National Policy Statements for Energy (NPS) published in July 2011 including: • • Overarching National Policy Statement for Energy (EN-1); and National Policy Statement for Renewable Energy Infrastructure (EN-3) Whilst the NPS are designed to guide decision makers in relation to nationally significant infrastructure, the guidance can also be considered relevant in the assessment of smaller schemes below 50MW capacity onshore. Local Plan Policy - North Norfolk Core Strategy The site is located within the Countryside policy area where Core Strategy Policy SS 2 would support the principle of renewable energy projects, subject to compliance with other relevant Core Strategy policies. Policy SS4 states that renewable energy will be supported where impacts on amenity, wildlife and landscape are acceptable. Policy EN 7 states: ‘Renewable energy proposals will be supported and considered in the context of sustainable development and climate change, taking account of the wide environmental, social and economic benefits of renewable energy gain and their contribution to overcoming energy supply problems in parts of the District. Proposals for renewable energy technology, associated infrastructure and integration Development Committee 43 18 December 2014 of renewable technology on existing or proposed structures will be permitted where individually, or cumulatively, there are no significant adverse effects on; • • • the surrounding landscape, townscape and historical features / areas; residential amenity (noise, fumes, odour, shadow flicker, traffic, broadcast interference); and specific highway safety, designated nature conservation or biodiversity considerations. In areas of national importance large scale renewable energy infrastructure will not be permitted unless it can be demonstrated that the objectives of the designation are not compromised. Small-scale developments will be permitted where they are sympathetically designed and located, include any necessary mitigation measures and meet the criteria above. Large scale renewable energy proposals should deliver economic, social, environmental or community benefits that are directly related to the proposed development and are of reasonable scale and kind to the local area’. When considering landscape and visual impact, officers have taken account of advice not only within CS Policy EN 7 (Renewable Energy) but also advice within Policy EN 2 (Protection and Enhancement of Landscape and Settlement Character) which states: ‘Proposals for development should be informed by, and be sympathetic to, the distinctive character areas identified in the North Norfolk Landscape Character Assessment and features identified in relevant settlement character studies. Development proposals should demonstrate that their location, scale, design and materials will protect, conserve and, where possible, enhance: • • • • • • • • the special qualities and local distinctiveness of the area (including its historical, biodiversity and cultural character) gaps between settlements, and their landscape setting distinctive settlement character the pattern of distinctive landscape features, such as watercourses, woodland, trees and field boundaries, and their function as ecological corridors for dispersal of wildlife visually sensitive skylines, hillsides, seascapes, valley sides and geological features nocturnal character the setting of, and views from, Conservation Areas and Historic Parks and Gardens. the defined Setting of Sheringham Park, as shown on the Proposals Map’. PRINCIPLE OF DEVELOPMENT There is no policy requirement for the applicant to undertake a sequential approach to site selection and therefore the key factors influencing location choice for the type of development proposed include, amongst other things, availability of land to accommodate the development and availability of and distance from electrical grid connection. The site is located on non-agricultural land and the principle of the proposed development in this location is considered acceptable subject to compliance with Core Strategy policies and relevant material considerations such as Government advice. Development Committee 44 18 December 2014 LANDSCAPE The site lies within the Low Plains (LP3) landscape character type as defined in the North Norfolk Landscape Character Assessment (SPD June 2009). The broad characteristics of this landscape type at the former RAF Coltishall site is a strong 'aerodrome character' with large expanses of hard and soft spaces. To the south of the site lies landscape described within the Broadland District Landscape Character Assessment SPD (Sept 2013) as Tributary Farmland (D3). Broadland District Council have been consulted, albeit that BDC are also the determining authority for the smaller section of proposed solar farm at the southern end of the runway. A key consideration is the effect a large area of solar panels and associated infrastructure has on the character and appearance of this character type and also the wider landscape. The proposed development would occupy approximately 87 hectares (approximately 215 acres) of non-agricultural land. The applicant has submitted a Landscape and Visual Impact Assessment (LVIA) which has been prepared in accordance with recognised standards and procedures by suitably qualified professionals and is considered acceptable in principle. The submitted LVIA suggests that, subject to the implementation of mitigation planting, the development will not result in significant impacts to the local landscape character or visual receptors. This is concurred with by the Council's Landscape Officer, however there are concerns that the proposed mitigation planting may not be secured due to potential changes in the proposed access to the development. Mitigation planting has been proposed on the northern and southern ends of the old runway, as short to mid-range views of the development are possible from nearby public highways and permissive paths. However, there is the potential that a new access be developed from Cemetery Road to the north which may render the planting impractical and have a greater impact on the landscape. This is a matter which requires further clarification from the applicant and landowner(s) but could be secured by way of planning conditions. In respect of loss of agricultural land, the Agricultural Land Classification (ALC) map produced by Natural England identifies the former RAF Coltishall site within the 'non-agricultural land' designation. Therefore technically no loss of agricultural land would occur. Notwithstanding the ALC designation the site has been used more recently for sheep grazing and it may be possible that sheep grazing could continue to take place under panels to manage the wildflowers and grassland and therefore could be seen as a form of farm diversification. Therefore, subject to the imposition of conditions to secure appropriate mitigation planting and landscape management, it is considered that the landscape impact of the proposal would be broadly compliant with relevant Development Plan policy. IMPACT ON BIODIVERSITY An Ecological Assessment dated Sept 2014 prepared by Wild Frontier Ecology has been submitted and has been prepared in accordance with recognised standards and procedures by suitably qualified professionals and is considered acceptable in principle. The main concern raised by the Council's Landscape Officer is the impact the proposed development would have on a skylark population of District significance. The ecological assessment has identified that the site of the solar development has Development Committee 45 18 December 2014 around 140 breeding territories of skylark, and the surrounding grassland a further 60 territories. This is considered to be an unprecedented number of breeding territories within such a small defined area. The skylark is a Red Listed bird of Conservation Concern due to the dramatic decline the overall population has suffered in the last few decades (primarily as a result of agricultural practices). The proposed development would severely adversely impact the skylark population on the site. The skylark is a Priority Species and is listed under Section 41 of the Natural Environment and Rural Communities (NERC) Act 2006. Priority Species have effectively replaced Biodiversity Action Plan (BAP) Species and are the species of principle importance for the conservation of biodiversity in England. Local Planning Authorities have a statutory duty under the NERC Act to conserve and enhance biodiversity with the Section 41 species to be used as a guide to implement that duty. Furthermore, the National Planning Policy Guidance states that pursuing the aim of sustainable development means moving from net losses in biodiversity to net gains. There is a current lack of clarity within the Ecological Assessment and submitted draft Mitigation statements as to what the overall impact would be and what mitigation is required and whether such mitigation is suitable or achievable. The Landscape Officer considers that some of this lack of clarity is based on the unknown construction timings of the