MEMORIAL UNION BUILDING KEWEENAW COMMONS UPGRADE GENERAL WORK

advertisement
ADDENDUM #1
PROJECT 34-16-02
MEMORIAL UNION BUILDING
KEWEENAW COMMONS UPGRADE
GENERAL WORK
May 6, 2016
Contractor shall list all addenda by number on the bid form to ensure conformity in the bid.
Drawings, Specifications and/or Proposals are herein amended, expanded and/or modified, as
hereinafter described, and become a part of the Contract Documents with the same force and effect as
if incorporated, herein, originally. Any contrary provisions contained, or referred to, in Drawings and/or
Specifications, shall remain applicable unless overridden by this Addendum. Revised or contrary
provisions herein shall not affect any other part of the Contract Documents and any deletions, additions,
substitutions and/or revisions mentioned, shall include all labor, materials, methods, modifications, etc.
required for complete performance of the work.
CONTRACT DOCUMENT MODIFICATIONS AND CLARIFICATIONS
Clarification:
1. All floor removal and prep for new work shall be by the flooring contractor.
2. Work in the main walkway during the time period of June 3-8 is limited to flooring work.
3. Flooring protection of new flooring in the main walkway is to be by the flooring contractor.
4. Dust control shall be installed on an as needed basis for activities that may generate a fair
amount of dust, impacting the traffic on the main corridor. An example would be removal of
the CMU adjacent to the main corridor.
Drawings:
1. Add to note indicating new FRP column cover over existing structural columns; rework ceiling
around column as required.
Other:
1. List of attendees at Mandatory walk-thru is attached.
End of Addendum