development, which once confirmed may allow adequate mitigation and monitoring to be put in place via a Construction and Ecological Management Plan (CEMP). However, the solar farm will drastically reduce the available habitat for skylark resulting in a severe reduction in the skylark population and likely to put pressure on neighbouring populations as well. Following the ‘mitigation hierarchy’ which is embedded within the core principles of the National Planning Policy Framework, it is likely that both onsite mitigation, in the form of habitat creation/maintenance within the remaining grassland areas in the blue line, and offsite compensation, secured through a financial contribution, will be required to achieve no net loss of this Priority Species. However, as yet there is no confirmation that the required mitigation and compensation is achievable therefore the development fails to comply with the NPPF or local policy EN9 (as the skylark is a protected BAP species). Officers are in continual discussion with the applicant about this matter and the Committee will be updated orally regarding any further development towards achieving an appropriate mitigation scheme. RESIDENTIAL AMENITY The Committee has had the opportunity to view the development site from various locations and therefore will be able to appreciate the relationship between the nearest residential properties and the application site. In respect of impact of the solar farm itself on residential amenity, the nearest residential properties to the site itself are Honeysuckle and Sudan Cottages at the northern end of Frogge Lane. The dwellings are orientated north-east and south-west and side onto the former airbase perimeter fence which is approximately 32m to the west. The application site boundary is some 63m from the nearest of these dwellings with perimeter track and retained grassland in between including the dwellings curtilages which contain planting and some outbuildings. Whilst the proposed solar farm may be visible from a small number of other properties, given the distance between residential properties and the application site and having Development Committee 46 18 December 2014 regard to the height of the panels, it is not considered that the proposal solar farm would in any way result in overbearing impacts or loss of daylight or sunlight. The panels are designed to absorb sunlight and therefore glare is not likely to occur from the panels themselves. It is also to be noted that planting is proposed at this point of the application site boundary In respect of any CCTV systems to be installed on site, (which are generally required for insurance purposes), the applicant has not provided details of the type and number of cameras to be installed on site. Having learned from the experience of systems on other sites within the District, Officers consider that, because of the general distances from properties, appropriately positioned cameras would not be likely to pose a significant risk to the amenity of residents. Nonetheless, it is recommended that a condition be imposed requiring approval of the full details of any CCTV system prior to its installation to ensure that the CCTV to be installed is as unobtrusive as possible both in terms of visibility in the landscape and impact of amenity. Officers are of the understanding that no loudspeaker system is proposed and conditions could be imposed to ensure this remains so. In respect of noise or other disturbance it is not considered that the proposal would give rise to unacceptable impacts. Officers consider that the proposal would not likely result in any significant adverse impacts to residential amenity and the proposal would comply with the requirements of Core Strategy Policy EN 4. Nonetheless it is recommended that conditions be imposed to ensure, amongst other things, that noise impacts remain acceptable and to ensure that the CCTV system to be installed is first approved by the Local Planning Authority. LIGHT POLLUTION In respect of any concerns about light pollution, it is understood that the applicants are not proposing to erect external lighting. In any event, were the Committee minded to approve the application, conditions could be imposed which would prevent external lights being installed without the prior approval of the Local Planning Authority. HIGHWAY SAFETY It is considered that the proposed development, although large in scale, would not pose a highway safety risk during its operational life with very few vehicle movements associated with maintenance and repair of the panels once constructed and few vehicles movements associated with the maintenance of the grassland. It is only during the construction phase when a significant number of vehicle movements will be generated and it is delivery of the panels and associated equipment and materials to site together with construction workers that would be likely to create the most number of vehicle movements. The applicant proposes to access the site with construction traffic from the main north entrance via Badersfield. The applicant indicates that the construction phase would take between 16-24 weeks for a solar farm of this scale and has indicated that approximately 600 deliveries would take place to bring materials onto site. This is in addition to staff movements for the 50-100 members of staff on site each day at peak construction period (some of which are likely to arrive by minibus). The applicant has indicated they will employ banksmen to manage the traffic into the site. Notwithstanding the on-going concerns from residents in Badersfield about increasing Development Committee 47 18 December 2014 traffic passing through the settlement to access the former RAF Coltishall site, the Highway Authority have raised no objection to the proposal on the basis that traffic uses the access routes specified in the application (which could be secured by planning condition). Therefore, on the basis that the Highway Authority has no objection in principle to the development and subject to the imposition of conditions it is considered that the proposal would accord with Core Strategy Policies CT 5 and CT 6. IMPACT ON FOOTPATHS In relation to the impact of the development on footpath users, it is considered that the proposed development would not have any adverse impacts. FLOOD RISK The application site area is above 1 hectare in size and the applicant has submitted a flood risk assessment which has been assessed by the Environment Agency (EA). The Environment Agency have raised no objections to the proposal but have nonetheless provided some advice on measures that may be required to deal with surface water discharge. Subject to the imposition of conditions, the proposal would accord with Development Plan Policy EN 10. CONTAMINATION In respect of contamination, one of the primary risks relates to the previous military use of the site. In particular there is the risk of unexploded ordnance and the applicant would need to carry out necessary checks before work commences to ensure the risk to construction workers is minimised. In addition there are risks from contamination in the soil associated with the previous uses on the site. The Environment Agency have not objected to the principle of the development but have noted that 'The proposed development requires shallow piling across the site, cable runs and the construction of a transformer building. We are concerned that there is the potential for these groundworks to find previously undetected contamination within the unsaturated zone and potentially cause the mobilisation of existing groundwater contamination. We require sufficient information to be confident that the development will not cause or promote contamination of the groundwater. The proposed development area should be subject to investigation and assessment, with subsequent remediation, as may be necessary to ensure any residual levels of contaminants found to be present do not pose an unacceptable risk to the groundwater. Groundwater monitoring should also be undertaken before, during and post construction'. The Environment Agency have suggested the imposition of four conditions as set out above in their consultation reply. Given that the applicant wishes to commence on site early in 2015 if permission is granted, officers understand that further discussions are taking place between the applicant and the Environment Agency and the Committee will be updated orally if and when any further progress is made. Nonetheless the Committee would be entitled to approve the development with conditions if the matters are not progressed prior to determination. Subject to the imposition of conditions and notes attached to the permission, the proposal would accord with Development Plan Policy EN 13. Development Committee 48 18 December 2014 ARCHAEOLOGY & IMPACT ON LISTED BUILDINGS, CONSERVATION AREA AND OTHER HISTORIC ASSETS The former RAF Coltishall site (including the airfield and runway) was designated a Conservation Area by NNDC in 2010. As part of this process eight buildings were included on the Councils ‘Local List’ in addition to the already designated Scheduled Ancient Monument Blast Walls and Spitfire Pens. With this in mind RAF Coltishall should be seen as one of the Districts most important military sites of national significance. Whilst the airfield dates back to 1939 prior to the outbreak of WWII, its greatest significance comes from its Cold War development period. The survival of the intact runway hardstanding was an integral part of the decision to designate the base a Conservation Area. The applicant has submitted a Heritage Report produced by Donald Insall Associates which concludes that: 'The proposed scheme offers substantial public benefits of providing an optimum viable use for the site with environmental benefits which would secure the future of the important historic military landscape and its heritage assets in the long-term, with only relatively minimal and temporary ‘less than substantial’ harm to their significance. The proposals meet the tests for sustainable development, insofar as these relate to the historic environment in the National Planning Policy Framework, as well as North Norfolk County Council and Broad District Council policies and should be welcomed in heritage terms'. When considering the impact on historic assets, the Committee is advised to take account of advice not only within CS Policy EN 7 (Renewable Energy) but also Policy EN 8 (Protecting and Enhancing the Historic Environment) which states: ‘Development proposals…should preserve or enhance the character and appearance of designated assets, other important historic buildings, structures, monuments and landscapes, and their settings through high quality, sensitive design. Development that would have an adverse impact on their special historic or architectural interest will not be permitted’. In coming to its view the Committee should also take into account the advice contained within the National Planning Policy Framework (the Framework) which specifically addresses the need for conserving and enhancing the historic environment at paragraphs 126 – 141. Paragraph 132 states: ‘When considering the impact of a proposed development on the significance of a designated heritage asset, great weight should be given to the asset’s conservation. The more important the asset, the greater the weight should be. Significance can be harmed or lost through alteration or destruction of the heritage asset or development within its setting. As heritage assets are irreplaceable, any harm or loss should require clear and convincing justification. Substantial harm to or loss of a grade II listed building, park or garden should be exceptional. Substantial harm to or loss of designated heritage assets of the highest significance, notably scheduled monuments, protected wreck sites, battlefields, grade I and II* listed buildings, grade I and II* registered parks and gardens, and World Heritage Sites, should be wholly exceptional’. Development Committee 49 18 December 2014 Paragraph 133 states: ‘Where a proposed development will lead to substantial harm to or total loss of significance of a designated heritage asset, local planning authorities should refuse consent, unless it can be demonstrated that the substantial harm or loss is necessary to achieve substantial public benefits that outweigh that harm or loss, or all of the following apply: • the nature of the heritage asset prevents all reasonable uses of the site; and • no viable use of the heritage asset itself can be found in the medium term through appropriate marketing that will enable its conservation; and • conservation by grant-funding or some form of charitable or public ownership is demonstrably not possible; and • the harm or loss is outweighed by the benefit of bringing the site back into use’. Paragraph 134 states: ‘Where a development proposal will lead to less than substantial harm to the significance of a designated heritage asset, this harm should be weighed against the public benefits of the proposal, including securing its optimum viable use’. The former RAF Coltishall site was designated as a Conservation Area in 2010. In respect of the effect of the development on Conservation Areas, Section 72 of the Planning (Listed Buildings and Conservation Areas) Act 1990 places a general duty on planning authorities to pay special attention to the desirability of preserving or enhancing the character or appearance of a Conservation Area. This is coupled with the requirements of Core Strategy Policy EN8, which requires development to preserve or enhance the character and appearance of the Conservation Area. Officers consider that there is no doubt that the installation of nearly 200,000 solar panels across the site would adversely affect the character and appearance of the Conservation Area as clearly indicated within the photomontages produced by the applicant. This harm would arise across a large part of the former flying field and through the inclusion of ancillary structures and fencing which it is considered would change the fundamental character of the airfield from one of generally open uninterrupted views across the airfield to one partly masked by temporary low-level structures whilst the solar panels and related equipment are located on site. In addition the proposal would have some impact on the setting of the Scheduled Ancient Monuments located at the site including the numerous Cold War blast walls located predominantly on the eastern side of the site and non-designated blast walls on the south western side together with adverse impacts on the Spitfire Pen located at the north western side of the site. English Heritage have concluded that serious harm would arise to a number of designated heritage assets on site and have suggested that the scheme be withdrawn and redesigned to reduce its impacts. However English Heritage have stopped short of suggesting that 'Substantial Harm' would result and have concluded instead that 'Less than Substantial Harm' under NPPF paragraph 134 would result. Whilst Officers accept that harm would occur, it is appropriate to consider this harm to be 'less than substantial' because no important heritage assets are directly affected through physical works and the development itself is reversible without permanently damaging the heritage assets on site. Ultimately it is a matter of planning judgment for Development Committee 50 18 December 2014 the Development Committee in weighing the harm to heritage assets against the statutory duties under Section 72 and also against the public benefits arising from the proposal. On other similar proposals across the District, a financial contribution has been secured by developers to help maintain heritage assets on the site. It would seem appropriate to secure a similar arrangement in this instance and discussions are commencing with the applicant to secure a financial contribution for the maintenance of heritage assets throughout the lifetime of the development. Subject to the imposition of conditions to limit the time that the solar farm would be permitted on site and subject to the completion of a Unilateral Undertaking or S106 Obligation to secure funding of at least £25k towards the upkeep/maintenance of heritage assets on the site it is considered that the proposal would accord with the general aims of Core Strategy Policy EN 8. RENEWABLE ENERGY & COMMUNITY BENEFITS Policy EN 7 requires that large scale renewable energy proposals should deliver economic, social, environmental or community benefits that are directly related to the proposed development and are of reasonable scale and kind to the local area. The applicants have submitted a document titled 'Statement of Community Involvement'. This sets out how the local community were engaged at pre-application stage. The document refers to a number of possible community projects suggested at pre-application stage including provision of leisure or sporting facilities in the local community; provision of a footpath and/or cycle route across the site to link up Badersfield, Scottow and Coltishall; and the potential for residents to be provided with renewable energy or solar panels. The applicant refers to the possibility of further discussions taking place with the Local Planning Authority in respect of these projects but to date no such further discussions have taken place. Nonetheless consideration has to be given as to whether the suggested Community projects would comply with Government advice at paragraph 204 of the National Planning Policy Framework (the NPPF) and CIL Regulation 122 tests in respect that section 106 planning obligations “should only be sought where they meet all of the following tests: • • • Necessary to make the development acceptable in planning terms; Directly related to the development; and Fairly and reasonably related in scale and kind to the development” Officer advice is that the Development Committee should not give any weight to possible community projects when determining the application as they would be unlikely to pass the tests set out above. In respect of renewable energy benefits, the applicants have indicated that the proposed 49.9MW solar farm would generate enough electricity to supply approximately 15,000 homes with their annual electricity requirements. The applicant has not provided a breakdown of the expected number of KWh generated by the proposal. The most recent Department for Environment and Climate Change (DECC) figures of electricity usage per household suggested that approximately 4715.5 kWh of electricity were used per consumer (household) annually in North Norfolk. Using this figure the proposed solar farm would need to generate 70,732,500 KWh of electricity per annum to supply 15,000 homes. Development Committee 51 18 December 2014 The most recent large-scale solar at the former RAF West Raynham site was predicted to generate approximately 48.153GWh (48,153,000KWh) of electricity per annum based on a stated capacity of the solar farm of approximately 49.9MW (enough electricity to power approximately 10,212 homes annually). Officer therefore would question whether the figures quoted by the applicant are overstated. This is important when assessing the public benefits against harm. Officers would therefore suggest that a lower figure of 10-11,000 homes is used in the assessment of electricity generation. Nonetheless, the solar farm would make the proposal one of the largest solar farms in the country and would make a significant contribution towards meeting national renewable energy targets, to which significant weight can be attached. It is considered that, subject to the imposition of conditions to secure appropriate mitigation, the proposal would comply with the requirements of Policy EN 7. CUMULATIVE IMPACTS IN COMBINATION WITH OTHER PLANS AND PROJECTS IN THE AREA At the time of writing this report it is understood that there are no other plans or projects in the area which the Committee would need to be aware of in terms of assessing cumulative impacts in relation to the proposed solar farm at the former RAF Coltishall site. OTHER MATTERS During the consultation process a number of comments have been made about whether the runway at the former RAF Coltishall site could be brought into active service to transport goods into and out of the site in connection with existing and future planned business operations. Whilst the solar farm itself would not be located on the existing runway and therefore opens up the possibility of its use, the landowner (Norfolk County Council) has made clear that it does not see aviation use as part of its future plans for the site. On 24 November 2014, a report to County Council’s Economic Development Sub-Committee, stated: “4.2 Aviation The possibilities of aviation use at the former RAF Coltishall site have been a recurring theme since the based closed to military use. This has broadly followed a number of strands. Firstly, that Norwich International Airport (NIA) should be relocated to make use of the longer runway, and release the existing airport site for alternative commercial use, or housing. Secondly, the site could be used for other commercial aviation use, such as aircraft storage and breakage. Thirdly, that the site could be used for light aircraft and other related use such as ATC and heritage. 4.3 In terms of the relocation of NIA there are huge technical and economic obstacles in developing civil aviation use at Coltishall. There would need to be massive investment in redeveloping the operational infrastructure, and in off-site transportation improvements. NIA has plenty of capacity for expansion with no shortage of slots and a recently expanded terminal building capable of accommodating substantial increases in passenger numbers. NIA can meet the changing needs of short haul aircraft for decades to come. NIA have made Development Committee 52 18 December 2014 it clear that they do not want to relocate, that it would not make economic sense to move the operation further away from its catchment area, and would resist any proposals to do so. 4.4 The ad-hoc aviation use is not considered viable either. Recent enquiries to use the airfield for film production use have again highlighted a number of operational safety concerns over allowing aviation use to any real extent on an unlicensed facility. In taking forward the solar development, officers undertook an exercise to understand the compatibility between aviation and solar. The conclusion of this work was that if protection zones are provided for aviation use then a lost opportunity cost arises. Buffer / protection zones would be required, between the solar site and the parts of the airfield that may be used for aviation use – approximately 60 acres of potential solar development land would be ‘sterilised’ reducing the scale of the solar farm that could be accommodated on the site, reducing its financial viability and the income to the Council (without at this time any firm commercial aviation use offsetting this reduction). As a consequence the size of the solar farm agreed to be taken forward for planning consent (49.9MW) will, once complete, prevent the former airfield from being used for aviation purposes (at least until the panels are removed, which is unlikely before 2040). In addition to the above, the applicant has provided an Aviation Evaluation Summary Report prepared by aviation experts. This responds to the following questions posed by the applicants: • • • What the Civil Aviation Authority’s (CAA) requirements would be should the runway be utilised for aerodrome purposes; What supporting infrastructure would be required; and What criteria would the solar farm have to meet to enable the two uses to co-exist The report concludes that safeguarding of the runway and ancillary areas would have significant implications for the design and financial viability of the proposed solar farm. In addition, safeguarding of the runway is not considered to be viable in the absence of a firm commitment to utilise it in the near future given the commitment this would require with respect to capital costs and on-going revenue requirements. The runway at the former RAF Coltishall site is not protected in planning policy terms and ultimately it is a matter of economic viability for the landowner in terms of return on their investment. Officer advice therefore is to assess the proposal before the Committee on the basis that no economic use of the runway is currently planned. Refusal based on the potential of the solar farm to inhibit the use of the former runway could not be justified in planning terms. SUMMARY The installation of a 49.9MW solar farm would, amongst other things, have adverse impacts on heritage assets including Scheduled Ancient Monuments and the wider Conservation Area and, without appropriate mitigation, could result in adverse landscape impacts and significant impacts on breeding skylarks. At the time of writing this report it was not concluded as to whether appropriate mitigation could be sought to address the impact on skylark habitat but, if appropriate mitigation was considered possible, then it would be a matter of weighing the impacts of the proposal against any public benefits (whilst having regarding for the Development Committee 53 18 December 2014 requirements under Section 72 of the Planning (Listed Buildings and Conservation Areas) Act 1990). The public benefit of the proposal in terms of renewable energy generation is a material consideration to which significant weight should be afforded in accordance with the guidance set out in paragraph 98 of the National Planning Policy Framework (NPPF). If appropriate mitigation for breeding skylarks is not possible and/or appropriate landscape mitigation is not secured then these are further matters which would weigh against the grant of planning permission. The Committee will be updated orally regarding progress towards achieving acceptable landscape and ecological mitigation for skylarks. In all other respects, the proposal would accord with Development Plan policies and, subject to the imposition of appropriate conditions and the completion of a Unilateral Undertaking or S106 Obligation to secure funding for the maintenance of heritage assets and to secure monitoring of the effectiveness of required landscape and biodiversity mitigation, the proposal would comply with relevant Development Plan policies. RECOMMENDATION: DELEGATED AUTHORITY TO THE HEAD OF PLANNING TO APPROVE subject to confirmation that appropriate landscape and breeding skylark habitat improvements can be secured and subject to the completion of a Unilateral Undertaking or S106 Obligation to secure at least £25k for the maintenance of heritage assets on site and to secure monitoring of the effectiveness of required landscape and biodiversity mitigation and subject to the imposition of specific conditions listed below: • 30 Year permission (including removal of equipment after this time); • • Landscape and Biodiversity Enhancements (including a Landscape and Ecological Management Plan); Agreement of Construction Traffic Management Plan and Access Route; • No loudspeakers or CCTV systems to be installed unless permission granted; • No lighting to be installed unless permission granted And all other conditions considered to be appropriate by the Head of Planning. (5) SUTTON - PF/14/1382 - Erection of detached single-storey dwelling; The Horseshoe, The Street for Mr Cutting Minor Development - Target Date: 18 December 2014 Case Officer: Miss C Ketteringham Full Planning Permission CONSTRAINTS Countryside Development Committee 54 18 December 2014 RELEVANT PLANNING HISTORY PLA/19761425 PO - Erection of three residential dwellings Refused 15/11/1976 PLA/19761675 PO - Erection of two dwellings Approved 10/01/1977 PLA/20020154 PO - Erection of three dwellings Refused 21/05/2002 PLA/20021353 PO - Erection of one dwelling Approved 30/07/2003 PLA/20031271 PF - Erection of detached dwelling with garage Withdrawn 22/09/2003 PLA/20040111 PF - Erection of four detached dwellings Approved 15/03/2005 PLA/20040139 PF - Erection of dwelling Refused 25/03/2004 PLA/20050398 PO - Erection of two-storey dwelling Refused 05/07/2005 PLA/20060520 PF - Variation of condition 13 of planning permission reference 20040111 (four dwellings) to enable the development to take place in accordance with revised flood risk assessment Approved 10/08/2006 PF/11/0937 HOU - Erection of double garage, attached two bay cart shed, storage areas at ground level and in roof space Refused 11/11/2011 PF/12/0076 HOU - Erection of double garage/two bay cart shed Withdrawn by Applicant 18/03/2012 THE APPLICATION Is a full application for the erection of a detached three bedroom bungalow. Access is from a private drive known as The Horseshoe. Parking is provided with a single attached garage and parking spaces in front of the garage. REASONS FOR REFERRAL TO COMMITTEE At the request of Councillor Stevens having regard to the following planning issue(s): The application site is surrounded by housing and could be regarded as an infill plot. PARISH COUNCIL Sutton Parish Council - no response REPRESENTATIONS None CONSULTATIONS Highways Authority - no objection subject to a condition on the provision of parking. HUMAN RIGHTS IMPLICATIONS It is considered that the proposed development may raise issues relevant to Article 8: The Right to respect for private and family life. Article 1 of the First Protocol: The right to peaceful enjoyment of possessions. It is considered that refusal of this application as recommended may have an impact on the individual Human Rights of the applicant. However, having considered the likely impact and the general interest of the public, refusal of the application is considered to be justified, proportionate and in accordance with planning law. Development Committee 55 18 December 2014 CRIME AND DISORDER ACT 1998 - SECTION 17 The application raises no significant crime and disorder issues. POLICIES North Norfolk Core Strategy (Adopted September 2008): SS 2 - Development in the Countryside EN 4 - Design CT 5 - The transport impact of new development CT 6 - Parking provision MAIN ISSUES FOR CONSIDERATION 1. Principle of development 2. Contrary to Policy SS 2 APPRAISAL Although the site is within the centre of Sutton it is within the Countryside policy area. (Sutton is not a designated settlement within the adopted North Norfolk Core Strategy.) Within the Countryside policy area under the terms of Policy SS 2 proposals for new market housing should not be permitted. The access to this plot is from The Horseshoe which is a small development of four houses, which was developed on land originally part of Horseshoe Cottages curtilage. This development was approved during the period of the policies of the earlier Local Plan which allowed for small groups of infill dwellings. This site was not part of that garden but the garden of an adjacent dwelling The Pightle. The plot had been detached from that property sometime before 2006. There are no highway objections to this current proposal. A previous application on the site was refused on access and visibility grounds. The proposal proposed a different access arrangement from another private drive. As regards the design for the dwelling proposed, at five metres to the ridge this is relatively low and the dwelling has a hipped roof. The relationship with the adjacent dwelling (The Pightle) is considered acceptable. The dwelling on the other side is a two storey dwelling with a blank gable wall that would be unaffected by the proposed development. While the bungalow is of no outstanding architectural merit it would fit in with the surrounding development. Reasonably good quality materials are proposed for its construction. Though the proposed bungalow covers a good proportion of the plot, enough space is left for a reasonable size garden and parking for at least two cars. The National Planning Policy Framework clarifies the primary status of the Development Plan as paragraph 12 states it 'does not change the statutory status of the development plan as the starting point for decision making. Proposed development that accords with an up-to-date Local Plan should be approved, and proposed development that conflicts should be refused unless other material considerations indicate otherwise'. The Council currently has a demonstrable 5 year land supply as is required by the National Planning Policy Framework for the North Norfolk Core Strategy to be regarded as up-to-date. In conclusion, while there are no objections to the property on design or amenity grounds, the proposal is contrary to Policy SS2. Accordingly, the application is recommended for refusal. Development Committee 56 18 December 2014 RECOMMENDATION: To refuse for the reason specified below. The proposal constitutes an unacceptable form of development in the Countryside policy area where there is a general presumption against residential development. It is considered that the applicant has failed to demonstrate satisfactorily that there are material considerations to justify a departure from Development Plan policy in this case. The proposal is therefore considered to be contrary to the adopted Development Plan Policy SS 2. (6) APPLICATIONS APPROVED UNDER DELEGATED POWERS ALDBOROUGH - PF/14/1302 - Change of use from A4 (public house)/residential to C3 (Residential); The Old Red Lion, The Green for Mr I Webster (Full Planning Permission) ANTINGHAM - PF/14/1261 - Erection of single-storey rear extension and installation of rooflights to facilitate conversion of loft to habitable accommodation; Kimberley, Bradfield Road, Southrepps for Mr and Mrs Richardson (Householder application) AYLMERTON - PF/14/1324 - Erection of single-storey front extension; Edgewood Cottage, Holt Road for Mrs J Wright (Householder application) BACTON - NMA1/14/0619 - Non-material amendment request to alter south wall to make study rectangular; Seabrink, Beach Road for Mr W & Mrs E Coombe & Hay (Non-Material Amendment Request-Household) BARSHAM - NMA1/11/0167 - Non material amendment request to permit insertion of two additional windows to the first floor west elevation; The Gatehouse, Long Lane, East Barsham for Mrs Williamson (Non-Material Amendment Request-Household) BARTON TURF - PF/14/1199 - Erection of single storey rear extension; 4 School Road, Barton Turf, Norwich, NR12 8AT for Mr & Mrs Wilcox (Householder application) BEESTON REGIS - PF/14/1306 - Erection of single-storey side/front extension; Anglia Mowers, Britons Lane for Anglia Mowers (Full Planning Permission) BINHAM - PF/14/1273 - Installation of two dipole antennas, a 1.8m diameter satellite dish, two GPS antennas and ancillary development; Ntl Site 11407, Cockthorpe Airfield, The Street, Cockthorpe for Arqiva Ltd (Full Planning Permission) BLAKENEY - PF/14/1281 - Erection of single-storey dwelling; Sea Grass, Saxlingham Road for Mr and Mrs C Miller (Full Planning Permission) Development Committee 57 18 December 2014 BLAKENEY - PF/14/1053 - Erection of 0.9 metre boundary fence and gates; 41 High Street for Mrs J Robb (Householder application) BLAKENEY - LA/14/1068 - Erection of two-storey and single-storey extensions to link dwelling to annexe, single-storey extension to annexe and erection of boat store to front elevation of annexe; 50 High Street for Mr & Mrs M Archer (Listed Building Alterations) BODHAM - NMA3/14/0035 - Non material amendment request to permit to insert additional rooflight to rear elevation roof slope; Plot 2, John William Way for Mr and Mr Prince (Non-Material Amendment Request) BRININGHAM - NMA1/12/0242 - Non material amendment to permit change of windows to ground floor west and north elevations and door and window to window in east elevation and rooflight to south elevation; Moriah Cottage, Dereham Road for Mr P Williams (Non-Material Amendment Request-Household) BRISTON - PF/14/1203 - Erection of side extension & raise roof height to existing detached garage; 4 Thornton Close for Mr and Mrs Coles (Householder application) BRISTON - NP/14/1464 - Prior notification of intention to erect agricultural storage building; Markshall Game Farm, Craymere Beck, Melton Constable for Mr V Daniels (Prior Notification (Agricultural)) CATFIELD - PF/14/1277 - Erection of detached double garage; Thatch Croft, The Street for Mr Castleton (Householder application) CLEY-NEXT-THE-SEA - PF/14/1282 - Removal of condition 4, 5 and 6 of planning permission 10/1070 to permit permanent residential occupation; 2 Rectory Hill Barns, Holt Road for Mr Lacoste (Full Planning Permission) CORPUSTY AND SAXTHORPE - PF/14/1197 - Change of use of land to garden and erection of double garage; Manor House, Norwich Road, Corpusty for Mr G Sinclair (Full Planning Permission) CROMER - PF/14/0975 - Erection of summer house; Estate Managers Office, Hanover Court, Overstrand Road for Hanover Housing (Full Planning Permission) CROMER - PF/14/1237 - Erection of replacement two-storey side/rear extension; The Watch House, The Gangway for Mr Hill (Householder application) CROMER - LA/14/1238 - Erection of two-storey side/rear extension, replacement single-storey rear extension with roof terrace and internal and external alterations; The Watch House, The Gangway for Mr Hill Development Committee 58 18 December 2014 (Listed Building Alterations) CROMER - PF/14/1214 - Insertion of external door and creation of new access for flat; 1 The Gangway for Mr M Newlands (Householder application) CROMER - LA/14/1215 - Insertion of external door and internal alterations to facilitate creation of new access to flat; 1 The Gangway for Mr Newlands (Listed Building Alterations) DILHAM - PF/14/1152 - Conversion of agricultural barn to residential dwelling and erection of detached single garage and creation of new access; New Barn, Honing Road for Fyebridge Limited (Full Planning Permission) DUNTON - NP/14/1375 - Prior notification of intention to erect manure/general storage agricultural building; Land off Toftrees Road for Mr Blyth (Prior Notification (Agricultural)) EAST RUSTON - PF/14/1331 - Erection of single-storey front extension; Cedar Lodge, Drabbs Lane for Mr Wright (Householder application) ERPINGHAM - PF/14/1050 - Conversion of workshop accommodation; Chapel House, Chapel Road for Mr J Claxton (Householder application) to habitable FAKENHAM - LA/14/1204 - Erection of single storey rear extension to facilitate conversion to dwelling; 12 Market Place for B & L Properties Ltd (Listed Building Alterations) FAKENHAM - PF/14/1213 - Variation of conditions 2 & 3 of planning permission ref: 14/0399 to change to external materials and windows to proposed extension; 12 Market Place for B & L Properties Ltd (Full Planning Permission) FAKENHAM - AI/14/1312 - Display of illuminated fascia, totem and directional signs; Thurlow Nunn, Enterprise Way for Vauxhall (Advertisement Illuminated) FAKENHAM - PF/14/1283 - Change of use of first floor storage to cafe/restaurant (A3); 23A Bridge Street for Mrs D Pollard (Full Planning Permission) FAKENHAM - NMA1/89/2604 - Non-material amendment request to change brick type on Plots 148-177 inclusive; The Rowans (off Salmons Way) for Necton Management Ltd (Non-Material Amendment Request) FELMINGHAM - PF/14/1327 - Erection of two-storey side extension; Bethany Cottage, Stow Heath Road for Mr B Davies (Householder application) HAPPISBURGH - PF/14/1005 - Removal of debris, redundant structures and materials and re-alignment of rock sill sea defence to upper foreshore; Development Committee 59 18 December 2014 Foreshore Beach, Happisburgh for North Norfolk District Council (Full Planning Permission) HEMPTON - PF/14/1255 - Retention of 1.8 metre high fence and gate; 18 Raynham Road for Mr S Futter (Householder application) HICKLING - PF/14/1106 - Erection of two single-storey dwellings; Land at Heron Way for Mr F Howard (Full Planning Permission) HICKLING - PF/14/1264 - Conversion of agricultural barn to 4 residential dwellings; Brightmere Farm, Stalham Road for Caddow Design and Build Ltd (Full Planning Permission) HINDOLVESTON - PF/14/1170 - Demolition of pitched roof and erection of flat roof to linked extension, insertion and re-location of doors and windows.; Methodist Chapel, The Street, Hindolveston for Mrs Webb (Full Planning Permission) HINDOLVESTON - LA/14/1171 - Internal and external alterations to facilitate conversion of chapel to residential dwelling; Methodist Chapel, The Street, Hindolveston for Mrs Webb (Listed Building Alterations) HOLT - LA/14/1345 - Demolition of rear single-storey extension and erection of replacement, insertion of replacement sash windows to front elevation and recover front elevation dormers; 22 & 22a High Street for Miss D J Bottrill (Listed Building Alterations) HOLT - NMA1/12/1164 - Non-material amendment request to erect close boarded fence with planting in front; The Railway Tavern, 2 Station Road for Capricorn Estate Partnership (Non-Material Amendment Request) HORNING - PF/14/1210 - Erection of rear & side single storey extensions; 15 Broadwater Way for Mrs Moore (Householder application) HOVETON - PF/14/1335 - Erection of single-storey side extension; Nortons, Meadow Drive for Mr D Olley (Householder application) INGHAM - PF/14/1293 - Installation of roof light; Rookery Barn, Sea Palling Road, Ingham for Mr A Richardson (Householder application) INGHAM - LA/14/1294 - Internal alterations and insertion of rooflight; Rookery Barn, Sea Palling Road for Mr Richardson (Listed Building Alterations) INGWORTH - NMA1/14/0684 - Non material amendment request to permit the insertion of balustrade to south west balcony and revised window and door to north east elevation; West End Cottage, West End for Mr and Mrs M Farrow (Non-Material Amendment Request-Household) Development Committee 60 18 December 2014 KELLING - PF/14/1263 - Removal of condition 2 of planning permission 05/0622 to permit permanent residential occupation; Rose Cottage, The Street for Mr & Mrs Cordeaux (Full Planning Permission) KETTLESTONE - LA/14/1058 - Demolition of garden walls; The Old Barn Farmhouse, 45 The Street for Mrs S Hollier (Listed Building Alterations) KETTLESTONE - PF/14/1371 - Erection of agricultural lean to storage building; Land at White House Farm, Fakenham Road for M & K Hattrell Farms (Full Planning Permission) LUDHAM - PF/14/1247 - Erection of two-storey rear extension (Revised design of planning permission 14/0696 omitting dormer & replacing with rooflight); Yew Tree Cottage, Staithe Road for Mr V Enever (Householder application) MUNDESLEY - PF/14/1290 - Change of use from hair salon to additional living accommodation; 7 High Street for Gold Park Salon (Full Planning Permission) MUNDESLEY - PF/14/1342 - Erection of single-storey rear and front extensions; 16 Trunch Road for Mrs J Sutton (Householder application) NORTH WALSHAM - PF/14/0711 - Change of use from car showroom to D1 (place of worship); 13-21 Bacton Road for New Life Community Church (Full Planning Permission) NORTH WALSHAM - PF/14/1266 - Erection of single-storey side extension, detached car port and creation of vehicle access; 68 Yarmouth Road for Mr and Mrs E Joyce (Householder application) NORTH WALSHAM - PF/14/1279 - Erection of two-storey side and single-storey rear extensions; 14 Hamilton Close for Mr G Turner (Householder application) NORTH WALSHAM - LA/14/1315 - Internal and external alterations to facilitate repairs; 6 Church Street for North Walsham Chiropractic Clinic (Listed Building Alterations) NORTH WALSHAM - PF/14/1223 - Change of use from ground floor retail (A1) and first floor storage to Chiropodist (D1) and installation of replacement shop front; 31 Market Place for Mr Hoyes (Full Planning Permission) NORTH WALSHAM - PF/14/1270 - Variation of condition 3 of planning permission ref:05/1482 to permit re-location of access road within site; Ebridge Mill, Happisburgh Road, White Horse Common for Barn Owl Conversions Ltd (Full Planning Permission) Development Committee 61 18 December 2014 NORTH WALSHAM - LA/14/1311 - Internal alterations and maintenance; 29-30 Market Place for Acorn Properties (Listed Building Alterations) NORTH WALSHAM - AI/14/1314 - Display of two illuminated and one non illuminated signs; 46 Market Place for Yorkshire Building Society (Advertisement Illuminated) NORTH WALSHAM - LA/14/1316 - Installation of replacement non and illuminated signs; 46 Market Place for Yorkshire Building Society (Listed Building Alterations) NORTH WALSHAM - PM/14/1317 - Erection of two detached two-storey dwellings; 43 Marshgate for Mr M Alexander (Reserved Matters) NORTH WALSHAM - PF/14/1336 - Variation of condition 2 of planning permission ref: 14/0963 to permit change of pitched to flat roof of rear extension and insertion of roof lantern; 32 Happisburgh Road for Mr & Mrs Rush (Householder application) OVERSTRAND - PF/14/1219 - Retention of replacement front porch; 20 Pauls Lane for Mr Thompson (Householder application) OVERSTRAND - PO/14/0451 - Erection of forty two dwellings; Land to the South of Mundesley Road for Mr and Mrs Hughes (Outline Planning Permission) PASTON - NMA1/13/1242 - Non material amendment request to permit insertion of door and window to east elevation and fenestration revisions to north, south and west elevations of the proposed garage conversion to holiday accommodation; Sundial Cottage, Chapel Road for Mr J Manricks (Non-Material Amendment Request) RAYNHAM - NP/14/1374 - Prior notification of intention to erect manure/general purpose storage building; Land to north of Shereford Gate Plantation, Fakenham Road, Raynham for Mr Blyth (Prior Notification (Agricultural)) RAYNHAM - NP/14/1376 - Prior notification of intention to erect manure/general storage agricultural building; Land east of West Raynham Airfield, West Raynham for Mr Blyth (Prior Notification (Agricultural)) RAYNHAM - PF/13/0983 - Change of use of former aircraft hanger buildings to B2 (general industrial) and B8 (storage including agricultural storage); Former RAF Hangers T1 & T2, West Raynham for Sigma Energy Ltd (Full Planning Permission) RAYNHAM - PF/14/0989 - Change of use of former agricultural buildings to single residential dwelling; Manor Farm Barns, West Raynham Road, South Raynham, for Raynham Farm Company (Full Planning Permission) Development Committee 62 18 December 2014 RAYNHAM - PF/14/1217 - Change of use of agricultural land to garden; Land rear of St Margarets House, The Street, West Raynham for Mr Dodd (Full Planning Permission) ROUGHTON - NMA1/14/0365 - Non material amendment request to permit revised windows and door layout to south east and west elevations and re-position of chimney; Adajcent to Keepers Retreat, Old Turnpike Road, Roughton, Norwich, NR11 8SP for Mr and Mrs D Williams (Non-Material Amendment Request) RUNTON - NMA1/14/0794 - Non material amendment request to permit the increase of proposed single storey side extension width to 2.08m; Saxonholme, Home Close, West Runton, Cromer, NR27 9QF for Mr M Hogan (Non-Material Amendment Request-Household) RUNTON - PF/14/1304 - Erection of single-storey rear extension; Calveswell Barn, Calves Well Lane, West Runton, Cromer, NR27 9LU for Mr Brandish (Householder application) SCOTTOW - PF/14/1038 - Change of use of hanger to B2 and B1 use (general and light industrial use) and associated outside storage; Hanger 4, Former RAF Coltishall, Scottow, NR105GB for Norfolk County Council (Full Planning Permission) SCULTHORPE - PF/14/1268 - Erection of single-storey detached fitness room and garden shed; Butterfly Barn 5, The Grange, Lynn Road, Sculthorpe, Fakenham, NR21 9LL for Mr Bashforth (Householder application) SCULTHORPE - PF/14/0921 - Erection of replacement shop building and provision of defined parking; Shell Fakenham, Creake Road, Sculthorpe, Fakenham, NR21 9HT for Shell UK Retail (Full Planning Permission) SHERINGHAM - PF/14/1230 - Erection of rear porch and replacement of flat roof to pitched on garage to facilitate conversion to ancillary accommodation; 8 Uplands Park, Sheringham, NR26 8NE for Mr and Mrs N Catchpole (Householder application) SHERINGHAM - PF/14/0774 - Continued use of A3 (café) for a mixed use of A3 (café)/A5 (hot food take-away) and retention of flue; 26 High Street, Sheringham, NR26 8JR for Mr A Stevenson (Full Planning Permission) SHERINGHAM - PF/14/1182 - Erection of rear conservatory; 3 (Plot 4) Augusta Court, Sheringham, NR26 8AH for Mr Duffield (Householder application) SHERINGHAM - NMA1/14/0235 - Non material amendment request to permit fenestrational changes and introduction of roof light.; Lotus House, 10 Station Approach, Sheringham, NR26 8RA for Mr & Mrs Lee (Non-Material Amendment Request) Development Committee 63 18 December 2014 SHERINGHAM - PF/14/1299 - Erection of side conservatory; 75 Beeston Common, Sheringham, NR26 8EU for Mr Talbot (Householder application) SHERINGHAM - AN/14/1310 - Display of non-illuminated hanging sign; 20 Church Street, Sheringham, NR26 8QS for The Salvation Army Trustee Company (Advertisement Non-Illuminated) SIDESTRAND - PF/14/1289 - Conversion and extension of roof space to bedroom with ensuite and insertion of rooflights to west roof slope; South Barn, Cromer Road, Sidestrand, Cromer, NR27 0LT for Mr Smith (Householder application) SOUTHREPPS - PF/14/1275 - Change of use of Post Office to residential dwelling & erection of front wall; Post Office, High Street, Southrepps, NR11 8AH for Mr D Geary (Full Planning Permission) STALHAM - PF/13/1518 - Continued use of sports ground for car boot sales; Stalham Football Club Rivers Park, Brumstead Road, Stalham, Norwich, NR12 9BJ for Mr D Penrose (Full Planning Permission) SWANTON NOVERS - PF/14/1221 - Erection of single-storey side extension; Brick Kiln Farmhouse, St Giles Road, Swanton Novers, Melton Constable, NR24 2RB for Mr Jenny (Householder application) THURNING - PF/14/1308 - Erection of two-storey side extension; Craymere Beck House, Craymere Beck Road, Thurning, Melton Constable, NR24 2LN for Mr S Garnier (Householder application) THURNING - LA/14/1309 - Internal alterations and erection of two-storey side extension; Craymere Beck House, Craymere Beck Road, Thurning, Melton Constable, NR24 2LN for Mr S Garnier (Listed Building Alterations) TRUNCH - PF/14/1267 - Erection of front single-storey extension; 3 Blooms Turn, Trunch, North Walsham, NR28 0PQ for Mr and Mrs A Evans (Householder application) TUNSTEAD - PF/14/1322 - Erection of single-storey side extension; Bracken House, Anchor Street, Tunstead, Norwich, NR12 8HR for Mr Atthowe (Householder application) TUNSTEAD - PF/14/1355 - Erection of extension to existing agricultural building; Church Farm, Church Road, Tunstead, Norwich, NR12 8RG for R and J M Place Ltd (Full Planning Permission) UPPER SHERINGHAM - PF/14/1236 - Widening of existing entrance; Mill Cottage, Holt Road, Upper Sheringham, Sheringham, NR26 8TN for Ms Hunt (Householder application) Development Committee 64 18 December 2014 WALCOTT - PF/14/0886 - Erection of single-storey replacement dwelling; Gladstone Lodge, Archibald Road, Walcott, Norwich, NR12 0NF for Mr & Mrs B W Nunn (Full Planning Permission) WALCOTT - PF/14/1278 - Construction of two rock sill sea defences; Beach at Ostend, Walcott for North Norfolk District Council (Full Planning Permission) WALSINGHAM - PF/14/1248 - Erection of single-storey side/rear extension and chapel/studio with covered link corridor; The Retreat, 63A Wells Road, Walsingham, NR22 6DX for Mr R Pipes (Householder application) WALSINGHAM - PF/14/1198 - Erection of single-storey rear extension; 13 Egmere Wells Cottages, Wells Road, Egmere, Walsingham, NR22 6AU for Miss Kirby (Householder application) WARHAM - LA/14/1163 - Internal alterations; Keepers Cottage, Grove Farm, Wells Road, Warham, Wells-next-the-Sea, NR23 1NG for Coke Estates Ltd (Listed Building Alterations) WELLS-NEXT-THE-SEA - PF/14/1180 - Demolition of front extension & erection of replacement single-storey front extension; Sea Breeze, Plummers Drive, Wells-next-the-Sea, NR23 1ET for Mr and Mrs Wynne (Householder application) WELLS-NEXT-THE-SEA - PF/14/1150 - Variation of condition 2 of planning permission ref: 14/0080 to permit single-storey rear extension and the cladding and rendering of the west elevation's gable wall.; 1 Mill Court, Wells-next-the-Sea, NR23 1HF for Hodgkinson Builders (Full Planning Permission) WELLS-NEXT-THE-SEA - PF/14/1257 - Installation of replacement and upgrade of pole with antennae (total height 17.5m) in revised position within compound and siting of 2 new cabinets.; Land at New Farm, Warham Road, Wells-next-the-Sea for CTIL and Telefonica UK Ltd (Full Planning Permission) WELLS-NEXT-THE-SEA - PF/14/0604 - Conversion and extension of ground floor from A1 (retail) to a mixed use of A1 (retail) and B1 (office) and erection of ground floor and first floor extensions to provide residential flat and additional A1 and B1 floor area and separate B1 office and installation of first-floor side window and ground floor doors; 8 Freeman Street, Wells-next-the-Sea, NR23 1BA for Mr I Hodgkinson (Full Planning Permission) WELLS-NEXT-THE-SEA - LA/14/1121 - Demolition of rear boundary fence and erection of replacement 1.6m wall; Woodgets End, 22 Chapel Yard, Wells-next-the-Sea, NR23 1BJ for Mr Seaton (Listed Building Alterations) Development Committee 65 18 December 2014 WELLS-NEXT-THE-SEA - LA/14/1298 - Retention of internal alterations, insertion of replacement larger rear window and roof light and demolition and re-construction of chimney stack; 10 High Street, Wells-next-the-Sea, NR23 1EP for Mr J Batten (Listed Building Alterations) WEST BECKHAM - PF/14/1218 - Erection of single-storey front extension; Lower Farm, Back Lane, West Beckham, Holt, NR25 6PH for Mr and Mrs Livingstone (Householder application) WEYBOURNE - PF/14/1146 - Erection of two-storey front/side and single-storey rear extensions and insertion of replacement front dormer windows; 4 All Saints Close, Weybourne, Holt, NR25 7HH for Mr & Mrs Hemsley (Householder application) WIVETON - PF/14/1303 - Erection of single-storey detached guest lodge ancillary to Rose Cottage and extension to existing garden room; Rose Cottage, 14 Chapel Street, Wiveton, Holt, NR25 7TQ for Mrs C Von Rittberg (Householder application) WORSTEAD - PF/14/1047 - Erection of linked extension to existing industrial storage building.; Marine & Industrial LLP, Station Road, Worstead, NORTH WALSHAM, NR28 9RZ for Marine & Industrial LLP (Full Planning Permission) (7) APPLICATIONS REFUSED UNDER DELEGATED POWERS BACTON - PF/14/1234 - Use of converted out-buildings as separate dwelling; Bay Cottage, The Green, Edingthorpe, North Walsham, NR28 9SR for Mr Sidebotham (Full Planning Permission) BLAKENEY - PF/14/1228 - Demolition of dwelling and erection of replacement two and a half-storey dwelling.; Hartland, 57 New Road, Blakeney, Holt, NR25 7PA for Swan Homes (Full Planning Permission) DILHAM - PU/14/1149 - Prior notification of intention to change of use of agricultural building to dwelling house (C3); Tin Lodge, Broad Fen Lane, Dilham for Bindwell Ltd (Change of Use Prior Notification) HOLT - PF/14/1048 - Installation of tennis court and erection of 2.75m chain link fence; Jenis Barn, Thornage Road, Holt, NR25 6ST for Mr R Woods (Householder application) HORNING - PF/14/1202 - Erection of detached two-storey dwelling; Land at Leeds Way, Horning, NR12 8LU for Mr D Watts (Full Planning Permission) WELLS-NEXT-THE-SEA - PF/14/1070 - Alterations to dormer windows and balcony to the front elevation and erection of wall to rear of rear courtyard to conceal refuse bins; The Golden Fleece, The Quay, Wells-next-the-Sea, NR23 1AH for Mr Brundle (Full Planning Permission) Development Committee 66 18 December 2014 WITTON - PF/14/1260 - Erection of first floor balcony to west elevation; Whitehouse Barn, Old Hall Road, Witton, North Walsham, NR28 9UG for Mr R Taylor (Householder application) APPEALS SECTION (8) NEW APPEALS None (9) INQUIRIES AND HEARINGS - PROGRESS None (10) WRITTEN REPRESENTATIONS APPEALS - IN HAND BARSHAM - PF/13/1494 - Removal of Condition 3 of planning permission reference: 01/0855 to permit full residential occupation; Barsham Barns, Green Way, North Barsham, Walsingham, NR22 6AP for Mr A Hudson CROMER - PF/13/0979 - Erection of two three-storey dwellings and one two-storey dwelling; Land at Roughton Road, adjacent 1 Burnt Hills, Cromer, NR27 9LW for PP3 CROMER - PF/13/1521 - Erection of crematorium with access roads, car park and ancillary works; Land north of Cromer Cemetery, Holt Road, Cromer, NR27 9JJ for Crematoria Management Ltd LUDHAM - PF/14/0664 - Erection of detached two-storey dwelling; 14 Catfield Road, Ludham, Great Yarmouth, NR29 5QT for Mr A Tedder NORTH WALSHAM - PF/14/0728 - Erection of one and a half-storey dwelling and detached garage; Rear of 3 Benets Avenue, North Walsham, Norfolk for Mr G Sexton SUTTON - PF/14/0216 - Erection of one and a half storey dwelling and attached garage; Fairfield, Church Road, Sutton, Norwich, NR12 9SA for Mr R Banester WALCOTT - ENF/14/0020 - 2 metre high fence adjacent to highway.; Desamy, Lynton Road, Walcott, Norwich, NR12 0NA (11) APPEAL DECISIONS - RESULTS AND SUMMARIES MELTON CONSTABLE - PF/14/0158 – Construction of 2 detached residential dwellings; 14 Melton Street Melton Constable for Melbobby Limited APPEAL DECISION:- DISMISSED This application was for two detached dwellings on a site in the Melton Constable Conservation Area. The Inspector identified four main issues to be considered. Development Committee 67 18 December 2014 • • • • effect on the character and appearance of the Conservation Area whether the development would provide acceptable living conditions for future occupiers. effect on living conditions in a neighbouring property parking/highway safety With regard to the character of Conservation Area the Inspector noted that this is defined by the solid late Victorian terraced dwellings built for the railway workers with regimented building lines. The Inspector concluded that the two proposed dwellings would have a cramped relationship with the surrounding development and would “constitute a conspicuously incoherent and crowded development” at odds with the distinctively regimented terraced dwellings. He also criticised certain aspects of the design of the proposed dwellings. Turning to living conditions the Inspector found that the proposed garden areas to serve the new dwellings “are appreciably smaller than those found in nearby houses and notably smaller than the footprint of the dwellings.” He was not persuaded that these garden areas would provide a meaningful area to sit out, dry clothes or allow children to play. He was also concerned about a sizeable birch tree on the site which would be retained but would adversely affect daylight levels to one of the two proposed dwellings. The Inspector went on to assess the impact of the proposed development on a neighbouring dwelling, concluding that this would result in “an unacceptably gloomy environment resulting in significant harm to the living conditions” in the neighbouring property. On highway safety, the Inspector noted parking on footways already occurs and was concerned that the proposed two dwelling would cause further pressure on the limited on-street parking, to the detriment of highway safety. The Inspector acknowledged that the proposal would have some benefits but concluded that these would not be sufficient to outweigh the identified harm were the development to proceed. Accordingly he dismissed the appeal. MELTON CONSTABLE - PF/14/0159 – Construction of 4 semi-detached (2x2) residential dwellings ; 12 Melton Street Melton Constable for Melbobby Limited APPEAL DECISION:- DISMISSED This appeal was against the Council’s refusal of planning permission for 4 semi-detached (2x2) dwellings within the designated Conservation Area. Although on a different site, the Inspector identified similar issues to the appeal summarised above, relating to application PF/14/0158 • effect on the character and appearance of the Conservation Area • living conditions for future occupiers • effect of living conditions in a neighbouring dwelling • parking/highway safety The Inspector found that the proposed dwellings would have a poor and cramped relationship with the characteristic terraced dwellings in the vicinity and was also critical of certain aspects of the design. Development Committee 68 18 December 2014 As with the previous appeal the Inspector considered that the gardens of the proposed dwellings were smaller than the gardens of nearby houses and that the garden spaces of two of the units were “especially ungenerous.” The Inspector was also troubled by the proximity of the appeal site to the Marriot Way industrial site, concluding that “allowing the appeal would increase the likelihood of a statutory nuisance scenario that would be detrimental to the viability of businesses….on an established industrial zone.” The relationship of the proposed dwellings with an existing neighbouring dwelling was assessed. On this issue the Inspector concluded that two of the proposed dwellings would have an overbearing relationship, “overshadowing parts of both the dwelling and its garden.” On the final issue, parking and highway safety, the Inspector reached the same conclusions as on the previous appeal. There is limited on-street parking in the immediate vicinity and the proposed development would be likely to result in congestion to the detriment of highway safety. The Inspector again acknowledged that the proposal would have some benefits but concluded that these would not be sufficient to outweigh the identified harm were the development to proceed. The appeal was therefore dismissed. (Source: RMH/PC Manager Ext.6016) (12) COURT CASES - PROGRESS AND RESULTS Matthew Champion v. North Norfolk District Council and others (Crisp Maltings, Great Ryburgh The Council’s decision to grant planning permission (Council’s reference PF/09/0966) for two grain silos, a lorry park and associated development at the Crisp Maltings site in Great Ryburgh was the subject of a Judicial Review. The Review was dealt with in the High Court by Mr James Dingemans QC sitting as a deputy High Court judge and judgment was given on 7 May 2013. The review was allowed and the planning permission quashed. The District Council and Crisp Maltings Ltd. applied for leave to appeal against the decision of the High Court to the Court of Appeal. Leave to appeal was granted and by way of a judgment issued on 18 December 2013 the appeal was allowed. The consequence of the Court of Appeal decision was that the order of the High Court (to quash the Planning permission) was set aside and the permission therefore “stands”. An application was made on behalf of Mr Champion for permission to appeal to the Supreme Court and granted on 30 July 2014. The next stage in the protracted legal process is for the parties (Mr Champion, the District Council and Crisp Maltings Ltd.) to agree a statement of facts and issues by 27 February 2015 and to file skeleton arguments with the Court. The appeal has been provisionally listed for hearing by the Supreme Court on 23 June 2015. It is fair to say that the legal basis upon which the objector’s case is founded has changed since the original High Court case was heard. The further appeal to the Supreme Court now places greater emphasis on broader issues of the approach of the Development Committee 69 18 December 2014 UK courts to underlying EU directives relating to the assessment of environmental impacts of proposed development; essentially the Supreme Court is being asked to consider the principles of how developments are screened as well as the specific development of the Crisp Maltings site in Great Ryburgh. (Source: Roger Howe, Planning Legal Manager Ext. 6016) Development Committee 70 18 December 2014